annual mff progress report...(on track, potential problem, at risk) on track 1 tranche 1 update...

266
Annual MFF Progress Report 32234013 For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE Project Title MFF - Railway Sector Investment Program (Facility Concept) Project No. 32234-013 Country/ Regional Bangladesh Department SARD Key Dates Approval Date Original Closing Date Revised Closing Date 10 Oct 2006 01 Dec 2011 09 Oct 2016 Division SATC MFF Amount ($ million) 430.00 Source OCR ADF Cofinancing ($ million) N/A Source N/A Facility Summary ADB approved the MFF - Railway Sector Investment Program (Facility Concept) for an aggregate amount not exceeding $430.00 million from ADB’s ADF, OCR on 10 October 2006. Impact: Promote sustainable national economic growth and poverty reduction in Bangladesh. it will achieve this by improving rail transport efficiency and capacity. Outcome: Improve the performance of the railways sector through enhanced efficiency Outputs: BR becomes a commercially focused rail service provider BR corporate governance is improved BR safety record is improved Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework. Estimated Total No. of Tranches to be Processed 1 Approved Tranches To Date 3 Approved Tranche Amount to Date 380.00 Facility Change in Scope Category Date Proposed Change N/A N/A N/A Tranche Completion Report N/A Facility Completion Report N/A MFF Performance Rating (On Track, Potential Problem, At Risk) On Track 1

Upload: others

Post on 26-Oct-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

32234013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - Railway Sector Investment Program (Facility Concept)

Project No. 32234-013

Country/Regional

Bangladesh Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

10 Oct 2006 01 Dec 2011 09 Oct 2016

Division SATC

MFF Amount ($ million)

430.00Source OCR

ADF

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - Railway Sector Investment Program (Facility Concept) for an aggregate amount not exceeding $430.00 million from ADB’s ADF, OCR on 10 October 2006.

Impact: Promote sustainable national economic growth and poverty reduction in Bangladesh. it will achieve this by improving rail transport efficiency and capacity.

Outcome: Improve the performance of the railways sector through enhanced efficiency

Outputs: BR becomes a commercially focused rail service provider BR corporate governance is improved BR safety record is improved

Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

1

Approved Tranches To Date 3

Approved Tranche Amount to Date

380.00

Facility Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

1

Page 2: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleMFF - Railway Sector Investment Program (Subproject 1)

Project No. 32234-023

Country/Regional Bangladesh Loan/Grant No.

2316, 2317

Project Officer Mohammad Islam Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

13 Feb 2007 30 Jun 2011 09 Oct 2016

Division SATC

Tranche Amount($ million)

130.00 Source ADFOCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/32234-023/main

1 DED = Detailed Engineering Design.

2

Page 3: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the MFF - Railway Sector Investment Program (Subproject 1), not exceeding the aggregate amount of $130.00 million on 13 February 2007. Impact: Promote sustainable national economic growth and poverty reduction in Bangladesh. It will achieve this by improving rail transport efficiency and capacity. Outcome: Improve the performance of the railways sector through enhanced efficiency Outputs: 2316: Double track between Tongi and Bhairab Bazar completed 2317: BR becomes a commercially focused rail service provider 2317: BR corporate governance is improved 2317: BR safety record is improved Implementation Arrangements: Bangladesh Railway is the executing agency for the investment program. Loan 2316 is the investment project, while Loan 2317 is the reform component of Tranche 1. Two implementation units were established: (a) the reform implementation unit staffed by qualified officers from BR, and (b) the project implementation unit headed by the project director who will supervise the investment project. An inter-ministerial committee co-chaired by the Secretary, Ministry of Commerce, and consisting of representatives from Economic Relations Division, Ministry of Establishment, the Prime Minister's Officer, Bangladesh Railway, and other agencies, has also been established to oversee, monitor and provide necessary policy guidance. Implementation Status: Loan 2316: Construction of the Tongi-Bhairab Bazar Double Track (64 km) is under implementation. All procurement activities have been completed. Loan 2317: The contract for procurement of videoconferencing equipment and recruitment of the consultants for ERP software implementation are ongoing.

Tranche Change in Scope

Category Date Approved Proposed Change

Minor Change 18 Sep 2015 Inclusion of a new subcategory for signaling equipment under the disbursement categories, and reallocation of funds from the existing equipment category and the unallocated amount to the new cost item.

1 DED = Detailed Engineering Design.

3

Page 4: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

119.04 100.00 113.78 98.18

Significant Developments During the Year

Tranche 1 (Loans 2316, 2317) for $30.00 million from the Asian Development Fund (ADF) and Ordinary Capital Resources (OCR), was approved on 13 February 2007 and declared effective on 24 April 2007. Tranche 1 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $119.05 million (100.0%) and $113.78 million (98.2%), respectively. Loan 2316: Construction of the Tongi-Bhairab Bazar double track was awarded on 27 July 2011, and the project is now under implementation. The physical progress of the project is 99% as of 31 December 2015 (Tongi-Bhairab Component). The additional funding for the construction work is being provided by Tranche 2. Loan 2317: The proposed Tariff Reform and Corporatization of Bangladesh Railway's Container Business was approved by the Prime Minister in December 2015. Scope Change: There was one minor change for this tranche in 2015. Undertaking and Covenants: There are 36 covenants for Tranche 1, all of which are being complied with.

1 DED = Detailed Engineering Design.

4

Page 5: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche Title Railway Sector Investment Program - Tranche 2 Project No. 32234-043

Country/Regional Bangladesh Loan/Grant No.

2845

Project Officer Mohammad Islam Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

22 Dec 2011 30 Jun 2016 N/A

Division BRM

Tranche Amount($ million)

150.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

35.00

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/32234-043/main

Tranche Summary

ADB approved the Railway Sector Investment Program - Tranche 2, not exceeding the aggregate amount of $150.00 million on 22 December 2011.

Impact: Efficient and safe railway transport in the Dhaka-Chittagong and Dhaka-Ishurdi-Darsana-Khulna/India corridor

Outcome: Improved railway transport capacity in the Dhaka-Chittagong and Dhaka-Ishurdi-Darsana-Khulna/India corridors

Outputs: 1. Tongi-Bhairab Bazar Double Track completed; 2. Signaling system Darsana-Ishurdi improved 3.Yards rehabilitated and loops extended in the Darsana-Ishurdi-Sirajganj Bazar section

Implementation Arrangements: Bangladesh Railway is the executing agency for the investment program. Project Implementation Unit is headed by Project Director (General Manager) for the implementation and coordination of the project.

Implementation Status: Civil work of Tongi-Bhairab Bazar Double Track and Loops extended in the Darsana-Ishurdi-Sirajganj Bazar section are almost completed. On the other hand, progress of Signaling Contract is only 18% by the end of December 2015. The estimated cost overrun of $35.00 million is to be covered under Tranche 4 within total MFF amount.

1 DED = Detailed Engineering Design.

5

Page 6: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

147.75 100.00 148.48 100.00

Significant Developments During the Year

Tranche 2 (Loan 2845) is a loan of $50.0 million from Ordinary Capital Resources (OCR), which was approved on 22 December 2011 and declared effective on 05 November 2012. Tranche 2 is rated as On Track.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $147.75 million (100.0%) and $148.48 million (100.0%), respectively. By December 2015, progress of the subprojects are at: (1) 99.71% for construction of Tongi-Bhairab Bazar double track; (2) rehabilitation of loop line at 90%; and (3) signaling at 18%.

Scope Change: There were no scope changes for this tranche in 2015.

Undertaking and Covenants: The covenants under this tranche are being complied with.

1 DED = Detailed Engineering Design.

6

Page 7: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 3 UPDATE

Tranche Title Railway Sector Investment Program - Tranche 3 Project No. 32234-053

Country/Regional Bangladesh Loan/Grant No.

3097

Project Officer Markus Roesner Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

09 Dec 2013 9 Oct 2016 N/A

Division SATC

Tranche Amount($ million)

100.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/32234-053/main

Tranche Summary

ADB approved the Railway Sector Investment Program - Tranche 3, not exceeding the aggregate amount of $100.00 million on 9 December 2013.

Impact: Efficient and safe railway transport in Bangladesh.

Outcome: Improved railway transport capacity in the main line network of Bangladesh Railway

Outputs: New passenger carriages commissioned

Implementation Arrangements: Bangladesh Railway (BR) is the executing agency, a dedicated Project Director under the Project Implementation Unit (PIU) for Investment Projects, which was established under the first tranche, and is responsible for the implementation of Tranche 3.

Implementation Status: The amount of $72.392 million was committed on 27 November 2014 to finance the 50 broad gauge passenger carriages and 100 meter gauge passenger carriages for BR's main line network in two contracts. The carriages will be delivered in 2016. Payment is based on ADB's commitment procedure and will be made upon delivery and commissioning of the carriages. Out of the loan amount of $100 million, the cumulative amount for contract awards and disbursements comprises $72.392 million (72 %) and $0.1 million (0.1 %) respectively as of 31 December 2015. The performance of goods contractors is satisfactory. No further contract awards are planned and the contracts do not include any provisions for price escalation and quantities will not be altered for this kind of goods contracts.

1 DED = Detailed Engineering Design.

7

Page 8: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

72.39 100.00 0.17 100.00

Significant Developments During the Year

Tranche 3 (Loan 3097) is a loan of $100.00 million from Ordinary Capital Resources (OCR), which was approved on 09 December 2013 and declared effective on 17 September 2014. Tranche 3 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 3 have reached $72.39 million (100.0%) and $.17 million (100.0%), respectively. Targeted outputs were delivered within schedule. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: The 9 covenants under this tranche are being complied with.

1 DED = Detailed Engineering Design.

8

Page 9: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

35290013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - North Eastern Region Capital Cities Development Investment Program

Project No. 35290-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

23 Jun 2009 30 Jun 2016 22 Jun 2019

Division SAUW

MFF Amount ($ million)

200.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - North Eastern Region Capital Cities Development Investment Program for an aggregate amount not exceeding $200.00 million from ADB’s OCR on 23 June 2009. Impact: Improved environment and well-being of urban residents in the five program cities Outcome: Sustainable and increased access to better urban services in five program cities Outputs: Part A: Improved urban infrastructure and services A.1 Expanded and rehabilitated water supply systems A.2 Sewage collection, management, and treatment, and improved sanitation A.3 Solid waste management systems Part B: Strengthened institutional development and investment program management B.1 Urban institutional, financial, and service delivery reforms and strengthened municipal capacity B.2 Improved public utility management B.3 Increased public awareness B.4 Investment program capacity Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 3

Approved Tranche Amount to Date

182.00

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

9

Page 10: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

10

Page 11: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleNorth Eastern Region Capital Cities Development Investment Program, Tranche 1

Project No. 35290-023

Country/Regional India Loan/Grant No.

2528

Project Officer Ron Slangen Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

01 Jul 2009 30 Apr 2016 N/A

Division SAUW

Tranche Amount($ million)

30.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/35290-023/main

1 DED = Detailed Engineering Design.

11

Page 12: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the North Eastern Region Capital Cities Development Investment Program, Tranche 1, not exceeding the aggregate amount of $30.00 million on 1 July 2009. Impact: Improved environment and well-being or urban residents in the five program cities. Outcome: Sustainable and increased access to better urban services in all 5 cities Outputs: The Project will provide prioritized urban infrastructure development subprojects in five cities, supported by a program of institutional development and capacity building. Part A. Improved urban infrastructure and services 1. Expanded and rehabilitated water supply systems 2. Solid waste management systems Part B: Strengthened institutional development and investment program management 3. Urban institutional, financial, and service delivery reforms and strengthened municipal capacity Activities with Milestones Implementation Arrangements: The executing agency is the Ministry of Urban Development (MOUD). An investment program coordination cell (IPCC) has been established in MOUD. IPCC is responsible for the overall management of NERCCDIP in the five cities. The team was tasked to (i) monitor overall the physical progress and implementation, (ii) review the subprojects submitted by the states according to the subproject selection criteria, (iii) consolidate payment and reimbursement requests, (iv) report on the progress of NERCCDIP implementation and other matters, (v) monitor implementation of the overall reform program and compliance with loan covenants, and (vi) provide assistance to the states. Implementation Status: All water supply subprojects in Aizawl, Agartala, Gangtok and Kohima were completed. The solid waste management subproject in Kohima is nearing completion. There were delays in solid waste management subproject (landfill works) in Shillong due to poor performance of the contractor. Tranche 1 period (30 April 2016) is planned to be extended by 14 months to: (i) complete balance works of Shillong landfill works, (ii) finance initial O&M period of Kohima landfill-compost facility, and (iii) continue the services of the design, construction supervision and management consultants (DSMCs).

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

12

Page 13: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

22.67 98.78 19.42 100.00

Significant Developments During the Year

Tranche 1 (Loan 2528) is a loan of $25.54 million from Ordinary Capital Resources (OCR), which was signed on 4 August 2009 and declared effective on 19 November 2009. Tranche 1 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $22.67 million (98.8%) and $19.42 million (100.0%), respectively. All water supply subprojects in Aizawl, Agartala, Gangtok and Kohima were completed. The solid waste management subproject in Kohima is nearing completion. There were delays in solid waste management subproject (landfill works) in Shillong due to poor performance of the contractor. Urban institutional, financial, service delivery and public utility management reforms are ongoing. The design, construction supervision and management consultants (DSMCs) are continuously supporting the EAs on ongoing project management activities. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: There are 13 undertakings and 28 covenants for Tranche 1. All the undertakings and covenants are being complied with by the EA. All six (6) Auditor's Report and Audited Project Financial Statements for fiscal year 2015 for Tranche 1 were submitted by the EA and reviewed by ADB.

1 DED = Detailed Engineering Design.

13

Page 14: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche TitleNorth Eastern Region Capital Cities Development Investment Program - Tranche 2

Project No. 35290-033

Country/Regional India Loan/Grant No.

2834

Project Officer Ron Slangen Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

31 May 2011 30 Jun 2016 30 Jun 2018

Division SAUW

Tranche Amount($ million)

72.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/35290-033/main

1 DED = Detailed Engineering Design.

14

Page 15: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the North Eastern Region Capital Cities Development Investment Program - Tranche 2, not exceeding the aggregate amount of $72.00 million on 16 December 2011. Impact: Sustainable urban services in 5 program cities Outcome: Improved access to selected urban services in 5 program cities Outputs: (i) Constructed and rehabilitated water supply infrastructure (ii) Constructed sanitation infrastructure (iii) Constructed and installed SWM infrastructure (iv) Strengthened local government for better financial management and sustainable service delivery (v) Efficient Project Management Unit (PMU) operational Implementation Arrangements: The executing agency is the Ministry of Urban Development (MOUD). An investment program coordination cell (IPCC) will be established in MOUD. IPCC will be responsible for the overall management of the project in the five cities. The team will (i) monitor overall the physical progress and implementation, (ii) review the subprojects submitted by the states according to the subproject selection criteria, (iii) consolidate payment and reimbursement requests, (iv) report on the progress of project implementation and other matters, (v) monitor implementation of the overall reform program and compliance with loan covenants, and (vi) provide assistance to the states. Implementation Status: For Water Supply, Solid Waste Management and Sanitation, 30 of the 42 contracts have been awarded, with physical works in various stages of implementation in all states. Remaining 12 contracts expected to be awarded by early 2016. On strengthened local government, financial management and sustainable service delivery, reforms are in progress in 3 states, with support from institutional development consultants. All Project Management Units have been formed in all 5 states and are functioning efficiently.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

1 DED = Detailed Engineering Design.

15

Page 16: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

41.17 99.18 18.56 100.00

Significant Developments During the Year

Tranche 2 (Loan 2834) is a loan of $60.00 million from Ordinary Capital Resources (OCR), which was signed on 19 November 2012 and declared effective on 19 February 2013. Tranche 2 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $41.17 million (99.2%) and $18.56 million (100.0%), respectively. All water supply, solid waste management and sanitation subprojects in Aizwal, Shillong, Kohima, Agartala and in Gangtok are in various stages of implementation. Urban institutional, financial, service delivery and public utility management reforms are ongoing. The design, construction supervision and management consultants (DSMCs) are continuously supporting the EAs on ongoing project management activities. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: There are 13 undertakings and 31 covenants for Tranche 2. All the undertakings and covenants are being complied with by the EA. All six (6) Auditor's Report and Audited Project Financial Statements for fiscal year 2015 for Tranche 2 were submitted by the EA and reviewed by ADB.

1 DED = Detailed Engineering Design.

16

Page 17: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 3 UPDATE

Tranche TitleNorth Eastern Region Capital Cities Development Investment Program – Tranche 3

Project No. 35290-043

Country/Regional India Loan/Grant No.

3337

Project Officer Neeta Pokhrel Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

27 Nov 2015 22 Jun 2019 N/A

Division SAUW

Tranche Amount($ million)

80.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/35290-043/main

Tranche Summary

ADB approved the North Eastern Region Capital Cities Development Investment Program ? Tranche 3, not exceeding the aggregate amount of $80.00 million on 27 November 2015. Impact: improved environment and well-being of urban residents in the program cities (defined by Investment Program). Outcome: increased access to sustainable and improved urban services in Agartala and Aizawl. Outputs: water supply infrastructure constructed and rehabilitated sanitation infrastructure constructed solid waste management infrastructure constructed and rehabilitated capacity for project implementation and service delivery improved. Implementation Arrangements: Not Applicable Implementation Status: Not Yet Effective

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

17

Page 18: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating

Financial

Contract Awards

Disbursements

Safeguards

Technical

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

0.00 0.00 0.00 0.00

Significant Developments During the Year

1 DED = Detailed Engineering Design.

18

Page 19: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

36330013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - Railway Sector Investment Program (Facility) Project No. 36330-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

31 Aug 2011 31 Dec 2018 N/A

Division SATC

MFF Amount ($ million)

500.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - Railway Sector Investment Program (Facility) for an aggregate amount not exceeding $500.00 million from ADB’s OCR on 31 August 2011. Impact: Improved transport network and greater mobility Outcome: Energy-efficient, safe, reliable, affordable and environment-friendly railway system developed Outputs: 1. Expanded physical infrastructure and enhanced efficiency of infrastructure use 2. Improved operations efficiency of Indian Railways 3. Clean development mechanism (CDM) application and implementation for the investment program Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 2

Approved Tranche Amount to Date

280.00

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

19

Page 20: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche Title Railway Sector Investment Program - Tranche 1 Project No. 36330-023

Country/Regional India Loan/Grant No.

2793

Project Officer Guenter Hoelscher Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

18 Oct 2011 30 Jun 2018 N/A

Division SATC

Tranche Amount($ million)

150.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/36330-023/main

Tranche Summary

ADB approved the Railway Sector Investment Program - Tranche 1, not exceeding the aggregate amount of $150.00 million on 18 October 2011. Impact: Improved transport system in the country Outcome: An energy-efficient, safe, reliable, affordable and environment-friendly railway system developed Outputs: 1. Expanded physical infrastructure and enhanced efficiency of infrastructure use 2. Improved operations efficiency 3. Clean development mechanism (CDM) application and implementation for the investment program Implementation Arrangements: The Ministry of Railways is the executing agency of the facility, with the Rail Vikas Nigam Ltd. as the key implementing agency for the railway improvement component. Retroactive financing and advance contracting for works, goods and consulting services have been approved. Loan proceeds are being disbursed in accordance with ADB's Loan Disbursement Handbook and detailed arrangements agreed upon between the Government and ADB. Implementation Status: Rail doubling and electrification works are ongoing, with two remaining contracts being procured. The piggy-backed technical assistance is ongoing, while the draft financing investment plan for implementing nationally appropriate mitigation action (NAMA) is being prepared.

1 DED = Detailed Engineering Design.

20

Page 21: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

147.69 100.00 80.91 100.00

Significant Developments During the Year

Tranche 1 (Loan 2793) is a loan of $150.00 million from Ordinary Capital Resources (OCR), which was approved on 18 October 2011 and declared effective on 05 October 2012. Tranche 1 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $147.69 million (100.0%) and $80.91 million (100.0%), respectively. The weighted physical progress for works is 40% after about 61% elapsed time for implementation of Tranche 1. The piggy-backed technical assistance is ongoing; the monitoring reports on greenhouse gas emission and efficiency in India Railways (for inter-urban rail) have been submitted. Scope Change: There were no scope changes for this tranche in 2015. However, a minor change to implementation arrangements was approved in February 2015 to confirm that local transportation, freight, insurance and other related expenses specified in the goods contracts are eligible for reimbursement. Undertaking and Covenants: There are 15 undertakings and 47 covenants for Tranche 1, all of which are being complied with.

1 DED = Detailed Engineering Design.

21

Page 22: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche Title Railway Sector Investment Program - Tranche 2 Project No. 36330-033

Country/Regional India Loan/Grant No.

3108

Project Officer Guenter Hoelscher Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

06 Feb 2014 30 Jun 2019 N/A

Division SATC

Tranche Amount($ million)

130.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/36330-033/main

Tranche Summary

ADB approved the Railway Sector Investment Program - Tranche 2, not exceeding the aggregate amount of $130.00 million on 6 February 2014. Impact: Energy-efficient, safe, reliable, affordable and environment-friendly railway transport developed Outcome: Improved railway transport capacity in the project rail routes Outputs: Track components delivered to construction sites for installation Implementation Arrangements: The Ministry of Railways is the executing agency of the facility, with the Rail Vikas Nigam Ltd. as the key implementing agency for the railway improvement component. Retroactive financing and advance contracting for works, goods and consulting services have been approved. Loan proceeds are being disbursed in accordance with ADB's Loan Disbursement Handbook and detailed arrangements agreed between the Government and ADB. Implementation Status: All three supply contracts for rails and thick web switches are ongoing.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

22

Page 23: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

112.28 100.00 66.18 100.00

Significant Developments During the Year

Tranche 2 (Loan 3108) is a loan of $130.00 million from Ordinary Capital Resources (OCR), which was approved on 06 February 2014 and declared effective on 28 March 2014. Tranche 2 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $112.28 million (100.0%) and $66.18 million (100.0%), respectively. The two contracts for the supply of rails and another for thick web switches have all been awarded; supply of rails is ongoing. Scope Change: There were no scope changes for this tranche in 2015. However, a minor change to implementation arrangements was approved in February 2015 to confirm that local transportation, freight, insurance and other related expenses specified in the goods contracts are eligible for reimbursement. Undertaking and Covenants: There are 23 undertakings and covenants for Tranche 2, which are all being complied with.

1 DED = Detailed Engineering Design.

23

Page 24: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

37066013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - Rural Roads Sector II Investment Program (Facility Concept)

Project No. 37066-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

20 Dec 2005 31 Mar 2010 N/A

Division SATC

MFF Amount ($ million)

750.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - Rural Roads Sector II Investment Program (Facility Concept), not exceeding the aggregate amount of $750.00 million on 20 December 2005. Impact and Outcome: The impact of the MFF is to help reduce poverty and deprivation, and support economic growth of rural communities in India. The outcome is to enhance access to markets, employment opportunities, and social services, including health and education. Outputs: The expected output is to provide better and more efficient physical infrastructure which will lead to improve connectivity between rural and urban communities and greater access to markets and economic activity. Significant Developments of the Facility: Project Completion Report (PCR) for Tranches 1, 2, and 4 have been completed. PCR preparation for Tranche 3 is ongoing, while Facility Completion Report (FCR) and PCR for Tranche 5 will be prepared in 2017.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 5

Approved Tranche Amount to Date

794.85

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

24

Page 25: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

1 DED = Detailed Engineering Design.

25

Page 26: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

37091013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - Agribusiness Infrastructure Development Investment Program (Facility)

Project No. 37091-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

16 Sep 2010 31 Dec 2018 N/A

Division SAER

MFF Amount ($ million)

170.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - Agribusiness Infrastructure Development Investment Program (Facility) for an aggregate amount not exceeding $170.00 million from ADB’s OCR on 16 September 2010. Impact: Greater value of horticulture products captured by the stakeholders of the integrated value chain (IVC) inselected regions of Bihar and Maharashtra. Outcome: Private and public sectors invest and private sector manages at least 8 IVCs for horticultural HVC, which are inclusive of small scale farmers. Outputs: Value chain functioning. Significant Developments of the Facility: Procurement of concessionaires for agribusiness infrastructure and development and its operation is ongoing. ADB undertook an analysis of the agribusiness sector and the MFF to identify bottlenecks and expedite implementation. The results of the analysis were discussed with the government, and ensuing remedial actions are being taken.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 2

Approved Tranche Amount to Date

91.90

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

26

Page 27: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

27

Page 28: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleAgribusiness Infrastructure Development Investment Program - Tranche 1

Project No. 37091-023

Country/Regional India Loan/Grant No.

2669

Project Officer Paolo Spantigati Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

24 Sep 2010 N/A N/A

Division INRM

Tranche Amount($ million)

67.60 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/37091-023/main

1 DED = Detailed Engineering Design.

28

Page 29: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Agribusiness Infrastructure Development Investment Program - Tranche 1, not exceeding the aggregate amount of $67.60 million on 24 September 2010. Impact: Greater value of horticulture products captured by the stakeholders of the integrated value chain (IVC) in Muzaffarpur and Patna-Nalanda regions of Bihar. Outcome: Private and public sectors invest and private sector manages 2 end-to-end IVCs for horticultural high value crops (HVC), which are inclusive of small-scale farmers (through PPP contract). Outputs: A. IVCs Infrastructure in Muzzafarpur and Patna-Nalanda Set Up and Functional B. IVC stakeholders effectively particiapte in and properly manage the IVC C. State Government perform efficiently their regulatory and oversight functions of the IVCs and the PPP contracts Implementation Arrangements: The executing agency is the Bihar Department of Agriculture. Its project management unit (PMU) provides administrative support, contracting of the PPP transactions, monitoring and evaluation, and financial management. The PMU invites bids from the private sector to design, construct, operate, and maintain the IVC infrastructure and will contract them on a PPP basis, with land provided by the government. Implementation Status: The government and ADB agreed that the current project PPP model does not appear fully appropriate, given the characteristics of the sector and the rigidities and complexities of PPPs that are challenging for agribusiness stakeholders. The government is exploring alternative approaches with ADB's support.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

1 DED = Detailed Engineering Design.

29

Page 30: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

0.16 0.00 0.00 0.00

Significant Developments During the Year

Tranche 1 (Loan 2669) is a loan of $67.60 million from Ordinary Capital Resources (OCR), which was approved on 24 September 2010 and declared effective on 30 August 2012. $32.50 million was canceled on 2 May 2014, reducing the net loan amount to $35.10 million. Tranche 1 is rated as On Track. There was no significant progress on the tranche implementation in 2015. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $.16 million (.0%) and $.00 million (.0%), respectively. The government, with the support of ADB, is exploring alternative approaches to achieve the project outcome. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: The tranche has 19 project-specific covenants. Of these, seven have been complied with, nine are being complied with and three are not yet due.

1 DED = Detailed Engineering Design.

30

Page 31: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche TitleAgribusiness Infrastructure Development Investment Program - Tranche 2

Project No. 37091-033

Country/Regional India Loan/Grant No.

2837

Project Officer Paolo Spantigati Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

19 Dec 2011 31 Dec 2015 N/A

Division INRM

Tranche Amount($ million)

24.30 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/37091-033/main

1 DED = Detailed Engineering Design.

31

Page 32: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Agribusiness Infrastructure Development Investment Program - Tranche 2, not exceeding the aggregate amount of $24.30 million on 19 December 2011. Impact: Increased producer returns from HVC from increased private sector investment in value adding infrastructure from value chains in Maharashtra. Outcome: Expanded agricultural value chains and better integration of small scale farmers into IVCs in the Nashik and Aurangabad-Amravati regions Outputs: 1. IVCs Infrastructure in Nashik and Aurangabad-Amravati regions set up and functional 2. IVC stakeholders effectively participate in and manage IVCs 3. Project Management support strengthened Implementation Arrangements: The executing agency is the Department of Cooperation, Marketing and Textile (DCMT) in Maharashtra. The implementing agency is a project management unit (PMU) within the Maharashtra State Agricultural Marketing Board. Under PFR 2 the components comprise the award of private sector concession contracts for the development and operation of two IVC programs in Nashik and Aurangabad-Amravati regions. In parallel, the Project will support Government to identify and design the development of IVCs in other regions for inclusion in a subsequent PFR/Tranche application. Implementation Status: The tender process for agribusiness concessionaires is underway. Contract awards and disbursements are for consultant services to support project implementation and preparation of a subsequent tranche project.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

0.87 7.75 0.49 4.34

1 DED = Detailed Engineering Design.

32

Page 33: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Significant Developments During the Year

Tranche 2 (Loan 2837) is a loan of $24.30 million from Ordinary Capital Resources (OCR), which was approved on 19 December 2011 and declared effective on 9 April 2012. Tranche 2 is rated as Actual Problem. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $.87 million (7.8%) and $.49 million (4.3%), respectively. The request for proposals for the PPP concessionaires was first issued in March 2014, but no bids were received and the bidding process was cancelled. After the restructuring of the PPP model, a second bid was launched on 27 October 2015. The deadline for submission of proposals is 8 January 2016. Depending on the results of the bidding process, the tranche may be extended to complete the project. There was no significant physical progress in the implementation of the tranche in 2015. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: Of the 21 project-specific covenants, 17 are being complied with while four are not yet due.

1 DED = Detailed Engineering Design.

33

Page 34: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

37139013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - Uttaranchal Power Sector Investment Program (Facility Concept)

Project No. 37139-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

30 Mar 2006 30 Jun 2012 30 Mar 2016

Division SAEN

MFF Amount ($ million)

300.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - Uttaranchal Power Sector Investment Program (Facility Concept) for an aggregate amount not exceeding $300.00 million from ADB’s OCR on 30 March 2006. Impact: Contribute to economic development in Uttaranchal and the northern region of India through expanded power supply at competitive prices Outcome: Clean Energy Development: (i) expansion of the electric power service area and improvements in the reliability and quality of supply; and (ii) promotion of energy efficiency by renovating, modernizing, and upgrading exisitng hydropower plantsTransmission Expansion:New associated hydropower plants connected to the state's grid and the northern region grid within 6 months of commissioningCapacity Building:Sector sustainability resulting from continued reforms and improvements in operational efficiency Outputs: CLEAN ENERGY DEVELOPMENT: New small hydropower plants Energy efficiency improvements by renovating, modernizing, and upgrading existing hydropower plants Development of hydrometeorological monitoring framework Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 4

Approved Tranche Amount to Date

284.92

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

34

Page 35: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

35

Page 36: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleMFF - Uttaranchal Power Sector Investment Program (Subproject 1)

Project No. 37139-023

Country/Regional India Loan/Grant No.

