method statement final.docx
TRANSCRIPT
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS
AT
RAS AL KHAIR
METHOD STATEMENT
FOR DREDGING & RECLAMATION WORKS
DATE: RAMADAN 1435H
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS ATRAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 1 of 61
CONTENTS
DREDGING WORKS AND CONSTRUCTION OFTWO CONTAINER BERTHS
ATRAS AL KHAIR
Item Page No.
1. List of Key Personnel :
2.General Project Details :
3. Method of Construction :
4. APPENDIX ‘A’
Method Statement indicating Compliance with all Clauses of Specification :
5. APPENDIX ‘B’ :
Photographs of Equipment :
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS ATRAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 2 of 61
1. LIST OF KEY PERSONNEL
Title Name Telephone No.
Project Manager :
Dredging Engineer :
Dredger Master :
Technical Office Engineer :
Safety Engineer :
Port Control : VHF Channel 67/19 0515187877
SEAPA Resident Engineer : Mehdi 0551918151
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS ATRAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized Contracting
Company Ltd.
Date: Ramadan 1435HPage No.: Page 3 of 61
Project Manager
DredgerMaster
MechanicalChief
Engineer
Laboratory Technician
Technician Electrical Mechanic
TechnicianMechanic
DredgerOperator
Reclamation Engineer
CivilForeman
CivilForeman
WelderPipe fitter
Labor
Heavy Duty Driver
LaboratoryHelper
Divers Seaman
Heavy Duty Operator
Secretary
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 4 of 61
2. GENERAL PROJECT DETAILS
1. General
The Ports Authority is developing the Port of Ras Al Khair. The marine part of this development is the construction of the following works:
Remaining 185m of Berth 8 to complete the East –West line of the berths
A Roll on Roll off berth at junction of Berths 8 & 9.
Two Container Berths 330LM each
Dredging of Basin alongside to a depth of -15.00
Reclamation of all areas behind the quaywall and the West lagoon.
Edge Protection works at the south-west end of Berth 10.
Removal of core rockfill and armour from existing bund.
2. Method Statement
Under the terms of the contract a ‘Method Statement’ is required to be submitted for Dredging & Reclamation works of the contract.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 5 of 61
(Contd…. from previous page)
Description of Works
Works included in this Method Statement are as follows:
a) Dredging of basin up to depth -15.00 .
b) Dredging of trench to depth -18.50 for Berth 8 and Roll on Roll off Berth.
c) Dredging of trench to depth -20.00 for Berths 9 & 10.
d) Reclamation of storage area behind quaywalls.
e) Reclamation of lagoon area west of the existing road.
f) Provision of surcharge in various Storage Areas as required and directed by the Engineer.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 6 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 7 of 61
METHOD OF CONSTRUCTION
1. Survey
2. Boreholes & Testing
3. Permits from Govt. Agencies
4. Contractor’s Working Area
5. Equipment utilized for Dredging & Reclamation
6. Construction Schedule
7. Dredging Calculations
8. Sequence of Works
9. Reporting & Information
10. Monitoring
11. Risk Analysis & Mitigation
12. Compaction requirements for Reclamation
13. Contractor’s Comments
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 8 of 61
1. SURVEY
The Survey Points and Bench Marks provided by the Ports will be utilized for the project.
Other points will be established for convenience of checking, and will be submitted to the
Engineer for approval before usage.
Topographic and Hydrographic surveys will be carried out in the presence of the Engineer’s
representatives. Arrangements for spot checking (soundings) shall also be made to ensure
matters remain under check.
Multi beam echo sounder will be employed for all hydrographic survey work.
Prior to commencement of dredging, a number of runs by the echo-sounder will establish
the presence of any obstruction on the sea-bed. As the Port is a new port it is not
envisaged that this should be a problem.
Tide Gauges, wind sock etc. will be provided to ensure all weather parameters are known
during the dredging operations.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 9 of 61
2. BOREHOLES & TESTING
A local firm will be engaged after obtaining approval from the Ports and all necessary information
obtained.
From the borehole information provided at tender stage, material appears to be good, suitable
material for reclamation.
However it appears that no boreholes were taken in the Basin Area. At least two boreholes wll
be taken in the Basin Area up to -18.00 or as directed by the Engineer to confirm suitability of
material.
Daily testing or as required at the change of dredged materials will be carried out in the presence
of the Engineer’s Representative and commensurate action taken as regards the suitability of the
material for reclamation purposes. Any poor material encountered will be dumped in the Spoil
Area.
After completing the Soil Investigations, if the results differ appreciably from that shown at the
tender stage, appropriate adjustments will be made to the Method Statement, to the approval of
the Engineer.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 10 of 61
3. PERMITS FROM GOVT. AGENCIES
As we will be working within the confines of a working Port, we envisage that there will be
no requirements of Permits or any permission to be taken from any Govt. Agency (Four
member committee etc.).
