environment work method statement (ewms)
Post on 29-Dec-2021
20 Views
Preview:
TRANSCRIPT
Title: Environmental Work Method Statement Template
ID: MSID-4-228 Version: 23.0 Date Published: 03/07/2018
Management System - Uncontrolled Document when Printed
ENVIRONMENT WORK METHOD STATEMENT (EWMS)
SWMS Title: EWMS No: Revision No:
Work must be performed in accordance with this SWMS. The SWMS must be available for inspection where the task is being performed, at all times during the task. If the SWMS is revised, all versions should be kept.
Organisation Details:
CPB Downer Joint Venture Supervisor on Project:
(Name and Mobile Phone Number)
Stuart Sweeney/Pat Carroll
Project Manager:
(Name and Mobile Phone Number)
David Saggerson Date: 08/09/2021 Work Pack Ref No:
Work Activity: (Description of the Job)
Bridge St Underbridge Construction including Temporary Jetty across Parramatta River
Work Location:
Bridge Rd, Cumberland Hospital, Westmead
Business Defined High Risk Construction Work Tasks
Note: Those activities marked with an asterisk (*) are Safety Essential related.
☐ * Work at Height where a worker or an object could fall more than 2 metres
☐ Work in areas that may be contaminated or flammable atmosphere
☐ Work on a telecommunication tower
☐ * Working in and around Mobile Plant ☐ Work in/near trench deeper than1.5 m ☐ Work in a tunnel
✓ * Work with Temporary Works ☐ Work in or near a confined space ☐ Work likely to involve disturbing asbestos
☐ * Working with Live Services ☐ Demolition of load-bearing structure ☐ Use of explosives
☐ * Working near Live Traffic (road or railway including light rail)
☐ Tilt-up or precast concrete elements ☐ Diving Work
☐ * Electrical Work ☐ Work in artificial extremes of temperature ☐ Work on/ near chemical/fuel/refrigerant lines
☐ * Work involving Mobile Cranes and Lifting Operations
✓ Work in or near water or other liquid that involves a risk of drowning ✓ A task that is not a Business defined High
Risk Construction Work task.
Working on, in or adjacent to a waterway
Who will ensure compliance Name: David Barkho, Yogesh Pindoliya How compliance be measured
In accordance with ECM, CEMP and subplans; Weekly Inspections; ER Inspections; Monthly Reviews
How will the control measures be reviewed?
3 monthly reviews Who will review control measures
Name: Yogesh Pindoliya
2 PLR-EWMS-0001 Bridge RD Underbridge Construction including Temporary Jetty across Parramatta River
Title: Environmental Work Method Statement Template
ID: MSID-4-228 Version: 23.0 Date Published: 03/07/2018
Management System - Uncontrolled Document when Printed
Page 3 of 6
Activity/Task What are the tasks involved?
List the work tasks in a logical order.
What are the hazards/risks?
Identify the hazards/risks that may cause harm to workers or the public.
What are the control measures?
Describe what will be done to control the risk. What will you
do to make the activity as safe as possible?
Enabling works • Excavate ramp at eastern
Abutment for piling rig and jetty access
HRCW – Working on, in or adjacent to a waterway
• Sediment and site run-off into Parramatta River
• All personnel to attend, listen, understand and sign onto Environmental Control Map which details mitigation measures implementation
• Ensure Erosion and Sediment Controls are installed in accordance with approved Erosion and Sediment Control Plan – ESCP01
• Ensure work crew is kept up to date on current weather forecast and correct control measures are put in place for any inclement weather as per Table 1 outlined in ESCP01
• Access road to be capped with Select material
• Install earth bunds at abutment and wrap with geotextile
• Install rock checks to slow water flow down access ramp
• Grade the piling platform and access road as well as installed catch drain as required to direct water to sump to treat and discharge
Access for substructure
• Install temporary jetty from eastern to western Abutment including Pier segment
1. Vibrate and drive in temp hollow steel columns
2. Install supporting beams
3. Install deck including handrails
4. Repeat for 1-3 for next segment
HRCW – Working on, in or adjacent to a waterway
• Sediment from river bed
• Ensure Erosion and Sediment Controls are installed in accordance with approved Erosion and Sediment Control Plan
• Schedule works for a period of no rainfall and low flows as much as possible
• Installation of floating silt curtain during piling works
• Monitor sediment during and after installation - expectation is minimal
• Install coir logs at each embankment as per ESCP01
Title: Environmental Work Method Statement Template
ID: MSID-4-228 Version: 23.0 Date Published: 03/07/2018
Management System - Uncontrolled Document when Printed
Page 4 of 6
Activity/Task What are the tasks involved?
