analysis and discussion of deepwater horizon accident · pdf fileanalysis and discussion of...

23
Analysis and Discussion of Deepwater Horizon Accident and Barrier Strategies NTNU, Faculty of Engineering Science and Technology, Department of Marine Technology. Nathalie M. De Oliveira Jeevith Hegde

Upload: vanthuy

Post on 22-Mar-2018

225 views

Category:

Documents


2 download

TRANSCRIPT

Analysis and Discussion of Deepwater Horizon Accident and Barrier Strategies

NTNU, Faculty of Engineering Science and Technology,Department of Marine Technology.

Nathalie M. De Oliveira

Jeevith Hegde

ContentsList of Figures 2

List of Tables 2

1 Introduction 41.1 Overview of topics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41.2 Structure of report . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

2 Terminology and abbreviations 52.1 Terminology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52.2 Abbreviations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

3 Summary of the Macondo blowout 6

4 Discussion- failed barriers 74.1 Man Technology Organization (MTO) . . . . . . . . . . . . . . . . . . . . . . . . . . . 74.2 Energy flow perspective . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 94.3 Comparison with similar accidents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 104.4 Comparison with the Texas City Refinery accident (2005) . . . . . . . . . . . . . . . . . 10

5 Proposed barrier strategies 115.1 Context . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 115.2 Risk assessment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 115.3 Hazard identification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12

5.3.1 Preliminary hazard analysis (PHA) . . . . . . . . . . . . . . . . . . . . . . . . 125.3.2 Risk level picture . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

5.4 Risk treatment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 165.5 Specific barrier strategy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 165.6 Performance requirements/standards . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19

6 Conclusions 20

References 21

A Appendix- PHA Parameters 22A.1 Probability Classes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22A.2 Severity Classes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22

1

List of Figures1 MTO analysis for Macondo Blowout . . . . . . . . . . . . . . . . . . . . . . . . . . . . 72 Step diagram with MTO barrier perspective . . . . . . . . . . . . . . . . . . . . . . . . 83 Energy barrier perspective . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 94 Barrier management in the planning phase [PSA, 2013] . . . . . . . . . . . . . . . . . . 115 Proposed barrier management- prevent accidents . . . . . . . . . . . . . . . . . . . . . 176 Proposed barrier management- mitigate consequences . . . . . . . . . . . . . . . . . . . 18

List of Tables1 Comparison of similar accidents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102 Hazard identification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 123 Preliminary hazard analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 134 Preliminary hazard analysis (continued) . . . . . . . . . . . . . . . . . . . . . . . . . . 145 Initial risk matrix . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 156 Residual risk matrix . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 157 Risk matrix colour legend . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 158 Barrier performance standard- functional level . . . . . . . . . . . . . . . . . . . . . . . 199 Barrier performance standard- element level . . . . . . . . . . . . . . . . . . . . . . . . 1910 Barrier performance standard- organization level . . . . . . . . . . . . . . . . . . . . . 2011 Probability classes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2212 Severity classes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22

2

PrefaceThis report is a mandatory task in the course TMR4555, Applied Risk Analysis. The group members areNathalie M. de Oliveira and Jeevith Hegde. Both members have worked together in all parts of the project.

The accident assigned to the pair was the Macondo Blowout of April 2010. Even though environmental,economic and reputation losses were hefty in this event, the team chose to focus on issues related topersonnel safety. This decision was made in order to keep the work scope manageable.

MTO and energy flow perspectives were used to analyze the accident. Barrier failures were classifiedbased on technical, human and organizational. Barrier failures in the interface between human and or-ganizational aspects amounted to high number and therefore received attention when designing a newbarrier strategy.

The new barrier strategy proposed included man, technology and organization barriers and listed theirperformance requirements. The team hopes to have achieved compliance with PSA’s demands on de-signing barriers and a continuous barrier management process.

The team would like to acknowledge Professor Jan.Erik. Vinnem for his continued assistance and forsharing his knowledge with the class on the subject of Offshore Risk Assessment. The image for the titlepage is credited to [Ideum - ideas + media, 2010].

A famous quote from the character Uncle Ben in the comic Spiderman reads, “With great power comesgreat responsibility” . The Macando well would have been one of the deepest offshore wells ever com-pleted, but the stakeholders involved in this accident failed to foresee the fatal accident propagation. Astrivial as it may sound, this quote summarizes the lack of top level management focus of the stakeholderson safety.

3

1 Introduction

1.1 Overview of topicsThe list of greatest human engineering accomplishments is long. From building the huge pyramids in an-cient Egypt, to sending men to the moon or exploring the depths of the ocean, deeds have been executedby groups of engineers and other professionals that awe us. But oftentimes these mind blowing projectsend up costing us much more than we were willing to pay, mainly when consequences are difficult totranslate to monetary units, being cashed out on the environment or in lives that are lost.

Nonetheless, we believe most of these unwanted losses can be avoided if a proper barrier managementsystem is implemented. The objective of the barrier management system is to isolate what we hold valu-able from potential threats.

Deepwater Horizon, an ultra-deepwater semi-submersible offshore oil drilling rig built in 2001, owned byTransocean and working for BP in its last mission, had an inadequate Barrier Strategy for the Macondodrilling project. The consequence summed up to 11 deaths, 17 major injuries, sinking of the rig andmassive environmental damage from estimated 5 million barrels of released hydrocarbons [CSB, 2014].In the year previous to their accident, Deepwater horizon had drilled down to 10.5 km, the deepest oiland gas well in the world. A great achievement followed by a terrible fall.

But what was inappropriate in Deepwater Horizon’s Barrier Strategy? Which barriers failed and whatcould have been done differently to achieve another outcome? In an accident with the Macondo Blowoutmagnitude, it is a challenge to answer these questions with the certainty that all possible aspects havebeen regarded. In this work, the aim is to address some of the most relevant barrier failures, as well as tosuggest barriers that could have been implemented to avoid the accident.

We noted that by far the two notions "Safety Culture must be rooted with top management" and "BarrierManagement must be a continuous process, keeping pace with changes occurring in the execution phaseof the project in opposition to a static safety strategy designed in the planning stage and never updated",are the most valuable changes that should be implemented in the organizations involved in this accidentand overall over the entire Oil and Gas industry.

