Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 1 An-Najah National University Faculty of Engineering & IT Department of Building Engineering Construction Project Management Course code: 10611472 Dr. Luay Dwaikat PhD Construction Economics & Management Course Outline Introduction to project management Project Work breakdown Time Planning & Scheduling Techniques Critical Path Method – CPM Resources Management & Planning Cost Planning Cash Flow Analysis Time Cost Trade-Off Crashing a schedule Project Monitoring & Control Earned Value Management Computer Applications in CM

Upload: others

Post on 21-Mar-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 1

An-Najah National University Faculty of Engineering & IT Department of Building Engineering

Construction Project Management

Course code: 10611472

Dr. Luay Dwaikat PhD Construction Economics & Management

Course Outline

Introduction to project management Project Work breakdown Time Planning & Scheduling Techniques Critical Path Method – CPM Resources Management & Planning Cost Planning Cash Flow Analysis Time Cost Trade-Off Crashing a schedule Project Monitoring & Control Earned Value Management Computer Applications in CM

Page 2: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 2

Grading System

1st exam 25 %

2nd exam 25 %

Final exam 50 %

Hope You Success

Text Book & References

Text Book: Hinze, J.W., 2011. Construction Planning and

Scheduling, 4th edition. Pearson Prentice Hall, New Jersy, USA

References: Mubarak, S., 2010. Construction Project Scheduling and Control,

2nd edition. John Wiley & Sons, Inc, Hoboken, New Jersey

PMI, 2013. A guide to the project management body of knowledge (PMBOK guide), 5th ed. Project Management Institute, Inc., Pennsylvania, USA

PMI, 2011. Practice Standard for Earned Value Management, 2nd ed. Project Management Institute, Inc, Pennsylvania, USA

Page 3: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 3

Communication & Contact

You can use the Zagel system to post your comments and enquiries in the discussion forum.

Frequently check the Zagel system to find my assignments .

Before we start

Attend the class on time.

Switch off your mobile.

Stop the side talks.

Be a smart listener.

Use your analytical skills.

Question every piece of information you acquire.

Page 4: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 4

What is a Project?

A project is defined as a temporary endeavor (effort) undertaken to create a unique product or service. Has a definite beginning and a definite end.

Project Characteristics

Temporary

Unique

definite beginning and a definite end

Consumes resources

Page 5: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 5

Examples of projects include: • Developing a new product or service. • Designing a new transportation vehicle. • Constructing a building or facility. • Running a campaign for political office. • Implementing a new business procedure or

process.

What is Project Management?

Project management is the application of knowledge, skills, tools and techniques to project activities in order to meet or exceed stakeholder needs and expectations from a project.

Project management is the planning, organizing, directing, and controlling of company resources for a relatively short-term objective that has been established to complete specific goals and objectives.

Page 6: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 6

Management Functions

● Planning

● Organizing

● Staffing

● Directing

● Controlling

What are the stakeholder needs?

competing demands among:

• time, cost, and quality.

• Identified requirements (needs) and

unidentified requirements (expectations).

Page 7: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 7

Project Management Components

Scope

Time

Cost

Quality

Human Resource

Communications

Risk

Procurement

In construction

Project Management is the sum of all activities such as Planning,organising ,implementing and controlling a project in order to meet the client’s expectation from start to finish within the planned period, budget and quality.”

Page 8: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 8

Project Constraints

Constraints triangle:

Time

Cost

Quality

Why a Project Fails???

Unclear project objectives

Unrealistic expectations

Risk not identified

Inadequate planning & co-ordination

Resources are not available

Low productivity

Weak project & technical management

Page 9: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 9

Why a Project Fails???

Ineffective project organization

Inadequate quality systems

Inappropriate management control system

Poor team co-ordination

CONSTRUCTION PROJECTS

Page 10: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 10

Project life cycle – Owner Perspective

1) Pre construction/Design

2) Procurement

3) Construction

4) Close-out

1) Pre construction

This stage includes the following phases:

1) conceptual planning

2) schematic design

3) design development

4) contract documents

Page 11: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 11

2) Procurement

Also known as award or biding phase

The project formally transits from design into construction

This stage begins with a public advertisement for all interested bidders or an invitation for specific bidders

In fast-track projects, this phase overlaps with the design phase

It is very important stage to select highly qualified contractors.

is not wise to select the under-bid contractors

3) Construction/Execution

The actual physical construction of the project

This stage takes the project from procurement through the final completion

It is the time where the bulk of the owner’s funds will be spent

It is the outcome of all previous stages (i.e., good preparation means smooth construction)

Changes during construction may hinder the progress of the project

Page 12: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 12

4) Close-out

Transition from design and construction to the actual use of the constructed facility

In this stage, the management team must provide documentation, shop drawings, as-built drawings, and operation manuals to the owner organization (as-built drawings are the original contract drawings adjusted to reflect all the changes that occurred)

Assessment of the project team’s performance is crucial in this stage for avoiding mistakes in the future.

Actual activity costs and durations should be recorded and

compared with that was planned. This will serve as the basis for the estimating and scheduling of future projects

Ref.

Hinze, J.W., 2011. Construction Planning and Scheduling, 4th edition. Pearson Prentice Hall, New Jersy, USA

CONSTRUCTION PLANNING AND

SCHEDULING

Page 13: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 13

Planning

The road to project failure is paved with poor plans

PLANNING: Influencing the future by making decisions today based on missions, needs and objectives.

It is an art not science.

Planning is NOT a one time activity

Page 14: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 14

Categories of planning:

Time

Cost

Resources

Quality

Contingency

Time Planning

When to start

when to finish

Time plans will be transformed to schedule (time scale)

Page 15: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 15

Time planning steps

1) Divide project into component parts

2) Sequencing component parts in order of

accomplishment

3) Assign durations to each component

part

Cost Planning

Allocating direct and indirect costs to the project components

Expenditure/revenue

( cost / schedule integration)

Page 16: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 16

Resources Planning

Construction Resources includes:

money

Material

Human resources

Equipments and tools

Check if the needed resources are available or NOT.

Eliminate idle time.

Resources should be planned considering the budget.

Attention to critical resources for project success

Quality Planning

what is the minimum accepted quality?

Should I exceed the required quality?

How can I achieve this quality?

Page 17: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 17

Contingency (Risk) Planning

Planning for variability and uncertainty

“What if” planning to include items subject to variability which are significantly impact project cost and time

Control The heart of the project management system is CONTROLLING

the execution of the works.

The purpose of this control is to determine and predict deviations in a project so corrective actions can be taken.

The milestones of the control process are as follows: To determine the aim To evaluate the actual results and to compare to the planned

Page 18: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 18

Control

İt defines the quality of the management

Construction scheduling

Page 19: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 19

Construction scheduling

To be able to build up a successful schedule. You need to:

1) Define activities

2) Establish activities relationships 3) assign durations to activities 4) resources and costs allocation 5) calculate early and late start/finish times 6) calculate float values and identify the critical

path

Construction activity

Anything that must be accomplished in order to complete the project may be considered as activity.

Consumes time and resources.

Activity duration: is the estimated time required to complete an activity.

Page 20: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 20

Project Breakdown

Work Breakdown Structure

Integrating Planning Integration of time, cost and resource

planning against the same basic structure (WBS)

Resource budgeting against time

Cost budgets plotted against time

Page 21: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 21

Thousands of tasks

The psychologists say our brains can normally comprehend around 7-9 items simultaneously.

So, divide and subdivide the project.

The WBS (Work Breakdown Structure)

It is used to break down the project from one main and relatively big entity into smaller, defined, manageable and controllable units, usually called work groups (packages) or tasks, or, at the finest level of detail (which is undesirable) activities

Page 22: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 22

Take care!!!

The deeper you go into the lower levels of the WBS, the more detailed knowledge you’ll need to know.

See next slide.

House

Structure

Mechanical

Electrical

Sub – str.

Super str.

HVAC

Plumbing

Earth work

Foundation

Str. elements

Finishing

Excavation

Backfilling

leveling

Blinding

footings

Tie beams

Ground slab

columns

beams

Roof slab

Level 2

Level 3

Level 4

Level 5

Level 1

1.0

1.1 1.2 1.3

1.1.1 1.1.2 1.2.1 1.2.2

1.1.2.2 1.1.2.1 1.1.1.2 1.1.1.1

Plaster

Tile

painting

Doors &

windows

Page 23: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 23

The WBS

(Work Breakdown Structure) 1.0 house

1.1 structure

1.1.1 sub – structure

1.1.1.1 earth work

E10 excavation

E20 backfilling

E30 leveling

1.1.1.2 foundation

F10 blinding

F20 footings

F30 tie beams

F40 ground slab

1.1.2 super structure

1.1.2.1 structural elements

CS10 columns

CS 20 beams

CS 30 roof slab

1.1.2.2 finishing

C10 plaster

C20 tile

C30 painting

C40 doors & windows

1.2 mechanical

1.2.1 HVAC

The WBS

it is a major task to undo.

Why???

Because cost collections begins at a WBS element,

Page 24: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 24

Conclusion

The work breakdown structure defines the product elements (work packages).

And their interrelations to each other and to the product.

The WBS mostly ends with project tasks.

Using the tasks you can extract project’s activities.

Construction scheduling

Page 25: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 25

Construction scheduling

To be able to build up a successful schedule. You need to:

1) Define activities

2) Establish activities relationships 3) assign durations to activities 4) resources and costs allocation 5) calculate early and late start/finish times 6) calculate float values and identify the critical

path

Construction activities

Anything that must be accomplished in order to complete the project may be considered as activity.

Page 26: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 26

Activities Duration

Activity duration: is the estimated time required to complete an activity.

Activity duration mainly calculated based on:

1) the quantities take off.

2) labor or machines productivity rates.

Activities Duration

Durations could be estimated by experience. ( previous similar jobs)

If experience not available, others experience could be utilized.

If not, handbooks of productivity rates are available provide the required information.

Page 27: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 27

Activities Duration

Activity duration can be calculated as follows:

quantity of the work

= crew hours

qty / crew hour

qty / crew hour is the productivity rate.

Time unit is hours could be changed to working days.

Activities Duration

Example: assume that you have a floor tile area of 600 M2 , and the productivity rate of a tile mason and one helper is 1.5 M2 / hour.

By applying the previous equation:

600 M2

= 400 hours

1.5 M2 / h

If the time unit is working day ( 8 hours) :

400 hours

= 50 days

8 hours

Page 28: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 28

Activities Duration

By using two tile masons and two helpers:

600 M2

= 200 hours

2 x 1.5 M2 / h

If the time unit is working day ( 8 hours) :

200 hours

= 25 days

8 hours

Activities Duration

By using 3 tile masons and 3 helpers:

600 M2

= 133.3 hours = 134 hours

3 x 1.5 M2 / h

If the time unit is working day ( 8 hours) :

134 hours

= 16.75 days = 17 days

8 hours

Time preferably should be rounded up :

Page 29: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 29

Activities Duration

By using 4 tile masons and 4 helpers:

600 M2

= 100 hours

4 x 1.5 M2 / h

If the time unit is working day ( 8 hours) :

100 hours

= 12.5 days = 13 days

8 hours

Activities Duration

Assume in the previous example that this activity is critical and should be finished within 5 days:

If the working day is 8 hours :

5 days X 8 hours = 40 hours Apply the equation :

600 M2

= 40 hours X

X = 15 M2 / h is the productivity rate The crew number should be 15 / 1.5 = 10 gangs

Page 30: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 30

Activities Duration Vs. Direct Cost

Having defined an activity duration, it means that the planner have already defined the number of resources that will be employed in a particular activity.

Knowing activity duration and resources employed, it is simple to estimate the activity direct cost.

example

If the daily production rate for a crew that works in an activity is 175 units/day and the total crew cost per day is 100 $. The material unit cost is 1 $.

a. Calculate the time and cost it takes the

crew to finish 1400 units

b. Calculate the total unit cost.

