Vectus Ltd. 2007 Copyright Page 1
Vectus SverigeStatus av provbanan i Uppsala
Vectus Ltd. 2007 Copyright Page 2
This is Vectus
• Small vehicles (3-6 pass) => individual transport
• Stations off main line
=> travel to destination without intermediate stop
=> high average speed
• On demand.
=> No timetables.
=> Negligible waiting time 24 / 7
=> Total time for travel kept at minimum.
• Short headways (2-3 secs) => high line capacity
• Light and slim guideways => low investment
• Driver-less and dedicated track => low operational cost
Vectus Ltd. 2007 Copyright Page 3
Company DescriptionCompany Description
� Shareholders
� Business Scope• Development and supply of commercial PRT systems for public transport use
• Project Management and consulting (feasibility, simulation, planning)
• Technology licensing
• POSCO E&C, POSTEEL, POSDATA, POSMEC, POSCON (all POSCO affiliates; POSCO 2008, revenues 34 000 MUSD; profits 3 830 MUSD)
• Noventus (Swedish company)
� OrganizationBODBOD
Vectus Ltd. (UK)Vectus Ltd. (UK)
R&D (test track)R&D (test track)
Vectus Ltd.,
Korea Korea BranchBranchVectus Ltd., Vectus Ltd.,
Sweden Sweden BranchBranch
Sales : NonSales : Non--AsiaAsia FinanceFinance Sales : AsiaSales : AsiaMarketingMarketing
Vectus Ltd. 2007 Copyright Page 4
• WGH, UK Guideway and chassis
• Noventus, Swe Control system
• Relcon, Swe RAM – LCC
• Scandpower, Swe Safety and Quality
• Scandpower, Nor Safety
• Skanska, Swe Civil works, station bldg
• Bravida, Swe Electrical installations
• Idesign, Swe Design
• TDI-AVE, UK Cabin
• Parker-SSD, Swe Power supply & propulsion
• Force, UK Linear Motors
• Semcon, Swe Mech design
• Tikab, Swe Mech analysis
• Conort, Swe Mech analysis
• Transrail, Swe Systems engineering, project
mgmt
Vectus Test Track - Swedish and English Design
Vectus Ltd. 2007 Copyright Page 5
Advanced control system
• Distributed control– Limited system effect if there is a fault or problem
– Dynamic rerouting if there are disturbances
– System can be expanded without any performance degradation.
• Asynchronous control– Overall travel time vastly reduced in larger system at load
– Line capacity can be fully utilised
– No degradation at higher loads
• Dynamic moving block– Allows varying speed depending on
load conditions or track layout and still maintaining capacity
– Saves space in any queuingsituation
– Higher capacity than fixed block system
Key features
Vectus Ltd. 2007 Copyright Page 6
Key features
• Suitable for any application, elevated, ground or tunnel.
• Only blue parts required, structure is completely flexible. Very easy to bring inside buildings and make architectural integration.
• Vehicles are mechanically steered along the track
• Smart and SAFE switching, with mechanical guidance through the switch
• Mechanically ”locked” to the guideway.
• No moving parts in switches
Track and vehicle interface
Vectus Ltd. 2007 Copyright Page 7
Key features
Test Track – Linear Motors in Track
• No exposed voltage
• No current collection problems
• Less equipment in vehicles
• Higher system reliability.
Electrical drive with many options
Vectus control concept, and the safety case, accomodates a
multitude of propulsion system solutions.
Other Vectus solutions available to optimise
any system and meet customer demands:
• On-board LIM
• On-board tyre drive
• Current collection / On-board power storage
Vectus Ltd. 2007 Copyright Page 8
– Covers track, vehicle, control system (“ATC”), operation, maintenance etc.
– Safety case according to IEC 61508 (requirement to be as safe as current railway / metro)
– 3:rd party assessment for
• Safety instrumented system (SIS, i.e. part of control, brake, sensors etc)
• Track structure
Authority approval
Vectus Ltd. 2007 Copyright Page 9
All functions have been tested, we are operating with top level software, ticketing etc with multiple vehicles, merge operation etc.
Safety case accepted by SRAApproval for “experience” operation.
Test track Status
Vectus Ltd. 2007 Copyright Page 10
Test track layout
• Max speed: 45 km/h
• Max acceleration: 2 m/s2
• Max retardation: 5 m/s2
• Min headway: 3 sec
Vectus Ltd. 2007 Copyright Page 11
• Verify the technical solution
• Make a complete safety case (incl verification &
validation)
• Approval from relevant authorities
• Long term performance (reliability, maintenance etc.)
Targets for the Test track
Vectus Ltd. 2007 Copyright Page 12
Test track
Vectus Ltd. 2007 Copyright Page 13
Vectus Test Track, Recent Activities
• Experience operation (reliability)
– Full system operation 3-4 hours per day
– All vehicles, merge, minimal headways, station, ticketing
• Ride quality measurements
• Noise measurements
• Winter testing (snow and ice conditions, braking)
Vectus Ltd. 2007 Copyright Page 14
www.vectusprt.com www.vectusprt.se