annual report - oilweb.oilindia.in 5 of 29 2. secondary tank farm, (tank capacity 40, 000kls)...
TRANSCRIPT
ANNUAL REPORT
PROJECTS DEPARTMENT 2017-18
Page 1 of 29
1.0 PREAMBLE
The Projects Department is renamed Dept of earlier Production Project
department from 1st January of 2017 was created in 1982 with the core
purpose of providing infrastructural support to all three Assets to meet
their respective targets of Crude Oil & Natural Gas Production and their
Evacuation. From last 35 years, Projects Department has been
continuously providing infrastructural support in the form of
construction of OCS, EPS, WIS, Dehydration plant and Pipelines so that
produced Crude Oil and Natural Gas, after proper separation and
treatment, reaches OIL’s valued Customers, thereby fulfilling
Company’s business target.
2.0 MISSION To complete projects on time through “networking, collaboration and
engineering skills” and to enhance the level of excellence and
professionalism in the fields of E&P business by adopting new
technology and best practices to uphold OIL’s cherished goal to
become the fastest growing Energy Company with highest profitability.
3.0 OBJECTIVE
Create wealth for stakeholders with uncompromising quality and
safety standards.
Develop core competencies in the field of project management to
avoid cost and time over run while executing projects.
Respect for community and compliance to all safety, health and
environment norms.
Passion for excellence and willingness to learn, unlearn and
relearn.
Develop and sustain a culture of TEAM WORK (Together
Everyone Achieve More).
Page 2 of 29
4.0 ACTIVITIES OF THE DEPARTMENT
The various activities may be broadly classified as under –
i) Preparation of techno-economic feasibility report for new
projects related to Crude Oil & Natural Gas Production,
Transportation and Storage.
ii) Planning, Process Design , Feasibility Study, Front End
Engineering Design(FEED), Detail Design, Tendering &
Construction of Early Production Set-up (EPS), Oil Collecting
Station (OCS), Water Injection Station (WIS), Bowser
Unloading Station (BUS), Tank Farms, Effluent Treatment
Plants (ETP), Gas Compressor Station (GCS), Group Gathering
Station (GGS), Cross Country pipelines etc.
iii) Liaise with client to clarify technical issues and understand
client’s requirements.
iv) Prepare specifications for materials / equipment /
machineries required for above installations and thereafter
indenting, technical scrutiny, technical query generation and
consolidation, testing of materials, document checking.
v) Preparation of lay out drawings, contractual documents,
internal estimates etc. for finalization of contracts for
construction of above installations & cross-country pipelines.
vi) Engineering support (Clarify inter – discipline query, trouble
shooting and solve problem during construction etc)
Page 3 of 29
vii) Preparation of documents for obtaining permission from
statutory bodies like DGMS, Assam Pollution Control Board
(APCB) etc. for setting up new installations / modifications /
expansion of existing installations etc. Also, preparation of
necessary documents and liaison with Central / State
Government authorities to obtain permission to lay pipelines
for crude oil and natural gas transportation while crossing
Railway track, PWD roads, Bridges, River embankment etc.
viii) Capacity augmentation of existing production installations by
installation of additional separators, crude oil storage tanks
etc.
ix) Construction of crude dehydration facility for improvement of
crude oil quality.
x) Liaison with Land, Administration department and District
administration for resolving issues relating to land acquisition
and other administrative problems.
xi) Adopting necessary measures for control of Environmental
pollution.
xii) Participate in HAZOP & HAZID Studies.
xiii) Necessary cost control measures for overall profit of the
organization.
xiv) Ensuring all deliverables from department complies with
clients and company’s procedures and specifications.