2309

Project Officer Hiroki Kobayashi Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

02 Jan 2007 30 Jun 2012 30 Mar 2016

Division SAEN

Tranche Amount($ million)

41.92 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/37139-023/main

1 DED = Detailed Engineering Design.

36

Page 37: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the MFF - Uttaranchal Power Sector Investment Program (Subproject 1), not exceeding the aggregate amount of $41.92 million on 2 January 2007. Impact: Contribute to economic development in Uttaranchal and the northern region of India through expanded power supply at competitive prices Outcome: Clean Energy Development: (i) expansion of the electric power service area and improvements in the reliability and quality of supply; and (ii) promotion of energy efficiency by renovating, modernizing, and upgrading exisitng hydropower plantsCapacity Building: Sector sustainability resulting from continued reforms and improvements in operational efficiency Outputs: CLEAN ENERGY DEVELOPMENT: New small hydropower plants Energy efficiency improvements by renovating, modernizing, and upgrading existing hydropower plants Development of hydrometeorological monitoring framework CAPACITY BUILDING: Training of the Uttaranchal Energy Department and implementing agencies' staff for project management and implementation; development of human resource management program; upgrading of information technology systems Design of state-level power trading company Energy efficiency improvements by renovating, modernizing, and updgrading existing hydropower plants Energy efficiency improvements by renovating , modernizing, and upgrading existing hydropower plants Development of hydrometeorological monitoring network Implementation Arrangements: The executing agency is Uttarakhand Energy Department (UED) and the implementing agency is the Uttarakhand Jal Vidyut Nigam Limited (UJVNL). Implementation Status: The project was fundamentally delayed by the flood disaster in 2013 that substantial time is required for rebuilding. The reconstruction of the damaged small hydropower (SHP) projects is to be completed by June 2019. UJVNL has been working for rebidding of 4 SHPs in 2014 and 2015. A total of $16.17 million, which cannot be disbursed by the MFF period until 30 March 2016, was cancelled, and the loan amount was reduced to $25.75 million.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

37

Page 38: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

26.49 100.00 21.55 83.68

Significant Developments During the Year

Tranche 1 (Loan 2309) is a loan of $41.92 million from Ordinary Capital Resources (OCR), which was approved on 02 January 2007 and declared effective on 29 March 2007. Tranche 1 is rated as On Track. Partial cancellations of a total of $16.17 million, were approved on 30 March 2015 and 12 October 2015, reducing the loan amount to $25.75 million. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $26.49 million (100.0%) and $21.55 million (83.7%), respectively. The project was fundamentally delayed by the flood disaster in 2013 that substantial time is required for rebuilding. The reconstruction of the damaged small hydropower (SHP) projects is to be completed by June 2019. The rebidding of 4 small hydropower (SHP) projects has proceeded with 5 contracts awarded and 5 more in process. ADB approved the revised training program and activities have been undertaken with full participation of UJVNL staff. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: There are 26 covenants under this tranche, 10 of which have been complied with while 16 are being complied with.

1 DED = Detailed Engineering Design.

38

Page 39: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche TitleMFF - Uttarakhand Power Sector Investment Program - Project 2

Project No. 37139-033

Country/Regional India Loan/Grant No.

2498

Project Officer Hiroki Kobayashi Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

23 Dec 2008 30 Jun 2012 30 Mar 2016

Division SAEN

Tranche Amount($ million)

62.40 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/37139-033/main

Tranche Summary

ADB approved the MFF - Uttarakhand Power Sector Investment Program - Project 2, not exceeding the aggregate amount of $62.40 million on 23 December 2008. Impact: Contribute to economic development in Uttarakhand and the northern region of India through expanded power supply at competitive prices Outcome: Transmission Expansion: New associated hydropower plants connected to the state's grid and the northern region grid within 6 months of commissioning Outputs: Transmission Expansion: Eight high-voltage transmission lines and associated substations constructed Capacity Building: The Uttarakhand Energy Department and implementing agencies' staff trained for project management and implementation; development of human resource management program; upgrading of information technology systems Implementation Arrangements: The executing agency is the Uttarakhand Energy Department and the implementing agency is Power Transmission Corporation of Uttarakhand Limited. Implementation Status: The project was fundamentally delayed by the flood disaster in 2013 that substantial time is required for completion. A minimum of 3 years and 3 months beyond this will be required to complete the project that will be rebuilt after the disaster.

1 DED = Detailed Engineering Design.

39

Page 40: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

8.82 81.90 5.24 48.62

Significant Developments During the Year

Tranche 2 (Loan 2498) is a loan of $62.40 million from Ordinary Capital Resources (OCR), which was approved on 23 December 2008 and declared effective on 27 April 2009. Tranche 2 is rated as Potential Problem. Partial cancellation of $51.63 million was approved on 30 March 2015, reducing the loan amount to $10.77 million. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $8.82 million (81.9%) and $5.24 million (48.6%), respectively. The tranche was extended until 30 March 2016 (the end of the MFF availability period). To utilize the balance available due to the termination of contract for construction of 400 KV line, 6 Projects have been included in the tranche. One of these projects will be completed by the loan closing date of 30 March 2016, and the remaining are being dropped. The training proposal has been submitted & approved. Training activities will commence upon ADB 's approval of the advance to the imprest account. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: Tranche 2 has 10 covenants, 2 of which have been complied with while 8 are being complied with.

1 DED = Detailed Engineering Design.

40

Page 41: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 3 UPDATE

Tranche TitleMFF - Uttarakhand Power Sector Investment Program - Project 3

Project No. 37139-043

Country/Regional India Loan/Grant No.

2502

Project Officer Hiroki Kobayashi Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

08 Jan 2009 30 Jun 2012 30 Mar 2016

Division SAEN

Tranche Amount($ million)

30.60 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/37139-043/main

Tranche Summary

ADB approved the MFF - Uttarakhand Power Sector Investment Program - Project 3, not exceeding the aggregate amount of $30.60 million on 8 January 2009. Impact: Contribute to economic development in Uttarakhand and the northern region of India through expanded power supply at competitive prices Outcome: Transmission Expansion:New associated hydropower plants connected to the state's grid and the northern region grid within 6 months of commissioning Outputs: Transmission Expansion: Eight high voltage transmission lines and associated substations constructed Capacity Building: The Uttarakhand Energy Department and implementing agencies' staff trained for project management and implementation; development of human resource management program; upgrading of information technology systems Implementation Arrangements: The executing agency is the Uttarakhand Energy Department (UED) and the implementing agency is the Power Transmission Corporation of Uttarakhand Limited (PTCUL). Implementation Status: The project was fundamentally delayed by the flood disaster in 2013 that substantial time is required for completion. This is the only project that is expected to achieve full project completion by closing date.

1 DED = Detailed Engineering Design.

41

Page 42: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

27.12 96.85 19.61 70.04

Significant Developments During the Year

Tranche 3 (Loan 2502) is a loan of $30.60 million from Ordinary Capital Resources (OCR), which was approved on 08 January 2009 and declared effective on 27 April 2009. Tranche 3 is rated as Potential Problem. Partial cancellation of $2.60 million was approved on 30 March 2015, reducing the loan amount to $28 million. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 3 have reached $27.12 million (96.9%) and $19.61 million (70.0%), respectively. The project was fundamentally delayed by the flood disaster in 2013 that substantial time is required for completion. This is the only project that is expected to achieve full project completion by the closing date of 30 March 2016. The activities are in progress. Six transformers have been successfully transported to the site. Full completion, including testing and energizing, is expected by December 2015. The training proposal has been submitted & approved, and training activities will commence upon ADB s approval of the advance to the imprest account. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: The tranche has 10 covenants, 1 complied with while 9 are being complied with.

1 DED = Detailed Engineering Design.

42

Page 43: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 4 UPDATE

Tranche TitleUttarakhand Power Sector Investment Program - Tranche 4

Project No. 37139-053

Country/Regional India Loan/Grant No.

2924

Project Officer Hiroki Kobayashi Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

26 Oct 2012 30 Mar 2016 N/A

Division SAEN

Tranche Amount($ million)

150.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/37139-053/main

Tranche Summary

ADB approved the Uttarakhand Power Sector Investment Program - Tranche 4, not exceeding the aggregate amount of $150.00 million on 26 October 2012. Impact: Enhanced Hydropower Development in Uttarakhand. Outcome: Strong and reliable bulk power evacuation system from Uttarakhand to the Northern Grid. Outputs: Uttarakhand Integrated Transmission System for Alaknanda basin completed. Implementation Arrangements: The executing agency is the Uttarakhand Energy Department (UED) and the implementing agency is the Power Transmission Corporation of Uttarakhand Limited (PTCUL). Implementation Status: The project was fundamentally delayed by the flood disaster in 2013 that substantial time is required for completion. A minimum if 3 years and 3 months beyond this will be required to complete the four projects that will be rebuilt after the disaster.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

43

Page 44: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

10.12 100.00 7.28 100.00

Significant Developments During the Year

Tranche 4 (Loan 2924) is a loan of $150.00 million from Ordinary Capital Resources (OCR), which was approved on 26 October 2012 and declared effective on 30 August 2013. Tranche 4 is rated as On Track. Partial cancellations of $142.38 million, were approved on 30 March 2015 and on 12 October 2015, reducing the total loan amount to $7.62 million. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 4 have reached $10.12 million (100.0%) and $7.28 million (100.0%), respectively. The project was fundamentally delayed by the flood disaster in 2013 that substantial time is required for completion. A minimum of 3 years and 3 months will be required to complete the four projects that will be rebuilt after the disaster. Two projects are identified for the tranche. Both have encountered delays, thus, no further progress is envisioned towards the loan availability period. The training proposal has been submitted & approved, and training activities will commence upon ADB 's approval of the advance to the imprest account. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: Tranche 4 has 10 covenants and all are being complied with.

1 DED = Detailed Engineering Design.

44

Page 45: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

37143013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - North Eastern State Roads Investment Program (Facility Concept)

Project No. 37143-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

21 Jul 2011 30 Jun 2017 30 Jun 2021

Division SATC

MFF Amount ($ million)

200.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - North Eastern State Roads Investment Program (Facility Concept) for an aggregate amount not exceeding $200.00 million from ADB’s OCR on 21 July 2011. Impact: Improved surface transport connectivity in NER. Outcome: Improved mobility and accessibility in the project areas. Outputs: 1. Reconstructed and rehabilitated state roads 2. Improved business process and staff skills of PWDs Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 2

Approved Tranche Amount to Date

200.00

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

45

Page 46: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleMFF - North Eastern State Roads Investment Program - Tranche 1

Project No. 37143-023

Country/Regional India Loan/Grant No.

2770

Project Officer Anil Motwani Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

22 Aug 2011 31 Dec 2016 N/A

Division SATC

Tranche Amount($ million)

74.80 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/37143-023/main

Tranche Summary

ADB approved the MFF - North Eastern State Roads Investment Program - Tranche 1, not exceeding the aggregate amount of $74.80 million on 22 August 2011. Impact: Improved surface transport connectivity in NER Outcome: Improved mobility and accessibility in the project areas Outputs: 1. Reconstructed and rehabilitated state roads 2. Improved business process and staff skills Implementation Arrangements: The executing agency is Ministry of Development of North Eastern Region (MDONER) and the implementing agencies are the State Public Works Department of Assam, Meghalaya and Sikkim. Implementation Status: As of 31 December 2015, all contracts have been awarded and construction works are ongoing. There have been delays in payment to the contractor due to the fund flow issue between MDONER and state governments. The Project Management Consultant engaged by ADB assisted to further strengthen the capacity of the MDONER and help mainstream effective and efficient project implementation in processing fund release. The consultant commenced its services on May 2015.

1 DED = Detailed Engineering Design.

46

Page 47: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

50.02 94.07 9.48 100.00

Significant Developments During the Year

Tranche 1 (Loan 2770) is a loan of $74.80 million from Ordinary Capital Resources (OCR), which was signed on 9 July 2012 and declared effective on 22 October 2012. Tranche 1 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $50.02 million (94.1%) and $9.48 million (100.0%), respectively. Slow physical progress have been noted in the project states. However, MDONER and state governments were requested to closely monitor the progress until all subprojects are back on track. The following reflects the status of civil works for each state: Assam: 50.5%; Sikkim: 23%; and Meghalaya: 10%. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: There are 5 undertakings and 19 covenants for Tranche 1. All are complied with except for the submission of Audited Financial Statements (AFS) for FY2013-14 which are partly complied with. MDONER and PWD, Meghalaya need to submit its respective AFS. PWD, Sikkim needs to submit missing documents to complete the ADB review.

1 DED = Detailed Engineering Design.

47

Page 48: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche TitleNorth Eastern States Roads Investment Program (Project 2)

Project No. 37143-033

Country/Regional India Loan/Grant No.

3073

Project Officer Anil Motwani Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

02 Dec 2013 31 Mar 2020 N/A

Division SATC

Tranche Amount($ million)

125.20 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/37143-033/main

Tranche Summary

ADB approved the North Eastern States Roads Investment Program (Project 2), not exceeding the aggregate amount of $125.20 million on 2 December 2013. Impact: Improved mobility and accessibility in the project areas in NER Outcome: Improved efficiency of road transport in the projet areas in the states of Assam, Manipur, Mizoram and Tripura Outputs: Reconstructed and rehabilitated state roads Implementation Arrangements: The executing agency is Ministry of Development of North Eastern Region (MDONER) and the implementing agency is the State Public Works Department of Assam, Manipur, Mizoram and Tripura. The implementation period is estimated as 8 years including the pre-construction activities which started in September 2011. The completion date of the Project is estimated to be in September 2019. Implementation Status: As of 31 December 2015, all contracts have been awarded and construction works are ongoing. There have been delays in payment to the contractor due to fund flow issue between MDONER and state governments. The Project Management Consultant engaged by ADB assisted to further strengthen the capacity of the MDONER and help mainstream effective and effective project implementation in processing fund release. The consultant commenced its services on May 2015.

1 DED = Detailed Engineering Design.

48

Page 49: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

123.60 100.00 5.47 100.00

Significant Developments During the Year

Tranche 2 (Loan 3073) is a loan of $125.20 million from Ordinary Capital Resources (OCR), which was signed on 17 February 2014 and declared effective on 20 May 2014. Tranche 2 is rated as Potential Problem. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $123.60 million (100.0%) and $5.47 million (100.0%), respectively. Slow physical progress have been noted. However, MDONER and state governments are working continuously until all subprojects are back on track. The status of civil works in each state is: Assam: 0.0001%; Manipur: 17.5%; Mizoram: 6.6%; and Tripura: 1.3%. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: There are 5 undertakings and 21 covenants for Tranche 2. All have been complied or being complied with. The Audited Financial Statements for FY2014-2015 need to be submitted.

1 DED = Detailed Engineering Design.

49

Page 50: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

38254013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - North Karnataka Urban Sector Investment Program (Facility Concept)

Project No. 38254-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

06 Dec 2006 30 Jun 2016 05 Dec 2016

Division SAUW

MFF Amount ($ million)

270.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - North Karnataka Urban Sector Investment Program (Facility Concept) for an aggregate amount not exceeding $270.00 million from ADB’s OCR on 6 December 2006. Impact: Improvement of Urban Infrastructure and services resulting in overall improvement in quality of life in project ULBs; and related increase in economic opportunities and growth in north Karnataka and reduced imbalances between north Karnataka and the rest of the state Outcome: Improved basic urban services for at least the 4.3 million people living in the initially identified 25Investment Program ULBs Improved and sustainable infrastructure services within Investment Program ULBs that will in turn benefit the agriculture, industry and tourism sectorsPBDPS and/or PBMC modalities implemented and interest generated in other Indian states Outputs: Implemented investment program for sanitation Implemented investment program for water supply Implemented investment program for slum improvement in Investment Program ULB slums Implemented investment program for nonmunicipal infrastructure Implemented investment program for urban transport improvement Improved institutional capacity Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 4

Approved Tranche Amount to Date

279.30

Facility Change in Scope

Category Date Proposed Change

50

Page 51: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

51

Page 52: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche TitleMFF - North Karnataka Urban Sector Investment Program - Tranche 2

Project No. 38254-043

Country/Regional India Loan/Grant No.

2638

Project Officer Saugata Dasgupta Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

14 Jun 2010 30 Jun 2016 N/A

Division SAUW

Tranche Amount($ million)

123.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

0.00

Project Data Sheet http://www.adb.org/projects/38254-043/main

1 DED = Detailed Engineering Design.

52

Page 53: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the MFF - North Karnataka Urban Sector Investment Program - Tranche 2, not exceeding the aggregate amount of $123.00 million on 14 June 2010. Impact: Improved quality of life relative to the whole state. Outcome: Improved basic urban services for people living in program 22 ULBs. Outputs: Enhance capacity of urban infrastructure - Slum Improvement Enhance capacity of urban infrastructure - Institutional Development Enhance capacity of urban infrastructure - Non-Municipal Enhance capacity of urban infrastructure - Water Supply Enhance capacity of urban infrastructure - Sanitation (Sewerage) Implementation Arrangements: The executing agency is the Karnataka Urban Infrastructure Development and Finance Corporation (KUIDFC), and in coordination with the regional office based in Dharwad, constitute the Program Management Unit (PMU) for the investment program. Implementation Status: Water supply works are in advance stage of implementation and the progress of sewerage works are varied across the project towns. A total of 840 kms of water and 507 kms of sewerage networks have been laid and or rehabilitated. 8.05 kms of new drain built, water treatment capacity augmented by 48.7 MLD. Physical works are in progress for slum improvement works with 3,159 and 5,323 households served with improved water and sanitation facilities, respectively. Improvement of tourism infrastructure, district, information centers, and procurement of fire-fighting equipment for target ULBs have been completed.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

1 DED = Detailed Engineering Design.

53

Page 54: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

118.65 100.00 72.90 100.00

Significant Developments During the Year

Tranche 2 (Loan 2638) is a loan of $123.00 million from Ordinary Capital Resources (OCR) which was approved on 14 June 2010 and declared effective on 1 March 2011. Tranche 2 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $118.65 million (100.0%) and $72.90 million (100.0%), respectively. Eight contracts were awarded in 2015: 1 for community toilets; 5 for slum improvement works; and 2 for sewerage contracts. Technical and community education support were provided to project towns to enhance acceptance of volumetric water and sewerage tariffs among citizens. Progress of sewerage works are varied across the project towns. Physical progress is on schedule for water supply woks with most pipe laying works completed, and works on connection provision and installation of meters is ongoing. On slum improvement, NGOs were mobilized to target slum areas and have implemented community development programs including training and capacity development. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: Undertakings are being complied with. 3 of 21 covenants have been complied with and the remaining 18 are being complied with by the EA. Activities are ongoing to improve tariff collection in ULBs. Auditor's Report and Audited Project Financial Statements for fiscal year 2015 for Tranche 2 were submitted on time and reviewed by ADB.

1 DED = Detailed Engineering Design.

54

Page 55: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 3 UPDATE

Tranche TitleNorth Karnataka Urban Sector Investment Program - Tranche 3

Project No. 38254-053

Country/Regional India Loan/Grant No.

2882

Project Officer Saugata Dasgupta Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

22 Aug 2012 30 Jun 2016 N/A

Division SAUW

Tranche Amount($ million)

60.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

0.00

Project Data Sheet http://www.adb.org/projects/38254-053/main

Tranche Summary

ADB approved the North Karnataka Urban Sector Investment Program - Tranche 3, not exceeding the aggregate amount of $60.00 million on 22 August 2012. Impact: Improved quality of life in program ULBs and increased economic growth relative to the whole state. Outcome: Improved access to better urban services in 8 ULB. Outputs: Upgraded urban infrastructure. Strengthened municipal management and project implementation capacity. Implementation Arrangements: The executing agency is the Karnataka Urban Infrastructure Development and Finance Corp (KUIDFC) in coordination with the regional office based in Dharwad, shall constitute the Program Management Unit (PMU) for the investment program. Implementation Status: For the sanitation works component, two contracts were awarded in 2015. 93 kms of sewerage networks laid and rehabilitated, respectively. 86 kms water network has been laid and or rehabilitated. Two UIB building interiors contracts were awarded in 2015. Works in progress for three mapping contracts which were awarded for the survey component in 2014.

1 DED = Detailed Engineering Design.

55

Page 56: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

51.95 100.00 24.58 100.00

Significant Developments During the Year

Tranche 3 (Loan 2882) is a loan of $60.00 million from Ordinary Capital Resources (OCR), which was approved on 22 August 2012 and declared effective on 11 October 2013. Tranche 3 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 3 have reached $51.95 million (100.0%) and $24.58 million (100.0%), respectively. Four contracts were awarded in 2015: two for sanitation and two for UIB building interiors. Contracts are in different stages of implementation for all components. On service delivery, majority metering expected with assistance under Tranche 4 on completion. Water tariff collection efficiency is still not reached desired level. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: Undertakings are being complied with. 4 of the 20 covenants have been complied with and remaining 16 are being complied with by the EA. The Auditor's Report and Audited Project Financial Statements for fiscal year 2015 for Tranche 3 were submitted on time and reviewed by ADB.

1 DED = Detailed Engineering Design.

56

Page 57: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 4 UPDATE

Tranche TitleNorth Karnataka Urban Sector Investment Program - Project 4

Project No. 38254-063

Country/Regional India Loan/Grant No.

3088

Project Officer Saugata Dasgupta Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

09 Dec 2013 5 Dec 2016 N/A

Division SAUW

Tranche Amount($ million)

63.30 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/38254-063/main

Tranche Summary

ADB approved the North Karnataka Urban Sector Investment Program - Project 4, not exceeding the aggregate amount of $63.30 million on 9 December 2013. Impact: Improved quality of life in 14 ULBs in North Karnataka. Outcome: Improved urban service delivery in 14 ULBs in North Karnataka Outputs: Upgraded water supply network Expanded sewerage infrastructure Improved roads and lake development infrastructure Strengthened service delivery management capacity Enhanced project management and implementation capacity Implementation Arrangements: The executing agency is the Karnataka Urban Infrastructure Development and Finance Corp (KUIDFC) in coordination with the regional office based in Dharwad, shall constitute the Program Management Unit (PMU) for the investment program. Implementation Status: 15 civil works contracts, with a cumulative worth of $91.00 million (total amount) have been awarded under Project 4. Works have commenced and physical works are in progress. A total of 254 kms of water networks have been laid and or rehabilitated and 65 kms of new sewerage network were laid.

1 DED = Detailed Engineering Design.

57

Page 58: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

61.48 100.00 22.90 100.00

Significant Developments During the Year

Tranche 4 (Loan 3088) is a loan of $63.30 million from Ordinary Capital Resources (OCR), which was approved on 09 December 2013 and declared effective on 4 December 2014. Tranche 4 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 4 have reached $61.48 million (100.0%) and $22.90 million (100.0%), respectively. The seven contracts were awarded in 2015 for the implementation of 24x7 water supply schemes. Physical works are in progress. Service delivery management capacity building has commenced with one training program for 24x7 water supply contacts carried out in Fiscal Policy Institute during April 2015. Project management and implementation capacity building is ongoing. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: Undertakings are being complied with. There are 27 covenants for Tranche 4, of which 10 are complied with, 16 are being complied with by the EA and 1 is not yet due. The Auditor's Report and Audited Financial Statements for fiscal year 2015 for Tranche 4 were submitted on time and reviewed by ADB.

1 DED = Detailed Engineering Design.

58

Page 59: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

38255013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - Uttarakhand State-Road Investment Program (Facility Concept)

Project No. 38255-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

18 Dec 2006 31 Dec 2017 N/A

Division SATC

MFF Amount ($ million)

550.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - Uttarakhand State-Road Investment Program (Facility Concept) for an aggregate amount not exceeding $550.00 million from ADB’s OCR on 18 December 2006. Impact: Increased economic growth and reduced poverty in Uttarakhand Outcome: Improved efficiency and sustainability of road transport in Uttarakhand Outputs: 1. Paved, repaired, or rehabilitated state roads 2. Staff with improved skills in transparent planning (quality control, contract admin, etc) 3. Institutional reforms, etc. Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 3

Approved Tranche Amount to Date

340.00

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

59

Page 60: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 3 UPDATE

Tranche TitleUttarakhand State-Road Investment Program - Tranche 3

Project No. 38255-043

Country/Regional India Loan/Grant No.

3040

Project Officer Prabhasha Sahu Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

09 Oct 2013 31 Dec 2017 N/A

Division INRM

Tranche Amount($ million)

150.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/38255-043/main

Tranche Summary

ADB approved the Uttarakhand State-Road Investment Program - Tranche 3, not exceeding the aggregate amount of $150.00 million on 9 October 2013. Impact: Improved efficiency and sustainability of road transport in Uttarakhand Outcome: Improved efficiency of road transport in the project areas Outputs: 1. Selected priority roads are resurfaced, upgraded or rehabilitated 2. PWD staff skills and qualifications are improved 3. Road planning and programming uses objective data driven procedures and tools 4. Project management Implementation Arrangements: The Executing Agency is Public Works Department, Government of Uttarakhand (PWD, GoU). The EA will be assisted by 4 construction supervision consultants, 1 program management consultant and 1 project performance auditor. Implementation Status: The Project consists of 18 civil work contracts (14 NCB and 4 ICB); and 6 consulting services contracts. All contracts have been awarded and are at different stages of implementation.

1 DED = Detailed Engineering Design.

60

Page 61: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in Scope

Category Date Approved Proposed Change

Minor Change 13 Feb 2015 A minor change in scope was made for this trance in Feb 2015 to drop 4 roads (Package C1) out of 88 roads from the Project scope due to redesigning of roads in view of actual field conditions.

Tranche Performance

( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

135.34 94.90 40.04 100.00

Significant Developments During the Year

Tranche 3 (Loan 3040) is a loan of $150.00 million from Ordinary Capital Resources (OCR), which was approved on 09 October 2013 and declared effective on 28 January 2014. Tranche 3 is rated On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 3 have reached $135.35 million (94.9%) and $40.04 million (100.0%), respectively. All civil works contracts for about 1,000 km of roads are at various stages of execution. Scope Change: There was a minor scope change for this tranche in 2015. Undertaking and Covenants: There are 43 covenants and undertakings which are being complied with by the EA.

1 DED = Detailed Engineering Design.

61

Page 62: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

38272013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - Uttarakhand Urban Sector Development Investment Program

Project No. 38272-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

24 Jan 2008 25 Jan 2016 23 Jan 2018

Division SAUW

MFF Amount ($ million)

350.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - Uttarakhand Urban Sector Development Investment Program for an aggregate amount not exceeding $350.00 million from ADB’s OCR on 24 January 2008. Impact: Access of the urban population to water supply and sanitation facilities, improved with focus on weak capacity states. Outcome: People, especially vulnerable households, will have better quality and sustainable urban infrastructure and services in 31 urban towns. Outputs: Water supply infrastructure rehabilitated and constructed in selected towns out of 14 candidate towns. Sewerage infrastructure rehabilitated and constructed in selected towns out of 17 candidate towns. Solid waste management infrastructure rehabilitated and constructed in selected towns out of the 29 candidate towns. ULBs' roles in urban service delivery increases. Operational efficiency in water supply operations increases. Operators of water supply and sewerage systems follow sound financial management. PMU and PIU s subproject management capacity and transparency strengthened. Community infrastructure in selected slums out of 118 slums in Dehradun, Nainital, Haridwar, and Rudrapur upgraded. Urban traffic infrastructure improved in 14 small candidate towns. Significant Developments of the Facility: There was a minor change in scope for the facility in 2015.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 2

Approved Tranche Amount to Date

160.00

Facility Change in Scope

62

Page 63: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Category Date Proposed Change

Minor Change 08 Dec 2015 The availability of resource period was extended to 23 January 2018 on 8 December 2015.

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

63

Page 64: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleUttarakhand Urban Sector Development Investment Program - Project 1

Project No. 38272-023

Country/Regional India Loan/Grant No.

2410

Project Officer Saugata Dasgupta Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

01 Feb 2008 31 Dec 2012 23 Jan 2018

Division INRM

Tranche Amount($ million)

60.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/38272-023/main

1 DED = Detailed Engineering Design.

64

Page 65: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Uttarakhand Urban Sector Development Investment Program - Project 1, not exceeding the aggregate amount of $60.00 million on 1 February 2008. Impact: Improved quality of life for the urban residents in Uttarakhand's selected towns of strategic importance. Outcome: The expected outcome of the Investment Program is increased access to better quality and sustainable urban infrastructure and services for about 1.9 million people expected to be living in Dehradun, Nainital, and Haridwar by the end of project period (2016). Outputs: Implemented water supply subproject in Dehradun Implemented water supply subproject in Nainital Implemented water supply subproject in Haridwar Implemented sewerage subproject in Dehradun Strengthened ULBs Restructured WSS utilities for efficient and financially sustainable service delivery Increased local revenues and improved financial management Prepared PPP packages for selected subprojects Implementation Arrangements: Urban Development Department, Government of Uttarakhand (GoU)is the executing and implementing agency for the project. Project Management Unit (PMU) headed by Program Director, Project Implementation Units at Dehradun is established and functional. 2 Project Implementation Units (PIUs) at Dehradun and Nainital established and functional. Project Management Consultant and Two Design and Supervision Consultants are providing consultancy support to the PMU and PIUs. Implementation Status: Out of 11 civil works contracts and 1 supply contract originally envisaged under the project, 9 contracts have been completed, 3 are under different stages of implementation.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

1 DED = Detailed Engineering Design.

65

Page 66: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

59.47 99.12 44.71 88.28

Significant Developments During the Year

Tranche 1 (Loan 2410) is a loan of $60.00 million from Ordinary Capital Resources (OCR), which was approved on 01 February 2008 and declared effective on 17 December 2008. Tranche 1 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $59.47 million (99.1%) and $44.71 million (88.3%), respectively. About 70% physical progress have been achieved under the tranche. Eight works contracts have been physically completed. To date, there are 146 km of water pipeline laid, 22 water reservoirs operationalized, 120 pumps commissioned, and 102 km of sewers laid. The state also approved the accrual based double entry accounting manual. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: There are 28 loan covenants, 27 of which have been complied with and 1 covenant for PPP modality is being considered under Tranche 2 (Loan 2797-IND).

