prevention and management of blast … · management plan prevention and management of blast...

Post on 08-Jun-2018

216 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

MANAGEMENT PLAN

PREVENTION AND MANAGEMENT OF BLAST GENERATED NOx

Tata Steel Minerals Canada Ltd.

Direct Shipping Ore Project

November 2015

2015_11_04 Blasts NOx Management Plan.docx ii

Table of Contents page

1. Purpose ........................................................................................................................................ 1

2. Scope ............................................................................................................................................ 1

3. Background .................................................................................................................................. 1

3.1 Requirement for a Blast Generated NOx Management Strategy ........................................................ 1 3.2 Theory – NOx in Blast Fumes ............................................................................................................. 1 3.3 Causes of NOx Gases in Blasting ....................................................................................................... 2

4. Management Procedures............................................................................................................. 3

4.1 Blast Design by Explosives/Precursor Manufacturer/Supplier ............................................................ 3 4.2 Pre-Blast Environmental Assessment ................................................................................................. 3 4.3 Pre-Blast and Post-Blast Checklist ...................................................................................................... 3 4.4 Blast Log .............................................................................................................................................. 4

5. Documentation and Retroaction ................................................................................................. 6

5.1 Documentation ..................................................................................................................................... 6 5.2 Retroaction .......................................................................................................................................... 6

Appendices

Appendix A Blast Design Datasheet

Appendix B Pre-Blast Environmental Assessment List Appendix C Pre-Blast / Post-Blast Checklist Appendix D Blast Log

2015_11_04 Blasts NOx Management Plan.docx 1

1. Purpose

This procedure outlines responsibilities and guidelines for manage and assist in the minimisation and management

of blast fumes, in particular oxides of nitrogen (NOx) at the Direct Shipping Ore (DSO) Project operated by Tata

Steel Minerals Canada Ltd., near Schefferville, QC.

2. Scope

Those involved in blasting operations need to be aware of the causes, risks and consequences of the oxide of

nitrogen (NOx) gases that may emanate from their blasting activities. The aim of this Plan is to provide information

and recommended guidelines to assist in the prevention and management of blast generated NOx gases from

surface blasting operations. The Plan is specific to NOx gases and covers the following areas:

the likely causes of NOx gases from blasting

possible control measures to prevent or minimise blast generated NOx gases

management of NOx gases from blasting should they occur

This document provides a mitigation strategy based on the Code of Practice for Prevention and Management of

Blast Generated NOx Gases in Surface Blasting established by the Australian Explosives Industry and Safety Group

(AEISG) (Edition 2, August 2011)1.

3. Background

3.1 Requirement for a Blast Generated NOx Management Strategy

Air quality studies conducted by TSMC in the context Environmental Impact Assessments for Provincial and Federal

authorities show that air emissions (such as dust, NOx, CO and SO2) generated during blasting events can negatively

affect the air quality in the vicinity of the pits where blasting is conducted.

As part of an EIA submitted to the Canadian Environmental Assessment Agency (CEAA) in the fall of 2015 for the

Howse Property Project (HPP), TSMC has committed to the development and implementation of a Plan for the

prevention and management of blast generated NOx. This Plan will be put into effect when blasting at the HPP

starts. This plan is applicable to blasting at the following pits: Howse, Fleming 7N and Timmins 3N. However, its

application will be extended to other active pits as deemed necessary.

3.2 Theory – NOx in Blast Fumes

The group of gases known as Oxides of Nitrogen or NOx, of which the most common are nitric oxide (NO) and

nitrogen dioxide (NO2), are often found as by-products in the post-blast gases of ammonium nitrate-based

explosives. Together, these gases are loosely referred to as “NOx”. Nitric oxide is invisible, but nitrogen dioxide

ranges from yellow to dark red depending on the concentration and size of the gas cloud. These gases are

pollutants. NOx from blasting constitutes only a small proportion of the total NOx emissions from human activities

1 http://www.aeisg.org.au/images/stories/aeisg_cop_nox_edition_02aug2011.pdf

2015_11_04 Blasts NOx Management Plan.docx 2

(primarily power generation and motor vehicles) and natural sources. However blasting produces a sudden

localised release of gases with potentially high concentrations of NOx. Such gas emissions pose a health risk if

people are exposed to them before the plumes can dissipate.

