Sheet1PRELIMINARIESUpdated:2015

Item No.DescriptionsBreakdownAmount

PERFORMANCE BONDcontract amountx5%x0.6%xConstruction period + CMGD1BANK CHARGE

x5%x0.6%x2years0.0

subtotal0.0Profit & attendance : 10%0.0Total0.0

INSURANCES

1Insurance of WorksContract amounti)Contractor's all risk2,700,000.00x0.15%x6.00%(tax)243.00

ii)Workmen Compensation2,700,000.00x10.00%x22.00%x6.00%(tax)3,564.00

subtotal3,807.00Profit & attendance : 10%380.70Total4,187.70

SOCSO

Contract amounti)x10.00%x0.25%0.0

subtotal0.0Profit & attendance : 10%0.0Total0.0