Page 4 of 29
5.0 ACHIEVEMENTS
Following projects were completed / commissioned during the year
under review
(Up to March’ 17)
INSTALLATION LOCATION DATE OF COMPLETION / COMMISSIONING
1. MBLAL Project Duliajan, Moran, Jorhat & Tengakhat
Commissioned on 31/08/2016
2. Enclosed Ground Flare System of gas burning capacity of 2,81,000 SCUMD with automatic operation
Makum Commissioned on 31.01.2017
3. LPG Fire Fighting Duliajan Commissioned on 28.02.2017
6.0 PRESENT AND FUTURE PROJECTS Following are some major projects under execution/ various stages of
completion during the year under review
PROJECT LOCATION PRESENT STATUS AS ON 31.03.2017
1. Capacity Augmentation Project at ITF Tengakhat ( 2 nos. of 20000 Kls capacity floating roof crude oil storage tanks with associated facilities)
Tengakhat
Overall Progress :93.2%
Boundary wall - 98 % completed
Dyke wall - 98 % Internal Roads: 54%
Boilers Erection: 85 % Piping Works: 91%
completed Erection of Pump House:
94% Electrical Sub-Station:
98% Electrical & illumination
Works: 70 %
Tank : T-210: 97% completed T-209: 92 % completed
Process Hook-Up jobs: 55% completed
Page 5 of 29
2. Secondary Tank Farm, (Tank Capacity 40, 000KLS)
Madhuban 30.56%
3. Construction of Effluent Plant (Capacity-5000KLs)
Tengakhat Overall: 15%
4.
Construction of Group gathering Station (Capacity: 2000KLPD Crude, 5 MMSCMD NAG)
Baghjan Overall: 9.2% EPC Tender floated
5 Construction of Gas Compressor Station (Capacity: 0.45 MMSCMD Gas Boosting & Lifting facility)
Makum Overall:9.0% LSTK Tender for Construction of the installation: under bid evaluation. Project Management Consultancy: Tender floated
6 Water Injection Station Dikom Overall: 5%
7 Loc. HNE(Makum) to CGGS, Madhuban Gas Pipeline
Makum/ Madhuban
Overall: 14%
8 Gas Transmission Line from Baghjan to CGGS
Baghjan/ Madhuban
Overall: 2%
9 Oil Collecting Station at Nadua and Group Gathering Station, East Khagorijan
Nadua/ Khagorijan
Overall: 2%
Page 6 of 29
7.0 BRIEF NOTE ON COMPLETED PROJECTS:
A. IMPLEMENTATION OF SAFETY MEASURES AS PER REVISED OISD-117 AS WELL AS MB LAL COMMITTEE RECOMMENDATIONS FOR OIL’S TANK FARMS IN ASSAM:
Name of
the
Project
Implementation of Safety Measures as per
revised OISD-117 as well as MB Lal
Committee Recommendations for OIL’s Tank
Farms in Assam
Location DULIAJAN, Tengakhat, Moran, Jorhat
EPMC Engineers India Limited
EPC
Contractor Fabtech Projects & Engineers Ltd., Pune
EPC LOA
CCO/CF/121/2013 dated 16.8.2013
(Contract No: OIL/CONT/GLOBAL/8364/2013 -
SAP No. 6205228)
Scope
Detail Design, Engineering, Procurement, Site
Fabrication, Civil works, Piping works, Fire
protection system, HOT cranes, modification and
alteration works
Project Cost Rs. 151.68 Crores (approx.) with approved change
orders
Completion
Period
12 months from date of LOA for completion
CDD: 16.08.2014
Actual Completion Date: 31.08.2016
Page 7 of 29
Objective:
• To Implement the MB LAL committee recommendations & revised OISD
117 guidelines in Four tank farms of OIL
• Improved Safety - 100% compliance to prevalent industry statutory
norms with respect to process safety management system in our old
tank-farms
• Operational convenience – Adoption of latest state-of-the-art technology
in process control and safety
• Accurate Reporting - Centralized control room based operation with
dedicated online tank farm management system for inventory reporting
and control
Project Details:
Project Cost: 210 Crores. (APPROX.)
Mode of Execution:
• Considering the high safety implications, the project was taken up
with due importance across the organization.
• It was a brown field job and there was little space to place the new
facilities. Hence, some existing facilities within Tank Farm boundary
but not connected to the Tank Farm operations, were required to be
shifted from the old installations.
• M/s EIL was engaged as EPMC for the complete implementation of
these recommendations from study of the existing facilities,
formulation of the EPC contract for augmentation of the old safety
features of the Tank Farms to the level of the new requirement
including site supervision during project execution.
• M/s FPEL was appointed as the EPC for the project.
• Some important items viz. Rim seal fire protection system, High
velocity Long Range Monitors (HVLRM), Medium expansion Foam
Generators (MEFG) and some components of the Emergency Kit were
procured internally by OIL.
