Kenya Project Status Dec. 2014

2

Entrance wall; entrance gate design

Entrance wall condition before

3

Entrance wall condition after

EATL Office

Office conditions before

5

The side view of the office block, the entrance view

off the Administration block and the door step

made of marble with painting works complete

Office Block: aluminum cladding complete; AC installation complete, entry staircase done.

6

Reception Area of Office Block - before

7

Office Block – Reception Area

8

Office Block – Reception Area

9

Office Block – Interior staircase - before

10

Office Block – Interior staircase; the

correction of the previous status

11

Office Partitions Inside Office Block - Before

12

Office Block – all interior works complete; tint, and repainting of the office walls

13

Office meeting room before

14

Office meeting room after

Loading Bay

Before.

16

Loading Bay: access and observation platform complete; loading headers & valve

installation complete

Loading Bay

17

Loading Bay

Before.

After.

18

Entry weigh bridge: Before

Entry weighbridge

19

Entry Weigh Bridge & Cabin – After; Painting is complete. Installation of side beams to guard

vehicle is complete.

Entry weighbridge

20

Boundary Wall before

21

Street Lights

Installation of the street lights is complete.

22

Boundary Wall After.

Painting of the boundary wall is complete

23

Generator Room/ Oil Tank: before

Generator Room

24

Generator Room with diesel tank on top; the road is ready.

Generator Room

25

Generator Room with diesel tank on top

Generator Room

26

Before: With no paint and testing of RO & boiler was not done; pipe lines to RO was not

complete

Boiler and RO Plant House

27

Boiler & RO installation complete; water line to boiler and RO complete; insulation of steam

line in progress.

Boiler and RO Plant House

28

Installed RO and Boiler; Heavy fuel and water overhead tanks complete.

Boiler and RO Plant House

29

Weigh bride cabin with internet and

telephone.

30

Wide view for both Genset, Boiler weighbridge 2 plus cabin and water tank. - before

31

Wide view for both Genset, Boiler weighbridge 2 plus cabin and water tank.

32

Before; the weighbridge was not installed

Public Wash Room

33

wash Hand basins, toilets, overhead tanks and shower heads completed

Public Wash Room

34

Pump House

35

Tank farm MCC installed successfully – was moved from the temporary location (transformer

room) to here permanently. Foundation of the pump house is complete and fitting of the Header.

Pump House

36

Entry Guard House Before

37

Entry Guard house – ready with telephone and internet cable for connecting CCTV screen or

desktop to monitor trucks way in and out.

Entry Guard House

38

Exit Guard house – Side View

Exit Guard House

39

Before.

KRA Office & Transformer room

40

Ready with both AC, Telephone and internet point.

KRA Office

41

Transformer Room

42

Tank 1:

Tanks

43

Tank 2: Before

Tanks

44

Tank 3: Before

Tanks

45

Tank 4: Before

Tanks

46

Tanks Side view

Tanks

47

Tanks Side view

Tanks

48

Water Tank & Chimney for the boiler: 100% complete

Tanks

49

Pipe installation at the water tank. Successfully installed

Piping

50

Fire hydrant and product line from tanks to

loading bay

Piping

51

Road Works 100% done

Roads

52

Fire hydrant pipe before

Fire Hydrant pipes before and water line

from the county 100% complete

53

Fire hydrant pipe after

54

Insulation of steam lines complete

Pipe Insulation

55

Pipe Insulation

56

Will be used to trap any oil spillage from the tanks

Dyke Wall

57

To direct water away from the compound

Water Drainage before

58

Water Drainage after

59

Fire Hydrant line from the back side of the tank farm is 75% complete.Water transfer line from Tank 1 to tank 7 is on-going.

60

Installation of the agitators as per the required recommendations is complete in

phase one.

THANK YOU