hand sketch, re instate of work, grounding, foundation
TRANSCRIPT
-
Location : Wasit SS # 200 (Pit for equipment foundations for Line - A)
Disconnected cable Permanent cable Temporary cable
4-Way Exothermic weld joint Straight - Exothermic weld joint
Necessary modifications in existing ground mat for excavation & equipment foundation placement
Project : REPLACE POWER SUPPLY AT ABU ALI PLANTS
Phase - 1
Phase - 2