project execution model
Post on 26-Nov-2015
248 Views
Preview:
DESCRIPTION
TRANSCRIPT
-
Aker Kvaerner Common PEM
User Guide
-
AKER KVAERNER COMMON PEM USER GUIDE Page 2
CONTENTS
Page 1.0 Introduction to the Project Execution Model Initiative 3 2.0 PEM Planning and Control Structure 7
Strategic Level
Control Level Control Level Key Activities
Project Tendering Project Execution Project Management
Execution Level
3.0 Project Organisation 14 4.0 Description of the PEM Strategic Level PHASES 15 5.0 Description of the PEM Control Level STAGES 17 6.0 PEM Glossary of Terms and Abbreviations 23 Appendix A Control Level Milestone Requirements PROJECT TENDERING Appendix B Control Level Milestone Requirements PROJECT EXECUTION Appendix C Control Level Milestone Requirements PROJECT MANAGEMENT
-
AKER KVAERNER COMMON PEM USER GUIDE Page 3
1.0 INTRODUCTION TO THE PROJECT EXECUTION MODEL INITIATIVE Aker Kvaerner (AK) is a major contractor to the offshore and onshore
industries, providing contract management, services, products and integrated solutions spanning the complete life cycle value chain across a wide variety of business sectors.
For the purpose of successful execution and delivery, and not least as a
result of the last few decades demand for engineering, procurement and construction (EPC) deliveries coupled with the industrys requirement for control of costs, delivery time and quality, Kvaerner developed and documented an approach to project execution. In addition the merger of Aker Maritime and Kvaerner has contributed to a further improvement of this execution methodology and forms the basis for the Project Execution Model initiative in Aker Kvaerner (AK).
This document is an introduction and summary of the AK approach for
controlled execution of our projects. A model that is being rolled out across AK corporately for implementation by all business streams and their adaptation of the methodology to the requirements of the local contracting environment.
The Project Execution Model (PEM) is the most important business initiative
within AK and forms the basis for standardising our project execution methodology across our diverse business. It will also enable more consistent and improved performance towards satisfying our customers expectations as well as envisaged sustainable business presence in the markets we are currently participating.
The foundation of the methodology is many years of experience with offshore
and onshore industry projects from all over the world and not least the recent execution of several major EPC projects. A significant experience in this context is the knowledge of the actual project costs, how these are distributed and relate to the various activities over time and the processes influencing the end cost of the product.
The figure below illustrates typical costs experienced with major Harsh
Environment projects. As seen, half of the cost lies with procurement, some 30-40% with construction and only some 10% with engineering. However, at the same time investigations show that the influence of engineering over the end cost of the product is 90%, whilst the similar influencing power for procurement, construction and installation is around 5%, 3% and 2% respectively.
From this it is evident that although the expenditures of costs are much larger
in later phases, the possibility to influence the end (product) cost during the late phases is very limited.
-
AKER KVAERNER COMMON PEM USER GUIDE Page 4
A similar picture emerges from the Construction Industry Institutes gathering
of information from 700 major projects in North America, where the ability to influence the end cost was plotted against time, identifying the period during concept & system definition, i.e. prior to committing to major purchases, as the Critical Performance Period during which end cost could be influenced significantly.
-
AKER KVAERNER COMMON PEM USER GUIDE Page 5
The Harsh Environment and the North America figures give the same message it is the depth and quality of the project definition work during the early phases that decide success or failure. This is especially so for the cost aspect discussed here, but experience shows that other areas such as safety, project schedule and product quality very often follow a similar pattern.
The main lesson is therefore: Invest in the period prior to the heavy
investment in the form of time & man-hours (i.e. in project definition) and harvest the benefits at the tail end of the project.
Translating this learning into practical application is a challenge AK has taken
on when developing a systematic approach to the execution of projects. In this methodology AK has captured the need for giving focus to the early phases, in parallel with understanding the need for a continuous focus towards the end product as well as constantly ensuring that engineering is fit for construction, commissioning and operations. Further it should be noted that the methodology is equally adaptable to all project activities as the methodology outlines the path followed by most projects.
To take on the challenge of giving sufficient focus and attention to the early
phases, coupled with the required focus towards the end product, including construction and operational requirements, AK has subdivided the project life cycle into 6 execution phases.
The objective of this project execution model (PEM) and the breakdown into
these six phases is to improve quality, timely delivery and profitability, by
Providing management attention to critical activities and emphasis vs. the end result and timely delivery, throughout the project duration.
Subdividing the project into phases controlled by milestones. Specify strict quality requirements for each milestone, which
eliminates the transfer of work from one phase to the next Focus on inter-discipline dependencies to ensure quality in all parts of
the project Optimise the transfer of information from one project participant to
another
-
AKER KVAERNER COMMON PEM USER GUIDE Page 6
Specific attention to systems throughout the project life cycle When appropriate, dividing the product in part (sub) projects with clear
objectives and scope of work definition. Organising multidiscipline teams, for the individual phases and Sub-
projects respectively, accountable for budget adherence, timely delivery and quality.
Empowerment of teams Standardisation and reuse of solutions, products and execution
processes, Providing a sound basis for experience transfer.
AK PEM Introduction9th April 03 Page 33
PEM improvement processPEM Phase
& StageDescriptions
ImprovedPEM
Descriptions Recommendation by Business Area PEM Champion
Approval byAK PEM Network/ Steering
Committee
Project 1 Project 2 Project 3
Business Area PEM Champion
-
AKER KVAERNER COMMON PEM USER GUIDE Page 7
2.0 PEM PLANNING AND CONTROL STRUCTURE The link between the different work processes on a project is ensured through
the PEM. The PEM provides linkage between different disciplines and the different phases of the model and is broken down into three levels, Strategic, Control and Execution as indicated in the figure below.
Strategic Level The highest level in the PEM is the phase arrow, which is termed the
Strategic Level. Every project master schedule will reflect this level of the model.
Control Level The next level in the model is termed the Control Level in which the Strategic
Level Phases are further sub-divided into stages. There are mandatory milestones for each stage. Main interfaces to internal and external entities are also included in this level. The Control Level describes the sequence and completion level of multitasks through;
The major stage milestones within each phase Quality Levels and key deliverables for each stage
The Control Level is also reflected in the project schedule in the form of
allocated milestone dates and gate reviews.
AK PEM Introduction9th April 03 Page 13
Aker Kvaerner PEM
FEASIBILITY &CONCEPT
SYSTEMDEFINITION
DETAILING &FABRICATION
TENDER
& KICK-OFF
SYSTEMCOMPLETION
ASSEMBLY/ERECTION
STRATEGIC
EXECUTION
CONTROL
Specific work processes,systems & procedures
Corporate
Business Areas
Projects
Control level:
Major Milestones
Strategic level:
Execution level:SYSTEM DEFINITION PHASE - STAGE 3
MaterialQuantity
SimulationLevel 3
Update MTO/(MaterialQuantityBudget) Level 3
Call Off
Specifyremaining
Special Items
P&ID Level 3
UpdatePiping
DatabaseLevel 3
RequisitionPiping
&Valves
Review issueP&ID Level 3
Technicalinput POremaining
Special Items
WeightControl
Vendor Info.Inline
Instruments
Weight andCOG Piping
Level 3
3.3
3.3
L10
3.3
L14
3.3
L16
3.3
L17
3.3
L11
3.3
L12
3.3
L15
GlobalIntegration
ModelReviewLevel 3
PartProductPhase
ModelReviewLevel 2
EquipmentModellingLevel 3
Piping Design Level 3&
Clash Check
ProduceSystem
Isometric(RelevantSystems)
Piping &Layout
Review P&IDLevel 3
Pipe SupportDesignLevel 3
IssueStress ISO
StressCalculation
NO
YES
Input toStructural
To Stress ISOReport in Part
ProductPhase
Freeze Infoall
Equipment>=1tonn
Operational &Maintenance
ReviewLevel 3
HSEVerification
Level 3
3.3
L01
3.3
L02
3.3
L05
3.3
L06
3.3
L03
3.3
L04
3.3
L07
3.3 L13
CriticalLine
3.2
Prepare TestDefinition
DetailedPiping
FabricationMethod
Planning
CommissioningLimits (P&ID &
Line List)
3.3
L08
3.3
L09
Overall Methodfor Installation/
Pre-fab.
Execution level:
-
AKER KVAERNER COMMON PEM USER GUIDE Page 8
Key Activities
Key activities are major work tasks carried out throughout the project lifecycle.
The control level defines the quality requirement for each of the key activities (deliverables) for each PEM milestone. The key activities are presented in three Modules Project Tendering; Project Execution and Project Management.
Project Tendering Applying the PEM approach to the tendering process will deliver a well
defined and clearly understood project scope. The Tendering and Kick-Off phase has its own set of Key Activities covering
both Project Execution and Project Management Activity. This reflects the smaller, multi-discipline teams which will normally be involved in the tendering process.
The stages and milestones within the Tender and Kick-Off Phase reflect the
mandatory requirements of Group Policy 3.1 Tendering and Project Contract Risk. Progress through the Tender and Kick-Off Phase is controlled through Aker Kvaerners web based support tool the Risk Dashboard.