1.2 Structure of reportThis report analyzes the Macondo accident and the Barrier Strategy that was in place when the accidenthappened. It also discusses what could have been different in order to minimize the escalation of theoutcome or even interrupt the chain of events that caused the blowout.

The report will follow the risk for the people perspective, meaning the more than 80 days of oil spillafter the sinking of the rig a, before the definitive shut down of the well, and the environmental damageare outside the scope of this report. We choose to limit the analysis of the accident up to the rescue ofpersonnel not because the 5 million barrels of oil [Vinnem, 2014, The Deepwater Horizon Study Group(DHSG), 2011, CSB, 2014] reported to spill is of small importance, but to keep this work within a feasi-ble outline for the Risk Analysis course, taught by Professor Vinnem. Section 3 starts with a condensedpresentation of the accident chronology.

4

Section 4 starts by presenting barriers which failed and why, from a technical perspective, following theenergy flow perspective and MTO perspective. This analysis then evolves to include human and organi-zational aspects relevant to discussed failures that permitted the accident to escalate to the point where 11deaths and 17 injuries occurred. This part concludes with comparison of other similar accidents in termsof causes and consequences.

Section 5 proposes specified barrier strategy based on the failure of barrier functions revealed in the pre-vious section. The section 6 concludes the report.

2 Terminology and abbreviations

2.1 TerminologyIt is not unusual that different terms are used interchangeably across the oil and gas industry when de-scribing the topic of safety barriers. The definitions of barrier terminologies in this report is refereedfrom [Sklet, 2006].

Safety barriers- are physical and/or non-physical means planned to prevent, control, or mitigate unde-sired events or accidents.

Barrier function- is a function planned to prevent, control, or mitigate undesired events or accidents.

Barrier system- is a system that has been designed and implemented to perform one or more barrier func-tions.

Barrier element- A barrier element is a component or a subsystem of a barrier system that by itself is notsufficient, to perform a barrier function [Sklet, 2006].

2.2 Abbreviations

ALARP As Low As Reasonably PracticableBOP Blowout PreventerDHSG The Deepwater Horizon Study GroupEDS Emergency Disconnect SystemESD Emergency ShutdownHC HydrocarbonLMRP Lower Marine Riser PackageMTO Man Technology OrganizationNCS Norwegian Continental ShelfOIM Offshore Installation ManagerPSA Petroleum Safety AuthoritySIL Safety Integrity LevelTD Total Depth

5

3 Summary of the Macondo blowoutThe Macondo well-blowout accident resulted in 11 personnel fatalities, 17 personnel injuries, an esti-mated 5 million barrels of oil spilled, and vast environment pollution. [Vinnem, 2014, The DeepwaterHorizon Study Group (DHSG), 2011, CSB, 2014]

The accident progression of the Macondo well blowout began in late 2009 when hurricane Ida passedthe Mexican gulf damaging the Marinas rig. In January 2010, BP replaced the Marinas rig with theDeepwater Horizon rig from Transocean. When the exploration drilling resumed in February, a leak wasidentified in the yellow pod of the Blow-Out Preventer (BOP), subsequently the redundant blue pod re-duced the leak. However, insufficient charge in the blue pod battery was discovered during investigations.While drilling in depth of 13305 ft, influx of formation fluids were noticed and the drill pipe and welllogging tools were stuck. Drilling continued by well sidetracking operation. Two lost circulation inci-dents occurred in early April at depths of 18260 and 18360 feet. In both instances, the well was stabilizedby pumping lost-circulation fluids. At the total depth (TD) of 18360 ft, BP decided to terminate furtherdrilling citing unnecessary jeopardizing of the well bore.

BP chose to use the long string casing completion design and Haliburton was contracted to perform thecementing job. BP requested Halliburton to use 6 centralizers for the cementing job against BP’s originalplan of using 21 centralizers. The long string casing completion design was installed with 6 centralizers.On April 18th, BP attempted to circulate the well to plug the float collar or the reamer shoe. It took BPnine attempts before the float collar was converted at a pressure of 3142 psi. This high pressure requiredfor the operation, raised concerns about blockages in the reamer shoe, breakdown of surrounding wellformations and that the float collar may not have been converted as thought. Due to BP engineers fearsof wash-out at the weak formations, BP decided to carry out a partial bottoms-up circulation of the well.Partial bottoms-up circulation meant that any hydrocarbons remaining in the bore could linger in the up-per part of the well after cementing.

On 20th April, pressure monitoring observed the floats to be holding and the well in static state. BPplanned to start the temporary abandonment procedure consisting of positive pressure test, negative pres-sure test, displacing drilling mud in the riser, setting cement plug, pressure testing cement plug integrity,performing impression test, and installing lockdown sleeve.

The crew carried out two different positive pressure and negative pressure tests, which were performedless than 48 hours after the cementing job in the bottom of the well. Simultaneous operations (displacingmud, pressure testing, trip tank cleaning, offloading mud to support vessel) meant that the crew was un-able to monitor the mud pit levels. This also meant that the crew was unaware as to the amount of mudlost during displacement/flushing operations. There was more backflow than anticipated during the thefirst negative test and personnel at BP and Transocean had different interpretations of the results, whichled to an agreement for a second negative pressure test. The second negative pressure test was acceptedeven after abnormalities were found in terms of backflow in the drill pipe. The pressure in the drill pipeincreased and decreased several times.

The sea water was pushed into the drill derrick which was followed by uncontrolled flow of drilling mud.The crew diverted the hydrocarbon flow to the mud-gas separator, which was not designed to containhuge volumes of gas flowing through the well. Emergency systems failed to perform their function. Dueto the latent failure in the BOP control pod’s the emergency disconnect system (EDS) was not able to

6

disconnect the Lower Marine Riser Package (LMRP). Two explosions occurred in quick succession anda mayday call was made by the crew. The decision to evacuate the platform was made. Some crewmembers jumped to sea and others mustered around the lifeboats. The evacuation process was chaotic,but 115 on board managed to be rescued.

For the next 83 days BP and partners made a series of attempts to stop flow of hydrocarbons into the Gulfof Mexico and after 10 different attempts were able to kill and seal the Macondo well.