However, on our own, we will be taking care not to spoil the environment and will ensure
that whatever measures need to be taken are followed by all staff and equipment.
Any permit requirements from the Coast Guards or the Customs will be fulfilled to their
satisfaction.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 11 of 61
4. CONTRACTOR’S WORK AREA
A Contractor’s Work Area is shown in the Tender drawings which will be developed for the
production of the blocks.
A block loading jetty will be constructed at the required location where all mooring craft and
marine equipment will be parked when not in use or during inclement weather. Care will be
taken not to interrupt Port small craft traffic at Berth 4.
Diesel, the fuel for most marine craft will be brought in from land after taking permission from the
required Customs and Coast Guards authorities.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 12 of 61
5. * EQUIPMENT UTILIZED FOR DREDGING & RECLAMATION
1. DredgerIHC Beaver 65 DDSP(Modified by IHC)
: Dredging depth: 22m.Cutter Power: 700 KWDelivery Pipeline: 650mm dia.Dredger Pump: ……. HP
2. Tug BoatIHC Delta Multicraft1400 – DMC 1400
: Power: 609 HPSpeed: 8 knotsBollard pull: 7T
3. Survey Boat :
4. Pilot Boat :
5. Hopper BargeSelf propelled barge
:
6. Pipeline 650mm dia. : Length: …… m.
7. PontoonsBackhoe
:Doosan
8. Bulldozers :
9. Shovel :
10. Grader : Caterpillar
11. Steel Roller : Volvo
12. Other Equipment: : Tide GaugeGPSWind sockSilt curtains, booms etc.
* Note: Photographs of marine equipment included in Appendix ‘B’
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 13 of 61
6. CONSTRUCTION SCHEDULE
The Construction Schedule for all works is enclosed. It can be seen that dredging
westwards in the line of Berth 8 up to a depth of -15.00 is the first activity to be
undertaken.
The same dredger will be employed to form the trench up to -18.50 after which blockwork
placing for the quaywall could commence.
As there are no interface requirements with any other contractor, we do not foresee any
problem in continuing with the dredging and blockwork installation on the rest of the
quaywalls as programmed.
The stages of construction are shown on Page No. 14.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS ATRAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized Contracting
Company Ltd.
Date: Ramadan 1435HPage No.: Page 14 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 15 of 61
7. DREDGING CALCULATIONS
Total volume to be dredged : 2,125,540 cu.m.
Assume period required : 15 months
Volume of dredging/month : 141,703 cu.m./month
Rate of Dredging, assuming 20 days/month work : 7,085 cu.m./day
Note that the dredger is provided with pumps, situated below water level on the ladder, hence is capable to carry out dredging operations up to -22.00 satisfactorily.
i.e. one dredger is capable to carry out all dredging works of the contract. However, should the need arise for a grab dredger for cutting the trench or for removal of hard material in the Basin, we have arrangements for deploying a grab dredger.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 16 of 61
8. SEQUENCE OF WORK
The sequence of work will be as follows:
1. IN-SURVEY
2. DREDGING
a) Berth 8 & Ro Ro
Dredging up to -15.00 in the line of the trench. Dredging of trench up to -18.50 . Approval from Consultant for proceeding with quaywall construction.
b) Berths 9 & 10
Dredging up -15.00 in the line of the trench Dredging of trench up to -20.00 . Approval from Consultant for proceeding with quaywall construction.
c) Basin
Dredging up to -15.00 .
3. OUT SURVEY
4. RECLAMATION
Prior to any reclamation the following works need to be carried out:
a. Removal of rockfill underlayer and core from rear of Berth 8 and its storage.
b. Removal of rockfill underlayer and core from the rear of Berths 9 & 10 and its storage.
c. The rock armour, underlayer etc. of the West Breakwater (besides the Lagoon) will be removed and stored at the location required by the Ports.
d. A further layer and geotextile will be provided before reclamation will proceed in the area.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 17 of 61
8. SEQUENCE OF WORKS (Contd…….)
e. Filling the area behind Berth 8.
f. All excess dredged material at this stage ill be diverted to the West Lagoon area.
g. Filling the area behind Berths 9 & 10 up to bund.
h. After completion of blockwall, provision of rear rockfill, filter, geotextile etc. complete the reclamation up to the sand bund *.
Stages I – V
Drawings included in Appendix B show the various stages of dredging and reclamation.
* Note: Sand bund will be of coarse material and will not in any way alter the characteristics of the fill.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 18 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 19 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 20 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 21 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 22 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 23 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 24 of 61
9. REPORTING & INFORMATION
Daily Reports will be submitted to the Engineer.