Despite a long history of blast-related NOx emissions, very few quantitative studies have been done under realistic

field conditions. The underlying causes of high NOx are fuel-deficiency in the explosive or detonation reactions that

do not continue to completion. There are many ways in which these conditions may arise.

In the absence of a single general cause or general solution, this Plan was developed by TSMC as an aid to

identifying the local cause of NOx and as a prompt for possible ways to address those causes. It should be

understood that, given the complexity of the problem and the inherent variability in the blasting environment, NOx

events may still occur even after prevention and mitigating actions have been put in place. The Plan therefore

include advice on managing blasts that could produce NOx gases.

3.3 Causes of NOx Gases in Blasting

The post-blast gases and fumes are generated as a result of the ammonium nitrate-based explosive detonation at

the blast site. The factors that trigger the formation of the NOx are various but the following factors are among the

main contributors in the generation of post-blast fumes during the mining process:

Explosive formulation and quality assurance; Geological Conditions; Climate/seasonality; Blast design; Explosive product selection; Contamination of explosive in the blast-hole; On-bench practices.

Section 5 of the Code of Practice for Prevention and Management of Blast Generated NOx Gases in Surface

Blasting should be consulted as an aid to identifying causes and mitigation measures.

As a result, the formation of the toxic fumes can be managed through some preventive controls considering the

geological conditions during the design phase, designing an appropriate design for the blast, selecting an

appropriate product formulation for the detonation, considering the weather condition during the time of loading;

implementing on-bench practiced to minimise the potentials for water ingress into blasting area; minimising the

contamination of explosives in blast holes.

2015_11_04 Blasts NOx Management Plan.docx 3

4. Management Procedures

4.1 Blast Design by Explosives/Precursor Manufacturer/Supplier

The manufacturer and/or supplier of the precursors or bulk explosives must ensure products are formulated appropriately to prevent/minimise the generation of NOx gases during blasting. The products should be authorised, with quality control systems in place to ensure that the manufactured/supplied products meet specifications. For each blast, a copy of the Blast Design datasheet must be forwarded to TSMC on-site Environmental team. An example “Blast Design” datasheet is provided in Appendix A of this Plan. The explosives manufacturer/supplier must provide documentation for modification and alterations to explosive and/or precursor formulations. Documentation must be provided to TSMC on-site Environmental team and must cover the following aspects:

1. recording any modification/alteration and updating relevant authorisations, Technical Data Sheets, Material Safety Data Sheets, work procedures, and training programs as and where relevant;

2. ensuring changes continue to meet the requirements of this Code;

4.2 Pre-Blast Environmental Assessment

In collaboration with the blasting manager, TSMC on-site Environmental team will complete a Pre-Blast Environmental Assessment. A copy of the Pre-Blast Environmental Assessment list is provided in Appendix B. The assessment covers 6 criteria:

Explosive Formulation and Quality Assurance Geological conditions Blast Design Explosive product selection On bench practices Contamination of explosives in the blast hole

The assessment may be conducted days before a blasting event is scheduled.

4.3 Pre-Blast and Post-Blast Checklist

Appendix C contains an example of the Pre-Blast / Post-Blast checklist, currently in use at the site. The Pre-Blast / Post-Blast checklist The following parameters will be added to the Pre-Blast section of the checklist:

a) Acknowledgement of the Environmental Assessment by the responsible for drilling and blasting b) Meteorological conditions: wind speed, wind direction, temperature, precipitation c) For pits located in the vicinity of the Workers’ camp (ex.: Howse, Fleming 7N, Timmins 3N) , blasting must

be conducted while the wind is NOT blowing in direction of the Workers’ camp The following parameters will be added to the Post-Blast section of the checklist:

2015_11_04 Blasts NOx Management Plan.docx 4

a) Visual Rating Scale: Assessment of the Post-Blast fume should using the AEISG visual NOx fume rating

scale. b) duration of any post-blast NOx gas event;

c) direction of movement of any post-blast NOx plume;

d) movement of any post-blast NOx gas plume relative to the established exclusion zone and any established

management zone;

e) results/readings of any NOx monitoring equipment employed for the blast;

f) video results of blasts where relevant

4.4 Blast Log

Appendix D contains an example of the Blast Log used for recording blasting events. This information log will continue to be used at the site for all blasts.