4 Discussion- failed barriers

4.1 Man Technology Organization (MTO)A step diagram of the Deepwater Horizon accident was constructed to identify key events and failed bar-riers leading to the accident. The illustration (Figure 2) depicts the failure in barriers during the accident.Accident causation theories such as, the domino theory, swiss cheese model and energy flow theoriescan be observed in this accident. To analyze the failure of barriers, an MTO perspective was chosen incombination with the step diagram as seen in Figure 2.

The scope for this analysis was selected to encompass key events leading to the Macondo accident. Acolor coding system is used to illustrate man, technology, and organizational barriers which failed duringthe accident progression.

Man

Organization

Technology

2

0

3

5

3

1

2

Figure 1: MTO analysis for Macondo Blowout

The results from the step diagram were further incorporated to setup a venn-diagram of MTO failedbarriers refer Figure 1. The results show that failures in the intersection of man and organizational barriersare higher in number than other categories. The combination of man and organization resulted in sixfailed barriers. Choice of long string completion, MMS approval to use single string completion, use of 6centralizers, incomplete bottoms up operations, early pressure testing, and alarm software disconnected.

7

Loss

of

Cir

cula

tio

n a

t 1

826

0ft

and

1

836

0ft

- St

op

pe

d D

rilli

ng

BP

Act

ors

Events

Halliburton TransoceanMinerals

Management Services

Mar

inas

ch

ang

ed t

o

Dee

pw

ate

r H

ori

zon

BO

P:

Leak

in

yello

w P

od

Feb

ruar

y 20

10M

arch

20

10

Ap

prov

ed S

ingl

e Lo

ng

strin

g ca

sin

g de

sign

Ap

ril 2

010

Ch

oic

e o

f Lo

ng

Str

ing

C

asin

g t

o c

om

ple

te t

he

wel

l.

Ap

ril 9

20

10A

pri

l 12

201

0A

pri

l 15

20

10

6 C

en

tral

ize

rs

inst

alle

d

Ap

ril 1

6

2010

Dec

isio

n t

o u

se 7

C

en

tral

ize

rs

An

aly

zed

7

C

en

tral

ize

rs d

esi

gn

Re

po

rt is

sue

d t

o B

P

wit

h c

on

cern

s o

n

nu

mb

er

of

cent

rali

zer

use

d se

nt

afte

r ce

me

nti

ng

Ap

ril 1

8

2010

Ap

ril 1

9

2010

Inco

mpl

ete

B

ott

om

s U

p

op

erat

ion

s

Ap

ril 2

0

2010

Ear

ly P

resu

rre

Tes

tin

g. B

efo

re

Ce

me

nt

Sett

ing

.

Sim

ult

ane

ou

s O

pe

rati

on

s

Dif

fere

nt

Ite

rpre

tati

on

of

Tw

o N

ega

tive

P

ress

ure

Te

st

We

ll K

ick

Red

irec

ted

G

as to

Se

para

tor

13:2

8 H

ours

20:0

0 H

ours

21:4

5 H

ours

Ou

tage

of

Po

we

rE

xplo

sio

n 1

an

d 2

Ala

rm

Soft

war

e D

isco

nn

ect

ed

ED

S

Mal

fun

ctio

n

Man

Org

an

iza

tion

Tech

nol

ogy

Bar

rier

Leg

end

21:4

9 H

ours

21:5

2 H

ours

Un

con

tro

lled

HC

Le

ak

Ben

din

g o

f D

rill

Pip

e

Figu

re2:

Step

diag

ram

with

MTO

barr

ierp

ersp

ectiv

e

8

4.2 Energy flow perspectiveThe energy flow principle was used to demonstrated the flow of excess energy from the potential source-the reservoir to the vulnerable target- the crew members and topside structure. Together with the energybarrier principle, other accident propagation theories such as the domino theory and the swiss cheesemodel also provide theoretical background in this analysis.

From Figure 3, it is observed that the accident causation models mentioned above can be illustrated as thefailed barriers in the Macondo blowout. The study assumed the Macondo blowout event to be the mainaccidental event. This event occurred because the physical barriers did not operate as they should havedue to man, technology, and organizational factors. Subsequently, the flow of energy progressed from thereservoir to the topside facility. The barriers established to protect the crew and the topside facility werefurther weakened by failure of additional MTO barriers such as gas detection, fire deluge, and evacuationsystems/process.

In majority of failed barriers, organization factors played a vital role in the accident. Choosing the lessprotective casing design, using less number of centralizers, pressure testing sooner than the cement settingtime, inadequate quality in maintenance of equipment- BOP and topside gas detection systems, disablingalarm functions of the fire and gas detection/fighting systems, and chaotic evacuation process all of whichcontributed to the increased severity of the accident.

Barrier Legend

Macondo Blowout

Man

Organization

Technology

Single String Completion Casing

Wel

lhea

d S

eal

Cho

ice

of S

ingl

e St

ring

Cas

ing

Blow Out Preventer

Shea

r R

am

s

An

nula

r Pr

even

tors

Pipe

Ram

s

BO

P

Cer

tifi

cati

on

Pressure Testing

Test

ing

afte

r C

emen

t Se

t

Val

ida

te T

est

R

esul

ts

Centralizers

Inte

rnal

C

omm

unic

atio

n

Val

idat

e R

esu

ltsEnergy

Flow

HC Detection and Mitigation

Mai

nte

nan

ce o

f F&

G B

arri

ers

Explosion

Fire

& G

as

De

tect

ion

Emer

gen

cy

Pre

pa

red

ne

ss

Red

irec

tio

n of

HC

Ala

rm a

nd

Del

uge

Sy

stem

s

Fire

Fig

htin

g Sy

ste

m

Evacuation

Energy Flow

Figure 3: Energy barrier perspective

9

4.3 Comparison with similar accidents[Vinnem, 2014] presents a table that compares similar accidents focusing on barrier functions and how/ifthey worked for each accident. From the presented set of accidents involving blowouts, three had severeconsequence for life. Table 1 presents comparison of the Macondo blowout accident with the Usumacintaand Enchova blowout accidents.

Table 1: Comparison of similar accidentsSl. No. Facts of Accident Macondo 2010 Usumacinta 2007 Enchova 1984

1 Initiating event High pressures in the wellbore andformation

Bad weather Unknown

2 Accident Progression During work for abandonment ofthe well, a kick occurred that esca-lated to a blowout, with two big ex-plosions, outage of power and sink-ing of the rig with a leaking well

While finishing to drill a well for asmall production platform, a stormapproached. The drilling platformwas moved and struck the top of aproduction valve tree on the fixedplatform, resulting in leaking of oiland gas. Safety valves were acti-vated but unable to seal completely.Personnel died during evacuation ofthe platform.