The control level Project Tendering Key Activities and milestone requirements
are as displayed in the following Champagne Diagram:
FEA S IB IL ITY &C O N C EPT
SY STEMD EFIN IT IO N
D ETA IL IN G &FA B R IC A TIO N
TEN D E R
& K IC K -O FF
S YSTEMC O M P LETIO N
A SSE M B LY/ER EC TIO N
M ilestones:C O N C EPT C O M PLETE
M 1D
G LO B A L D ESIG N C O M PLETE
M 2C M 3C
PR EA SSEM B LIES R EA D Y FO R
SH IPM EN TM 4C
M EC H A N IC A LC O M PLETE
M 5D
C LIEN T TA K EO V ER
SU B M ITTEN D ER
K IC K -O FF C O M PLETE
Phase and stage transfer th rougholl gates?having stric t requ irem ents w .r.t. quality ,schedule and cost
-
AKER KVAERNER COMMON PEM USER GUIDE Page 9
Project Tendering Control Level Milestone Requirements / Quality Levels DM Risk Policy Decision Milestone (DM1) (DM2) (DM3) (DM4 (DM5)
-
AKER KVAERNER COMMON PEM USER GUIDE Page 10
Project Execution The control level Project Execution key activities quality requirements are
displayed in the following Champagne Diagram PROJECT EXECUTION Control Level Milestone Requirements / Quality Levels
-
AKER KVAERNER COMMON PEM USER GUIDE Page 11
Project Management Module The Project Management Module comprises those project activities
associated with organising, monitoring and controlling the delivery of the work scope.
Again, the Key Activities reflect multidiscipline activities to be delivered in a
co-ordinated way in the correct sequence. Thus, the work of several disciplines / departments / work processes will be required to achieve the milestone requirements for any particular Key Activity.
The Project Management Control Level Key Activities and Milestone Requirements are displayed in the following Champagne Diagram. PROJECT MANAGEMENT Control Level Milestone Requirements / Quality Levels
-
AKER KVAERNER COMMON PEM USER GUIDE Page 12
The project management will on a continuous basis follow up, review and check the activities of the project. To facilitate this process the appropriate tools and systems are available to report status, events and project future development, to evaluate deviations from original plan and to make and take decisions that need to be implemented.
Project Management.
Interface Control
Quality
Decision
Proj Schedules
Budget/Cost
Change Control
Event/Risk Reports
Economy
Progress
Tools for control and monitoring: Management evaluationof deviation and risk:
Management Decision:
-
AKER KVAERNER COMMON PEM USER GUIDE Page 13
Execution Level The content of the Execution Level reflects the individual business and is thus
not common. The Execution Level is the third level in the PEM. The execution level
encompasses multifunctional work processes with flow sheets as well as milestone activity descriptions, check lists and quality requirements. Activities are smaller work tasks and related deliverables that make up a key activity. The activity descriptions reside within the activity flowcharts and detail the input and output, checklist and procedural definition of the activity and tools required to perform it. The Execution Level is the basis for the development of the network in the project programme.
A typical structure for the execution level is indicated here:
AK PEM Introduction
Stage Objectives
Concept Execution
DETAILING& FABRICATION
SYSTEM COMPLETION
FEASIBILITY &CONCEPT
SYSTEM DEFINITION
ASSEMBLY/ERECTIONKey Activities
Phases
M1B M1C M1D M2C M5DM4CM3A M3CM3BM1A M2A
QL1
QL1
QL2
QL1
QL1
QL3QL1 QL2
M2B
QL2
QL2
QL1 QL2
QL1
QL2
QL2
QL3
QL3
QL3
QL2 QL3 QL4
QL3
QL7
QL4
QL7
QL6QL4 QL6
QL4 Q5
QL1 QL2 QL3 QL4
Procurement 1st priority Equipment2nd priority Equipment3rd priority EquipmentBulk Material/MTO
System EngineeringP&ID,Line List & MELEIT Databases& registers
HSE in Design
Layout and 3D Model
Fabrication/Construction
Completion
Sub Contracting1st priority subcontracts2nd priority subcontracts
QL4 QL5
M4A M4B M5A M5B M5C
QL5 QL5QL1
QL1
QL2QL2 QL3
QL3 QL4
QL4
QL5
QL2 QL3 QL3QL5
QL5
QL4
QL1 QL2
QL3
QL6 QL7
QL5
QL5 QL6
QL5QL5
QL6
QL5
QL1
QL5
QL5
QL4 QL4 QL4
Key Activities
Action List
Gate ReviewReport
Control LevelExecution Level
Process
Structural
HVAC
Architectual
Instrument
Mechanical
Civil
Electrical
Piping
Activity Descriptions
Flow Charts
Control Object checklists
Existing Procedures orDiscipline knowledge base or Governing documentation
Work Processes
Quality Level descriptions
MilestoneRequirements
Key ActivityM
ilest
one
Discipline Gate Review
Summary Reports
D i s c i p l i n e G a t e R e v i e w S u m m a r y R e p o r t P r o j e c t N a m e :P r o j e c t N o . :
C l i e n t :
D i s c i p l i n e :S t a g e M i l e s t o n e :
P r e p a r e d b y ( L e a d . e n g . )R e v i e w e d b y ( D e p t . M g r . )
N o . S u b j e c t C o m p l i a n c e1 I s t h e s t a t u s o f a l l a c t i v i t ie s / c o n t r o l o b je c t s c o m p l ia n t w i t h t h e
d i s c i p l i n e s t a g e o b je c t i v e s ?
2 A r e a l l d e v i a t i o n s / h o l d s s u m m a r i z e d a n d r is k s in d i c a t e d i n t h e a t t a c h e d " s u m m a r y o f d e v i a t i o n s , h o l d s a n d r i s k s " ?
3 A r e t h e i n p u t s r e c e i v e d o f t h e c o r r e c t s t a t u s a n d u s e d f o r t h e a c t iv it y a s p e r a p p l i c a b le f l o w c h a r t
4 A r e " H o l d s " , a s a p p l i c a b l e , in d i c a t e d o n t h e i s s u e d / r e l e a s e d d o c u m e n t s ?
5 A l l a p p l i c a b l e a c t iv i t y c h e c k li s t s c o m p l e t e d a n d d e v i a t io n s / h o l d s l i s t e d ?
6 H a v e i n d e p e n d e n t s p o t - c h e c k s b e e n e x e c u t e d o n t h e A c t i v i t y c h e c k l i s t s ?
7 V a l i d a t i o n a n d c h e c k i n g p r o c e d u r e ( C P 2 2 1 . 0 0 4 ( Z o e t e r m e e r ) C P 3 1 2 8 ( S o le n t ) + E N G 0 0 5 , E N G 0 0 6 , E N G 0 0 7 , E n g 0 1 2 ( S t o c k t o n ) ) i m p l e m e n t e d : - C h e c k p r i n t s - A p p r o v a l s o f i s s u e d d o c u m e n t s ( s i g n e d o f f ) - I n t e r d i s c i p l i n e r e v i e w ( K e y D o c u m e n t R e v i e w s , in t e r s q u a d s , e t c ) - I m p l e m e n t a t i o n o f c l i e n t c o m m e n t s
8 A n y c r i t ic a l d e la y s o f t h e a c t u a l w o r k c o m p a r e d t o t h e l e v e l 3 / 4 s c h e d u l e s ?
9 D i s c i p l i n e g a t e r e v ie w c h e c k l i s t c o m p l e t e d a s a p p l ic a b l e ?
1 0 A n y k e y le a r n i n g t h a t n e e d s t o b e c o m m u n i c a t e d w i t h i n E & C ( e . g . v i a P r o je c t s , L e s s o n s L e a r n e d s y s t e m s , P r o c e d u r e s e t c . ) ?
D i s t r i b u t i o n : P r o j e c t m a n a g e r
L e a d e n g in e e r D is c i p l i n e m a n a g e r
P E M G a t e R e v ie w t e a m Q A m a n a g e r
A t t a c h m e n t s :S u m m a r y o f D i s c i p li n e G a t e R e v ie w C h e c k L i s t , d e v i a t io n s , h o l d s a n d r i s k s
T h e t e c h n ic a l s p e c ia l is t / d e p a r t m e n t m a n a g e r i s r e s p o n s ib l e t o c h e c k t h e s u b je c t s b e l o w a n d c o m p le t e t h e f o r m , t o b e c o m p le t e d a n d i s s u e d m in 3 w o r k i n g d a y s b e f o r e g a t e r e v i e w
D i s c i p l i n e G a t e R e v i e w S u m m a r y R e p o r t P r o j e c t N a m e :P r o j e c t N o . :
C l i e n t :D i s c i p l i n e :
S t a g e M i l e s t o n e :
P r e p a r e d b y ( L e a d . e n g . )R e v i e w e d b y ( D e p t . M g r . )
N o . S u b j e c t C o m p l i a n c e1 I s t h e s t a t u s o f a l l a c t i v i t ie s / c o n t r o l o b j e c t s c o m p l ia n t w i t h t h e
d i s c i p l i n e s t a g e o b je c t i v e s ?
2 A r e a l l d e v i a t i o n s / h o l d s s u m m a r i z e d a n d r is k s in d i c a t e d i n t h e a t t a c h e d " s u m m a r y o f d e v i a t i o n s , h o ld s a n d r i s k s " ?
3 A r e t h e i n p u t s r e c e iv e d o f t h e c o r r e c t s t a t u s a n d u s e d f o r t h e a c t iv i t y a s p e r a p p l ic a b le f l o w c h a r t
4 A r e " H o l d s " , a s a p p l i c a b l e , i n d i c a t e d o n t h e i s s u e d / r e l e a s e d d o c u m e n t s ?
5 A l l a p p l i c a b l e a c t iv i t y c h e c k l i s t s c o m p l e t e d a n d d e v i a t i o n s / h o l d s l i s t e d ?
6 H a v e i n d e p e n d e n t s p o t - c h e c k s b e e n e x e c u t e d o n t h e A c t i v i t y c h e c k l is t s ?