Page 8 of 29
Expected Benefits:
Apart from complying with the statutory recommendation’s the newly
built up facilities after project completion has enhanced process safety
standards and has also brought in operational excellence to a great
extent. Manpower required to operate the tank-farms has been
optimized, information management system for production reporting
has become scientific, and certain benchmark for operation has been
established as per industry standards. This all has benefited OIL in
enhancing the operable life of these old tank-farms to a large extent
and has brought down the risk level of the nearby installations
B. ENCLOSED GROUND FLARE SYSTEM AT MAKUM OCS COMMISSIONED DURING 2016-17:
At present, the flare gases of Oil Collecting Stations are burnt in open
pit flare where the flame is visible from outside. It has inherent heat
and light radiation problem which causes OIL to pay compensations to
the nearby farmers for damage of crops etc. So, in order to offset these
drawbacks and to comply with the latest environmental norms, the
enclosed ground flare system with automation had been installed at
Makum OCS with R&D budget. This technology has been adopted for
the first time for burning of flare gases in an Oil Collecting Station.
The flare system has the following benefits over the conventional open
pit flare:-
a. Flame is smokeless
b. Flame is not visible from outside.
c. It has low noise level as per OMR/ OISD regulations.
d. Flame is eco-friendly (low NOx, CO emission) and thereby
reducing carbon footprint.
e. Low heat radiation as the flare enclosures are having inner
ceramic refractory lining.
Page 9 of 29
f. It has liquid knock out facility with auto dumping which
separates entrained oil thereby saving wastage of crude oil.
g. It has Water Seal Drum at the upstream of the flare stack which
acts as a flash back arrester.
f. Operationally very safe as it can be operated from Local Control
Panel as well as Remote Control Panel located in control room.
g. It has automatic gas detection and pilot ignition system which
allows the system to run in auto mode.
i. It has burner staging valves which ensures efficient combustion
of flare gases.
h. Accurate real time data like gas flow, liquid level, pressure and
temperature etc. are displayed in the control panel located in the
control room.
Project Details:
Project Cost: Rs. 3.69 Crores
Contractor: M/s Combustion Research Associates, NOIDA
Mode of Execution: Turn Key Implementation of Design, Engineering,
Fabrication, Supply and Installation & Commissioning of Non-
luminous enclosed ground flare system at Makum OCS.
Page 10 of 29
Process Area of Flare
Local Control Air Compressor for auto valve operation
Page 11 of 29
C. LPG FIRE FIGHTING SYSTEM:
Objective: Hiring of services for Supply, erection, testing &
commissioning of overground fire protection system of LPG Recovery
Plant and LPG Filling Plant in OIL, Duliajan
Project Details: The above project job of replacement of underground
fire protection pipelines to over ground along with the additional jobs
required to meet various relevant OISD guidelines was handed over to
Projects Department in the month of March 2015. After transfer of the
instant work to Projects Department, it was felt prudent to have a
detailed discussion with the consultant, members from LPG, Fire and
PP department and also a member from M/s EIL. During the discussion
it was also observed that the calculation done by consultant for the fire
water requirement for LPG recovery & filling plant is on a higher side as
compared to the Fire water requirement for CTF evaluated by M/s EIL.
Therefore, it was opined that the LPG plant fire water requirement
needs to be vetted/crosschecked by a third party preferably M/s EIL as
M/s EIL are already executing an EPMC works for similar firefighting
facilities in OIL’s tank farms under MB Lal projects and they are fully
aware of OIL’s existing facilities and. The Fire water adequacy study
Remote Control Panel
Real time Process Data at
Page 12 of 29
was done by M/s EIL for the fire fighting up gradation at LPG and their
report vide letter no. A345-101-16-47-TR-0101 Rev0 has been found to
be acceptable to OIL. It was recommended that Fire water & pumping
requirement built by OIL for CTF under MB LAL Project is fully
adequate to cater fire water demand of entire complex of OIL at
Duliajan i.e. CTF, LPG RP, LPG FP & LPG Storage. They suggested that
Tapping from CTF (existing 12inch built under MB LAL Project) is
adequate to cater fire water demand for LPG Plant area.