During a drilling activity a gas leakcaused a fire to start. This first firewas controlled, and a second fire,from a oil leak, occurred and lasteduntil the following day. Personneldied during evacuation of the plat-form.

3 Fatalities 11 of 126 (9%) 22 of 81 (27%) 42 of 249 (17%)

It is interesting to observe that in the previous two blowouts deaths occurred during the evacuation pro-cess in the installation, and Macondo’s accident investigations lead us to believe that no lives were lostduring this process.

One could infer that Transocean had better evacuation procedures than PEMEX (Usumacinta) or Petro-bras (Enchova). Even though it was reported that a split chain of command between the Offshore In-stallation Manger (OIM) and the captain confused some of the crew members during the evacuation inDeepwater Horizon, no fatalities resulted during the evacuation stage [Vinnem, 2014, The DeepwaterHorizon Study Group (DHSG), 2011].

4.4 Comparison with the Texas City Refinery accident (2005)BP’s Texas City Refinery explosion claimed 15 lives and injured more than 170 people.

Although this accident and Macondo Blowout aren’t strictly similar, a parallel can be draw in the underly-ing causes of both events. To start, both accidents were considered avoidable if BP had taken appropriatemeasures (BP was identified as the main responsible). The lack of a safety culture geared towards systemsafety instead of only focusing to avoid labor accidents was also common to both events. The lack ofappropriate maintenance in the level transmitters of the knockout drum and of the slitter tower, leadingto malfunction, resembles the inadequate inspection of the BOP pods, previous to its installation in Ma-condo. Lastly, the refinery operator decision to ignore the high level alarm and continue to fill in thetower with hydrocarbons (BP Texas City Refinery) reminds us of BP’s decision to proceed with the wellabandonment procedure even though the pressure test result indicated something was amiss in the well(Macondo well). In both cases, there was pressure to complete work as fast as possible, that is, pressureto cut costs [CSB, 2007, The Deepwater Horizon Study Group (DHSG), 2011].

10

5 Proposed barrier strategiesFrom the previous sections it is observed that a barrier strategy management is vital to avoid risk ofmajor accidents. The barrier strategies can be developed at different levels such as, man, technology, andorganization. The Petroleum Safety Authority (PSA) in Norway has in the past focused on developing aframework for building a barrier strategies [PSA, 2013]. Figure 4 is the framework suggested by PSA todevelop specific barrier strategies and corresponding performance standards for the barriers.

Figure 4: Barrier management in the planning phase [PSA, 2013]

The PSA barrier management framework was utilized in this study to develop barrier strategies. Thesubsections describe the method in detail.

5.1 ContextIn relation to the Macondo blowout, the study was limited to risk of blowout during drilling operationsat offshore installations. The study assumed that such an accident can re-occur in the Norwegian Con-tinental Shelf (NCS) and the PSA regulations were referred for requirements on various contexts suchas safety functions, fire and explosion protection systems, competence and training, and evacuation pro-cess [Petroleum Safety Authority Norway- PSA, 2014].

5.2 Risk assessmentThe risk assessment process mentioned in the barrier management framework is a four step process.The first step is to identify hazards in and to the system. The second step is to control the hazards byidentifying barrier functions, elements and performance requirements. The third step is to perform a

11

qualitative or quantitative risk analysis of the system. The final step is to asses and evaluate the risks andpresent a risk picture [PSA, 2013].

5.3 Hazard identificationHazard identification was carried out through a brainstorming session and by focusing on failed MTObarriers in Macondo blowout. The hazard identification was organized on basis of the checklist providedin [Rausand, 2011](page 67). The identification was limited to a blowout scenario and correspondingfire, explosion, and evacuation related hazards. Table 2 presents the generic hazards identified for thesafety case.

Table 2: Hazard identificationSL. No. Generic Hazard Hazard1 Mechanical hazards High/unstable pressure in the well

StabilityDegradation of equipment

2 Dangerous materials Flammable3 Thermal hazards Flame

ExplosionPersonnel exposed to high temperature and heat radiation

4 Organizational hazards Safety cultureLess than adequate maintenanceLess than adequate competenceCrowd control

5.3.1 Preliminary hazard analysis (PHA)

A PHA was carried out with the process as described in [Rausand, 2005]. Barrier functions and elementswere introduced as preventive measures to reduce the risk of a blowout. Both existing risk level withoutproposed barriers and residual risk with proposed barriers were assessed. The preventive actions wereutilized to also develop proposed barrier strategy as discussed in Section 5.

Table 3, 4 presents the PHA worksheet with existing risk level and residual risk level. Table 5, 6 presentthe corresponding initial and residual risk picture.

12

Tabl

e3:

Prel

imin

ary

haza

rdan

alys

isIn

itial

Ris

kR

esid

ual

Ris

kG

ener

icH

azar

dId

entifi

erH

azar

dA

ccid

entE

vent

Prob

able

Cau

ses

Prob

abil-

itySe

veri

tyR

isk

Lev

elPr

even

tive

Act

ions

Prob

abili

tySe

veri

tyR

isk

Lev

elM

echa

nica

lH

azar

ds1a

Hig

h/un

stab

lepr

essu

rein

the

wel

l

Incr

ease

dre

ser-

voir

pres

sure

Fluc

tuat

ions

info

rmat

ion

pres

sure

44

16Is

olat

ear

eas

with

diff

eren

tpr

es-

sure

san

dflu

ids.

Pres

sure

Test

ing

(Neg

ativ

ean

dPo

sitiv

e).

Bot

tom

sU

p.

32

6

1bSt

abili

tyL

oss

ofst

abili

tySh

ipco

llisi

on3

39

Col

lisio

nA

void

ance

Ala

rms

and

Safe

tyZ

one

Reg

ulat

ions

22

4

1cR

ough

wea

ther

43

12A

void

Rig

Dri

ftan

dD

rive

off

42

81d

Deg

rada

tion

ofeq

uipm

ent

Lea

kC

orro

sion

23

62

36

Dan

gero

usM

ater

ials

2aFl

amm

able

Hyd

roca

rbon

re-

leas

e(t

opsi

de)

Igni

tion

Sour

ce4

416

Isol

ated

hydr

ocar

bons

subs

ea.