1 DED = Detailed Engineering Design.

66

Page 67: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche TitleUttarakhand Urban Sector Development Investment Program - Tranche 2

Project No. 38272-033

Country/Regional India Loan/Grant No.

2797

Project Officer Saugata Dasgupta Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

31 Oct 2011 31 Dec 2015 23 Jan 2018

Division INRM

Tranche Amount($ million)

100.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/38272-033/main

1 DED = Detailed Engineering Design.

67

Page 68: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Uttarakhand Urban Sector Development Investment Program - Tranche 2, not exceeding the aggregate amount of $100.00 million on 3 November 2011. Impact: People, especially vulnerable households, will have increased access to better quality and sustainable urban infrastructure and services in 31 urban towns. Outcome: UDD and UUDSA provide improved urban services in 5 towns. Outputs: 1. Water supply infrastructure rehabilitated and constructed in Dehradun, Nainital, Haldwani, Ramnagar and Roorkee. 2. Sewerage infrastructure rehabilitated and constructed in Roorkee and designed for Ramnagar. 3. Performance of water supply operations improved in Nainital. 4. PMU and PIU's subproject management capacity and transparency strengthened. Implementation Arrangements: The Urban Development Department (UDD), Government of Uttarakhand (GoU) is the executing agency and implementing agency for the project. Project Management Unit, headed by Program Director is established and functional at Dehradun. 5 Project Implementation Units at Dehradun, Nainital, Ramnagar, Roorkee and Haldwani established and functional. Project Management Consultant and Design and Supervision Consultant recruited under Tranche 1 is providing consultancy support for this Tranche also. Implementation Status: Out of 12 civil works contracts envisaged under the project, 10 works contracts have been awarded and are in different stages of implementation, while 2 contracts are being retendered due to high bid price. UDD is planning to bid the 3 supply contracts for the supply and installation of water meters and the water operator by March 2016.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

1 DED = Detailed Engineering Design.

68

Page 69: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

44.77 44.77 20.51 87.86

Significant Developments During the Year

Tranche 2 (Loan 2797) is a loan of $100.00 million from Ordinary Capital Resources (OCR), which was approved on 03 November 2011 and declared effective on 15 April 2013. Tranche 2 is rated as Potential Problem. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $44.77 million (44.8%) and $20.51 million (87.9%), respectively. About 25% physical progress has been achieved under the Tranche. 364 km of water pipeline has been laid and 17 water reservoirs were constructed. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: There are 20 loan covenants, of which, 18 covenants have been complied with and 2 are not yet due.

1 DED = Detailed Engineering Design.

69

Page 70: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

38411013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - Orissa Integrated Irrigated Agriculture & Water Management Investment Program (Facility Concept)

Project No. 38411-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

18 Sep 2008 30 Sep 2017 17 Sep 2018

Division SAER

MFF Amount ($ million)

188.20Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - Orissa Integrated Irrigated Agriculture & Water Management Investment Program (Facility Concept) for an aggregate amount not exceeding $188.20 million from ADB’s OCR on 18 September 2008. Impact: Enhanced economic growth and reduced poverty in the selected river basins in Orissa with direct benefit to 1.7 million people in the subproject area Institutionalization of effective mechanisms to put into operation PIM-based agriculture growth Outcome: Enhanced productivity, water-use efficiency, and sustainability of irrigated agriculture in the selectedexisting schemes in the river basins having 215,000 hectares (ha) designed command areaImproved institutional performance of irrigation service delivery (with PIM) and water resources management (with IWRM) Outputs: A. Productive and Sustainable Irrigated Agriculture Management Systems 1. Participatory planning and WUA strengthening (a) Participatory scheme planning with feasibility studies and SIP (b) WUA micro plans (c) Strengthened WUAs: viable WUAs set up to become effective community organization, ready to receive investment support and to enhance agriculture production and women s participation 2. Irrigation and associated infrastructure including CAD: good quality infrastructure designed and constructed, following appraised plan and WUA micro plans 3. Agriculture development and livelihood enhancement: stipulated services in SIPs and micro plans provided, and set targets are achieved 4. Sustainable O&M systems established: irrigation schemes operated and maintained on a sustainable basis B. Institutions Strengthened and Project Management Systems Operational 1. Policy, planning, and legal framework (a) State Water Policy revised and implemented, with regular review by WRB (b) State Water Plan updated with basin plans for the four northern river basins (c) WUA Act and Rule refined for more sustainable and inclusive PIM 2. DOWR institutional setup, structure, skill mix, and business processes strengthened (a) Institutional development vision and strategy refined (b) Permanent PIM directorate established (c) Quality control cell established (d) DOWR CDP refined (e) WALMI reforms with autonomy 3. Systems to support sustainable O&M (a) Fund allocation following FC recommendations (b) Water rates

70

Page 71: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

revised to meet the allocation needs (c) Collection improved with WUA involvement (d) Land records improved providing WUA-specific data for collection and demand (e) Scheme MIS for O&M performance monitoring and planning (f) DOWR establishes links between water rate collection and allocation (g) Pilot delegation of water tariff collection and retention by WUAs 4. Progress towards IWRM becoming operational (a) Appropriate IWRM functions and institutional arrangements defined (b) Institutions established to make IWRM operational (c) Participatory RBO established with DSS 5. Project management system established and made fully operational - DOWR offices - Line agencies - Local governments - WUAs - NGOs - Private providers 6. Training and Capacity Development: capacities of project institutions are strengthened through training (for project management, PIM, IWRM, and agriculture development) Significant Developments of the Facility: There was a minor scope change for the facility in 2015.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 2

Approved Tranche Amount to Date

136.50

Facility Change in Scope

Category Date Proposed Change

Minor Change 09 Feb 2015 Extension of the MFF availability period from 30 September 2017 to 17 September 2018 and a minor change of the MFF to restore coastal embankments within the investment program area.

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

71

Page 72: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleORISSA Integrated Irrigated Agriculture & Water Management Investment Program - Project 1

Project No. 38411-023

Country/Regional India Loan/Grant No.

2444, 8240

Project Officer Cynthia Malvicini Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

26 Sep 2008 30 Sep 2013 30 Sep 2015

Division SAER

Tranche Amount($ million)

16.50 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/38411-023/main

1 DED = Detailed Engineering Design.

72

Page 73: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the ORISSA Integrated Irrigated Agriculture & Water Management Investment Program - Project 1, not exceeding the aggregate amount of $16.50 million on 8 October 2008. Impact: 1. Enhanced economic growth and reduced poverty in the selected river basins with direct benefit to 450,000 people in the tranche-1 subproject area (70,000ha).2. Initial institutionalization of effective mechanisms for Participatory Irrigation Management (PIM) Outcome: 1. Enhanced productivity, water use efficiency, and sustainability of irrigated agriculture in the selected existing schemes in 70,000 ha2. improved institutional performance of irrigation service delivery with empowered WUAs Outputs: Component A: Productive and sustainable irrigated agriculture management systems - A-1. Participatory Planning and WUA Strengthening A-2. Irrigation and associated infrastructure A-3. Agriculture Development and Livelihood Enhancement following micro-plans provided, and targets achieved A-4. Sustainable O&M Systems Established Component B. Institutions Strengthened and Project Management Systems B-1. Policy, Planning and Legal Framework B-2. DOWR Institutional Setup, Structure, Skill Mix, and Business Processes Strengthened B-3. Systems to Support Sustainable O&M B-4. Operationalizing IWRM B-5. Project Management System B-6. Training/Capacity Development Implementation Arrangements: The Department of Water Resources (DOWR) of the State of Orissa is the executing agency. A project management unit (PMU) was established headed by a full time project director. The PMU is a multidisciplinary structure comprising staff from DOWR and staff deputed from other line departments or recruited from the market. It is supported by a multidisciplinary team of consultants for institutional strengthening and project management for capacity development, quality control, and project management. The PMU is responsible for the identification, formulation, implementation, and operation and maintenance of all subprojects including conformance with the State, national, and ADB social and environmental safeguards policies. Implementation Status: Earlier implementation delays, weak contractor performance, and scheduling of works during monsoon months affected the progress of physical works. Thus, the loan was extended for a second time from 30 March 2015 to 30 September 2015. A reallocation of loan proceeds was approved based on actual assessment and reconciliation of issued contracts. The ADB loan has reached physical completion, while the OFID loan will require extension to enable OFID to process final disbursements.

1 DED = Detailed Engineering Design.

73

Page 74: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in Scope

Category Date Approved Proposed Change

Minor Change 29 Apr 2015 An extension of the loan by 6 months from 31 March 2015 to 30 September 2015 and reallocation of loan proceeds.

Tranche Performance

( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

42.72 91.87 36.09 77.61

Significant Developments During the Year

Tranche 1 is a loan of $46.50 million, of which $16.50 is from Ordinary Capital Resources (Loan 2444) and $30.00 million is from OPEC Fund for International Development (Loan 8240), which was approved on 26 September 2008 and declared effective on 4 June 2009. Tranche 1 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $42.72 million (91.9%) and $36.09 million (77.6%), respectively. A review mission from 24 November to 8 December 2015 reported that all civil works have been completed except for two works packages in Taladanda (T2 and T5), which will be completed through state resources. Financial closing activities are ongoing. Scope Change: There was a minor scope change for this tranche in 2015. Undertaking and Covenants: There are 16 covenants for Project 1. DOWR has generally complied satisfactorily with all the covenants.

1 DED = Detailed Engineering Design.

74

Page 75: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche TitleOrissa Integrated Irrigated Agriculture and Water Management Investment Program - Project 2

Project No. 38411-043

Country/Regional India Loan/Grant No.

3265

Project Officer Cynthia Malvicini Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

30 Jun 2015 17 Sep 2018 N/A

Division SAER

Tranche Amount($ million)

120.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/38411-043/main

Tranche Summary

ADB approved the Orissa Integrated Irrigated Agriculture and Water Management Investment Program - Project 2, not exceeding the aggregate amount of $120.00 million on 30 June 2015. Impact: economic growth, including agricultural growth, in Odisha is sustainable, broad-based and more inclusive (12th Five-Year Plan: 2012-2017). Outcome: productivity of agriculture in selected river basins in Odisha increased. Outputs: Water resources and irrigation management of state and water user institutions strengthened Irrigation system and associated infrastructure modernized and managed. Implementation Arrangements: Not Applicable Implementation Status: Not Yet Effective

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

75

Page 76: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating

Financial

Contract Awards

Disbursements

Safeguards

Technical

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

0.00 0.00 0.00 0.00

Significant Developments During the Year

1 DED = Detailed Engineering Design.

76

Page 77: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

38412013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - Assam Integrated Flood and Riverbank Erosion Risk Management Investment Program (Facility Concept)

Project No. 38412-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

19 Oct 2010 30 Sep 2017 N/A

Division SAER

MFF Amount ($ million)

120.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - Assam Integrated Flood and Riverbank Erosion Risk Management Investment Program (Facility Concept) for an aggregate amount not exceeding $120.00 million from ADB’s OCR on 19 October 2010. Impact: Reduced economic vulnerability and social disruption caused by flood and riverbank erosion risks in Assam Outcome: FRERM systems in Assam provide enhanced resilience to flood and riverbank erosion risks in selected flood-prone areas along the Brahmaputra River, benefiting about 1 million people Outputs: 3. Institutional and financial capacities of FRERM institutions in Assam developed and strengthened 1. Integrated FRERM planning, institutional and knowledge bases developed and effectively implemented in Assam 2. Comprehensive FRERM nonstructural and structural measures developed, implemented, and sustainably maintained in selected subproject areas, protecting flood-prone areas along 90 km critical reach of the Brahmaputra River having 97,500 ha of urban and productive agriculture land Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

1

Approved Tranches To Date 1

Approved Tranche Amount to Date

56.90

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

77

Page 78: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

78

Page 79: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleMFF - Assam Integrated Flood and Riverbank Erosion Risk Management Investment Program - Tranche 1

Project No. 38412-023

Country/Regional India Loan/Grant No.

2684

Project Officer Natsuko Totsuka Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

25 Oct 2010 30 Sep 2014 31 Jul 2016

Division SAER

Tranche Amount($ million)

56.90 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/38412-023/main

1 DED = Detailed Engineering Design.

79

Page 80: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the MFF - Assam Integrated Flood and Riverbank Erosion Risk Management Investment Program - Tranche 1, not exceeding the aggregate amount of $56.90 million on 25 October 2010. Impact: FRERM systems provide enhanced resilience to flood and riverbank erosion risks in 3 subproject areas benefiting about 1 million people along the Brahmaputra River Outcome: State Government of Assam provides reliable, effective and sustainable FRERM systems in selected subproject areas in Assam along the Brahmaputra River Outputs: A. FRERM planning, institutional and knowledge basis established A.1. FRERM Policy and Plan Framework fully established A.2. Respective roles and key results areas of FRERM institutions clarified and their respective capacities for participatory DRM developed A.3. Improved data and knowledge base for integrated FRERM A.4. Knowledge sharing and regional networking mobilized and effective working relationships established for undertaking regular investigation and planning, and knowledge management activities B. Comprehensive FRERM program implemented with DMC participation B.1. Empowered communities play a role in FRERM Programs B.2. Nonstructural measures are provided to DMCs up to GP; and CBFRM provided to highly vulnerable villages B.3. Cost effective FRERM structural measures provided in the 3 subproject areas B.4. Sustainable FRERM infrastructure monitoring, maintenance and adaptation institutionalized in the 3 subproject areas C. FREMAA Program Management developed C.1. Appropriate project management system established incl. results monitoring with indicators agreed and baseline data determined C.2. Capacities of FRERM institutions strengthened 3. Efficient program management Implementation Arrangements: The Assam state government, acting through the Flood and River Erosion Management Agency of Assam (FREMAA), will be the executing agency. FREMAA manages its technical, disaster risk management and safeguards, and finance and account divisions. At each subproject level, subproject implementation offices are established augmenting the existing Water Resources Department field offices with multidisciplinary staff. Implementation Status: All packages for major civil works, associated construction materials, and consulting services had been awarded as of end-2014. Civil works for construction of riverbank protections and rehabilitation/ construction of flood embankments continued in 2015. Activities for community-based flood management and institutional capacity strengthening were also continued in 2015. All project activities are reaching the final stage, and are expected to be completed by July 2016.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

80

Page 81: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

42.95 93.16 26.00 75.11

Significant Developments During the Year

Tranche 1 (Loan 2684) is a loan of $56.90 million from Ordinary Capital Resources (OCR), which was approved on 25 October 2010 and was declared effective on 4 August 2011. In September 2014, $7.00 million of the loan proceeds was canceled, with the latest tranche amount at $49.90 million. Tranche 1 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $42.95 million (93.2%) and $26.00 million (75.1%), respectively. Major civil works that had been awarded previous years made progress in 2015. Construction of riverbank protections at three sites, construction of flood embankments at one site, and rehabilitation of flood embankments at one site are in progress. The construction and rehabilitation of flood embankments got delayed due to prolonged land acquisition procedures, but the issues have been sorted out in 2015. Activities for community-based flood management were completed. All project activities are expected to be completed before July 2016. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: Of the 24 project-specific covenants, 18 are being complied with, three have been complied with, and three are not yet due.

1 DED = Detailed Engineering Design.

81

Page 82: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

39630013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - National Power Grid Development Investment Program (Facility Concept)

Project No. 39630-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

28 Mar 2008 31 Mar 2015 31 Dec 2015

Division SAEN

MFF Amount ($ million)

600.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - National Power Grid Development Investment Program (Facility Concept) for an aggregate amount not exceeding $600.00 million from ADB’s OCR on 28 March 2008. Impact: Increased transmission capacity and affordable and reliable power supply for sustained economic growth Outcome: National Power Grid strengthening and augmentation/expansion with transmission bottlenecks removed and losses reduced Outputs: 800kV HVDC North eastern Northern / Western Inter connector Upgrading transmission corridor from Uttaranchal Significant Developments of the Facility: Loan 2415-IND: National Power Grid Development Investment Program - Tranche 1 - has financially closed on 11 May 2015. Loan 2510-IND: National Power Grid Development Investment Program - Tranche 2 is due for loan closing on 31 December 2015. Loan 2823-IND: National Power Grid Development Investment Program - Tranche 3 has financially closed on 19 May 2015.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 3

Approved Tranche Amount to Date

676.00

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

82

Page 83: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

83

Page 84: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche TitleMFF - National Power Grid Development Investment Program - Tranche 2

Project No. 39630-033

Country/Regional India Loan/Grant No.

2510

Project Officer Vallabha Karbar Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

03 Mar 2009 30 Jun 2014 31 Dec 2015

Division INRM

Tranche Amount($ million)

200.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/39630-033/main

Tranche Summary

ADB approved the MFF - National Power Grid Development Investment Program - Tranche 2, not exceeding the aggregate amount of $200.00 million on 3 March 2009. Impact: To promote sustained social and economic prosperity and growth in India by providing adequate and reliable power supply. Outcome: Enhanced transmission network reliability and efficiency through expansion and augmentation of the national transmission grid. Outputs: +/-800kV HVDC Northeastern-Northern/Western Interconnector Implementation Arrangements: The executing agency is the Power Grid Corporation of India Ltd. (POWERGRID). It has set up a program management unit (PMU) that will be responsible for processing and implementing the investment program, responsible for construction and commissioning of subprojects, and facilitate submission of the implementation progress reports. Implementation Status: All 11 contract packages have been awarded and are under various stages of implementation.

1 DED = Detailed Engineering Design.

84

Page 85: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

123.84 94.29 122.44 98.74

Significant Developments During the Year

Tranche 2 (Loan 2510) is a loan of $124.00 million from Ordinary Capital Resources (OCR), which was approved on 03 March 2009 and declared effective on 18 May 2009. Tranche 2 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $123.84 million (94.3%) and $122.44 million (98.7%), respectively. All contract packages have been awarded. Project has completed 100% foundations (4372 nos), 4351 Tower erections against 4372, and Stringing of 1686.3 kms out 1752 kms. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: All the covenants were complied or are being complied with.

1 DED = Detailed Engineering Design.

85

Page 86: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

40031013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - Rajasthan Urban Sector Development Investment Program

Project No. 40031-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

31 Oct 2007 31 Dec 2014 31 Dec 2016

Division SAUW

MFF Amount ($ million)

273.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - Rajasthan Urban Sector Development Investment Program, not exceeding the aggregate amount of $273.00 million on 31 October 2007. Impact and Outcome: The impact of the MFF is to increase economic growth, reduce poverty, and sustain improvements in the urban environment and the quality of life in the 15 initially identified ULBs in Rajasthan. The outcome is to improve access to sustainable urban infrastructure and services for the 1.6 million people in the Investment Program ULBs, and to strengthen the capacity of these ULBs to manage urban services in a sustainable manner by the end of the Program (2014). Outputs: The expected outputs are grouped into two parts. Part A will improve (i) water supply systems in ULBs by rehabilitating, strengthening, and expanding networks and constructing new supply systems; (ii) sewerage and drainage by constructing new systems and extending existing ones; (iii) solid waste collection, processing and treatment, and disposal by developing sanitary landfill sites; (iv) road rehabilitation and road safety; (v) social infrastructure, such as slum improvements and other municipal facilities that may be prioritized as the master plans are updated and finalized; and (vi) infrastructure support for cultural heritage, such as access roads and sanitation facilities. The outputs in Part B will involve (i) capacity building and institutional development to make the state system more responsive, empower local government, improve the financial performance of the local bodies and service providers, and improve urban services overall for citizens; and (ii) management and implementation support for the implementation of the Investment Program. Significant Developments of the Facility: ADB received a request, duly endorsed by the Borrower, for an extension of the loan closing dates of Tranche 2 and Tranche 3 until 31 December 2016. Tranche 1 closed on 31 December 2014 and its loan account was closed on 22 May 2015. A partial loan cancellation of $7.09 million under Tranche 2 and $3.0 million under Tranche 3 were undertaken in December 2015. Beside these, there are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 3

86

Page 87: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Approved Tranche Amount to Date

273.00

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

87

Page 88: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche TitleRajasthan Urban Sector Development Investment Program - Tranche 2

Project No. 40031-033

Country/Regional India Loan/Grant No.

2506

Project Officer Pushkar Srivastava Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

19 Jan 2009 30 Jun 2014 31 Dec 2016

Division INRM

Tranche Amount($ million)

150.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/40031-033/main

1 DED = Detailed Engineering Design.

88

Page 89: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Rajasthan Urban Sector Development Investment Program - Tranche 2, not exceeding the aggregate amount of $150.00 million on 19 January 2009. Impact: Increased economic growth and sustained improvement in the urban environment and quality of life in the identified urban local bodies (ULBs) in Rajasthan (the Project ULBs) Outcome: Increased access to sustainable urban infrastructure and services for approximately 1.5 million people in the identified 12 Project ULBs by the end of the Project Outputs: Water supply subprojects successfully implemented Sewerage and sanitation subprojects successfully implemented Urban Transport subprojects successfully implemented Urban drainage subprojects successfully implemented Capacity development subproject successfully implemented in all Project ULBs Implementation Arrangements: The executing agency is the state government of Rajasthan acting through its Local Self Government Department (LSGD). The LSGD manages the program in the urban local bodies (ULBs) through the investment program management unit (IPMU), which (i) monitors the implementation of the investment program, (ii) reviews subprojects submitted by ULBs and periodic financing requests, (iii) reports on the progress of the program. The IPMU is assisted by investment program management consultants (IPMC) in managing the Investment Program and ensuring the technical quality of design and construction. Implementation Status: There are 48 civil works, one equipment and seven consultancy contract packages that have been awarded in Tranche 2. Of the 48 civil work contracts, 21 contracts are physically completed, 20 contracts are under implementation and 7 contracts have been terminated. The equipment contract has been closed. The project has started delivering the project outcomes and outputs. The major project outputs achieved to date are: (i) 1,064 km of water supply lines laid; (ii) 301 km of sewer lines laid; and (iii) 4 railway over bridges constructed. Though the performance rating for disbursement is shown to be a potential problem, it will get resolved once the loan extension request is processed with the disbursements spread out over the extension period.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

89

Page 90: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

124.08 99.90 103.15 83.04

Significant Developments During the Year

Tranche 2 (Loan 2506) is a loan of $150.00 million from Ordinary Capital Resources (OCR), which was approved on 19 January 2009 and declared effective on 20 April 2009. ADB received a request in December 2015, duly endorsed by the Borrower, for an extension of the loan closing date of Tranche 2 until 31 December 2016. Another partial loan cancellation of $7.09 million under Tranche 2 was undertaken in December 2015, reducing the net loan amount to $124.21 million. Tranche 2 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $124.08 million (99.9%) and $103.15 million (83.0%), respectively. About 90% physical progress has been achieved under the tranche. There are no major implementation issues. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: Out of 44 covenants, 36 covenants are complied, 2 covenants are not yet due, and 6 covenants are under process.

1 DED = Detailed Engineering Design.

90

Page 91: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 3 UPDATE

Tranche TitleRajasthan Urban Sector Development Investment Program - Tranche 3

Project No. 40031-053

Country/Regional India Loan/Grant No.

2725

Project Officer Pushkar Srivastava Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

13 Dec 2010 30 Jun 2015 31 Dec 2016

Division INRM

Tranche Amount($ million)

63.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/40031-053/main

1 DED = Detailed Engineering Design.

91

Page 92: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Rajasthan Urban Sector Development Investment Program - Tranche 3, not exceeding the aggregate amount of $63.00 million on 13 December 2010. Impact: Increased access to sustainable urban infrastructure and services for 2.16 million people in the identified 15 ULBs. Outcome: Improved urban services in the 15 ULBs. Outputs: Improved and increased metered water supply service area in Baran and Chittorgarh. Increased sewerage treatment coverage in the 5 ULBs. Reduced flooding through improved urban drainage in Sawai Madhopur. Traffic flow improved as a result of construction of two minor bridges in Sawai Madhopur and one road work in Dholpur. Increased solid waste collection and disposal in 10 ULBs. Fire Fighting strengthened in at least 5 ULBs. Heritage sites in 7 ULBs conserved. Implementing Agencies and IAs effectively manage project financed assets. Implementation Arrangements: The executing agency is the state government of Rajasthan acting through its Local Self Government Department (LSGD). The LSGD manages the program in the urban local bodies (ULBs) through an investment program management unit (IPMU), which (i) monitors the implementation of the investment program, (ii) reviews subprojects submitted by ULBs and periodic financing requests, and (iii) reports on the progress of the program. The IPMU is assisted by investment program management consultants (IPMC) in managing the Investment Program and ensuring the technical quality of design and construction. Implementation Status: Out of 45 contracts which have been awarded to date, 27 contracts have been completed, one contract terminated and the remaining 17 contracts are under progress. Though the performance rating for disbursement is shown to be an actual problem, it will get resolved once the loan extension request is processed with the disbursements spread out over the extension period. The overall rating would also be on track once this change is done.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

92

Page 93: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

59.25 98.76 42.13 70.21

Significant Developments During the Year

Tranche 3 (Loan 2725) is a loan of $63.00 million from Ordinary Capital Resources (OCR), which was approved on 13 December 2010 and declared effective on 16 June 2011. ADB received a request, duly endorsed by the Borrower in December 2015, for an extension of the loan closing date of the tranche until 31 December 2016. A partial loan cancellation of $3.0 million was undertaken in December 2015, reducing the net loan amount to $60.0 million. Tranche 3 is rated as Actual Problem. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 3 have reached $59.25 million (98.8%) and $42.13 million (70.2%), respectively. About 75% physical progress has been achieved under the tranche. There are no major implementation issues. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: Out of 44 covenants, 38 covenants were complied, 1 covenant is not yet due, and 5 covenants are under process.

1 DED = Detailed Engineering Design.

93

Page 94: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

40156013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - Sustainable Coastal Protection and Management Investment Program (Facility)

Project No. 40156-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

31 Dec 2010 31 Dec 2019 31 Dec 2019

Division SAER

MFF Amount ($ million)

250.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - Sustainable Coastal Protection and Management Investment Program (Facility) for an aggregate amount not exceeding $250.00 million from ADB’s OCR on 29 September 2010. Impact: Improved income and reduced poverty of the coastal communities in the subproject areas of three coastal states Outcome: Protected and managed shorelines in the three states meeting the needs of stakeholders and the environment. Outputs: Sustainable plans and management for shorelines developed (i) Participatory shoreline management plans to meet the long term needs for for shoreline management for 3 state coastlines prepared and endorsed; (ii) Coastal management information system to support planning and management established; (iii) Project management system established and operational, and subprojects for future tranches planned and designed. Coastal Erosion and Instability Reduced: (i) Costal erosion and instability reduced; (ii) Community and private sector engaged in coastal erosion and instability reduction Enhanced capacity for integrated shoreline planning and development - (i) Enhanced capacity for districts and states to plan, design, and implement shoreline protection and management projects; (ii) Enhanced capacity for state/district agencies, local experts/agencies, local bodies and stakholders to provide specialist support for planning, modelling, design, checking and review for coastal protection and management; (iii) Beaches are managed and maintained by the communities and stakeholders; (iv) SEAs formally mandated to coordinate all costal protection and management programs Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework. Tranche 2 for Karnataka is under preparation. This tranche will support nine subprojects consisting of six coastal protection subprojects designed to address the issues of medium to severe coastal erosion and three community subprojects for areas of low erosion resulting in the protection of approximately 55 km of coastline.

Estimated Total No. of 1

94

Page 95: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranches to be Processed

Approved Tranches To Date 1

Approved Tranche Amount to Date

51.56

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

95

Page 96: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleSustainable Coastal Protection and Management Investment Program - Tranche 1

Project No. 40156-023

Country/Regional India Loan/Grant No.

2679

Project Officer Rajesh Yadav Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

06 Oct 2010 31 Dec 2014 30 Jun 2017

Division INRM

Tranche Amount($ million)

51.56 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/40156-023/main

1 DED = Detailed Engineering Design.

96

Page 97: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Sustainable Coastal Protection and Management Investment Program - Tranche 1, not exceeding the aggregate amount of $51.56 million on 6 October 2010. Impact: Improved income and reduced poverty of the coastal communities in the subproject areas of two coastal states Outcome: Protected and managed shorelines in the two states meeting the needs of stakeholders and the environment Outputs: 1. Sustainable plans and management for shorelines developed - (i) Participatory shoreline management plans to meet the long term needs for shoreline management for 2 state coastlines prepared and endorsed; (ii) coastal management information system, to support planning and management established; (iii) project management system established and operational, and supbrojects for future tranches planned and designed. 2. Coastal Erosion and Instability Reduced - (i) coastal erosion and instability reduced; (ii) community and private sector engaged in coastal erosion and instability reduction 3. Enhanced capacity for integrated shoreline planning and development - (i) Enchanced capacity for districts and states to plan, design, and implement shoreline protection and management projects; (ii) Enhanced capacity for state/district agencies, local experts/agencies, local bodies and stakeholders to provide specialist support for planning, modelling, design, checking and review for coastal protection and management; (iii) beaches are managed and maintained by the communities and stakeholders; (iv) SEAs formally mandated to coordinate all coastal protection and management programs Implementation Arrangements: The SEAs for Tranche 1 are the Karnataka Public Works, Ports and Inland Water Transport Department for Karnataka and the Maharashtra Maritime Board for Maharashtra. Each government has established a program steering committee to provide broad project oversight; policy guidance; facilitate interdepartmental coordination; and help institutionalize effective mechanisms to plan, improve, and manage coastal management initiatives. A program management unit, headed by a project director, has been established in each state. Implementation Status: In both Maharashtra and Karnataka, civil works progress is under various stages of execution. In Maharashtra, shoreline management plans (SMPs) have been prepared and shoreline management organizations (SMOs) for Mirya bay have been established. In Karnataka, one SMO has been registered at Bengre and another one at Ullal is in the final stage of registration.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

97

Page 98: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

34.29 66.52 16.46 81.48

Significant Developments During the Year

Tranche 1 (Loan 2679) is a loan of $51.56 million from Ordinary Capital Resources (OCR), which was approved on 06 October 2010 and was declared effective on 28 November 2011. Tranche 1 is rated as Potential Problem. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $34.29 million (66.5%) and $16.46 million (81.5%), respectively. In both the states, coastal infrastructure management units were formally set-up and the migration of coastal management information systems on specialized software applications is in progress. In Karnataka, SMPs for 3 coastal districts have been finalized. In Maharashtra, draft SMP procedures (updated) was prepared, and a pilot plan for one district (Sindhudurg) out of 6 coastal districts was prepared. A management tour to the United Kingdom and the Netherlands was conducted for Karnataka in June 2015 to learn from the coastal projects implemented in these countries. Civil works in both states have achieved significant progress in 2015. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: There are 20 undertakings in project agreement and 30 covenants for Tranche 1. For undertakings, 19 are being complied with and one is not yet due. For covenants, 14 were complied with, 13 partially complied with, and 3 not yet due.