List the work tasks in a logical order.
What are the hazards/risks?
Identify the hazards/risks that may cause harm to workers or the public.
What are the control measures?
Describe what will be done to control the risk. What will you
do to make the activity as safe as possible?
• Grey-headed flying fox (GHFF) colony impacts
• (HOLD POINT) Refer to GHFF Mitigation
Application Procedure (Item 3, 4 and 5).
• (HOLD POINT) Consult with flying-fox expert to
determine appropriate control and implement any
additional control measures. Update
Environmental Control Map if any additional
measures are required to be implemented.
• notify Department of Planning, Industry and
Environment prior to commencement of new high-
risk activity
• notify WIRES vaccinated and trained rescuer in
flying-foxes to be on stand-by at commencement
of new high-risk activity and be informed of
duration of activity.
• work-specific monitoring at camp required
– daily from commencement of new high-risk
activity
– by two vaccinated and trained personnel for
rescue if required (N.B. A reduction of two
personnel daily to one personnel daily, then one
personnel weekly will be determined by flying-fox
expert based on flying-fox behaviour after 5 days
of evaluation from commencement of high-risk
activity)
• work-specific camp monitors to have direct radio
or phone communications with piling machine
operators to allow prompt ‘stop works’ if required
• plant operators to notify camp monitors before
commencing high risk activity and check-in with
camp monitors for any flying-fox welfare issues
Title: Environmental Work Method Statement Template
ID: MSID-4-228 Version: 23.0 Date Published: 03/07/2018
Management System - Uncontrolled Document when Printed
Page 5 of 6
Activity/Task What are the tasks involved?
List the work tasks in a logical order.
What are the hazards/risks?
Identify the hazards/risks that may cause harm to workers or the public.
What are the control measures?
Describe what will be done to control the risk. What will you
do to make the activity as safe as possible?
• daily construction activities to begin with lower
level noise disruption (i.e. do not begin with piling)
• avoid obstructing waterway flying-fox transit path
at night with plant or machinery
• camp monitor to assess camp after sunset and
determine if and when young flying-foxes begin
creching in case of scheduled night works
• camp monitor to provide daily evaluation of works
to flying-fox expert
• Section 7.5.1 from the Parramatta Light Rail
GHFF Construction Monitoring Program applies:
– a Responsible Person (i.e. flying-fox expert,
vaccinated camp monitor) would need to have
authority to temporarily stop construction work in
the stop work zone if the GHFF are highly
stressed, as evidenced by:
• diurnal fly-outs leading to splintered camps in
sensitive locations
• welfare impacts
• multiple negative interactions with public (e.g.
flying-fox on ground, flying-fox scratch or contact
with humans)
– works would be allowed to resume when the
flying-fox expert determines that the GHFF are no
longer stressed and at risk to themselves or
people
– construction activities may need to temporarily
stop between the camp and splinter group. A
contingency response team consisting of two
(preferably ABLV vaccinated) people, contactable
Title: Environmental Work Method Statement Template
ID: MSID-4-228 Version: 23.0 Date Published: 03/07/2018
Management System - Uncontrolled Document when Printed
Page 6 of 6
Activity/Task What are the tasks involved?
List the work tasks in a logical order.
What are the hazards/risks?
Identify the hazards/risks that may cause harm to workers or the public.
What are the control measures?
Describe what will be done to control the risk. What will you
do to make the activity as safe as possible?
by radio or mobile, will be required to flush the
bats back to the camp by safe and agreed
methods.
o PCPLR Supervisor – Pat Carroll - 0428 922
740
o PCPLR Project Engineer – Yogesh Pindoliya –
0448 339 576
• Keep record details of the weekly visual checks.