Page 31: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 31

Solution

Activity duration = Qty / crew output =1400 / 175 = 8 days Crew cost = 8 days * 100 $/day = 800 $ Material cost = 1400 unit * 1 $ = 1400 $

Total direct cost = Labor cost + Material Cost = 800 $ + 1400 $ = 2200 $ Total Unit cost = total cost / quantity = 2200 $ / 1400 unit = 1.57 $/unit

Some Factors that affects Duration

1) Weather.

2) Availability and training of Labor.

3) Required quality

4) Familiarity with the work.

5) Quality of workmanship specified.

6) Quality of management/supervision.

7) Size and completion date of project.

8) Length and incidence of holidays.

9) Physical constraints of the site. Such as access, size, storage space and etc.

Page 32: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 32

Types of Construction activities

1) production/construction activity.

2) Procurement activity.

3) Management activity.

production/construction.

production/construction activities: activities that relate directly to the physical efforts of creating the project.

E.g. Concrete work, plaster, tile and etc.

Usually use traditional resources, labor, material and equipments.

Page 33: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 33

Procurement.

Procurement activities: These activities

include arranging for the acquisition of materials, money, equipment and manpower.

Influence the start of production activities.

Should be incorporated in the Schedule if they are long or special orders.

Management.

Management activities: support and administrative tasks.

Such as, preparing inspection reports, obtain shop drawing approvals. Tracking submittal approval and tests.

Page 34: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 34

Construction Scheduling methods

Construction scheduling

What is the difference between a schedule and a Plan?

The schedule: putting the plan on time scale.

Schedule: what would be done in a certain

time and who will be working.

Page 35: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 35

Most Common Scheduling methods

common scheduling methodologies:

Bar Chart (Gantt Chart)

Critical Path Method (CPM)

PERT (program Evaluation & Review Technique)

Linear Scheduling Method (LSM)

Bar Chart or Gantt chart

Bar chart is a collection of activities listed vertically, and the horizontal scale represents the time.

First applied by HENRY GANTT in 1917

Page 36: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 36

Bar Chart or Gantt chart

Time (weeks)

Ac

tivit

y

A

B

C

D

E

F

2 3 4 5 6 7 8 1

Advantages of Bar / Gantt Chart

1) Plan, schedule and progress are all depicted graphically on a single chart

2) Easily read

3) Provides simple way to schedule small projects

4) Provides summary display of more detailed plans and schedules.

5) Best used for management briefings

Page 37: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 37

Bar Chart or Gantt chart

Time (weeks)

Ac

tivit

y

A

B

C

D

E

F

2 3 4 5 6 7 8 1

Current time

Disadvantages of Bar / Gantt Chart

1) Activity dependencies cannot adequately be shown.

2) Difficult to determine how activity progress delays affect project completion.

3) Difficult to establish and maintain for large projects

Page 38: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 38

Critical Path Method (CPM)

Two basic methods of analysis:

1) ADM -- Arrow Diagramming Method or

Activity On Arrow (AOA) or I-J Method

2) PDM -- Precedence Diagramming Method Activity On Node (AON) Method

1) ADM -- Arrow Diagramming Method

• Activity on Arrow (AoA) or noun as i – j method

• In The ADM the activity represented by an arrow.

• The arrow head represents the relation with other activities (interdependency).

• it looks like the following figure

Page 39: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 39

ADM -- Arrow Diagramming

Method

excavation i j

7

The Excavation activity OR activity i - j with duration of 7 (time unit)

Event i Event j

ADM -- Arrow Diagramming Method • Linear sequencing

• Summation of all activities durations = total duration

Form work

10 11 Pour concrete

12 13 Deshuttering

14 Steel rebar

2 1 1 7

Total Duration = 2 + 1 + 1 +7 = 11 days

Page 40: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 40

ADM -- Arrow Diagramming

Method

11

12

10

walls plaster 14 15

13

ADM -- Arrow Diagramming

Method

Sitting 1

Order

Formwork

Excavate erect

out

make

Formwork timber foundation 2 3 4 5 6

Sitting 1

erect Excavate

out Formwork foundation 2 4 5

3

Page 41: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 41

Dummy activities

Build wall 1 2

Wall Plaster 3 13

plumbing 4

electrical

conduit

Joinery 1st

fixings

Dummy activities

Build wall 1 2

Plaster wall 5 13

plumbing 6

3

4

Dummy activity has ZERO duration and Does NOT consume resources.

1) Dummies help in activities identification

Page 42: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 42

Dummy activities • If activity R follows P and activity S follows T

• does the above figure depict the statement.???

11

R

S

P

T

What about this

P 12

R

T 11

S

Page 43: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 43

Dummy activities • If the method statement changed that activity S is

dependent on both activities P & T. and activity R

dependent on P only.

P 12

R

T 11

S

2) Dummy activities help to maintain the logic of the network

Exercise: draw arrow diagram for the following project.

Activity Duration Predecessor

A 2 --

B 2 A

C 4 A

D 1 C

E 4 B & C

F 2 B

G 1 D

H 4 F & E

I 2 F

J 4 G & H

K 4 I & H

L 1 K & J

Page 44: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 44

A

2

C 4

D 1

B

2

F

2

G

1

H

4

I

2

J 4

L

1

K 4

10 15 25

20

30

40 55

35

50

45 60 65

The Arrow Network will be:

E

4 27

Network calculations

• Forward Pass: deals with the early start and early finish

• Backward Pass: deals with the late start and late finish

Page 45: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 45

An activity time values • ES: the earliest time that an activity can start as determined

by the latest of the early finish times of all immediately preceding activities.

• EF: the earliest time that an activity can finish, determined by EF = ES + D

• LS : the latest time that an activity can start without delaying the project completion. LS = LF – D.

• LF : the latest time that an activity can be finished without

delaying the project completion, as determined by the earliest of the late starts of the immediately succeeding activities.

Example

A 1 E

2

C

4 1 2 4 5

3

1 2 6 8

3

Forward Pass calculations to determine the early start and early finish dates

EF = ES + Duration

Beginning of the day convention

Page 46: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 46

Example

1 2 4 5

3

1 2 6 8

3

Backward pass calculations to determine the late start and late finish dates

1 2 6 8

4 LS = LF – Duration

A E

2

C

4 1

Example

1 2 4 5

3

1 6 10 17

3

Backward pass calculations to determine the late start and late finish dates

1 6 10 17

8 LS = LF – Duration

A E

7

C

4 5

Page 47: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 47

Tabular Schedule

Activity

Duration

ES

EF

LS

LF

A 1 1 2 1 2

B 2 1 3 2 4

C 4 2 6 2 6

D 2 3 5 4 6

E 2 6 8 6 8

Total Float (TF) TF = LS – ES OR LF - EF

Activity Duration

ES EF LS LF TF

A 1 1 2 1 2 0

B 2 1 3 2 4 1

C 4 2 6 2 6 0

D 2 3 5 4 6 1

E 2 6 8 6 8 0

TF: the amount of time that an activity can be delayed before it impacts the project completion.

Page 48: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 48

ES – EF Schedule

day

Ac

tivit

y

A

B

C

D

E

2 3 4 5 6 7 8 1

Early Times Schedule (ES – EF)

LS – LF Schedule

day

Ac

tivit

y

A

B

C

D

E

2 3 4 5 6 7 8 1

Late Times Schedule (LS – LF)

Page 49: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 49

Early / Late times schedule

day

Ac

tivit

y

A

B

C

D

E

2 3 4 5 6 7 8 1

Both Early / Late Times Schedule

Critical Path

1 2 4 5

3

1 2 6 8

3

The critical path: is the longest path in the network and the shortest possible duration.

1 2 6 8

4 LS = LF – Duration

A E

2

C

4 1

Page 50: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 50

A

2

C 4

D 1

E

4

B

2

F

2

G

1

H

4

I

2

J 4

L

1

K 4

1 2 3

4

5

6

9 10

7

8

11 12 13

1 3 5 7 15

7 7 11 15 19 20

15 8

Forward Pass calculations (ES, EF)

A

2

C 4

D 1

E

4

B

2

F

2

G

1

H

4

I

2

J 4

L

1

K 4

1 2 3

4

5

6

9 10

7

8

11 12 13

1 3 7 11 15

7 7 11 15 19 20

15 14

backward Pass calculations (LS, LF)

Page 51: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 51

A

2

C 4

D 1

E

4

B

2

F

2

G

1

H

4

I

2

J 4

L

1

K 4

1 2 3

4

5

6

9 10

7

8

11 12 13

1 3 5 7 15

7 7 11 15 19 20

15 8

1 3 7 11 15

7 7 11 15 19 20

15 14

Determining the Critical Path

A

2

C 4

D 1

E

4

B

2

F

2

G

1

H

4

I

2

J 4

L

1

K 4

1 2 3

4

5

6

9 10

7

8

11 12 13

1 3 5 7 15

7 7 11 15 19 20

15 8

1 3 7 11 15

7 7 11 15 19 20

15 14

Determining the Critical Path

The Critical path passes through activities where TF = 0

Page 52: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 52

Early Schedule Activity

Duration ES EF

A 2 1 3

B 2 3 5

C 4 3 7

D 1 7 8

E 4 7 11

F 2 5 7

G 1 8 9

H 4 11 15

I 2 7 9

J 4 15 19

K 4 15 19

L 1 19 20

A

B

C

D

E

F

G

H

I

J

K

L

2 4 6 8 10 12 14 16 18 20

Bar / Gantt chart Early Start / Finish

EF = ES + D Activity

Day

Page 53: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 53

Early / Late Schedule Activity Duration ES EF LS LF

A 2 1 3 1 3

B 2 3 5 5 7

C 4 3 7 3 7

D 1 7 8 13 14

E 4 7 11 7 11

F 2 5 7 9 11

G 1 8 9 14 15

H 4 11 15 11 15

I 2 7 9 13 15

J 4 15 19 15 19

K 4 15 19 15 19

L 1 19 20 19 20

A

B

C

D

E

F

G

H

I

J

K

L

2 4 6 8 10 12 14 16 18 20

Bar / Gantt Chart Late Start / Finish

LS = LF - D Activity

Day

Page 54: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 54

Activity Duration ES EF LS LF TF

A 2 1 3 1 3 0

B 2 3 5 5 7 2

C 4 3 7 3 7 0

D 1 7 8 13 14 6

E 4 7 11 7 11 0

F 2 5 7 9 11 4

G 1 8 9 14 15 6

H 4 11 15 11 15 0

I 2 7 9 13 15 6

J 4 15 19 15 19 0

K 4 15 19 15 19 0

L 1 19 20 19 20 0

Total Float (TF): The amount of time an activity can be delayed without

delaying the overall project completion.

TF = LF – EF

= LS - ES

A

B

C

D

E

F

G

H

I

J

K

L

2 4 6 8 10 12 14 16 18 20

Bar / Gantt of the previous network

Day

Page 55: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 55

2) PDM Precedence Diagramming Method Activity On Node (AON) Method

PDM is the primary method in use today.

Used by most of the computer software.

MS Project

Primavera

Sure Track

PDM Precedence Diagramming Method

The PDM depicts activities as NODES in the network linked with logic lines.

The node representing the activity.

Arrow representing relationship / dependency

PDM should be red left to right

Page 56: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 56

PDM Precedence Diagramming Method

PDM looks like the following:

Activity A

Activity B

• The shape of the node could be any shape

PDM vs. ADM

A C

B D

A C

B D

1 2 3

4 6 5

=

ADM PDM

Page 57: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 57

PDM vs. ADM

A C

B

D

A 1

3

5

4 =

ADM PDM

2

B

C

D

Exercise

Draw a PDM for the following activities.

