airport master plan update ad

Upload: anon660454306

Post on 07-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 Airport Master Plan Update aD

    1/14

    APPENDIX D

    AIRPORT DEVELOPMENT COST

    ESTIMATE WORKSHEETS

  • 8/6/2019 Airport Master Plan Update aD

    2/14

    Project Description Local Cost FAA Cost Total Cost

    Phase 1 (0-5 Years)Airside Improvements

    1A. SHORTEN RUNWAY 7-25 (3,700' X 60') & CONSTRUCT CONNECTING TAXIWAY TO RUNWAY 25 $49,100 $442,000 $491,000

    1B. OVERLAY RUNWAY 7-25 (3,700 X 60')(4105' Total Length) $48,902 $439,922 $488,824

    Subtotal $98,002 $881,922 $979,824

    2. SEAL RUNWAY 11-29 SHOULDER PAVEMENT (4,300' X 75') $196,116 $0 $196,116

    Airside Improvements Subtotal $294,118 $881,922 $1,175,940

    Landside Improvements

    5. RECONSTRUCT APRON A-3 N/S TAXILANES $23,998 $215,984 $239,983

    6. SEAL APRON A-3 E/W TAXILANE $3,647 $33,126 $36,874

    7A. RECONSTRUCT APRON A-1 (200' X 80' Wash DNR HELIPAD AREA) $13,581 $122,429 $136,010

    7B. REHABILITATE CONCRETE APRON A-2 (1,435' X 250') $6,375 $57,075 $63,450

    7C. SEAL APRON A-3 (1,030' X 300') $11,180 $101,020 $112,300

    7D. REHABILITATE MIDSTATE AVIATION CONCRETE APRON/RAMP $3,375 $30,075 $33,450

    Subtotal $34,511 $310,599 $345,2108. CONSTRUCT T-HANGAR (12,500 S.F.) $347,300 $0 $347,300

    9. CONSTRUCT 2 COMMON CLEAR-SPAN HANGARS $281,300 $0 $281,300

    Landside Improvements Subtotal $690,757 $559,710 $1,250,666

    Other Capital Expansion/Development

    10. INSTALL AIRPORT ROADWAY INDENTIFICATION/ DIRECTIONAL SIGNAGE $600 $5,600 $6,300

    Other Capital Expansion/Development Subtotal $600 $5,600 $6,300

    Phase 1 Total $985,475 $1,447,231 $2,432,906

    Phase 2 (5-10 Years)

    Airside Improvements

    1. SEAL RUNWAY 7-25 (3,700' X 60') $16,500 $148,800 $165,300

    2. SEAL TAXIWAYS A, B, C, D, F, AND RUNWAY 25 ENTRANCE TAXIWAY $19,444 $174,899 $194,344

    3A. EXTEND RUNWAY 11-29 (4,600' X 75') $98,330 $884,570 $982,9003B. CONSTRUCT ENTRANCE TAXIWAY TO RUNWAY 29 $23,085 $207,961 $231,045

    Subtotal $121,415 $1,092,531 $1,213,945

    4. CONSTRUCT NORTH PARTIAL PARALLEL TAXIWAY TO RUNWAY 11-29 $88,965 $800,585 $889,550

    Airside Improvements Subtotal $246,324 $2,216,815 $2,463,139

    Landside Improvements

    5. SEAL APRON A-3 N/S TAXILANES $2,812 $24,910 $27,623

    6. SEAL APRON A-3 E/W TAXILANE $3,647 $33,126 $36,874

    7A. SEAL APRON A-1 (200' X 80' Wash DNR HELIPAD AREA) $2,466 $22,094 $24,560

    7B. SEAL APRON A-3 (1,030' X 300') $3,647 $33,126 $36,874

    Subtotal $6,113 $55,220 $61,434

    8A. CONSTRUCT COMMON CLEAR-SPAN HANGAR $143,800 $0 $143,800

    8B. CONSTRUCT AUTO PARKING AREA $156,540 $0 $156,540

    Subtotal $300,340 $0 $300,340

    Landside Improvements Subtotal $312,913 $113,257 $426,270

    Other Capital Expansion/Development

    9. INSTALL SECURITY/ WILDLIFE PERIMETER FENCE $48,601 $437,609 $486,310

    Other Capital Expansion/Development Subtotal $48,601 $437,609 $486,310

    Phase 2 Total $2,767,681 $3,375,719

    Project Cost

    ESTIMATED PROJECT COSTS AND FUNDING

    BOWERS FIELD AIRPORT - PHASED DEVELOPMENT PLAN

    SUMMARY

  • 8/6/2019 Airport Master Plan Update aD

    3/14

    Project Description Local Cost FAA Cost Total Cost

    Project Cost

    ESTIMATED PROJECT COSTS AND FUNDING

    BOWERS FIELD AIRPORT - PHASED DEVELOPMENT PLAN

    SUMMARY

    Phase 3 (10-15 Years)

