Update on the Escambia/Santa Rosa Regional Advanced Traffic Management

System (ATMS) Feasibility andImplementation Plan

Ben Faust, P.E.

Advanced Traffic Management System

Advanced Traffic Management System

Todays Presentation Agenda• Update on Traffic Signal System Operations

& Engineering Support Contract• Update on ATMS Phase I• Overview of ATMS Feasibility Study

• Project Schedule & Progress• ATMS Phase II – Future Funding

Update on Traffic Signal System Operations & Engineering Support Contract

DRMP - to work on Best Practices for Regional Traffic Operations Optimization:

– Regional Traffic Engineering Champion– Optimize Regional Signal Operations– Continue the Signal Retiming efforts– Manage and operate ATMS projects

Advanced Traffic Management System

FDOT Financial Project ID 428058-52-01Design-Build project 18 Intersections, fiber optic connection to signal controller and CCTV cameras

• Brent Lane & Bayou Boulevard from Highway 29 to 12th Avenue

• SR95 (N Palafox Street) from Brent Lane to Fairfield Drive

• Fairfield Drive from Texar Drive to North 9th Avenue

Staff training completed • in final test phase

The ATMS Phase 1 Project

• Monitors system-wide traffic conditions and devices

• Enables proactive management• Empowers users with data,

accessible via web enabled devices• Ensures system integrity through

data validation• Centralizes documentation and

inventory control

The ATMS Phase 1 Project

Escambia/Santa Rosa Regional Advanced Traffic Management System Feasibility

Study and Implementation Plan

ATMS Study

• City of Pensacola contracted with Atkins

• The results of this study will be used to develop a project or series of projects that will evolve the existing signal systems into a regional ATMS, and will identify immediate, intermediate, and future needs.

ATMS Study

• Notice to Proceed to Atkins: May 13, 2015• 3 Stakeholder meetings in June & July

• Develop ATMS Phase II RFP by December• Final Masterplan and Implementation Plan

completed by June 2016

ATMS Study Schedule

Existing Conditions

ATMS Framework

ATMS Study Schedule

ATMS Implementation Plan

Technology Review

Develop ATMS Requirements

TMC - Operations

Implementation Plan &RFP Development

• Meeting with FDOT October 22nd

– Provide Details on Masterplan to date– Discuss viable funding alternatives

• Develop Request for Proposal– Design Build for ATMS Phase II– Other deployment options

ATMS Study

DRAFT

ATMS Study

DRAFT

Questions?