7 V a l i d a t i o n a n d c h e c k i n g p r o c e d u r e ( C P 2 2 1 . 0 0 4 ( Z o e t e r m e e r ) C P 3 1 2 8 ( S o le n t ) + E N G 0 0 5 , E N G 0 0 6 , E N G 0 0 7 , E n g 0 1 2 ( S t o c k t o n ) ) i m p l e m e n t e d : - C h e c k p r i n t s - A p p r o v a l s o f i s s u e d d o c u m e n t s ( s i g n e d o f f ) - I n t e r d i s c i p l i n e r e v i e w ( K e y D o c u m e n t R e v i e w s , in t e r s q u a d s , e t c ) - I m p le m e n t a t i o n o f c l i e n t c o m m e n t s
8 A n y c r i t ic a l d e la y s o f t h e a c t u a l w o r k c o m p a r e d t o t h e l e v e l 3 / 4 s c h e d u l e s ?
9 D i s c i p l i n e g a t e r e v ie w c h e c k l i s t c o m p l e t e d a s a p p l i c a b l e ?
1 0 A n y k e y l e a r n i n g t h a t n e e d s t o b e c o m m u n i c a t e d w i t h i n E & C ( e . g . v i a P r o je c t s , L e s s o n s L e a r n e d s y s t e m s , P r o c e d u r e s e t c . ) ?
D i s t r i b u t i o n : P r o j e c t m a n a g e r
L e a d e n g in e e r D i s c i p l i n e m a n a g e r
P E M G a t e R e v ie w t e a m Q A m a n a g e r
A t t a c h m e n t s :S u m m a r y o f D is c i p l i n e G a t e R e v ie w C h e c k L i s t , d e v i a t io n s , h o l d s a n d r i s k s
T h e t e c h n ic a l s p e c i a l is t / d e p a r t m e n t m a n a g e r is r e s p o n s i b l e t o c h e c k t h e s u b j e c t s b e lo w a n d c o m p le t e t h e f o r m , t o b e c o m p le t e d a n d i s s u e d m in 3 w o r k i n g d a y s b e f o r e g a t e r e v i e w
D i s c i p l i n e G a t e R e v i e w S u m m a r y R e p o r t P r o j e c t N a m e :
P r o j e c t N o . :
C l i e n t :D i s c i p l i n e :
S t a g e M i l e s t o n e :
P r e p a r e d b y ( L e a d . e n g . )
R e v i e w e d b y ( D e p t . M g r . )
N o . S u b j e c t C o m p l i a n c e1 I s t h e s t a t u s o f a l l a c t i v i t ie s / c o n t r o l o b j e c t s c o m p l ia n t w i t h t h e
d i s c i p l i n e s t a g e o b je c t i v e s ?
2 A r e a l l d e v i a t i o n s / h o l d s s u m m a r i z e d a n d r is k s in d i c a t e d i n t h e a t t a c h e d " s u m m a r y o f d e v i a t i o n s , h o ld s a n d r i s k s " ?
3 A r e t h e i n p u t s r e c e iv e d o f t h e c o r r e c t s t a t u s a n d u s e d f o r t h e a c t iv it y a s p e r a p p l ic a b le f l o w c h a r t
4 A r e " H o l d s " , a s a p p l i c a b l e , i n d i c a t e d o n t h e i s s u e d / r e l e a s e d d o c u m e n t s ?
5 A ll a p p l i c a b l e a c t iv i t y c h e c k li s t s c o m p l e t e d a n d d e v i a t i o n s / h o l d s l i s t e d ?
6 H a v e i n d e p e n d e n t s p o t - c h e c k s b e e n e x e c u t e d o n t h e A c t i v i t y c h e c k l is t s ?
7 V a l i d a t i o n a n d c h e c k i n g p r o c e d u r e ( C P 2 2 1 . 0 0 4 ( Z o e t e r m e e r ) C P 3 1 2 8 ( S o le n t ) + E N G 0 0 5 , E N G 0 0 6 , E N G 0 0 7 , E n g 0 1 2 ( S t o c k t o n ) ) i m p l e m e n t e d : - C h e c k p r i n t s - A p p r o v a l s o f i s s u e d d o c u m e n t s ( s i g n e d o f f ) - I n t e r d i s c i p l i n e r e v i e w ( K e y D o c u m e n t R e v i e w s , in t e r s q u a d s , e t c ) - I m p le m e n t a t i o n o f c l i e n t c o m m e n t s
8 A n y c r i t ic a l d e la y s o f t h e a c t u a l w o r k c o m p a r e d t o t h e l e v e l 3 / 4 s c h e d u l e s ?
9 D i s c i p l i n e g a t e r e v ie w c h e c k l i s t c o m p l e t e d a s a p p l i c a b l e ?
1 0 A n y k e y l e a r n i n g t h a t n e e d s t o b e c o m m u n i c a t e d w i t h i n E & C ( e . g . v i a P r o je c t s , L e s s o n s L e a r n e d s y s t e m s , P r o c e d u r e s e t c . ) ?
D i s t r i b u t i o n : P r o j e c t m a n a g e r
L e a d e n g in e e r D i s c i p l i n e m a n a g e r
P E M G a t e R e v ie w t e a m Q A m a n a g e r
A t t a c h m e n t s :S u m m a r y o f D is c i p li n e G a t e R e v ie w C h e c k L i s t , d e v i a t io n s , h o l d s a n d r i s k s
T h e t e c h n ic a l s p e c i a l is t / d e p a r t m e n t m a n a g e r is r e s p o n s i b l e t o c h e c k t h e s u b j e c t s b e lo w a n d c o m p le t e t h e f o r m , t o b e c o m p le t e d a n d i s s u e d m in 3 w o r k i n g d a y s b e f o r e g a t e r e v i e w
D i s c i p l i n e G a t e R e v i e w S u m m a r y R e p o r t P r o j e c t N a m e :P r o j e c t N o . :
C l i e n t :D i s c i p l i n e :
S t a g e M i l e s t o n e :
P r e p a r e d b y ( L e a d . e n g . )R e v i e w e d b y ( D e p t . M g r . )
N o . S u b j e c t C o m p l i a n c e1 I s t h e s t a t u s o f a l l a c t i v i t i e s / c o n t r o l o b je c t s c o m p l ia n t w i t h t h e
d i s c i p l i n e s t a g e o b je c t i v e s ?
2 A r e a l l d e v i a t i o n s / h o l d s s u m m a r i z e d a n d r is k s in d i c a t e d i n t h e a t t a c h e d " s u m m a r y o f d e v i a t i o n s , h o ld s a n d r i s k s " ?
3 A r e t h e i n p u t s r e c e iv e d o f t h e c o r r e c t s t a t u s a n d u s e d f o r t h e a c t i v i t y a s p e r a p p l ic a b le f l o w c h a r t
4 A r e " H o l d s " , a s a p p l i c a b l e , in d i c a t e d o n t h e i s s u e d / r e l e a s e d d o c u m e n t s ?
5 A l l a p p l i c a b l e a c t iv i t y c h e c k l i s t s c o m p l e t e d a n d d e v i a t io n s / h o l d s l i s t e d ?
6 H a v e i n d e p e n d e n t s p o t - c h e c k s b e e n e x e c u t e d o n t h e A c t i v i t y c h e c k l is t s ?
7 V a l i d a t i o n a n d c h e c k i n g p r o c e d u r e ( C P 2 2 1 . 0 0 4 ( Z o e t e r m e e r ) C P 3 1 2 8 ( S o le n t ) + E N G 0 0 5 , E N G 0 0 6 , E N G 0 0 7 , E n g 0 1 2 ( S t o c k t o n ) ) i m p l e m e n t e d : - C h e c k p r i n t s - A p p r o v a l s o f i s s u e d d o c u m e n t s ( s i g n e d o f f ) - I n t e r d i s c i p l i n e r e v i e w ( K e y D o c u m e n t R e v i e w s , i n t e r s q u a d s , e t c ) - I m p le m e n t a t i o n o f c l i e n t c o m m e n t s
8 A n y c r i t ic a l d e la y s o f t h e a c t u a l w o r k c o m p a r e d t o t h e l e v e l 3 / 4 s c h e d u l e s ?
9 D i s c i p l i n e g a t e r e v ie w c h e c k l i s t c o m p l e t e d a s a p p l ic a b l e ?
1 0 A n y k e y le a r n i n g t h a t n e e d s t o b e c o m m u n i c a t e d w i t h i n E & C ( e . g . v i a P r o j e c t s , L e s s o n s L e a r n e d s y s t e m s , P r o c e d u r e s e t c . ) ?
D i s t r i b u t i o n : P r o j e c t m a n a g e r
L e a d e n g i n e e r D is c i p l i n e m a n a g e r
P E M G a t e R e v ie w t e a m Q A m a n a g e r
A t t a c h m e n t s :S u m m a r y o f D is c i p l i n e G a t e R e v i e w C h e c k L i s t , d e v i a t io n s , h o l d s a n d r i s k s
T h e t e c h n ic a l s p e c ia l is t / d e p a r t m e n t m a n a g e r is r e s p o n s ib l e t o c h e c k t h e s u b je c t s b e lo w a n d c o m p le t e t h e f o r m , t o b e c o m p l e t e d a n d i s s u e d m in 3 w o r k i n g d a y s b e f o r e g a t e r e v i e w
-
AKER KVAERNER COMMON PEM USER GUIDE Page 14
3.0 PROJECT ORGANISATION
The PEM is a product, sequence and phase-oriented model. Hence the tasks to be performed vary throughout the execution, responding to the requirements of the respective phases. This implies that the project organisation must be dynamic and be adjusted to suit the requirements within each phase.
The project management functions covered by the management team and key management personnel remain intact throughout all project phases in order to provide continuity and keep full focus on the final product. However, the teams physical composition, location, organisational structure and emphasis will reflect the phase, scope of supply, business strategies and associated challenges.