    Airside Improvements

    1. OVERLAY RUNWAY 11-29 (4,600' X 75') $63,000 $566,900 $629,900

    2. INSTALL MALSF TO RUNWAY 29 $25,000 $225,000 $250,000

    3. SEAL RUNWAY 7-25 (3,700' x 60') $17,870 $160,530 $178,400

    4. CONSTRUCT SOUTH PARTIAL PARALLEL TAXIWAY TO RUNWAY 11-29 $59,885 $538,665 $598,550

    5A. SEAL TAXIWAYS A, B, C, D, F, AND RUNWAY 25 ENTRANCE TAXIWAY $19,444 $174,899 $194,344

    5B. SEAL NORTH PARTIAL PARALLEL TAXIWAY TO RUNWAY 11-29 $4,910 $43,990 $48,900

    Subtotal $24,354 $218,889 $243,244

    Airside Improvements Subtotal $190,109 $1,709,984 $1,900,094

    Landside Improvements

    6. SEAL APRON A-3 N/S TAXILANES $2,812 $24,910 $27,623

    7. SEAL APRON A-3 E/W TAXILANE $3,647 $33,126 $36,874

    8A. OVERLAY APRON A-1 (200' X 80' Wash DNR HELIPAD AREA) $7,036 $63,424 $70,4608B. OVERLAY APRON A-2 (1,435' X 250') $54,579 $491,411 $545,990

    8C. OVERLAY APRON A-3 (1,030' X 300') $37,463 $337,067 $374,530

    8D. OVERLAY MIDSTATE AVIATION APRON/RAMP $9,591 $86,519 $96,110

    Subtotal $108,669 $978,421 $1,087,090

    9. CONSTRUCT T-HANGAR (12,500 S.F.) $347,300 $0 $347,300

    10. CONSTRUCT COMMON CLEAR-SPAN HANGAR $143,800 $0 $143,800

    11A. CONSTRUCT AIRPORT PASSENGER TERMINAL BUILDING $458,800 $0 $458,800

    11B. CONSTRUCT AIRPORT MAINTENANCE BUILDING $92,500 $0 $92,500

    11C. CONSTRUCT AUTO PARKING AREA $110,860 $0 $110,860

    Subtotal $662,160 $0 $662,160

    Landside Improvements Subtotal $1,268,389 $1,036,458 $2,304,846

    Phase 3 Total $1,458,498 $2,746,442 $4,204,940

    Bowers Field Airport Phased Development Total Cost Estimates (0-20 years) $2,443,973 $6,961,354 $10,013,565

  • 8/6/2019 Airport Master Plan Update aD

    4/14

    Unit Local FAA Total CostProject Description Unit Quantity Cost Cost Cost (100%)

    AIRSIDE IMPROVEMENTS

    1A. SHORTEN RUNWAY 7-25 (3,700' X 60') & CONSTRUCT CONNECTING TAXIWAY TO RUNWAY 25

    Mobilization L.S. 1 $35,000.00 $3,500 $31,500 $35,000

    Temporary Marking, Lighting and Barricades L.S. 1 $10,000.00 $1,000 $9,000 $10,000

    Pavement Marking Removal S.F. 15,000 $1.00 $1,500 $13,500 $15,000

    Pavement Removal S.Y. 770 $4.00 $308 $2,772 $3,080

    Joint and Crack Repair L.F. 14,800 $2.00 $2,960 $26,640 $29,600

    Full Depth Pavement Repair S.Y. 1,670 $8.00 $1,336 $12,024 $13,360

    Removal of Existing Lighting System L.S. 1 $10,000.00 $1,000 $9,000 $10,000

    Earthwork C.Y. 10,000 $2.50 $2,500 $22,500 $25,000

    Subgrade Stabilizing Geotextile S.Y. 1,870 $2.00 $374 $3,366 $3,740

    7" Crushed Aggregate Base Course S.Y. 1,870 $7.00 $1,309 $11,781 $13,090

    Bituminous Surface Course (3") Ton 330 $75.00 $2,475 $22,275 $24,750

    Bituminous Prime Coat Gal. 935 $2.00 $187 $1,683 $1,870

    Bituminous Tack Coat Gal. 190 $2.00 $38 $342 $380

    Pavement Marking S.F. 35,000 $0.75 $2,625 $23,625 $26,250Erosion Control, Seeding & Marking L.S. 1 $10,000.00 $1,000 $9,000 $10,000

    15 kW Constant Current Regulator Each 1 $8,000.00 $800 $7,200 $8,000

    Modifications to Vault and Controls L.S. 1 $10,000.00 $1,000 $9,000 $10,000

    2-4" PVC Concrete Encased Electrical Duct L.F. 90 $20.00 $180 $1,620 $1,800

    3" Rigid Steel Duct (Direct Bore) L.F. 170 $10.00 $170 $1,530 $1,700

    Electrical Cable and Trench (in Pavement) L.F. 9,400 $6.00 $5,640 $50,760 $56,400

