End User Training Manual
for
SAP PM – Plant maintenance
Process Name: Reconditioning / Shutdown
Process No: TRF/EPM/5.0
Control Copy No: TRF/EPM/5.0/
����� � �&'� (�&� �����
Doc Version Description Prepared by Date Reviewed by Approved by 00 Original Palani Dorai 18.12.2009
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 2 of 23
Introduction
Enterprise Plant maintenance process in TRF has the following business processes.
��"� �" ���� ���)������������ �" �������� �� �
�� ������� ����� Preventive Maintenance process �� �� � ������� � ��� Equipment Calibration processes �� ��
!� ������� �!��� Unplanned / Breakdown Maintenance processes �� ��
"� ������� �"��� External services processes �� ��
#� ������� �#��� Reconditioning / Shutdown processes.
For each of the above processes, there are separate End User Training Manuals are available
This document covers sl. No. 5. Of the above list, that is Reconditioning / Shut down Process.
This End User Training manual on Reconditioning / Shut down Process consists of the
following sequence of sub-processes
1. Creation of an Order - Transaction code IW31
2. Order Confirmation - Transaction code IW44
3. Technical Completion - Transaction code IW32
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 3 of 23
1. Creation of an Order - Transaction code IW31
Procedural Steps
Purpose • Creation of an Order for Reconditioning / shut down process
Transaction Code IW31
Navigation: SAP Easy Access > Logistics > Plant maintenance > Maintenance Processing > Order > IW31 (Create (General)
Procedure
Enter the Transaction code IW31 in the command field as shown in the screen below
Or go as per the navigation shown below and click IW31 - Create
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 4 of 23
Press <Enter> or click on the check mark icon in the top left side corner of the Screen, the following screen will appear Key-in the Order type and the equipment NO (since the user knows for which equipment he is creating the order)
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 5 of 23
.
Click on the check mark icon, the following window appears
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 6 of 23
Key-in data in to the fields as shown in the following screen. Use drop down list to get the values.
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 7 of 23
After keying-in of the above data, click on the operation tab, the following screen appears.
Key-in data in this field
Key-in data in this field
Key-in data in this field
Key-in data in this field
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 8 of 23
If date is to be changed, Select the line, (refer screen below), and
Click on the Act date push button, the following screen appears
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 9 of 23
Click on the date tab, the following screen appears
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 10 of 23
Enter the required details in the two fields as shown in the screen below
Return back to the screen by clicking .
Key-in date
Key-in option
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 11 of 23
Repeat the same for all other operations
Click on the components tab, the following screen appears.
Click on the List push button, the following screen appears showing all the parts of the equipment,
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 12 of 23
Select and double click on the required items, it will get populated on the screen(s) as shown below.
Repeat the same, for all the required items. For our example we have selected (two items s, As shown in the screen(s) below
Release the order by clicking the release button , and
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 13 of 23
Note the message at the status line, as shown in the screen below.
Save the data by clicking the save button . the following screen appears
Note the message at the status line of the screen above, which is shown in the screen below,, and note down the Order NO released.
End of document on T-code IW31
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 14 of 23
Manual Process
The following three sub-processes are done manually outside the SAP Plant maintenance
system. They are
a) The material is ordered, received, inspected and binned in stores,
And then
b) Component is issued from stores,
c) Upon receipt of the components
The tasks of the order are performed And the
Order is completed
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 15 of 23
2. Order Confirmation - Transaction code IW44
Procedural Steps
Purpose
• To Confirm the Order
Transaction Code IW44
Navigation: SAP Easy Access > Logistics > Plant maintenance > Maintenance Processing > Complete Confirmation > Entry > Collective Time confirmation > IW44 (without Selection)
Procedure
Enter the Transaction code IW44 in the command field as shown in the screen below
Or go as per the navigation shown below and click IW44- Order Confirmation
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 16 of 23
Press <Enter> or click on the check mark icon in the top left side corner of the Screen, the following screen will appears.
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 17 of 23
�
�
�
$�� %���&�������������
�� '�()��� %��* �+�� ������������* ����� ����,-##.!���� %��������+������
&� ,�()��� %������� ���������� %���)������ /���+�����%�- ����� %����������&��������
�� .%��'�* ��'���� %���%��'�&����+� %���� ���� /��� ���� /���+�����%�- ���&����
�
$�������� ���� � %������� ������������'���� %������� ����+���������������- �� ��������������� � %��
�����+� %��+�����������%�- ��&���- ��
�
�
Key-in the order Number in this field Key-in t he operation
number in this field Check mark this field
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 18 of 23
/�������'� %� �+��)+�0 ��� � ���� ����������- ����� ��+������ �����������������&���- ��
�
��
$�� %���&���������������� � %��� %� ��������� ���������������&�������'����� � ���� �� ������ ������ %��
����� ����+������+� %������������/����.%��'� ��1���� %���%��'�&����+� %���� ���� /��� ���� /���+����
�%�- ��&���- �
�
� Check mark this Final Confirmation Field
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 19 of 23
Click the check mark icon , the following screen appears population the other values of the
operation in their respective fields,
In the above screen note the confirmation number.
and then press the save icon to save the document.. Check for the confirmation message in the
status line as shown in the below screen.
Return back to the Home Screen or SAP Easy Access screen.
End of document of T-code IW44
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 20 of 23
3. Technical Completion - Transaction code IW32
Procedural Steps
Purpose
• To complete the order
Transaction Code IW32
Navigation: SAP Easy Access > Logistics > Plant maintenance > Maintenance Processing > Order > IW32
Procedure
Enter the Transaction code IW32 in the command field as shown in the screen below
Or go as per the navigation shown below and click IW32 – Change Order
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 21 of 23
Press <Enter> or click on the check mark icon in the top left side corner of the Screen, the following screen will appears. In that screen, Key-in the order number in the order field.
Click on the check mark icon to get the following screen
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 22 of 23
Click on the Technical completion push button.
The following complete pop up window appears
Project: MISSION SURE
�������������� � ����TRF/EPM/5.0�$##!��%"##
Page 23 of 23
If required change the Reference date and Reference time.
Click the check mark icon,, the following screen appears,
Check for the confirmation message, at the status line which is shown in the below screen
and then press the save icon to save the document.
End of document on T-code IW32
End of Training Manual on Reconditioning / Shut down process, Document No: �������������� � ����TRF/EPM/5.0�$##!��%"##