1 DED = Detailed Engineering Design.

98

Page 99: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

40423013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title Rural Connectivity Investment Program (Facility Concept)

Project No. 40423-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

12 Jul 2012 30 Jun 2018 N/A

Division SATC

MFF Amount ($ million)

800.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the Rural Connectivity Investment Program (Facility Concept) for an aggregate amount not exceeding $800.00 million from ADB’s OCR on 12 July 2012. Impact: Reduction in poverty and deprivation, and inclusive socioeconomic growth of the communities served by the investment program roads Outcome: Connectivity of selected rural communities in five investment program states of Assam, Chhattisgarh, Madhya Pradesh, Odisha, and West Bengal to markets, district headquarters, and other centers of economic activity is improved and sustainable. Outputs: 1. Selected priority rural roads in five investment program states are constructed to all-weather standard 2. Quality of design of the investment program roads is improved. 3. Maintenance of the investment program roads is improved and sustained. 4. Road safety measures are incorporated into the life cycle of the investment program roads. 5. Qualification and skills of PMGSY engineers, technicians, site supervisors, PRI staff concerned, design consultants, and contractors in the investment program states are improved and maintained. 6. Facility is managed effectively. Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 3

Approved Tranche Amount to Date

800.00

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

99

Page 100: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

100

Page 101: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche Title Rural Connectivity Investment Program - Tranche 1 Project No. 40423-023

Country/Regional India Loan/Grant No.

2881

Project Officer Ashok Srivastava Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

22 Aug 2012 31 Dec 2015 31 Dec 2017

Division INRM

Tranche Amount($ million)

252.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/40423-023/main

1 DED = Detailed Engineering Design.

101

Page 102: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Rural Connectivity Investment Program - Tranche 1, not exceeding the aggregate amount of $252.00 million on 22 August 2012. Impact: Connectivity of selected rural communities in five RCIP states to markets, district headquarters, and other centers of economic activity is improved and sustainable Outcome: Connectivity of selected communities in five RCIP states prioritized by PMGSY for 2012 sanction is improved and sustainable Outputs: 1. Selected priority rural roads prioritized by PMGSY for 2012 sanction are constructed to all-weather standard 2. Quality of design of RCIP roads is improved 3. Maintenance of RCIP roads is improved and sustainable 4. Road safety measures are incorporated into the lifecycle of RCIP roads 5. Qualification and skills of PMGSY engineers, technicians, site supervisors, concerned staff of PRI, design consultants and contractors in RCIP states is improved and maintained 6. Effective project management provided Implementation Arrangements: The national executing agency is the Ministry of Rural Development (MORD). The state-level executing agencies are Assam Public Works Roads Department, Chhattisgarh State Department of Panchayat and Rural Development, Madhya Pradesh State Department of Panchayat and Rural Development, Odisha State Department of Rural Development, and West Bengal State Department of Panchayat and Rural Development. Implementation Status: About 3,037 km (88%) length of roads constructed: Assam-316 km; Chhattisgarh-851 km; Madhya Pradesh-1187 km; Odisha- 520 km; and West Bengal- 163 km.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

1 DED = Detailed Engineering Design.

102

Page 103: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

249.54 99.03 173.52 100.00

Significant Developments During the Year

Tranche 1 (Loan 2881) is a loan of $252.00 million from Ordinary Capital Resources (OCR), which was approved on 22 August 2012 and declared effective on 05 June 2013. Tranche 1 is rated On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $249.54 million (99.0%) and $173.52 million (100.0%), respectively. 531 out of 532 contracts have been awarded, with 1 contract dropped: Assam - all 143 contracts awarded; Chhattisgarh - all 83 contracts awarded; Madhya Pradesh all 112 contracts awarded; Odisha - 169 contracts awarded ; and West Bengal - 25 contracts awarded. Bid documents for RRNMUs and RCTRCs have been awarded and work is ongoing. Scope Change: There were no scope changes for this tranche in 2015 Undertaking and Covenants: There are 32 undertakings and covenants, all of which are being complied.

1 DED = Detailed Engineering Design.

103

Page 104: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche Title Rural Connectivity Investment Program - Tranche 2 Project No. 40423-033

Country/Regional India Loan/Grant No.

3065

Project Officer Ashok Srivastava Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

25 Nov 2013 31 Dec 2017 N/A

Division INRM

Tranche Amount($ million)

275.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/40423-033/main

Tranche Summary

ADB approved the Rural Connectivity Investment Program - Tranche 2, not exceeding the aggregate amount of $275.00 million on 25 November 2013. Impact: Improved connectivity of selected rural communities in five RCIP states to markets, district headquarters, and other centers of socio-economic activity. Outcome: Improved accessibility of selected communities in five RCIP states Outputs: 1. Selected rural roads are constructed to all-weather standard 2. Quality of design of RCIP roads is improved 3. Maintenance of RCIP roads is improved and sustainable 4. Road safety measures are incorporated into the lifecycle of RCIP roads 5. Effective project management provided Implementation Arrangements: The national executing agency is the Ministry of Rural Development (MORD). The state-level executing agencies are Assam Public Works Roads Department, Chhattisgarh State Department of Panchayat and Rural Development, Madhya Pradesh State Department of Panchayat and Rural Development, Odisha State Department of Rural Development, and West Bengal State Department of Panchayat and Rural Development. Implementation Status: About 1,474 km of roads constructed: Assam- 122 km; Chhattisgarh- 309 km; Madhya Pradesh- 480 km; Odisha- 210 km; and West Bengal- 353 km

1 DED = Detailed Engineering Design.

104

Page 105: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

214.46 100.00 121.61 100.00

Significant Developments During the Year

Tranche 2 (Loan 3065) is a loan of $275.00 million from Ordinary Capital Resources (OCR), which was approved on 25 November 2013 and declared effective on 31 March 2014. Tranche 2 is rated On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $214.46 million (100.0%) and $121.61 million (100.0%), respectively. 702 out of 733 contracts have been awarded, with 31 contracts under bidding: Assam - all 192 contracts awarded and 4 under bidding; Chhattisgarh - all 43 contracts awarded; Madhya Pradesh - all 82 contracts awarded; Odisha - 287 contracts awarded and 23 under bidding; and West Bengal - 120 contracts awarded and 4 contracts under bidding. Bid documents for the Rural Road Network Management Unit and the Rural Connectivity Training and Research Centre have been approved by ADB and will be bided out shortly. Scope Change: There were no scope changes for this trance in 2015. Undertaking and Covenants: There are 6 covenants for this tranche, of which 4 are complied and 2 are under process

1 DED = Detailed Engineering Design.

105

Page 106: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 3 UPDATE

Tranche Title Rural Connectivity Investment Program - Tranche 3 Project No. 40423-053

Country/Regional India Loan/Grant No.

3306

Project Officer Ashok Srivastava Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

22 Oct 2015 30 Jun 2018 N/A

Division SATC

Tranche Amount($ million)

273.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/40423-053/main

Tranche Summary

ADB approved the Rural Connectivity Investment Program - Tranche 3, not exceeding the aggregate amount of $273.00 million on 22 October 2015. Impact: improved access to markets, district headquarters, and other centers of socio-economic activities aligned with India's Five Year Plan, 2012-2017. Outcome: improved and sustained connectivity of selected rural communities in the investment program states. Outputs: Selected rural roads are constructed to all-weather standard quality of design of RCIP roads is improved maintenance of RCIP roads is improved and sustained road safety measures are incorporated into the design institutional capacity strengthened effective project management provided. Implementation Arrangements: The national executing agency is the Ministry of Rural Development (MORD). The state-level executing agencies are Assam Public Works Roads Department, Chhattisgarh State Department of Panchayat and Rural Development, Madhya Pradesh State Department of Panchayat and Rural Development, Odisha State Department of Rural Development, and West Bengal State Department of Panchayat and Rural Development. Implementation Status: Project was declared effective on 29 December 2015.

1 DED = Detailed Engineering Design.

106

Page 107: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

0.00 0.00 0.00 0.00

Significant Developments During the Year

Tranche 3 (Loan 3306) is a loan of $273.00 million from Ordinary Capital Resources (OCR), which was approved on 22 October 2015 and declared effective on 29 December 2015. Tranche 3 is rated as On Track. Progress: Project declared effective on 29 December 2015. Scope Change: Not applicable Undertaking and Covenants: Not applicable

1 DED = Detailed Engineering Design.

107

Page 108: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

40648013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - Infrastructure Development Investment Program for Tourism (Facility Concept)

Project No. 40648-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

28 Sep 2010 30 Jun 2020 N/A

Division SAUW

MFF Amount ($ million)

250.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - Infrastructure Development Investment Program for Tourism (Facility Concept) for an aggregate amount not exceeding $250.00 million from ADB’s OCR on 28 September 2010. Impact: Enhanced contribution of the tourism sector to sustainable and inclusive economic growth Outcome: Increased volume of domestic and international tourists to destinations within each participating state Outputs: Enhanced quality of natural and cultural attractions Strengthened capacity of sector agencies and local communities for planning, development, management, and marketing of tourist destinations and attractions Greater participation by local communities in tourism-related economic activities Improved basic urban infrastructure and services at tourist destinations and attractions Improved connectivity Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 3

Approved Tranche Amount to Date

210.77

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

108

Page 109: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

109

Page 110: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleInfrastructure Development Investment Program for Tourism - Tranche 1

Project No. 40648-023

Country/Regional India Loan/Grant No.

2676

Project Officer Vivek Vishal Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

04 Oct 2010 30 Jun 2017 N/A

Division SAUW

Tranche Amount($ million)

43.42 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/40648-023/main

1 DED = Detailed Engineering Design.

110

Page 111: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Infrastructure Development Investment Program for Tourism - Tranche 1, not exceeding the aggregate amount of $43.42 million on 4 October 2010. Impact: Enhanced contribution of the tourism sector to sustainable and inclusive economic growth Outcome: Increased volume of domestic and international tourists to destinations within each participating state Outputs: Enhanced quality of natural and cultural attractions Greater participation by local communities in tourism-related economic activities Improved basic urban infrastructure and services at tourist destinations and attractions Improved connectivity Strengthened capacity of concerned sector agencies and local communities for planning, development, management and marketing of tourist destinations and attractions Implementation Arrangements: Punjab: As proposed during the project processing stage, the implementation arrangement, comprising the Department of Tourism (DOT), Government of Punjab (GOP) as the executing agency (EA), a state-level empowered committee (SLEC) chaired by states' Chief Secretary, with Secretary of the DOT as member secretary and secretaries from relevant line departments; the Punjab Heritage and Tourism Promotion Board (PHTPB) as the Implementation Unit (IA) of the Investment Program housing the Project Management Unit (PMU) headed by the Project Director; Project Implementation Units (PIUs) in Amritsar and Ropar; the project implementation cell with the Forest Department; Project Management Consultant (PMC) and Design and Supervision Consultant (DSC) is in place and is functional. Himachal Pradesh: The Department of Tourism and Civil Aviation (DOTCA), Government of Himachal Pradesh is the executing agency. The Himachal Pradesh Tourism Development Board (HPTDB) is the implementing agency with a fully staffed Project Management Unit (PMU). Three PIUs (Kangra, Shimla and Kullu) are established and fully staffed. A State-Level Empowered Committee (SLEC) was established to take all decisions related to the investment Program on behalf of the State. A team of consultants including the Project Management Consultants (PMC), Design Supervision Consultants (DSC), and NGOs for community-based tourism development are supporting the PMU and PIUs in project implementation. Implementation Status: There are 33 contract packages (24 civil works and 9 goods) in Himachal Pradesh. Similarly in Punjab, there are 24 contract packages (20 civil works and 4 goods). All contracts have been awarded and are in various stages of implementation, except for one works contract package in Punjab which is being procured.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

111

Page 112: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

41.60 100.00 20.03 100.00

Significant Developments During the Year

Tranche 1 (Loan 2676) is a loan of $43.42 million from Ordinary Capital Resources (OCR), which was approved on 04 October 2010 and declared effective on 26 October 2011. Tranche 1 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $41.61 million (100.0%) and $20.03 million (100.0%), respectively. About 56% physical progress has been achieved and the implementation progress under the tranche is satisfactory. Himachal Pradesh has awarded all 33 contracts and has achieved about 40% of physical progress. Punjab has awarded 23 contracts out of 24, and has achieved a physical progress of about 65%. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: There are 11 covenants for Tranche 1, of which 2 are complied with and 9 are under process.

1 DED = Detailed Engineering Design.

112

Page 113: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche TitleInfrastructure Development Investment Program for Tourism - Tranche 2

Project No. 40648-033

Country/Regional India Loan/Grant No.

2833

Project Officer Sourav Majumder Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

15 Dec 2011 31 Dec 2017 N/A

Division SAUW

Tranche Amount($ million)

43.84 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/40648-033/main

1 DED = Detailed Engineering Design.

113

Page 114: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Infrastructure Development Investment Program for Tourism - Tranche 2, not exceeding the aggregate amount of $43.84 million on 15 December 2011. Impact: Increased Volume of domestic and international tourists to destinations within the states of Tamil Nadu and Uttarakhand Outcome: Enhanced tourism environment in Tamil Nadu and Uttarakhand. Outputs: 1. Improved basic urban infrastructure and services at tourist destinations and attractions 2. Improved connectivity 3. Enhanced quality of natural and cultural attractions 4. Greater participation by local communities in tourism-related economic activities 5. Strengthened capacity of sector agencies and local communities for planning, development, management, and marketing of tourist destinations and attractions Implementation Arrangements: Uttarakhand: The Department of Tourism (DOT), Government of Uttarakhand (GOU) is the EA; A state-level empowered committee (SLEC) chaired by State's Chief Secretary, with Secretary of the DOT as member secretary; and secretaries from relevant line departments has been formed. The Uttarakhand Tourism Development Board (UTDB) is the implementing agency of the Investment Program, housing the PMU headed by the Project Director. PIUs have been set up in Dehradun, Bhimtal and Kotdwar. PMC and DSCs are in place and is functional. Tamil Nadu: The Department of Tourism & Culture (DOTC), Government of Tamil Nadu (GOTN) is the executing agency. A state-level empowered committee (SLEC) chaired by Chief Secretary, with Secretary of the DOT as member secretary and secretaries from relevant line departments has been formed. The Tamil Nadu Tourism Development Commissionerate (TNTDC) is the implementing agency of the Investment Program, housing the PMU headed by the Project Director. PIUs are functional at the cities where subprojects are being implemented. PMC and DSC are in place and also functional. Implementation Status: There are 23 contract packages (12 civil works packages, 5 goods packages and 6 consulting packages) in Uttarakhand. Similarly in Tamil Nadu, there are 19 contract packages (13 civil works packages, 4 goods packages and 2 consulting packages). 37 contracts have been awarded and are in various stages of implementation. Two packages (1 works and 1 goods) in Uttarakhand and three works packages in Tamil Nadu (at final stages of award), remains to be awarded.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

114

Page 115: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

31.03 100.00 8.85 100.00

Significant Developments During the Year

Tranche 2 (Loan 2833) is a loan of $43.84 million from Ordinary Capital Resources (OCR), which was approved on 15 December 2011 and declared effective on 19 June 2012. Tranche 2 is rated as On Track. Majority of the contracts in Tamil Nadu were awarded in 2015. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $31.03 million (100.0%) and $8.85 million (100.0%), respectively. About 30% physical progress has been achieved and the implementation progress under the tranche is satisfactory. Uttarakhand has awarded majority of the contracts (21 out of 23) and has achieved 35% of physical progress. Tamil Nadu has also awarded majority of the contracts (16 out of 19) and has achieved a physical progress of about 20%. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: There are 16 covenants for Tranche 2, of which 2 are complied with and 14 are under process.

1 DED = Detailed Engineering Design.

115

Page 116: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 3 UPDATE

Tranche TitleInfrastructure Development Investment Program for Tourism - Tranche 3

Project No. 40648-034

Country/Regional India Loan/Grant No.

3223

Project Officer Vivek Vishal Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

11 Dec 2014 30 Jun 2020 N/A

Division SAUW

Tranche Amount($ million)

123.51 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/40648-034/main

1 DED = Detailed Engineering Design.

116

Page 117: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Infrastructure Development Investment Program for Tourism - Tranche 3, not exceeding the aggregate amount of $123.51 million on 11 December 2014. Impact: increased volume of domestic and international tourists to destinations within the states of Himachal Pradesh, Punjab, and Uttarakhand. Outcome: enhanced tourism environment in Himachal Pradesh, Punjab, and Uttarakhand. Outputs: Enhanced quality of natural and cultural attractions Greater participation by local communities in tourism-related economic and livelihood activities Improved basic urban infrastructure and incidental services at tourist destinations and gateways Improved connectivity to tourist attractions Strengthened capacity of sector agencies and local communities for planning, development, management, and marketing of tourist destinations and attractions and promoting private sector participation and small businesses Implementation Arrangements: Punjab: As proposed during the project processing stage, the implementation arrangement, comprising the Department of Tourism (DOT), Government of Punjab (GOP) as the executing agency (EA), a state-level empowered committee (SLEC) chaired by states' Chief Secretary, with Secretary of the DOT as member secretary and secretaries from relevant line departments; the Punjab Heritage and Tourism Promotion Board (PHTPB) as the Implementation Unit (IA) of the Investment Program housing the Project Management Unit (PMU) headed by the Project Director; Project Implementation Units (PIUs) in Amritsar and Ropar; the project implementation cell with the Forest Department; Project Management Consultant (PMC) and Design and Supervision Consultant (DSC) is in place and is functional. Himachal Pradesh: The Department of Tourism and Civil Aviation (DOTCA), Government of Himachal Pradesh is the executing agency. The Himachal Pradesh Tourism Development Board (HPTDB) is the implementing agency with a fully staffed Project Management Unit (PMU). Three PIUs (Kangra, Shimla and Kullu) are established and fully staffed. A State-Level Empowered Committee (SLEC) was established to take all decisions related to the investment Program on behalf of the State. A team of consultants including the Project Management Consultants (PMC), Design Supervision Consultants (DSC), and NGOs for community-based tourism development are supporting the PMU and PIUs in project implementation. Uttarakhand: The Department of Tourism (DOT), Government of Uttarakhand (GOU) is the EA; A state-level empowered committee (SLEC) chaired by State's Chief Secretary, with Secretary of the DOT as member secretary; and secretaries from relevant line departments has been formed. The Uttarakhand Tourism Development Board (UTDB) is the implementing agency of the Investment Program, housing the PMU headed by the Project Director. PIUs have been set up in Dehradun, Bhimtal and Kotdwar. PMC and DSCs are in place and is functional. Implementation Status: The Project overachieved the contract award and disbursements targets for 2015. The projections for contract award and disbursements would be finalized after the fielding of Inception Mission planned in February 2016. There were 62 contracts ( 17 in Himachal Pradesh, 18 in Uttarakhand and 27 in Punjab). Out of 62 contracts, a total 20 contracts ( 5 in Himachal Pradesh, 5 in Uttarakhand and 10 in Punjab) have been awarded in 2015.

1 DED = Detailed Engineering Design.

117

Page 118: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

36.95 77.54 3.21 47.19

Significant Developments During the Year

Tranche 3 (Loan 3223) is a loan of $123.51 million from Ordinary Capital Resources (OCR), which was approved on 11 December 2014, and declared effective on 28 October 2015. Tranche 3 is rated as Potential Problem although this tranche overachieved SARD's contract award and disbursement targets of 2015. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 3 have reached $36.95 million (77.5%) and $3.21 million (47.2%), respectively. Overall Progress is satisfactory for Punjab, Himachal Pradesh and Uttarakhand. About 10% physical progress has been achieved under the tranche with same contribution from all 3 states. Out of 62 contracts, 20 civil works contracts (5 in Himachal Pradesh, 5 in Uttarakhand and 10 in Punjab) have been awarded in 2015 and works are in progress under these contracts Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: There are 19 covenants for Tranche 3, of which 2 are complied with and 17 are under process

1 DED = Detailed Engineering Design.

118

Page 119: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

41116013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - Jammu and Kashmir Urban Sector Development Investment Program (Facility Concept)

Project No. 41116-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

31 May 2007 31 Dec 2015 31 Mar 2017

Division SAUW

MFF Amount ($ million)

300.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - Jammu and Kashmir Urban Sector Development Investment Program (Facility Concept) for an aggregate amount not exceeding $300.00 million from ADB’s OCR on 31 May 2007. Impact: Sustainable economic growth through the provision of urban infrastructure services and the promotion of urban management improvement in Jammu and Srinagar, and selected towns with tourism potential in Jammu and Kashmir Outcome: Improved living environment and employment opportunities for the 2.4 million people living in Srinagar, Jammu and other participating towns with tourism flow, and Improved capacities of participating institutions in managing sector reforms and service delivery Outputs: Water supply system constructed Development of underground sewerage system and supply of sanitation of maintenance equipment Municipal solid waste processing and treatment with development of sanitary landfill sites Road and junction capacity augmentation and road safety improvements Capacity building and Institutional Development Implemented investment program for other municipal/urban infrstracture GIS created Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 3

Approved Tranche Amount to Date

212.20

Facility Change in Scope

Category Date Proposed Change

119

Page 120: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

120

Page 121: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleMFF - Jammu and Kashmir Urban Sector Development Investment Program (Subproject 1)

Project No. 41116-023

Country/Regional India Loan/Grant No.

2331

Project Officer Saugata Dasgupta Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

04 Jun 2007 31 Oct 2012 31 Dec 2016

Division INRM

Tranche Amount($ million)

42.20 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/41116-023/main

1 DED = Detailed Engineering Design.

121

Page 122: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the MFF - Jammu and Kashmir Urban Sector Development Investment Program (Subproject 1), not exceeding the aggregate amount of $42.20 million on 4 June 2007. Impact: Sustainable economic growth though the provision of urban infrastructure services and the promotion of urban management improvement in Jammu and Srinagar, and selected towns with tourism potential in the state of Jammu & Kashmir. Outcome: Improved living environment in Srinagar and Jammu Outputs: Water supply system for Srinagar Development of underground sewerage system for part of Jammu Development of SWM treatment facility at Srinagar Implementation Arrangements: The executing agency is the Economic Reconstruction Agency (ERA), Jammu and Kashmir. The ERA, under its Chief Executive Officer, is responsible for policy direction and strategic oversight. Two project management units (PMUs) have been created under the ERA for the implementation of the ongoing program, one in Jammu and the other one in Srinagar. PMUs identifies appraises, formulates and implements all subprojects and ensure compliance with the social and environmental safeguard policies. Implementation Status: Of the 10 civil work contracts under the Project, 3 contracts have been physically completed, 5 contracts are at different stages of implementation and 2 contracts are terminated due to poor performance. Capping activities of the first landfill cell constructed under the project has been completed. The second landfill cell is under use. The water supply line from Harwan to Nishat has been commissioned.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

1 DED = Detailed Engineering Design.

122

Page 123: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

37.05 97.36 34.57 100.00

Significant Developments During the Year

Tranche 1 (Loan 2331) is a loan of $42.20 million from Ordinary Capital Resources (OCR), which was approved on 04 June 2007, and declared effective on 25 March 2008. Partial cancellation of loan funds of $5.00 million, effective on 11 August 2014 was undertaken under Tranche 1. The net loan amount became $37.20 million. Tranche 1 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $37.05 million (97.4%) and $34.57 million (100.0%), respectively. About 93% physical progress have been achieved under Tranche 1 and it is in advanced stage of implementation. The progress is satisfactory under the Tranche. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: Out of the 44 covenants, 34 covenants have been complied with, 1 covenant is not yet due, and 9 covenants are under process.

1 DED = Detailed Engineering Design.

123

Page 124: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche TitleJammu and Kashmir Urban Sector Development Investment Program - Tranche 2

Project No. 41116-033

Country/Regional India Loan/Grant No.

2925

Project Officer Ron Slangen Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

26 Oct 2012 31 Mar 2017 N/A

Division SAUW

Tranche Amount($ million)

110.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/41116-033/main

1 DED = Detailed Engineering Design.

124

Page 125: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Jammu and Kashmir Urban Sector Development Investment Program - Tranche 2, not exceeding the aggregate amount of $110.00 million on 26 October 2012. Impact: Improved living environment in Jammu and Srinagar. Outcome: Improved urban services in Jammu and Srinagar. Outputs: 1. Improved water supply infrastructure. 2. Improved urban transport infrastructure. 3. Improved drainage infrastructure. 4. Institutional capacity of ERA and ULBs strengthened. 5. Project management system operational. Implementation Arrangements: The executing agency is the Economic Reconstruction Agency (ERA), Jammu and Kashmir. The ERA, under its Chief Executive Officer, is responsible for policy direction and strategic oversight. Two project management units (PMUs) have been created under the ERA for the implementation of the ongoing program, one in Jammu and the other one in Srinagar. PMUs identify, appraise, formulate and implement all subprojects and ensure compliance with the social and environmental safeguard policies. Implementation Status: All civil works and goods contracts have been awarded in 2015. Three major contracts are being closely monitored to ensure physical progress is on track. These are: (1) flyover in Srinagar, (ii) flyover in Jammu, and (iii) water supply tanks and distribution works in Jammu.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

87.72 100.00 28.09 100.00

1 DED = Detailed Engineering Design.

125

Page 126: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Significant Developments During the Year

Tranche 2 (Loan 2925) is a loan of $110.00 million from Ordinary Capital Resources (OCR), which was approved on 26 October 2012 and declared effective on 19 August 2013. Tranche 2 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $87.73 million (100.0%) and $28.09 million (100.0%), respectively. Three major contracts are being closely monitored: (I) flyover in Srinagar, (ii) flyover in Jammu, and (iii) water supply tanks and distribution works in Jammu. Physical progress for both flyovers is 41% against 75% of time elapsed. Additional labor and equipment will be mobilized by the contractor to expedite works. Physical progress for the water supply contract in Jammu is only 9% against 75% time elapsed. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: Of the 21 covenants, 3 covenants have been complied with and 18 are being complied with.

1 DED = Detailed Engineering Design.

126

Page 127: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 3 UPDATE

Tranche TitleJammu and Kashmir Urban Sector Development Investment Program - Tranche 3

Project No. 41116-043

Country/Regional India Loan/Grant No.

3132

Project Officer Atsushi Kaneko Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

05 Aug 2014 31 Mar 2017 N/A

Division SAUW

Tranche Amount($ million)

60.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/41116-043/main

1 DED = Detailed Engineering Design.

127

Page 128: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Jammu and Kashmir Urban Sector Development Investment Program - Tranche 3, not exceeding the aggregate amount of $60.00 million on 18 June 2014. Impact: improved living environment in Srinagar and Jammu. Outcome: improved urban services in Jammu and Srinagar. Outputs: Improved water supply infrastructure. Improved urban transport infrastructure. Improved drainage infrastructure. Institutional capacity of the Srinagar and Jammu Municipal Corporations improved. Implementation Arrangements: The executing agency is the Economic and Reconstruction Agency (ERA), Jammu and Kashmir. The ERA, under its Chief Executive Officer, is responsible for policy direction and strategic oversight. Two project management units (PMUs) have been created under the ERA for the implementation of the ongoing program, one in Jammu and the other one in Srinagar. PMUs identify, appraise, formulate and implement all subprojects and ensure compliance with the social and environmental safeguard policies. Implementation Status: The tranche has 7 civil works and 2 consultancy packages. Of the 7 civil works contracts, 5 have been awarded, 2 is under procurement. The consultancy package for the implementation of GAP was mobilized in August, while the recruitment of consultancy package for capacity building will be completed within a few months.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

41.17 100.00 9.69 100.00

1 DED = Detailed Engineering Design.

128

Page 129: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Significant Developments During the Year

Tranche 3 (Loan 3132) is a loan of $60.00 million from Ordinary Capital Resources (OCR), which was approved on 5 August 2014, and became effective on 29 January 2015. Tranche 3 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 3 have reached $41.17 million (100.0%) and $9.69 million (100.0%), respectively. Physical progress is on track except for one package, Jammu parking, which still currently under procurement. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: Of the 21 covenants, 3 have been complied with and 18 are being complied with.