    Electrical Cable and Trench L.F. 9,600 $2.50 $2,400 $21,600 $24,000

    Runway Edge Lights (MIRL) (in Pavement) Each 46 $600.00 $2,760 $24,840 $27,600

    Taxiway Edge Lights (MITL) (in Pavement) Each 16 $600.00 $960 $8,640 $9,600

    Retro-Reflector Each 15 $75.00 $113 $1,013 $1,125

    Non-Lighted Guidance Sign Each 1 $1,500.00 $150 $1,350 $1,500

    PAPI System (2 Box) Each 2 $10,000.00 $2,000 $18,000 $20,000

    REIL System Each 2 $12,500.00 $2,500 $22,500 $25,000

    Miscellaneous Construction Costs L.S. 1 $20,000.00 $2,000 $18,000 $20,000

    Construction Cost $39,285 $353,561 $392,845

    Engineering, Administrative & Legal Costs (25%) $9,800 $88,400 $98,200

    Subtotal - Shorten Runway 7-25 $49,100 $442,000 $491,000

    1B. OVERLAY RUNWAY 7-25 (3,700 X 60')(4105' Total Length)

    Mobilization L.S. 1 $50,000.00 $5,000 $45,000 $50,000

    Cold Milling S.Y. 3,156 $4.00 $1,262 $11,362 $12,624

    Bituminous Surface Course Ton 6,030 $50.00 $30,150 $271,350 $301,500

    Bituminous Tack Coat Gal. 3,450 $2.00 $690 $6,210 $6,900

    Miscellaneous Construction Costs L.S. 1 $20,000.00 $2,000 $18,000 $20,000

    Construction Cost $39,102 $351,922 $391,024

    Engineering, Administrative & Legal Costs (25%) $9,800 $88,000 $97,800

    Subtotal -Overlay Runway 7-25 $48,902 $439,922 $488,824

    2. SEAL RUNWAY 11-29 SHOULDER PAVEMENT (4,300' X 75')

    Mobilization L.S. 1 $16,000.00 $16,000 $0 $16,000

    Temporary Marking, Lighting and Barricades L.S. 1 $10,000.00 $10,000 $0 $10,000

    Pavement Marking Removal S.F. 15,000 $1.00 $15,000 $0 $15,000

    Joint and Crack Repair L.F. 12,500 $2.00 $25,000 $0 $25,000

    Slurry Seal S.Y. 35,833 $2.00 $71,666 $0 $71,666

    Pavement Marking S.F. 15,000 $0.75 $11,250 $0 $11,250

    Miscellaneous Construction Costs L.S. 1 $8,000.00 $8,000 $0 $8,000

    Construction Cost $156,916 $0 $156,916

    Contingency Engineering, Legal, & Administrative Costs (25%) $39,200 $0 $39,200

    Subtotal - Seal Runway 11-29 Shoulder Pavement $196,116 $0 $196,116

    ESTIMATED PROJECT COSTS AND FUNDING

    BOWERS FIELD AIRPORT - PHASED DEVELOPMENT PLAN

    PHASE 1 (0-5 YEARS)

    K:\2000-312\Amp\AMP-calc\cost estimates\cost.xls 6/3/2004 Page 1

  • 8/6/2019 Airport Master Plan Update aD

    5/14

    Unit Local FAA Total Cost

    Project Description Unit Quantity Cost Cost Cost (100%)

    ESTIMATED PROJECT COSTS AND FUNDING

    BOWERS FIELD AIRPORT - PHASED DEVELOPMENT PLAN

    PHASE 1 (0-5 YEARS)

    LANDSIDE IMPROVEMENTS

    5. RECONSTRUCT APRON A-3 N/S TAXILANES

    Mobilization L.S. 1 $18,000.00 $1,800 $16,200 $18,000

    Temporary Marking, Lighting and Barricades L.S. 1 $5,000.00 $500 $4,500 $5,000

    Pavement Removal S.Y. 7,600 $4.00 $3,040 $27,360 $30,400

    Subgrade Stabilizing Geotextile S.Y. 5,230 $2.00 $1,046 $9,414 $10,460

    7" Crushed Aggregate Base Course S.Y. 5,230 $7.00 $3,661 $32,949 $36,610

    Bituminous Surface Course (3") Ton 920 $75.00 $6,900 $62,100 $69,000

    Bituminous Prime Coat Gal. 2,620 $2.00 $524 $4,716 $5,240

    Bituminous Tack Coat Gal. 530 $2.00 $106 $954 $1,060

    Pavement Marking S.F. 550 $0.75 $41 $371 $413

    Erosion Control, Seeding & Marking L.S. 1 $5,000.00 $500 $4,500 $5,000

    Retro-Reflector Each 24 $75.00 $180 $1,620 $1,800

    Miscellaneous Construction Costs L.S. 1 $9,000.00 $900 $8,100 $9,000

    Construction Cost $19,198 $172,784 $191,983

    Contingency Engineering, Legal, & Administrative Costs (25%) $4,800 $43,200 $48,000

