“enterprise” or “ orporate” version of base software ...€¦ · on the service shack. can...
TRANSCRIPT
ADDENDUM TO RFP NO. 1178-16/17
Date: July 26, 2016
Project: Security Cameras for District Office
From: Vivien Watts, Director of Business Services
Addendum Number: ___2___
THIS ADDENDUM IS ISSUED AS PART OF THE CONTRACT DOCUMENTS FOR THIS PROJECT AND AMENDS
ONLY THOSE ITEMS SPECIFICALLY DEFINED HEREIN. THIS ADDENDUM MUST BE ACKNOWLEDGED ON
THE BID FORM. YOUR FAILURE TO DO SO MAY RENDER YOUR BID NON-RESPONSIVE.
This addendum includes the following three (3) sections:
Section I: Questions and Answers
Section II: Specifications for Security Camera Equipment Network
Section III: Marengo Building Floor Plan
Section I: Questions and Answers
Question 1: Is Milestone Video Management Base software required for this project? If yes, then is
“Enterprise” or “Corporate” version of base software required?
Answer 1: AUSD currently utilizing Milestone Video Management software for several sites.
Channel licenses for cameras will need to be for the “Expert” version of Milestone
Question 2: There are 15 XPROTECT LPR Camera License noted in the technical specifications. Please
clarify the number. From report I received from our team in LA who attended the job
walk may 3 be XPROTECT LPR Camera License needed for this site. The rest can be
regular XPECL camera licenses. We can always upgrade the camera license to LPR
capability if needed.
Answer 2: For bidding purposes, only bid Milestone Xprotect Expert Camera licenses. No
Milestone LPR licenses are needed in this bid at this time.
Question 3: Please confirm the distance between each camera, and the next available IDF is less
320-feet. This spec for the 802.3 Ethernet protocol and CAT-5/6e limitation to minimize
the packet loss and line impedance.
Answer 3: It has been determined that several cameras will be beyond the 320 foot limitation.
Include in your proposal to install a 4 foot wall enclosure in the designated location (see
drawing A-2.7). Also include the cost & labor to install power inside the enclosure to the
nearest electrical panel, run 6-strand fiber optic cable to the Network Operations Center
(NOC) along with its termination(LC) onto fiber patch panels at each end (contractor
provided).
Question 4: Can a wireless solutions considered for locations where we assess the routing of conduit
can be difficult?
Answer 4: Wireless solutions will be considered.
Question 5: Is the Milestone VMS currently existing?
Answer 5: Yes. AUSD currently has Milestone Expert 2014 installed and have over 110 IP cameras
spread among 5 recording servers.
Question 6: Will the Milestone VMS be accessible via software client or direct server interface?
Answer 6: Either.
Question 7: Milestone base camera licenses were not included in the original specification. Are
these existing, or are these to be provided and installed by the contractor?
Answer 7: Contractors will need to include camera licenses for each camera. AUSD has Milestone
Xprotect Expert as their VMS version. For bidding purposes, no Xprotect LPR licenses
are required at this time; only camera channel licenses.
Question 8: Will all camera require XPROTECT LPR licenses?
Answer 8: For bidding purposes, no Xprotect LPR licenses are required at this time; only camera
channel licenses.
Question 9: Will the NAS unit require RAID configuration? If yes, what type?
Answer 9: The 10 300GB SAS 15k RPM hard drives will be installed onto an existing Cisco UCS C240
server and be configured as RAID-10. That setup will be used for all cameras to record
24/7 and store the ‘LIVE’ portion. The Qnap NAS and its 24 hard drives will be setup in
either 1 or 2 RAID-5 arrays. This will be used as archive storage. AUSD’s Technology
department will be available to assist in the configuration; however, bidders must have
someone knowledgeable to perform the installation and configuration.
Question 10: Will conduit be required to all external camera locations?
Answer 10: Please see attached cabling specifications. As a general rule: there should be no
exposed cabling, internal or external, unless it is above ceiling tiles.