Piling • Install bored cast insitu reinforced concrete piles at Abutment and pier
HRCW – Working on, in or adjacent to a waterway
• Sediment from piling at pier
• Water ponding in abutment piling pad
• Concrete slurry run-off into river
• Ensure Erosion and Sediment Controls are
installed in accordance with approved Erosion
and Sediment Control Plan
• Install silt fencing and coir logs downslope of
temporary jetty and piling platform but above
water line as per ESCP01
• Install fabric wrapped rock / earth bunds around
piling platform as outlined in ESCP01
• Divert run-off and install sump away from work
area but within project boundary as per ESCP01
• Installation of floating silt curtain during piling
works
• Pile rig to have enclosed spoil bucket and dispose
into spoil bin
• Spoil bin and truck for removal to be lined with
plastic
• Concrete poured with tremie placed inside
permanent steel casing
• Designated concrete washout bins to be set up
within the project boundaries but away from the
river.
Title: Environmental Work Method Statement Template
ID: MSID-4-228 Version: 23.0 Date Published: 03/07/2018
Management System - Uncontrolled Document when Printed
Page 7 of 6
Activity/Task What are the tasks involved?
List the work tasks in a logical order.
What are the hazards/risks?
Identify the hazards/risks that may cause harm to workers or the public.
What are the control measures?
Describe what will be done to control the risk. What will you
do to make the activity as safe as possible?
Grey-headed flying fox disruption • (HOLD POINT) Refer to GHFF Mitigation
Application Procedure (Item 3, 4 and 5).
• (HOLD POINT) Consult with flying-fox expert to
determine appropriate control and implement any
additional control measures. Update
Environmental Control Map if any additional
measures are required to be implemented.
• notify Department of Planning, Industry and
Environment prior to commencement of new high-
risk activity
• notify WIRES vaccinated and trained rescuer in
flying-foxes to be on stand-by at commencement
of new high-risk activity and be informed of
duration of activity.
• work-specific monitoring at camp required
– daily from commencement of new high-risk
activity
– by two vaccinated and trained personnel for
rescue if required (N.B. A reduction of two
personnel daily to one personnel daily, then one
personnel weekly will be determined by flying-fox
expert based on flying-fox behaviour after 5 days
of evaluation from commencement of high-risk
activity)
• work-specific camp monitors to have direct radio
or phone communications with piling machine
operators to allow prompt ‘stop works’ if required
• plant operators to notify camp monitors before
commencing high risk activity and check-in with
camp monitors for any flying-fox welfare issues
Title: Environmental Work Method Statement Template
ID: MSID-4-228 Version: 23.0 Date Published: 03/07/2018
Management System - Uncontrolled Document when Printed
Page 8 of 6
Activity/Task What are the tasks involved?
List the work tasks in a logical order.
What are the hazards/risks?
Identify the hazards/risks that may cause harm to workers or the public.
What are the control measures?
Describe what will be done to control the risk. What will you
do to make the activity as safe as possible?
• daily construction activities to begin with lower
level noise disruption (i.e. do not begin with piling)
• avoid obstructing waterway flying-fox transit path
at night with plant or machinery
• camp monitor to assess camp after sunset and
determine if and when young flying-foxes begin
creching in case of scheduled night works
• camp monitor to provide daily evaluation of works
to flying-fox expert
• Section 7.5.1 from the Parramatta Light Rail
GHFF Construction Monitoring Program applies:
– a Responsible Person (i.e. flying-fox expert,
vaccinated camp monitor) would need to have
authority to temporarily stop construction work in
the stop work zone if the GHFF are highly
stressed, as evidenced by:
• diurnal fly-outs leading to splintered camps in
sensitive locations
• welfare impacts
• multiple negative interactions with public (e.g.
flying-fox on ground, flying-fox scratch or contact
with humans)
– works would be allowed to resume when the
flying-fox expert determines that the GHFF are no
longer stressed and at risk to themselves or
people
– construction activities may need to temporarily
stop between the camp and splinter group. A
contingency response team consisting of two
(preferably ABLV vaccinated) people, contactable
Title: Environmental Work Method Statement Template
ID: MSID-4-228 Version: 23.0 Date Published: 03/07/2018
Management System - Uncontrolled Document when Printed
Page 9 of 6
Activity/Task What are the tasks involved?
List the work tasks in a logical order.
What are the hazards/risks?
Identify the hazards/risks that may cause harm to workers or the public.
What are the control measures?