    Subtotal - Reconstruct Apron A-3 N/S Taxilanes $23,998 $215,984 $239,983

    6. SEAL APRON A-3 E/W TAXILANE

    Mobilization L.S. 1 $5,000.00 $500 $4,500 $5,000

    Temporary Marking, Lighting and Barricades L.S. 1 $1,000.00 $100 $900 $1,000

    Pavement Marking Removal S.F. 485 $1.00 $49 $437 $485

    Joint and Crack Repair L.F. 2,910 $2.00 $582 $5,238 $5,820

    Slurry Seal S.Y. 6,425 $2.00 $1,285 $11,565 $12,850

    Pavement Marking S.F. 2,425 $0.75 $182 $1,637 $1,819

    Miscellaneous Construction Costs L.S. 1 $2,500.00 $250 $2,250 $2,500

    Construction Cost $2,947 $26,526 $29,474

    Contingency Engineering, Legal, & Administrative Costs (25%) $700 $6,600 $7,400

    Subtotal - Seal Apron A-3 E/W Taxilane $3,647 $33,126 $36,874

    7A. RECONSTRUCT APRON A-1 (200' X 80' Wash DNR HELIPAD AREA)

    Mobilization L.S. 1 $10,000.00 $1,000 $9,000 $10,000Temporary Marking, Lighting and Barricades L.S. 1 $1,000.00 $100 $900 $1,000

    Pavement Removal S.Y. 3,330 $4.00 $1,332 $11,988 $13,320

    Subgrade Stabilizing Geotextile S.Y. 3,330 $2.00 $666 $5,994 $6,660

    7" Crushed Aggregate Base Course S.Y. 3,330 $7.00 $2,331 $20,979 $23,310

    Bituminous Surface Course (3") Ton 580 $75.00 $4,350 $39,150 $43,500

    Bituminous Prime Coat Gal. 1,670 $2.00 $334 $3,006 $3,340

    Bituminous Tack Coat Gal. 340 $2.00 $68 $612 $680

    Pavement Marking L.S. 1 $1,000.00 $100 $900 $1,000

    Erosion Control, Seeding & Marking L.S. 1 $1,000.00 $100 $900 $1,000

    Miscellaneous Construction Costs L.S. 1 $5,000.00 $500 $4,500 $5,000

    Construction Cost $10,881 $97,929 $108,810

    Contingency Engineering, Legal, & Administrative Costs (25%) $2,700 $24,500 $27,200

    Subtotal - Reconstruct Wash DNR Helipad Area $13,581 $122,429 $136,010

    7B. REHABILITATE CONCRETE APRON A-2 (1,435' X 250')

    Mobilization L.S. 1 $5,000.00 $500 $4,500 $5,000

    Temporary Marking, Lighting and Barricades L.S. 1 $1,000.00 $100 $900 $1,000Pavement Marking Removal S.F. 3,000 $1.00 $300 $2,700 $3,000

    Joint and Crack Clean and Seal L.F. 21,600 $1.25 $2,700 $24,300 $27,000

    Full Depth Concrete Repair S.Y. 200 $50.00 $1,000 $9,000 $10,000

    Pavement Marking S.F. 3,000 $0.75 $225 $2,025 $2,250

    Miscellaneous Construction Costs L.S. 1 $2,500.00 $250 $2,250 $2,500

    Construction Cost $5,075 $45,675 $50,750

    Contingency Engineering, Legal, & Administrative Costs (25%) $1,300 $11,400 $12,700

    Subtotal - Rehabilitate Concrete Apron A-2) $6,375 $57,075 $63,450

    K:\2000-312\Amp\AMP-calc\cost estimates\cost.xls 6/3/2004 Page 2

  • 8/6/2019 Airport Master Plan Update aD

    6/14

    Unit Local FAA Total Cost

    Project Description Unit Quantity Cost Cost Cost (100%)

    ESTIMATED PROJECT COSTS AND FUNDING

    BOWERS FIELD AIRPORT - PHASED DEVELOPMENT PLAN

    PHASE 1 (0-5 YEARS)

    7C. SEAL APRON A-3 (1,030' X 300')

    Mobilization L.S. 1 $10,000.00 $1,000 $9,000 $10,000

    Temporary Marking, Lighting and Barricades L.S. 1 $2,000.00 $200 $1,800 $2,000

    Pavement Marking Removal S.F. 3,000 $1.00 $300 $2,700 $3,000

    Joint and Crack Repair L.F. 8,000 $2.00 $1,600 $14,400 $16,000

    Slurry Seal S.Y. 24,400 $2.00 $4,880 $43,920 $48,800

    Coal Tar Emulsion Seal Coat S.Y. 550 $5.00 $275 $2,475 $2,750

    Pavement Marking S.F. 3,000 $0.75 $225 $2,025 $2,250

    Miscellaneous Construction Costs L.S. 1 $5,000.00 $500 $4,500 $5,000

    Construction Cost $8,980 $80,820 $89,800

    Contingency Engineering, Legal, & Administrative Costs (25%) $2,200 $20,200 $22,500