Photographs of work in progress will be submitted together with the Weekly Reports.
An In-survey will be carried out in the presence of the Engineer’s Representative and the
sheets signed for records.
An Out-survey will be carried out in the presence of the Engineer’s Representative suitable
for submission by the Ports to the mariners.
The dredger and all support vessels will remain in constant contact by radio with the
Harbour Master to ensure none of the Port incoming or outgoing vessels are interrupted by
the operations.
24 hour operation is envisaged for all dredging and reclamation work.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 25 of 61
10. MONITORING
Constant monitoring of the following parameters will be carried out:
Turbidity
Movement of silt
Water quality.
Please note that the temperature of the water may be higher in the basin due to the presence of
the Ma’aden outfall. The water may be saltier too.
Consequently, care will be taken regarding concrete for the structures, steelwork, slope protection
rock etc. to ensure that they stand well to the additionally aggressive conditions found in the
Basin. It is expected that the temperature and salinity of the Basin may reduce after dredging has
been carried out as a larger body of water will be available for dispersion.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 26 of 61
11. RISK ANALYSIS AND MITIGATION
The Harbour appears to be well protected where the dredging works and reclamation
works are to take place. Large current/waves cannot enter the harbor as breakwaters
shield the Port from the North and the North-west winds. The lagoon is totally protected
from the west and the north sides. Little mitigation measures need to be carried out in this
respect.
Interference with shipping is also foreseen to be minimum as all work is to the west of the
existing shipping berths and traffic. Only small boats, vessels visiting Berth 4 will need to
be diverted slightly when the final dredging up to -15.00 in the basin will be carried out.
This should be simply straightforward and should not pose any problem or would require
mitigation measures.
Any risk to environment shall be mitigated by ensuring there are no leaks in the joints of
the discharge pipes.
If dredging operations result in silt/sedimentation finding its way into the adjacent basin,
silt curtains will be provided to ensure that it is kept to a minimum.
As the Western Lagoon is on the other side of the main road leading to the Aluminium
Berths 5, 6 & 7, alternative roads will be provided if the permanent road will be closed for
traffic. Alternatively if the Port allow ramps with mild slopes will be provided to ensure
passage of heavily loaded trucks without difficulty. There will be some interface
requirement with the contractor CHEC who has constructed a temporary road west of the
Main Road on which they will be moving their Armour Blocks made available from the
North Breakwater.
All marine staff will be provided with life jackets, life buoys and rafts will be available for
any emergency.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 27 of 61
11. RISK ANALYSIS AND MITIGATION (Contd…..)
Adequate beacons, buoys etc. will be provided for the dredging operations to eliminate
chances of collision. Flood Lighting will be provided such that it would not confuse the
shipping. All vessels shall be equipped with VHF phones and mobile telephones to
ensure rapid communication.
We understand that a number of days will be lost for the dredging operation because of
dusty and windy weather. All marine craft will be parked safety during such conditions and
the Ports kept well-informed of their positions.
Care will be taken in the sequence of reclamation that tail water never gets trapped.
Overflow weirs etc. will be constantly provided and monitored to ensure discharge of
excess water.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 28 of 61
12. COMPACTION REQUIREMENTS FOR RECLAMATION
From the materials indicated to be dredged and used for reclamation, it appears that the
required densities will be reached without resorting to either Dynamic Compaction or
Vibroflotation.
As the dredged material appears to be more in quantity than the reclamation area volumes,
it is expected that surcharge will need to be placed on all areas. This in itself will provide
the long term consolidation required for either the Lagoon Area or the Port Storage Areas.
Areas behind the wharf which are subject to more stringent requirements will be carried out
by the future construction contractor of the Container Terminal.
Homogeneity of fill will be ensured by constant movement of the dredged material by
bulldozers. Fine material pockets will not be allowed to form that may lower the quality
requirements of the fill.
Should densities not be achieved for any reason above water levels, 10T rollers will be
provided to compact the fill in layers to give the required compaction in the Storage Areas.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 29 of 61
13. CONTRACTOR’S COMMENTS
a) Surcharge
From preliminary calculations it appears that there will be more dredged material than what is
required for reclamation. Should the quantity of dredging exceed the allocated BOQ quantity,
we assume that a Change Order will be provided as all quantities are subject to
remeasurement. Consequently, surcharge will have to be provided in the reclamation areas
which will induce settlement and consolidation of the fill in the long run.
