american electric power’s
TRANSCRIPT
American Electric Power’s
Approach to New Generation Needs
October 30, 2007
AEP: An Introduction
WindHydroNuclearNGCoal
1%310MW
2%870MW
8%2,200MW
16%6,800MW
73%25,600MW
AEP Facts at a Glance
Largest U.S. Electricity Generator and coal user
1. 5 Million Customers2. 11 States (7-East & 4-West)3. 36,000 MW Generation4. 75-80 MM tons of coal per year5. 39,000 Miles Transmission6. 210,000 Miles Distribution 7. 20,000 Employees8. US$ 12.6 Billion Revenue9. US$ 38 Billion in Assets
AEP Needs New Capacity
AEP needs newbaseload generating capacityin our eastern region by 2010,and western region by 2011
AEP has not added base load capacity since 1991
6,0006,000
4,0004,000
2,0002,000
00
Cap
acity
Def
icie
ncy
(MW
)
(1,000)(1,000)20052005 20072007 20092009 20112011 20132013
Eastern Retirements
Eastern W/O Retirements
Western (PSO & SWEPCO)
AEP’s Portfolio Approach to New Generation Additions
• Proposing two 600MW IGCC projects – Ohio and West Virginia
• Proposing two 600 MW ultrasupercritical PC units – Oklahoma and Arkansas
• Purchasing over 1100 MW in existing gas assets• Installing 640 MW in gas fired peaking units –
Oklahoma and Arkansas• Installing 500 MW gas fired combined cycle unit
– Louisiana• Purchasing over 1000 MW in wind energy (275
MW PPA in place)
Strategies to Meet Generation Needs
• Use technologies to provide for future GHG capture – facilities designed to incorporate future CCS
• Employ most efficient technologies to minimize GHG and other emissions
• Maintain a diversified approach – There is no one right answer
COALCOALAEP’s commitment to coal has been a basic element
of our generation strategy
We know coal It’s abundant, available and affordableIt’s important to the states we serveIt’s important to our nation
Coal Is Fundamental
U.S. Coal Capacity Additions
0123456789
1011121314151617181920
1940 1945 1950 1955 1960 1965 1970 1975 1980 1985 1990 1995 2000 2005 2010 2015 2020 2025
Source: U.S. Department of Energy NETL & Annual Energy Outlook 2005.
Cap
acity
Add
ed (G
Ws)
U.S. Coal Capacity Additions, 1940 U.S. Coal Capacity Additions, 1940 –– 20252025
20 YearMarket Trough
Industry Growth Trend Not Seen in
50 Years
Capacity Addition Levels Not Seen
in 40 Years
AEP’s Current Approach
• Integrated Gasification Combined Cycle (IGCC) for eastern applications– The best choice for the future in a carbon constrained
world– Based on the combination of an applicable
technology and an acceptable commercial deal• Ultra-Supercritical Pulverized Coal (USPC)
– Highest efficiency “conventional” coal application – Based on the lack of an acceptable IGCC solution for
western coal
Integrated Gasification Combined Cycle (IGCC)
AEP East
Generating Technology Options: Integrated Gasification Combined Cycle (IGCC) Plants
IGCC’s Promise
• Best emission characteristics among coal-based technologies– Greater potential to meet future emission requirements
• Most CO2 Capture-friendly coal technology• The technology of choice for bituminous coals
– Strategically important to the energy security and economies of many states and the U.S.
• Most efficient coal-based technology (when mature)• Feedstock & product flexibility (with added cost)
– Coal, petcoke, or biomass feedstocks– Electricity, steam, syngas, liquid fuels, or chemical products
Primary Sites
Mountaineer IGCC Plant
Coal Storage Area
Cooling Tower
Flare
Power Block
Coal Prep
Gasification
Coal Unloading Area
ASU
Gas Cleanup
Phased Approach to Project Development
• Minimize Project Risk Through a Staged Approach (increasing levels of definition)– Feasibility Study– Front End Engineering and Design– Engineering, Procurement and
Construction– Commercial Operation
AEP Functional Requirements
• Broad Fuel Supply– Central/Northern Appalachian– Illinois Basin– Pet Coke Blending
• Turndown– Must operate as a part of an electrical
power system• Competitive Thermal Performance• Meet air emission and water effluent
limits throughout operating regime
Regulatory Overview - Ohio
• Application made to Ohio Power Siting Board (OPSB) for Certificate of Convenience and Necessity – March 2006
– Certificate granted March 2007
Regulatory Overview - Ohio
• Filed for IGCC Rate Recovery – March 2005– Three-Phase Approach
• Direct recovery of development costs as expended (approved by OH PUCO in April 2006)
• Inclusion of Construction Work in Progress during EPC phase
• Recovery of direct costs post-COD with a return on our investment
• Phase one recovery appealed to Ohio Supreme Court– Oral arguments October 2007– Decision expected March 2008
Regulatory Overview –West Virginia/Virginia
• Certificate of Public Convenience and Necessity filed with West Virginia PSC – January 2006– Supplemental information package filed May
2006– Final testimony filed July 2007– Hearings scheduled December 2007– Order expected March 2008
• Rate Adjustment Filing made with Virginia SCCJuly 2007– Order expected April 2008
Permitting Activities
• Air Permitting
– Extensive modeling conducted for both Ohio and West Virginia for all phases of operation including startup/shutdown and steady state
– Applications filed in both states October 2, 2006
Permitting Activities
• US Corps of Engineers permit application for Ohio submitted May 2006
• Landfill permit for Ohio to be submitted later this year
• NPDES (wastewater) permit applications to be submitted to fit state regulatory schedules
Ultra-Supercritical (USPC) Pulverized Coal
AEP West
Higher Pressure/Temperature –Better Plant Efficiency
• Sub-Critical Boiler designs – Water boiling to steam with pressures < ‘critical point’
• Super-critical steam cycles – Water to steam without boiling. Pressure > 3208psi
• Critical Point – 3208psi/705°F• Ultra-Supercritical steam cycle – Steam
temperatures > 1100°F as defined by EPRI
History of Super-Critical Units
• First super-critical (SC) unit – AEP Philo Unit 6. COD – 1956; 125 MW with steam conditions of 4500psi/1150°F/1050°F/1000°F double-reheat
• Largest SC units – AEP 1300 MW series• World-wide population – Over 200 units• Typical steam pressures – 3350 to 4200 psi• Typical steam temps – 1000 to 1050°F
Why USPC?