Re-

duce

Ris

kof

Exp

losi

on.

Red

uce

Dur

atio

nan

dSi

zeof

Lea

k.L

imit

Exp

osur

eof

Pers

onne

lat

Dan

ger

Zon

es.

23

6

The

rmal

Haz

ards

3aFl

ame

Fire

Hyd

roca

rbon

leak

(top

side

)4

416

Isol

ated

hydr

ocar

bons

subs

ea.

Re-

duce

Ris

kof

Exp

losi

on.

Red

uce

Dur

atio

nan

dSi

zeof

Lea

k.L

imit

Exp

osur

eof

Pers

onne

lat

Dan

ger

Zon

es.

23

6

3bE

xplo

sion

Hyd

roca

rbon

re-

leas

e(t

opsi

de)

HC

leak

(top

side

)3

412

Isol

ated

hydr

ocar

bons

subs

ea.

Re-

duce

risk

ofex

plos

ion.

Red

uce

du-

ratio

nan

dsi

zeof

leak

.Lim

itex

po-

sure

ofpe

rson

nel

atda

nger

zone

s.Pe

rson

nele

vacu

atio

n

23

6

3cPe

rson

nel

ex-

pose

dto

high

tem

pera

ture

and

heat

radi

atio

n

Fire

Impr

oper

faci

lity

desi

gn4

28

Lim

itE

xpos

ure

ofPe

rson

nel

atD

ange

rZ

ones

.Fa

cilit

yde

sign

base

don

haza

rds

32

6

Org

aniz

atio

nal

Haz

ards

4aSa

fety

Cul

ture

Syst

emsa

fety

com

prom

ised

Lac

kof

top

man

-ag

emen

tfoc

uson

safe

ty

53

15M

anag

emen

tfo

cus

onsa

fety

thro

ugh

inte

r/in

tra

com

pany

cam

-pa

igns

,A

ccou

ntab

ility

ofth

eco

mpa

nyto

war

dssa

fety

inci

dent

sth

roug

hin

dust

ryan

dna

tiona

lre

gula

tions

32

6

4bSa

fety

Cul

ture

Wro

ngex

ecut

ion

ofpl

ans

Com

mun

icat

ion

chal

leng

esbe

twee

nst

ake-

hold

ers.

53

15E

stab

lishi

ngsi

ngle

poin

tof

con-

tact

sand

anal

yzin

git

thro

ugh

soci

alne

twor

kan

alys

is

41

4

4cSa

fety

Cul

ture

Syst

emsa

fety

com

prom

ised

Focu

son

deliv

-er

ysc

hedu

lein

-st

ead

ofsa

fety

53

15M

anag

emen

tfo

cus

onsa

fety

thro

ugh

inte

r/in

tra

com

pany

cam

-pa

igns

,A

ccou

ntab

ility

ofth

eco

mpa

nyto

war

dssa

fety

inci

dent

sth

roug

hin

dust

ryan

dna

tiona

lre

gula

tions

32

6

13

Tabl

e4:

Prel

imin

ary

haza

rdan

alys

is(c

ontin

ued)

Initi

alR

isk

Res

idua

lR

isk

Gen

eric

Haz

ard

Iden

tifier

Haz

ard

Acc

iden

tEve

ntPr

obab

leC

ause

sPr

obab

il-ity

Seve

rity

Ris

kL

evel

Prev

entiv

eA

ctio

nsPr

obab

ility

Seve

rity

Ris

kL

evel

Org

aniz

atio

nal

Haz

ards

4dSa

fety

Cul

ture

Pers

onne

lsa

fety

com

prom

ised

Com

plac

ent

attit

ude

tow

ards

safe

ty

52

10M

anag

emen

tfo

cus

onsa

fety

thro

ugh

inte

r/in

tra

com

pany

cam

-pa

igns

,E

stab

lishi

ngco

ntin

uous

impr

ovem

ent

safe

tydr

ive

inth

eco

mpa

ny

32

6

4eSa

fety

Cul

ture

Syst

emsa

fety

com

prom

ised

Ove

rloo

king

pos-

sibi

lity

ofm

ajor

acci

dent

s

53

15M

anag

emen

tfo

cus

onsa

fety

thro

ugh

inte

r/in

tra

com

pany

cam

-pa

igns

,A

ccou

ntab

ility

ofth

eco

mpa

nyto

war

dssa

fety

inci

dent

sth

roug

hin

dust

ryan

dna

tiona

lre

gula

tions

32

6

5aL

ess

than

adeq

uate

mai

n-te

nanc

e

Proj

ectd

elay

Focu

son

deliv

-er

ysc

hedu

lein

-st

ead

ofsa

fety

53

15M

anag

emen

tfo

cus

onsa

fety

thro

ugh

inte

r/in

tra

com

pany

cam

-pa

igns

,A

ccou

ntab

ility

ofth

eco

mpa

nyto

war

dssa

fety

inci

dent

sth

roug

hin

dust

ryan

dna

tiona

lre

gula

tions

32

6

5bSy

stem

safe

tyco

mpr

omis

edL

owqu

ality

au-

dits

(cer

tifica

tion)

44

16A

ccou

ntab

ility

ofth

eco

mpa

nyto

-w

ards

safe

tyin

cide

nts

thro

ugh

in-

dust

ryan

dna

tiona

lreg

ulat

ions

42

8

5cPr

ojec

tde

lay,

Syst

eman

dpe

rson

nel

safe

tyco

mpr

omis

ed

Cos

tcu

tting

inop

erat

ions

42

8R

e-op

timiz

em

aint

enan

ceco

sts

31

3

5dL

ess

than

adeq

uate

com

-pe

tenc

e

Wro

ngde

cisi

onm

akin

gL

ack

oftr

aini

ngan

dex

peri

ence

ofpe

rson

nel

43

12In

vest

men

tin

trai

ning

pers

on-

nel.