As the surcharge will be in the wind direction, some form of treatment would be required at
the top of the surcharge to ensure that it does not blow itself into the basin or other areas of
the Port.
b) Filling of West Breakwater
Before filling could commence in the Lagoon area, the eastern side of the breakwater will
need to be provided with a layer of filter and geotextile. Apparently there is no provision for
this work in the contract BOQ.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435HPage No.: Page 30 of 61
APPENDIX A
METHOD STATEMENT INDICATING
COMPLIANCE WITH ALL CLAUSES OF
SPECIFICATION
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS ATRAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATIONWORKS
Issued by:Rawabi Specialized Contracting Company
Ltd.
Date: Ramadan 1435HPage No.: Page 31 of 61
General
(C)4 DREDGING AND RECLAMATION
(C)4.1 Dredging
(C)4.1.1. The area to be dredged is shown in the Drawings. All dredging shall be to the profiles shown in the Drawings.
Dredging will be carried out in accordance with the bathymetric survey (In-Survey) agreed by the Engineer.
Rates for dredging all materials
(C)4.1.2 The removal of rubbish, foreign object or obstructions found on the seabed.
Noted.
Obstacles (C)4.1.3 In order to prevent damage to his plant and equipment, it is recommended that the Contractor should locate and remove such obstructions before beginning dredging.
Noted.
Plant and methods
(C)4.1.4 The plant and methods used for dredging shall be subject to the prior approval of the Engineer, but such approval shall not relieve the Contractor of his responsibility for ensuring that his plant and methods are suitable, efficient and sufficient for the works, nor of any other of his responsibilities under the Contract.
The method of dredging and transporting material shall be such as to obviate any deposition of material navigable channels or berths. In the event of unavoidable spillage occurring to such an extent that siltation of any navigable channel or berth occurs, the Contractor shall, at his own expense, immediately restore the affected channel or berth to its original depth to the satisfaction of the Ports and the Engineer.
Details of the dredger are attached. In case of breakdown (which may not be frequent as dredger is new) we will mobilize a second dredger which is working at King Abdul Aziz Port, Dammam.
Noted. Care will be taken so that the silt etc. should not find its way into the channel. If required, silt curtains will be employed to ensure sediments do not move far.
Programme to be flexible
(C)4.1.5 The programme of dredging must be flexible. It may need to be varied to meet the working needs of the Port and the construction programme, or for any other reason considered necessary by the Engineer. Meetings shall be held with the Engineer or any other party, as and when required by the Engineer, to arrange a suitable programme.
Noted. As long as it does not delay the construction of the quaywall, in which case extension of time will be requested.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS ATRAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATIONWORKS
Issued by:Rawabi Specialized Contracting Company
Ltd.
Date: Ramadan 1435HPage No.: Page 32 of 61
(C)4.1.6 Not used.
Tolerances and limitations
(C)4.1.7 The tolerances and limitations of dredging are as follows:-
(a) Quaywall foundation trench.The finished trench profile shall not, at any point, be shallower than the design profile shown in the Drawings, neither shall it be deeper than the design profile by more than 250mm, nor wider than the design profile by more than 500mm (on each side). Should these tolerances be exceeded, except on the written instructions of the Engineer, the Contractor shall, at his own expense, backfill over cut areas in accordance with the Engineer’s instructions.
(b) Quay-SideWithin 30 metres of the quay face, the Contractor shall not over-dredge by more than 250mm below the design profile. Should such over-dredging occur, the Contractor shall, at his own expense, backfill to the design profile with approved material.
a) Noted.
b) Noted.
Side slopes
(C)4.1.8 The side slopes to the boundaries of the prescribed dredging areas and the side slopes to the quay-wall foundation trench shall be dredged in accordance with the design profiles shown in the Drawings, or to whatever other such profiles as the Engineer may decide, having regard to the nature of the materials present. Alternatively, if approved by the Engineer, a series of benches equivalent to the exhibited side slope may be dredged, and any such benching shall be deemed to be a side slope for the purpose of this Clause.
Agreed. Benching will be carried out to form the slopes.
Disposal of dredged material
(C)4.1.9 If dredged material is suitable for use as reclamation fill (as specified in (C)4.2.4), it shall be deposited in areas to be reclaimed. If it is not suitable for this purpose, it shall be dumped, in accordance with the Engineer’s instructions, in the approved spoil ground shown in the Drawings.
Dredged material unsuitable for use will be dumped in the Spoil Area, the coordinates of which are known.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS ATRAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATIONWORKS
Issued by:Rawabi Specialized Contracting Company
Ltd.
Date: Ramadan 1435HPage No.: Page 33 of 61
Disposal of dredged material(Contd….)
Before tendering, the Contractor shall satisfy himself as to the distance between areas to be dredged and the spoil ground and reclamation areas and shall include in his rates and prices for dredging for the conveyance of dredged material from any part of the areas to be dredged to any part of the spoil ground or reclamation areas. No claim will be entertained in respect of length of haul between the dredged areas and the spoil grounds specified herein.