Activity Activity Description predecessor A Lay out -- B Excavation A C place formwork B E purchase steel -- F bend steel E G place steel C,F H order concrete -- D place concrete G,H

Page 58: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 58

The PDM will be:

A B C

E F

H

D

G

Exercise

Activity Predecessor

A --

B A

C A

D B,C

E C

F D,E

G E

H F,G

• Draw a PDM for the following activities.

Page 59: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 59

Solution

A B D F H

C E G

Activities Relationships

Types of relations between activities:

1) Finish to start – FS

2) Start to Finish – SF

3) Finish to Finish – FF

4) Start to Start - SS

Page 60: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 60

1) Finish to start – FS Relationship

The traditional relationship between activities.

Implies that the preceding activity must finish before the succeeding activities can start.

Example: the plaster must be finished before the tile can start.

Finish to start with delay relationship

Pour concrete

1 day

Deshuttering

2 days

Deshuttering should start after 28 days of concrete curing

Pour concrete

1 day

Deshuttering

2 days

FS/28

28 days is delay time or LAG means that: deshuttering can start 28 days after

Concrete has been poured

Page 61: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 61

Finish to start with delay relationship

3) Star to Finish – SF relationship

Appear illogical or irrational.

Typically used with delay time OR LAG.

The following examples proofs that it is logical.

Page 62: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 62

2) Star to Finish – SF relationship

steel reinforcement

Erect formwork

Order concrete

SF/5

Pour concrete

The concrete supplier stipulates 5 days order before delivery.

3) Finish to Finish – FF relationship

Both activities must finish at the same time.

Can be used where activities can overlap to a

certain limit.

Page 63: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 63

Finish to Finish – FF relationship

Position flagpole

In the hole

Set flagpole

In the hole

Backfill

hole

FF

Finish to Finish with delay relationship

Erect

scaffolding Remove

Old paint

sanding

painting inspect Dismantle

scaffolding

FF/1

FF/2

Page 64: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 64

4) Start to Start – SS relationship

• Both activities must start at the same time.

Start to Start – SS relationship

Spread grout

Clean surface

Set tile

SS

Clean floor area

Page 65: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 65

Precedence Network Calculations

the basic information that should be calculated in the precedence network are:

1) Early activity start (ES)

2) Early activity finish (EF)

3) Late activity start (LS)

4) Late activity finish (LF)

5) Free Float (FF)

6) Total Float (TF)

Precedence Network Calculations

ES: the earliest time that an activity can start as determined by the latest of the early finish times of all immediately preceding activities.

EF: the earliest time that an activity can finish, determined by EF = ES + D

LS : the latest time that an activity can start without delaying the project completion.

LS = LF – D.

LF : the latest time that an activity can be finished without delaying the project completion, as determined by the earliest of the late starts of the immediately succeeding activities.

Page 66: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 66

Precedence Network Calculations

FF: the amount of time that an activity can be delayed before it impacts the start of any succeeding activities.

TF: the amount of time that an activity can be delayed before it impacts the project completion.

Lag: the amount of time that exists between the EF of an activity and the ES of a specified succeeding activity.

LAGAB = ESB - EFA

Precedence Network Calculations

The previously mentioned information can be illustrated in the activity nod in the network:

Activity description

Duration ES

EF

LS

LF TF FF

Page 67: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 67

Precedence Network Calculations

Reminder: The manual calculations assumes that the relationships between activities are Finish to Start (FS) Type.

Precedence Network Calculations

Dur. ES EF FF TF LF

LS

A

1 1

2 0 0 2

1

B

9 2

11 0 0 11

2

D

5 11

16 0 0 16

11 4 16

20 0 0 20

16 1 20

21 0 0 21

20

F H

C

5 5

10 3 0 7

2

E

4 10

14 3 0 11

7 6 14

20 3 3 17

11

G

5 4 3

1) Forward pass calculations 4) Backward pass calculations

2) Calculate the Lag ( LAGAB = ESB - EFA

0

0 0 0 0

0 0

3) Calculate the Free Float (FF) FF = min. LAG

5) Calculate total Float (TF = LS – ES OR LF – EF)

Page 68: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 68

Precedence Network Calculations

Dur. ES EF FF TF LF

LS

A

1 1

2 0 0 2

1

B

9 2

11 0 0 11

2

D

5 11

16 0 0 16

11 4 16

20 0 0 20

16 1 20

21 0 0 21

20

F H

C

5 5

10 3 0 7

2

E

4 10

14 3 0 11

7 6 14

20 3 3 17

11

G

5 4 3

6) Determine the Critical Path

0

0 0 0 0

0 0

The critical path passes through the critical activities where TF = 0

A

B

C

D

E

F

G

H

2 4 6 8 10 12 14 16 18 20

Bar / Gantt chart Early Start / Finish

EF = ES + D Activity

Time

Page 69: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 69

A

B

C

D

E

F

G

H

2 4 6 8 10 12 14 16 18 20

Bar / Gantt chart Late Start / Finish

LS = LF - D Activity

Time

Bar / Gantt chart

Time

A

B

C

D

E

F

G

H

2 4 6 8 10 12 14 16 18 20

Activity

Page 70: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 70

Dur. ES EF FF TF LF

LS

Block work

6 1

7 0 7

1

plumbing

4 7

11 0 11

7

plaster

8 17

25 0 25

17 1 28

29 0 29

28

Floor tile

sub-frames

1 16

17 9 8

7

electrical

conduit

2 15

17 8 9

7

6 11

17 0 17

11

Inspection

Water

proofing

3 25

28 0 28

25

1) Forward pass calculations 4) Backward pass calculations

2) Calculate the Lag ( LAGAB = ESB - EFA

3) Calculate the Free Float (FF) FF = min. LAG

0

0

0

8

0 0

9

0 0

Exercise

Dur. ES EF FF TF LF

LS

Block work

6 1

7 0 0 7

1

plumbing

4 7

11 0 0 11

7

plaster

8 17

25 0 0 25

17 1 28

29 0 0 29

28

Floor tile

sub-frames

1 16

17 9 9 8

7

electrical

conduit

2 15

17 8 8 9

7

6 11

17 0 0 17

11

Inspection

Water

proofing

3 25

28 0 0 28

25 0

0

0

8

0 0

9

0 0

5) Calculate total Float (TF = LS – ES OR LF – EF)

6) Determine the Critical Path

Page 71: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 71

Constraints

The reason why two activities must be done in particular order can be termed as constraint.

Without constraints on a project, all activities theoretically can begin on the first day of construction.

Types of construction Constraints

1) Physical constraints.

2) Resource constraints.

3) Safety constraints.

4) Financial constraints.

5) Environmental constraints.

6) Management constraints.

7) Contractual constraints.

8) Regulatory constraints.

Page 72: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 72

Physical constraints.

Physical constraints exist due to physical process of construction.

Physical constraints defined by “HOW” the project is to be carried out. ( Method of construction).

You need to erect formwork before you can cast concrete.

Resource constraints

These constraints imposed wherever two activities cannot be carried out simultaneously because insufficient resources are available.

E.g. two activities require a crane to be performed and you have just one crane. So, they should not be performed at the same time.

E.g. The amount of required concrete per day exceeds the production capacity of a batch plant.

Page 73: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 73

Safety constraints.

Safety constraints imposed by safety requirements through performing the work.

Sometime imposes that two activities could not be performed at the same time due to non-safe work conditions. ( E.g. overhead and ground level work at the same area.)

Imposes specific sequence of the work. (e.g. erecting of scaffolding before external paints can start)

Imposes non-working days due to extremely hot or cold days.

Financial constraints

Financial constraints: high cost activities could be delayed due to non-availability of cash requirements during construction.

The amount of cost a company can pay within a specific period of time usually limited. So, try to avoid overlap between high cost activities.

Page 74: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 74

Environmental constraints.

Environmental constraints include restrictions to the work to avoid environmental violations.

E.g. not working in certain area during specific times to avoid affecting proliferation of eagles and fish run.

Management constraints.

Management constraints reflect decisions of management that result in a reasonable benefit of the company.

E.g. the management decided to borrow from your project resources to be utilized in another project.

E.g. the management decided to extend the new year holiday another 2 days.

Page 75: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 75

Contractual constraints

The owner may impose constraints on the construction process.

E.g. the owner may require a particular phase of the project to be fully completed and occupied before start construction of next phase.

And he may require to minimize the noise and dust because that portion is occupied and in operation.

Regulatory constraints.

These type of constraints related to the regulations of the area of construction. Imposed by municipality, government, etc.

E.g. if the construction site in the downtown, heavy vehicles like concrete mixers prohibited to access the site in a specific times of the day. So, you can just cast concrete at night.

Page 76: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 76

Impacts of constraints on the network

In the initial definition of the network, it is desirable to minimize the number of constraints, because excessive constraints have the following impact of the project.

1) Reduce scheduling flexibility.

2) Lengthen project duration.

3) Generally increase project costs.

4) Confuse basic scheduling logic.

Impacts of constraints on the network

The imposition of constraints in the network results in linear ordering of activities. Which is not desired. (recall: the linear order of activities prolong the project duration and set most of the activities as critical).

Page 77: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 77

Impacts of constraints on the network

Only physical constraints should be considered in the early preparation of the network.

Other constraints can be deferred until actual schedule of activities. Where it can be determined that :

1) the constraints are not met by the schedule.

2) It can be addressed by shifting of activities within their available float time.

Resource Management Resources Allocation & Leveling

Page 78: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 78

Resources Allocation & Leveling

So far, the network analysis has been considered using one resource only which is time.

Construction activities in practice use other resources like labor, material, equipment and money.

Moreover, the network analysis considered no limitations of the traditional resources (labor, material, equipment and money) which is not the case in practice.

Resources Allocation & Resources Leveling

A time only network assumes that any other needed resources are available at any time.

E.g. if the excavation activity requires three large mechanical excavators, A time only network assumes that these excavators are available on site at the required time. This seems to be uneconomic situation.

Page 79: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 79

Resource Profile

Time

res

ou

rce

Not preferred resources demand

(Histogram)

Page 80: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 80

Time

res

ou

rce

preferred resources demand

(Histogram)

resources aggregation diagram (Histogram)

It is a graphical representation of the resources aggregation vs. project’s duration. And it shows the project resources demand along its duration for different time units, daily, weekly or monthly.

And its important to the contractor to know the amount of needed resources to carry out the job and to check their availability, in addition, the resources histogram shows the fluctuation in the resources demand and enables the scheduler to obtain even resources demand.

Page 81: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 81

Resource Aggregation

Resources aggregation: is the summation of the resources that are used to carry out the program on a time period basis. For example, day to day , or week to week.

resources aggregation

A

1 1

2 0 0 2

1

B

9 2

11 0 0 11

2

D

5 11

16 0 0 16

11 4 16

20 0 0 20

16 1 20

21 0 0 21

20

F H

C

5 5

10 3 0 7

2

E

4 10

14 3 0 11

7 6 14

20 3 3 17

11

G

Dur. ES EF FF TF LF

LS

Labors

Activity desc.

8H 9H 5H 8H 4H

2H 4H 7H

Page 82: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 82

Priorities & Sorts

The activities making up the network must be listed in order of their priority of resources allocation.

The network shows the logical sequence of activities. (predecessor and successor).

The listing of activities must therefore reflects the dependency of some activities .

Activities Sort

Activity Duration ES TF Resource unit

A 1 1 0 8 H

B 9 2 0 9 H

C 5 2 3 7 H

D 5 11 0 5 H

E 4 7 3 4 H

F 4 16 0 8 H

G 6 11 3 2 H

H 1 20 0 4 H

Activity sort reflects the logic sequence of the network.