Describe what will be done to control the risk. What will you
do to make the activity as safe as possible?
by radio or mobile, will be required to flush the
bats back to the camp by safe and agreed
methods.
o PCPLR Supervisor – Pat Carroll - 0428 922
740
o PCPLR Project Engineer – Yogesh Pindoliya –
0448 339 576
• Keep record details of the weekly visual checks.
Form, Reo Pour concrete for abutment and pier
• Excavate to top of pile level and blind
• Form and pour Abutments A and B including wingwalls
• Form and pour pier column
• Install Precast headstock – and FRP infill
HRCW – Working with temporary works
• Slurry / water run-off into
• Ensure Erosion and Sediment Controls are
installed in accordance with approved Erosion
and Sediment Control Plan ESCP01
• Installation of floating silt curtain during FRP
works at pier column
• No tools to be left unattended on jetty. Lanyards
on tools to be used where appropriate.
• No rubbish / waste to be left unattended on the
temporary jetty or near the river. Kick boards to
be installed along jetty where appropriate
Title: Environmental Work Method Statement Template
ID: MSID-4-228 Version: 23.0 Date Published: 03/07/2018
Management System - Uncontrolled Document when Printed
Page 10 of 6
Activity/Task What are the tasks involved?
List the work tasks in a logical order.
What are the hazards/risks?
Identify the hazards/risks that may cause harm to workers or the public.
What are the control measures?
Describe what will be done to control the risk. What will you
do to make the activity as safe as possible?
Cut pile casing at center piers
Divers to cut pile encasement below water level
HRCW – Working on, in or adjacent to a waterway
• Debris in waterway
• Installation of floating silt curtain
• Steel casing to be connected with chains prior to
cutting to ensure entire section is removed
• Works to be carried out by licensed and
competent personnel
• Ensure all pieces of encasement are removed
from the river
Construct superstructure
Install Super-T girders
FRP diaphragm
FRP bridge deck
HRCW – Working on, in or adjacent to a waterway
• Sediment and site run-off into Parramatta River
• Dropped items / tools into Parramatta River
• Ensure Erosion and Sediment Controls are
installed in accordance with approved Erosion
and Sediment Control Plan
• No tools to be left unattended on jetty. Lanyards
on tools to be used where appropriate
• During bridge deck pour and wet curing, any
excess slurry or water to be diverted to a sump on
site
Remove temporary jetty
Remove temporary jetty and make area good
1. Remove support beams and handrails by crane.
2. Remove deck by crane.
3. Remove steel columns by mobile crane with grab attachment via vibratory method (High Impact Works).
4. Reinstate batters / embankments
HRCW – Working with temporary works
• Uncontrolled sediment / suspended material floating downstream
• Works to be planned for dry period.
• Installation of slit boom when removing temporary
piles
Grey-headed flying fox disruption • (HOLD POINT) Refer to GHFF Mitigation
Application Procedure (Item 3, 4 and 5).
• (HOLD POINT) Consult with flying-fox expert to
Title: Environmental Work Method Statement Template
ID: MSID-4-228 Version: 23.0 Date Published: 03/07/2018
Management System - Uncontrolled Document when Printed
Page 11 of 6
Activity/Task What are the tasks involved?
List the work tasks in a logical order.
What are the hazards/risks?
Identify the hazards/risks that may cause harm to workers or the public.
What are the control measures?
Describe what will be done to control the risk. What will you
do to make the activity as safe as possible?
Works to be undertaken for a duration of up to 3-4 weeks, commencing in late September 2021.
determine appropriate control and implement any
additional control measures. Update
Environmental Control Map if any additional
measures are required to be implemented.
• notify Department of Planning, Industry and
Environment prior to commencement of new high-
risk activity
• notify WIRES vaccinated and trained rescuer in
flying-foxes to be on stand-by at commencement
of new high-risk activity and be informed of
duration of activity.