Should the dredged material be utilized for reclaiming the western lagoon, the contractor must ensure that his operations do not disrupt Ma’aden Aluminium Company’s and Port traffic to Berths 5-7.
No dredged spoil shall be dumped in any area other than the specified spoil ground or such other spoil ground as may subsequently be directed by the Engineer. The Contractor shall hold the Ports indemnified against any claim that may be made against it through the Contractor’s default in this respect.
The rates for dredging and disposal of material shall include for all temporary moorings, stages, pipe work, sluices, temporary bunding and any other works necessary for carrying out the work in an efficient manner.
Noted
Noted
Noted
Agreed
No simultaneous discharge
(C)4.1.10 Not used.
Surveys of dredging areas
(C)4.1.11 Prescribed dredging areas shall be surveyed from time to time during and after dredging operations, as specified below or as required by the Engineer, for the purposes of measurement or for any other reason. The cost of all such surveys will be deemed to be included in the Contractor’s rates and prices for dredging.
Unless otherwise specified or required by the Engineer, surveys shall be made using a suitable launch fitted with an approved echo sounder and positioning shall be made by using approved electronic location equipment. For this purpose, the Contractor shall provide operators who have been trained by the supplier of the equipment and certified as capable of such duties.
Joint monthly surveys will be conducted for the inclusion of quantities in the interim valuations.
Noted.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS ATRAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATIONWORKS
Issued by:Rawabi Specialized Contracting Company
Ltd.
Date: Ramadan 1435HPage No.: Page 34 of 61
Surveys of dredging areas(Contd…)
Bar calibration or the echo sounding equipment shall be carried out prior to the commencement of each day’s surveying and at such other times as the Engineer may direct and the corrections shall be agreed between the Contractor and the Engineer.
Noted.
Surveys of foundation trench
(C)4.1.12 The method of survey of the quay-wall foundation trench after completion, or alleged completion, shall consist of close-centred spot soundings to provide cross-sections at regular intervals. The techniques used and the frequency of soundings and cross-sections shall be to the approval of the Engineer. Notwithstanding any such approval, the techniques and frequencies shall be amended if required by the Engineer as the work proceeds. For the purpose of this Clause, the foundation trench shall be deemed to include for all dredged side slopes or benches, and the surveys shall also be extended for an approved distance on each side of the trench.
Agreed.
Joint surveys
(C)4.1.13 Before dredging commences, the Contractor and the Engineer shall jointly make survey of all areas which are to be dredged and all areas in which reclamation is to be placed. The method and frequency of sounding shall be to the Engineer’s approval. The Contractor shall prepare a drawing showing the agreed levels, and this shall be signed by the Contractor and the Engineer. On the basis of the agreed drawing, the Contractor shall prepare drawings showing sections through these areas, all to the Engineer’s satisfaction.
Unless otherwise specified or required by the Engineer, the survey procedure described in Clause (C)4.1.11 above shall be repeated for all interim and final measurements, and the quantities determined by difference, but with due regard to over-dredged material (see Clause (C)4.1.17).
In-survey will be carried out by Gulf Consult in the presence of the Engineer shortly.
Agreed.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS ATRAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATIONWORKS
Issued by:Rawabi Specialized Contracting Company
Ltd.
Date: Ramadan 1435HPage No.: Page 35 of 61
Payment (C)4.1.14 Payment for dredging will be made under the appropriate items in the Bills of Quantities, and the quantities shall be determined in accordance with Clauses (C)4.1.11 to (C)4.1.13 for the following:-
(a) the sum of net volumes of materials dredged from prescribed dredging areas and deposited in reclamation areas, as specified.
(b) the sum of net volumes of materials dredged from prescribed dredging areas and dumped in the spoil ground or elsewhere, as specified.
No payment will be made for dredging per se, in borrow areas, or elsewhere as specified, for the purpose of winning reclamation fill.
Agreed.
Agreed.
Siltation, inflow etc
(C)4.1.15 Payment for dredging any one area will be made once only. Until all dredging and reclamation has been completed to the Engineer’s satisfaction, the Contractor shall remain responsible for the removal from dredged areas of any subsequent influx of materials, whether this be caused by siltation, sedimentation, inflow, collapse of side slopes, discharge or deposition, or any other cause, irrespective of whether or not this may be directly attributable to the Contractor’s operations.
When required to do so by the Engineer, the Contractor shall determine the depth of siltation (the term shall be taken to include the influx of silt or mud, however caused) in any specified area, at any time after dredging. The method, which shall be to the approval of the Engineer, shall enable such deposits to be differentiated from the underlying materials where, in the opinion of the Engineer, this is reasonably possible.
