analysis and discussion of deepwater horizon accident · pdf fileintroduction failed barrier...
TRANSCRIPT
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
Analysis and Discussion of Deepwater HorizonAccident and Barrier Strategies
Nathalie M. De Oliveira,Jeevith Hegde
Faculty of Engineering Science and Technology,Department of Marine Technology, NTNU
[email protected]@ntnu.no
January 23, 2015
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
Content
1 IntroductionSummary of Macando BlowoutComparison to other similar accidents
2 Failed Barrier AnalysisStep DiagramMTO AnalysisBow-Tie Diagram
3 Proposed Barrier StrategyPSA ProcessHazard IdentificationSpecific Barrier StrategyBarrier Requirements
4 Conclusion
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
Summary of Macando BlowoutComparison to other similar accidents
Accident Summary
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
Summary of Macando BlowoutComparison to other similar accidents
Comparison to other similar accidents
Similar Blowout Accidents
Macondo 2010
Initiating event- High pressures in the wellboreAccident Progression- Well abandonment- kick inwell- hydrocarbon leak- two explosionsFatalities- 11 of 126 (9%)
Usumacinta 2007
Initiating event- Bad weatherAccident Progression- Storm- hydrocarbon leakFatalities- 22 of 81 (27%)
Enchova 1984
Initiating event- UnknownAccident Progression- Drilling- Gas leakFatalities- 42 of 249 (17%)
The evacuation process in Deepwater Horizon, did notresult in fatalities [Vinnem, 2014].
One could infer that Transocean had better evacuationprocedures than PEMEX (Usumacinta) or Petrobras(Enchova).
Texas City Refinery
Initiating event- Overfilling of splitter tower.Accident Progression- Maintenance faults- malfunction oflevel transmitters- explosionFatalities- 15 peopleInjured- 170 people
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
Step DiagramMTO AnalysisBow-Tie Diagram
Step Diagram
Loss of Circulation at 18260ft and
18360ft- Stopped DrillingB
P
Actors Even
ts
Hal
libur
ton
Tran
soce
anM
iner
als
Ma
nag
em
ent
Se
rvic
es
Marinas changed to Deepwater
Horizon
BOP: Leak in yellow Pod
February 2010 March 2010
Approved Single Long string cas ing design
April 2010
Choice of Long String Casing to complete the
well.
April 9 2010 April 12 2010April 15
2010
6 Central izers installed
April 16 2010
Decision to use 7 Central izers
Analyzed 7 Central izers design
Report issued to BP with concerns on
number of centrali zer used sent
after cementing
April 18 2010
April 19 2010
Incomplete Bottoms Up operations
April 20 2010
Early Presurre Testing. Before Cement Setting.
Simultaneous Operat ions
Different Iterpretation of Two Negative Pressure Test
Well Kick
Redirected Gas to
Separator
13:28 Hours 20:00 Hours 21:45 Hours
Outage of Power
Explosion 1 and 2
Alarm Software
Disconnected
EDS Malfunction
Man
Organization
Technology
Barrier Legend
21:49 Hours 21:52 Hours
Uncontrolled HC Leak
Bending of Drill Pipe
Figure: Step Diagram
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
Step DiagramMTO AnalysisBow-Tie Diagram
MTO Analysis
Failed MTO Barriers
Man
Organization
Technology
2
0
3
5
3
1
2
Failures in the intersection ofman and organizational barriersare higher in number than othercategories.
The combination of man andorganization resulted in six failedbarriers
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
Step DiagramMTO AnalysisBow-Tie Diagram
Bow-Tie Diagram
Barrier Legend
Macondo Blowout
Man
Organization
Technology
Single String Completion Casing
We
llh
ead
Sea
l
Cho
ice
of S
ingl
e St
ring
Cas
ing
Blow Out Preventer
She
ar R
ams
An
nul
ar
Prev
ento
rs
Pipe
Ram
s
BO
P
Cer
tifi
cati
on
Pressure Testing
Test
ing
afte
r C
emen
t Se
t
Val
ida
te T
est
R
esul
ts
Centralizers
Inte
rnal
C
omm
uni
cati
on
Val
ida
te R
esu
ltsEnergy
Flow
HC Detection and Mitigation
Mai
nte
na
nce
of
F&G
Bar
rier
s
Explosion
Fire
& G
as
De
tect
ion
Emer
gen
cy
Pre
pa
red
ne
ss
Red
irec
tio
n o
f HC
Ala
rm a
nd
Del
uge
Sy
stem
s
Fire
Fig
htin
g Sy
ste
m
Evacuation
Energy Flow
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
PSA ProcessHazard IdentificationSpecific Barrier StrategyBarrier Requirements
PSA Barrier Mangement Process
Figure: [PSA, 2013]
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
PSA ProcessHazard IdentificationSpecific Barrier StrategyBarrier Requirements
Hazard Identification
SL. No. Generic Hazard Hazard
1 Mechanical hazards High/unstable pressure in the wellStabilityDegradation of equipment
2 Dangerous materials Flammable
3 Thermal hazards FlameExplosionPersonnel exposed to high temperature and heat radi-ation
4 Organizational hazards Safety cultureLess than adequate maintenanceLess than adequate competenceCrowd control
[Rausand, 2011]
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
PSA ProcessHazard IdentificationSpecific Barrier StrategyBarrier Requirements
Preliminary Hazard Analysis
Terminologies
Generic Hazard
Mechanical, dangerous, thermal and organizational.