1 DED = Detailed Engineering Design.

129

Page 130: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

41598013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - National Capital Region Urban Infrastructure Financing Facility (Facility Concept)

Project No. 41598-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

10 Aug 2010 30 Jun 2017 30 Jun 2018

Division SAUW

MFF Amount ($ million)

150.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - National Capital Region Urban Infrastructure Financing Facility (Facility Concept) for an aggregate amount not exceeding $150.00 million from ADB’s OCR on 10 August 2010. Impact: Improved quality of life and economic well-being of urban residents in NCR and CMAs Outcome: Urban residents use improved growthsupporting, public health, and environmental urban infrastructureservices in the intervention cities of NCR and CMAs in accordance with Regional Plan 2021 priorities Outputs: High quality urban public health and environmental infrastructure created High quality economic growth-related regional and urban infrastructure created Strengthened capacity of NCRPB and subborrowers to scale-up urban infrastructure and improve basic urban services Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

1

Approved Tranches To Date 1

Approved Tranche Amount to Date

78.00

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

130

Page 131: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

131

Page 132: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleMFF -National Capital Region Urban Infrastructure Financing Facility -Tranche 1

Project No. 41598-023

Country/Regional India Loan/Grant No.

2660

Project Officer Norio Saito Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

18 Aug 2010 31 Dec 2014 N/A

Division SAUW

Tranche Amount($ million)

78.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/41598-023/main

1 DED = Detailed Engineering Design.

132

Page 133: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the MFF -National Capital Region Urban Infrastructure Financing Facility -Tranche 1, not exceeding the aggregate amount of $78.00 million on 18 August 2010. Impact: Urban residents use improved urban infrastructure services in the intervention cities of National Capital Region (NCR) and counter magnet areas (CMA) in accordance with Regional Plan 2021 priorities. Outcome: Improved transport system and connectivity in NCR, and access to safe drinking water in subproject cities. Outputs: Road network improved in Jhajjar and Sonepat Districts Traffic diverted from Badli city center Multi-Modal Transit Centers (MMTC) developed in Anand Vihar and Sarai Kale Khan Provision of safe drinking water and water supply coverage increased in Panipat City Project Management and capacity building Provision of safe drinking water and water supply coverage increased in Pataudi Implementation Arrangements: The executing agency is the National Capital Region Planning Board (NCRPB). The Project Sanctioning and Monitoring Group (PSMG) of NCRPB will continue to be the focal point for subproject appraisal, approval, and overall guidance. The project divisions of the various sub-borrowers oversee subproject implementation. Implementation Status: Loan closing was on 31 December 2014. However, the loan account is not yet financially closed while social safeguards issues, particularly disputed land ownership of some sections of two road subprojects, are being resolved.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

1 DED = Detailed Engineering Design.

133

Page 134: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

60.00 99.97 60.00 100.00

Significant Developments During the Year

Tranche 1 (Loan 2660) is a loan of $60.00 million from Ordinary Capital Resources (OCR), which was approved on 18 August 2010, and declared effective on 29 June 2011. As of 31 December 2014, Tranche 1 was closed and the net loan amount was fully disbursed. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $60.00 million (100.0%) and $60.00 million (100.0%), respectively. Construction of remaining uncompleted Tranche 1 subprojects (two road, two water supply, and one drainage) is ongoing and will continue to be supported by Tranche 2, if approved. Social safeguards issues concerning disputed land ownership of some sections of two road subprojects are being monitored closely to ensure compliance with ADB Safeguard Policy Statement. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: There are nine (9) undertakings and eight (8) covenants for Tranche 1 which are being mostly complied with. In two road subprojects, the state government decided to carry out mutation of land in favor of the sub-borrower for entire length of the roads, except for the sections where villagers have gone to court.

1 DED = Detailed Engineering Design.

134

Page 135: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

41603013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - Bihar Urban Development Investment Program (Facility Concept)

Project No. 41603-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

01 Mar 2012 31 Dec 2021 N/A

Division SAUW

MFF Amount ($ million)

200.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - Bihar Urban Development Investment Program (Facility Concept) for an aggregate amount not exceeding $200.00 million from ADB’s OCR on 29 March 2012. Impact: Urban population in relatively poor and weak capacity state (Bihar) has improved access to water supply and sanitation facilities. Outcome: People, especially vulnerable household, will have access to better quality and sustainable urban water supply and sewerage services in Bhagalpur, Darbhanga, Gaya and Muzaffarpur. Outputs: Water supply infrastructure in 3 towns improved. Sewerage infrastructure in 1 town improved. O&M of the asset created by the subprojects improved. Urban service delivery management improved. Project management and implementation skills and transparency in improved. Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 1

Approved Tranche Amount to Date

65.00

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

135

Page 136: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

136

Page 137: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleBihar Urban Development Investment Program - Tranche 1

Project No. 41603-023

Country/Regional India Loan/Grant No.

2861

Project Officer Neeta Pokhrel Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

16 Apr 2012 30 Jun 2017 N/A

Division SAUW

Tranche Amount($ million)

65.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

4.00

Project Data Sheet http://www.adb.org/projects/41603-023/main

Tranche Summary

ADB approved the Bihar Urban Development Investment Program - Tranche 1, not exceeding the aggregate amount of $65.00 million on 13 April 2012. Impact: People, especially vulnerable household, will have increased access to better quality and sustainable urban infrastructure and services in Bhagalpur, Darbhanga, Gaya and Muzaffarpur. Outcome: BUIDCo and ULB improve infrastructure, operations and sustainability in water supply in Bhagalpur. Outputs: 1. Water supply infrastructure rehabilitated and newly constructed in Bhagalpur. 2. Staffing and skills for water supply operations improved in Bhagalpur. 3. Systems for water supply service delivery management improved in Bhagalpur. 4. Subproject implemented on time within the budget in a transparent manner. Implementation Arrangements: Executing agency is Urban Development and Housing Department (UDHD) and implementing agency is Bihar Urban Infrastructure Development Corporation (BUIDCO). Implementation Status: The design-build-operate contract for the Bhagalpur water supply Phase 1 (BWSP1) was awarded in 2014 and contractor has taken over full operation of the Bhagalpur water supply services in July 2015. The contractor completed all designs and construction is expected to start in January 2016.

1 DED = Detailed Engineering Design.

137

Page 138: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

44.20 0.00 7.82 0.00

Significant Developments During the Year

Tranche 1 (Loan 2861) is a loan of $57.00 million from Ordinary Capital Resources (OCR), which was approved on 16 April 2012 and declared effective on 6 June 2013. The original loan amount approved by ADB for Tranche 1 is $65.00 but $8.00 million was subsequently cancelled in November 2014 upon the request of the Government. Tranche 1 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $44.20 million (.0%) and $7.82 million (.0%), respectively. The design build and operate contract for BWSP1 was awarded in July 2014 and the contractor mobilized in October 2014. The contractor has taken over full operation of the Bhagalpur water supply services in July 2015. The contractor completed all designs and construction is expected to start in January 2016. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: Out of the 22 project specific covenants, 21 are being complied and/or complied with while one is not yet due. Undertakings are being generally complied with.

1 DED = Detailed Engineering Design.

138

Page 139: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

41614013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title Assam Power Sector Enhancement Investment Program Project No. 41614-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

18 Nov 2009 N/A N/A

Division SAEN

MFF Amount ($ million)

200.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the Assam Power Sector Enhancement Investment Program for an aggregate amount not exceeding $200.00 million from ADB’s OCR on 18 November 2009. Impact: A sustainable state power sector with increased T & D capacity to support inclusive economic growth. Outcome: Enhanced quality and expanded service delivery of electricity through improved technical, commercial, and financial performance and capability of power utilities. Outputs: Access to power Energy Efficiency enhancement Distribution franchise investment Significant Developments of the Facility: The closing date of the Facility has been extended from 30 June 2015 to 31 October 2019. Other than this, there are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 4

Approved Tranche Amount to Date

251.20

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

139

Page 140: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

140

Page 141: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleAssam Power Sector Enhancement Investment Program - Tranche 1

Project No. 41614-023

Country/Regional India Loan/Grant No.

2592

Project Officer Jyotirmoy Banerjee Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

18 Nov 2009 28 Feb 2014 31 Mar 2013

Division SAEN

Tranche Amount($ million)

61.30 Source OCRTASF

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/41614-023/main

1 DED = Detailed Engineering Design.

141

Page 142: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Assam Power Sector Enhancement Investment Program - Tranche 1, not exceeding the aggregate amount of $60.30 million on 27 November 2009. Impact: A sustainable state power transmission sector to support inclusive economic growth. Outcome: Enhanced transmission capacity and quality with physical and institutional capacity development. Outputs: Nonphysical Investments: Renewable Energy Development Nonphysical Investments: Institutional and/or capacity development of ASEB, APGCL, AEGCL, and LAEDCL Nonphysical Investments: Distribution franchising Physical Investments: Access to power (transmission) Constructed new transmission lines and substations, augmented existing substations, and miscellaneous transmission system improvement activities Physical Investments: Energy efficiency enhancement (transmission loss reduction) Extended and augmented existing substations Nonphysical Investments: Project implementation support Implementation Arrangements: The Assam Electricity Grid Corporation Limited (AEGCL) is the executing agency (EA) for tranches 1 and 2 (Loans 2592 and 2667) while the Assam Power Distribution Company Limited (APDCL) is the EA for tranche 3 (Loan 2800). The three tranches were delegated to India Resident Mission on 16 June 2015. The revised loan closing date for all the 3 tranches is 30 June 2016. Implementation Status: The Project has achieved about 95% implementation progress.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

1 DED = Detailed Engineering Design.

142

Page 143: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

47.27 95.30 40.67 81.99

Significant Developments During the Year

Tranche 1 (Loan 2592) is a loan of $60.30 million from Ordinary Capital Resources (OCR), which was approved on 18 October 2009 and declared effective on 11 January 2010. Tranche 1 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $47.27 million (95.3%) and $40.67 million (82.0%), respectively. The Project has achieved about 95% overall progress. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: There are about 4 undertaking and 26 loan covenants. All undertaking and covenants are being complied with by the EA. The Auditor's Report and Audited Financial Statements for the fiscal year 2015 were submitted and reviewed.

1 DED = Detailed Engineering Design.

143

Page 144: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche TitleMFF - Assam Power Sector Enhancement Investment Program - Tranche 2

Project No. 41614-033

Country/Regional India Loan/Grant No.

2677

Project Officer Jyotirmoy Banerjee Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

05 Oct 2010 30 Nov 2013 30 Jun 2016

Division SAEN

Tranche Amount($ million)

89.70 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/41614-033/main

Tranche Summary

ADB approved the MFF - Assam Power Sector Enhancement Investment Program - Tranche 2, not exceeding the aggregate amount of $89.70 million on 5 October 2010. Impact: A sustainable state power sector with increased transmission and distribution capacity to support inclusive economic growth Outcome: Enhanced quality and expanded service delivery of electricity in Assam through improved technical, commercial, and financial performance and capability of the power sector utilities Outputs: Access to power: Constructed new transmission lines and substations, and other transmission system improvement activities Energy efficiency enhancement : Extended and augmented transmission substations, refurbished existing substations, reactive compensation, introduction of new technologies to reduce loss Implementation Arrangements: The Assam Electricity Grid Corporation Limited (AEGCL) is the executing agency (EA) for tranches 1 and 2 (Loans 2592 and 2667) while the Assam Power Distribution Company Limited (APDCL) is the EA for tranche 3 (Loan 2800). The three tranches were delegated to India Resident Mission on 16 June 2015. The revised loan closing date for all the 3 tranches is 30 June 2016. Implementation Status: The Project has achieved about 95% overall progress.

1 DED = Detailed Engineering Design.

144

Page 145: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

65.25 97.53 55.35 82.74

Significant Developments During the Year

Tranche 2 (Loan 2677) is a loan of $66.90 million from Ordinary Capital Resources (OCR), which was approved on 5 October 2010 and declared effective on 1 April 2011. Tranche 2 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $65.25 million (97.5%) and $55.35 million (82.7%), respectively. The Project has achieved about 95% overall progress. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: There are about 6 undertaking and 23 loan covenants. All undertaking and covenants are being complied with by the EA. The Auditor's Report and Audited Financial Statements for the fiscal year 2015 were submitted and reviewed.

1 DED = Detailed Engineering Design.

145

Page 146: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 3 UPDATE

Tranche TitleAssam Power Sector Enhancement Investment Program - Tranche 3

Project No. 41614-035

Country/Regional India Loan/Grant No.

2800

Project Officer Jyotirmoy Banerjee Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

04 Nov 2011 31 Dec 2014 30 Jun 2016

Division SAEN

Tranche Amount($ million)

50.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/41614-035/main

Tranche Summary

ADB approved the Assam Power Sector Enhancement Investment Program - Tranche 3, not exceeding the aggregate amount of $50.00 million on 4 November 2011. Impact: Enhanced quality and expanded service delivery of electricity in Assam Outcome: APDCL becomes sustainable company with increased efficiency and distribution network capacity Outputs: Constructed and augmented distribution lines and substations, and conclusion of electrification programs Renovated and modernized distribution substations. Implementation Arrangements: The Assam Electricity Grid Corporation Limited (AEGCL) is the executing agency (EA) for tranches 1 and 2 (Loans 2592 and 2667) while the Assam Power Distribution Company Limited (APDCL) is the EA for tranche 3 (Loan 2800). The revised loan closing date for all the 3 tranches is 30 June 2016. Implementation Status: The Project has achieved about 95% overall progress.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

146

Page 147: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance

( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

30.69 92.15 26.87 80.70

Significant Developments During the Year

Tranche 3 (Loan 2800) is a net loan of $33.30 million from Ordinary Capital Resources (OCR), which was approved on 4 November 2011 and declared effective on 16 April 2012. Tranche 3 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 3 have reached $30.69 million (92.2%) and $26.87 million (80.7%), respectively. The Project has achieved about 95% overall progress. The loan has been extended to 30 June 2016. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: There are about 5 undertaking and 26 loan covenants. All undertakings sand covenants are being complied with by the EA. The Auditor's Report and Audited Financial Statements for the fiscal year 2015 were submitted and reviewed.

1 DED = Detailed Engineering Design.

147

Page 148: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 4 UPDATE

Tranche TitleAssam Power Sector Enhancement Investment Program - Tranche 4

Project No. 41614-036

Country/Regional India Loan/Grant No.

3200

Project Officer Aziz Yusupov Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

25 Nov 2014 30 Jun 2019 N/A

Division SAEN

Tranche Amount($ million)

50.20 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/41614-036/main

Tranche Summary

ADB approved the Assam Power Sector Enhancement Investment Program - Tranche 4, not exceeding the aggregate amount of $50.20 million on 25 November 2014. Impact: an enhanced quality and expanded service delivery of electricity in Assam. Outcome: increased operational efficiency and expanded distribution network capacity of Assam Power Distribution Company Ltd. (APDCL). Outputs: Enhanced capacity of distribution system improved technology of operations and maintenance (O&M) system. Implementation Arrangements: The Assam Power Distribution Company Ltd (APDCL) is the executing agency for Tranche 4 having the overall responsibility for (i) project management, (ii) coordinate implementation, and (iii) function as project implementation unit to assist in day-today project implementation. The PMU will be responsible for implementing, monitoring, and reporting the progress of project implementation to ADB, the GOI, and GOA. Implementation Status: Implementation of Tranche 4 is satisfactory with respect to all indicators and is rated "on track" as of Q3 2015. However, due to delays in contract award, the overall project is rated as potential problem as of Q4 2015.

1 DED = Detailed Engineering Design.

148

Page 149: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

27.07 53.93 2.70 0.00

Significant Developments During the Year

Tranche 4 (Loan 3200) is a loan of $50.20 million from Ordinary Capital Resources (OCR), which was approved on 25 November 2014 and declared effective on 12 May 2015. Tranche 4 is rated as Potential Problem. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 4 have reached $27.07 million (53.9%) and $2.70 million (.0%), respectively. The project's physical progress is 46.74% against the elapsed loan period of 24% from the loan approval. The procurement plan includes 5 ICB contracts and 1 consulting services contract. Contract for the consulting services has been signed and consulting firm has commenced the assignment. Out of 5 ICB contracts, 3 have been awarded and the remaining 2 will be awarded in the first quarter of 2016. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: As of inception mission, the EA confirmed that the 23 loan covenants will be complied with.

1 DED = Detailed Engineering Design.

149

Page 150: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

41627013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - Himachal Pradesh Clean Energy Development Investment Program (Facility Concept)

Project No. 41627-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

23 Oct 2008 22 Oct 2018 N/A

Division SAEN

MFF Amount ($ million)

800.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - Himachal Pradesh Clean Energy Development Investment Program (Facility Concept) for an aggregate amount not exceeding $800.00 million from ADB’s OCR on 23 October 2008. Impact: A sustainable state electricity sector and improved state finances. Outcome: Increased hydropower production, as well as improved planning, implementation, management and sector governance. Outputs: Capacity development component (i) Project-oriented: Implemented capacity development of various departments of HPPCL, focusing on (a) project preparation, implementation and management (including procurement, disbursements, safeguards compliance, and reporting); (b) financial management and accountability; and (c) knowledge transfer for compliance with ADB policies and procedures (ii) Corporate development: (a) Implemented capacity development to improve governance, fiduciary oversight, and organizational structuring; and (b) Developing in-house expertise within HPPCL on private sector participation modalities and CDM procedures. (iii) Implement enterprise resource planning solution at HPSEB Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 4

Approved Tranche Amount to Date

732.10

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

150

Page 151: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

151

Page 152: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleMFF - Himachal Pradesh Clean Energy Development Investment Program (Tranche 1)

Project No. 41627-023

Country/Regional India Loan/Grant No.

2461

Project Officer Vallabha Karbar Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

27 Oct 2008 31 Mar 2014 31 Mar 2016

Division INRM

Tranche Amount($ million)

150.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/41627-023/main

1 DED = Detailed Engineering Design.

152

Page 153: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the MFF - Himachal Pradesh Clean Energy Development Investment Program (Tranche 1), not exceeding the aggregate amount of $150.00 million on 27 October 2008. Impact: A sustainable state electricity sector and improved state finances. Outcome: Increased hydropower production, as well as improved planning, implementation, management and sector governance. Outputs: Capacity development component: (i) Project-oriented: Implemented capacity development of various departments of HPPCL, focusing on (a) project preparation, implementation and management (including procurement, disbursements, safeguards compliance, and reporting); (b) financial management and accountability; and (c) knowledge transfer for compliance with ADB policies and procedures (ii) Corporate development: (a) Implemented capacity development to improve governance, fiduciary oversight, and organizational structuring; and (b) Developing in-house expertise within HPPCL on private sector participation modalities and CDM procedures. (iii) Implement enterprise resource planning solution at HPSEB Tranche 1 funds electro-mechanical contracts and some civil works of the 111 MW Sawra Kuddu Project and Stage 1 of the Kashang Project (65 MW) Implementation Arrangements: HPPCL is the Implementing Agency. Implementation Status: HPPCL has achieved overall implementation progress of more than 95%. E&M and civil works are under advanced stage of implementation. Loan closing date has been extended from 31 March 2014 to 31 March 2016 upon request of Himachal Pradesh Power Corporation Limited (Implementing Agency) and endorsement of Department of Economic Affairs, Government of India.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

1 DED = Detailed Engineering Design.

153

Page 154: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

138.97 92.65 138.51 92.34

Significant Developments During the Year

Tranche 1 (Loan 2461) is a loan of $150.00 million from Ordinary Capital Resources (OCR), which was approved on 27 October 2008, and declared effective on 15 December 2008. The current loan closing date has been extended from 31 March 2014 to 31 March 2016. Tranche 1 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $138.97 million (92.6%) and $138.51 million (92.3%), respectively. HPPCL has achieved overall implementation progress of more than 95%. E&M and civil works are under advanced stage of implementation. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: All undertakings and covenants are being complied with.

1 DED = Detailed Engineering Design.

154

Page 155: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche TitleMFF - Himachal Pradesh Clean Energy Development Investment Program -Tranche 2

Project No. 41627-033

Country/Regional India Loan/Grant No.

2596

Project Officer Vallabha Karbar Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

08 Dec 2009 30 Jun 2014 30 Jun 2017

Division INRM

Tranche Amount($ million)

59.10 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/41627-033/main

Tranche Summary

ADB approved the MFF - Himachal Pradesh Clean Energy Development Investment Program -Tranche 2, not exceeding the aggregate amount of $59.10 million on 8 December 2009. Impact: A sustainable state electricity sector and improved state finances Outcome: Increased hydropower production. Outputs: Hydropower generation infrastruction constructed - Subproject proposed for tranche 2: The civil works contract package consisting of the construction of the diversion barrage, power intake, desanding arrangements and gates and hoisting arrangements for the 11 MW Sawra Kuddu hydroelectric project . Implementation Arrangements: HPPCL is the Implementing Agency. Implementation Status: HPPCL has achieved overall implementation progress of more than 85%. The contract Diversion, Barrage and De-sanding Arrangement (DBID) is under advanced stage of implementation. The current loan closing date of Loan 2596-IND has been extended from 31 Dec 2015 to 30 June 2017 upon the request of Himachal Pradesh Power Corporation Limited (Implementing Agency), and endorsement of Department of Economic Affairs, Government of India. An amount of $3.00 million was cancelled from Tranche 2 on 31 December 2014 upon the request of Himachal Pradesh Power Corporation Limited (Implementing Agency), and endorsement of Department of Economic Affairs, Government of India.

1 DED = Detailed Engineering Design.

155

Page 156: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

53.48 95.32 46.06 82.11

Significant Developments During the Year

Tranche 2 (Loan 2596) is a loan of $59.10 million from Ordinary Capital Resources (OCR), which was approved on 08 December 2009, and declared effective on 13 May 2010. The current loan closing date has been extended from 30 June 2014 to 30 June 2017. Tranche 2 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $53.48 million (95.3%) and $46.06 million (82.1%), respectively. HPPCL has achieved overall implementation progress of more than 85%.The contract Diversion, Barrage and De-sanding Arrangement (DBID) is under advanced stage of implementation. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: All undertakings and covenants are being complied with.

1 DED = Detailed Engineering Design.

156

Page 157: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 3 UPDATE

Tranche TitleMFF - Himachal Pradesh Clean Energy Development Investment Program - Tranche 3

Project No. 41627-043

Country/Regional India Loan/Grant No.

2687

Project Officer Vallabha Karbar Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

22 Oct 2010 30 Jun 2016 N/A

Division INRM

Tranche Amount($ million)

208.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/41627-043/main

Tranche Summary

ADB approved the MFF - Himachal Pradesh Clean Energy Development Investment Program - Tranche 3, not exceeding the aggregate amount of $208.00 million on 22 October 2010. Impact: A sustainable state electricity sector and improved state finances. Outcome: Increased clean energy production Outputs: Hydropower generation Infrastructure constructed - Subprojects proposed for tranche 3: Construction of the 100 MW Sainj Hydroelectric project, and Stage II and III of the Integrated Kashang Hydroelectric Project (subproject construction includes certain civil works, underground powerhouse, river diversion, intake and desilting, electrical & interconnection works) Implementation Arrangements: HPPCL is the Implementing Agency. Implementation Status: HPPCL has achieved overall implementation progress of 80%. The Electro-mechanical and civil works for the hydroelectric project (HEP) is ongoing.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

157

Page 158: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

187.32 100.00 157.81 100.00

Significant Developments During the Year

Tranche 3 (Loan 2687) is a loan of $208.00 million from Ordinary Capital Resources (OCR), which was approved on 22 October 2010, and declared effective on 17 March 2011. Tranche 3 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 3 have reached $187.32 million (100.0%) and $157.81 million (100.0%), respectively. HPPCL has achieved overall implementation progress of 80%.The Electro-mechanical and civil works for the hydroelectric project (HEP) is ongoing. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: All undertakings and covenants are being complied with.

1 DED = Detailed Engineering Design.

158

Page 159: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 4 UPDATE

Tranche TitleHimachal Pradesh Clean Energy Development Investment Program - Tranche 4

Project No. 41627-053

Country/Regional India Loan/Grant No.

2914

Project Officer Vallabha Karbar Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

02 Oct 2012 30 Jun 2018 N/A

Division INRM

Tranche Amount($ million)

315.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/41627-053/main

Tranche Summary

ADB approved the Himachal Pradesh Clean Energy Development Investment Program - Tranche 4, not exceeding the aggregate amount of $315.00 million on 2 October 2012. Impact: Increased hydropower production and contribution to climate change mitigation with improved project management and sector governance in Himachal Pradesh. Outcome: Improved capacity of HPPCL to generate and sell electricity from hydropower and manage its operations. Outputs: 1. Shongtong Karcham Hydroelectric Project becomes operational on time and within budget. 2. Data center and disaster recovery center installed in HPPCL corporate facilities and are operational 3. Capacity of HPPCL personnel on project management, operations and maintenance improved Implementation Arrangements: HPPCL is the Implementing Agency. Implementation Status: HPPCL has achieved overall implementation progress of 40%. An amount of $58.00 million was cancelled from Tranche 4 on 26 August 2014 upon the request of Himachal Pradesh Power Corporation Limited (Implementing Agency), and endorsement of Department of Economic Affairs, Government of India.

1 DED = Detailed Engineering Design.

159

Page 160: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

161.79 94.32 45.53 79.69

Significant Developments During the Year

Tranche 4 (Loan 2914) is a loan of $315.00 million from Ordinary Capital Resources (OCR), which was approved on 02 October 2012, and declared effective on 17 January 2013. Tranche 4 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 4 have reached $161.79 million (94.3%) and $45.53 million (79.7%), respectively. HPPCL has achieved overall implementation progress of 40%. The civil works contract for the hydroelectric project (HEP) is ongoing. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: All undertakings and covenants are being complied with.

1 DED = Detailed Engineering Design.

160

Page 161: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

42265013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF-Assam Urban Infrastructure Investment Program Project No. 42265-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

09 Sep 2011 30 Jun 2018 N/A

Division SAUW

MFF Amount ($ million)

200.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF-Assam Urban Infrastructure Investment Program for an aggregate amount not exceeding $200.00 million from ADB’s OCR on 30 September 2011. Impact: Urban population in relatively poor and weak capacity state (Assam) has improved access to water supply, sanitation, and urban infrastructure facilities. Outcome: Improved and sustainable water supply, sanitation and drainage in the selected project cities in Assam. Outputs: 1. Improved, regular and sustainable metered water supply in Guwahati 2. Solid waste management infrastructure improved in Dibrugarh 3. Improved urban drainage system in Dibrugarh and Guwahati 4. Project management and implementation skills strengthened in the implementing agencies and ULBs. Significant Developments of the Facility: There are no significant developments of the facility, including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

1

Approved Tranches To Date 1

Approved Tranche Amount to Date

81.00

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

161

Page 162: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

162

Page 163: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleAssam Urban Infrastructure Investment Program - Tranche 1

Project No. 42265-023

Country/Regional India Loan/Grant No.

2806

Project Officer Ashok Srivastava Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

18 Nov 2011 30 Jun 2018 N/A

Division SAUW

Tranche Amount($ million)

81.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/42265-023/main

1 DED = Detailed Engineering Design.

163

Page 164: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Assam Urban Infrastructure Investment Program - Tranche 1, not exceeding the aggregate amount of $81.00 million on 18 November 2011. Impact: Improved and sustainable urban services in selected project cities in Assam (synchronized with the MFF's DMF outcome). Outcome: Efficient and improved pre-distribution water supply infrastructure in Guwahati, and drainage and solid waste management in Dibrugarh (consolidated MFFs DMF outputs) Outputs: 1. Improved and increased water supply area in project city 2. Solid waste management infrastructure improved in Dibrugarh city 3. Reduced flooding through improved urban drainage in the project cities 4. Implementing agencies and ULBs effectively manage the project Implementation Arrangements: The Guwahati Development Department (GDD) is the Investment Program's executing agency (EA) and the Implementing Agencies (IAs) are Guwahati Metropolitan Development Authority and Dibrugarh Municipal Board. Implementation Status: Out of the three ongoing civil works contracts, two contracts were terminated by the EA due to poor performance of the contractor. The Invitation for Bids (IFB) for the balance works of the terminated contracts were issued in December 2015. The other ongoing contract is for drainage works in Dibrugarh. Procurement for a solid waste management package in Dibrugarh is currently ongoing.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

38.08 85.75 6.20 100.00

1 DED = Detailed Engineering Design.

164

Page 165: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Significant Developments During the Year

Tranche 1 (Loan 2806) is a loan of $81.00 million from Ordinary Capital Resources (OCR), which was approved on 18 November 2011 and declared effective on 25 April 2012. Tranche 1 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $38.08 million (85.7%) and $6.20 million (100.0%), respectively. Out of the three ongoing civil works contracts, two contracts were terminated by the EA due to poor performance of the contractor and bids have been invited for remaining works of the terminated contracts. The other ongoing contract is for drainage works in Dibrugarh. Procurement for a solid waste management package in Dibrugarh is currently ongoing. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: There are 31 covenants for Tranche 1, of which 27 are being complied with and/or compliant, while 4 are not yet due. Undertakings are being complied with.

1 DED = Detailed Engineering Design.

165

Page 166: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

42266013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title Kolkata Environmental Improvement Investment Program (Facility Concept)

Project No. 42266-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

26 Sep 2013 31 Dec 2023 N/A

Division SAUW

MFF Amount ($ million)

400.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the Kolkata Environmental Improvement Investment Program (Facility Concept) for an aggregate amount not exceeding $400.00 million from ADB’s OCR on 26 September 2013. Impact: Improved access to water supply and sanitation in KMC Outcome: Improved water supply, sewerage, and drainage service quality and operational sustainability in selected areas of KMC Outputs: Inefficient water supply assets rehabilitated. Sewerage extension to peripheral areas continued. Financial and project management capacity further developed. Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 1

Approved Tranche Amount to Date

100.00

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

166

Page 167: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

167

Page 168: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleKolkata Environmental Improvement Investment Program - Tranche 1

Project No. 42266-023

Country/Regional India Loan/Grant No.

3053

Project Officer Neeta Pokhrel Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

22 Oct 2013 30 Jun 2019 N/A

Division SAUW

Tranche Amount($ million)

100.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

2.20

Project Data Sheet http://www.adb.org/projects/42266-023/main

Tranche Summary

ADB approved the Kolkata Environmental Improvement Investment Program - Tranche 1, not exceeding the aggregate amount of $100.00 million on 22 October 2013. Impact: Improved water supply, sewerage, and drainage service quality and operational sustainability in select areas of KMC Outcome: Improved operational efficiency and coverage of water supply, sewerage, drainage services in selected areas of KMC. Outputs: Inefficient water supply assets rehabilitated. Sewerage extension to peripheral areas continued. Financial and project management capacity further developed. Implementation Arrangements: The Kolkata Municipal Corporation is the executing and implementing agency of the investment program. Implementation Status: Five water supply and sewerage contracts and two consulting contracts are ongoing.