Noted.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS ATRAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATIONWORKS
Issued by:Rawabi Specialized Contracting Company
Ltd.
Date: Ramadan 1435HPage No.: Page 36 of 61
Interim measurements
(C)4.1.16 The Engineer will give monthly certificates on account of sums which may become payable. Interim measurements will be based on either:-
a) agreed joint surveys, as specified in Clause (C)4.1.13 or
b) agreed net volumes of material dredged during the month to which the Certificate relates.
Agreed.
Agreed.
Over-dredging (C)4.1.17 Payment will not be made for any material dredged from below or outside of the design profiles shown in the Drawings, or any other such profiles as the Engineer may from time to time direct, and the volume of any such material shall be deducted from the total volume dredged to determine the net volume for which payment is due.
Agreed.
Final measurement
(C)4.1.18 On completion, or alleged completion, of dredging in any particular area, the survey procedures specified in Clause (C)4.1.11 to (C)4.1.13 above shall be repeated. If it is found that the required profile has not been attained, or the required slopes not properly formed, the Contractor shall further deepen, extend or correct such areas as necessary, all to the satisfaction of the Engineer. A further joint survey of the area shall then be made for the purpose of final measurement. A deduction shall be made, in accordance with Clause (C)4.1.17, for material dredged from below or outside of the required profile.
A survey will first be carried out ourselves and then the Client will be notified.
Final sweep of dredged areas
(C)4.1.19 On completion of all dredging and reclamation, the Contractor shall sweep the whole of the dredged area, using equipment approved by the Engineer, to ensure that no high spots or obstruction remains. If any such high spots or obstructions are revealed, the Contractor shall remove them at his own expense.
Agreed.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS ATRAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATIONWORKS
Issued by:Rawabi Specialized Contracting Company
Ltd.
Date: Ramadan 1435HPage No.: Page 37 of 61
Weekly returns
(C)4.1.20 The Contractor shall, at the end of each week, submit to the Engineer’s Representative in duplicate, and in such form as the Engineer shall require, a return of the measurements of materials dredged.
Noted.
Rates to be inclusive
(C)4.1.21 All costs in connection with the provision and maintenance, in good working order, of all necessary plant and equipment necessary for dredging will be deemed to be included in the rates and prices in the priced Bills of Quantities.
Noted.
General
(C)4.2 Reclamation
(C)4.2.1 The area to be reclaimed is shown in the Drawings. All reclamation shall be carried out to the lines and levels shown in the Drawings, unless otherwise directed by the Engineer.
The levels shown in the Drawings shall be deemed to be those required at the end of the Maintenance Period. The Contractor shall make allowance, therefore, for settlement of the reclamation fill after placement. This shall be done by initially placing the fill levels higher than those shown in the Drawings and the magnitude of this allowance shall be agreed between the Contractor and the Engineer (or otherwise determined by the Engineer) on the basis of all available data. Fill above water level shall be laid and compacted in 300mm thick layers and shall be compacted to 75% Relative Density. The density tests shall be carried out on a 50m grid.
The Contractor shall allow in his rates and prices entered in the priced Bills of Quantities for the additional material required to allow for settlement.
A topographic survey will be carried out and agreed with the Engineer before placing any reclamation material.
Fill will be compacted as required.
Agreed.
Source of reclamation material
(C)4.2.2 The source material provided for reclamation filling shall consist of material arising from any source always that both the source and quality of the material are to the approval of the Engineer. Any such approval of source material given by the Engineer shall not relieve the Contractor of his full responsibility for ensuring that the finished reclamation satisfies all the requirements of this Specification.
The source of reclamation material will be the suitable dredged material from the trench and the basin.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS ATRAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATIONWORKS
Issued by:Rawabi Specialized Contracting Company
Ltd.
Date: Ramadan 1435HPage No.: Page 38 of 61
Samples for approval
(C)4.2.3 The Contractor shall submit any such samples of the reclamation fill source material as are required from time to time by the Engineer for the purpose of approval.
Noted.
Reclamation fill grading above chart datum
(C)4.2.4.2 All material deposited in the reclamation for use as reclamation fill above chart datum shall consist of naturally occurring soils and rock fragments and shall have a grading curve wholly within the limits shown graphically in Figure 2 below. The principal limits are as follows:
The Specification will be followed.
Lab tests will be carried out continuously to the Engineer’s satisfaction.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS ATRAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATIONWORKS
Issued by:Rawabi Specialized Contracting Company
Ltd.
Date: Ramadan 1435HPage No.: Page 39 of 61
Segregation to be minimized
(C)4.2.5 The placement of reclamation fill shall be carried out in such a manner that segregation of material is limited and that specified gradings are satisfied throughout the as-placed material.