Page 83: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 83

Major Sort

Activity Duration ES TF Resource unit

A 1 1 0 8 H

B 9 2 0 9 H

C 5 2 3 7 H

E 4 7 3 4 H

G 6 11 3 2 H

D 5 11 0 5 H

F 4 16 0 8 H

H 1 20 0 4 H

Activity sort with ES time as Major sort

Major & Minor Sorts

Activity Duration ES TF Resource unit

A 1 1 0 8 H

B 9 2 0 9 H

C 5 2 3 7 H

E 4 7 3 4 H

D 5 11 0 5 H

G 6 11 3 2 H

F 4 16 0 8 H

H 1 20 0 4 H

Activity sort with ES time as Major sort & TF as Minor Sort

Page 84: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 84

A

B

C

D

E

F

G

H

2 4 6 8 10 12 14 16 18 20

Allocated resources

Time

8H

9H 9H 9H 9H 9H 9H 9H 9H 9H

7H 7H 7H 7H 7H

5H 5H 5H 5H 5H

4H 4H 4H 4H

8H 8H 8H 8H

2H 2H 2H 2H 2H 2H

4H

Ac

tivit

y

2 4 6 8 10 12 14 16 18 20

Ac

tivit

y

Time

Total Labor 8 16 16 16 16 16 13 13 13 13 7 7 7 7 7 10 8 8 8 4

Early start resources aggregation

A

B

C

D

E

F

G

H

8H

9H 9H 9H 9H 9H 9H 9H 9H 9H

7H 7H 7H 7H 7H

5H 5H 5H 5H 5H

4H 4H 4H 4H

8H 8H 8H 8H

2H 2H 2H 2H 2H 2H

4H

Page 85: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 85

Time

Total Labor 8 16 16 16 16 16 13 13 13 13 7 7 7 7 7 10 8 8 8

La

bo

r

2

4

6

8

10

12

14

16

Early start resources aggregation diagram (Histogram)

2 4 6 8 10 12 14 16 18 20

4

Late start

Another histogram can be obtained if Late start considered. Shows different resources demand.

And many histograms can be obtained considering a different time in the network.

Each histogram shows different resources demand.

Page 86: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 86

Late start Sort

Activity Duration LS TF Resource unit

A 1 1 0 8 H

B 9 2 0 9 H

C 5 5 3 7 H

E 4 10 3 4 H

D 5 11 0 5 H

G 6 14 3 2 H

F 4 16 0 8 H

H 1 20 0 4 H

Activity sort with LS time as Major sort & TF as Minor Sort

A

B

C

D

E

F

G

H

2 4 6 8 10 12 14 16 18 20

Ac

tivit

y

Time

8H

9H 9H 9H 9H 9H 9H 9H 9H 9H

7H 7H 7H 7H 7H

5H 5H 5H 5H 5H

4H 4H 4H 4H

8H 8H 8H 8H

2H 2H 2H 2H 2H 2H

4H

Total Labor 8 9 9 9 16 16 16 16 16 13 9 9 9 7 7 10 10 10 10 4

Late start resources aggregation

Page 87: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 87

Time

Total Labor

La

bo

r

2

4

6

8

10

12

14

16

8 9 9 9 16 16 16 16 16 13 9 9 9 7 7 10 10 10 10 4

Late start resources aggregation diagram (Histogram)

2 4 6 8 10 12 14 16 18 20

Time

Total Labor

La

bo

r

2

4

6

8

10

12

14

16

8 9 9 9 16 16 16 16 16 13 9 9 9 7 7 10 10 10 10 4

Early start vs Late start resources aggregation diagram (Histogram)

2 4 6 8 10 12 14 16 18 20

Page 88: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 88

Time

Total Labor

La

bo

r

2

4

6

8

10

12

14

16

8 9 9 9 16 16 16 16 16 13 9 9 9 7 7 10 10 10 10 4

Early start vs Late start resources aggregation diagram (Histogram)

2 4 6 8 10 12 14 16 18 20

Dur. ES EF FF TF LF

LS

5 5

8

2

2

4

6

3 2

3

6

A/8H

B/9H

C/2H

D/4H

H/5H

G/2H

F/8H

E/5H

I/5H

J/2H

K/6H

1

6 0 0 6

1 6

11 0 0 11

6

6

8 0 6 14

12

8

14 8 8 22

16

11

14 0 0 14

11

11

13 0 6 19

17

10

16 6 6 22

16

6

10 0 6 16

12 13

16 6 6 22

19

14

22 0 0 22

14

22

24 0 0 24

22

Activity/unit/day

Page 89: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 89

Activities Sort

• Activity Duration ES TF Resource unit

A 5 1 0 8 H

C 5 6 0 2 H

D 3 6 6 4 H

B 4 6 6 9 H

H 6 8 8 5 H

E 6 10 6 5 H

G 3 11 0 2 H

F 2 11 6 8 H

I 3 13 6 5 H

J 8 14 0 2 H

K 2 22 0 6 H

Activity sort with ES time as Major sort & TF and duration as Minor Sorts

2 4 6 8 10 12 14 16 18 20

Time

Total

Labor 8 8 8 8 8 15 15 16 16 12 20 20 17 12 12 2 2 2 2 2

Early start resources aggregation

A

C

H

D

F

E

8H

2H 2H 2H 2H

5H 5H 5H

4H 4H

8H

I

J

K

5H 5H 5H

5H

2H

22 24

8H 8H 8H 8H

2H

5H 5H 5H

5H 5H 5H

8H

5H 5H

2H 2H 2H 2H 2H 2H 2H

6H 6H

2 6 6

B 9H 9H 9H 9H 9H 9H 9H 9H

G 2H 2H 2H

Page 90: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 90

Total

Labor 8 8 8 8 8 15 15 16 16 12 20 20 17 12 12 2 2 2 2 2 2 6 6

La

bo

r

2

4

6

8

10

12

14

16

Time

2 4 6 8 10 12 14 16 18 20 22 24

18

20

Early start resources aggregation diagram

Activities Sort • Activity Duration LS TF Resource unit

A 5 1 0 8 H

C 5 6 0 2 H

G 3 11 0 2 H

D 2 12 6 4 H

B 4 12 6 9 H

J 8 14 0 2 H

E 6 16 6 5 H

H 6 16 8 5 H

F 2 17 6 8 H

I 3 19 6 5 H

K 2 22 0 6 H

Activity sort Activity sort with LS time as Major sort & TF and duration as Minor Sorts

Page 91: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 91

2 4 6 8 10 12 14 16 18 20

Time

Total

Labor 8 8 8 8 8 2 2 2 2 2 2 15 15 11 11 12 20 20 17 17

Late start resources aggregation

A

C

D

F

E

8H

2H 2H 2H 2H

5H 5H

8H

I

K

5H

22 24

8H 8H 8H 8H

2H

5H 5H 5H

8H

5H 5H

6H 6H

17 6 6

5H

B 9H 9H 9H 9H

H 5H 5H 5H 5H 5H 5H

4H 4H

G 2H 2H 2H

J 2H 2H 2H 2H 2H 2H 2H 2H

Total

Labor

La

bo

r

2

4

6

8

10

12

14

16

Time

2 4 6 8 10 12 14 16 18 20 22 24

18

20

8 8 8 8 8 2 2 2 2 2 2 15 15 11 11 12 20 20 17 17 17 6 6

Late start resources aggregation diagram

Page 92: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 92

La

bo

r

2 4 6 8

10 12 14 16

18 20

Time 2 4 6 8 10 12 14 16 18 20 22 24

La

bo

r

2 4 6 8

10 12 14 16 18 20

Time 2 4 6 8 10 12 14 16 18 20 22 24

Late start

Early start

Total

Labor 8 8 8 8 8 15 15 16 16 12 20 20 17 12 12 2 2 2 2 2 2 6 6

La

bo

r

2

4

6

8

10

12

14

16

Time

2 4 6 8 10 12 14 16 18 20 22

18

20

Early/Late start resources aggregation diagram

Page 93: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 93

Smoothing/Leveling

Let us program activity F to start by its late start day which is day 17

And activity I to start by day 14.

The resulting resources aggregation histogram will be as follows:

2 4 6 8 10 12 14 16 18 20

Time

Total

Labor 8 8 8 8 8 15 15 16 16 12 12 12 12 12 12 7 10 10 2 2

Early start resources aggregation

A

C

H

D

F

E

8H

2H 2H 2H 2H

5H 5H 5H

4H 4H

8H

I

J

K

5H 5H 5H

5H

2H

22 24

8H 8H 8H 8H

2H

5H 5H 5H

5H 5H 5H

8H

5H 5H

2H 2H 2H 2H 2H 2H 2H

6H 6H

2 6 6

B 9H 9H 9H 9H 9H 9H 9H 9H

G 2H 2H 2H

Page 94: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 94

Total

Labor

La

bo

r

2

4

6

8

10

12

14

16

Time

2 4 6 8 10 12 14 16 18 20 22 24

18

20

8 8 8 8 8 15 15 16 16 12 12 12 12 12 12 7 10 10 2 2 2 6 6

2 4 6 8 10 12 14 16 18 20

Time

Total

Labor 8 8 8 8 8 15 15 16 16 12 12 12 12 7 7 2 10 10 7 7

Early start resources aggregation

A

C

H

D

F

E

8H

2H 2H 2H 2H

5H 5H 5H

4H 4H

8H

I

J

K

5H 5H 5H

5H

2H

22 24

8H 8H 8H 8H

2H

5H 5H 5H

5H 5H 5H

8H

5H 5H

2H 2H 2H 2H 2H 2H 2H

6H 6H

7 6 6

B 9H 9H 9H 9H 9H 9H 9H 9H

G 2H 2H 2H

Page 95: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 95

Total

Labor

La

bo

r

2

4

6

8

10

12

14

16

Time

2 4 6 8 10 12 14 16 18 20 22 24

18

20

8 8 8 8 8 15 15 16 16 12 12 12 12 7 7 2 10 10 7 7 7 6 6

Smoothing/Leveling

Let us program activity H to start by its late start time.

So its resources demand starts with its Late start date.

The resulting resource aggregation and histogram will be as follows:

Page 96: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 96

2 4 6 8 10 12 14 16 18 20

Time

Total

Labor 8 8 8 8 8 15 15 11 11 7 15 15 12 10 12 7 7 7 7 7

resources aggregation

A

C

H

D

F

E

8H

2H 2H 2H 2H

5H 5H 5H

4H 4H

8H

I

J

K

5H 5H 5H

5H

2H

22 24

8H 8H 8H 8H

2H

5H 5H 5H

5H 5H 5H

8H

5H 5H

2H 2H 2H 2H 2H 2H 2H

6H 6H

7 6 6

B 9H 9H 9H 9H 9H 9H 9H 9H

G 2H 2H 2H

Total

Labor 8 8 8 8 15 15 11 11 7 15 15 12 10 12 7 7 7 7 7 7 6 6

La

bo

r

2

4

6

8

10

12

14

16

Time

2 4 6 8 10 12 14 16 18 20 22

18

20

Page 97: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 97

Smoothing/Leveling

Let us program

1) activity D to start on 10th day. 2) activity B to start by its early start time 6th day. 3) activity H to start on 12th day. 4) activity E to start 10th day. 5) activity F to start by late start 16th day. 6) activity I to start by late start 18th day The resulting resource aggregation and histogram will be

as follows:

2 4 6 8 10 12 14 16 18 20

Time

Total

Labor

resources aggregation

A

C

H

D

F

E

8H

2H 2H 2H 2H

4H 4H

I

J

K

5H

2H

22 24

8H 8H 8H 8H

2H

5H 5H 5H 5H 5H 5H

5H 5H 5H 5H 5H 5H

8H 8H

5H 5H

2H 2H 2H 2H 2H 2H 2H

6H 6H

8 8 8 8 8 11 11 11 11 11 11 12 12 12 12 15 15 7 7 7 2 6 6

B 9H 9H 9H 9H 9H 9H 9H 9H

G 2H 2H 2H

Page 98: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 98

Total

Labor

La

bo

r

2

4

6

8

10

12

14

16

Time

2 4 6 8 10 12 14 16 18 20 22 24

18

20

8 8 8 8 8 11 11 11 11 11 11 12 12 12 12 15 15 7 7 7 2 6 6

Smoothing/Leveling

In case activity D is splitable activity. It could be interrupted to be carried out in two parts.