1 DED = Detailed Engineering Design.

168

Page 169: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

50.86 74.80 13.46 100.00

Significant Developments During the Year

Tranche 1 (Loan 3053) is a loan of $100.00 million from Ordinary Capital Resources (OCR), which was approved on 22 October 2013 and declared effective on 30 May 2014. Tranche 1 is rated as Potential Problem. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $50.86 million (74.8%) and $13.46 million (100.0%), respectively. Bidding of the performance-based water loss management package failed. Package is being re-examined prior to rebidding. The additional package for the sewerage and drainage network was approved for award while the contract for renovation of PMU Office was awarded. Recruitment of the public communication and social development consultants are at financial evaluation stage while recruitment of GIS mapping consultant was initiated. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: There are 27 project specific covenants for Tranche 1, of which, 24 are being complied with and/or compliant, while 3 are not yet due. Undertakings and covenants are being generally complied.

1 DED = Detailed Engineering Design.

169

Page 170: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

42378014

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title Power System Expansion and Efficiency Improvement Investment Program (Facility Concept)

Project No. 42378-014

Country/Regional

Bangladesh Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

28 Nov 2012 31 Dec 2018 N/A

Division SAEN

MFF Amount ($ million)

700.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the Power System Expansion and Efficiency Improvement Investment Program (Facility Concept) for an aggregate amount not exceeding $700.00 million from ADB’s OCR on 28 November 2012. Impact: Increased energy sector contribution to low-carbon economic growth in Bangladesh Outcome: Increased access to clean and reliable supply of electricity in Bangladesh Outputs: Improved efficiency in electricity generation, transmission, and distribution Increased renewable energy use Enhanced capacity of power sector agencies and farmer organizations Project management system in place Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 3

Approved Tranche Amount to Date

700.00

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

170

Page 171: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

171

Page 172: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitlePower System Expansion and Efficiency Improvement Investment Program - Tranche 1

Project No. 42378-015

Country/Regional Bangladesh Loan/Grant No.

0320, 2966

Project Officer Aziz Yusupov Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

12 Dec 2012 31 Dec 2018 N/A

Division SAEN

Tranche Amount($ million)

185.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/42378-015/main

Tranche Summary

ADB approved the Power System Expansion and Efficiency Improvement Investment Program - Tranche 1, not exceeding the aggregate amount of $185.00 million on 12 December 2012. Impact: Increased access to clean and reliable electricity supply in Bangladesh Outcome: Improved efficiency in electricity generation, and transmission in Bangladesh Outputs: 1. Increased generation capacity 2. Increased transmission capacity 3. Enhanced capacity of power sector agencies 4. Project management system in place Implementation Arrangements: The executing agencies for Tranche 1 include Northwest Power Generation Company Limited (NWPGCL), Bangladesh Power Development Board (BPDB), Power Grid Company of Bangladesh (PGCB), and Power Division of the Ministry of Power, Energy, and Mineral Resources (MPEMR). Implementation Status: By end of 2015, the project's physical progress is 62% against the elapsed loan period of 47% from loan approval. All procurement packages have been contracted and disbursement of funds is ongoing on a systematic basis. Project is satisfactory with respect to all indicators and is rated "on track" as of fourth quarter of 2015. It is expected to retain this rating in the first quarter of 2016 as the loan proceeds are expected to be disbursed regularly.

1 DED = Detailed Engineering Design.

172

Page 173: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

172.34 100.00 87.64 100.00

Significant Developments During the Year

Tranche 1 (Loan 2966) is a loan of $185.00 million from Ordinary Capital Resources (OCR), which was approved on 12 December 2012 and declared effective on 25 June 2013. Tranche 1 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $172.35 million (100.0%) and $87.64 million (100.0%), respectively. By end of 2015, the project's physical progress is 62% against the elapsed loan period of 47% from loan approval. All procurement packages have been contracted. Consulting service for Tranche 3 preparation commenced in June 2015. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: There are 26 covenants: 24 are being complied with while 2 are not yet due.

1 DED = Detailed Engineering Design.

173

Page 174: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche TitlePower System Expansion and Efficiency Improvement Investment Program - Tranche 2

Project No. 42378-016

Country/Regional Bangladesh Loan/Grant No.

3087

Project Officer Aziz Yusupov Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

30 Nov 2013 30 Jun 2019 N/A

Division SAEN

Tranche Amount($ million)

310.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/42378-016/main

Tranche Summary

ADB approved the Power System Expansion and Efficiency Improvement Investment Program - Tranche 2, not exceeding the aggregate amount of $310.00 million on 11 December 2013. Impact: Increased access to reliable supply of electricity Outcome: Increased Transmission and Distribution capability in the power system Outputs: Increased Transmission Capacity Increased south Dhaka distribution network capacity Increased north Dhaka distribution network capacity Efficiently managed project Implementation Arrangements: Executing agencies for Tranche 2 are Power Grid Company of Bangladesh (PGCB), Dhaka Power Distribution Company Limited (DPDCL), and Dhaka Electricity Supply Company Limited (DESCO). PGCB will implement transmission component. DPDC will implement South Dhaka distribution network component. DESCO will implement North Dhaka distribution network component. Implementation Status: By end of 2015, the project's physical progress is 3% against the elapsed loan period of 33% from loan approval. Project is satisfactory with respect to all indicators and is rated "on track" as of fourth quarter of 2015. However, the rating is at risk and can be converted to "potential problem" in ADB's system by first quarter 2016 due to the delayed award of some contracts.

1 DED = Detailed Engineering Design.

174

Page 175: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

169.55 100.00 16.03 100.00

Significant Developments During the Year

Tranche 2 (Loan 3087) is a loan of $310.00 million from Ordinary Capital Resources (OCR), which was approved on 9 December 2013 and declared effective on 14 March 2014. Tranche 2 is rated as On Track. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $169.55 million (100.0%) and $16.03 million (100.0%), respectively. By end of 2015, the project's physical progress is 32% against the elapsed loan period of 33% from loan approval. 10 of the 14 procurement contracts were awarded in 2015. There is no consulting service to be financed in this tranche. Scope Change: There were no scope changes for this tranche in 2015. Undertaking and Covenants: There are 19 covenants and all are being complied with.

1 DED = Detailed Engineering Design.

175

Page 176: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 3 UPDATE

Tranche TitlePower System Expansion and Efficiency Improvement Investment Program - Tranche 3

Project No. 42378-017

Country/Regional Bangladesh Loan/Grant No.

3350

Project Officer Aziz Yusupov Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

08 Dec 2015 30 Jun 2021 N/A

Division SAEN

Tranche Amount($ million)

205.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/42378-017/main

Tranche Summary

ADB approved the Power System Expansion and Efficiency Improvement Investment Program - Tranche 3, not exceeding the aggregate amount of $205.00 million on 8 December 2015. Impact: better access to reliable electricity supply in Bangladesh. Outcome: increased efficiency and capacity of the power system in Bangladesh. Outputs: Power generation system expanded and upgraded through replacement of an aging steam and gas turbine power plant of 220 megawatt (MW) capacity with a more efficient 400 MW gas-fired Combined Cycle Power Plant (CCPP) at Ashuganj Power Station complex transmission system expanded and upgraded through upgrade or construction of 132kv transmission lines and substations in Chittagong Division demand side energy efficiency improved through replacement of meters with approximately 700,000 pre-payment meters in Dhaka Division. Implementation Arrangements: Not Applicable Implementation Status: Not yet effective

1 DED = Detailed Engineering Design.

176

Page 177: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating

Financial

Contract Awards

Disbursements

Safeguards

Technical

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

0.00 0.00 0.00 0.00

Significant Developments During the Year

Tranche 3 (Loan 3350) is a loan/grant of $425.00 million from Ordinary Capital Resources (OCR), which was approved on 8 December 2015. Progress: Not yet effective Scope Change: Not yet effective Undertaking and Covenants: Not yet effective

1 DED = Detailed Engineering Design.

177

Page 178: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

42466014

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title Skills for Employment Investment Program Project No. 42466-014

Country/Regional

Bangladesh Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

19 May 2014 30 Jun 2021 N/A

Division SAHS

MFF Amount ($ million)

350.00Source ADF

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the Skills for Employment Investment Program for an aggregate amount not exceeding $350.00 million from ADB’s ADF on 19 May 2014. Impact: increased income and productivity of the working population aged 15 years and over. Outcome: increased employment in priority sectors and skills for males and females. Outputs: market responsive inclusive skills training delivered quality assurance system strengthened institutions strengthened effective program management Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 1

Approved Tranche Amount to Date

100.00

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

178

Page 179: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche Title Skills for Employment Investment Program - Tranche 1 Project No. 42466-015

Country/Regional Bangladesh Loan/Grant No.

0391, 3131

Project Officer Rudi Louis Hendrikus Van Dael Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

03 Jun 2014 30 Jun 2018 N/A

Division SAHS

Tranche Amount($ million)

100.00 Source ADF

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/42466-015/main

1 DED = Detailed Engineering Design.

179

Page 180: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Skills for Employment Investment Program - Tranche 1, not exceeding the aggregate amount of $100.00 million on 3 June 2014. Impact: increased employment in priority sectors and skills for males and females [NSDP 2 & 3]. Outcome: increased inclusive access to skills training in priority sectors. Outputs: Market-responsive inclusive skills training delivered, Quality assurance system strengthened, Institutions strengthened, and Effective program management Implementation Arrangements: The executing agency is the Finance Division of the Ministry of Finance (MOF) and the Skills Development Coordination and Monitoring Unit (SDCMU) under the Finance Division will be the implementing agency. Other implementing agencies for tranche 1 include the Directorate of Technical Education under the Ministry of Education, Bureau of Manpower, Employment and Training under the Ministry of Expatriates Welfare and Overseas Employment, 3 Bangladesh Institute of Technical Assistance Centers under the Ministry of Industries, Bangladesh Technical Education Board, National Skill Development Council Secretariat (NSDC-S), and Bangladesh Bank Small and Medium Enterprise (SME) Department. A Skill Development Implementation Committee headed by the Executive Project Director will include representatives from all the implementing agencies and 9 industry associations in 6 priority sectors and Palli-Karma Sahayak Foundation (PKSF) to provide a common forum to discuss implementation issues and to make joint efforts to resolve problems emanating from implementation. Implementation Status: The SDCMU has signed contracts with 6 industry associations, and memoranda of understanding with the BB-SME Department, PKSF and 32 public training institutions. Of the total enrolment target of 228,615, there are 20,096 enrolled as of 25 November 2015 in public training institutions and 6 industry associations (4,568 of which are female), 5,983 have been certified and 2,350 have either been placed in jobs or have been self-employed.

1 DED = Detailed Engineering Design.

180

Page 181: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in Scope

Category Date Approved Proposed Change

Minor Change 13 Aug 2015 A minor change in implementation arrangement was approved to change the frequency of reimbursement from ADB from quarterly to a monthly basis subject to meeting the threshold of $100,000 for each withdrawal application. Paras. 74, 81 and 84 of the FAM was revised as follows: Para. 74: Subsequent monthly disbursements will be subject to liquidation of previous advance/expenditures in line with the project agreement. Para. 81: For the expenditures of training conducted by different agencies, the SDCMU will request, in accordance with the Loan Disbursement Handbook, reimbursement from ADB primarily on a monthly basis by withdrawal applications and the statement of expenditures which list the progress payments based on the project agreements with the GoB entities and the contracts with the Associations and PKSF. Para. 84: Every month, each agency engaged in training will submit expenditure statement along with bank statement to the Project Director at the SDCMU. Each agency will submit quarterly progress reports and monthly expenditure reports in agreed format.

Minor Change 30 Jun 2015 A minor change in scope and implementation arrangement was approved for the inclusion of a provision on retroactive financing under Schedule 1 of the Grant Agreement, as follows: Withdrawals from the Grant Account may be made for reimbursement of eligible expenditures under the Project before the effective Date, but not earlier than 12 months before the date of this Grant Agreement, subject to a maximum amount equivalent to 20% of the Grant amount.

1 DED = Detailed Engineering Design.

181

Page 182: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

49.69 100.00 9.88 58.40

Significant Developments During the Year

Tranche 1 (Loan 3131) is a loan of $100.00 million from the Asian Development Fund (ADF), which was approved on 3 June 2014 and declared effective on 24 July 2014. Tranche 1 is rated as Potential Problem. Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $49.69 million (100.0%) and $9.88 million (58.4%), respectively. The SDCMU has signed contracts with 6 industry associations, and memoranda of understanding with the BB-SME Department, PKSF and 32 public training institutions. Of the total enrolment target of 228,615, there are 20,096 enrolled as of 25 November 2015 in public training institutions and 6 industry associations (4,568 of which are female), 5,983 have been certified and 2,350 have either been placed in jobs or have been self-employed. Scope Change: There were two (2) minor scope changes for this tranche in 2015. Undertaking and Covenants: There are 15 covenents for Tranche 1. Seven (7) covenants have been complied. Eight (8) are not yet due.

1 DED = Detailed Engineering Design.

182

Page 183: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

43253013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title Karnataka Integrated and Sustainable Water Resources Management Investment Program

Project No. 43253-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

25 Sep 2014 30 Sep 2021 N/A

Division SAER

MFF Amount ($ million)

150.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the Karnataka Integrated and Sustainable Water Resources Management Investment Program for an aggregate amount not exceeding $150.00 million from ADB’s OCR on 25 September 2014. Impact: improved sustainable water security in selected river basins in Karnataka. Outcome: integrated water resources management successfully implemented in selected river basins in Karnataka. Outputs: State and basin institutions strengthened for IWRM Irrigation system infrastructure and management modernized Program management systems operational Significant Developments of the Facility: There are no significant developments of the facility including major changes to roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 2

Approved Tranche Amount to Date

106.00

Facility Change in Scope

Category Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

183

Page 184: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleKarnataka Integrated and Sustainable Water Resources Management Investment Program - Project 1

Project No. 43253-023

Country/Regional India Loan/Grant No.

3172

Project Officer Lance Gore Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

17 Oct 2014 31 Mar 2019 N/A

Division SAER

Tranche Amount($ million)

31.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/43253-023/main

1 DED = Detailed Engineering Design.

184

Page 185: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Karnataka Integrated and Sustainable Water Resources Management Investment Program - Project 1, not exceeding the aggregate amount of $31.00 million on 17 October 2014.

Impact: integrated water resources management in selected river basins in Karnataka successfully implemented.

Outcome: river basin plan for Krishna-8 (K-8) subbasin successfully implemented.

Outputs: State and basin institutions strengthened for IWRM. Irrigation system infrastructure and management modernized Project and management systems operational

Implementation Arrangements: The executing agency (EA) is the State of Karnataka acting through the Karnataka Neeravari Nigam Limited (KNNL). The EA is responsible for execution of the entire program, coordination of all activities particularly those requiring other government ministerial actions, and disbursement support. A program management unit was established within KNNL with Managing Director, KNNL as the program director. A project implementation office (PIO) for Output 1 (state and basin institutions strengthened for IWRM) was established within the Advanced Centre for Integrated Water Resources Management (AC-IWRM). For modernizing irrigation system infrastructure and management (Output 2), each irrigation subproject will have a dedicated PIO based within the existing irrigation subdivision. Command area development authorities (CADAs) will provide tertiary and field system support for implementation of the program as part of the PIO.

Implementation Status: The project support consultants were mobilized in December 2015 and the contract for the supply and installation of flow measurement and telemetry system was signed on 23 November 2015.The civil works contract for the Gondi canal rehabilitation is expected to be awarded in January 2016. Director, AC-IWRM was mobilized in September 2015 and the Chief Technical Advisor, AC-IWRM started work in August 2015. Recruitment of two other international consultants (river basin modeler and hydrologist) is underway. AC-IWRM is developing a program on IWRM certification in collaboration with the UNESCO-Institute for Water Education.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

185

Page 186: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

5.20 100.00 0.00 0.00

Significant Developments During the Year

Tranche 1 (Loan 3172) is a loan of $31.00 million from Ordinary Capital Resources (OCR), which was approved on 17 October 2014 and declared effective on 13 July 2015. Tranche 1 is rated as Potential Problem.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $5.20 million (100.0%) and $.00 million (.0%), respectively. EA is processing advance payments for the two contracts awarded in late November 2015, and disbursements are expected to start in January 2016.

Scope Change: There were no scope changes for this tranche in 2015.

Undertaking and Covenants: There are 20 covenants for Project 1, 3 of which have been complied with, 12 are being complied with, and 5 are not yet due.

1 DED = Detailed Engineering Design.

186

Page 187: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

43253024

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title Karnataka Integrated Urban Water Management Investment Program

Project No. 43253-024

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

28 Mar 2014 15 Mar 2024 N/A

Division SAUW

MFF Amount ($ million)

150.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the Karnataka Integrated Urban Water Management Investment Program for an aggregate amount not exceeding $150.00 million from ADB’s OCR on 28 March 2014.

Impact: Improved sustainable water security in selected river basins in Karnataka.

Outcome: Improved water resources management in urban areas in selected river basins in Karnataka

Outputs: Expanded and upgraded UWSS infrastructure. Improved water resource planning, monitoring and service delivery. Strengthened operational and administrative capacity of KUIDFC and ULBs

Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 2

Approved Tranche Amount to Date

106.00

Facility Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

187

Page 188: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleKarnataka Integrated Urban Water Management Investment Program - Tranche 1

Project No. 43253-025

Country/Regional India Loan/Grant No.

0399, 3148

Project Officer Norio Saito Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

29 Jul 2014 30 Sep 2019 N/A

Division SAUW

Tranche Amount($ million)

75.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/43253-025/main

Tranche Summary

ADB approved the Karnataka Integrated Urban Water Management Investment Program - Tranche 1, not exceeding the aggregate amount of $75.00 million on 29 July 2014.

Impact: Improved sustainable water security in the Upper Tunga Bhadra subbasin

Outcome: Improved water resources management in selected urban areas of the Upper Tunga Bhadra subbasin

Outputs: Expanded and upgraded UWSS infrastructure in three towns of the Upper Tunga Bhadra subbasin Improved water resource planning, monitoring, and service delivery Strengthened operational and administrative capacity of KUIDFC and ULBs

Implementation Arrangements: The executing agency is the State of Karnataka acting through the Karnataka Urban Infrastructure Development and Finance Corp (KUIDFC). The key implementing agencies are the urban local bodies (ULBs) of Byadagi, Davanagere, and Harihar.

Implementation Status: Three sewerage contracts were awarded in 2015. Works have commenced and physical works are in progress. Remaining one package for sewerage works is in the procurement process. The procurement for water supply works will start in 2016.

1 DED = Detailed Engineering Design.

188

Page 189: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

25.10 100.00 4.06 0.00

Significant Developments During the Year

Tranche 1 (Loan 3148) is a loan of $75.00 million from Ordinary Capital Resources (OCR), which was approved on 29 July 2014 and declared effective on 7 May 2015. Tranche 1 is rated as On Track.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $25.10 million (100.0%) and $4.06 million (.0%), respectively. Three sewerage subprojects awarded in 2015 have made satisfactory progress. Remaining one package for sewerage works is in the procurement process. The procurement for water supply works will start in 2016.

Scope Change: There were no scope changes for this tranche in 2015.

Undertaking and Covenants: The 20 undertakings and 23 covenants are being complied with by the EA. The Auditor's Report, Audited Financial Statement and Audited Project Financial Statement for fiscal year 2015 for Tranche 1 were submitted by the EA and reviewed by ADB on time.

1 DED = Detailed Engineering Design.

189

Page 190: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

43464013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - Himachal Pradesh Clean Energy Transmission Investment Program (Facility Concept)

Project No. 43464-013

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

30 Sep 2011 30 Jun 2018 N/A

Division SAEN

MFF Amount ($ million)

350.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - Himachal Pradesh Clean Energy Transmission Investment Program (Facility Concept) for an aggregate amount not exceeding $350.00 million from ADB’s OCR on 30 September 2011.

Impact: Himachal Pradesh power sector transmits clean energy to end users in Himachal Pradesh and India.

Outcome: HPPTCL has sufficient assets and capacity to support its mandate as the state transmission utility company.

Outputs: New transmission system assets are operational HPPTCL's management capacity enhanced HPPTCL manages implementation of the MFF tranches on time and within budget.

Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 2

Approved Tranche Amount to Date

223.00

Facility Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

190

Page 191: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

191

Page 192: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleMFF-Himachal Pradesh Clean Energy Transmission Investment Program - Tranche 1

Project No. 43464-023

Country/Regional India Loan/Grant No.

2794

Project Officer Takeshi Shiihara Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

18 Oct 2011 30 Jun 2018 N/A

Division SAEN

Tranche Amount($ million)

113.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/43464-023/main

Tranche Summary

ADB approved the MFF-Himachal Pradesh Clean Energy Transmission Investment Program - Tranche 1, not exceeding the aggregate amount of $113.00 million on 18 October 2011.

Impact: HPPTL has sufficient assets and capacity to support its mandate as the state transmission utility company

Outcome: HPPTL has increased its asset base and its capacity.

Outputs: New Transmission system assets are operational HPPTCL's management capacity enhanced

Implementation Arrangements: HPPTCL will be the executing agency as well as the implementing agency for the investment program.

Implementation Status: For Loan 2794, which includes 3 substation and 1 transmission line projects, all civil work contracts have been awarded totaling $85 million. 75% of the loan has been utilized.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

192

Page 193: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

83.34 94.64 35.16 100.00

Significant Developments During the Year

Tranche 1 (Loan 2794) is a loan of $113.00 million from Ordinary Capital Resources (OCR), which was approved on 18 October 2011 and declared effective on 19 January 2012. Tranche 1 is rated as On Track.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $83.34 million (94.6%) and $35.16 million (100.0%), respectively. The progress of civil works was previously delayed due to forest clearance issues, etc. which have been largely resolved. Currently, works have been progressing and there are no major issues. The administrative capacities of the EA are being gradually strengthened through the engagement of 4 individual consultants (e.g. financial expert and project planning engineer), utilizing the earmarked budget under the loan.

Scope Change: There were no scope changes for this tranche in 2015.

Undertaking and Covenants: Out of 25 covenants, 6 are complied with, 16 are being complied with and 3 are not yet due.

1 DED = Detailed Engineering Design.

193

Page 194: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche TitleHimachal Pradesh Clean Energy Transmission Investment Program - Tranche 2

Project No. 43464-026

Country/Regional India Loan/Grant No.

3001

Project Officer Takeshi Shiihara Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

07 May 2013 30 Jun 2018 N/A

Division SAEN

Tranche Amount($ million)

110.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/43464-026/main

Tranche Summary

ADB approved the Himachal Pradesh Clean Energy Transmission Investment Program - Tranche 2, not exceeding the aggregate amount of $110.00 million on 7 May 2013.

Impact: Increased electricity transmission in Himachal Pradesh.

Outcome: Improved capacity of HPPTCL to transmit electricity from hydropower generation sources within and outside of Himachal Pradesh.

Outputs: New Transmission system assets are operational Enterprise resource planning (ERP) system, phase II and additional IT hardware installed in HPPTCL corporate facilities and are operational Capacity of HPPTCL personnel on project management, and transmission utility operations improved

Implementation Arrangements: HPPTCL will be the executing agency as well as the implementing agency for the investment program, responsible for supervising subproject implementation and monitoring of subproject operational performance.

Implementation Status: For Loan 3001, which includes 8 substation and 6 transmission line projects, despite the delay in contract awards they had experienced, the level of contract awards has been picking up. The total contracted amount now stands at $70 million, which is 65% of the loan utilization rate.

1 DED = Detailed Engineering Design.

194

Page 195: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

70.31 100.00 16.51 97.14

Significant Developments During the Year

Tranche 2 (Loan 3001) is a loan of $110.00 million from Ordinary Capital Resources (OCR), which was approved on 07 May 2013 and declared effective on 13 November 2014. Tranche 2 is rated as On Track.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $70.31 million (100.0%) and $16.51 million (97.1%), respectively. There are still some contract packages where the EA has not been granted forest clearance so the progress of civil works has been stalled. The EA has been, overall, making good progress in the execution of civil works.

Scope Change: There were no scope changes for this tranche in 2015.

Undertaking and Covenants: Out of 24 covenants, 5 are complied with, 16 are being complied with and 3 are not yet due.

1 DED = Detailed Engineering Design.

195

Page 196: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

43467014

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title Madhya Pradesh Energy Efficiency Improvement Investment Program (Facility Concept)

Project No. 43467-014

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

07 Jul 2011 28 Feb 2015 28 Feb 2018

Division SAEN

MFF Amount ($ million)

400.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the Madhya Pradesh Energy Efficiency Improvement Investment Program (Facility Concept) for an aggregate amount not exceeding $400.00 million from ADB’s OCR on 7 July 2011.

Impact: Continuous and higher quality supply of electricity to rural households in Madhya Pradesh

Outcome: Improved operational efficiency of electricity distribution in rural areas of Madhya Pradesh

Outputs: 1. Separated power supply to agricultural pumps and households and installed high-voltage distributionsystem (HVDS) 2. Improved upstream 33kV systems3. Installed meters and new household connections4. Access to business development services improved for microenterprises headed by women5. Built capacity of women's self help groups to provide energy-related microenterprise developmentservices and gender sensitive user awareness and energy conservation

Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 2

Approved Tranche Amount to Date

400.00

Facility Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

196

Page 197: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

197

Page 198: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleMadhya Pradesh Energy Efficiency Improvement Investment Program - Tranche 1

Project No. 43467-015

Country/Regional India Loan/Grant No.

2764

Project Officer Jyotirmoy Banerjee Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

27 Jul 2011 28 Feb 2015 28 Feb 2018

Division INRM

Tranche Amount($ million)

200.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/43467-015/main

1 DED = Detailed Engineering Design.

198

Page 199: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Madhya Pradesh Energy Efficiency Improvement Investment Program - Tranche 1, not exceeding the aggregate amount of $200.00 million on 15 July 2011.

Impact: Continuous and higher quality supply of electricity to rural households in Madhya Pradesh

Outcome: Improved operational efficiency of electricity distribution in rural areas of Madhya Pradesh, benefiting 1.4 million households

Outputs: 1. Separate feeders for agricultural pumps and households and installed High Voltage DistributionSystems (HVDS) 2. Installed meters, new household connections.3. Access to business development services improved for women-headed microenterprises4. Built capacity of women self help groups

Implementation Arrangements: The State of Madhya Pradesh and the following three electricity distribution companies will serve as the Executing Agencies (EAs): (i) The Madhya Pradesh Madhya Kshetra Vidut Vitaran Company Limited (Central Zone Distribution Company/DISCOM-C); (ii) The Madhya Pradesh Poorva Kshetra Vidut Vitaran Company Limited (Eastern Zone Distribution Company/DISCOM-E); and (iii) The Madhya Pradesh Paschim Kshetra Vidut Vitaran Company Limited (Western Zone Distribution Company/DISCOM-W).

Implementation Status: DISCOM-C, DISCOM-E and DISCOM-W have each established their Project Management Units (PMUs). Each PMU has been fully staffed is carrying out implementation satisfactorily. Physical progress of the project is 56%.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

1 DED = Detailed Engineering Design.

199

Page 200: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

166.88 83.44 85.70 95.91

Significant Developments During the Year

Tranche 1 (Loan 2764) is a loan of $200.00 million from Ordinary Capital Resources (OCR), which was approved on 15 July 2011 and declared effective on 19 October 2011. Tranche 1 is rated as On Track.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $166.88 million (83.4%) and $85.70 million (95.9%), respectively. Terminated contracts are under various stages of procurement, and contracts of $29 million have been awarded. Following Outputs 3 and 4 have been achieved:access to business development services improved for women-headed microenterprises; and built capacity of women self help groups. DISCOM-wise physical progress is as follows: DISCOM-C, 58%; DISCOM-E, 45%; and DISCOM-W, 66%.

Scope Change: There were no scope changes for this tranche in 2015.

Undertaking and Covenants: Of the 30 covenants, 20 have been complied with, while 10 are currently being complied with.

1 DED = Detailed Engineering Design.

200

Page 201: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche TitleMadhya Pradesh Energy Efficiency Improvement Investment Program - Tranche 2

Project No. 43467-016

Country/Regional India Loan/Grant No.

2830

Project Officer Jyotirmoy Banerjee Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

15 Dec 2011 28 Feb 2015 28 Feb 2018

Division INRM

Tranche Amount($ million)

200.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/43467-016/main

Tranche Summary

ADB approved the Madhya Pradesh Energy Efficiency Improvement Investment Program - Tranche 2, not exceeding the aggregate amount of $200.00 million on 14 December 2011.

Impact: Improved operational efficiency of electricity distribution in rural areas of Madhya Pradesh

Outcome: Efficient electricity distribution expanded in 15 project districts in Madhya Pradesh

Outputs: 1. Separate feeders for agricultural pumps and households2. Installed High Voltage Distribution Systems (HVDS)3. Installed meters and improved supply quality4. Strengthened 33 kV network

Implementation Arrangements: The State of Madhya Pradesh and the following three electricity distribution companies will serve as the Executing Agencies (EAs): The Madhya Pradesh Madhya Kshetra Vidut Vitaran Company Limited (Central Zone Distribution Company/DISCOM-C); The Madhya Pradesh Poorva Kshetra Vidut Vitaran Company Limited (Eastern Zone Distribution Company/DISCOM-E); and The Madhya Pradesh Paschim Kshetra Vidut Vitaran Company Limited (Western Zone Distribution Company/DISCOM-W).

Implementation Status: DISCOM-C, DISCOM-E and DISCOM-W have each established their Project Management Units (PMUs). Each PMU has been fully staffed is carrying out implementation satisfactorily. Physical progress of the project is 57%.