The project organisation will complete work meeting respective PEM
milestone and quality requirements before or at the end of each PEM stage. Further the organisational structure and composition will again reflect the scope of work to be performed, the phase in question as well as the overall business strategies in place.
The project management will on a continuous basis follow up, review and check the activities of the project. To facilitate this process the appropriate tools and systems are available to report status, events and project future development, to evaluate deviations from original plan and to make and take decisions that need to be implemented. One of the important elements of project management & control which PEM brings is the requirement to identify where the PEM milestones will occur on the project and to check & verify progress at these milestones prior to proceeding further. This check & verification process is referred to as a PEM Gate Review. Projects are required to establish at the outset a PEM Strategy which will set out when & how Gate Reviews will be organised. Consideration will be given to the significance of individual milestones to determine an appropriate level of scrutiny and who should conduct the review.
The capabilities of the project organisation are very important for the
successful outcome of the project execution. The attitudes and cultural elements are therefore given high visibility in the training of AK personnel and during project execution. Integral to the AK approach is to:
Focus on the totality (end product) rather than sub-optimisation Be solution oriented Be proactive rather than reactive Keep a hands on attitude, at the same time as ensuring that tasks and
decisions are performed on the most appropriate level Focus on actions required to solve and overcome challenges Solve problems now rather than wait until it may be too late Be accountable through delegation of complete tasks and
accompanying authority
-
AKER KVAERNER COMMON PEM USER GUIDE Page 15
SECTION 4.0
DESCRIPTION OF THE PEM
STRATEGIC LEVEL PHASES
-
AKER KVAERNER COMMON PEM USER GUIDE Page 16
PEM STRATEGIC LEVEL The top level Strategic is divided into several phases. The phases in the strategic level represent how a general project progresses from start towards the end result. There are 5 sequential phases as follows: Phase 1 Feasibility and Concept. Phase 2 System Definition. Phase 3 Detailing and Fabrication. Phase 4 Assembly/Erection. Phase 5 System Completion. Aker Kvaerner may be involved in some or all of these phases dependent on the individual project. In addition there is the Tender and Kick-Off Phase. This phase is mandatory for all projects, irrespective of which sequential phase (1-5) the actual project execution starts from. The strategic level is shown simply in the diagram below:
-
AKER KVAERNER COMMON PEM USER GUIDE Page 17
SECTION 5.0
DESCRIPTION OF THE PEM
CONTROL LEVEL STAGES
-
AKER KVAERNER COMMON PEM USER GUIDE Page 18
PEM Control Level - Tender & Kick-Off
Description
Pre-qualify for all targeted projects and thereafter prepare a winning tender with an acceptable risk exposure and profit potential. Provide firm schedules, technical and commercial basis for start up of the project in accordance with established Aker Kvaerner methods and procedures.
Evaluate, decide and obtain approval to bid. Pending a positive decision to bid, prepare tender documentation and get the required approvals. Review and identify design basis maturity vs Aker Kvaerner Project Execution Model (AKPEM) and shape scope accordingly. Submit tender to the client. Negotiate and sign contract for the work tendered. Hand-over to the project execution team, including:
start up and mobilisation plans
project execution strategy and organisation descriptions
project financing plans
project risk assessment
project baseline schedules and budgets
The phase includes Kick-Off of the project based on administrative and technical start-up packages.
Complete design basis to the nearest milestone of the Aker Kvaerner Project Execution Model (AKPEM). From this milestone onwards the project follows the standard phases of the AKPEM.
Key Stage Objectives
Receipt of (ITT)Invitation to Tender
Key Stage ObjectivesProject Execution Concept/Feed/Design Maturity CheckProject Management ITT review Tender cost, schedule
and budget Update KT Analysis Check Winning strategy
& cost vs Client objectives/ budget
Initial project execution strategy
Update risk register Nominate Tender Team Bid/No Bid
Key Stage ObjectivesProject Execution Verify/Develop Scope of
Work for Project ExecutionProject Management Mobilise tender team &
Kick-off Tender Execution Strategy,
budget and plan Project Execution Strategy
&t Schedule HSE program Estimating/Weight & Cost Define Org. / Nominate Key
Project Personnel Pricing/Compensation
strategy & Formats Tender clarific./ qualifics Risk Analysis Draft Tender
Key Stage ObjectivesProject Execution SOW Verified and Project
Execution approvedProject Management Tender Document Review &
Management Approvals Project Execution Strategy,
Organisation & Project Team Cost estimate & Cash flow Schedule / Manpower
Projection Plan Contract: Terms & Conditions Sub-Contracts: Terms &
Conditions Negotiation Mandate and
Team Risk Management
Risk Register Contingency determination
Price/compensation formats Group Risk Committee review
(if required by policy)
ASSESS
TENDERPHASE START SUBMIT TENDER
Stage TA
PREPAREStage TB
MTA MTB
TENDER & KICK OFFTender phase
Stage TD NEGOTIATE
Key Stage ObjectivesProject Execution Bid Clarifications Project Management Negotiations Bid clarifications Update:
- Key data- Price- Contingency- Risk Analysis- Execution Plan
Management approval
Contract ready forsignature
Prepare Hand-over toProject Team
SIGN CONTRACT
MTE
APPROVEStage TC Stage TE
KICK-OFF
MTDMTC
KICK-OFF COMPLETE
Key Stage ObjectivesProject Execution Tender Team Hand-over Scope of Work Start-up Plan Design Basis AlignmentProject Management Mobilise Project team Tender Team Hand-over Client Kick-off Meeting(s) Project Start-up Plan (Mgmt) Internal Kick-off meetings Teambuilding
DRAFT TENDERBID / NO BID
POSITIONING
Key Stage Objectives Business Development Prospect ID & Screening Perform KT Analysis Check Core Capability &
Strategy Profile (CCSP) Client Contact/Objectives Winning Strategy Partners & Scope Identify Tender
Accountable Prequalification
Receipt of (ITT)Invitation to Tender
Key Stage ObjectivesProject Execution Concept/Feed/Design Maturity CheckProject Management ITT review Tender cost, schedule
and budget Update KT Analysis Check Winning strategy
& cost vs Client objectives/ budget
Initial project execution strategy
Update risk register Nominate Tender Team Bid/No Bid
Key Stage ObjectivesProject Execution Verify/Develop Scope of
Work for Project ExecutionProject Management Mobilise tender team &
Kick-off Tender Execution Strategy,
budget and plan Project Execution Strategy
&t Schedule HSE program Estimating/Weight & Cost Define Org. / Nominate Key
Project Personnel Pricing/Compensation
strategy & Formats Tender clarific./ qualifics Risk Analysis Draft Tender
Key Stage ObjectivesProject Execution SOW Verified and Project
Execution approvedProject Management Tender Document Review &
Management Approvals Project Execution Strategy,
Organisation & Project Team Cost estimate & Cash flow Schedule / Manpower
Projection Plan Contract: Terms & Conditions Sub-Contracts: Terms &
Conditions Negotiation Mandate and
Team Risk Management
Risk Register Contingency determination
Price/compensation formats Group Risk Committee review
(if required by policy)
ASSESS
TENDERPHASE START SUBMIT TENDER
Stage TA
PREPAREStage TB
MTAMTA MTBMTB
TENDER & KICK OFFTender phase
Stage TD NEGOTIATE
Key Stage ObjectivesProject Execution Bid Clarifications Project Management Negotiations Bid clarifications Update:
- Key data- Price- Contingency- Risk Analysis- Execution Plan
Management approval
Contract ready forsignature
Prepare Hand-over toProject Team
SIGN CONTRACT
MTEMTE
APPROVEStage TC Stage TE
KICK-OFF
MTDMTDMTCMTC
KICK-OFF COMPLETE
Key Stage ObjectivesProject Execution Tender Team Hand-over Scope of Work Start-up Plan Design Basis AlignmentProject Management Mobilise Project team Tender Team Hand-over Client Kick-off Meeting(s) Project Start-up Plan (Mgmt) Internal Kick-off meetings Teambuilding
DRAFT TENDERBID / NO BID
POSITIONING
Key Stage Objectives Business Development Prospect ID & Screening Perform KT Analysis Check Core Capability &
Strategy Profile (CCSP) Client Contact/Objectives Winning Strategy Partners & Scope Identify Tender
Accountable Prequalification
-
AKER KVAERNER COMMON PEM USER GUIDE Page 19
PEM Control Level - Feasibility & Concept
Description - Phase 1
Develop the best possible business case and winning solution for the client. The phase is also referred to as the value-engineering phase. The concept to be used is selected in this phase and thereby the project CAPEX and OPEX levels are defined (+/- 50 to 20 %), which then can be compared to the product income levels.
