6 steps from project scope to schedule

Post on 25-Dec-2014

278 Views

Category:

Business

0 Downloads

Preview:

Click to see full reader

DESCRIPTION

Project managers are often looking for accelerators to improve project delivery and lessen the administrative burden. MindGenius solves this problem by providing an easy transition from project scope to an actionable project schedule in 6 easy steps.

TRANSCRIPT

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

6 Steps from Project Scope to Schedule with MindGenius by Andrew Makar

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

Process of translating project scope into an actionable task can be a tedious one

MindGenius solves this problem in 6 easy steps

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

MindGenius takes results of brainstorming session and helps you organize thoughts and ideas

Step 1. Brainstorm the project scope 

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

Fig. 1 Brainstorm Project Scope

In Figure 1, MindGenius was used to collect and organize project requirements

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

Use a Work Breakdown Structure (WBS) to define the scope

In MindGenius, Select Home - Map Layouts and select the affinity map layout to change the map layout (Figure 2)

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

Fig. 2 WBS

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

Assign dependencies between the tasks in the Work Breakdown Structure.

Select Tasks - Gantt View from the MindGenius navigation bar

In the Predecessors column, enter the task number of the preceding tasks which will adjust the Gantt chart (Figure 3).

Step 2. Assign task dependencies in the Gantt Chart view

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

Fig. 3 Gantt Chart Sequencing

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

Tasks can be added, removed and moved throughout the task outline

Any change to the tasks in this view will also be reflected in the mind map view

This means project managers can choose the view that makes the most sense for the job

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

The next step is to estimate the duration of the tasks

Clicking on a task will allow the user to adjust task parameters i.e. start dates, finish dates, milestones and costs.

Step 3. Estimate task duration 

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

Fig. 4 Duration Estimation

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

Define project team and assign them to specific tasks.

Double click on the Resource column and select Edit Resource List.

Step 4. Assign resources to tasks 

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

Fig. 5 Define the project team

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

Team members can be assigned to a specific task by clicking on the check box (Figure 6)

Track specific work and team member progress

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

Fig. 6 Assign team members to tasks

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

Fig. 7 Assign Resources in Gantt View

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

Project manager can switch back to the mind map view (Figure 8)

Fig. 8 Resource Assignment Map View

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

By selecting the Task - Create Resource Map button, tasks will be organised by resource

Navigate and filter map by resource using the Map Explorer

Step 5. Create a Resource Map and filter for Resource Assignments 

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

Fig. 9 Resource Map

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

Small project – MindGenius can manage schedule

Larger project - entire mind map can be exported to Microsoft Project.

Milestones, start, finish dates, resources and costs will all easily export to the Microsoft Project schedule.

Step 6. Export to Microsoft Project for detailed schedule development (optional) 

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

In 6 easy steps, project managers can define project scope and generate a meaningful project schedule within a single tool.

Fig. 10 MS Project Export

All rights reserved worldwide. Copyright © 2013 MindGenius Ltd.

For a free 30 day trial, visit www.mindgenius.com