Question 11: Will conduit be required to extend the full distance from the closest IDF / MDF to the
camera location? If yes, what type?
Answer 11: See attached cabling specifications.
Question 12: Will innerduct / corrugated tubing be required on ALL interior cabling locations to
protect the cable, including plenum runs?
Answer 12: Innerduct will be needed only where cable is exposed and not above a ceiling tile.
Question 13: Will network cables be terminated on existing patch panels or will the contractor
provide and install separate patch panels?
Answer 13: For bidding purposes: contractor shall install onto a separate patch panel provided by
the contractor.
Question 14: Will network cables terminate directly into the cameras, or will a termination to a jacke
be required with a patch cable to the camera?
Answer14: Termination directly into the camera will be acceptable. See attached cabling
specifications.
Question 15: Will the project require installation using the latest BICSI / TIA / EIA standards and local
NEC codes?
Answer15: See Section II on this addendum for cabling specifications.
Question 16: Due to the requirements of Camera #12 being able to read license plates and its location
on the service shack. Can it be moved to the outer face of the overhead deck between
camera #11 & #13 and installed with a long range lens to meet the required function of
that camera reading license plates of cars entering/exiting through that gate.
Answer 16: For bidding purposes, no Xprotect LPR licenses are required at this time; only camera
channel licenses. The purpose of Camera #12 is to capture the service trucks by the
Chestnut gate.
Question 17: Axis P33634-VE, that comes in 2 models, the 12MM (3.3-12mm) and the 6MM (2.5-
6mm)? Which model designated for this installation?
Answer 17: The 12MM model is acceptable for our purposes.
Question 18: Will building permits be required?
Answer 18: No
Question 19: Are background checks/fingerprints to be required for workers on site? If yes, please
indicate if costs are to be subsidized by AUSD or paid for by the contractor.
Answer 19: No, background checks will not be required for workers on site since the project will not
be on a school campus. If background checks/fingerprints are done, they are to be paid
for by the contractor.
Question 20: Due to the requirements of Camera #12 being able to read license plates and its location
on the service shack. Cn it be moved to the outer face of the overhead deck between
camera #11 & #13 and installed with a long range lens to meet the required function of
that camera reading license plates of cars entering/exiting through that gate.
Answer 20: Yes. We would consider the option of moving camera #12 from the service shack to the
outer face of the overhead between cameras #11 and #13.
END OF SECTION I
Section II: Specifications for Security Camera Equipment Network
1. GENERAL REQUIREMENTS
1. The Scope of Work
1. Contractor(s) shall provide all materials and labor to render a security system complete and
operable for all locations as specified within this document and related drawings. Work
includes, but not necessarily limited to the following:
a. Examine all other specification sections and drawings for related work required to be
included as work under Division 27.
b. Vendor shall supply and install all owner supplied and contractor supplied equipment.
c. Vendor shall supply, install and configure all active and passive equipment, i.e., security
camera devices, controllers, servers, NAS, switches and licenses to complete a fully
functional security monitoring solution.
2. Location is Alhambra Unified School District Administrative Office Buildings.
3. All new equipment shall be connected to PLENUM CATEGORY 6 cables.
2. CODES AND STANDARDS
1. The Contractor shall adhere to all building, regulatory, and equipment standards applicable to
the project. These standards shall include, but not be limited to the following:
a. Except as modified by governing codes and by the Contract Documents, comply with
applicable provisions and recommendations of the following:
i. The cabling and components shall carry Underwriters Laboratory (UL) Listing.
ii. National Electric Code (NEC), in particular, Sections 800-3(b) and 800-3(d).
iii. TIA/EIA-568B.1 Commercial Building Telecommunications Cabling Standards, Part
1: General Requirements.
iv. TIA/EIA-568-B.1-1
Commercial Building Telecommunications Cabling Standard Part 1: General
Requirements Addendum 1 Minimum 4-Pair UTP and 4-Pair ScTP Patch Cable Bend
Radius (ANSI/TIA/EIA-568-B.1-1-2001)
v. TIA/EIA-568-B-2-1
Commercial Building Telecommunications Cabling Standard Part 1: General
Requirements Addendum 3 – Supportable Distances and Channel Attenuation for
Optical Fiber Applications by Fiber Type.