Identifier
Identify and arrange different probable causes.
Hazard
Specific hazard in relation to generic hazard.
Accidental Event
Describe what, when, where things can go wrong.
Probable Causes
Causes triggering the accidental event.
Probability
Evaluating likelihood of occurrence of an accidentevent.
Severity
Evaluating consequences if an accident eventoccurs.
Initial Risk Level
Factor of probability, severity and lack of preventivemeasures.
Residual Risk Level
Factor of probability, severity and introduction ofpreventive measures.
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
PSA ProcessHazard IdentificationSpecific Barrier StrategyBarrier Requirements
Risk Picture
Initial Risk Picture
Residual Risk Picture
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
PSA ProcessHazard IdentificationSpecific Barrier StrategyBarrier Requirements
Barriers according to PSA Memo- Part 1
Reduce Risk of Hydrocarbon Leak from the Well
Isolate areas with different pressures and fluids.
Prevent collapsing and leak of well formation.
Regulate flow of Hydrocarbons
Kill the well
Avoid Rig Drift and Drive off
Avoid External Ship
Collision
Isolated hydrocarbons subsea.
Risers BOP Casing Casing CentralizersDrilling
Mud
Bar
rie
r F
un
ctio
ns
Bar
rier
Ele
men
ts
BOP
Sub
-Fu
ncti
ons
Drilling Mud
Choke Valve
Kill Line Valve
BOP
Emergency Shutdown
Dynamic Positioning
System
Collision Avoidance
Alarms
Safety Zone Regulations
Bottoms-up
Pressure Testing (Negative and
Postive)
Perf
orm
ance
Req
uire
men
ts
Organization and Man barriers are included in each barrier element because the selection of the above phyiscal barriers depends on the individual/organization perceptions in form of analysis and design.
Management focus on safety through campaigns. (Top to bottom and bottom to top) Accountability of the company towards safety incidents through industry and national regulations Establishing single point of contacts and analysing it through Social Network Analysis tools Continuous improvement of safety drive in the company and expansion of each project’s Risk Analysis Assessment to keep up with changes made to the original plan
during the execution phase - continuous reassessment of the risk picture. Periodically re-optimize maintenance costs Investment in continuous training of personnel in best available safety practices Investment in mentoring programmes Hiring competent personnel Sharing lessons learnt to other companies Timely certificaiton and maintenance of safety critical systems
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
PSA ProcessHazard IdentificationSpecific Barrier StrategyBarrier Requirements
Barriers according to PSA Memo- Part 2
Redirect Hydrocarbons to Safe Area
Reduce Consequence of Hydrocarbon Leak
Reduce Duration and Size of Leak
Limit Exposure of Personnel at Danger Zones
Plans for Emergency Preparedness
Personnel EvacuationReduce Risk of Explosion
Fire & Gas
Detection
Alarm and
Deluge Systems
Emergency Procedures
Fire & Gas
Detection
Process Shudown Systems
Fire and Gas
Detectors
Emergency Safety
Procedures
Shudown Process
Fire and Gas
DetectorsSafety Alarms Sprinklers
Facility Design Based on Hazards
Explosion Resistant
Constrution
Area Isolation (Restricted Personnel
Access Areas)
LifeboatsSupport Vessels
Personnel Protective Equipment
Bar
rier
Fun
ctio
nsB
arri
er E
lem
ents
Sub
-Fu
ncti
on
s
Organization and Man barriers are included in each barrier element because the selection of the above phyiscal barriers depends on the individual/organization perceptions in form of analysis and design.