Inve

stm

ent

inm

ento

ring

prog

ram

mes

.H

irin

gco

mpe

tent

pers

onne

l.Sh

arin

gle

sson

sle

arne

dto

othe

rcom

pani

es

22

4

5eW

ork

over

load

Lac

kof

pers

onne

l3

412

Hir

ing

com

pete

ntpe

rson

nel

base

don

proj

ect

fore

cast

s.O

utso

urci

ngw

ork

toco

nsul

tant

com

pani

es

32

6

5fC

row

dC

ontr

olM

anov

erbo

ard

Cri

tical

pro-

cess

/pro

cedu

reva

riat

ions

33

9Ti

mel

yce

rtifi

catio

nan

dm

aint

e-na

nce

ofsa

fety

criti

cal

syst

ems,

Plan

sfo

rem

erge

ncy

prep

ared

ness

base

don

faci

lity

desi

gn.

22

4

5gea

rly

laun

chof

life

craf

tsIm

prop

erev

acua

-tio

npr

oced

ure

34

12Pl

ans

for

Em

erge

ncy

Prep

ared

ness

base

don

faci

lity

desi

gn2

24

14

5.3.2 Risk level picture

From Table 3 and 4 a risk picture was established in a 4 X 5 risk matrix. The risk matrix is based on theALARP principle along with classification inputs from [Rausand, 2005]. The classification of probabilityand severity classes are provided in Appendix A of the report. Table 7 provides the color legend for the4 X 5 risk matrix.

Initial risk matrix- The results from the initial risk matrix show 15 hazards, which fall under the notacceptable limits of the ALARP principle. While 5 hazards fall under the acceptable zone of the ALARPprinciple.

Table 5: Initial risk matrixFrequency/Consequence

1-Very Unlikely 2-Remote 3-Occasional 4-Probable 5-Frequent

4-Catastrophic 3b, 5e, 5g 1a, 2a, 3a, 5b

3-Critical 1d 1b, 5f 1c, 5d 4b, 4c, 4e, 5a

2-Major 3c, 5c 4a, 4d

1-Minor

Residual risk matrix- Residual risk matrix demonstrates the risk reduction achieved by introduction ofrisk reducing measures (preventive actions). In other words, the residual risk is the risk left over after theintroduction of risk reducing measures.The results from the residual risk matrix show a reduction in risklevel. 16 hazard items fall under the acceptable zone of the ALARP principle, but these risks can furtherbe reduced by introducing additional preventive actions. While 5 hazard items fall under the acceptablezone of the ALARP principle.

Table 6: Residual risk matrixFrequency/Consequence

1-Very Unlikely 2-Remote 3-Occasional 4-Probable 5-Frequent

4-Catastrophic

3-Critical 1d, 2a, 3a, 3b, 5b

2-Major 1b, 5d, 5g 1a, 3c, 4a, 4c, 4d,4e, 5a, 5e, 5f

1c

1-Minor 5c 4b

Table 7: Risk matrix colour legendColour Legend

Not Acceptable- Risk reduction required

Acceptable using ALARP. Consider further risk reduction.

Acceptable.

15

5.4 Risk treatmentOne of the steps in the PSA barrier management framework is to evaluate need for further risk treatmentafter introducing the preventive actions. In the current study, the residual hazards in the system were aslow as reasonably practicable- ALARP. Therefore, the study continued with the next stage- developingspecific barrier strategy to avoid recurrence of such accidents in the future. The next subsection describesthe barrier functions, sub functions and elements.

5.5 Specific barrier strategyAccording to [PSA, 2013], the setup of barrier management for the offshore industry consists of the fol-lowing steps: the risk picture identifies risks that need reduction; the reduction of these risks is achievedby implementation of barrier functions; barrier functions must be further specified down to barrier ele-ments; to be manageable, these functions or elements need to be measured or evaluated in some way, andthe way to do it is do define which requirements they need to fulfill.

In this section we present the selected barrier functions and elements, both to decrease the probabilitythat an accident may occur, in Figure 5 and to decrease the consequence in case an accident occurs, inFigure 6. Later, in section 5.6 performance requirements/standards, the requirements are presented.

Figure 5 can be roughly divided in two parts, one part where a block diagram presents technical barriers,and the second part where a green rectangle presents man and organizational barriers. These barriers areconnected to the risk picture presented in tables 3 and 4. The same is valid for Figure 6. While technicalbarriers presented in both figures were already in place in Deepwater Horizon albeit containing failures,some of the suggested man and organizational barriers were not part of their barrier strategy in the timeof the accident.

16

Red

uce

Pro

bab

ility

of

Hyd

roca

rbo

n L

eak

fro

m t

he

Wel

l

Iso

late

are

as w

ith

diff

eren

t pr

essu

res

and

flu

ids.

Pr

even

t co

llaps

ing

and

leak

of

wel

l fo

rmat

ion

. R

egu

late

flo

w o

f H

ydro

carb

ons

Kill

th

e w

ell

Avo

id R

ig D

rift

and

Dri

ve o

ff

Avo

id

Ext

ern

al S

hip

C

ollis

ion

Iso

late

d h

ydro

carb

ons

subs

ea.

Ris

ers

BO

PC

asin

gC

asin

gC

entr

aliz

ers

Dri

llin

g M

ud

Barrier Functions Barrier Elements

BO

P

Sub-Functions

Dri

llin

g M

ud

Cho

ke

Val

veK

ill L

ine

Val

ve

BO

P

Emer

gen

cy

Shu

tdo

wn

Dyn

amic

P

osi

tio

nin

gSy

stem

Col

lisio

n

Avo

idan

ce

Ala

rms

Safe

ty Z

one

Reg

ula

tio

ns

Bot

tom

s-up

Pres

sure

Tes

ting

(N

egat

ive

and

P

ost

ive

)

Performance Requirements

Org

an

izat

ion

an

d M

an b

arr

iers

are

incl

ude

d in

ea

ch b

arr

ier

ele

me

nt b

eca

use

the

sele

ctio

n o

f th

e ab

ove

ph

yisc

al b

arr

iers

dep

end

s o

n t

he

ind

ivid

ua

l/o

rga

niz

ati

on

per

cep

tio

ns

in f

orm

o

f a

na

lysi

s a

nd

des

ign

.