vi. TIA/EIA-568-B.1-3
Commercial Building Telecommunications Cabling Standard Part 1: General
Requirements Addendum 3 – Supportable Distances and Channel Attenuation for
Optical Fiber Applications by Fiber Type.
vii. TIA/EIA-568-B.2-1
Commercial Building Telecommunications Cabling Standard Part 2: Balanced Twisted
Pair Components Addendum 1 Transmission Performance Specifications for 4-Pair
100 Ohm Category 6 Cabling (ANSI/TIA/EIA-568-B.2-1-2002).
viii. TIA/EIA-568-B.2-2
Commercial Building Telecommunications Cabling Standard Part 2: Balanced
Twisted-Pair Cabling Components Addendum 2 (ANSI/TIA/EIA-568-B.2-22001)
ix. TIA/EIA-568-B.2-3
Commercial Building Telecommunications Cabling Standard Part 2: Balanced Twisted-
Pair Cabling Addendum 3 Additional Considerations for Insertion Loss and Return
Loss Pass/Fail Determination (ANSI/TIA/EIA-568-B.2-3-2002)
x. TIA/EIA-568-B.2-4
Commercial Building Telecommunications Cabling Standard Part 2: Balanced Twisted
Pair Components Addendum 4 Solderless Connection Reliability Requirements for
Copper Connecting Hardware (ANSI/TIA/EIA-568-B.2-4-2002)
xi. TIA/EIA-568-B.3
Optical Fiber Cabling Components Standard (ANSI/TIA/EIA-568-B.3-2000)
xii. TIA/EIA-568-B.3-1
Optical Fiber Cabling Components Standard Addendum 1 Additional Transmission
Performance Specifications for 50/125 um Optical Fiber Cables (ANSI/TIA/EIA-568-
B.3-1-2002)
xiii. TIA/EIA-455-B
Standard Test Procedure for Fiber Optic Fibers, Cables, Transducers, Sensor,
connecting and Terminating Devices, and other Fiber Optic components.
xiv. TIA/EIA 569C Commercial Building Standard for Telecommunications Pathways
& Spaces.
xv. TIA/EIA 606-A Administration Standard for the Telecommunications Infrastructure
of Commercial Buildings.
xvi. TIA/EIA 607-A Commercial Building Grounding and Bonding Requirements for
Telecommunications
xvii. ANSI/TIA/EIA-854 Full Duplex Ethernet Specification for 1000 Mb/s Operating over
Category 6 Balanced Twisted-Pair Cabling.
xviii. IEEE Standards: 802 series.
xix. IEEE C62.41 Recommended Practice on Surge Voltages in Low-Voltage AC Power
Circuits.
xx. BiCSi TDB Manual; Building Industry Consulting Service International, Tampa,
Florida.
xxi. Federal Communications Commission (FCC), part 68 rule.
xxii. California Electrical Code (CEC).
xxiii. Occupational Safety and health Act (OSHA).
xxiv. California modification to OSHA.
xxv. National Fire Protection Association (NFPA)
a) NFPA-70 National Electrical Code (NEC)
xxvi. IEEE Institute of Electrical Engineers
a) IEEE 802 Specifications for Local Area Networks and Wireless Networks
xxvii. UCB ITS Standards for identification and Administration
3. SUBMITTALS
1. Awarded contractor shall submit for approval within 10 calendar days, from date of award, all
equipment and materials listing the manufacturer's catalog information for the following
items:
a. List of materials for each item:
i. Manufacturer
ii. Model Number
iii. UL listing
iv. Quantity
v. Equipment Cut Sheets
vi. All electronic devices.
2. Name of project manager, qualifications certifications, list of similar projects with dates,
length of employment with the company.
3. Submit the manufacturer, model number, serial number, software manufacturer, product
name, version number and date of equipment certification (certificate) of all test equipment
being deployed.