• Best efficiency of direct combustion applications– Least fuel consumed– Lowest emissions, including carbon dioxide
• Acceptable IGCC technical solutions exist– But not in combination with commercial
solution
IGCC / USPC / SPC / Sub-Critical PC Efficiency Comparison
CO2 Emissions varywith Heat Rate & Coal Rank
0.85
0.90
0.95
1.00
1.05
1.10
8500 9000 9500 10000 10500
Net Unit Heat Rate (Full Load), Btu/kwh
CO
2 Em
issi
ons,
Ton
s/M
WH
Bituminous
Sub Bituminous
Lignite
Figures for Supercritical and Subcritical are for existing units w /environmental control retrof its.
Recent Ultra-Supercritical Units World-wide
Power PlantElectric Power
CompanyRated Output
(MW)MS Pressure
(psi) Steam Temp (F) CommissioningUS:Eddystone 1 Philadelphia Electric Co 325 4700 1120/1050/1050 1959
Japan:Noshino 2 Tohoko 600 3495 1050/1100 1994Haranomaci #1 Tohoko 100 3553 1050/1100 1997Matsuura #2 EPDC 100 3495 1100/1100 1997Nanoa-Ohta #2 Hokuriku 740 3495 1100/1100 1998Haranomaci #2 Tohoko 1000 3553 1112/1112 1998Misumi #1 Tongoho 1000 3553 1112/1112 1998Tachibana-wan Kyushyu 700 3495 1050/1100 2000Tachibana-wan #1 EPDC 1050 3626 1112/1130 2000Tsuruga #2 Hokuriku 700 3495 1100/1100 2000Reihoku #2 Kyushyu 700 3495 1100/1100 2000Tachibana-wan #2 EPDC 1050 3626 1112/1130 2001Hatachinaka 1 Tokyo Electric 1000 3553 1112/1112 2002Isogo 1 EPDC 1050 3626 1112/1130 2002Maizuni 1 Kansai 900 3495 1100/1100 2003Maizuni 2 Kansai 900 3495 1100/1100 2003
Europe:Avedore - 530 4350 1076/1112 2000Niederaussem - 1000 4061 1076/1112 2003
Low NOx Burners
Typical USC Arrangement (PRB Fuel)
Activated Carbon Injection
AEP’s Ultra-Supercritical Proposals
• Red Rock - 600 MW plant fueled by PRB in OK– Managed by OG&E, OMPA as minority partner– Located at OG&E’s Sooner Station– COD 2012
• John W. Turk – 600 MW plant fueled by PRB in SW Arkansas– Several likely minority partners– Greenfield, located in Hempstead County– COD 2011
Regulatory Status - Oklahoma
• Application filed with OCC Jan 2007• Air permit filed with ODEQ Dec 2006
• OCC issued order denying application October 11, 2007– Found need for capacity in 2012– Did not demonstrate that Red Rock was the
most reasonable alternative
Regulatory Status - Arkansas
• Application with APSC Dec 2006– Final arguments 10/22/2007– Order expected by year end
• Air permit application made with ADEQ Aug 2006– Air permit expected February 2008
Conclusions
• AEP committed to IGCC for Ohio/West Virginia– Regulatory filings made– Permitting progressing– Transmission Interconnection progressing
• AEP must have a degree of regulatory certainty in order to proceed
Conclusions• AEP solutions for western jurisdictions and fuels
not the same– Technologies are available– Missing commercial deal - guarantees
• Price • Schedule• Performance
• Absent such commercial assurances and until utility IGCC is more mature, AEP intends to use most efficient pulverized coal application available - USPC