1 DED = Detailed Engineering Design.

201

Page 202: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

175.88 87.94 88.06 96.67

Significant Developments During the Year

Tranche 2 (Loan 2830) is a loan of $200.00 million from Ordinary Capital Resources (OCR), which was signed on 27 February 2012 and declared effective on 9 May 2012. Tranche 2 is rated as On Track.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $175.88 million (87.9%) and $88.06 million (96.7%), respectively. Terminated contracts are under various stages of procurement and contract of $18.4 million have been awarded. DISCOM-wise physical progress is as follows: DISCOM-C, 35%; DISCOM-E, 58%; and DISCOM-W, 77%.

Scope Change: There were no scope changes for this tranche in 2015.

Undertaking and Covenants: Of the 30 covenants, 21 have been complied with, while 9 are currently being complied with.

1 DED = Detailed Engineering Design.

202

Page 203: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

44167013

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title Flood and Riverbank Erosion Risk Management Investment Program

Project No. 44167-013

Country/Regional

Bangladesh Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

26 Jun 2014 30 Jun 2023 N/A

Division SAER

MFF Amount ($ million)

255.00Source ADF

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the Flood and Riverbank Erosion Risk Management Investment Program for an aggregate amount not exceeding $255.00 million from ADB’s ADF on 26 June 2014.

Impact: improved livelihoods in the project area.

Outcome: reduced flood and riverbank erosion risks in the subproject areas.

Outputs: Flood and riverbank erosion risk mitigation functioning at priority reaches Strengthened institutional systems for flood and riverbank erosion risk management, and Operational program management systems

Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 1

Approved Tranche Amount to Date

65.00

Facility Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

203

Page 204: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleFlood and Riverbank Erosion Risk Management Investment Program - Project 1

Project No. 44167-014

Country/Regional Bangladesh Loan/Grant No.

0396, 3138

Project Officer Natsuko Totsuka Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

03 Jul 2014 30 Jun 2019 N/A

Division SAER

Tranche Amount($ million)

65.00 Source ADF

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/44167-014/main

1 DED = Detailed Engineering Design.

204

Page 205: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Flood and Riverbank Erosion Risk Management Investment Program - Project 1, not exceeding the aggregate amount of $65.00 million on 3 July 2014.

Impact: improved livelihoods in the project area.

Outcome: reduced flood and riverbank erosion risks in the subproject areas.

Outputs: Flood and riverbank erosion risk mitigation functioning at priority reaches Strengthened institutional systems for flood and riverbank erosion risk management Operational program management system

Implementation Arrangements: The executing agency is the Bangladesh Water Development Board (BWDB) under the Ministry of Water Resources. A project management office was established within BWDB to manage project implementation, which is undertaken by subproject management offices in each subproject area. BWDB has overall responsibility for executing the program/project and ensuring achievement of project objectives. The Department of Disaster Management under the Ministry of Disaster Management and Relief serves as the implementing agency for the community-based flood risk management subcomponent.

Implementation Status: The progress of ongoing activities is satisfactory, despite delays in the commencement of works and the mobilization of the institutional strengthening and project management consultant team. Riverbank protection works at the most critical site are ongoing, and bank protection works at other sites are expected to be started in January 2016. All remaining major civil works packages are also expected to be started within 2016.

Tranche Change in Scope

Category Date Approved Proposed Change

Minor Change 04 Dec 2015 Increase in the imprest advance ceiling from $6.5 million to $14.7 million. This was for enabling timely payments during the periods of active major civil works that started in November 2015.

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

1 DED = Detailed Engineering Design.

205

Page 206: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

32.14 88.25 18.05 100.00

Significant Developments During the Year

Tranche 1 (Loan 3138, Grant 0396) is a loan of $65.00 million from the Asian Development Fund (ADF) and a grant of $15.30 million from the Government of Netherlands, which was approved on 03 July 2014 and declared effective on 17 September 2014. Tranche 1 is rated as On Track.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $32.14 million (88.3%) and $18.05 million (100.0%), respectively. Major civil works for riverbank protections at one site started in November 2015. Procurement of three works packages for two other sites was conducted in 2015, and the works are expected to be started in January 2016. The institutional strengthening and project management consultant team mobilized in 2015.

Scope Change: There was a minor change for this tranche in 2015.

Undertaking and Covenants: There are 35 covenants: 3 were complied with, 21 are being complied with, and 11 are not yet due.

1 DED = Detailed Engineering Design.

206

Page 207: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

44213015

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title MFF - Secondary Education Sector Investment Program (Facility Concept)

Project No. 44213-015

Country/Regional

Bangladesh Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

27 Sep 2013 30 Jun 2023 N/A

Division SAHS

MFF Amount ($ million)

500.00Source ADF

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the MFF - Secondary Education Sector Investment Program (Facility Concept) for an aggregate amount not exceeding $500.00 million from ADB’s ADF on 27 September 2013.

Impact: Increased employability of secondary education graduates

Outcome: A more efficient and equitable and higher-quality secondary education system

Outputs: Enhanced quality and relevance of secondary education More equitable access and better retention Strengthened secondary education management and governance

Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 2

Approved Tranche Amount to Date

275.00

Facility Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

207

Page 208: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleSecondary Education Sector Investment Program - Tranche 1

Project No. 44213-016

Country/Regional Bangladesh Loan/Grant No.

3047

Project Officer Eisuke Tajima Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

21 Oct 2013 31 Dec 2017 N/A

Division SAHS

Tranche Amount($ million)

90.00 Source ADF

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/44213-016/main

1 DED = Detailed Engineering Design.

208

Page 209: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Secondary Education Sector Investment Program - Tranche 1, not exceeding the aggregate amount of $90.00 million on 21 October 2013.

Impact: A more efficient and equitable and higher-quality secondary education system

Outcome: Improved inclusive participation in secondary education

Outputs: Enhanced quality and relevance of secondary education More equitable access and better retention Strengthened secondary education management and governance

Implementation Arrangements: The executing agency is the Ministry of Education (MOE) and the Directorate of Secondary and Higher Education (DSHE) is key implementing agency. Other MOE agencies involved in secondary education will be co-implementing agencies. An interministerial sector program steering committee led by the MOE Secretary will oversee implementation, approve annual operation plans, review verification of disbursement linked indicator (DLI) achievement, and ensure compliance with fiduciary oversight arrangements. A sector program implementation committee led by the DSHE Director General will coordinate implementation by all agencies, review implementation progress, and recommend approval of annual operation plans. A sector program support unit will support DSHE functional units and field offices in daily implementation, preparing annual operation plans, and compiling progress reports including DLI progress and achievement reports.

Implementation Status: Disbursement linked indicators (DLIs) for Years 1, 2 and 3 have been satisfied as shown in the reports on DLI achievement. According to the DLI protocol and the interim financial reports for the corresponding periods, government spending on the SESIP Program Budget Head exceeds ADB contribution for the corresponding period with a total of $100 million (36% of Tranche 1 and 2 of ADB financing) has been disbursed.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

1 DED = Detailed Engineering Design.

209

Page 210: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

80.00 100.00 80.00 100.00

Significant Developments During the Year

Tranche 1 (Loan 3047) is a loan of $90.00 million from the Asian Development Fund (ADF), which was approved on 21 October 2013 and declared effective on 6 December 2013. Tranche 1 is rated as On Track.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $80.00 million (100.0%) and $80.00 million (100.0%), respectively. An electronic government procurement (EGP) initiative was successfully introduced in the Ministry of Education (MOE) for SESIP implementation. About 340 staff in MOE, Directorate of Secondary and Higher Education (DSHE), and co-implementing agencies were trained, and full operationalization of electronic procurement is planned in 2015-2017, along with the Procurement Capacity Development Plan under MOE institutions. Other developments include increased reliance on an integrated budgeting and accounting system-generated financial reports, which has improved financial reporting and internal controls, and establishment of a new Procurement and Finance Wing in DSHE. Joint Sector Review of the secondary education sector took place with strong government ownership. The government's SWAp road map was re-confirmed. Supported by the National Education Policy, MOE has committed to implement SESIP to achieve the secondary education sector road map (2013-2023) targets.

Scope Change: There were no scope changes for this tranche in 2015.

Undertaking and Covenants: There are 18 covenants for Tranche 1. 16 covenants have been complied with two (2) not yet due.

1 DED = Detailed Engineering Design.

210

Page 211: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche TitleSecondary Education Sector Investment Program - Tranche 2

Project No. 44213-017

Country/Regional Bangladesh Loan/Grant No.

3320

Project Officer Eisuke Tajima Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

20 Nov 2015 31 Dec 2017 N/A

Division SAHS

Tranche Amount($ million)

185.00 Source ADF

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/44213-017/main

1 DED = Detailed Engineering Design.

211

Page 212: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Secondary Education Sector Investment Program - Tranche 2, not exceeding the aggregate amount of $185.00 million on 20 November 2015.

Impact: a more efficient, equitable, and higher quality secondary education system (National Education Policy 2010, Secondary Education Sector Roadmap 2013-2023).

Outcome: inclusive participation in secondary education improved.

Outputs: Quality and relevance of secondary education enhanced Equitable access and retention of secondary education increased Secondary education management and governance strengthened

Implementation Arrangements: The executing agency is the Ministry of Education (MOE) and the Directorate of Secondary and Higher Education (DSHE) is key implementing agency. Other MOE agencies involved in secondary education will be co-implementing agencies. An interministerial sector program steering committee led by the MOE Secretary will oversee implementation, approve annual operation plans, review verification of disbursement linked indicator (DLI) achievement, and ensure compliance with fiduciary oversight arrangements. A sector program implementation committee led by the DSHE Director General will coordinate implementation by all agencies, review implementation progress, and recommend approval of annual operation plans. A sector program support unit will support DSHE functional units and field offices in daily implementation, preparing annual operation plans, and compiling progress reports including DLI progress and achievement reports.

Implementation Status: All the disbursement linked indicators (DLIs) for Year 3 have been satisfied as shown in the report on DLI achievement. According to the DLI protocol and the interim financial reports for the corresponding periods, government spending on the SESIP Program Budget Head exceeds ADB contribution for the corresponding period. Maximum amount allocated to Year 3 has been disbursed.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

1 DED = Detailed Engineering Design.

212

Page 213: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

20.00 100.00 20.00 100.00

Significant Developments During the Year

Tranche 2 (Loan 3320) is a loan of $185.00 million from the Asian Development Fund (ADF), which was approved on 20 November 2015 and declared effective on 15 December 2015. Tranche 2 is rated as On Track.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $20.00 million (100.0%) and $20.00 million (100.0%), respectively. Priority procurement packages for the tranche have been identified. Bidding documents are being prepared. Consultations for the development of the National Curriculum Policy Framework have started.

Scope Change: There were no scope changes for this tranche in 2015.

Undertaking and Covenants: There are 18 covenants for Tranche 2. 16 covenants have been complied with two (2) not yet due.

1 DED = Detailed Engineering Design.

213

Page 214: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

45148004

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title Greater Colombo Water and Wastewater Management Improvement Investment Program (Facility Concept)

Project No. 45148-004

Country/Regional

Sri Lanka Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

25 Oct 2012 31 Dec 2020 N/A

Division SAUW

MFF Amount ($ million)

300.00Source OCR

ADF

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the Greater Colombo Water and Wastewater Management Improvement Investment Program (Facility Concept) for an aggregate amount not exceeding $300.00 million from ADB’s ADF, OCR on 25 October 2012.

Impact: Improved urban environment and quality of life for the residents in Greater Colombo

Outcome: Improved water supply and wastewater service and management in Greater Colombo

Outputs: 1. Rehabilitated and expanded water supply system and reduced NRW in Colombo city2. Improved wastewater Services in Greater Colombo3. Reformed institution and capacity building for water supply and wastewater service4. Project management system in place

Significant Developments of the Facility: There was a minor scope change for the Facility in 2015.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 3

Approved Tranche Amount to Date

300.00

Facility Change in ScopeCategory Date Proposed Change

Minor Change 08 Dec 2015 Minor change was approved on 8 December 2015 to reduce the physical scope of the wastewater investment component and revise the financing plan to reflect the proposed European Investment Bank parallel cofinancing.

214

Page 215: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

215

Page 216: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleGreater Colombo Water and Wastewater Management Improvement Investment Program - Tranche 1

Project No. 45148-005

Country/Regional Sri Lanka Loan/Grant No.

2947, 2948

Project Officer Kamal Dahanayake Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

16 Nov 2012 30 Jun 2017 N/A

Division SLRM

Tranche Amount($ million)

84.00 Source ADFOCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

27.00

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/45148-005/main

1 DED = Detailed Engineering Design.

216

Page 217: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Greater Colombo Water and Wastewater Management Improvement Investment Program - Tranche 1, not exceeding the aggregate amount of $84.00 million on 22 November 2012.

Impact: Improved water supply and wastewater service and management in Greater Colombo

Outcome: Improved efficiency and financial sustainability of water supply services in Colombo City

Outputs: 1. Rehabilitated water supply network and reduced NRW in Colombo City2. Strengthened institutional structure and capacity of NWSDB.3. Project 1 successfully managed and implemented

Implementation Arrangements: The Ministry name has changed to Ministry of City Planning and Water Supply in 21 September 2015. The implementing agency is the National Water Supply Drainage Board (NWSDB), through its Project Management Unit (PMU).The National Steering Committee (NSC) is established to oversee the progress and implementation. The NSC is chaired by the Secretary of the Ministry of City Planning and Water Supply and representatives from National Water Supply and Drainage Board , External Resources Department, National Planning Department and other relevant agencies participate. The implementation arrangements are described in detail in the Facility Administration Manual (FAM) for the Investment Program.

Implementation Status: There are two major civil works packages under Tranche 1 - (i) system rehabilitation in Colombo North area package (ICB 1) and (ii) system rehabilitation in Colombo East area package (ICB 2). Both contracts have been awarded and construction works are in progress. ICB 1 physical progress is 16% and ICB 2 physical progress is 2%. Design and supervision consultant recruitment has been delayed. After cancellation of the procurement process for selection of design and supervision consultants in 2014, new recruitment process started in 2015. Consultants are planned to be mobilized in June 2016. Project Management Unit (PMU) is fully established and staffed. As recruitment of design and supervision consultants has been delayed, the project has recruited 4 individual consultants. Three consultants have been recruited by the Executing Agency (EA). ADB has recruited one consultant. Two National Steering Committee meetings were held during the year, and quarterly progress reports have been submitted. There is a need to extend the loan period due to the delay in awarding the two (2) ICB contracts. EA will submit extension request to ADB in 2016.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

217

Page 218: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

65.76 100.00 17.71 100.00

Significant Developments During the Year

Tranche 1 (Loans 2947, 2948) is a loan of $84.00 million from the Asian Development Fund (ADF) and Ordinary Capital Resources (OCR) which was approved on 22 November 2012 and declared effective on 25 September 2013. Tranche 1 is rated as On Track.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $65.76 million (100.0%) and $17.71 million (100.0%), respectively. Overall physical progress is 8%. Progress of non-physical activities under the Gender Action Plan and Public Awareness Campaign has been delayed due to delay in recruitment of consultancy firms to implement this component. PMU is currently managing these programs through PMU staff.ICB 02 was awarded on 21 April 2015. ADB approved submission 2 for Media Consultants package on 06 November 2015.

Scope Change: There were no scope changes for this tranche in 2015.

Undertaking and Covenants: There are 24 covenants in this tranche. 21 covenants have been complied with. Balance 3 covenants are not yet due.

1 DED = Detailed Engineering Design.

218

Page 219: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche TitleGreater Colombo Water and Wastewater Management Improvement Investment Program - Tranche 2

Project No. 45148-007

Country/Regional Sri Lanka Loan/Grant No.

3029, 3030, 8282

Project Officer Kamal Dahanayake Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

26 Sep 2013 30 Jun 2019 N/A

Division SLRM

Tranche Amount($ million)

88.00 Source ADFOCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

11.00

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/45148-007/main

1 DED = Detailed Engineering Design.

219

Page 220: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Greater Colombo Water and Wastewater Management Improvement Investment Program - Tranche 2, not exceeding the aggregate amount of $88.00 million on 26 September 2013.

Impact: Improved water supply and wastewater service and management in Greater Colombo

Outcome: Improved system, efficiency and financial sustainability of water supply and wastewater services in Greater Colombo

Outputs: 1. Rehabilitated and expanded water supply system, and reduced NRW, in Greater Colombo2. Completed designs and improved preparedness for wastewater investments3. Strengthened institutional structure and capacity of service providers4. Project 2 successfully managed and implemented

Implementation Arrangements: The executing agency is the Ministry of Urban Development, Water Supply and Drainage.The implementing agency is National Water Supply Drainage Board (NWSDB), through its Project Management Unit (PMU). National Steering Committee (NSC) has been established for the entire implementation period of Greater Colombo Water and Wastewater Management Improvement Investment Program (Investment Program) and also for Tranche 1 and Tranche 2. The NSC is chaired by the Secretary of the Ministry of City Planning and Water Supply and representatives from National Water Supply and Drainage Board , External Resources Department, National Planning Department and other relevant agencies participate. The implementation arrangements are described in detail in the Facility Administration Manual (FAM) for the Investment Program.

Implementation Status: PMU has been established under Tranche 1 and staff recruited fully for tranche 2. Procurement of major civil works contracts is ongoing.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

1 DED = Detailed Engineering Design.

220

Page 221: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

0.30 0.69 0.56 6.94

Significant Developments During the Year

Tranche 2 (Loans 3029, 3030, 8282) is a loan of $88.00 million from the Asian Development Fund (ADF) and Ordinary Capital Resources (OCR), which was approved on 26 September 2013 and declared effective on 23 September 2014. Tranche 2 is rated as Actual Problem.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $.30 million (.7%) and $.56 million (6.9%), respectively. There are two major civil works packages under Tranche 2 - (i) system rehabilitation in Colombo West area package (ICB 3) and (ii) system rehabilitation in Colombo South area package (ICB 4). ICB 3 contract is under technical evaluation. ICB 4 contract technical evaluation has been completed and financial evaluation report has been submitted to ADB for clearance. Both contracts were planned to be awarded in 2015, but as of 31 December 2015, none of the contracts have been awarded. Only one civil work contract of contract value less than $ 1.00 million was awarded in 2015. Overall physical progress of this tranch is 1%. NGO consultancy submission 2 was submitted to ADB and was approved on 18 December 2015. Design and supervision consultants for this tranch will be recruited under Tranche 1.

Scope Change: There were no scope changes for this tranche in 2015.

Undertaking and Covenants: There are 21 covenants in this tranche. 18 covenants have been complied with. Two covenants are not yet due. One covenant is partly complied with.

1 DED = Detailed Engineering Design.

221

Page 222: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 3 UPDATE

Tranche TitleGreater Colombo Water and Wastewater Management Improvement Investment Program (Tranche 3)

Project No. 45148-008

Country/Regional Sri Lanka Loan/Grant No.

3348, 3349

Project Officer Mingyuan Fan Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

08 Dec 2015 31 Dec 2020 N/A

Division SAUW

Tranche Amount($ million)

128.00 Source ADFOCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/45148-008/main

Tranche Summary

ADB approved the Greater Colombo Water and Wastewater Management Improvement Investment Program (Tranche 3), not exceeding the aggregate amount of $128.00 million on 8 December 2015.

Impact: improved water supply and wastewater service and management in Greater Colombo aligned with the Vision for a New Sri Lanka, 2010-2020.

Outcome: improved system efficiency and financial sustainability of water supply and wastewater services in Colombo.

Outputs: Water supply system rehabilitated and expanded, and NRW reduced in northeast part of Colombo city (including funding the financing gap for Project 1) Water supply system rehabilitated and expanded, and NRW reduced in southwest part of Colombo city (including funding the financing gap for Project 2) Wastewater system rehabilitated and expanded in south catchment area of Colombo Secondary wastewater treatment plant constructed in south catchment area of Colombo Institutional structure and capacity of service providers strengthened.

Implementation Arrangements: Not Applicable

Implementation Status: Not Yet Effective

1 DED = Detailed Engineering Design.

222

Page 223: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating

Financial

Contract Awards

Disbursements

Safeguards

Technical

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

0.00 0.00 0.00 0.00

Significant Developments During the Year

1 DED = Detailed Engineering Design.

223

Page 224: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

45224002

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title Rajasthan Renewable Energy Transmission Investment Program (Facility Concept)

Project No. 45224-002

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

26 Sep 2013 31 Dec 2018 N/A

Division SAEN

MFF Amount ($ million)

300.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the Rajasthan Renewable Energy Transmission Investment Program (Facility Concept) for an aggregate amount not exceeding $300.00 million from ADB’s OCR on 26 September 2013.

Impact: Accelerated development of renewable energy sources in Rajasthan and India

Outcome: Cleaner electricity mix with more efficient and effective generation and transmission system achieved

Outputs: 1. Bulk power transmission system in Rajasthan expanded2. Institutional capacity for renewable energy parks and transmission system developed.

Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 1

Approved Tranche Amount to Date

62.00

Facility Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

224

Page 225: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleRajasthan Renewable Energy Transmission Investment Program - Tranche 1

Project No. 45224-003

Country/Regional India Loan/Grant No.

3052, 8275

Project Officer Vallabha Karbar Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

22 Oct 2013 31 Dec 2016 N/A

Division SAEN

Tranche Amount($ million)

62.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/45224-003/main

1 DED = Detailed Engineering Design.

225

Page 226: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Rajasthan Renewable Energy Transmission Investment Program - Tranche 1, not exceeding the aggregate amount of $62.00 million on 22 October 2013.

Impact: Accelerated development of renewable energy sources in Rajasthan/India.

Outcome: Cleaner electricity mix with more efficient and effective generation and transmission system

Outputs: 1. Bulk power transmission system in Rajasthan expanded.2. Institutional capacity for renewable energy parks and transmission system developed.

Implementation Arrangements: Rajasthan Rajya Vidyut Prasaran Nigam Limited (RRVPNL), the state transmission licensee in Rajasthan, and the Energy Department of Rajasthan will be the executing agencies for the investment program. Rajasthan Renewable Energy Corporation (RREC), the state government nodal agency responsible for developing renewable energy will coordinate with the state government to provide the necessary land for power project developers. RRVPNL has the capacity to execute and monitor the implementation of the investment program-financed transmission projects. This capacity is underpinned by the establishment of a dedicated project management unit at RRVPNL since 2012 for design, supervision, and procurement. Project implementation will be handled by RRVPNL s regional office in Jodhpur, Rajasthan. Private sector investment proposals and the related bidding process will be handled by a committee of secretaries from the government, supported by RREC. Project management, preparatory work for future subprojects, and implementation support will be financed by the Rajasthan government.

Implementation Status: Last Review Mission was on 22-24 December 2015. Project Management Unit indicated that Project may need an extension of the loan by 6-9 months to complete ICB 1 and ICB 2. They will submit formal request to DEA and ADB.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

1 DED = Detailed Engineering Design.

226

Page 227: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

73.17 89.84 9.30 45.06

Significant Developments During the Year

Tranche 1 (Loan 3052) is a loan of $62.00 million from Ordinary Capital Resources (OCR), which was approved on 22 October 2013 and declared effective on 06 November 2014. Tranche 1 is rated as Potential Problem.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $73.17 million (89.8%) and $9.30 million (45.1%), respectively. Out of 7 procurement packages, 4 contracts have been signed while 3 contracts have been awarded and awaiting signing.

Scope Change: There were no scope changes for this tranche in 2015.

Undertaking and Covenants: Loan covenants are being complied with, some are partly complied with, and there are some that are not yet due.

1 DED = Detailed Engineering Design.

227

Page 228: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

46268001

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title Clean Energy Finance Investment Program Project No. 46268-001

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

30 Oct 2014 N/A N/A

Division SAPF

MFF Amount ($ million)

500.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the Clean Energy Finance Investment Program for an aggregate amount not exceeding $500.00 million from ADB’s OCR on 30 October 2014.

Impact: increased renewable energy infrastructure.

Outcome: facilitated investment in renewable energy.

Outputs: Enhanced availability of long-term financing to support renewable energy projects Improved institutional capacity of IREDA

Significant Developments of the Facility: Not Yet Effective

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 1

Approved Tranche Amount to Date

200.00

Facility Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

N/A

228

Page 229: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche Title Clean Energy Finance Investment Program - Tranche 1 Project No. 46268-002

Country/Regional India Loan/Grant No.

3186

Project Officer Anqian Huang Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

17 Nov 2014 30 Apr 2019 N/A

Division SAPF

Tranche Amount($ million)

200.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/46268-002/main

Tranche Summary

ADB approved the Clean Energy Finance Investment Program - Tranche 1, not exceeding the aggregate amount of $200.00 million on 17 November 2014.

Impact: increased renewable energy infrastructure.

Outcome: Facilitated investment in renewable energy.

Outputs: Enhanced availability of long-term financing to support renewable energy projects. Improved institutional capacity of IREDA.

Implementation Arrangements: Not Applicable

Implementation Status: Not Yet Effective

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

229

Page 230: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating

Financial

Contract Awards

Disbursements

Safeguards

Technical

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

0.00 0.00 0.00 0.00

Significant Developments During the Year

1 DED = Detailed Engineering Design.

230

Page 231: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

47037003

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title Green Power Development and Energy Efficiency Improvement Investment Program

Project No. 47037-003

Country/Regional

Sri Lanka Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

15 Jul 2014 31 Mar 2021 N/A

Division SAEN

MFF Amount ($ million)

300.00Source OCR

ADF

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the Green Power Development and Energy Efficiency Improvement Investment Program for an aggregate amount not exceeding $300.00 million from ADB’s ADF, OCR on 15 July 2014.

Impact: increased access to clean and reliable power supply.

Outcome: enhanced clean power generation, system efficiency and reliability.

Outputs: Hydropower generation developed and connected to the grid in the Central Province Transmission infrastructure enhanced Efficiency of medium voltage network improved Demand-side management for energy efficiency improved Capacity development support provided to Ceylon Electricity Board.

Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 1

Approved Tranche Amount to Date

150.00

Facility Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

231

Page 232: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

232

Page 233: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleGreen Power Development and Energy Efficiency Improvement Investment Program - Tranche 1

Project No. 47037-004

Country/Regional Sri Lanka Loan/Grant No.

3146, 3147, 8290

Project Officer Mukhtor Khamudkhanov Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

29 Jul 2014 31 Mar 2020 N/A

Division SAEN

Tranche Amount($ million)

150.00 Source ADFOCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/47037-004/main

1 DED = Detailed Engineering Design.

233

Page 234: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the Green Power Development and Energy Efficiency Improvement Investment Program - Tranche 1, not exceeding the aggregate amount of $150.00 million on 29 July 2014.

Impact: enhanced clean power generation, system efficiency and reliability.

Outcome: increased hydropower generation capacity and transmission and medium voltage network efficiency.

Outputs: Hydropower generation developed in the Central Province. Transmission infrastructure capacity enhanced. Efficiency of medium voltage network improved. Demand-side management for energy efficiency improved. Capacity development support provided to CEB.

Implementation Arrangements: The Ministry of Power and Energy (MOPE) will be the executing agency; Ceylon Electricity Board (CEB) will be the implementing agency. A steering committee, chaired by the MOPE secretary, will guide CEB and review progress and results. CEB will set up project implementation units. The units will oversee procurement, disbursement, financial management and accounting, quality assurance, social, and environmental issues; and will coordinate with the procurement committee, appointed by the cabinet or MOPE, depending on the contract size. Full-time managers will supervise each project component under the MFF.

Implementation Status: A review mission was fielded on 18-25 October 2015. Implementation is ongoing according to schedule. Tranche 1 is on track.

1 DED = Detailed Engineering Design.

234

Page 235: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in Scope

Category Date Approved Proposed Change

Minor Change 15 Dec 2015 It was originally envisaged that for Tranche 1, the OCR loan will finance construction of Moragolla hydropower plant and a portion of transmission infrastructure while ADF loan will finance medium-voltage network efficiency improvement, demand-side management pilots, consulting services, and a portion of transmission infrastructure.

Upon completion of evaluation and contract award approval, it became clear that transmission infrastructure can be financed fully from OCR loan due to a lower contract value as a result of competitive bidding and depreciation of the Sri Lankan Rupee for local currency financing portion.

As such, ADF loan will finance 100% of the medium-voltage network efficiency improvement, demand-side management pilots, consulting services, excluding local taxes and duties while OCR loan will finance 100% of construction of Moragolla hydropower plant and the transmission infrastructure, except Lots B1 and B2 of Package 2 originally proposed for AFD financing, excluding local taxes and duties.

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

25.00 0.00 0.77 0.00

1 DED = Detailed Engineering Design.

235

Page 236: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Significant Developments During the Year

Tranche 1 (Loans 3146, 3147) is a loan of $150.00 million from the Asian Development Fund (ADF), and Ordinary Capital Resources (OCR), which was approved on 29 July 2014 and declared effective on 02 February 2015. Tranche 1 is rated as On Track.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $25.00 million (.0%) and $.77 million (.0%), respectively. As of end-2015, the project's physical progress is 16.91% compared with the elapsed loan period of 25% from loan approval, and 17.74% from loan effectiveness. Out of 4 procurement packages covering 7 ICB lots, 4 ICB lots have been awarded, of which 2 contracts have already been received, and 2 contracts are financed by AFD.

Scope Change: There was a minor scope change for this tranche in 2015.

Undertaking and Covenants: Out of 21 loan covenants, one covenant has been complied with, five are being complied with, and 15 will be complied with.

1 DED = Detailed Engineering Design.

236

Page 237: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

47083001

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title Accelerating Infrastructure Investment Facility in India Project No. 47083-001

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

27 Sep 2013 31 Dec 2016 N/A

Division SAPF

MFF Amount ($ million)

700.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the Accelerating Infrastructure Investment Facility in India for an aggregate amount not exceeding $700.00 million from ADB’s OCR on 27 September 2013.