• work-specific monitoring at camp required
– daily from commencement of new high-risk
activity
– by two vaccinated and trained personnel for
rescue if required (N.B. A reduction of two
personnel daily to one personnel daily, then one
personnel weekly will be determined by flying-fox
expert based on flying-fox behaviour after 5 days
of evaluation from commencement of high-risk
activity)
• work-specific camp monitors to have direct radio
or phone communications with piling machine
operators to allow prompt ‘stop works’ if required
• plant operators to notify camp monitors before
commencing high risk activity and check-in with
camp monitors for any flying-fox welfare issues
• daily construction activities to begin with lower
level noise disruption (i.e. do not begin with piling)
• avoid obstructing waterway flying-fox transit path
Title: Environmental Work Method Statement Template
ID: MSID-4-228 Version: 23.0 Date Published: 03/07/2018
Management System - Uncontrolled Document when Printed
Page 12 of 6
Activity/Task What are the tasks involved?
List the work tasks in a logical order.
What are the hazards/risks?
Identify the hazards/risks that may cause harm to workers or the public.
What are the control measures?
Describe what will be done to control the risk. What will you
do to make the activity as safe as possible?
at night with plant or machinery
• camp monitor to assess camp after sunset and
determine if and when young flying-foxes begin
creching in case of scheduled night works
• camp monitor to provide daily evaluation of works
to flying-fox expert
• Section 7.5.1 from the Parramatta Light Rail
GHFF Construction Monitoring Program applies:
– a Responsible Person (i.e. flying-fox expert,
vaccinated camp monitor) would need to have
authority to temporarily stop construction work in
the stop work zone if the GHFF are highly
stressed, as evidenced by:
• diurnal fly-outs leading to splintered camps in
sensitive locations
• welfare impacts
• multiple negative interactions with public (e.g.
flying-fox on ground, flying-fox scratch or contact
with humans)
– works would be allowed to resume when the
flying-fox expert determines that the GHFF are no
longer stressed and at risk to themselves or
people
– construction activities may need to temporarily
stop between the camp and splinter group. A
contingency response team consisting of two
(preferably ABLV vaccinated) people, contactable
by radio or mobile, will be required to flush the
bats back to the camp by safe and agreed
methods.
Title: Environmental Work Method Statement Template
ID: MSID-4-228 Version: 23.0 Date Published: 03/07/2018
Management System - Uncontrolled Document when Printed
Page 13 of 6
Activity/Task What are the tasks involved?
List the work tasks in a logical order.
What are the hazards/risks?
Identify the hazards/risks that may cause harm to workers or the public.
What are the control measures?
Describe what will be done to control the risk. What will you
do to make the activity as safe as possible?
o PCPLR Supervisor – Pat Carroll - 0428 922
740
o PCPLR Project Engineer – Yogesh Pindoliya –
0448 339 576
• Keep record details of the weekly visual checks.
Earthworks & Pavement
Backfill works
Construction of approach slabs
Completion works – barriers, fencing, guard rail and lighting
HRCW – Working on, in or adjacent to a waterway
Erosion from stockpiled materials
Uncover and disturb unexpected contaminate material
Run-off from paving activities or curing entering the waterway
• Ensure Erosion and Sediment Controls are
installed in accordance with approved Erosion
and Sediment Control Plan ESCP01
• Monitor, review and amend ERSED as works
progress
• In-situ waste classifications to be undertaken
where feasible and asbestos hygienist to be on-
call if any asbestos contaminated material is
found.
• No stockpiling is to occur along river edge
• Prior to any forecast rain, cover all bare areas
with geofabric or jut matting
All All Grey-headed flying fox (GHFF) colony is located 200m away from the worksite therefore this document will be reviewed by flying fox expert.
• (HOLD POINT) Refer to GHFF Mitigation
Application Procedure (Item 3, 4 and 5).
• (HOLD POINT) Consult with flying-fox expert to
determine appropriate control and implement any
additional control measures. Update
Environmental Control Map if any additional
measures are required to be implemented.
• notify Department of Planning, Industry and
Title: Environmental Work Method Statement Template
ID: MSID-4-228 Version: 23.0 Date Published: 03/07/2018
Management System - Uncontrolled Document when Printed
Page 14 of 6
Activity/Task What are the tasks involved?
List the work tasks in a logical order.
What are the hazards/risks?
Identify the hazards/risks that may cause harm to workers or the public.
What are the control measures?
Describe what will be done to control the risk. What will you
do to make the activity as safe as possible?
Environment prior to commencement of new high-
risk activity
• notify WIRES vaccinated and trained rescuer in
flying-foxes to be on stand-by at commencement
of new high-risk activity and be informed of
duration of activity.