4. Shop drawings shall indicate equipment locations, wiring and schematics, details, panel
configurations, sizes and a point-to-point-wiring diagram of all circuits. Shop drawings shall
indicate interfaces to equipment furnished by others, identifying numbers of wires,
termination requirements, and other pertinent details. Responsibility for each end of
interfaces shall be noted on shop drawings. Contractor shall supply shop drawings 1 week
prior to installation.
5. Create a Gantt chart (schedule) that displays the critical components from start to project
completion. The chart should be a general schedule with 6 – 8 major inputs overtime. Please
do not use or create a Critical Path Method (CPM) or Performance Evaluation Review
Technique (PERT), these are too detailed.
6. Entire system shall be supported by engineering documentation including:
a. Riser diagrams indicating all devices, cabinets and they’re point-to-point connections in a
manner following floor plan layout.
7. Record Drawings:
a. Submit a list created in MS Excel version 2010 or newer of the following:
i. A complete listing of all installed Security Cameras displaying the building ID, floor,
room number (classroom must list room number) or area (areas without an area
designation), SECURITY CAMERA model number, serial number, MAC address, and
assigned identification number. The spreadsheet shall be created in a 3 ring binder
with tabs for each building and each floor. Submit three copies of the 3 ring binder.
ii. Create five (5) CDROMS of the above information and three(3) 3-ring binders of the
printed information to be delivered to the architect at close out.
b. Submit five “As Built” marked up (E size) drawings and three CDROMs for all as contractor
installed security cameras. “As Built” drawings shall include the SECURITY CAMERA device
number, asset number and MAC address (per label section of the written specifications)
near each device “As Built” drawings are to be created in AutoCAD Version 2012 or newer.
The architect shall provide base drawings to be modified. Drawings shall be delivered to
the architect.
4. QUALITY ASSURANCE
1. Contractor shall warranty all work executed and materials furnished shall be free from defects
of material and workmanship for a period of ONE year from acceptance date of Contract
Completion. Immediately upon receipt of written notice from the District, Contractor shall
repair or replace (all supplied equipment, parts and materials) at no expense to the District
Any defective material or work which may be discovered before final acceptance of work, or
within warranty period; any material or work damaged thereby; and adjacent material or
work which may be displaced in repair or replacement. Examination of or failure to examine
work by the District shall not relieve Contractor from these obligations.
2. Persons skilled in the trade shall install the system in accordance with best trade practice.
Further, in accordance with all applicable building codes.
5. ENGINEERING CONSIDERATIONS
1. All structured cabling (copper cable) shall be rated Category 6 “Plenum”.
a. All indoor cable shall be Plenum rated Category 6.
b. All outdoor cable shall be Category 6 outdoor rated and not exceed more than 50 feet
from the point of entry within a building unless extended by metal conduit that is
grounded at both ends.
c. Where contractor changes the design route, then contractor shall supply a fully conduit
pathways at no additional cost to the District should the AUSD make such an election.
2. All trades shall coordinate the installation of equipment, materials and parts with each
other.
6. DESIGN CRITERIA
1. The contractor shall terminate all pairs to TIA/EIA 568B Standard configuration.
2. Contractor shall bond together all cable grounds to the distribution racks, and bond racks to
the building electrical ground per BICSI requirements.
2. PRODUCTS AND REQUIREMENTS
1. FIRE ALARM
1. Fire alarm signals shall not be cut in the course of construction. Where existing F/A signals
may impede the installation of enclosures, vaults, conduits or other items then the Cabling
vendor shall notify the architect.
2. Equipment vendor is hereby notified that any cut fire alarm signal requires the entire site to
be recertified. Equipment vendor shall reimburse AUSD for any and all fire alarm
recertification that occurs accidently or otherwise.
3. Alert architect when there exist F/A signal mixed with other signaling. Architect shall be
given written notification within 24 hours of all observed F/A within conduits, pull boxes and
vaults that are mixed signal.
