Hung Huynh, Engineering Manager

January 9, 2019

SR 522

Paradise Lake Rd to Snohomish River

Roger Millar, Secretary of Transportation

Keith Metcalf, Deputy Secretary of Transportation

2

Agenda

• Current State

• SR 522/Paradise Lake Road to Snohomish River Widening

• SR 522/Paradise Lake Road Interchange Improvements

• Q & A

3

Current state

Existing Funding

2017 - 19: $750K

2025 - 27: $5M

2027 - 29: $5M

Funding need amount assumes project is fully funded in 2019

4

SR 522/Paradise Lake Rd to Snohomish River

Widening

• Estimate is $90 million (assumes project is fully funded in 2019)

• Eight known fish barriers

• If full funding is available:

o Preconstruction duration is estimated to be 2 years

o Construction duration is estimated to be 3 years

• Once funding is available:

o Design fish passages

o Update environmental documentation

o Update and acquire right of way

o Procure design-build contract

5

4 known fish barriers

at the Paradise Lake

Road Interchange

8 known fish barriers

between Paradise

Lake Road and the

Snohomish River

6

Fish barrier is

under tall walls

7

Fish barrier extends

under railroad track

8

SR 522/Paradise Lake Road Interchange

Improvements

9

Recommended Alternative

10

SR 522/Paradise Lake Road Interchange

Improvements

• Estimate is $90 million (assumes project is fully funded in 2019)

• Four known fish barriers

• If full funding is available:

o Preconstruction duration is estimated to be 3 years

o Construction duration is estimated to be 3 years

• Once full funding is available:

o Design fish passages

o Update environmental documentation

o Determine and acquire right of way

o Procure design-build contract

11

Questions?