Management focus on safety through campaigns. (Top to bottom and bottom to top) Accountability of the company towards safety incidents through industry and national regulations Establishing single point of contacts and analysing it through Social Network Analysis tools Continuous improvement of safety drive in the company and expansion of each project’s Risk Analysis Assessment to keep up with changes made to the original plan
during the execution phase - continuous reassessment of the risk picture. Periodically re-optimize maintenance costs Investment in continuous training of personnel in best available safety practices Investment in mentoring programmes Hiring competent personnel Sharing lessons learnt to other companies Timely certificaiton and maintenance of safety critical systems
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
PSA ProcessHazard IdentificationSpecific Barrier StrategyBarrier Requirements
Barrier Performance Requirement- Functional Level
Barrier Performance Stan-dard
Performance Standard
(Functionality, In-tegrity, Vulnerability)
Isolate areas with different pres-sures and fluids
Functionality Established pressure limits in various zones
Prevent collapsing and leak ofwell formation
Functionality Loss of drilling mud should not exceed the given limit
Regulate flow of Hydrocarbons Integrity Minimum failure rate of BOP through quantitativeanalysis. Example- SIL analysis
Isolated hydrocarbons subsea Integrity Minimum failure rate of BOP through quantitativeanalysis. Example- SIL analysis
Avoid Rig Drift and Drive off Functionality Limits and accuracy dynamic positioning system en-velopes
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
PSA ProcessHazard IdentificationSpecific Barrier StrategyBarrier Requirements
Barrier Performance Requirement- Element Level
Barrier Performance Stan-dard
Performance Standard
(Functionality, In-tegrity, Vulnerability)
Fire and Gas Detectors Integrity Determine acceptable failure rate of detectors throughquantitative analysis. Example- SIL analysis
Emergency Safety Procedures Functionality Be aligned with the risk pictureSafety Alarms Integrity Determine acceptable failure rate of detectors through
quantitative analysis. Example- SIL analysisSprinklers Integrity Determine acceptable failure rate of FF equipment
through quantitative analysis. Example- SIL analysisProcess Shutdown Systems Integrity Determine acceptable failure rate of Process Shutdown
System through quantitative analysis. Example- SILanalysis
Lifeboats Functionality Have sufficient capacity to include all personnel on-board the rig
Support Vessels Functionality Response to an emergency call within a given timelimit
Restricted Personnel Access Ar-eas
Functionality Normally manned working stations should be shelteredor out of reach from potential explosions caused by HCrelease
Personnel Protective Equipment Vulnerability Guarantees impact and thermal protection to a stipu-lated level
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
PSA ProcessHazard IdentificationSpecific Barrier StrategyBarrier Requirements
Barrier Performance Requirement- Organizational Level
Barrier Performance Stan-dard (Functionality,Integrity, Vulnerabil-ity)
Performance Standard
Management focus on safety through cam-paigns
Functionality Commit management time to safety activi-ties. Safety walk. Walk-Observe-Feedback.
Accountability of the company towardssafety incidents through industry and na-tional regulations
Functionality Social corporate responsibility drive
Establishing single point of contacts andanalyzing it through Social Network Analy-sis tools
Functionality Make contact information of single pointsof contact public and know
Continuous improvement of safety drivein the company and expansion of eachprojects Risk Analysis Assessment to keepup with changes made to the original planduring the execution phase - continuous re-assessment of the risk picture.
Functionality Risk Analysis Assessments should be re-viewed at fixed intervals during planningphase and whenever a major modificationto plan occurs during project execution
Periodically re-optimize maintenance costs Functionality At predetermined given time intervals, aim-ing to cut a given percentage of labor
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
PSA ProcessHazard IdentificationSpecific Barrier StrategyBarrier Requirements
Barrier Performance Requirement- Organizational Level
Barrier Performance Stan-dard (Functionality,Integrity, Vulnerabil-ity)
Performance Standard
Investment in continuous training of per-sonnel in best available safety practices
Functionality Annual evaluation of relevant technicalknowledge
Investment in mentoring programmes Functionality Ensure mentoring program for new employ-ees
Hiring competent personnel Functionality Assessment of technical knowledge and per-sonality
Sharing lessons learnt to other companies Functionality Target number of published industry whitepapers
Timely certification and maintenance ofsafety critical systems
Integrity Traceability of equipment and process cer-tificates
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
Conclusion
1 Complex systems = complex accident propagation
2 Risk analysis must be performed and updated
3 Barrier management is paramount
4 Organizational and human barriers are constantly in demandduring accident progression
5 Systems safety should not be neglected in favor of traditionalHSE indicators
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
References
CSB, (2007)
CSB Safety Video: Explosion at BP Refinery.YouTube: http://youtu.be/c9JY3eT4cdM
CSB, (2014)
Deepwater Horizon Blowout Animation.YouTube: https://www.youtube.com/watch?v=FCVCOWejlag
Petroleum Safety Authority Norway- PSA (2014)
PSA regulations.Webpage: PSA regulations
PSA, (2013)
Principles for barrier management in the petroleum industryTechnical Report
Rausand, M, (2005)
Lecture Notes- Risk Assessment- Preliminary Hazard Analysis (PHA).
Rausand, M, (2011)
Risk Assessment : Theory, Methods, and Applications.Book- John Wiley & Sons, Inc.
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project
IntroductionFailed Barrier Analysis
Proposed Barrier StrategyConclusion
References
Sklet, (2006)
Safety barriers on oil and gas platforms. Means to prevent hydrocarbon releases.PhD Thesis
(DHSG)(2011)
The Deepwater Horizon Study Group (DHSG)(2011). Final report on the investigation of the Macondo wellblowoutTechnical report, Center for Catastrophic Risk Management (CCRM).
Vinnem (2014)
Offshore Risk Assessment Vol 1 and 2Springer, London, 3rd edition
Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project