    Subtotal - Fuel Resistant Seal Coat Airport Fueling Facility Pavement $11,180 $101,020 $112,300

    7D. REHABILITATE MIDSTATE AVIATION CONCRETE APRON/RAMP

    Mobilization L.S. 1 $5,000.00 $500 $4,500 $5,000

    Temporary Marking, Lighting and Barricades L.S. 1 $1,000.00 $100 $900 $1,000

    Pavement Marking Removal L.S. 1 $1,000.00 $100 $900 $1,000

    Joint and Crack Clean and Seal L.F. 3,000 $1.25 $375 $3,375 $3,750

    Full Depth Concrete Repair S.Y. 250 $50.00 $1,250 $11,250 $12,500

    Pavement Marking L.S. 1 $1,000.00 $100 $900 $1,000

    Miscellaneous Construction Costs L.S. 1 $2,500.00 $250 $2,250 $2,500

    Construction Cost $2,675 $24,075 $26,750

    Contingency Engineering, Legal, & Administrative Costs (25%) $700 $6,000 $6,700

    Subtotal - Rehabilitate Midstate Aviation Concrete Apron/Ramp $3,375 $30,075 $33,450

    8. CONSTRUCT T-HANGAR (12,500 S.F.)

    Mobilization L.S. 1 $5,000.00 $5,000 $0 $5,000

    Pavement Removal S.Y. 1700 $4.00 $6,800 $0 $6,800Construct Nested T-Hangar L.S. 1 $250,000.00 $250,000 $0 $250,000

    Utility Work L.S. 1 $5,000.00 $5,000 $0 $5,000

    Earthwork C.Y. 500 $10.00 $5,000 $0 $5,000

    Concrete Connections L.S. 1 $5,000.00 $5,000 $0 $5,000

    Miscellaneous Construction Costs L.S. 1 $1,000.00 $1,000 $0 $1,000

    Construction Cost $277,800 $0 $277,800

    Contingency Engineering, Legal, & Administrative Costs (25%) $69,500 $0 $69,500

    Subtotal - Construct T-Hangar $347,300 $0 $347,300

    9. CONSTRUCT 2 COMMON CLEAR-SPAN HANGARS

    Mobilization L.S. 1 $5,000.00 $5,000 $0 $5,000

    Hangar Demolition L.S. 1 $10,000.00 $10,000 $0 $10,000

    Construct 70' x 70' Common Hangar L.S. 2 $100,000.00 $200,000 $0 $200,000

    Utility Work L.S. 1 $5,000.00 $5,000 $0 $5,000

    Earthwork C.Y. 200 $10.00 $2,000 $0 $2,000Concrete Connections L.S. 1 $2,500.00 $2,500 $0 $2,500

    Erosion Control, Seeding and Mulching L.S. 1 $500.00 $500 $0 $500

    Construction Cost $225,000 $0 $225,000

    Contingency Engineering, Legal, & Administrative Costs (25%) $56,300 $0 $56,300

    Subtotal - Construct Common Clear-Span Hangar(s) $281,300 $0 $281,300

    K:\2000-312\Amp\AMP-calc\cost estimates\cost.xls 6/3/2004 Page 3

  • 8/6/2019 Airport Master Plan Update aD

    7/14

    Unit Local FAA Total Cost

    Project Description Unit Quantity Cost Cost Cost (100%)

    ESTIMATED PROJECT COSTS AND FUNDING

    BOWERS FIELD AIRPORT - PHASED DEVELOPMENT PLAN

    PHASE 1 (0-5 YEARS)

    OTHER CAPITAL EXPANSION/DEVELOPMENT

    10. INSTALL AIRPORT ROADWAY INDENTIFICATION/ DIRECTIONAL SIGNAGE

    Mobilization L.S. 1 $5,000.00 $500 $4,500 $5,000

    Construction Cost $500 $4,500 $5,000

    Contingency Engineering, Legal, & Administrative Costs (25%) $100 $1,100 $1,300

    Subtotal -Install Airport Inditification/Directional Signage $600 $5,600 $6,300

    K:\2000-312\Amp\AMP-calc\cost estimates\cost.xls 6/3/2004 Page 4

  • 8/6/2019 Airport Master Plan Update aD

    8/14

    Unit Local FAA Total Cost

    Project Description Unit Quantity Cost Cost Cost (100%)

