applied science international success story implosion of the oliverio … · 2016. 6. 20. ·...

1
© Applied Science International, LLC. www.appliedscienceint.com | www.extremeloading.com APPLIED SCIENCE INTERNATIONAL SUCCESS STORY IMPLOSION OF THE OLIVERIO KRAEMER HOSPITAL Fábio Bruno Construções contracted Applied Science International (ASI) to model the implosion of the Oliverio Kraemer (OK) Hospital. The six-story high building was located less than 40 metres from the neighboring Albert Schweitzer (AB) Hospital. The continued operation of the neighboring hospital was essential. Hence, at the time of the demolition there were more than 800 people – including patients, doctors and nursing staff inside the AB hospital. Demolition ASI Headquarters: 2012 T.W. Alexander Drive, Durham, NC 27709-3887 Tel: +1.919.645.4090 | Fax: +1.919.645.4085 The sequence of demolition of the structure was modeled in the Extreme Loading ® for structures software to ensure that the structure will fail away from AB Hospital. Only the columns of the first three floors were demolished. To limit the vibration and damage to the neighboring hospital the last row of columns of the OK hospital near the AB was not to be imploded. Throughout the process, Applied Science International and Fábio Bruno Construções were able to see the results of each proposed scenario to determine whether the demolition will go as planned. It was decided that the infill walls were to be removed completely from the first three floors except for the walls near the AB hospital. Additionally to ensure complete collapse, the internal walls were removed from the top three floors while the external walls were not removed. The demolition went as planned on May 15 2016 and no damage occurred in the AB hospital and no excessive vibration was reported. One of the concerns in the design of the demolition scheme was to ensure complete collapse of the structure. Partial collapse also referred to as “squatting” means that part of the structure stays intact after the demolition. This creates an additional hazard and waste of ime to demolish the remaining part.

Upload: others

Post on 04-Mar-2021

18 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: APPLIED SCIENCE INTERNATIONAL SUCCESS STORY IMPLOSION OF THE OLIVERIO … · 2016. 6. 20. · IMPLOSION OF THE OLIVERIO KRAEMER HOSPITAL Fábio Bruno Construções contracted Applied

© Applied Science International, LLC.

www.appliedscienceint.com | www.extremeloading.com

APPLIED SCIENCE INTERNATIONAL SUCCESS STORY

IMPLOSION OF THE OLIVERIO KRAEMER HOSPITAL

Fábio Bruno Construções contracted Applied Science International (ASI) to model the implosion of the Oliverio Kraemer (OK) Hospital. The six-story high building was located less than 40 metres from the neighboring Albert Schweitzer (AB) Hospital. The continued operation of the neighboring hospital was essential. Hence, at the time of the demolition there were more than 800 people – including patients, doctors and nursing staff inside the AB hospital.

Demolition

ASI Headquarters:2012 T.W. Alexander Drive, Durham, NC 27709-3887Tel: +1.919.645.4090 | Fax: +1.919.645.4085

The sequence of demolition of the structure was modeled in the Extreme Loading ® for structures software to ensure that the structure will fail away from AB Hospital. Only the columns of the first three floors were demolished. To limit the vibration and damage to the neighboring hospital the last row of columns of the OK hospital near the AB was not to be imploded.

Throughout the process, Applied Science International and Fábio Bruno Construções were able to see the results of each proposed scenario to determine whether the demolition will go as planned. It was decided that the infill walls were to be removed completely from the first three floors except for the walls near the AB hospital. Additionally to ensure complete collapse, the internal walls were removed from the top three floors while the external walls were not removed.

The demolition went as planned on May 15 2016 and no damage occurred in the AB hospital and no excessive vibration was reported.

One of the concerns in the design of the demolition scheme was to ensure complete collapse of the structure. Partial collapse also referred to as “squatting” means that part of the structure stays intact after the demolition. This creates an additional hazard and waste of ime to demolish the remaining part.