Let us program activity B to start on the 7th day .

And activity H to starts by its Late start day.

And activity E to start on the 14th day.

The resulting resource aggregation and histogram will be as follows:

Page 99: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 99

2 4 6 8 10 12 14 16 18 20

Time

Total

Labor 8 8 8 8 8 6 11 11 11 11 10 10 11 12 12 12 12 12 12 7

Early start resources aggregation

A

C

H

D

F

E

8H

2H 2H 2H 2H

5H 5H 5H

4H

8H

I

J

K

5H 5H 5H

5H

2H

22 24

8H 8H 8H 8H

2H

5H 5H 5H

5H 5H 5H

8H

5H 5H

2H 2H 2H 2H 2H 2H 2H

6H 6H

7 6 6

B 9H 9H 9H 9H

G 2H 2H 2H

4H

Total

Labor

La

bo

r

2

4

6

8

10

12

14

16

Time

2 4 6 8 10 12 14 16 18 20 22 24

18

20

8 8 8 8 8 6 11 11 11 11 10 10 11 12 12 12 12 12 12 7 7 6

Page 100: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 100

Early Start or Early Finish

There are many solutions between the limits of Early Start and Late start.

The optimal solution is zero fluctuation histogram. Which is hard to be achieved.

It is preferred to solve the problem toward the Early start resources aggregation diagram.

WHY ?!

Early Start or Early Finish

Because if there are labor availability problems to be overcome, they will occur in the early beginning of the project.

By other words, if the program based on the Late Start date, it means that all the activities are Critical, and any labor problem will affect the project completion.

Page 101: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 101

Remember

The total project’s duration should NOT be affected while resources are leveled.

Do Not shift any critical Activity.

Activity Duration Predecessors Labor/day

A 3 - 9

B 5 - 6

C 1 - 4

D 1 A 10

E 7 B 16

F 6 B 9

G 4 C 5

H 3 C 8

I 6 D,E 2

J 4 F,G 3

K 3 H 7

Example: Schedule the following activities and level the

resources

Page 102: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 102

Answer the followings:

1) When will the project end? 2) How many labors will work in the project? 3) What is the average labor demand along the project? 4) In the ES schedule how much is the peak demand on

the resource and when will occur ? 5) Level the resource and schedule the activities based on

the optimum resource usage?

Resources Leveling summary steps

1) Prepare a complete activity schedule. (network calculations) 2) sort the activities based on the ES as major sort and TF as minor sort. 3) Draw a bar chart of the project based on ES timing of the activities. 4) Draw the TF beside each non critical activity. 5) Write the resource usage above each bar of the related activity. 6) Aggregate (determine the resource sum) the resources in each time

period. (e.g. day). 7) Calculate the total usage of resources = Σ time unit period usage. 8) Calculate the average resource usage = Σ usage / utilization period. 9) Shift non-critical activities within their TF to decrease the peaks and raise

the valleys. 10) Aggregate resources in each time period after shifting any activity. 11) When shifting activities, it is preferred to start with the activities that have

no successors, as shifting these activities will not affect other activities.

12) Shift activities only that will enhance the resource profile.

Page 103: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 103

Dur. ES EF FF TF LF

LS

3

A/9H

1

4 0 8 12

9

1

C/4H

1

2 0 9 11

10

1

D/10H 4

5 8 8 13

12

3

H/8H

2

5 0 11 16

13

4

G/5H

2

6 6 9 15

11

6

F/9H

6

12 0 3 15

9

7

E/16H

6

13 0 0 13

6

5

B/6H 1

6 0 0 6

1

6

I/2H

13

19 0 0 19

13

4

J/3H

12

16 3 3 19

15

3

K/7H

5

8 11 11 19

16

Act / Units/day

Dur. ES EF FF TF LF

LS

3

A

1

4 0 8 12

9

1

C

1

2 0 9 11

10

1

D 4

5 8 8 13

12

3

H

2

5 0 11 16

13

4

G

2

6 6 9 15

11

6

F

6

12 0 3 15

9

7

E

6

13 0 0 13

6

5

B 1

6 0 0 6

1

6

I

13

19 0 0 19

13

4

J

12

16 3 3 19

15

3

K

5

8 11 11 19

16

Activity

Page 104: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 104

Activity Duration ES TF Resource unit

B 5 1 0 6

A 3 1 8 9

C 1 1 9 4

G 4 2 9 5

H 3 2 11 8

D 1 4 8 10

K 3 5 11 7

E 7 6 0 16

F 6 6 3 9

J 4 12 3 3

I 6 13 0 2

Activities Sort

Time

Total

Labor/DAY 19 28 28 29 18 32 32 25 25 25 25 19 5 5 5 2 2 2

Early start resources aggregation

B

A

H

C

F

D

6H

9H

10H

4H

J

I

8H

9H

3H

2H

G 9H 9H 5H

E 16H

2 4 6 8 10 12 14 16 18 1 3 5 7 9 11 13 15 17 19

K 7H

= 326

Page 105: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 105

La

bo

r

5

10

15

20

25

30

35

40

Time

Early start resources aggregation diagram

19 28 28 29 18 32 32 25 25 25 25 19 5 5 5 2 2 2

2 4 6 8 10 12 14 16 18 1 3 5 7 9 11 13 15 17 19

Time

Total

Labor/DAY 19 28 28 29 25 25 25 25 19 5 5 5 18 32 32 2 2 2

Early start resources aggregation

B

A

H

C

F

D

6H

10H

4H

J

I

8H

9H

3H

2H

G 5H

E 16H

9H

2 4 6 8 10 12 14 16 18 1 3 5 7 9 11 13 15 17 19

K 7H

= 326 10 15 15 15 21 21 21 21 25 25 25 25 19 19 13 12 12 12

Page 106: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 106

Time

Total

Labor/DAY 10 15 15 15 21 21 21 21 25 25 25 25 19 19 13 12 12 12

Early start resources aggregation

B

A

H

C

F

D

6H

9H

10H

4H

J

I

8H

9H

3H

2H

G 9H 9H 5H

E 16H

2 4 6 8 10 12 14 16 18 1 3 5 7 9 11 13 15 17 19

K 7H

La

bo

r

5

10

15

20

25

30

35

40

Time

leveled resource aggregation diagram

10 15 15 15 21 21 21 21 25 25 25 25 19 19 13 12 12 12

2 4 6 8 10 12 14 16 18 1 3 5 7 9 11 13 15 17 19

Page 107: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 107

When Resources are Limited

Resources Allocation

When Resources are Limited Resources Allocation

The previous method of resources aggregation has been carried out within a fixed project duration.

The basic objective was to optimize the use of the resources and to know the mount of resources needed to carry out the job on time period basis.

And to maintain the network based duration.

Page 108: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 108

Allocation within resources restraints

Another situation which you may face in practice is the restricted resources availability.

Where you have to carry out the job with the available resources only.

In this case the project duration may be prolonged to suit the availability of the restricted resources.

Resources Allocation

A

1 1

2 0 0 2

1

B

9 2

11 0 0 11

2

D

5 11

16 0 0 16

11 4 16

20 0 0 20

16 1 20

21 0 0 21

20

F H

C

5 5

10 3 0 7

2

E

4 10

14 3 0 11

7 6 14

20 3 3 17

11

G

Dur. ES EF FF TF LF

LS

Resources

Activity desc.

8H 9H 5H 8H 4H

2H 4H 7H

Page 109: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 109

2 4 6 8 10 12 14 16 18 20

Ac

tivit

y

Time

Total Labor 8 16 16 16 16 16 13 13 13 13 7 7 7 7 7 10 8 8 8 4

Early start resources aggregation

A

B

C

D

E

F

G

H

8H

9H 9H 9H 9H 9H 9H 9H 9H 9H

7H 7H 7H 7H 7H

5H 5H 5H 5H 5H

4H 4H 4H 4H

8H 8H 8H 8H

2H 2H 2H 2H 2H 2H

4H

Time

Total Labor 8 16 16 16 16 16 13 13 13 13 7 7 7 7 7 10 8 8 8

La

bo

r

2

4

6

8

10

12

14

16

Early start resources aggregation diagram (Histogram)

2 4 6 8 10 12 14 16 18 20

4

Page 110: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 110

Solve the schedule

Assume that the available labors in the company restricted to 10 helpers, and the company decided to carry out the job without resorting to hire more labor.

The resulting program will exceed the Early finish date based on the network.

2 4 6 8 10 12 14 16 18 20

Ac

tivit

y

Time

Total Labor 8 9 9 9 16 16 16 16 16 13 11 11 11 7 7 10 8 8 8 4

Early start resources aggregation

A

B

C

D

E

F

G

H

8H

9H 9H 9H 9H 9H 9H 9H 9H 9H

7H 7H 7H 7H 7H

5H 5H 5H 5H 5H

4H 4H 4H 4H

8H 8H 8H 8H

2H 2H 2H 2H 2H 2H

4H

Page 111: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 111

Time

Total Labor 8 9 9 9 16 16 16 16 16 13 11 11 11 7 7 10 8 8 8

La

bo

r

2

4

6

8

10

12

14

16

resources profile (Histogram)

2 4 6 8 10 12 14 16 18 20

4

Resources based scheduling Scheduling limited resources

two methods of examination:

1) Series method

2) Parallel method

Page 112: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 112

Rules for scheduling activities with limited resources

1) schedule activities to start as soon as their predecessors have been completed.

2) if more than one activity using a specific limited resources can be scheduled, priority is given to the activity with early Late Start. ( LS as Major Sort)

3) if two or more activities have the same Late start, give priority to the activity with least Total Float. (TF as Minor Sort)

4) if the activities have the same Total Float in the minor sort, give the priority to the activity with the Largest Number of Resources.

5) If the activities are tied in the number of resources, give priority to the activity that has already started.

Resources Allocation

A

1 1

2 0 0 2

1

B

9 2

11 0 0 11

2

D

5 11

16 0 0 16

11 4 16

20 0 0 20

16 1 20

21 0 0 21

20

F H

C

5 5

10 3 0 7

2

E

4 10

14 3 0 11

7 6 14

20 3 3 17

11

G

Dur. ES EF FF TF LF

LS

Resources

Activity desc.

8H 9H 5H 8H 4H

2H 4H 7H

Page 113: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 113

Activity list

Activity Duration LS TF Resource unit

A 1 1 0 8 H

B 9 2 0 9 H

C 5 5 3 7 H

E 4 10 3 4 H

D 5 11 0 5 H

G 6 14 3 2 H

F 4 16 0 8 H

H 1 20 0 4 H

Activity sort with LS time as Major sort & TF as Minor Sort

Resources aggregation diagram

4 8 12 16 20 24

Ac

tivit

y

Time

8 9

A

B

C

D E

F G

8H

9H

7H

5H

4H

8H

2H

4H

2 6 10 14 22 26

Time 18

9 9 9 9 9 9 9 9 7 7 7 7 7 9 9 9 9 7 10 10 2

2

4

6

8

10

La

bo

r

12 Labor

Limit

9H 9H 9H 9H 9H 9H 9H 9H

7H 7H 7H

4H 4H 4H

5H

2H

5H

2H

5H

2H

5H

2H 2H

8H 8H

10 10 Total Labor

H

7H

4

8H

Page 114: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 114

Reschedule the following project

considering 20 units of the given

resource are available in one day.