Impact: Increased availability of infrastructure

Outcome: Facilitated private sector investment in infrastructure PPPs

Outputs: 1. Enhanced availability of long-term finance for PPP projects2. Improved project management

Significant Developments of the Facility: There was a minor scope change for the facility in 2015.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 2

Approved Tranche Amount to Date

700.00

Facility Change in ScopeCategory Date Proposed Change

Minor Change 10 Aug 2015 MFF 0077, as approved in the Recommendation section of the Report and Recommendation of the President, states that interest for loans under the facility will be determined in accordance with ADB's London interbank offered rate (LIBOR)-based lending (LBL) facility. For Tranche 2, GOI requested ADB to disburse at least part of the loan proceeds in local currency. Tranche 2 therefore will

237

Page 238: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Category Date Proposed Change

pilot a new modality under which ADB can, at IIFCL's option, disburse in either Indian Rupees (INR) under ADB's local currency loan product using offshore INR Linker Bonds, or in Dollars under the LBL facility. For an INR disbursement, the applicable interest rate will be the cost of issued INR Linker Bonds (expressed in percentage terms) plus a margin. The minor change of the MFF was proposed to accommodate this financing option.

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

238

Page 239: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleAccelerating Infrastructure Investment Facility in India - Tranche 1

Project No. 47083-002

Country/Regional India Loan/Grant No.

3048

Project Officer Vivek Rao Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

21 Oct 2013 31 Dec 2016 N/A

Division SAPF

Tranche Amount($ million)

400.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/47083-002/main

Tranche Summary

ADB approved the Accelerating Infrastructure Investment Facility in India - Tranche 1, not exceeding the aggregate amount of $400.00 million on 21 October 2013.

Impact: Increased availability of infrastructure

Outcome: Facilitated private sector investment in infrastructure PPPs

Outputs: 1. Enhanced availability of long-term finance for PPP subprojects2. Improved project management

Implementation Arrangements: The India Infrastructure Finance Company Limited (IIFCL) is the executing and implementing agency. IIFCL Board provides policy direction and strategic oversight. The project management unit (PMU) of IIFCL monitors day-to-day implementation of the Facility. The environment and social safeguards management unit (ESMU) is responsible for the compliance with state and national policies and the environmental and social safeguards framework (ESSF) of IIFCL.

Implementation Status: As of 31 December 2015, L3048 has disbursed 91% of the loan amount (around $364.9 million) for 15 PPP subprojects and is expected to be fully disbursed by the first quarter of 2016.

1 DED = Detailed Engineering Design.

239

Page 240: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in Scope

Category Date Approved Proposed Change

Minor Change 01 Dec 2015 Temporary waiver of the 40% of the loan amount take-out limit. IIFCL has committed to undertaking the compensatory transactions by March 2016 to ensure that the take-out limit of 40% is restored.

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

395.63 100.00 364.90 100.00

1 DED = Detailed Engineering Design.

240

Page 241: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Significant Developments During the Year

Tranche 1 (Loan 3048) is a loan of $400.00 million from Ordinary Capital Resources (OCR), which was approved on 21 October 2013 and declared effective on 21 February 2014. Tranche 1 is rated as On Track.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $395.63 million (100.0%) and $364.90 million (100.0%), respectively. The strong disbursements under L3048 contributed to financing: (a) seven greenfield road subprojects, one power transmission project and one solar power generation project; and (ii) takeout financing transactions of 6 subprojects (i.e., three state roads, two solar projects, and the international airport in Hyderabad).

Scope Change: There was a minor scope change for this tranche in 2015.

Undertaking and Covenants: With regard to IIFCL's compliance with conditions set forth in the loan agreement, IIFCL has complied with the quarterly risk management reporting to its board risk committee. With regard to the additional covenants to implement an integrated management information system to replace the current manual systems, IIFCL retained a system provider to manage the implementation but is not satisfied with the vendor 's delivery. Consequently, IIFCL is issuing a fresh request for proposal to retain a new vendor. With this delay, IIFCL is not expected to have an integrated management information system until 2016. In the meantime, it will continue to rely on platforms that offer a mix of automated and manual solutions. While ADB has provided a waiver for this covenant under the first tranche, the covenant has been maintained with a revised completion date in the second tranche. Re-submission of audit requirements for FYE 31 March 2015, IIFCL was reminded to submit the acceptable project level audit report (Statutory Auditor's Opinion) of the statement of subprojects which was due last 30 September 2015.

1 DED = Detailed Engineering Design.

241

Page 242: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche TitleAccelerating Infrastructure Investment Facility in India - Tranche 2

Project No. 47083-003

Country/Regional India Loan/Grant No.

3307

Project Officer Jennifer Romero-Torres Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

30 Oct 2015 31 Mar 2019 N/A

Division SAPF

Tranche Amount($ million)

300.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/47083-003/main

Tranche Summary

ADB approved the Accelerating Infrastructure Investment Facility in India - Tranche 2, not exceeding the aggregate amount of $300.00 million on 30 October 2015.

Impact: Investments in infrastructure increased (Twelfth Five-Year Plan, 2012-2017)

Outcome: Private sector investments in infrastructure PPPs facilitated.

Outputs: Availability of long-term finance for PPP subprojects enhanced Operational capacity of IIFCL improved

Implementation Arrangements: Not Applicable

Implementation Status: Not Yet Effective

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

242

Page 243: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating

Financial

Contract Awards

Disbursements

Safeguards

Technical

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

0.00 0.00 0.00 0.00

Significant Developments During the Year

1 DED = Detailed Engineering Design.

243

Page 244: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

47101001

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title Assam Power Sector Investment Program Project No. 47101-001

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

03 Jul 2014 30 Jun 2024 N/A

Division SAEN

MFF Amount ($ million)

300.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the Assam Power Sector Investment Program for an aggregate amount not exceeding $300.00 million from ADB’s OCR on 3 July 2014.

Impact: increased availability of electricity in Assam.

Outcome: increased capacity and efficiency of energy generation and distribution systems in Assam.

Outputs: Generation system upgraded and expanded Distribution system upgraded and expanded Institutional capacity of APGC & APDC strengthened Project management system in place.

Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 2

Approved Tranche Amount to Date

98.00

Facility Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

244

Page 245: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche Title Assam Power Sector Investment Program - Tranche 1 Project No. 47101-002

Country/Regional India Loan/Grant No.

3140

Project Officer Aziz Yusupov Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

11 Jul 2014 30 Jun 2019 N/A

Division SAEN

Tranche Amount($ million)

50.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/47101-002/main

Tranche Summary

ADB approved the Assam Power Sector Investment Program - Tranche 1, not exceeding the aggregate amount of $50.00 million on 11 July 2014.

Impact: increased capacity and efficiency of energy generation systems in Assam.

Outcome: increased capacity and efficiency in Lakwa power plant.

Outputs: Generation system upgraded and expanded Institutional capacity of APGC & APDC strengthened.

Implementation Arrangements: Assam Power Generation Corporation Ltd (APGCL) is the executing agency (EA) for Tranche 1 having the overall responsibility for the implementation of project components. The Project Management Unit (PMU) already established under the Chairman, Assam Power Distribution Company Ltd (APDCL) and will function as overall project coordination entity. The Project implementation units (PIUs) are established within APGCL and APDCL and will have the responsibilities of overall implementation of the Investment Program.

Implementation Status: The capacity building component is being fully implemented. Implementation of Tranche 1 is satisfactory in respect of all indicators and is rated on track as of Q4 2015.

1 DED = Detailed Engineering Design.

245

Page 246: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

2.31 0.00 0.06 0.00

Significant Developments During the Year

Tranche 1 (Loan 3140) is a loan of $50.00 million from Ordinary Capital Resources (OCR), which was approved on 11 July 2014 and declared effective on 12 May 2015. Tranche 1 is rated as On Track.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $2.31 million (.0%) and $.06 million (.0%), respectively. The project's physical progress is 12.20% against the elapsed loan period of 30% from loan approval. The procurement plan includes 1 ICB package and 8 consulting services contract. Notice of award has been issued for the ICB package and 5 contracts for consulting services have been signed. The remaining consulting services packages are expected to be contracted within Q1 2016.

Scope Change: There were no scope changes for this tranche in 2015.

Undertaking and Covenants: As of inception mission, the EA confirmed that the 22 loan covenants will be complied with.

1 DED = Detailed Engineering Design.

246

Page 247: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche Title Assam Power Sector Investment Program - Tranche 2 Project No. 47101-003

Country/Regional India Loan/Grant No.

3327

Project Officer Aziz Yusupov Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

23 Nov 2015 31 Dec 2019 N/A

Division SAEN

Tranche Amount($ million)

48.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/47101-003/main

Tranche Summary

ADB approved the Assam Power Sector Investment Program - Tranche 2, not exceeding the aggregate amount of $48.00 million on 23 November 2015.

Impact: enhanced quality and expanded service delivery of electricity in Assam.

Outcome: Increased efficiency and capacity of power distribution system in Assam.

Outputs: Distribution system expanded and upgraded. Institutional capacity of APDCL strengthened.

Implementation Arrangements: Not Applicable

Implementation Status: Not Yet Effective

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

247

Page 248: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating

Financial

Contract Awards

Disbursements

Safeguards

Technical

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

0.00 0.00 0.00 0.00

Significant Developments During the Year

1 DED = Detailed Engineering Design.

248

Page 249: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

47273002

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title Integrated Road Investment Program Project No. 47273-002

Country/Regional

Sri Lanka Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

25 Sep 2014 30 Sep 2024 N/A

Division SATC

MFF Amount ($ million)

800.00Source OCR

ADF

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the Integrated Road Investment Program for an aggregate amount not exceeding $800.00 million from ADB’s ADF, OCR on 25 September 2014.

Impact: Improved connectivity between rural communities and socioeconomic centers in Sri Lanka

Outcome: Increased transport efficiency on project roads

Outputs: Improved road conditions between the selected rural communities and socioeconomic centers Enhanced capacity of road agencies

Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program and policy and legal framework.

Estimated Total No. of Tranches to be Processed

3

Approved Tranches To Date 3

Approved Tranche Amount to Date

407.00

Facility Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

249

Page 250: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche Title Integrated Road Investment Program-Tranche 1 Project No. 47273-003

Country/Regional Sri Lanka Loan/Grant No.

3171

Project Officer Lee Tai Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

03 Oct 2014 30 Sep 2021 N/A

Division SATC

Tranche Amount($ million)

100.00 Source ADF

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/47273-003/main

Tranche Summary

ADB approved the Integrated Road Investment Program-Tranche 1, not exceeding the aggregate amount of $100.00 million on 3 October 2014.

Impact: Improved connectivity between rural communities and socioeconomic centers

Outcome: Increased transport efficiency on project roads

Outputs: 1. Improved road conditions between the selected rural communities and socioeconomic centers inSouthern Province 2. Enhanced capacity of road agencies3. Preparation of projects completed for succeeding projects

Implementation Arrangements: The Executing Agency is the Ministry of Highways, Ports and Shipping. The Implementing Agency is the Road Development Authority (RDA). A project implementation unit under the RDA was set-up to implement the project.

Implementation Status: As of 31 December 2015, 15 contracts (9 under Goods and Works and 6 under Consulting Services) have been awarded.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

250

Page 251: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

70.78 0.00 31.19 0.00

Significant Developments During the Year

Tranche 1 (Loan 3171) is a loan of $118.00 million from the Asian Development Fund (ADF), which was approved on 03 October 2014 and declared effective on 07 January 2015. Tranche 1 is rated as On Track.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $70.78 million (.0%) and $31.19 million (.0%), respectively. Tranche 1 has awarded 9 civil works contracts and 6 consulting contracts (2 firms and 4 individuals).

Scope Change: There were no scope changes for this Tranche in 2015.

Undertaking and Covenants: There are 18 undertakings and covenants for Tranche 1 which are being complied with.

1 DED = Detailed Engineering Design.

251

Page 252: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 2 UPDATE

Tranche Title Integrated Road Investment Program-Tranche 2 Project No. 47273-004

Country/Regional Sri Lanka Loan/Grant No.

3221, 3222

Project Officer Lee Tai Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

11 Dec 2014 30 Sep 2019 N/A

Division SATC

Tranche Amount($ million)

107.00 Source ADFOCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/47273-004/main

Tranche Summary

ADB approved the Integrated Road Investment Program-Tranche 2, not exceeding the aggregate amount of $107.00 million on 11 December 2014.

Impact: improved connectivity between rural communities and socioeconomic centers in Sri Lanka

Outcome: increased transport efficiency on project roads.

Outputs: Improved road conditions between the selected rural communities and socioeconomic centers.

Implementation Arrangements: The Executing Agency is the Ministry of Highways, Ports and Shipping and the Implementing Agency is the Road Development Authority (RDA). A project implementation unit under the RDA will implement the project.

Implementation Status: 13 contracts have been awarded under Loan 3221 and 7 contracts under Loan 3222.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

252

Page 253: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

50.37 100.00 16.97 0.00

Significant Developments During the Year

Tranche 2 (Loans 3221, 3222) is a loan of $107.00 million from the Asian Development Fund (ADF), Ordinary Capital Resources (OCR), which was approved on 11 December 2014 and declared effective on 23 July 2015. Tranche 2 is rated as On Track.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 2 have reached $50.37 million (100.0%) and $16.97 million (.0%), respectively. Under Tranche 2, 13 contracts have been awarded. There was a request to rebid 16 packages as bid prices are substantially higher than existing budget. After review, the 16 packages were increased to 18 packages. Invitation for bids rebidding was published on 14 December 2015.

Scope Change: There were no scope changes for this tranche in 2015.

Undertaking and Covenants: There are 16 undertakings and covenants for Tranche 2, which are all being complied with.

1 DED = Detailed Engineering Design.

253

Page 254: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 3 UPDATE

Tranche Title Integrated Road Investment Program-Tranche 3 Project No. 47273-005

Country/Regional Sri Lanka Loan/Grant No.

3325, 3326

Project Officer Lee Tai Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

23 Nov 2015 30 Sep 2021 N/A

Division SATC

Tranche Amount($ million)

200.00 Source ADFOCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/47273-005/main

Tranche Summary

ADB approved the Integrated Road Investment Program-Tranche 3, not exceeding the aggregate amount of $200.00 million on 23 November 2015.

Impact: connectivity between rural communities and socioeconomic centers in Sri Lanka improved by year 2027 (Annual Report, Ministry of Finance, Sri Lanka).

Outcome: transport efficiency on project roads increased.

Outputs: Road conditions between the selected rural communities and socioeconomic centers improved capacity of road agencies enhanced.

Implementation Arrangements: Not Applicable

Implementation Status: Not Yet Effective

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

1 DED = Detailed Engineering Design.

254

Page 255: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating

Financial

Contract Awards

Disbursements

Safeguards

Technical

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

0.00 0.00 0.00 0.00

Significant Developments During the Year

1 DED = Detailed Engineering Design.

255

Page 256: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

47341001

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title South Asia Subregional Economic Cooperation Road Connectivity Investment Program

Project No. 47341-001

Country/Regional

India Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

28 Mar 2014 31 Dec 2021 N/A

Division SATC

MFF Amount ($ million)

500.00Source OCR

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the South Asia Subregional Economic Cooperation Road Connectivity Investment Program for an aggregate amount not exceeding $500.00 million from ADB’s OCR on 28 March 2014.

Impact: Increased domestic and regional trade through North Bengal and Northeastern Region (NB-NER) of India

Outcome: Improved road connectivity and efficiency of the NB-NER international trade corridor

Outputs: Improved roads for regional connectivity Developed capacity and supported project implementation for MPWD

Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

-

Approved Tranches To Date 1

Approved Tranche Amount to Date

300.00

Facility Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

256

Page 257: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleSouth Asia Subregional Economic Conectivity Road Connectivity Investment Program - Tranche 1

Project No. 47341-002

Country/Regional India Loan/Grant No.

3118

Project Officer Tsuneyuki Sakai Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

01 Apr 2014 30 Jun 2022 N/A

Division SATC

Tranche Amount($ million)

300.00 Source OCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/47341-002/main

1 DED = Detailed Engineering Design.

257

Page 258: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Summary

ADB approved the South Asia Subregional Economic Conectivity Road Connectivity Investment Program - Tranche 1, not exceeding the aggregate amount of $300.00 million on 1 April 2014.

Impact: Increased domestic and regional trade through NB-NER

Outcome: Improved road connectivity and efficiency of the NB-NER international trade corridor

Outputs: Improved roads for regional connectivity Developed capacity and supported project improvement for MPWD

Implementation Arrangements: There are two executing agencies: (I) Ministry of Road Transport and Highways (MORTH) for national highways; and (ii) Manipur Public Works Department (MPWD) for state roads and capacity development. MoRTH will be responsible for the inter-ministerial coordination; day-to-day subproject management; sector development implementation; consultant recruitment and procurement of works; withdrawal applications; project progress reports and maintaining project accounts and complete loan financial records. The key implementing agencies are MoRTH, MPWD and West Bengal Public Works Department (WBPWD). They are responsible to implement subprojects as MoRTH agency; inter-departmental coordination; provide counterpart staff and land facilities and report on progress of subprojects.

Implementation Status: Most of the preconstruction works have been completed. MoRTH and WBPWD has been conducting close monitoring of the implementation status including frequent meetings and site visits by high officials.

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

132.43 45.26 6.28 17.34

1 DED = Detailed Engineering Design.

258

Page 259: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Significant Developments During the Year

Tranche 1 (Loan 3118) is a loan of $300.00 million from Ordinary Capital Resources (OCR), which was approved on 01 April 2014 and declared effective on 24 June 2015. Tranche 1 is rated as Actual Problem.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $132.43 million (45.3%) and $6.28 million (17.3%), respectively. Tranche 1 loan became effective in June 2015 and the project is in the initial stage of implementation.

Scope Change: There were no scope changes for this tranche in 2015.

Undertaking and Covenants: The 31 covenants under this tranche are being complied with.

1 DED = Detailed Engineering Design.

259

Page 260: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Annual MFF Progress Report

47381001

For the meaning of each item, please refer to the MFF Annual Report Definitions Table. FACILITY UPDATE

Project Title Mahaweli Water Security Investment Program Project No. 47381-001

Country/Regional

Sri Lanka Department SARD

Key Dates

ApprovalDate

Original Closing Date

Revised Closing Date

24 Jun 2015 31 Dec 2024 N/A

Division SAER

MFF Amount ($ million)

453.00Source OCR

ADF

Cofinancing($ million)

N/ASource N/A

Facility Summary

ADB approved the Mahaweli Water Security Investment Program for an aggregate amount not exceeding $453.00 million from ADB’s ADF, OCR on 24 June 2015.

Impact: improved agricultural production and sustained economic growth in the North Central Province, Central Province, North Western Province and Eastern Province.

Outcome: secured access to water resources for agricultural and drinking purposes in project areas

Outputs: New and improved water conveyance and storage infrastructure constructed Systems for improving water resources management and productivity developed Multidisciplinary investment program management operational

Significant Developments of the Facility: There are no significant developments of the facility including major changes to the roadmap, investment program, and policy and legal framework.

Estimated Total No. of Tranches to be Processed

1

Approved Tranches To Date 1

Approved Tranche Amount to Date

150.00

Facility Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Completion Report N/A

Facility Completion Report N/A

MFF Performance Rating (On Track, Potential Problem, At Risk)

On Track

260

Page 261: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

TRANCHE 1 UPDATE

Tranche TitleMahaweli Water Security Investment Program - Tranche 1

Project No. 47381-002

Country/Regional Sri Lanka Loan/Grant No.

3267, 3268

Project Officer Lance Gore Department SARD

Key Dates

ApprovalDate

OriginalClosing Date

RevisedClosing Date

02 Jul 2015 30 Jun 2020 N/A

Division SAER

Tranche Amount($ million)

150.00 Source ADFOCR

CofinancingAmount ($ million)

N/A Source N/A

Estimated Cost Overrun ($ million)

N/A

Estimated AmountUsed for DED1

($ million)

N/A

Project Data Sheet http://www.adb.org/projects/47381-002/main

Tranche Summary

ADB approved the Mahaweli Water Security Investment Program - Tranche 1, not exceeding the aggregate amount of $150.00 million on 2 July 2015.

Impact: improved agricultural production and sustained economic growth in the North Central Province, Central Province, North Western Province and Eastern Province

Outcome: secured access to water resources for agricultural and drinking purposes in project areas

Outputs: 1. New and improved water conveyance and storage infrastructure constructed2. Systems for improving water resources management and productivity developed3. Multi-disciplinary investment program management operational

Implementation Arrangements: The executing agency is the Ministry of Mahaweli Development and Environment (MMDE). A program management unit (PMU) was established within MMDE to manage project implementation, which is undertaken by project implementation units in each of the three investment projects. MMDE has overall responsibility for coordination, management, monitoring, and supervision.

Implementation Status: The PMU has been fully functioning. Procurement of goods and works has been initiated. The procurement for the rehabilitation of the Minipe Left Bank Canal - Stage 1 is in progress. Bidding documents for the four other main works packages are currently being finalized. The program management, design and supervision consultants were mobilized in November 2015.

1 DED = Detailed Engineering Design.

261

Page 262: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

Tranche Change in ScopeCategory Date Proposed Change

N/A N/A N/A

Tranche Performance( Quarterly Performance as of 31 Dec 2015 )

On Track Potential Problem Actual Problem

Overall Rating ✓Financial ✓Contract Awards ✓Disbursements ✓Safeguards ✓Technical ✓

Contract Awards &Disbursements(Cumulative)

Contract Awards Disbursements

$ million % $ million %

20.73 96.50 15.86 100.00

Significant Developments During the Year

Tranche 1 (Loans 3267, 3268) is a loan of $150.00 million from the Asian Development Fund (ADF) and Ordinary Capital Resources (OCR), which was approved on 24 June 2015 and declared effective on 26 October 2015. Tranche 1 is rated as On Track.

Progress: As of 31 December 2015, contract awards and disbursements under Tranche 1 have reached $20.73 million (96.5%) and $15.86 million (100.0%), respectively. Initial procurement of goods and works are underway. The program management, design and supervision consultants were mobilized in November 2015.

Scope Change: There were no scope changes for this tranche in 2015.

Undertaking and Covenants: Tranche 1 is in its early stages. Loan covenants are being complied with.

1 DED = Detailed Engineering Design.

262

Page 263: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

MFF ANNUAL PROGRESS REPORT DEFINITIONS

Ref. No. Term Meaning

FACILITY UPDATE

1. Project Title - Indicates the MFF name following this naming convention: MFF – {Facility Name}

2. Project No. - Indicates the facility’s 8-digit project number3. Country/Regional - Indicates the name of the country covered by the facility.4. Department - Indicates the name of the department processing the MFF.5. Approved Date - Indicates the date of ADB approval of the facility.6 Original Closing Date - Indicates the facility’s original closing date.7. Revised Closing Date - Indicates the facility’s revised closing date.8. Division - Indicates the name of the division processing the MFF.9. MFF Amount ($ million) - Indicates the approved MFF amount.10. Source - Indicates the funding source/s of the MFF approved amount,

whether it is OCR/ADF.11. Cofinancing Amount ($

million)- Indicates the DVA cofinancing amount. If not applicable, “N/A” is

displayed.12. Source - Indicates the source of the cofinancing amount. If not applicable,

“N/A” is displayed.13. Facility Summary

Impact and Outcome - States the facility’s impact and outcome as indicated in the DMF report.

Outputs - States the facility’s outputs as indicated in the DMF report.Significant Development of the facility

- Describes any significant development of the facility including major changes to the roadmap, investment program, and policy and legal framework.

14. Expected Total No. ofTranches

- Indicates the number of envisioned or pipelined tranches as presented in the RRP, if any.

15. Approved Tranches toDate

- Indicates the number of approved tranches to date.

16. Approved TrancheAmount to Date

- Indicates the current year’s cumulative tranche amount to date.

17. Facility Change in ScopeCategory - Indicates whether the category for the facility’s proposed change is

major or minor.Date Approved - Indicates the date when the request for change in scope for the

facility is approved.Proposed Change - Summarizes the content of the change in scope request; revisions

to outcome, outputs and/or inputs; and new targets and/or indicators.

18. Completed Tranches toDate

- Indicates the URL of the completed tranches’ Project Completion Report (PCR).

19. Facility CompletionReport

- Indicates the URL of the Facility Completion Report (FCR). Note that a facility is completed when all its tranches are closed.

20. Overall MFFPerformance Rating (OnTrack, PotentialProblem, At Risk)

- Indicates the rating of the MFF. The facility will be rated on the basis of 3 separate parameters:

(i) MFF delays, (ii) Tranche performance, and (iii) Compliance with undertakings.

Poor performance (red rating) on account of the 3 indicators will place the facility ‘at risk’ and may lead to its suspension and

263

Page 264: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

MFF ANNUAL PROGRESS REPORT DEFINITIONS

Ref. No. Term Meaning

FACILITY UPDATE

possible cancellation; poor performance (red rating) on account of 2 parameters will indicate potential problems and would require RDs to draw an action plan to rectify the facility‘s performance.

MFF Delays - Contributors to MFF Delays are:(i) Substantial delays in tranche processing, and/or (ii) Substantial delays in tranche implementation.

Timeliness in Tranche processing will be evaluated against the tranche sequencing program forecasted in the RRP. Tranches processed …

(i) within one year of the forecasted period will be given an ‘on track‘ (green) rating;(ii) between 1 and 2 years of the forecasted date will be given a ‘Potential problem‘ (yellow) rating, and (iii) beyond 2 years of the forecasted date will be given an ‘at risk‘ (red) rating.

For MFFs where a time-bound tranche sequencing program was not forecasted in the RRP, only, MFF delays will be determined on the following grounds:

(i) if less than 2 years have passed since approval of the previous tranche (up to the stage where the entire MFF has been turned into tranches), a green rating is granted,(ii) if more than 2 years but less than 3 years have elapsed, a yellow rating is given; and(iii) if more than 3 years have elapsed, a red rating applies.

Compliance with MFF undertaking

- The assessment should include compliance with Safeguards and PCP requirements, as well as any timely Reform implementation targets.

(i) Non-compliance with more than 3 undertaking will place the facility in ‘red‘ (unsatisfactory).(ii) Non-compliance with any ‘safeguards‘, ‘PCP‘ and/or ‘reform implementation‘ undertakings will place the MFF in ‘red‘ (unsatisfactory).(iii) Non-compliance with 2 undertakings (other than those outlined in the preceding sentence), will place the facility as ‘partly satisfactory‘. (iv) Compliance with all undertakings with a maximum of one exception (other than those outlined before), will signify a ‘satisfactory‘ criteria.

Tranche Performance - (i) Poor performance (‘at risk‘) on 33% or more of the MFF tranches (by number) would place the MFF ‘at risk‘ (red).(ii) ‘Potential problem‘ rating on 33% or more of the MFF tranches (by number) would categorize the MFF as ‘potential problem‘ (yellow), unless a red rating is triggered.(iii) Other ratings will result ‘on track‘ (green)

264

Page 265: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

MFF ANNUAL PROGRESS REPORT DEFINITIONS

Ref. No. Term Meaning

TRANCHE UPDATE

1. Tranche Title - Indicates the tranche name following this naming convention: MFF – {tranche name} (Tranche {tranche no.})

2. Project No. - Indicates the tranche’s 8-digit project number.3. Country/Regional - Indicates the name of the country covered by the tranche.4. Loan/Grant No. - Indicates the tranche’s 4-digit loan number. If loan numbers are

available 5. Project Officer - Indicates the name of the mission leader or project implementation

officer.6 Department - Indicates the name of the department processing the tranche.7. Tranche Approved Date - Indicates the tranche’s date of ADB approval.8. Original Closing Date - Indicates the tranche’s original loan closing date.9. Revised Closing Date - Indicates the tranche’s revised loan closing date.10. Division - Indicates the name of the division processing the tranche.11. Tranche Amount

including cofinancing ($million)

- Indicates the tranche’s total approved and cofinancing amount.

12. Source - Indicates the funding source of the tranche amount, whether it is OCR/ADF.

13. Cofinancing amount ($million)

- Indicates the tranche’s cofinancing amount.

14. Source - Indicates the funding source of the cofinancing amount.15. Estimated Cost Overrun

Amount- Indicates the cost overrun amount incurred by the tranche at the

time of preparation of the MFF Annual Progress Report. If not applicable, “N/A” is indicated.

16. Estimated Amount Usedfor detailed engineeringdesign (DED)

- Indicates the amount used for DED. If not applicable, “N/A” is indicated.

17. Project Data Sheet(PDS)

- Indicates the URL for the tranche’s PDS.

18. Tranche SummaryImpact and Outcome - States the tranche’s impact and outcome as indicated in the DMF

report.Outputs - States the tranche’s outputs as indicated in the DMF reportImplementation Arrangements

- Briefly highlights the tranche’s implementation arrangements.

Implementation Status - Briefly highlights the tranche’s implementation progress.19. Tranche Change in

ScopeCategory - Indicates whether the category for the proposed change is major or

minor.Date Approved - Indicates the date when request for change in scope was approved.Proposed Change - Summarizes the content of the change in scope request; revisions

to outcome, outputs and/or inputs; and new targets and/or indicators.

20. Tranche Performance - Indicates the performance rating of the tranche as indicated in the 2011 MFF Staff instructions and PAI 5.08. It is rated in the following categories: (i) financial, (ii) contract awards, (iii) disbursements, (iv) safeguards, and (v) technical.

21. Contract Awards &Disbursements

- Indicates the tranche’s cumulative amount and rate of the contract awards and disbursement in the year of the preparation of the MFF

265

Page 266: Annual MFF Progress Report...(On Track, Potential Problem, At Risk) On Track 1 TRANCHE 1 UPDATE Tranche Title MFF - Railway Sector Investment Program (Subproject 1) Project No. 32234-023

MFF ANNUAL PROGRESS REPORT DEFINITIONS

Ref. No. Term Meaning

TRANCHE UPDATE

(Cumulative) annual report.22. Significant

Developments Duringthe Year

Physical Progress - Briefly describes the physical progress of the tranche.Nonphysical Progress - Briefly describes the nonphysical progress of the tranche.Scope Change - Briefly describes the tranche’s request for change in scope, if any.Undertaking with Covenants

- Briefly describes the number of undertakings and covenants that the tranche has complied with.

266