Scope: Selection of an optimal concept solution based on frozen and proven functional requirements, leading up an agreed and firm design basis Perform technical/economic optimisation of the selected concept to achieve a best for purpose technology, price and delivery time Identify a project execution strategy & plan based on the common AKPEM including a strategy for procurement & subcontracts Establish a cost budget and ensure a manageable execution risk for all parties Key Stage Objectives
OPPORTUNITY APPRAISAL
Key Stage ObjectivesProject Execution Define HSE Requirements Identify product, markets Establish possible process solutions Identify infrastructure requirements Identify environmental requirements Identify key process/ product
interfacesProject Management Evaluate business opportunity Establish first cost estimate
FEASIBLE CONCEPTS SELECTED
Stage 1A
FEASIBILITY STUDIESStage 1B
ALTERNATIVESGENERATED
M1A M1B
Phase 1
Key Stage ObjectivesProject Execution Define HSE goals Perform preliminary simulation & flow
diagrams Size Key equipment Layout block model and unit
arrangements Define preliminary construction
methods Identify major completion aspects
affecting the concept selectionProject Management Establish general execution
philosophy Define screening criteria Update cost estimate Rank alternatives Perform Risk assessment
CONCEPT SELECTIONKey Stage ObjectivesProject Execution Perform HSE studies to verify the
concepts and Environmental Impact assessment for permitting
Consolidate the final design basis. Optimize Process/System simulation
and flow diagrams Size remaining equipment and add to
equipment list Optimize overall layout including safety
assessment Update Constr. and Compl. methods Evaluate Local requirements Define Site enabling preparation criteria Project Management Develop overall execution schedule Establish preliminary Project Execution
Strategy Update cost estimate Determine Sourcing categories and
scenarios Update Risk assessment, concepts
Stage 1C
CONCEPT DEFINITIONStage 1D
Key Stage ObjectivesProject Execution Update HSE Studies and analyses and
prepare Environmental impact report Freeze functional requirements, design basis,
overall system description and layout Update Equipment list, flow diagrams Prepare electrical Single Line Diagram
Prepare preliminary P&IDs Inquire 1st priority equipment POs Finalize Overall Layout and unit arrangement Update Construction and Completion methods Site enabling subcontract package complete &
awarded Define Local requirementsProject Management Pre-qualify Main Sub-Contractors Finalise Project Execution Strategy Establish cost estimate Update Risk assessment Prepare preliminary detailed project schedule
CONCEPT SELECTED
M1C
CONCEPT COMPLETE
M1D
FEASIBILITY & CONCEPT
OPPORTUNITY APPRAISAL
Key Stage ObjectivesProject Execution Define HSE Requirements Identify product, markets Establish possible process solutions Identify infrastructure requirements Identify environmental requirements Identify key process/ product
interfacesProject Management Evaluate business opportunity Establish first cost estimate
FEASIBLE CONCEPTS SELECTED
Stage 1A
FEASIBILITY STUDIESStage 1B
ALTERNATIVESGENERATED
M1AM1A M1BM1B
Phase 1
Key Stage ObjectivesProject Execution Define HSE goals Perform preliminary simulation & flow
diagrams Size Key equipment Layout block model and unit
arrangements Define preliminary construction
methods Identify major completion aspects
affecting the concept selectionProject Management Establish general execution
philosophy Define screening criteria Update cost estimate Rank alternatives Perform Risk assessment
CONCEPT SELECTIONKey Stage ObjectivesProject Execution Perform HSE studies to verify the
concepts and Environmental Impact assessment for permitting
Consolidate the final design basis. Optimize Process/System simulation
and flow diagrams Size remaining equipment and add to
equipment list Optimize overall layout including safety
assessment Update Constr. and Compl. methods Evaluate Local requirements Define Site enabling preparation criteria Project Management Develop overall execution schedule Establish preliminary Project Execution
Strategy Update cost estimate Determine Sourcing categories and
scenarios Update Risk assessment, concepts
Stage 1C
CONCEPT DEFINITIONStage 1D
Key Stage ObjectivesProject Execution Update HSE Studies and analyses and
prepare Environmental impact report Freeze functional requirements, design basis,
overall system description and layout Update Equipment list, flow diagrams Prepare electrical Single Line Diagram
Prepare preliminary P&IDs Inquire 1st priority equipment POs Finalize Overall Layout and unit arrangement Update Construction and Completion methods Site enabling subcontract package complete &
awarded Define Local requirementsProject Management Pre-qualify Main Sub-Contractors Finalise Project Execution Strategy Establish cost estimate Update Risk assessment Prepare preliminary detailed project schedule
CONCEPT SELECTED
M1CM1C
CONCEPT COMPLETE
M1DM1D
FEASIBILITY & CONCEPT
-
AKER KVAERNER COMMON PEM USER GUIDE Page 20
PEM Control Level - System Definition
Description - Phase 2
The main objective of the System Definition Phase is to detail the concept and freeze system design, implement vendor information and complete the area design to a level where the interfaces between the systems and various areas are frozen. Procurement activities including order placement and vendor follow-up performed according to technical input and project requirements to enable freezing the design. All external interfaces with design impact shall have been included in the design and confirmed frozen by the other party. Subsequently, by end of this phase, the layout is frozen and "clash free, final detail engineering can proceed independently for the respective areas and fabrication and assembly/erection documentation can be prepared.
System design with focus on operability and maintainability with all safety aspects analysed and mitigating measures incorporated in the design shall have been performed . Working environment analyses, reviews and inspections to achieve arrangements for a safe and worker friendly environment done. Equipment and bulk materials sufficient to meet engineering supplier information and site need requirements procured. All requirements for subcontracting, manufacturing or temporary facilities shall have been included. Establish Methods for fabrication, assembly/erection and completion established and method requirements implemented in the design. Boundaries established and frozen and management of interfaces towards subcontractors and other contractors identified. Weight and cost budgets verified and likewise for contract milestones and detailed construction schedules.
Key Stage Objectives
M1D Milestone M2ACritical POs Awarded Milestone M2B
Layout and Main Structure FrozenMilestone M2C
Global Design Complete
Phase 2: System Definition Stage 2A:
SYSTEM DEFINITION Stage 2B: SYSTEM DESIGN & LAYOUT DEVELOPMENT
Stage 2C: GLOBAL DESIGN
Key Stage Objectives Work Scope
HSE and safety risk assessment, preliminary
First vendor information for 1 Priority POs implemented in
System Engineering
P&IDs, Line List , MEL , EIT registers/databases and 3D model
Procurement
1st priority Equipment POs awarded
Subcontracting plan & strategy complete
Fabrication/Construction methods and draft plan
Completion established and draft preparations
Key Stage Objectives Work Scope
HSE and safety risk assessment checked First vendor information for 2nd Priority POs implemented in System Engineering P&IDs , MEL, EIT registers/databases and 3D model Procurement; 2nd and 3rd priority equipment POs awarded, First bulk material orders out Subcontracting; 1st priority subcontract issued, 2nd priority subcontracts draft
Key Stage Objectives Work Scope
HSE and safety risk assessment frozen Frozen vendor information for all POs implemented in System Engineering P&IDs, Line List, MEL, EIT registers/databases and 3D model Procurement; All equipment POs awarded, all bulk materials orders placed Layout and 3D model are Clash free, Ready to outfitting details, All major interfaces frozen Subcontracting; 1st priority subcontracts awarded, 2nd priority subcontracts issued
-
AKER KVAERNER COMMON PEM USER GUIDE Page 21
Subcontracting; 1st priority subcontracts awarded, 2nd priority subcontracts issued Completion preparation substantially complete
Project Management
Prepare and verify project schedule and cost estimate
QA plan established
Quantity and weight baseline & trending program
Project Management Prepare Detailed Deliverable Schedule and update current cost estimate HSE program for engineering and procurement in place
Project Management Verify Contract Milestones and Detailed Construction Schedule and update current cost estimate HSE program for construction in place
-
AKER KVAERNER COMMON PEM USER GUIDE Page 22
PEM Control Level - Detailing & Fabrication
Description - Phase 3
The main objective of this phase is to complete detail design, prepare fabrication and construction documentation and fabricate and finalise part assemblies and modules Mechanical Complete.
Finalise detail design with all vendor information implemented and material take off done. Perform and issue work preparation documentation. Perform fabrication activities according to established methods. Mechanical complete product(s) ready for assembly/erection, including equipment packages. Verify the detailed schedules for the assembly/erection phase and ensure that all relevant site activities are documented MC complete.
Key Stage Objectives
Key Stage ObjectivesProject Execution Engineering databases complete All fabrication Bulk Material delivered Shop engineering detailing and work preparation for fabrication Pipe spools, Steel sections and Concrete sections prefabricated. Deep/major foundations & trenches completed. Construction site temporary facilities completed Hook-up/Commissioning Subcontracts awardedProject Management Update cost, schedule & risk program
Key Stage ObjectivesProject Execution Layout and 3D Model as build mark up of part
assemblies/modules All Bulk Material available to support the
Assembly / Erection sequence Part assemblies and modules/package units
fabricated and mechanically complete Commissioning commenced on selected
systemsProject Management Update cost, schedule & risk program
DETAIL DESIGN & SUBCONTRACTING
Key Stage ObjectivesProject Execution HSE risk assessment complete Close out HAZOP action items Final vendor information from all POs incorporated in System Engineering and layout / 3D model System Engineering & Layout / 3D model documentation issued for construction Material take off finalised and bulk material top up orders placed 2nd priority FC Subcontracts awarded Hook-up/Commissioning Subcontracts inquired Completion requirement incorporated in fabrication documentation Issue P& IDs IFC Issue Isometrics IFCProject Management Milestones and Detailed Construction Schedule verified. HSE program for construction and completion in place
M2C
Stage 3A
PRE FABRICATION &MANUFACTURING COMPLETE
Stage 3B
DETAIL DESIGN COMPLETE & SUBCONTRACTS AWARDED
M3A M3CM3B
DETAILING & FABRICATIONPhase 3
Stage 3C FABRICATION
PRE FABRICATION &MANUFACTURING
PREASSEMBLIESREADY FOR SHIPMENT
Key Stage ObjectivesProject Execution Engineering databases complete All fabrication Bulk Material delivered Shop engineering detailing and work preparation for fabrication Pipe spools, Steel sections and Concrete sections prefabricated. Deep/major foundations & trenches completed. Construction site temporary facilities completed Hook-up/Commissioning Subcontracts awardedProject Management Update cost, schedule & risk program
Key Stage ObjectivesProject Execution Layout and 3D Model as build mark up of part
assemblies/modules All Bulk Material available to support the
Assembly / Erection sequence Part assemblies and modules/package units
fabricated and mechanically complete Commissioning commenced on selected
systemsProject Management Update cost, schedule & risk program
DETAIL DESIGN & SUBCONTRACTING
Key Stage ObjectivesProject Execution HSE risk assessment complete Close out HAZOP action items Final vendor information from all POs incorporated in System Engineering and layout / 3D model System Engineering & Layout / 3D model documentation issued for construction Material take off finalised and bulk material top up orders placed 2nd priority FC Subcontracts awarded Hook-up/Commissioning Subcontracts inquired Completion requirement incorporated in fabrication documentation Issue P& IDs IFC Issue Isometrics IFCProject Management Milestones and Detailed Construction Schedule verified. HSE program for construction and completion in place
M2C
Stage 3A
PRE FABRICATION &MANUFACTURING COMPLETE
Stage 3B
DETAIL DESIGN COMPLETE & SUBCONTRACTS AWARDED
M3AM3A M3CM3CM3B
DETAILING & FABRICATIONPhase 3
Stage 3C FABRICATION
PRE FABRICATION &MANUFACTURING
PREASSEMBLIESREADY FOR SHIPMENT
-
AKER KVAERNER COMMON PEM USER GUIDE Page 23
PEM Control Level - Assembly/Erection
Description - Phase 4
The objective of this phase is to assemble the various parts products to a complete facility/product. Major equipment, pre- assemblies and modules are transported to site and installed. The construction work is MC complete & quality records available. Final insulation done and labelling & identification complete. All systems shall be ready for commissioning and commissioning can commence on selected systems. Surplus material definition and realisation started. Detailed schedules for the completion phase verified.
