arlington public schools purchasing office · arlington public schools purchasing office ......

13
Arlington Public Schools Purchasing Office NOTICE OF ADDENDUM NO. 1 Issued on April 26, 2016 TITLE: REQUEST FOR PROPOSAL FOR PRE-QUALIFIED CONSTRUCTION MANAGER “AT RISK” SERVICES PROJECT NAME: NEW ELEMENTARY SCHOOL AT THE THOMAS JEFFERSON MIDDLE SCHOOL CAMPUS RFP NO.: 65FY16 RFP DUE DATE AND TIME: MAY 16, 2016 PRIOR TO 2:00 P. M., (LOCAL PREVAILING TIME) Adds Attachment F to the document. This Addendum No. 1 must be signed, dated and received in the Purchasing Office prior to the date and time stated above “OR” acknowledgment of receipt of this addendum may be noted on the RFP. (See RFP Title Page One). NAME OF VENDOR: ADDRESS: SIGNATURE: DATE: ISSUED BY: Ellen H. Wills, CPPB, VCO Assistant Director of Purchasing Telephone: (703) 228-7649 Cell: (703) 244-6580 Email: [email protected]

Upload: nguyendat

Post on 02-May-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

Arlington Public Schools Purchasing Office

NOTICE OF ADDENDUM NO. 1

Issued on April 26, 2016 TITLE: REQUEST FOR PROPOSAL FOR PRE-QUALIFIED

CONSTRUCTION MANAGER “AT RISK” SERVICES PROJECT NAME: NEW ELEMENTARY SCHOOL AT THE THOMAS JEFFERSON

MIDDLE SCHOOL CAMPUS RFP NO.: 65FY16 RFP DUE DATE AND TIME: MAY 16, 2016 PRIOR TO 2:00 P. M., (LOCAL PREVAILING TIME)

Adds Attachment F to the document. This Addendum No. 1 must be signed, dated and received in the Purchasing Office prior to the date and time stated above “OR” acknowledgment of receipt of this addendum may be noted on the RFP. (See RFP Title Page One).

NAME OF VENDOR: ADDRESS: SIGNATURE: DATE:

ISSUED BY: Ellen H. Wills, CPPB, VCO Assistant Director of Purchasing Telephone: (703) 228-7649 Cell: (703) 244-6580 Email: [email protected]

Proposed Concept 2, TJWG, October 2014

Summary of TJWG Concept Proposal

Attachment F

Aerial view looking north

Attachment F

Aerial view looking west

Attachment F

Aerial view looking south

Attachment F

Aerial view looking east

Attachment F

Aerial plan view

Attachment F

Existing conditions

Attachment F

Proposed Concept 2, TJWG, October 2014

Attachment F

South Old Glebe: existing

South Old Glebe: proposed

Site Sections along South Old Glebe Rd.

S. Old Glebe Rd. Existing Parking Lot & Parent Drop-off. Bus Loop T.J. Middle School

S. Old Glebe Rd. New Parking Garage T.J. Middle School

Attachment F

Existing conditions, TJMS

Attachment F

Proposed Scheme, TJWG, October 2014

Attachment F

Schedule

New Elementary School at Thomas Jefferson

Schedule end date J F M A M J J A S O N D J F M A M J J A S O N D Q1 Q2 Q3 Q4 Q1 A M J J A S O

BLPC / PFRC: 4/20, 5/4, 5/18, 6/1, 6/15

Concept Design: 10 weeks 6/10/2016

School Board informational item: Concept Design 6/16/2016

School Board approval: Concept Design 6/30/2016

BLPC / PFRC: 6/29, 7/20, 8/3, 8/17, 8/31, 9/7, 9/21

Schematic Design: 11 weeks 9/16/2016

School Board informational item: Schematic Design + early packages 9/22/2016

School Board approval: Schematic Design + early packages 10/6/2016

Design Development: 16 weeks (excludes one week for holidays) 1/20/2017

Use Permit Approval: 4 months Mar-17

Construction permitting for early packages Apr-17

GMP procurement of early packages (if any) May-17

Construction of early package: 4 months 9/1/2017

Arlington County Fair August 16-20

Start of school 9/5/2017

Construction Documents: 17 weeks 5/19/2017

School Board informational item: Final Design 5/18/2019

School Board approval: Final Design 6/1/2017

Permitting Jul-17

GMP procurement of full scope Aug-17

Construction: 21 months 5/24/2019

Arlington County Fair August 15-19

Punch list completion 7/12/2019

Arlington County Fair August 14-18

Furniture & Technology install 8/23/2019

School Opening 9/3/2019

Commissioning / M&V complete 9/27/2019

Net Zero Energy and Water year starts! 10/1/2019

2016 2017 2018 2019

BLPC dates: 4/20, 5/4, 5/18, 6/1, 6/15, 6/29, 7/20, 8/3, 8/17, 8/31, 9/7, 9/21

Joint BLPC / PFRC dates: 4/20, 5/18, 6/15, 7/20, 8/17, 9/21