Our Ghanewadi
ByGhanewadi Jal-Sanrakshan Munch
Jalna’s Goddess Ganga
Location.
Located in North of Jalna City about 8 Km on Kundlika River. Water flows from Ghanewadi to Jalna by Gravity.
GhanewadiAltitude 502 mt above Mean Sea Level
History of Ghanewadi• Constructed in early 1930 , completed in
1935.
• Construction was initiated by then Nizam of Hyderabad State
• Mr. Bezonji Faridoonji Jalnawalla took the contract of building the Ghanewadi lake and spent rupees two lakhs from his own pockets so that people of Jalna could have enough water for the city.
Specifications Of Dam• Build on Kundlika River.• Dam Height 15 Mt. ( 49 ft ).• Dam Length 836 Mt ( 2743 ft ).• Gross Capacity when built 14440000 Mt3
( 0.51 TMC ft ) • Purpose Drinking Water Supply.
Municipal Corporation Use to draw
4 mld of water from
Ghanewadi
Water Supply to Jalna.• 4 mld of water comes to filter bed by Gravity.
• 1960s there use to be water supply twice a day.
• 1970s Water Supply once a day.
1980s Water Supply Once a day.
1990s Water Supply Alternate Day.
2000s Water Supply Once a Week.
• Now Water Supply Once a Month.
Neglected & Forgotten.• Every one took water flowing from Ghanewadi
Granted.
• No up keeping of Dam Done by JMC
• No De-silting from 1935 to 2010 ……… 75 Years.
Water supply once in a week or twois matter of routine
Ghanewadi Jal-Sanrakshan Munch
2010 Summer
Initative by Shri. Rameshbhai Patel.
Ghanewadi Jal-Sanrakshan Munch
2010 Summer
First Year 2010• 4 JCB , 2 Pocklain , 25 Tippers & 16 Tractor Put to service.
• 45,000 Tractor of Silt Removed.
• 135,000 M3 storage capacity reclaimed.
Rs. 25 Lac Deployed by Munch&
Rs. 25.0 Lac spent by Farmers
First Year 2010
Farmers Supported very well and lifted all the silt by Spending Rs. 25 Lac.
First Year 2010• Participation from Society
First Year 2010• Participation from Society
Second Year 2011• 40,000 Tractors Removed.• 22.0 Lac Spent by Munch @ same spent by
Farmers.• 120,000 M3 Capacity reclaimed.
No Assistance Received fromGovernment
Third Year 2012• 36,000 Tractors Removed.• 20.0 Lac Spent by Munch @ same spent by
Farmers.• 108,000 M3 Capacity reclaimed.
No Assistance Received fromGovernment
Forth Year 2013
Work Started on 8 th March “ International Women’s day
40000 Tractors Removed
Fifth Year 2015
Work Started on 8 th March “ International Women’s day
40000 Tractors Removed
Work Till Date
Total Silt Removed: 2,19,000 Tractors
Water Capacity of Dam Increased by : 657 , 000, 000 Liter.65 Cr. 70 Lac Liter.
This alone can give 100 Lit per day to 2 Lac Population for 32 days if given daily. .
Ghanewadi Jal-Sanrakshan Munch
Why Remove Silt ?
Total Water Storage Capacity of Ghanewadi ( As Constructed )14,440,000,000 Liters.( 0.51 TMC )
Jalna Municipal Corporation gets 4.0 mld water per day ( 4,000,000 Liters Per Day ).
In a Year JMC gets 365 x 4,000,000 = 1,460,000,000 Liter Water from Ghanewadi.
Evaporation Losses + Seepage in Soil + Loss Due to Gal formation + use by farmers = 14,440,000,000 - 1,460,000,000 = 12,980,000,000 liter. ( 89% )
Only 11 % of Capacity is
Used
Ghanewadi Jal-Sanrakshan MunchWhy Remove Silt ?
11%
40%
10%
30%
9%
Water Utilization
Evaporation Loss
Utilized ByJalna
Seepage
Loss of Capacity by Siltation
Flow by Gravity 24x7 , No Electricity
Save Electric
Bill
Challenge This Year.• Lifting by Farmers Poor.• Reasons 1) Draught Situation. 2) Work started early……… Still there is time.
• Best Opportunity this year to do Big Work. We have three months in hand.
• Small Farmers needs to be given support.
Your Support Needed One Poclain, Five Tipper, Three Tractor.
Daily Gal Removal is 300 Tractor.
Daily Expense is Rs. 30000.
You can donate
• 50 Tractor Removal Rs. 5000• 100 Tractory Removal Rs. 10,000• 250 Tractor Removal Rs. 25,000• 500 Tractory Removal Rs. 50,000• 1000 Tractor Removal Rs. 1,00,000
Future Of Project We plan to continue the work till we recover lost capacity totally.
Chak De Ghanewadi