Key Stage Objectives
TRANSPORT & POSITIONING
M3C
ALL ASSEMBLY WORK COMPLETED
Stage 4A Stage 4B Stage 4C
ALL PREASSEMBLIESPOSITIONED
M4B M4C
MECHANICALCOMPLETION
MECHANICALCOMPLETE
Key Stage ObjectivesProject Execution Relevant as built mark-up complete Construction work mechanical complete & quality records available. Categorised Punch lists for all systems. All systems ready for commissioning and commenced in accordance with system completion schedule Final Insulation, Labelling & Identification complete.Project Management Update baseline and current cost estimate Establish HSE program for system completion phase
ASSEMBLY
Key Stage ObjectivesProject Execution Major equipment, Pre- assemblies & modules assembly installed. Install Balance of Plant Equipment and interconnecting piping systems. Minor structures, E& I installation and Main insulation complete. Final Labelling & Identification started. Operation & Maintenance Manuals available.Project Management Update baseline and current cost estimate and System Hand-over Schedule Implement HSE requirements
M4A
ASSEMBLY / ERECTIONPhase 4
Key Stage ObjectivesProject Execution Temporary Services & Power Distribution in place and Site roads complete up to sub-base. Major equipment, Pre- assemblies & modules transported to site and final positioned. On site fabrication and erection of major vessels and process equipment. Main Structures & Bridges CompleteProject Management Update baseline and current cost estimate Establish HSE requirements for Assembly & MC stages
TRANSPORT & POSITIONING
M3C
ALL ASSEMBLY WORK COMPLETED
Stage 4A Stage 4B Stage 4C
ALL PREASSEMBLIESPOSITIONED
M4BM4B M4CM4C
MECHANICALCOMPLETION
MECHANICALCOMPLETE
Key Stage ObjectivesProject Execution Relevant as built mark-up complete Construction work mechanical complete & quality records available. Categorised Punch lists for all systems. All systems ready for commissioning and commenced in accordance with system completion schedule Final Insulation, Labelling & Identification complete.Project Management Update baseline and current cost estimate Establish HSE program for system completion phase
ASSEMBLY
Key Stage ObjectivesProject Execution Major equipment, Pre- assemblies & modules assembly installed. Install Balance of Plant Equipment and interconnecting piping systems. Minor structures, E& I installation and Main insulation complete. Final Labelling & Identification started. Operation & Maintenance Manuals available.Project Management Update baseline and current cost estimate and System Hand-over Schedule Implement HSE requirements
M4AM4A
ASSEMBLY / ERECTIONPhase 4
Key Stage ObjectivesProject Execution Temporary Services & Power Distribution in place and Site roads complete up to sub-base. Major equipment, Pre- assemblies & modules transported to site and final positioned. On site fabrication and erection of major vessels and process equipment. Main Structures & Bridges CompleteProject Management Update baseline and current cost estimate Establish HSE requirements for Assembly & MC stages
-
AKER KVAERNER COMMON PEM USER GUIDE Page 24
PEM Control Level - System Completion
Description - Phase 5
The objective of this phase is complete the Contract Object in accordance with agreed schedule, quality and budget. Perform and finalise all commissioning activities. Ensure that any temporary items are removed and update relevant documents with as commissioned information. Perform the required preparations for start-up. Formalise the Operational responsibilities and start production and performance testing. Complete hand-over documentation, verify warranties and guaranties and sign-off on Acceptance Certificate
Establish experience data with Project Execution plan as built with lessons learned and relevant metrics for quantity/weight & productivity
Key Stage Objectives
M4
Stage 5A Stage 5C
SYSTEMSCOMMISSIONED
M5A
Phase 5
M5D
COMMISSIONING
START-UPCOMPLETE
Key Stage ObjectivesProject Execution Perform and finalise all commissioning activities. Preparations for start-up Temporary items removed. Relevant documents updated with as commissioned information Punch List cleared for start-upProject Management Update baseline and current cost estimate Implement HSE requirements
TAKE-OVER Key Stage Objectives Project Execution All work completed Update relevant documentation (as built) Complete hand-over documentation Punch lists clearedProject Management Warranties and guaranties sign-off on Acceptance Certificates Project Execution plan as built with lessons learned Metrics for quantity/weight & productivity Total HSE program implemented
Stage 5D
START-UPKey Stage ObjectivesProject Execution Operational Responsibilities formalised. Introduction of feedstock Start production Performance testingProject Management Implement HSE requirements
M5C
TAKEOVER COMPLETE
OFFSHORE INSTALLATION COMPLETE
M5B
Stage 5B (Offshore Projects) OFFSHORE
INSTALLATIONKey Stage ObjectivesProject Execution Preparation for sail away Perform tow out Complete installation of substructure / moorings / tethers Complete installation of the production facility Document offshore installation/hook-up work MC complete Offshore commissioningProject Management Update baseline and current cost estimate Implement HSE requirements
SYSTEM COMPLETION
M4
Stage 5A Stage 5C
SYSTEMSCOMMISSIONED
M5AM5A
Phase 5
M5DM5D
COMMISSIONING
START-UPCOMPLETE
Key Stage ObjectivesProject Execution Perform and finalise all commissioning activities. Preparations for start-up Temporary items removed. Relevant documents updated with as commissioned information Punch List cleared for start-upProject Management Update baseline and current cost estimate Implement HSE requirements
TAKE-OVER Key Stage Objectives Project Execution All work completed Update relevant documentation (as built) Complete hand-over documentation Punch lists clearedProject Management Warranties and guaranties sign-off on Acceptance Certificates Project Execution plan as built with lessons learned Metrics for quantity/weight & productivity Total HSE program implemented
Stage 5D
START-UPKey Stage ObjectivesProject Execution Operational Responsibilities formalised. Introduction of feedstock Start production Performance testingProject Management Implement HSE requirements
M5CM5C
TAKEOVER COMPLETE
OFFSHORE INSTALLATION COMPLETE
M5BM5B
Stage 5B (Offshore Projects) OFFSHORE
INSTALLATIONKey Stage ObjectivesProject Execution Preparation for sail away Perform tow out Complete installation of substructure / moorings / tethers Complete installation of the production facility Document offshore installation/hook-up work MC complete Offshore commissioningProject Management Update baseline and current cost estimate Implement HSE requirements
SYSTEM COMPLETION
-
AKER KVAERNER COMMON PEM USER GUIDE Page 25
SECTION 6.0
PEM GLOSSARY
OF
TERMS AND ABBREVIATIONS
-
AKER KVAERNER COMMON PEM USER GUIDE Page 26
PEM TERMS 1. Strategic Level
PEM: Project Execution Model Phase: The Project execution is divided into stages with Milestones at regular intervals Stage: Further work breakdown of a Phase, represented by key events or objectives in a
projects lifecycle. The Stage is characterised by the activities prior to reaching its milestone.
Milestones: Start and end of each stage within the Phase. A milestone is characterised by its multidiscipline nature. Milestones are measuring points where the combined effort from all the underlying activities meets the predefined milestone requirement..
2. Control Level
Key Activities: Deliverables grouped into a number of Key Activities for both Management & Discipline execution.
Quality Level: Defined grade of completeness for a Key Activity. A quality level chain is defined with description of grade of completeness for each quality level. Each quality level shall be achieved at certain major milestones.
3. Execution Level
Flow Chart: Flow chart diagram that describes the work flow within a discipline or management environment. The flow charts has input requirement & output data shown. The flow chart contains activity boxes. The activities are grouped in CTRs (Cost Time Resources) and has an Activity Description defined for each activity.
Cost Time Resources (CTR): DA group of Activities collected in a database for processing & planning of activities with man-hours and personnel categories linked to the activity. Also includes a summary of scope of work and deliverables.
Activity Description: Description of each activity with name and no. Detailed description of scope of work to be performed and list of deliverables for each activity.
Governing Documentation: Procedures, Work Instructions & Guidelines supporting the Flow charts work processes.