M

anag

em

ent

focu

s o

n s

afet

y th

rou

gh c

amp

aign

s. (

Top

to

bo

tto

m a

nd

bo

tto

m t

o to

p)

A

ccou

nta

bili

ty o

f th

e co

mp

any

tow

ard

s sa

fety

inci

den

ts t

hro

ugh

ind

ust

ry a

nd

nati

on

al r

egu

lati

on

s

Esta

blis

hin

g si

ngl

e p

oin

t o

f co

nta

cts

and

an

alys

ing

it t

hro

ugh

Soc

ial N

etw

ork

An

alys

is t

ools

C

on

tin

uo

us im

pro

vem

ent

of

safe

ty d

rive

in t

he

co

mp

any

and

exp

ansi

on

of

each

pro

ject

’s R

isk

An

alys

is A

sses

smen

t to

ke

ep u

p w

ith

ch

ange

s m

ade

to t

he

ori

gin

al p

lan

d

uri

ng

the

exe

cuti

on

phas

e -

co

nti

nu

ous

re

asse

ssm

ent

of t

he r

isk

pic

ture

.

Per

iodi

cally

re

-op

tim

ize

mai

nte

nan

ce c

osts

In

vest

men

t in

co

nti

nuo

us

trai

nin

g o

f p

erso

nne

l in

best

ava

ilab

le s

afet

y p

ract

ices

In

vest

men

t in

men

tori

ng p

rogr

amm

es

Hir

ing

com

pet

ent

per

son

nel

Sh

arin

g le

sso

ns

lear

nt

to o

ther

co

mp

anie

s

Tim

ely

ce

rtif

icai

ton

an

d m

ain

ten

ance

of

safe

ty c

riti

cal s

yste

ms

Figu

re5:

Prop

osed

barr

ierm

anag

emen

t-pr

even

tacc

iden

ts

17

Red

irec

t H

ydro

carb

ons

to S

afe

Are

a

Red

uce

Co

nse

qu

en

ce o

f H

ydro

carb

on

Lea

k

Red

uce

Dur

atio

n an

d Si

ze o

f Le

ak

Lim

it E

xpo

sure

of

Pe

rso

nn

el

at D

ange

r Zo

nes

Pla

ns

for

Emer

gen

cy

Prep

ared

ness

Per

son

nel

Eva

cuat

ion

Red

uce

Risk

of E

xplo

sio

n

Fire

& G

as

Det

ecti

on

Ala

rm a

nd

Del

uge

Sys

tem

s

Emer

gen

cy

Proc

edu

res

Fire

& G

as

Det

ecti

on

Proc

ess

Shud

own

Sy

stem

s

Fire

and

Gas

Det

ecto

rs

Emer

gen

cy

Safe

ty

Proc

edu

res

Sh

ud

ow

n

Proc

ess

Fire

and

Gas

De

tect

ors

Safe

ty A

larm

sSp

rink

lers

Faci

lity

Des

ign

Bas

ed

on H

aza

rds

Expl

osio

n R

esis

tant

C

onst

ruti

on

Are

a Is

ola

tio

n

(Res

tric

ted

Per

son

nel

Acc

ess

Are

as)

Life

boa

tsSu

pp

ort

V

esse

ls

Pers

onn

el

Prot

ecti

ve

Eq

uip

me

nt

Barrier Functions Barrier ElementsSub-Functions

Org

an

izat

ion

an

d M

an b

arr

iers

are

incl

ude

d in

ea

ch b

arr

ier

ele

me

nt b

eca

use

the

sele

ctio

n o

f th

e ab

ove

ph

yisc

al b

arr

iers

dep

end

s o

n t

he

ind

ivid

ua

l/o

rga

niz

ati

on

per

cep

tio

ns

in f

orm

o

f a

na

lysi

s a

nd

des

ign.

M

anag

em

ent

focu

s o

n s

afet

y th

rou

gh c

amp

aign

s. (

Top

to

bo

tto

m a

nd

bo

tto

m t

o to

p)

A

ccou

nta

bili

ty o

f th

e co

mp

any

tow

ard

s sa

fety

inci

den

ts t

hro

ugh

ind

ust

ry a

nd

nati

on

al r

egu

lati

on

s

Esta

blis

hin

g si

ngl

e p

oin

t o

f co

nta

cts

and

an

alys

ing

it t

hro

ugh

Soc

ial N

etw

ork

An

alys

is t

ools

C

on

tin

uo

us im

pro

vem

ent

of

safe

ty d

rive

in t

he

co

mp

any

and

exp

ansi

on

of

each

pro

ject

’s R

isk

An

alys

is A

sses

smen

t to

ke

ep u

p w

ith

ch

ange

s m

ade

to t

he

ori

gin

al p

lan

d

uri

ng

the

exe

cuti

on

phas

e -

co

nti

nu

ous

re

asse

ssm

ent

of t

he r

isk

pic

ture

.

Per

iodi

cally

re

-op

tim

ize

mai

nte

nan

ce c

osts

In

vest

men

t in

co

nti

nuo

us

trai

nin

g o

f p

erso

nne

l in

best

ava

ilab

le s

afet

y p

ract

ices

In

vest

men

t in

men

tori

ng p

rogr

amm

es

Hir

ing

com

pet

ent

per

son

nel

Sh

arin

g le

sso

ns

lear

nt

to o

ther

co

mp

anie

s

Tim

ely

ce

rtif

icai

ton

an

d m

ain

ten

ance

of

safe

ty c

riti

cal s

yste

ms

Figu

re6:

Prop

osed

barr

ierm

anag

emen

t-m

itiga

teco

nseq

uenc

es

18

5.6 Performance requirements/standardsPSA requires that safety barriers are specified along with their performance requirements in order toensure effective barrier management [PSA, 2013]. The main goal of this process is to ensure "measure-ment" of barrier performances to predefined barrier requirements.

Table 8, 9, 10 present requirements for the proposed barrier strategy. The barriers in Table 8 correspondto reducing probability of hydrocarbon leak from the well refer figure 5 while, Table 9 corresponds toreducing the consequence of hydrocarbon leak refer figure 6. Table 10 corresponds to both figures 5 and6.

