PRELIMINARIES Updated:2015 Descriptions Breakdown Amount PERFORMANCE BOND x 5% x 0.6% x Construction period + CMGD 1 BANK CHARGE x 5% x 0.6% x 2 years - subtotal - Profit & attendance : 10% - Total - INSURANCES 1 Insurance of Works i) Contractor's all risk ### x 0.15% x 6.00% (tax) 243.00 ii) Workmen Compensation ### x 10.00% x 22.00% x 6.00% (tax) 3,564.00 subtotal 3,807.00 Profit & attendance : 10% 380.70 Total 4,187.70 SOCSO i) x 10.00% x 0.25% - subtotal - Profit & attendance : 10% - Total - Item No. contract amount Contract amount Contract amount

Upload: look

Post on 30-Sep-2015

14 views

Category:

Documents


1 download

DESCRIPTION

Preliminaries item

TRANSCRIPT

Sheet1PRELIMINARIESUpdated:2015

Item No.DescriptionsBreakdownAmount

PERFORMANCE BONDcontract amountx5%x0.6%xConstruction period + CMGD1BANK CHARGE

x5%x0.6%x2years0.0

subtotal0.0Profit & attendance : 10%0.0Total0.0

INSURANCES

1Insurance of WorksContract amounti)Contractor's all risk2,700,000.00x0.15%x6.00%(tax)243.00

ii)Workmen Compensation2,700,000.00x10.00%x22.00%x6.00%(tax)3,564.00

subtotal3,807.00Profit & attendance : 10%380.70Total4,187.70

SOCSO

Contract amounti)x10.00%x0.25%0.0

subtotal0.0Profit & attendance : 10%0.0Total0.0