Quality Level (QL) Description: Defined grade of completeness for a Key Activity deliverable. A quality level chain is defined with description of grade of completeness for each quality level. Each quality level is normally achieved at a certain major milestone.
Control Objects: Each Key Activity deliverable is divided into several Control Objects that acts as information carrier (a set of information is linked to a control object) in a database or as a document or drawing.
Status Level: Defines grade of completeness for a control object defined by the Quality Level (QL) Description. A status level chain is defined with description of grade of completeness for each status level.
o S1 Preliminary. o S2 Released for Verification/ICD. o S3 Frozen. o S4 Detail Design Completed. o S5 Fabrication and Commissioning Information Added. o S6 Part Product As-Built Information Implemented. o S7 Product As-Built Information Implemented.
Check Lists: Gives the requirements at each Status Level for each Control Object. Key items is interface information to be used by other disciplines or customers.
-
AKER KVAERNER COMMON PEM USER GUIDE Page 27
PEM Abbreviations To be further developed. CCE Current Cost Estimate COG Centre of Gravity CTR Cost Time Resource DFO Documentation for Operation DM Decision Milestone EIT Electrical, Instrument and Telecommunications FEED Front End Engineering Design GRC Group Risk Committee HVAC Heating, Ventilation and Air Conditioning ITT Invitation to Tender LCI Life Cycle Information MC Mechanical Completion MEL Master Equipment List OEM Operation, Engineering and Maintenance Manual PCS Plant Completion System PVC/PSV Pressure Control Valve/Pressure Safety Valve P & ID Piping and Instrument Diagram PO Purchase Order RDG Risk Decision Gate
-
AKER KVAERNER COMMON PEM USER GUIDE Page 28
APPENDIX A
CONTROL LEVEL MILESTONE REQUIREMENTS
PROJECT TENDERING
-
AKER KVAERNER COMMON PEM USER GUIDE Page 29
PROJECT TENDERING Control Level Milestone Requirements / Quality Levels
-
AKER KVAERNER COMMON PEM USER GUIDE Page 30
PROJECT TENDERING MILESTONE MTA Key Activity: Engineering
Quality Level 1
ITT and Scope of Work reviewed Client requirements for Engineering identified Functional and Technical requirements reviewed/identified Concept/FEED/Design maturity assessed against PEM requirements for all relevant
engineering disciplines First Safety Assessment done Clarifications identified
Key Activity: Procurement
Quality Level 1
ITT and Scope of Work reviewed Client requirements for Procurement identified Supplier Contract conditions and preferred Suppliers reviewed and identified Sourcing level estimated Clarifications identified
Key Activity: Sub-Contracting
Quality Level 1
ITT and Scope of Work reviewed Client requirements for Subcontracting identified Draft Subcontracting Strategy established Clarifications identified
Key Activity: Fabrication/Construction
Quality Level 1
ITT and Scope of Work reviewed Client requirements for Fabrication/Construction identified Draft Fabrication/Construction method established Clarifications identified
Key Activity: Completion
Quality Level 1
ITT and Scope of Work reviewed Client requirements for Completion identified System Design Maturity with respect to completion assessed Clarifications identified
-
AKER KVAERNER COMMON PEM USER GUIDE Page 31
Key Activity: Tender Management and Administration
Quality Level 1
ITT and Scope of Work reviewed Client administrative requirements for this Tender identified Receipt of ITT acknowledged Tender cost and budget established Tender strategy and schedule established Tender Manager & Tender Team nominated Project Risk Profile checked including Core capability & Strategy profile and Business norms Bid evaluation performed Bid/No Bid Decision, DM 2, made (ref. Risk Policy Appendix 4)
Key Activity: Project Execution Strategy
Quality Level 1
ITT and Scope of Work reviewed Client requirements for Project Execution identified Establish Initial Project Execution strategy Update Key Target Analyses (KTA) and assess winning strategy & project attractiveness (Ref.
Core capability & Strategy Profile) Check winning strategy & cost versus clients objectives/budgets Confirm agreements with strategic stakeholders, partners and sub-contractors
Key Activity: Project Team Alignment/HR
Quality Level 1
Key Activity: HSE Management
Quality Level 1
ITT and Scope of Work reviewed Client requirements for HSE (Health, Safety and Environment) identified
Key Activity: Cost Management
Quality Level 1
ITT and Scope of Work reviewed Client requirements for Cost Estimating identified Compensation formats reviewed Tender cost estimate established Compensation strategy and format established
-
AKER KVAERNER COMMON PEM USER GUIDE Page 32
Key Activity: Planning/Scheduling
Quality Level 1
ITT and Scope of Work reviewed Client requirements for Planning/Scheduling identified Initial Project Execution Strategy reviewed Schedule proposal established Long Lead Item impact identified
Key Activity: Risk Management
Quality Level 1
ITT and Scope of Work reviewed Client requirements for Risk Management identified Contract, Milestones and Schedule etc. reviewed Risk Analyses prepared and risks and opportunities identified Risk Register updated for:
o External ( country, political, social) o Novelty ( technology, market, client) o Contractual & hand-over ( terms&conditions, claims, acceptance) o Financial ( cashflow, payment terms) o Contracting parties & terms ( client, consortium, major suppliers, subcontractors) o Health,Safety and Environmental (HSE) o Organisation and Human Resources o Construction/Siteworks o Scope and Project Execution capacity
Key Activity: Contract Management
Quality Level 1
ITT and Scope of Work reviewed Client requirements for Contracts identified;
o Contractual Terms & Conditions (T's & C's) o Price Formats
Contracting strategy and possible partners and JV's (Joint Ventures) identified
Key Activity: Quantity & Weight Management
Quality Level 1
ITT and Scope of Work reviewed Client requirements for Weight & Quantity Management identified Weight Management Strategy established Master Equipment List (MEL) available
Key Activity: Information Management
Quality Level 1
ITT and Scope of Work reviewed Client requirements for Information Handling identified Information Strategy initiated
-
AKER KVAERNER COMMON PEM USER GUIDE Page 33
Key Activity: Quality Management
Quality Level 1
ITT and Scope of Work reviewed Client requirements for Quality Management identified Quality Management Plan & Strategy initiated
Key Activity: Continuous Improvement
Quality Level 1
Need for improvement within project identified Opportunities for improvement within project identified
Key Activity: Change Management
Quality Level 1
ITT and Scope of Work reviewed Client requirements for Change Management identified Change Management Strategy initiated Client change conditions identified
-
AKER KVAERNER COMMON PEM USER GUIDE Page 34
PROJECT TENDERING MILESTONE MTB
Key Activity: Engineering
Quality Level 2
SOW for Project Execution defined and described for all engineering disciplines System and Area Design solutions reviewed Relevant Technical documentation updated
o Functional and Technical requirements o Design and Layout documentation o Analyses and estimates
Material take-off/estimates performed Input to organisation charts and MPP done
Key Activity: Procurement
Quality Level 2
Pricing strategy incorporated Procurement strategy established and competitive actions planned Supplier and Sub-Contractor checks and agreements performed Long Lead delivery times identified Strategic sourcing completed Input to organisation charts and MPP done
Key Activity: Sub-Contracting
Quality Level 2
Sub-Contracting Scope of Work defined Site Facilities cost estimated Rate assumptions established Input to organisation charts and MPP done Facility description established
Key Activity: Fabrication/Construction
Quality Level 2
Fabrication/Construction Scope of Work defined Site Facility cost estimated Rate assumptions established Input to organisation charts and MPP done Facility description established
Key Activity: Completion
Quality Level 2
Project Completion Scope of Work defined Draft completion organisation charts established for all phases Input to project organisation charts and MPP done
-
AKER KVAERNER COMMON PEM USER GUIDE Page 35
Key Activity: Tender Management and Administration
Quality Level 2
Tender execution strategy & schedule established Tender budget and schedule follow up Tender Team mobilised and tender Kick-off held Project key personnel nominated Project organisation charts prepared MPP (Manpower Projection Plan) established Sales strategy and success criteria established (ref. KTA) Project Risk Profile checked including Core capability & Strategy profile and
Business norms Major Milestone review frequency decided Bid evaluation performed Tender clarification and notification administration established Tender compiled for approval
Key Activity: Project Execution Strategy
Quality Level 2
Project execution strategy established including: o Engineering o Procurement o Contract & subcontracting strategies o HSE Programs o Fabrication & Construction o Completion o Schedule & milestones o Pricing/Compensation o Risk & Change Management o Work & Cost breakdown structure
Key Activity: Project Team Alignment/HR
Quality Level 2
Tender team alignment workshop(s) executed Project Management execution resources identified and part of tender & kick off
team
Key Activity: HSE Management
Quality Level 2
HSE Program established
-
AKER KVAERNER COMMON PEM USER GUIDE Page 36
Key Activity: Cost Management
Quality Level 2
Project cost estimate done Project pricing and compensation formats defined Sensitivity analyses performed Pricing assumptions finalised Compensation formats finalised Risk/reward scheme identified Cash flow developed
Key Activity: Planning/Scheduling
Quality Level 2
Project Schedule completed including: o Key Activity Schedule o Procurement Schedule and Long Lead items o Contract Milestone Schedule o Mobilisation Schedule
Key Activity: Risk Management
Quality Level 2
Contractual qualifications identified and determined Risk analyses performed and Project Risk Profile established Risk Register including response planning updated Risk reporting prepared
Key Activity: Contract Management
Quality Level 2
Contract and Sub-Contract Terms and Conditions (T's & C's) reviewed Contracting strategy with partners & JV's chosen Contractual exceptions and clarifications identified Pricing formats complete