Table 8: Barrier performance standard- functional levelBarrier Performance Standard Performance Standard

(Functionality, Integrity, Vulnera-bility)

Isolate areas with different pres-sures and fluids

Functionality Established pressure limits in various zones

Prevent collapsing and leak of wellformation

Functionality Loss of drilling mud should not exceed the given limit

Regulate flow of Hydrocarbons Integrity Minimum failure rate of BOP through quantitative analysis.Example- SIL analysis

Isolated hydrocarbons subsea Integrity Minimum failure rate of BOP through quantitative analysis.Example- SIL analysis

Avoid Rig Drift and Drive off Functionality Limits and accuracy dynamic positioning system envelopes

Table 9: Barrier performance standard- element levelBarrier Performance Standard Performance Standard

(Functionality, Integrity, Vulnera-bility)

Fire and Gas Detectors Integrity Determine acceptable failure rate of detectors through quanti-tative analysis. Example- SIL analysis

Emergency Safety Procedures Functionality Be aligned with the risk pictureSafety Alarms Integrity Determine acceptable failure rate of detectors through quanti-

tative analysis. Example- SIL analysisSprinklers Integrity Determine acceptable failure rate of FF equipment through

quantitative analysis. Example- SIL analysisProcess Shutdown Systems Integrity Determine acceptable failure rate of Process Shutdown System

through quantitative analysis. Example- SIL analysisLifeboats Functionality Have sufficient capacity to include all personnel onboard the

rigSupport Vessels Functionality Response to an emergency call within a given time limitRestricted Personnel Access Areas Functionality Normally manned working stations should be sheltered or out

of reach from potential explosions caused by HC releasePersonnel Protective Equipment Vulnerability Guarantees impact and thermal protection to a stipulated level

19

Table 10: Barrier performance standard- organization levelBarrier Performance Standard Performance Standard

(Functionality, Integrity, Vulnera-bility)

Management focus on safety through campaigns Functionality Commit management time to safety activi-ties. Safety walk. Walk-Observe-Feedback.

Accountability of the company towards safety inci-dents through industry and national regulations

Functionality Social corporate responsibility drive

Establishing single point of contacts and analyzing itthrough Social Network Analysis tools

Functionality Make contact information of single points ofcontact public and know

Continuous improvement of safety drive in the com-pany and expansion of each project’s Risk AnalysisAssessment to keep up with changes made to the orig-inal plan during the execution phase - continuous re-assessment of the risk picture.

Functionality Risk Analysis Assessments should be re-viewed at fixed intervals during planningphase and whenever a major modification toplan occurs during project execution

Periodically re-optimize maintenance costs Functionality At predetermined given time intervals, aim-ing to cut a given percentage of labor

Investment in continuous training of personnel in bestavailable safety practices

Functionality Annual evaluation of relevant technicalknowledge

Investment in mentoring programmes Functionality Ensure mentoring program for new employ-ees

Hiring competent personnel Functionality Assessment of technical knowledge and per-sonality

Sharing lessons learnt to other companies Functionality Target number of published industry whitepapers

Timely certification and maintenance of safety criticalsystems

Integrity Traceability of equipment and process cer-tificates

6 ConclusionsThrough this accident analysis, it is observed that complex systems tag along with complex accidentpropagation. The consequences in such systems also highlight the need for continued focus on barriermanagement. However, to understand the nature of faults and failures in such systems a thorough riskanalysis is paramount.

Organizational and human barriers and their performance requirements are difficult to define, maintain,and measure. Nonetheless, these barriers are frequently in demand during offshore accident progression.The current study observed that the amount of organization and human barriers that failed in the Macondoblowout increased both the probability of blowout occurrence as well as the consequences associate withthe blowout. In instances in this accident, technical barrier failed on account of previous organizationalor human barrier failure. For example, the failure to certificate the BOP probably allowed the wiring ofthe pods to go amiss and the battery on the yellow pod to discharge ahead of time, both technical failures.The same happened in the numerous attempts to control the HC leak to the sea, after the rig had sunk.

This study points on the direction that inadequate human and organizational barrier functions were tightlyconnected to the development of the Macondo accident. It indicates that there is room for improvementin assessment and treatment of major accidents scenarios, and that system safety should not be neglectedin favor of traditional HSE performance indicators.

20

References[CSB, 2007] CSB, U. (2007). CSB Safety Video: Explosion at BP Refinery . YouTube Video-

http://youtu.be/c9JY3eT4cdM.

[CSB, 2014] CSB, U. (2014). Deepwater Horizon Blowout Animation . YouTube Video-https://www.youtube.com/watch?v=FCVCOWejlag.

[Ideum - ideas + media, 2010] Ideum - ideas + media (2010). Deepwater horizon offshore drilling plat-form on fire. Photo.

[Petroleum Safety Authority Norway- PSA, 2014] Petroleum Safety Authority Norway- PSA (2014).PSA regulations. Webpage.

[PSA, 2013] PSA, P. (2013). Principles for barrier management in the petroleum industry. Technicalreport.

[Rausand, 2005] Rausand, M. (2005). Lecture Notes- Risk Assessment- Preliminary Hazard Analysis(PHA).

[Rausand, 2011] Rausand, M. (2011). Risk Assessment : Theory, Methods, and Applications. John Wiley& Sons, Inc.

[Sklet, 2006] Sklet, S. (2006). Safety barriers on oil and gas platforms. means to prevent hydrocarbonreleases.

[The Deepwater Horizon Study Group (DHSG), 2011] The Deepwater Horizon Study Group (DHSG)(2011). Final report on the investigation of the macondo well blowout. Technical report, Center forCatastrophic Risk Management (CCRM).

[Vinnem, 2014] Vinnem, J. E. (2014). Offshore Risk Assessment Vol 1 and 2, volume 1 and 2. Springer,London, 3rd edition edition.

21

A Appendix- PHA Parameters

A.1 Probability ClassesTable 11 presents classification of probability classes as suggested by [Rausand, 2005].

Table 11: Probability classesRank Probability class Description1 Very unlikely Once per 1000 years or more seldom2 Remote Once per 100 years3 Occasional Once per 10 years4 Probable Once per year5 Frequent Once per month or more often

A.2 Severity ClassesTable 12 presents classification of severity classes as suggested by [Rausand, 2005].

Table 12: Severity classesRank Severity class Description4 Catastrophic Failure results in major injury or death of per-

sonnel.3 Critical Failure results in minor injury to personnel, per-

sonnel exposure to harmful chemicals or radia-tion, or fire or a release of chemical to the envi-ronment

2 Major Failure results in a low level of exposure to per-sonnel, or activates facility alarm system.

1 Minor Failure results in minor system damage but doesnot cause injury to personnel, allow any kind ofexposure to operational or service personnel orallow any release of chemicals into the environ-ment.

22