Bulldozers will be utilized to mix the materials to ensure consistency is achieved in the reclamation materials.
Unsuitable material
(C)4.2.6 Any material not complying with the requirements of the Specification, or any other such requirements as the Engineer may from time to time stipulate, shall be deemed unsuitable and shall be rejected. Material so rejected shall be removed from the Site and replaced with suitable reclamation fill all at the Contractor’s expense.
Noted.
Programme to be flexible
(C)4.2.7 The programme of reclamation shall be flexible. It may need to be varied to meet the working requirements of the Port and the construction programme, or for any other reason considered necessary by the Engineer. Meetings shall be held with the Engineer, or any other party, as and when required by the Engineer to arrange as suitable programme.
Noted.
Clearance of seabed
(C)4.2.8 Before depositing any reclamation fill, the Contractor shall remove all vegetable matter, foreign objects and any other substances on the seabed which, in the opinion of the Engineer, could have an adverse effect on the Works. The cost of such removal shall be deemed to be included in the rates and prices entered by the Contractor in the Priced Bills of Quantities.
Noted. A visual survey will be carried out together with the Engineer’s representative on the Western Lagoon. Any filling behind the quaywall will be inspected at low tide.
The shallow areas are not expected to have any obstruction.
Pumping (C)4.2.9 If pumping plant is utilized, it shall be capable of placing reclamation fill to any level as directed by the Engineer in any part of the reclamation. This includes the placement of reclamation fill as a surcharge to levels higher than the finished levels shown on the drawings, as described in Clause (C)4.2.14 of this Specification.
Surcharge material will be provided as the dredged material appears to be in excess of the reclamation areas. Booster pumps will be utilized where necessary.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS ATRAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATIONWORKS
Issued by:Rawabi Specialized Contracting Company
Ltd.
Date: Ramadan 1435HPage No.: Page 40 of 61
Distance to borrow areas
(C)4.2.10 Before tendering the Contractor shall satisfy himself as to the distance between any borrow area and the reclamation area. He shall include in his rates and prices for the conveyance of material from any part of any borrow area to any part of the reclamation area and no claim will be entertained in respect of length of haul.
Noted.
Transport of reclamation fill
(C)4.2.11 Subject to the requirements of this Specification, the fill material shall be discharged into the reclamation area by whatever means the Contractor considers most suitable, including dumping and/or pumping through floating pipelines, provided always that his methods are to the approval of the Engineer. Whilst depositing into a reclamation area material dredged from the prescribed dredging area, the Contractor shall not simultaneously discharge into the same area material originally won from a borrow area.
Fill by trucks will be considered for the lagoon if desirable. Permission by the Ports from certain locations where crossing the roads will not be dangerous, will be sought. The road will be protected adequately.
Method statement with tender
(C)4.2.12 The Contractor shall, at the time of tendering, submit to the Engineer an outline description of the methods he proposes to use to convey and discharge material for reclamation.
Method Statement is being submitted.
Method of reclamation
(C)4.2.13 Reclamation will be performed by placing of material (if suitable) dredged from the prescribed dredging area shown on the Drawings or as instructed by the Engineer.
Noted.
Temporary surcharge
(C)4.2.14 As and where directed by the Engineer, additional material shall be placed as a temporary surcharge to pre-load the reclamation fill. The extent, level and duration of all surcharge loading will be decided by the Engineer, normally on the basis of soils tests and instrumentation, and the work shall be carried out strictly in accordance with the Engineer’s instructions.
Joint surveys shall be made in accordance with Clause (C)4.2.17 of this Specification, as and when necessary for measurement purposes.
Noted.
For interim payments, soundings will be taken or an echo sounder will be employed Noted.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS ATRAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATIONWORKS
Issued by:Rawabi Specialized Contracting Company
Ltd.
Date: Ramadan 1435HPage No.: Page 41 of 61
Disposal of surcharge material
(C)4.2.15 The surcharge material shall, when decided by the Engineer, be removed and carted away. Unless otherwise approved by the Engineer, all surcharge material shall comply with Specification Clause (C)4.2.4.
Joint surveys shall be made, in accordance with Clause (C)4.2.17 of this Specification, as and when necessary for measurement purposes.
Noted.
Method of payment
(C)4.2.16 Payment for reclamation will be as follows:
For material dredged from the prescribed area shown on the Drawings or as instructed by the Engineer, payment will only be made for dredging as described in Clause (C)4.1.14. No additional payment will be made for reclamation.
Noted.
Measure-ments
(C)4.2.17 Before the placing, in any area, of material obtained from borrow areas, the Contractor and the Engineer shall make a joint survey and the results shall be recorded on a drawing showing the agreed levels, which shall be signed by the Contractor and the Engineer or his Representative. The total as-placed volume of reclamation which will be required to reclaim any area shall be calculated using levels shown in this drawing and the finally required reclamation levels.