    AIRSIDE IMPROVEMENTS

    1. SEAL RUNWAY 7-25 (3,700' X 60')

    Mobilization L.S. 1 $12,000.00 $1,200 $10,800 $12,000

    Temporary Marking, Lighting and Barricades L.S. 1 $5,000.00 $500 $4,500 $5,000

    Pavement Marking Removal S.F. 30,000 $1.00 $3,000 $27,000 $30,000

    Joint and Crack Repair L.F. 3,700 $2.00 $740 $6,660 $7,400

    Slurry Seal S.Y. 24,670 $2.00 $4,934 $44,406 $49,340

    Pavement Marking S.F. 30,000 $0.75 $2,250 $20,250 $22,500

    Miscellaneous Construction Costs L.S. 1 $6,000.00 $600 $5,400 $6,000

    Construction Cost $13,224 $119,016 $132,240

    Engineering, Administrative & Legal Costs (25%) $3,300 $29,800 $33,100

    Subtotal - Seal Runway 7-25 $16,500 $148,800 $165,300

    2. SEAL TAXIWAYS A, B, C, D, F, AND RUNWAY 25 ENTRANCE TAXIWAY

    Mobilization L.S. 1 $14,000.00 $1,400 $12,600 $14,000

    Temporary Marking, Lighting and Barricades L.S. 1 $5,000.00 $500 $4,500 $5,000

    Pavement Marking Removal S.F. 21,625 $1.00 $2,163 $19,463 $21,625

    Joint and Crack Repair L.F. 8,900 $2.00 $1,780 $16,020 $17,800

    Slurry Seal S.Y. 36,900 $2.00 $7,380 $66,420 $73,800

    Pavement Marking S.F. 21,625 $0.75 $1,622 $14,597 $16,219

    Miscellaneous Construction Costs L.S. 1 $7,000.00 $700 $6,300 $7,000

    Construction Cost $15,544 $139,899 $155,444

    Engineering, Administrative & Legal Costs (25%) $3,900 $35,000 $38,900

    Subtotal -Seal Taxiways A,B,C,D,B, and Runway 25 Entrance Taxiway $19,444 $174,899 $194,344

    3A. EXTEND RUNWAY 11-29 (4,600' X 75')

    Mobilization L.S. 1 $70,000.00 $7,000 $63,000 $70,000

    Temporary Marking, Lighting and Barricades L.S. 1 $10,000.00 $1,000 $9,000 $10,000

    Pavement Marking Removal S.F. 30,000 $1.00 $3,000 $27,000 $30,000Pavement Removal S.Y. 8,890 $4.00 $3,556 $32,004 $35,560

    Removal of Existing Lighting System L.S. 1 $10,000.00 $1,000 $9,000 $10,000

    Earthwork L.S. 1 $10,000.00 $1,000 $9,000 $10,000

    Subgrade Stabilizing Geotextile S.Y. 8,190 $2.00 $1,638 $14,742 $16,380

    4" Crushed Aggregate Base Course S.Y. 8,190 $4.00 $3,276 $29,484 $32,760

    PCCP (6") S.Y. 8,190 $35.00 $28,665 $257,985 $286,650

    Bituminous Surface Course Shouldering L.S. 1 $10,000.00 $1,000 $9,000 $10,000

    Pavement Marking S.F. 30,000 $0.75 $2,250 $20,250 $22,500

    Erosion Control, Seeding & Marking L.S. 1 $10,000.00 $1,000 $9,000 $10,000

    15 kW Constant Current Regulator Each 1 $8,000.00 $800 $7,200 $8,000

    Modifications to Vault and Controls L.S. 1 $10,000.00 $1,000 $9,000 $10,000

    3" Rigid Steel Duct (Direct Bore) L.F. 320 $10.00 $320 $2,880 $3,200

    Electrical Cable and Trench (in Pavement) L.F. 10,000 $6.00 $6,000 $54,000 $60,000

    Electrical Cable and Trench L.F. 19,500 $2.50 $4,875 $43,875 $48,750

    Runway Edge Lights (MIRL) (in Pavement) Each 56 $600.00 $3,360 $30,240 $33,600

    Taxiway Edge Lights (MITL) (in Pavement) Each 4 $600.00 $240 $2,160 $2,400

    Non-Lighted Guidance Sign Each 1 $1,500.00 $150 $1,350 $1,500

    PAPI System (4 Box) Each 2 $20,000.00 $4,000 $36,000 $40,000Miscellaneous Construction Costs L.S. 1 $35,000.00 $3,500 $31,500 $35,000

    Construction Cost $78,630 $707,670 $786,300

    Engineering, Administrative & Legal Costs (25%) $19,700 $176,900 $196,600

    Subtotal - Extend Runway 11-29 $98,330 $884,570 $982,900

    ESTIMATED PROJECT COSTS AND FUNDING

    BOWERS FIELD AIRPORT - PHASED DEVELOPMENT PLANPHASE 2 (6-10 YEARS)

    K:\2000-312\Amp\AMP-calc\cost estimates\cost.xls 6/3/2004 Page 1

  • 8/6/2019 Airport Master Plan Update aD

    9/14

    Unit Local FAA Total Cost

    Project Description Unit Quantity Cost Cost Cost (100%)

    ESTIMATED PROJECT COSTS AND FUNDING

    BOWERS FIELD AIRPORT - PHASED DEVELOPMENT PLAN

    PHASE 2 (6-10 YEARS)