4. Data and other low voltage signaling shall not be mixed in the same conduit, pull box,
junction box, or manhole.
3. FIRE STOPPING
1. All penetrations shall be fire stopped. Fire stopping shall have the same or better rating as the
existing structure of which they penetrate. Refer to ‘Fire Stopping Material’ within this
document for additional requirements.
4. FIRE STOPPING MATERIAL
1. All conduit penetrations shall be labeled, laminated and affixed to the penetrated area. The
above items (photograph) shall include the label. The label shall be readable in the
photograph. Inform architect when it is not feasible for a readable label via photograph.
2. Fire stopping material shall be installed/applied to all core drills/wall penetrations. Fire
stopping material shall meet ASTM E814; acceptable product shall be 3M’s elastomer latex
caulk or equivalent.
3. All penetrations through fire rated walls shall be protected from the spread of fire with an
approved fire stop system equal or greater than the fire rating of the wall. Submit all fire stop
system request to the architect for approval.
5. COPPER CABLE
1. All indoor copper cable shall be plenum rated Category 6.
2. Premise (inside plant) copper cable for data is to be rated for IEEE 802.3 1000 Base T,
plenum rated, Category 6, 4 twisted pairs, solid wire, 22-24 AWG, unshielded, shall be
utilized in all buildings.
3. Outdoor (OSP) Copper cable for data is to be rated for IEEE 802.3 1000 Base T, nonplenum
rated, Category 6, 4 twisted pairs, solid wire, 22-24 AWG, unshielded. Cable shall be rated
for outdoor use.
4. Cable manufacturer’s labeling shall be readable in all exposed areas, junction boxes, patch
panels, enclosures, horizontal runs and verticals runs. AUSD has a number of instances where
the manufacturer’s label is unreadable. All unreadable cable shall be removed and replaced at
a cost to the Cabling vendor. The architect shall make the decision of whether the cable is
readable or unreadable.
5. Acceptable products – Amp, AT&T, Belden, Mohawk, Hitachi, Ortronics, Siemens and
General Cable or equivalent. Note: acceptable outdoor Category 6 cable shall be sourced
by any of the above. Both Mohawk and Hitachi supply Category 6 outdoor cable. However,
both interior and exterior cable shall be by the same manufacturer.
6. All cable used in this project shall be from the same manufacturer, same model number and
same NVP. All cabling and labor used by cabling vendor with more than one approved
manufacturer shall be replaced at no further cost to the District.
3. EXECUTION
1. GENERAL REQUIREMENTS – Refer to Construction Drawings and details for additional
requirements.
1. Tape Labels
1. The cabling vendor shall identify the location of all interior telcom boxes with a tape label.
This label shall be used by the equipment vendor to locate the telcom box. Label tape shall
have a black background with white lettering.
2. Equipment Configuration
1. The vendor shall configure new IP address range and VLAN(s) to support the installation of all installed security cameras. AUSD IT Department shall provide IP address ranges in which the equipment vendor shall use to configure cameras. VLANs and switches shall be configured to support AUSD’s existing network infrastructure and current industry standards for a K-12 institution. Configure existing switches where no new switch is being installed.
2. The equipment vendor shall configure Rapid-PVST on the Cisco switch stack where new equipment shall be installed. These stacks will also have a redundant fiber uplink to the collapsed-core in MKHS’ MDF. AUSD may elect to split the IDF having 1 0r 2 fiber uplinks to each core switch. The ‘Pathcost Method Long’ and UDLD shall also be configured on the newly installed switches.
3. The equipment vendor shall configure all existing switches directly supporting SECURITY CAMERA devices. The existing switches are on their own VLAN and these switches (when connected to SECURITY CAMERA devices) shall be segment into an additional VLAN. AUSD IT Department shall provide additional configuration information so that the switches can be properly configured.
3. Scaffolds and Vertical Lift Equipment
1. Vendor shall coordinate with the District the use of scaffolds and vertical lift equipment. All
vendors shall provide necessary scaffolds, floor protection, life/safety equipment to protect
the existing environment and vendor employees.