Unless approved by the Engineer, the Contractor shall not place material dredged from the prescribed dredging area upon material obtained from borrow areas. If such placing shall be approved, sufficient joint surveys shall be made to enable the volume of material from the prescribed dredging area which has been placed to be calculated and this volume shall be deducted from the volume of reclamation determined as described above.
Measurements will be based on the joint In-survey (topographic survey) carried out at the commencement of the contract.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS ATRAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATIONWORKS
Issued by:Rawabi Specialized Contracting Company
Ltd.
Date: Ramadan 1435HPage No.: Page 42 of 61
Measure-Ments(Contd…)
Reclamation areas shall be surveyed from time to time before, during and after reclamation, as specified above or as required by the Engineer, for the purposes of measurement or for any other reason. The cost of all such surveys will be deemed to be included in the Contractor’s rates and prices for reclamation.
Noted.
Weekly returns
(C)4.2.18 The Contractor shall, at the end of each week, submit to the Engineer’s Representative in duplicate, and in such form as the Engineer shall require, a return of the measurements of reclamation materials placed.
Noted.
Rates to be inclusive
(C)4.2.19 All costs in connection with the provision and maintenance, in good working order, of all necessary plant and equipment necessary for raising the reclamation areas to the required levels will be deemed to be included in the rates and prices in the priced Bills of Quantities.
The rates and prices shall also include for the costs of provision, and subsequent removal, of all temporary culverts and sluices necessary for the satisfactory completion of the reclamation in accordance with this Specification.
Noted.
Compaction to 75% relative density
(C)4.2.20 Where the reclamation fill is not subjected to surcharge loading, all fill above Mean High Water Springs Level shall be thoroughly compacted in layers by vibratory rolling, or by other means to the Engineer’s approval, such that the finished relative density of each layer is at least 75%. Relative
density Dr, shall be defined in terms of voids ratio, ‘e’, as follows:-
where emax and emin are determined using the procedures given in A.S.T.M. Standard D2049 ‘Test for relative density of cohesionless soils’.
A laboratory will be utilized who will assist us in determining the densities on a regular basis.
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS ATRAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATIONWORKS
Issued by:Rawabi Specialized Contracting Company
Ltd.
Date: Ramadan 1435HPage No.: Page 43 of 61
Testing of samples
(C)4.2.21 Representative samples of the reclamation fill within its upper 2 metres shall be tested in accordance with the Standard defined in Clause (C)4.2.20 above to determine their maximum and minimum voids ratios. Further samples shall be submitted to the Engineer if required.
Noted.
In-situ density measurements
(C)4.2.22 The Contractor shall measure the in-situ dry density of the compacted reclamation fill, at regular intervals as directed by the Engineer, using the procedure given in BS 1377 Test 15(B). Tests will be required by the Engineer at various levels within the upper 2 metres of fill and the Contractor shall excavate shallow pits as necessary to enable these tests to be made. Excavation of the last 200mm down to test level shall be done carefully by hand to avoid disturbance of the soil to be tested.
Noted.
Testing prior to construction
(C)4.2.23 In-situ density tests shall also be made, in accordance with the Engineer’s instructions, within the areas of buildings or other structures prior to their construction. The maximum depth of such tests below finished level will be 2 metres. (Where investigation to greater depth, by instrumentation, boreholes or Dutch probes, is also required, payment for these will be made under the items in the appropriate section of the Bills of Quantities.
Not applicable in our case.
---------------- x X x ----------------
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435H
Page No.: Page 44 of 61
APPENDIX B
PHOTOGRAPHS OF EQUIPMENT
1. Dredger
2. Tug Boat
3. Pilot Boat
4. Any other
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435H
Page No.: Page 45 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435H
Page No.: Page 46 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435H
Page No.: Page 47 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435H
Page No.: Page 48 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435H
Page No.: Page 49 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435H
Page No.: Page 50 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435H
Page No.: Page 51 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435H
Page No.: Page 52 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435H
Page No.: Page 53 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435H
Page No.: Page 54 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435H
Page No.: Page 55 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435H
Page No.: Page 56 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435H
Page No.: Page 57 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435H
Page No.: Page 58 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435H
Page No.: Page 59 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435H
Page No.: Page 60 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435H
Page No.: Page 61 of 61
DREDGING WORKS AND CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR
METHOD STATEMENTFOR
DREDGING AND RECLAMATION WORKS
Issued by:Rawabi Specialized
Contracting Company Ltd.
Date: Ramadan 1435H
Page No.: Page 62 of 61