    3B. CONSTRUCT ENTRANCE TAXIWAY TO RUNWAY 29

    Mobilization L.S. 1 $18,000.00 $1,800 $16,200 $18,000

    Temporary Marking, Lighting and Barricades L.S. 1 $5,000.00 $500 $4,500 $5,000

    Pavement Removal S.Y. 930 $4.00 $372 $3,348 $3,720

    Earthwork C.Y. 10,000 $2.50 $2,500 $22,500 $25,000

    Subgrade Stabilizing Geotextile S.Y. 2,750 $2.00 $550 $4,950 $5,500

    4" Crushed Aggregate Base Course S.Y. 2,750 $4.00 $1,100 $9,900 $11,000

    PCCP (6") S.Y. 2,750 $35.00 $9,625 $86,625 $96,250

    Pavement Marking L.S. 1 $1,000.00 $100 $900 $1,000

    Erosion Control, Seeding & Marking L.S. 1 $2,500.00 $250 $2,250 $2,500

    2-4" PVC Concrete Encased Electrical Duct L.F. 90 $20.00 $180 $1,620 $1,800

    Taxiway Edge Lights (MITL) (in Pavement) Each 4 $600.00 $240 $2,160 $2,400

    Retro-Reflector Each 29 $75.00 $218 $1,958 $2,175

    Non-Lighted Guidance Sign Each 1 $1,500.00 $150 $1,350 $1,500

    Miscellaneous Construction Costs L.S. 1 $9,000.00 $900 $8,100 $9,000

    Construction Cost $18,485 $166,361 $184,845

    Engineering, Administrative & Legal Costs (25%) $4,600 $41,600 $46,200

    Subtotal - Construct Entrance Taxiway to Runway 29 $23,085 $207,961 $231,045

    4. CONSTRUCT NORTH PARTIAL PARALLEL TAXIWAY TO RUNWAY 11-29

    Mobilization L.S. 1 $60,000.00 $6,000 $54,000 $60,000

    Temporary Marking, Lighting and Barricades L.S. 1 $5,000.00 $500 $4,500 $5,000

    Pavement Removal S.Y. 1,000 $4.00 $400 $3,600 $4,000

    Earthwork C.Y. 15,000 $2.50 $3,750 $33,750 $37,500

    Subgrade Stabilizing Geotextile S.Y. 12,300 $2.00 $2,460 $22,140 $24,600

    4" Crushed Aggregate Base Course S.Y. 12,300 $4.00 $4,920 $44,280 $49,200

    PCCP (6") S.Y. 12,300 $35.00 $43,050 $387,450 $430,500

    Pavement Marking L.F. 1,600 $0.75 $120 $1,080 $1,200

    Erosion Control, Seeding & Marking L.S. 1 $10,000.00 $1,000 $9,000 $10,000

    2-4" PVC Concrete Encased Electrical Duct L.F. 90 $20.00 $180 $1,620 $1,800

    Electrical Cable and Trench L.F. 7,500 $2.50 $1,875 $16,875 $18,750

    Taxiway Edge Lights (MITL) (in Pavement) Each 6 $600.00 $360 $3,240 $3,600

    Taxiway Edge Lights (MITL) Each 65 $500.00 $3,250 $29,250 $32,500

    Non-Lighted Guidance Sign Each 2 $1,500.00 $300 $2,700 $3,000

    Miscellaneous Construction Costs L.S. 1 $30,000.00 $3,000 $27,000 $30,000

    Construction Cost $71,165 $640,485 $711,650Contingency Engineering, Legal, & Administrative Costs (25%) $17,800 $160,100 $177,900