2. Vendors shall equip all workers with the necessary fall protection devices per OSHA and
follow OSHA applicable rules and regulations.
3. Vendors shall provide a ‘joint use’ of common equipment per section one of this
document.
4. Contract Close Out Submittals
1. Equipment Vendor shall submit the following as part of the contract close out:
a. In addition to the ‘as built’ drawings and other record drawings, several other reports
shall be required, as listed below.
i. AutoCAD 2012 or newer drawing displaying the physical location of each device,
asset tag number and the MAC address of each SECURITY CAMERA on a set of site
drawings supplied by the architect in AutoCAD 2012 or newer format.
ii. Pictures of all SECURITY CAMERAs located in special areas (outdoors, cafeteria,
theater, and both gymnasiums) on an Excel spreadsheet with a description of their
location, id number and MAC address.
17. Workmanship Requirements
1. Category 6 UTP Copper Cable
a. Cables shall be laid at least 3 feet from any fluorescent ballast (in places where this is not
possible, the architect shall be notified and cabling vendor shall provide the final
disposition). Further, cables shall be ‘kink’ free.
b. Where cables are bundled, they shall be tied at least every 4.0 feet.
c. Cables from each classroom or administrative area shall be pulled and punched
down per TIA/EIA 568B standards.
d. Category 6 data cables shall be supported at least 6” above existing suspended ceilings.
18. Labeling – Data
1. Temporary label and identify all location of telcom boxes (both existing and new).
a. Install tape label at all identified telcom box. Use a black label base with a white print.
Contractor shall submit their approach to identifying and labeling telcom box locations to
the architect for approval. Do not proceed without architect’s approval. Note some
locations may not have a telcom box but rather a cable terminated in the ceiling. Locate
the cable and mark the position so that it can be easily found.
2. All cables, outlets and terminations shall be labeled and designated in accordance with
District standard construction documents and below. Because there is a substantial installed
cabling infrastructure the cabling vendor shall use the existing numbering. However, AUSD IT
Department shall verify cabling sequence and cabling vendor shall not proceed without
approval of architect.
a. Equipment vendor shall install asset tracking tags on all active equipment installed in the
course of this contract. AUSD purchasing department shall provide tag number sequence.
This same information shall be listed on the ‘AS-BUILT’ AutoCAD drawings for close out.
19. All Category 6 cable shall be labeled per the earlier specification.
20. Clean Up
1. Cabling/equipment vendor shall replace all tiles damaged in the course of construction.
2. Cabling/equipment vendor shall remove smudges, dirt, etc. from all surfaces prior to the
final punch list. If walls, floors and other surfaces cannot be cleaned then Cabling/equipment
vendor shall repaint or replace damaged areas/items.
3. Cabling/equipment vendor shall replace all damaged carpet in the course of the construction
project.
21. Completion of Work
1. At the completion of the system, the contractor shall restore to its former condition, all
aspects of the project site and on a daily basis, shall remove all waste and excess materials,
rubbish debris, tools and equipment resulting from or used in the services provided under this
contract. All clean up, restoration, and removal noted above shall be by the contractor and at
no further cost to AUSD. If the contractor fails in its duties under this paragraph, then owner
may upon notice to the contractor perform the necessary clean up and deduct the costs
thereof from any amounts due or to become due to the contractor.
22. Reports
1. The contractor shall provide test documentation to the architect in a three ring binder(s) and
CD format within three weeks after the completion of a specific project. Refer to ‘Record
drawings’ in part one of this document. The test document shall detail the test method used
and the specific settings of the equipment during the tests. The binder(s) shall be clearly
marked on the outside front cover and spine with the words “AUSD District Office Security
Equipment Test Results,” date of completion (month and year) the name of the person
performing the tests and the vendor’s name.
2. With the above report, submit written certification that the installation conforms to
specifications, is complete, and is ready for inspection and customer testing.
END OF SECTION II
Section III: Marengo Building Floor Plan
See following page for floor plan