Example:

Dur. ES EF FF TF LF

LS

3

A/9H

1

4 0 8 12

9

1

C/4H

1

2 0 9 11

10

1

D/10H 4

5 8 8 13

12

3

H/8H

2

5 0 11 16

13

4

G/5H

2

6 6 9 15

11

6

F/9H

6

12 0 3 15

9

7

E/16H

6

13 0 0 13

6

5

B/6H 1

6 0 0 6

1

6

I/2H

13

19 0 0 19

13

4

J/3H

12

16 3 3 19

15

3

K/7H

5

8 11 11 19

16

Act / Units/day

Page 115: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 115

Activity Duration LS TF Resource unit

B 5 1 0 6

E 7 6 0 16

F 6 9 3 9

A 3 9 8 9

C 1 10 9 4

G 4 11 9 5

D 1 12 8 10

I 6 13 0 2

H 3 13 11 8

J 4 15 3 3

K 3 16 11 7

Activities Sort

Time

19 20 20 11 11 16 16 16 16 16 16 16 19 19 19 19 18 18

Resource Driven Schedule

B

6H

2 4 6 8 10 12 14 16 18 1 3 5 7 9 11 13 15 17 19

F 9H

E 16H

A

C

D

9H

10H

4H

G 5H

I 2H

H 8H

J 3H

K 7H

20 22 21

12 3 3 3

Page 116: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 116

La

bo

r

5

10

15

20

25

30

35

40

Time

2 4 6 8 10 12 14 16 18 1 3 5 7 9 11 13 15 17 19

19 20 20 11 11 16 16 16 16 16 16 16 19 19 19 19 18 18 12 3 3 3

20 22 21

Chapter 7

Money and Network Schedules

Page 117: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 117

Money and network schedules

Reminder, cost was one of the elements of project constraints triangle ( COST, TIME & QUALITY)

An effective management tries to minimize and integrate the above mentioned elements.

Money and network schedules

CPM provides a mean for relating time and money.

The application of resources to a project (materials, manpower and machinery) related to another resource which is MONEY.

The value of the resources for each activity represents a component of project cost.

Page 118: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 118

Project Cash Flow

It is quite significant to the contractor to know the amount of money that would be spent in each stage of the project.( Expenditures) CASH OUT

And compare it to the amount of money that would be received. (income) CASH IN

When studying cash flow, it is very important to determine the actual dates when the expenditures (cost) will take place.

Example

Consider the construction of 8-week foundation activity with operation cost of 8800 $. The operation cost is broken down into the following elements:

- Labor 1600 $ paid 200 $ weekly.

- Equipments 4000 $ paid 500 $ weekly after 4 weeks

- Materials 800 $ paid 100 $ weekly after 5 weeks

- Subcontractors 2400 $ paid 300 $ weekly after 3 weeks

Determine the expenses (cash out) of this activity.

Page 119: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 119

Solution

A time-scaled plan is developed for this activity for the payments for labor, plant, material, and subcontractors. The cost will be plotted weekly with the delay specified in the example.

Solution

Foundation weeks

2 3 4 5 6 7 8 9 10 11 12 13

Labor 1600 .

Equipment 4000 .

Material 800 .

Subcontractor 2400 .

Total

paymenet

Cumulative Payments

Page 120: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 120

Solution

Foundation weeks

2 3 4 5 6 7 8 9 10 11 12 13

Labor 1600 200 200 200 200 200 200 200 200

Equipment 4000 500 500 500 500 500 500 500 500

Material 800 100 100 100 100 100 100 100 100

Subcontractor 300 300 300 300 300 300 300 300 300

Total

paymenet 200 200 500 1000 1100 1100 1100 1100 900 900 600 100

Cumulative Payments

200 400 900 1900 3000 4100 5200 6300 7200 8100 8700 8800

Cu

mu

lati

ve

Co

st

(x 1

00

0)

2

4

6

8

10

Weeks

S-Curve for the activity

2 4 6 8 10 12 1 3 5 7 9 11 13

200 400 900 1900 3000 4100 5200 6300 7200 8100 8700 8800

Page 121: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 121

Typical S-Curve

The curve represents the cumulative expenditures of a project direct and indirect

Costs over time is called the S-curve

Developing S-Curve for a project

S-curve for a project can be developed using the following steps:

1. Constructing a simple bar chart for all the activities

of the project

2. Assigning costs to each activity using activity duration.

3. Plotting the cumulative amounts of expenditures versus time by smoothly connecting the projected amounts of expenditures over time.

Page 122: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 122

Activity Duration Predecessors Total cost

A 3 - 3,000

B 5 - 10,000

C 1 - 4,000

D 1 A 16,000

E 7 B 21,000

F 6 B 12,000

G 4 C 16,000

H 3 C 15,000

I 6 D,E 12,000

J 4 F,G 12,000

K 3 H 9,000

Example: Develop S-curve for the following project

Dur. ES EF FF TF LF

LS

3

A

1

4 0 8 12

9

1

C

1

2 0 9 11

10

1

D 4

5 8 8 13

12

3

H

2

5 0 11 16

13

4

G

2

6 6 9 15

11

6

F

6

12 0 3 15

9

7

E

6

13 0 0 13

6

5

B 1

6 0 0 6

1

6

I

13

19 0 0 19

13

4

J

12

16 3 3 19

15

3

K

5

8 11 11 19

16

Page 123: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 123

Time

Cost (x 1000 7 12 12 27 9 8 8 5 5 5 5 6 5 5 5 2 2 2

A

B

E

C

I

F

2,000

4,000

J

K

D

H

2 4 6 8 10 12 14 16 18 1 3 5 7 9 11 13 15 17 19

G

1,000

3,000

16,000

2,000

5,000

9H 9H 4,000

2,000

3,000

3,000

128 7 19 31 58 67 75 83 88 93 98 103 109 114 119 124 126 130 Cumulative

Cost (x 1000

Cu

mu

lati

ve

Co

st

(x 1

00

0)

20

40

60

80

100

120

140

Time

Cash flow ( S curve) diagram

2 4 6 8 10 12 14 16 18 1 3 5 7 9 11 13 15 17 19

128 7 19 31 58 67 75 83 88 93 98 103 109 114 119 124 126 130

Page 124: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 124

Project Income (Cash In)

The flow of money from the owner to the contractor is in the form of progress payments.

Estimates of work completed are made by the contractors periodically (usually monthly)

these estimates are based on evaluations of the percentage of total project completion or actual field measurements of quantities placed

Retention Retention is the amount of money retained

by the owner from every invoice, before a

payment is made to the contractor.

This is to ensure that the contractor will continue the work and that no problems will arise after completion.

This retainage amount ranges from 5% to 10%

Page 125: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 125

Time

Project income Curve

1 2 3 4 5 6 7 8

Cumulative

income

$

Time

Project cash Flow

1 2 3 4 5 6 7 8

Cumulative

Expenditures

& income

Revenue

Expenditures

Retention Release

Amount of

Negative

Cash Flow

Page 126: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 126

Project cash flow

a project’s cash flow is the difference between the project’s Expenditures and income

Cash flow = Cash in – Cash out

= Income - Expenditures

Cash Flow Analysis

Cash flow analysis consists of a detailed examination of funds disbursement (expenditures) and the receipt of revenue.

Cash flow shows if surplus fund available during project, or if negative cash position will occur during construction.

The cash position of contractor during project whether positive or negative is important.

Page 127: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 127

Negative cash position

Negative cash position means that the revenues obtained from a project insufficient to meet the financial obligations (expenditures) of the project.

In this case other fund from the company or from outside sources must be used.

Positive cash position

Positive cash position means that the revenues obtained from a project exceed the financial obligations (expenditures) of the project.

In this case surplus (extra) fund available with the contractor.

And the contractor may invest this surplus funds for short duration.

Page 128: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 128

Overtrading

Overtrading: arises when the current liabilities of a company exceed the current assets, even though the business is solvent.

Minimizing Contractor Negative Cash Flow

It is very essential to the contractor to minimize his negative cash flow because this may hinder him during performing the contract due to lack of financial resources

the procedures the contractor may follow to minimize negative cash flow are:

Page 129: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 129

Minimizing Contractor Negative Cash Flow 1) Asking for advanced or mobilization payment 2) Loading of rates, in which the contractor increases the prices of the earlier items in the bill of quantities. This ensures more income at the early stages of the project. 3) Adjustment of work schedule to late start timing in order to delay payments. In this

case, the contractor should be aware that delay might happen will affect the project completion time and may subject him to liquidated damages.

4) Reduction of delays in receiving revenues. 5) Achievement of maximum production in the field to increase the monthly

payments. 6) Reducing the retention. 7) Adjust the timing of delivery of large material orders to be with the submittal of the

monthly invoice. 8) Delay in paying labor wages, equipment rentals, material suppliers and subcontractors.

Advanced Payments

This is amount of money paid to the contractor for mobilization purposes. Then, it is deducted from contract progress payment.

The contractor may request an advanced or mobilization payment from the owner. This shifts the position of the income profile so that no negative cash position will occur.

Page 130: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 130

Time

Effect of advanced payment on improving cash flow

1 2 3 4 5 6 7 8

Cumulative

Expenditures

& income

income

Expenditures

Advanced

payment

Time-Cost Trade-Off

Some amount of knowledge brings more……

Page 131: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 131

Time-Cost Trade-Off

Projects managers seek the work to be carried out at minimum cost.

Therefore, they are prone to minimum cost duration (Normal Duration).

Unfortunately, minimum cost & minimum duration rarely coincide.

Time-Cost Trade-Off

The cost of an activity depends mainly on the amount of used resources.

Adding more resources to an activity increases the cost, but not necessarily result in proportionate decrease in the duration.

Page 132: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 132

Time & Cost Theoretical Relationship

Dir

ec

t C

os

t

Duration

A B

Minimum Duration

Time-Cost Trade-Off

For the following discussions it is important to remember:

Direct costs: Related to putting the facility components in place. They represent the resources used by an activity. (material, labor and equipment).

Page 133: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 133

Time-Cost Trade-Off

Indirect job costs (job overhead): costs that could not be attributed to a specific work item. (such as, site offices, superintendents, security fence & etc)

These costs are generally incurred whether or not productive work achieved.

Longer project duration will result in higher indirect costs.

Time-Cost Trade-Off

Operating Overhead costs (company overhead): If the cost cannot be attributed to any specific job, they are operating overhead costs, costs of running business. (head office costs, communications & etc).

These costs continue as long as the company exists even one project is running.

Page 134: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 134

Logic of Time-Cost Trade-Off

Assumption: increasing or decreasing

project’s duration will lead to increased direct

costs for the project.

Project duration

General relation of direct costs to project duration

Direct

Costs

Direct costs

Page 135: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 135

Logic of Time-Cost Trade-Off

Assumption: decreasing a project’s duration

will lead to lower indirect costs.

Project duration

General relation of indirect costs to project duration

Indirect

Costs

indirect costs

Page 136: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 136

Logic of Time-Cost Trade-Off

Assumption: A project’s duration can be

decreased by decreasing the duration of one or

more critical activities on the critical path.

Reducing Project Duration

As the critical path of the network decreased, some non-critical activities lose some amount of their total float.

A

B

C

D

F

Page 137: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 137

Logic of Time-Cost Trade-Off

Assumption: Decreasing a project’s duration may increase or decrease the total cost of a project depending upon whether the additional direct costs required to decrease the activity duration are greater or less than indirect costs savings of decreasing the project’s duration.

تقليل المدة لزمىيت للمشروع يمكه ان يزيد او يقلل مه التكلفت الكليتاإلضافيت المباشرة على ما اذا كاوت التكاليف يعتمد وذلك, للمشروع و أقل مه التوفير في التكاليف الغير مباشرةأأكبر المشروع لتقليل مدة . للمشروع

Project duration General relation of project costs to project duration

Project

Costs

Direct costs

indirect costs

Total project costs

Page 138: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 138

Graph analysis

A project’s total costs combines direct costs and indirect costs. Therefore, the curve of total costs versus duration involves adding the cost amounts of direct and indirect costs curves.