M/s EIL was then engaged as an engineering consultant for Preparation
of Technical input & Review of Drawings/Documents after award of job
to Successful contractor/bidder.
The scope of work of this contract involves design, engineering, Supply
of materials, preparation of construction drawings, obtaining approval
from Owner/ Owner representative, construction, fabrication, erection,
installation, integration with the existing system wherever required,
testing, painting, pre-commissioning, commissioning, equipment,
transportation, labor, consumables, tools and tackles etc. Residual
design, engineering, supply and laying of new fire water hydrant system
for the entire LPG plant area. This system mainly includes entire fire
water piping network both underground (U/G) and above ground (A/G),
fire hydrant, water monitor, Deluge Valve system, High Volume Long
Range Monitor (HVLRM) using foam, Hose and Hose boxes/Hose
Cabinets (with all accessories inside), Hose Reels with all accessories,
all type of valves (Gate valves, butterfly valves, drain valves etc.), RCC
pipe supports (Spacing of pipe support shall be as per OISD-116, 3rd
amendment) , composite pipe supports, Supports for Hose boxes &
Hose Reels. This works shall be carried out by the Contractor on Lump
sum basis for Engineering, Procurement and Construction (EPC) as
single point responsibility covering the erection of Free Issue Materials
(FIM). The following fire protection measures are envisaged:
Firewater header with hydrants, monitors, HVLRMs, sprays system etc.
Page 13 of 29
Hose cabinets (Type-II) and accessories
Automatic (Deluge operated) medium velocity water spray system LPG
plant
First Aid Fire protection (Fire extinguishers) and Personal Protective
Equipment are provided as per OISD.
A/G and U/G Fire water header are being laid as per guideline given in
OISD-116, 3rd amendment.
Corrosion protection tape coating are being provided for all
underground carbon steel fire water pipes up to 500mm above finished
ground level/ Existing ground level.
Above ground fire water piping & fire hydrant, are being painted with
“Fire Red” Paint to shade no. 536 of IS: 5.
All fire water networks have been hydro tested to a pressure of 18
g/cm2 (g).
10% of all welded joints have been radio-graphed and found in order.
50% of welded joints selected for radiography are field joints
Contractor to hook the proposed system with the existing pump house
of LPG plant. This shall be in normally closed situation and shall be in
addition to the new system.
Existing deluge water spray network for LPG mounded bullet area shall
be extended to provide water spray coverage for the flanges in the LPG
mounded area.
Reuse of Existing Deluge valve as specified elsewhere in the tender.
Project Cost: 15.41 Crores (APPROX.)
Mode of Execution: EPC/LSTK Mode.
Expected Benefits: To meet various relevant OISD recommendations
and comply with other statutory requirement.
Page 14 of 29
Page 15 of 29
8.0 PHOTOGRAPH OF MILESTONE SUCCESS OF VARIOUS PROJECT Some of the Snapshots of Present Status of ITF Augmentation Project:
Tank-210 (painting completed)
Piping Hydro test Pressure Recording
Page 16 of 29
Successful completion of hook-up job at TP-2
Boiler House with Chimney as per PCB norms
Page 17 of 29
Crude oil circulation pump house
Tank MOV Manifold outside dyke wall
Page 18 of 29
Electrical Sub-Station
Booster Pump House
Internal Road Work
Sludge Pit
Page 19 of 29
SNAPSHOT OF SUCCESS: MBLAL PROJECT
Fire Water Pump House Duliajan
Pressure Reducing Station for tank steam supply
Page 20 of 29
Fire Water Tank Duliajan
Switch Room Duliajan
Page 21 of 29
Fire Water Pump House Tengakhat
Switch Room Tengakhat
Page 22 of 29
Air Instruments Shed Tengakhat
Fire Water Pump House Moran
Page 23 of 29
Fire Water Tank Moran
Existing Tank Farm Moran
Page 24 of 29
Fire Water Tank Jorhat
Hydrant Line Jorhat
Page 25 of 29
Instrument Shed Jorhat
10.0 CAPEX UTILIZATION
PROJECT LOCATION PROJECT OST VS CAPITAL EXPENDITURE ( in Rs)
1. Capacity Augmentation of Intermediate Tank farm (2nos. of 20,000 KL capacity each, 50mtrs. dia crude oil storage tank.