2015_11_04 Blasts NOx Management Plan.docx 5

VISUAL NOX FUME RATING SCALE

2015_11_04 Blasts NOx Management Plan.docx 6

5. Documentation and Retroaction

5.1 Documentation

For each blast, the following documents will be reviewed and filed by TSMC on-site environmental team:

a) Blast Design by blasting company or responsible b) Pre-Blast Environmental Assessment c) Pre-Blast and Post-Blast Checklist d) Blast Log

5.2 Retroaction

Any reported significant NOx event or trends should be investigated to minimize the potential for ongoing generation of NOx gases and to mitigate the potential impacts of any such event. Such investigation should involve the explosives manufacturer and/or supplier. The fault tree (see Section 6 Code of Practice for Prevention and Management of Blast Generated NOx Gases in Surface Blasting) should assist any investigation and ensure all relevant factors are considered and adequately addressed. The results of any investigation of post-blast NOx gases should then be factored into the site specific procedures to minimize their production and to mitigate impacts.

Appendix A

Blast Design Datasheet Example Datasheet Currently in Use. To Be Amended As Per This Plan.

Appendix B

Pre-Blast Environmental Assessment List

Pre-Blast Environmental Assessment TSMC DSO - SCHEFFERVILLE

Blast #: Pit ID:

Scheduled Blast Date:

Assessed by: Assessement Date:

Assessment Criteria Likelihood Notes

PB 1: Explosive Formulation and Quality Assurance

Explosive product incorrectly formulated

Explosives product change

Inadequate mixing of raw materials

Delivery system metering incorrectly

Delivery system settings for explosive product delivery overridden

Explosive precursors not manufactured to specification

Precursor degradation during transport and storage

Raw material changes

Other:

PB 2: Geological conditions

Lack of relief in weak/soft strata

Inadequate confinement in soft ground

Explosive product seeping into cracks

Dynamic water in holes

Moisture in clay

Blast hole wall deterioration between drilling and loading eg cracks, voids, hole contraction

Chemistry of rock type e.g. limestone

Other:

PB 3: Blast Design

Explosive desensitisation due to the blast hole depth

Inappropriate priming and/or placement

Mismatch of explosives and rock type

Inter-hole explosive desensitisation

Intra-hole explosive desensitisation in decked blast holes

Initiation of significant explosive quantities in a single blast event

Other:

PB 4: Explosive product selection

Non water-resistant explosive products loaded into wet or dewatered holes

Excessive energy in weak/soft strata desensitising adjacent explosive product columns

Primer of insufficient strength to initiate explosive column

Desensitisation of explosive column from in-hole cord initiation

Inappropriate explosive product for application

Other:

PB 5: On bench practices

Hole condition incorrectly identified

Blast not drilled as per plan

Dewatering of holes diverts water into holes previously loaded with dry hole explosive products

Blast not loaded as per blast plan

Other:

PB 6: Contamination of explosives in the blast hole

Explosive product mixes with mud/sediment at bottom of hole.

Interaction of explosive product with drilling muds.

Penetration of stemming material into top of explosive column (fluid/pumpable explosive products only)

Water entrainment in explosive product

Moisture in ground attacking explosive product

Contamination of explosives column by drill cuttings during loading

Rainfall on a sleeping shot.

Other:

Appendix C

Pre-Blast / Post-Blast Checklist Example checklist Currently in Use. To Be Amended As Per This Plan.

<Original signed by>

Appendix D

Blast Log Example Datasheet Currently in Use.

<Original signed by>

top related