Remember, the direct costs curve has a negative slope (direct costs increase as duration decrease) and indirect costs curve has a positive slope (indirect costs decrease as duration decreases).

So, the slope of the total costs curves at any point

depends whether the slope of direct costs curve less than that of indirect cost curve.

Time-Cost Trade-off

The previous analysis suggests that in performing Time-Cost Trade-off analysis, it is necessary to determine the cost of decreasing the critical path by one time unit (day, month & etc).

The cost will vary depending upon which activity duration decreased.

Usually, select the activity with least shortening costs. (lowest additional cost per day of shortening) to minimize the additional costs of shortening.

Page 139: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 139

Reducing Project Duration

As the critical path of the network decreased, some non-critical activities lose some amount of their total float.

A

B

C

D

F

Reducing Project Duration

Thus, the extent to which an activity can be shortened and still has the effect of shortening the project is limited by the amount of total float exists in the parallel activities.

A

B

C

D

F

Page 140: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 140

Reducing Project Duration

As the projects duration decreases, the number of critical paths through the network increases.

A

B

C

D

F

Reducing Project Duration

If more than one critical path exist, it is necessary to reduce all critical paths in the network simultaneously, which becomes expensive.

A

B

C

D

F

Page 141: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 141

Four Different Solutions for Each Network

The schedule can be viewed in several different ways in order to satisfy the client. A client may wish to perform the project in the least cost, or in the least time. Or in any manner satisfies him.

1) All Normal: the original network and activity duration result in all normal solution, based on each activity being performed in its “NORMAL” least cost manner.

Remember, it is not necessarily the least cost or least time solution to schedule a project.

Four Different Solutions for Each Network

2) Least Cost: considering both direct and indirect costs, it may be possible to find a project duration that minimizes these total costs. By paying more to decrease one or more critical activity (direct cost) and save greater indirect costs. (Means that the result will be total cost saving.)

Page 142: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 142

Project duration General relation of project costs to project duration

Project

Costs

Direct costs

indirect costs

Total project costs

Four Different Solutions for Each Network

3) Least Time: A project can be shortened beyond its least cost duration. Until a point reached where no activities in the critical path can be physically shortened regardless of how many resources are applied. (results in higher costs)

Page 143: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 143

Four Different Solutions for Each Network

4) All crash: in this solution, every activity has been shortened as much as physically possible. Its duration the same as the least time solution, but its costs greater. Because the direct cost increases without further reductions in the indirect costs.

A fully crashed schedule occurs when all activities shortened to their shortest possible duration.

Four Different Solutions for Each Network

All crash

It is not an efficient approach since some non-critical activities will be shortened without having any shortening influence on the project duration.

Page 144: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 144

Logically reducing Project Duration

The logical approach is to shorten those activities that contribute to reduce the project duration.

To begin the time-cost trade-off in a rational manner, basic calculations needed.

First compute the early start and early finish times for each activity.

Dur. ES EF FF TF LF

LS

1 6

3

5

3

7 7 3

7

8

A

B

C

D G

F

E H

K

L

1 5

J

Reducing Project Duration to shortest possible duration

Page 145: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 145

Dur. ES EF FF TF LF

LS

1 6

3

5

3

7 7 3

7

8

A

B

C

D G

F

E H

K

L

1

2

2

8

2

5

5

13

9

16

9

12

2

9

16

23

16

19

23

28

5

J

16

21

0

0

0

0

3

0

0

0 0

0 4

1

0

2

4

2

1

0 0

9

2

0 0

9

3

1 1

12

9

7 0

16

13

4 4

16

9

0 0

20

12

7 3

23

16

0 0

23

18

2 2

23

20

4 4

28

23

0 0

Reducing Project Duration to shortest possible duration

Duration-Cost Data Activity Normal Crash Normal Crash days to cost per

Duration Duration Cost Cost Shorten day

A 1 1 800 800 0 -- B 7 4 1000 1600 3 200 C 6 4 300 500 2 100 D 3 2 400 800 1 400 E 3 1 100 200 2 50 F 7 5 500 800 2 150 G 8 4 200 1400 4 300 H 7 6 350 600 1 250 J 5 3 700 850 2 75 K 3 2 500 1000 1 500 L 5 4 450 800 1 350

Page 146: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 146

Logically reducing Project Duration

By computing the link lag values between activities. (Lag = ESB – EFA). It is logical that there is at least one path between the first activity and last activity where lag values are 0.

These activities forming the critical path. (other solution can be derived by computing TF).

In the previous network. Activity A,B,F,H and L forming the critical path.

Logically reducing Project Duration

To shorten the project’s duration it is essential to shorten one of the critical activities. A or B or F or H or L.

Without shortening the project will end after 28 days with a cost of 5300 $.

This is the normal duration cost. And any decrease in duration will increase the direct cost.

The following table shows information about activities.

Page 147: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 147

Identifying activities for 1st compression cycle

Activity A B F H L

Cost/day ∞ 200$ 150$ 250$ 350$

Cannot be shortened

At any cost

Least cost activity to shorten

Logically reducing Project Duration

From the previous table, it can be noticed that activity F has the least incremental shortening cost.( 150 $ per day).

E.g. Shortening F for 2 days costs 150 x 2 = 300 $.

Bear in mind, activities for shortening selected based on cost per day. Not on cycle cost basis.

Page 148: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 148

Logically reducing Project Duration

How many days activity F could be shortened?

The answer in computing the Network Interaction Limit (NIL).

So, reducing activity F by 2 days will affect the link lag values of the succeeding activities and TF of parallel activities.