Key Activity: Quantity & Weight Management
Quality Level 2
Weight Management Strategy complete; o Weight quantity breakdown defined o Weight and quantity allowances and contingencies identified
Weight Estimates performed Weight Management decided
Key Activity: Information Management
Quality Level 2
Information Management Strategy completed o IT/IS structure and plan defined o LCI (Life Cycle Information) draft defined o DFO (Documentation for Operation) draft defined
-
AKER KVAERNER COMMON PEM USER GUIDE Page 37
Key Activity: Quality Management
Quality Level 2
Quality Management Strategy complete Quality Plan draft established
Key Activity: Continuous Improvement
Quality Level 2
Continuous Improvement theme selected Continuous Improvement targets quantified Strategy for reaching targets identified Strategy for involving client identified Resources required to achieve targets identified
Key Activity: Change Management
Quality Level 2
Change Management Strategy complete o Project change procedure outlined o Basis for Change Control established
-
AKER KVAERNER COMMON PEM USER GUIDE Page 38
PROJECT TENDERING MILESTONE MTC Key Activity: Engineering
Quality Level 3
Scope of Work verified against engineering requirements and Project Execution approved
Key Activity: Procurement
Quality Level 3
Scope of Work verified Project Procurement Strategy approved Project Sourcing Strategy approved
Key Activity: Sub-Contracting
Quality Level 3
Rate assumptions verified Scope of Work verified and Project Sub-Contracting Strategy approved
Key Activity: Fabrication/Construction
Quality Level 3
Site facility cost verified Rate assumptions verified Scope of Work verified and Project Fabrication / Construction Strategy & Cost approved
Key Activity: Completion
Quality Level 3
Scope of Work verified and Project Completion Strategy & Cost approved Draft part system catalogue established
Key Activity: Tender Management and Administration
Quality Level 3
Tender & documentation reviewed, DM 3, by management and approved for submission, DM 4 (ref.Risk Policy Appendices 2, 5, 6, 7 and 8)
Group Risk Committee (GRC) meeting held as required Risk Classification completed (Low, Medium, High or Maximum Risk Project) Success criteria evaluated Negotiation mandate established Project organisation structure, chart, key Personnel and MPP approved Formal approval of tender and tender documentation complete
Key Activity: Project Execution Strategy
Quality Level 3
Project Execution Strategy and Plan approved and ready for implementation
-
AKER KVAERNER COMMON PEM USER GUIDE Page 39
Key Activity: Project Team Alignment/HR
Quality Level 3
Key Activity: HSE Management
Quality Level 3
HSE Program approved
Key Activity: Cost Management
Quality Level 3
Cost estimate approved Cash flow approved Pricing assumptions & Pricing approved Contingency and Profit level determined Risk/reward scheme approved Compensation format completed
Key Activity: Planning & Scheduling
Quality Level 3
All relevant Project Schedules approved
Key Activity: Risk Management
Quality Level 3
Contingency determined based on identified exposure Risk Register including response planning approved Risk reporting approved
Key Activity: Contract Management
Quality Level 3
Contract: o Contracting strategy approved o Terms and Conditions (T's & C's) approved o Qualifications approved
Subcontracts: o Terms and Conditions (T's & C's) approved o Critical subcontractor commitments made
Key Activity: Quantity & Weight Management
Quality Level 3
Weight and weight breakdown approved, including weight allowances and contingencies
-
AKER KVAERNER COMMON PEM USER GUIDE Page 40
Key Activity: Information Management
Quality Level 3
Information Management Strategy approved o IT/IS structure and plan o LCI (Life Cycle Information) draft o DFO (Documentation for Operation) draft
Key Activity: Quality Management
Quality Level 3
Quality Plan approved
Key Activity: Continuous Improvement
Quality Level 3
Revised CI strategy, resources and targets
Key Activity: Change Management
Quality Level 3
Project Change Management approved Basis for Change Control approved
-
AKER KVAERNER COMMON PEM USER GUIDE Page 41
PROJECT TENDERING MILESTONE MTD Key Activity: Engineering
Quality Level 4
Bid clarifications concluded and all relevant documentation updated and approved
Key Activity: Procurement
Quality Level 4
Bid Clarification concluded and all relevant documentation updated and approved
Key Activity: Sub-Contracting
Quality Level 4
Bid Clarifications concluded and all relevant documentation updated and approved
Key Activity: Fabrication/Construction
Quality Level 4
Bid Clarification concluded and all relevant documentation updated and approved
Key Activity: Completion
Quality Level 4
Bid Clarifications concluded and all relevant documentation updated and approved
Key Activity: Tender Management and Administration
Quality Level 4
Negotiation Team selected Bid clarifications concluded/settled Negotiations concluded Risk Classification verified Contract document complete and ready for approval, DM 5. (ref. Risk Policy Appendices 7, 9
and 10 ) Contract ready for handover to project team
Key Activity: Project Execution Strategy
Quality Level 4
Project Execution Strategy and Execution Plans adjusted for clarifications and negotiations Updated Project Execution Strategy approved
Key Activity: Project Team Alignment/HR
Quality Level 4
-
AKER KVAERNER COMMON PEM USER GUIDE Page 42
Key Activity: HSE Management
Quality Level 4
HSE program updated as required based on bid clarifications and contract negotiations
Key Activity: Cost Management
Quality Level 4
Price and contingency updated based on clarifications and negotiations Price and contingency approved by management
Key Activity: Planning & Scheduling
Quality Level 4
All Project Schedules affected by clarifications and negotiations updated and approved
Key Activity: Risk Management
Quality Level 4
Risk documentation updated and reassessed based on deviations from submitted tender in bid clarifications and negotiations;
o Risk analyses and Project Risk Profile o Risk Register o Risk Report
Updates approved by management
Key Activity: Contract Management
Quality Level 4
Contract and Subcontract documentation updated with exceptions and clarifications Contract and Subcontract documentation approved by management
Key Activity: Quantity & Weight Management
Quality Level 4
Weight and weight breakdown updated as per Scope of Work update Weight and weight breakdown update approved by management
Key Activity: Information Management
Quality Level 4
Information Management documentation updated as required and management approval obtained
Key Activity: Quality Management
Quality Level 4
Quality Plan updated as relevant
-
AKER KVAERNER COMMON PEM USER GUIDE Page 43
Key Activity: Continuous Improvement
Quality Level 4
Revised CI strategy, resources and targets Presentations made to client (as required)
Key Activity: Change Management
Quality Level 4
Basis for Change Control updated as relevant
-
AKER KVAERNER COMMON PEM USER GUIDE Page 44
PROJECT TENDERING MILESTONE MTE
Key Activity: Engineering
Quality Level 5
Technical and administrative handover completed Scope of Work start-up plan initiated Initiate design basis review Enable design basis alignment
Key Activity: Procurement
Quality Level 5
Commercial and administrative handover completed
Key Activity: Sub-Contracting
Quality Level 5
Technical, commercial and administrative handover completed
Key Activity: Fabrication/Construction
Quality Level 5
Technical and administrative handover completed
Key Activity: Completion
Quality Level 5
Technical and administrative handover completed
Key Activity: Tender Management and Administration
Quality Level 5
Technical, commercial and administrative handover completed Project team mobilisation as scheduled Tender team demobilised Client kick-off meeting performed Start-up plans implemented for
o Scope of Work o Administration & Management
Project kick-off meetings as scheduled
Key Activity: Project Execution Strategy
Quality Level 5
Project Execution Strategy and Execution Plans handover completed Draft milestone Status Checklist established Project Milestone Plan implemented in draft Project audit and verification activities
-
AKER KVAERNER COMMON PEM USER GUIDE Page 45
Key Activity: Project Team Alignment/HR
Quality Level 5
Project Management team and Project Board aligned Key consortium issues clarified Kick off meeting with customer executed Kick off meetings in project with mobilised personnel executed
Key Activity: HSE Management
Quality Level 5
HSE Management handover completed Project HSE Program established
Key Activity: Cost Management
Quality Level 5
Draft Control Budget established and cost breakdown structure implemented Commercial handover completed Commercial awareness program initiated
Key Activity: Planning & Scheduling
Quality Level 5
Completed handover of; o Key Activity Schedule o Procurement Schedule and Long Lead Items o Contract Milestone Schedule o Mobilisation Schedule o Deliverables o Manhour loading
Key Activity: Risk Management
Quality Level 5
Project Risk Model, Risk Register and Risk Report handover completed
Key Activity: Contract Management
Quality Level 5
Contract and Subcontract handover completed
Key Activity: Quantity & Weight Management
Quality Level 5
Weight and Quantity Management and Weight Report handover completed
-
AKER KVAERNER COMMON PEM USER GUIDE Page 46
Key Activity: Information Management
Quality Level 5
Information management handover completed IT/IS available in project
Key Activity: Quality Management
Quality Level 5
Quality Management handover completed Project Quality Plan established
Key Activity: Continuous Improvement
Quality Level 5
CI strategy, resources and targets communicated to client, project, Business Unit and Business Area
Key Activity: Change Management
Quality Level 5
Change Management handover completed Project Change Control Procedure established
-
AKER KVAERNER COMMON PEM USER GUIDE Page 47
APPENDIX B
CONTROL LEVEL MILESTONE REQUIREMENTS
PROJECT EXECUTION
-
AKER KVAERNER COMMON PEM USER GUIDE Page 48
PROJECT EXECUTION Control Level Milestone Requirements / Quality Levels
-
AKER KVAERNER COMMON PEM USER GUIDE Page 49
PROJECT EXECUTION MILESTONE 1A Key Activity : Concept Execution Activity : Concept Execution Quality Level 1 HSE Requirements established. Identify product and market. Establish possible process solutions infrastructure identified. Establish environmental requirements. Key process and product interfaces defined.
-
AKER KVAERNER COMMON PEM USE