• work-specific monitoring at camp required
– daily from commencement of new high-risk
activity
– by two vaccinated and trained personnel for
rescue if required (N.B. A reduction of two
personnel daily to one personnel daily, then one
personnel weekly will be determined by flying-fox
expert based on flying-fox behaviour after 5 days
of evaluation from commencement of high-risk
activity)
• work-specific camp monitors to have direct radio
or phone communications with piling machine
operators to allow prompt ‘stop works’ if required
• plant operators to notify camp monitors before
commencing high risk activity and check-in with
camp monitors for any flying-fox welfare issues
• daily construction activities to begin with lower
level noise disruption (i.e. do not begin with piling)
• avoid obstructing waterway flying-fox transit path
at night with plant or machinery
• camp monitor to assess camp after sunset and
determine if and when young flying-foxes begin
creching in case of scheduled night works
• camp monitor to provide daily evaluation of works
Title: Environmental Work Method Statement Template
ID: MSID-4-228 Version: 23.0 Date Published: 03/07/2018
Management System - Uncontrolled Document when Printed
Page 15 of 6
Activity/Task What are the tasks involved?
List the work tasks in a logical order.
What are the hazards/risks?
Identify the hazards/risks that may cause harm to workers or the public.
What are the control measures?
Describe what will be done to control the risk. What will you
do to make the activity as safe as possible?
to flying-fox expert
• Section 7.5.1 from the Parramatta Light Rail
GHFF Construction Monitoring Program applies:
– a Responsible Person (i.e. flying-fox expert,
vaccinated camp monitor) would need to have
authority to temporarily stop construction work in
the stop work zone if the GHFF are highly
stressed, as evidenced by:
• diurnal fly-outs leading to splintered camps in
sensitive locations
• welfare impacts
• multiple negative interactions with public (e.g.
flying-fox on ground, flying-fox scratch or contact
with humans)
– works would be allowed to resume when the
flying-fox expert determines that the GHFF are no
longer stressed and at risk to themselves or
people
– construction activities may need to temporarily
stop between the camp and splinter group. A
contingency response team consisting of two
(preferably ABLV vaccinated) people, contactable
by radio or mobile, will be required to flush the
bats back to the camp by safe and agreed
methods.
o PCPLR Supervisor – Pat Carroll - 0428 922
740
o PCPLR Project Engineer – Yogesh Pindoliya –
0448 339 576
Title: Environmental Work Method Statement Template
ID: MSID-4-228 Version: 23.0 Date Published: 03/07/2018
Management System - Uncontrolled Document when Printed
Page 16 of 6
Activity/Task What are the tasks involved?
List the work tasks in a logical order.
What are the hazards/risks?
Identify the hazards/risks that may cause harm to workers or the public.
What are the control measures?
Describe what will be done to control the risk. What will you
do to make the activity as safe as possible?
• Keep record details of the weekly visual checks.
Title: Environmental Work Method Statement Template
ID: MSID-4-228 Version: 23.0 Date Published: 03/07/2018
Management System - Uncontrolled Document when Printed
Page 17 of 6
Workers Consulted in the development of this SWMS
Name Position Company Signature Date
David Barkho Environmental Advisor CPBDJV
Andrew Peacock Senior Project Engineer CPBDJV
Yogesh Pindoliya Project Engineer CPBDJV
Sahanna Gandhi Site Engineer CPBDJV
Additions or Alterations Note: All alterations must be authorised by the Project Manager (or authorised delegate).
Date of Addition or Alteration
Project Manager Review (or authorised delegate)
Date of Review Authorised
☐ Yes ☐ No
☐ Yes ☐ No
☐ Yes ☐ No
☐ Yes ☐ No
☐ Yes ☐ No
☐ Yes ☐ No
Title: Environmental Work Method Statement Template
ID: MSID-4-228 Version: 23.0 Date Published: 03/07/2018
Management System - Uncontrolled Document when Printed
Page 18 of 6
1
2
3
4
I understand what the hazards of the work is and what the risks are
I understand what controls must be in place before starting work
I understand the requirements of this SWMS
I have been given an opportunity to comment on the method of work
Work Location Bridge St Bridge - Cumberland Work Pack Reference
Name of Worker Signature Date Name of Worker Signature Date
top related