Dur. ES EF FF TF LF

LS

1 6

3

5

3

7 7 3

7

8

A

B

C

D G

F

E H

K

L

1

2

2

8

2

5

5

13

9

16

9

12

2

9

16

23

16

19

23

28

5

J

16

21

0

0

0

0

3

0

0

0 0

0 4

1

0

2

4

2

1

0 0

9

2

0 0

9

3

1 1

12

9

7 0

16

13

4 4

16

9

0 0

20

12

7 3

23

16

0 0

23

18

2 2

23

20

4 4

28

23

0 0

Page 149: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 149

Dur. ES EF FF TF LF

LS

1 6

3

5

3

7 7 3

5

8

A

B

C

D G

F

E H

K

L

1

2

2

8

2

5

5

13

9

14

9

12

2

9

14

21

14

17

21

26

5

J

14

19

0

0

0

0

1

0

0

0 0

0 2

1

0

2

4

2

1

0 0

9

2

0 0

9

3

1 1

10

7

5 0

14

11

2 2

16

9

0 0

18

10

5 1

21

14

0 0

21

16

2 2

21

18

4 4

26

21

0 0

Summary of the first compression cycle

Cycle

#

Activity to

shorten

Can be

shortened NIL Days

shortened Cost per

day Cost per

cycle Total cost

Project duration

0 -- -- -- -- -- -- 5300 28

1 F 2 3 2 150 $ 300 $ 5600 26

Page 150: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 150

Identifying activities for 2nd compression cycle

Activity A B F H L

Cost/day ∞ 200$ ∞ 250$ 350$

Dur. ES EF FF TF LF

LS

1 6

3

5

3

7 7 3

5

8

A

B

C

D G

F

E H

K

L

1

2

2

8

2

5

5

13

9

14

9

12

2

9

14

21

14

17

21

26

5

J

14

19

0

0

0

0

1

0

0

0 0

0 2

1

0

2

4

2

1

0 0

9

2

0 0

9

3

1 1

10

7

5 0

14

11

4 2

16

9

0 0

18

10

5 1

21

14

0 0

21

16

2 2

21

18

4 4

26

21

0 0

Page 151: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 151

Dur. ES EF FF TF LF

LS

1 6

3

5

3

6 7 3

5

8

A

B

C

D G

F

E H

K

L

1

2

2

8

2

5

5

13

8

13

8

11

2

8

13

20

13

16

20

25

5

J

13

18

0

0

0

0

0

0

0

0 0

0 2

0

0

2

4

2

1

0 0

8

2

0 0

8

2

0 0

9

6

4 0

13

10

2 2

13

8

0 0

17

9

4 0

20

13

0 0

20

15

2 2

20

17

4 4

25

20

0 0

Summary of the 2nd compression cycle

Cycle

#

Activity to

shorten

Can be

shortened NIL Days

shortened Cost per

day Cost per

cycle Total cost

Project duration

0 -- -- -- -- -- -- 5300 28

1 F 2 3 2 150 $ 300 $ 5600 26

2 B 3 1 1 200 200 5800 25

Page 152: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 152

Identifying activities for 3rd compression cycle

Activity A B,C F H L

Cost/day ∞ 300 ∞ 250$ 350$

Dur. ES EF FF TF LF

LS

1 6

3

5

3

6 7 3

5

8

A

B

C

D G

F

E H

K

L

1

2

2

8

2

5

5

13

8

13

8

11

2

8

13

20

13

16

20

25

5

J

13

18

0

0

0

0

0

0

0

0 0

0 2

0

0

2

4

2

1

0 0

9

2

0 0

8

2

0 0

9

6

4 0

16

13

4 2

13

8

0 0

17

9

4 0

20

13

0 0

20

15

2 2

20

17

4 4

25

20

0 0

Page 153: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 153

Dur. ES EF FF TF LF

LS

1 6

3

5

3

6 6 3

5

8

A

B

C

D G

F

E H

K

L

1

2

2

8

2

5

5

13

8

13

8

11

2

8

13

19

13

16

19

24

5

J

13

18

0

0

0

0

0

0

0

0 0

0 2

0

0

1

3

2

1

0 0

8

2

0 0

8

2

0 0

8

5

3 0

13

10

2 2

13

8

0 0

16

8

3 0

19

13

0 0

19

14

1 1

19

16

3 3

24

19

0 0

Summary of the 3rd compression cycle

Cycle

#

Activity to

shorten

Can be

shortened NIL Days

shortened Cost per

day Cost per

cycle Total cost

Project duration

0 -- -- -- -- -- -- 5300 28

1 F 2 3 2 150 $ 300 $ 5600 26

2 B 3 1 1 200 200 5800 25

3 H 1 2 1 250 250 6050 24

Page 154: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 154

Identifying activities for 4th compression cycle

Activity A B,C F H L

Cost/day ∞ 300 ∞ ∞ 350$

Dur. ES EF FF TF LF

LS

1 6

3

5

3

6 6 3

5

8

A

B

C

D G

F

E H

K

L

1

2

2

8

2

5

5

13

8

13

8

11

2

8

13

19

13

16

19

24

5

J

13

18

0

0

0

0

0

0

0

0 0

0 2

0

0

1

3

2

1

0 0

8

2

0 0

8

2

0 0

8

5

3 0

13

10

2 2

13

8

0 0

16

8

3 0

19

13

0 0

19

14

1 1

19

16

3 3

24

19

0 0

Page 155: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 155

Dur. ES EF FF TF LF

LS

1 4

3

5

3

4 6 3

5

8

A

B

C

D G

F

E H

K

L

1

2

2

6

2

5

5

13

6

11

6

9

2

6

11

17

13

16

17

22

5

J

11

16

0

0

0

0

0

2

0

0 0

0 2

0

0

1

1

2

1

0 0

6

2

0 0

6

2

0 0

6

3

1 0

11

8

2 2

11

6

0 0

14

6

1 0

17

11

0 0

17

12

1 1

17

14

1 1

22

17

0 0

Summary of the 4th compression cycle

Cycle

#

Activity to shorten

Can be

shortened NIL Days

shortened Cost per

day Cost per

cycle Total cost

Project duration

0 -- -- -- -- -- -- 5300 28

1 F 2 3 2 150 $ 300 $ 5600 26

2 B 3 1 1 200 200 5800 25

3 H 1 2 1 250 250 6050 24

4 B,C 2 3 2 300 600 6650 22

Page 156: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 156

Identifying activities for 5th compression cycle

Activity A B,C F H L

Cost/day ∞ ∞ ∞ ∞ 350$

Dur. ES EF FF TF LF

LS

1 4

3

5

3

4 6 3

5

8

A

B

C

D G

F

E H

K

L

1

2

2

6

2

5

5

13

6

11

6

9

2

6

11

17

13

16

17

22

5

J

11

16

0

0

0

0

0

2

0

0 0

0 2

0

0

1

1

2

1

0 0

6

2

0 0

6

2

0 0

6

3

1 0

11

8

2 2

11

6

0 0

14

6

1 0

17

11

0 0

17

12

1 1

17

14

1 1

22

17

0 0

Page 157: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 157

Dur. ES EF FF TF LF

LS

4

3

4

3

4 6 3

5

8

B

C

D G

F

E H

K

L

2

6

2

5

5

13

6

11

6

9

2

6

11

17

13

16

17

21

5

J

11

16

0

0

0

0

0

2

0

0 0

0 2

0

0

1

1

1

A

1

2 2

1

0 0

6

2

0 0

6

2

0 0

6

3

1 0

11

8

2 2

11

6

0 0

14

6

1 0

17

11

0 0

17

12

1 1

17

14

1 1

21

17

0 0

Summary of the 5th compression cycle Cycle

#

Activity to shorten

Can be

shortened NIL Days

shortened Cost per

day Cost per

cycle Total cost

Project duration

0 -- -- -- -- -- -- 5300 28

1 F 2 3 2 150 $ 300 $ 5600 26

2 B 3 1 1 200 200 5800 25

3 H 1 2 1 250 250 6050 24

4 B,C 2 3 2 300 600 6650 22

5 L 1 ∞ 1 350 350 7000 21

Page 158: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 158

Identifying activities for 6th compression cycle

Activity A B,C F H L

Cost/day ∞ ∞ ∞ ∞ ∞

Assume the data given in the table, It is required to crash the project duration from its normal duration to a final duration of 121 days.

Activity Pred. Normal Crash

Cost/day Duration Cost Duration Cost

A -- 12 1200 10 1400 100

B A 20 1800 15 2800 200

C A 40 16000 30 22000 600

D C 30 1400 20 2000 60

E D,F 50 3600 40 4800 120

F B 60 13500 45 18000 300

Page 159: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 159

Project network

12

A

1

13

20

B

13

33

30

D

53

83

40

C

13

53

50

E

93

143

60

F

33

93

0

0

0

0

0

10

Identifying activities for 1st compression cycle

Activity A B F E

Cost/day 100 200 300 120

Page 160: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 160

Project network

12

A

1

13

20

B

13

33

30

D

53

83

40

C

13

53

50

E

93

143

60

F

33

93

0

0

0

0

0

10

Project network

10

A

1

11

20

B

11

31

30

D

51

81

40

C

11

51

50

E

91

141

60

F

31

91

0

0

0

0

0

10

Page 161: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 161

Summary of the 1st compression cycle

Cycle

#

Activity to shorten

Can be

shortened NIL Days

shortened Cost per

day Cost per

cycle Total cost

Project duration

0 -- -- -- -- -- -- 37500 143

1 A 2 ∞ 2 100 $ 200 $ 37700 141

Identifying activities for 2nd compression cycle

Activity A B F E

Cost/day ∞ 200 300 120

Page 162: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 162

Project network

10

A

1

11

20

B

11

31

30

D

51

81

40

C

11

51

50

E

91

141

60

F

31

91

0

0

0

0

0

10

Project network

10

A

1

11

20

B

11

31

30

D

51

81

40

C

11

51

40

E

91

131

60

F

31

91

0

0

0

0

0

10

Page 163: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 163

Summary of the 2nd compression cycle

Cycle

#

Activity to shorten

Can be

shortened NIL Days

shortened Cost per

day Cost per

cycle Total cost

Project duration

0 -- -- -- -- -- -- 37500 143

1 A 2 ∞ 2 100 $ 200 $ 37700 141

2 E 10 ∞ 10 120 1200 38900 131

Identifying activities for 3rd compression cycle

Activity A B F E

Cost/day ∞ 200 300 ∞

Page 164: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 164

Project network

10

A

1

11

20

B

11

31

30

D

51

81

40

C

11

51

40

E

91

131

60

F

31

91

0

0

0

0

0

10

Project network

10

A

1

11

15

B

11

26

30

D

51

81

40

C

11

51

40

E

86

126

60

F

26

86

0

0

0

0

0

5

Page 165: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 165

Summary of the 3rd compression cycle

Cycle

#

Activity to shorten

Can be

shortened NIL Days

shortened Cost per

day Cost per

cycle Total cost

Project duration

0 -- -- -- -- -- -- 37500 143

1 A 2 ∞ 2 100 $ 200 $ 37700 141

2 H 10 ∞ 10 120 1200 38900 131

3 B 5 10 5 200 1000 39900 126

Identifying activities for 4th compression cycle

Activity A B F E

Cost/day ∞ ∞ 300 ∞

Page 166: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 166

Project network

10

A

1

11

15

B

11

26

30

D

51

81

40

C

11

51

40

E

86

126

60

F

26

86

0

0

0

0

0

5

Project network

10

A

1

11

15

B

11

26

30

D

51

81

40

C

11

51

40

E

81

121

55

F

26

81

0

0

0

0

0

0

Page 167: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 167

Summary of the 4th compression cycle

Cycle

#

Activity to shorten

Can be

shortened NIL Days

shortened Cost per

day Cost per

cycle Total cost

Project duration

0 -- -- -- -- -- -- 37500 143

1 A 2 ∞ 2 100 $ 200 $ 37700 141

2 H 10 ∞ 10 120 1200 38900 131

3 B 5 10 5 200 1000 39900 126

4 F 15 5 5 300 1500 41400 121

Project Monitoring & Control

Earned Value Analysis

Page 168: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 168

Project Monitoring and Control

Project control can be divided as follows:

First: monitoring, understanding what is happening on a project. Obtaining information about project by some means.

Second: Control, is the action taken in response to the information obtained.

Monitoring Project status

Some means of Information retrieval:

Photography

Check-off lists ( Status Reports)

Bar chart.

Page 169: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 169

Check-off list

Activity Scheduled Actual status Notes

ID Description Start finish start finish %

14.01 5th floor columns 24 28 26 30 50 Weather

delay

14.02 5th Floor roof slab 32 45

Earned Value Analysis

Page 170: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 170

Earned Value Analysis

Controlling project time without considering the cost may lead to cost overrun.

So, Project time and cost should not be controlled separately.

The Earned Value (EV) concept solve the dilemma

340

Input data for Earned Value Analysis

Activity schedule, usually in the form of a bar chart.

Budgeted cost for each activity.

Percent complete for each activity.

Cost to date for each activity.

Page 171: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 171

Earned Value (EV)

In this techniques three measurements are important:

1. Budgeted cost of work Scheduled (BCWS) or known as ( planned value PV)

2. Budgeted cost of work performed (BCWP) or

known as (Earned Value EV) 3. Actual cost of work performed (ACWP) or

(Actual Cost AC)

BCWS

Ac

tivit

y

A

B

C

Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 1

D

10,000

2,000 2,000

1,000 1,000

1,000 1,000 1,000 1,000

2,000 2,000 2,000 2,000 1,000 1,000 10,000

12,000 14,000 16,000 18,000 19,000 20,000 10,000 BCWS

Weekly cost

Page 172: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 172

BCWS A

cti

vit

y

Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 1

5,000

2,000 2,000 2,000 2,000 1,000 1,000 10,000

12,000 14,000 16,000 18,000 19,000 20,000 10,000 BCWS

Weekly cost

10,000

15,000

20,000

BCWP

Ac

tivit

y

A

B

C

Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 1

D

9,000

2,000 2,000

1,000 1,000

1,000 1,000 1,000 1,000

1,000 2,000 2,000 9,000

10,000 12,000 14,000 9,000 BCWP

Weekly Value

Current time

1,000

1,000

15,000

Page 173: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 173

BCWP A

cti

vit

y

5,000

10,000

15,000

20,000

1,000 2,000 2,000 9,000

10,000 12,000 14,000 9,000 BCWP

Weekly Value 1,000

15,000

Current time

Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 1

Actual Cost ACWP

Ac

tivit

y

A

B

C

Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 1

D

9,000

2,500 2,500

1,000

2,000 2,500 2,500 9,000

11,000 13,500 16,000 9,000 ACWP

Weekly AC

Current time

2,000

1,000

17,000

Page 174: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 174

ACWP A

cti

vit

y

5,000

10,000

15,000

20,000

Current time

Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 1

2,000 2,500 2,500 9,000

11,000 13,500 16,000 9,000 ACWP

Weekly AC 1,000

17,000

Earned Value Analysis

Ac

tivit

y

5,000

10,000

15,000

20,000

Current time

Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 1

11,000 13,500 16,000 9,000 17,000 ACWP

10,000 12,000 14,000 9,000 BCWP 15,000

12,000 14,000 16,000 18,000 19,000 20,000 10,000 BCWS

BCWP

ACWP

BCWS

Page 175: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 175

Earned Value Key Values

Time

Co

st

BCWS

ACWP

BCWP

Current Time

Earned Value (EV)

Budgeted Cost at Completion (BAC): The original cost estimate.

Estimated at Completion (EAC): Is the forecast of the total actual cost required to complete the project based on performance to date and estimates of future.

Page 176: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 176

Budgeted cost of work Scheduled (BCWS) ( Planned Value PV)

The cost estimate based on the original schedule.

Budgeted cost of work preformed (BCWP) (Earned Value EV)

Is a measure of the value of what you have actually accomplished. According to your original activities cost estimate.

It is the value of the work you have achieved at any point in time.

Page 177: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 177

Actual cost of work performed (ACWP) (Actual Cost AC)

The Actual cost is what you have actually paid to accomplish the work.

Cost Variance (CV)

The difference between the value of the work performed based on your schedule calculations, and the actual cost you have paid.

CV = BCWP – ACWP

= EV - AC

Page 178: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 178

Schedule Variance (SV)

The difference between the BCWP and the BCWS

SV = BCWP – BCWS

= EV – PV

It is important to note that negative variances is bad indication to the project performance.

CV & SV

Time

Co

st

BCWS

ACWP

BCWP

Current Time

SV CV

Page 179: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 179

Cost Performance Index (CPI)

Is a measure of project progress in terms of spending project’s budget. It is the ration of the value of the work that has been performed to the actual cost

CPI = BCWP/ACWP

= EV / AC

If your CPI > 1 under budget, CPI<1 over budget

Schedule Performance Index (SPI)

Is a measure of project progress in terms of project schedule. It is the ration of performed work to the work that has been planned.

SPI = BCWP/BCWS

= EV / PV

If your SPI > 1 ahead of schedule, SPI<1 Behind Schedule

Page 180: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 180

Project Percent Complete (Pct)

Measures the project progress in term of percentage.

PC = (EV / BAC) x 100%

The Big Concern (EAC)

The EAC is the estimated Cost At Completion

EAC = ACWP + ( BAC – BCWP)

OR,

EAC = BAC / CPI

Page 181: An-Najah National University Project... · Construction Project Management Dr. Luay Dwaikat Spring Semester 2016/2017 11 2) Procurement Also known as award or biding phase The project

Construction Project Management Dr. Luay Dwaikat

Spring Semester 2016/2017 181

Variance at Completion (VAC)

VAC = BAC – EAC