Tengakhat Project Cost: 70.78 Crore
Expenditure: 54.82 Crore
2. Secondary Tank Farm, (Tank Capacity 40, 000KLS)
Madhuban Project Cost : 438.84 Cr
Expenditure : 72.79 Cr
3. Construction of Effluent Plant (Capacity-5000KLs)
Tengakhat
Project Cost : 139.10 +50.0 Cr.
Expenditure : NIL.
Page 26 of 29
4. Construction of Group gathering Station (Capacity: 2000KLPD Crude, 5 MMSCMD NAG)
Baghjan Project Cost : 349.0 + 2.96 Cr.
Expenditure : 0+0.86 cr.
5.
Construction of Gas Compressor Station (Capacity: 0.45 MMSCMD Gas Boosting & Lifting facility)
Makum Project Cost : 120.00 Cr Expenditure : NIL
6 Water Injection Station Dikom
7 Loc. HNE(Makum) to CGGS, Madhuban Gas Pipeline
Makum/Madhuban Budget Available: 25.60 Cr
8 Gas Transmission Line from Baghjan to CGGS
Baghjan/ Madhuban Project Cost : Under process
Expenditure : NIL
9 Oil Collecting Station at Nadua and Group gathering Station, East Khagorijan
Nadua / Khagorijan Project Cost : Under Process
Expenditure : NIL
11.0 COST SAVING MEASURES
Delay in timely completion of projects is one of the single most cost
escalation factors. Efforts have been made to complete all projects in
time, despite various constraints both internal & external. The concept of
Project Management is exercised by the Project Team and will prove to be
effective in terms of minimizing time delay. OIL Management has taken
action in this regard and few initiatives are on hand to make the Projects
Department a self-contained unit. This effort will definitely bring down
time delays and eventually minimize cost overrun of the Projects to a
great extent.
Control of external factors beyond control has been a major factor in
delay in execution of Projects but substantial results have been achieved
as an outcome of dedicated team effort by way of constant Liaison with
District Administration, NGOs etc.
Page 27 of 29
Implementation of methodologies: Engineering Project management
Consultancy (EPMC) Service for Basic Design, FEED, Tender preparation
and Project Management, Engineering Procurement & Construction
(EPC) contractor for Detail design, procurement and construction of
projects is cost saving measure for the ensuring quality, cost control of
the projects.
The introduction of Engineering, Procurement, Construction
Management (EPCM) methodology in the project execution shall lead
more efficient project management and cost control. This methodology is
being implemented in construction of the proposed EPS at Nadua &
Group Gathering station at Khagorijan.
12.0 ACCIDENTS
No accidents (minor, serious, fatal) occurred during the year under review.
13.0 ENVIRONMENTAL PROTECTION AND POLLUTION CONTROL
In line with the norms of MOEF, State pollution control board, OISD
guidelines & Mines Regulations, all possible measures adopted for
protection of environment, without compromising safety during all stages
of construction of pipelines & new installations. Some of the measures
are as below –
i) Creation of green belt at newly constructed installations.
ii) Sound barrier for generating sets, compressors, crude oil dispatch
pumps to prevent sound pollution. Use of acoustic generating sets.
iii) Construction of ground flare as per Environmental Protection Act
has been initiated for new OCSs & GGS.
iv) Construction Ground Flare system at Makum OCS.
Page 28 of 29
14.0 ORGANISATION & MANPOWER
Existing Nos.
Executive 15
Employee 06
Executive on Contract 04
15.0 TRAINGING ATTENDED
FINANCIAL YEAR
2016-2017 STRENGTH 15
IN HOUSE IN COUNTRY OVERSEAS EXECUTIVE 01 01 NIL
FINANCIAL YEAR
2016-2017 STRENGTH 9
IN HOUSE IN COUNTRY OVERSEAS EMPLOYEE 01 0 NIL
16.0 TRANSFER & RETIREMENT
No. of executive transferred during 2016-2017
03
No. of work person transferred during 2016-2017
Nil
Executive retired during 2016-2017
01
Work person retired during 2016-2017
Nil
No. of executives resigned during 2016-2017
01
No. of work persons resigned during 2016-2017
Nil
No. of executives joined during 2016-2017
07
No. of work persons joined during 2016-2017
Nil
-000-