    Subtotal - Construct Parallel Taxiway to Runway 11-29 $88,965 $800,585 $889,550

    LANDSIDE IMPROVEMENTS

    5. SEAL APRON A-3 N/S TAXILANES

    Mobilization L.S. 1 $5,000.00 $500 $4,500 $5,000

    Temporary Marking, Lighting and Barricades L.S. 1 $1,000.00 $100 $900 $1,000

    Pavement Marking Removal S.F. 550 $1.00 $55 $495 $550

    Joint and Crack Repair L.F. 1,100 $2.00 $220 $1,980 $2,200

    Slurry Seal S.Y. 5,230 $2.00 $1,046 $9,414 $10,460

    Pavement Marking S.F. 550 $0.75 $41 $371 $413

    Miscellaneous Construction Costs L.S. 1 $2,500.00 $250 $2,250 $2,500

    Construction Cost $2,212 $19,910 $22,123

    Contingency Engineering, Legal, & Administrative Costs (25%) $600 $5,000 $5,500

    Subtotal - Seal Apron A-3 N/S Taxilanes $2,812 $24,910 $27,623

    6. SEAL APRON A-3 E/W TAXILANE

    Mobilization L.S. 1 $5,000.00 $500 $4,500 $5,000

    Temporary Marking, Lighting and Barricades L.S. 1 $1,000.00 $100 $900 $1,000

    Pavement Marking Removal S.F. 485 $1.00 $49 $437 $485

    Joint and Crack Repair L.F. 2,910 $2.00 $582 $5,238 $5,820

    Slurry Seal S.Y. 6,425 $2.00 $1,285 $11,565 $12,850

    Pavement Marking S.F. 2,425 $0.75 $182 $1,637 $1,819

    Miscellaneous Construction Costs L.S. 1 $2,500.00 $250 $2,250 $2,500

    Construction Cost $2,947 $26,526 $29,474

    Contingency Engineering, Legal, & Administrative Costs (25%) $700 $6,600 $7,400

    Subtotal - Seal Apron A-3 E/W Taxilane $3,647 $33,126 $36,874

    K:\2000-312\Amp\AMP-calc\cost estimates\cost.xls 6/3/2004 Page 2

  • 8/6/2019 Airport Master Plan Update aD

    10/14

    Unit Local FAA Total Cost

    Project Description Unit Quantity Cost Cost Cost (100%)

    ESTIMATED PROJECT COSTS AND FUNDING

    BOWERS FIELD AIRPORT - PHASED DEVELOPMENT PLAN

    PHASE 2 (6-10 YEARS)

    7A. SEAL APRON A-1 (200' X 80' Wash DNR HELIPAD AREA)

    Mobilization L.S. 1 $5,000.00 $500 $4,500 $5,000

    Temporary Marking, Lighting and Barricades L.S. 1 $1,000.00 $100 $900 $1,000

    Pavement Marking Removal L.S. 1 $1,500.00 $150 $1,350 $1,500

    Joint and Crack Repair L.F. 1,000 $2.00 $200 $1,800 $2,000

    Slurry Seal S.Y. 3,330 $2.00 $666 $5,994 $6,660

    Pavement Marking L.S. 1 $1,000.00 $100 $900 $1,000

    Miscellaneous Construction Costs L.S. 1 $2,500.00 $250 $2,250 $2,500

    Construction Cost $1,966 $17,694 $19,660

    Contingency Engineering, Legal, & Administrative Costs (25%) $500 $4,400 $4,900

    Subtotal - Seal Apron A-1 (Wash DNR Helipad Area) $2,466 $22,094 $24,560

    7B. SEAL APRON A-3 (1,030' X 300')

    Mobilization L.S. 1 $5,000.00 $500 $4,500 $5,000

    Temporary Marking, Lighting and Barricades L.S. 1 $1,000.00 $100 $900 $1,000

    Pavement Marking Removal S.F. 485 $1.00 $49 $437 $485

    Joint and Crack Repair L.F. 2,910 $2.00 $582 $5,238 $5,820

    Slurry Seal S.Y. 6,425 $2.00 $1,285 $11,565 $12,850

    Pavement Marking S.F. 2,425 $0.75 $182 $1,637 $1,819Miscellaneous Construction Costs L.S. 1 $2,500.00 $250 $2,250 $2,500

    Construction Cost $2,947 $26,526 $29,474

    Contingency Engineering, Legal, & Administrative Costs (25%) $700 $6,600 $7,400

    Subtotal - Seal Apron A-3 $3,647 $33,126 $36,874

    8A. CONSTRUCT COMMON CLEAR-SPAN HANGAR

    Mobilization L.S. 1 $5,000.00 $5,000 $0 $5,000

    Construct 70' x 70' Common Hangar L.S. 1 $100,000.00 $100,000 $0 $100,000

    Utility Work L.S. 1 $5,000.00 $5,000 $0 $5,000

    Earthwork C.Y. 200 $10.00 $2,000 $0 $2,000

    Concrete Connections L.S. 1 $2,500.00 $2,500 $0 $2,500

    Erosion Control, Seeding and Mulching L.S. 1 $500.00 $500 $0 $500

    Construction Cost $115,000 $0 $115,000

    Contingency Engineering, Legal, & Administrative Costs (25%) $28,800 $0 $28,800

    Subtotal - Construct Common Clear-Span Hangar $143,800 $0 $143,800

    8B. CONSTRUCT AUTO PARKING AREA

    Mobilization L.S. 1 $12,000.00 $12,000 $0 $12,000

    Earthwork L.S. 1 $10,000.00 $10,000 $0 $10,000

    4" Crushed Aggregate Base Course S.Y. 1,510 $4.00 $6,040 $0 $6,040

    Bituminous Surface Course (10") Ton 880 $75.00 $66,000 $0 $66,000

    Bituminous Prime Coat Gal. 750 $2.00 $1,500 $0 $1,500

    Bituminous Tack Coat Gal. 450 $2.00 $900 $0 $900

    PCC Curb L.F. 1100 $18.00 $19,800 $0 $19,800

    Pavement Marking L.S. 1 $1,000.00 $1,000 $0 $1,000

    Parking Barricades Each 5 $200.00 $1,000 $0 $1,000

    Erosion Control, Seeding and Mulching L.S. 1 $1,000.00 $1,000 $0 $1,000

    Miscellaneous Construction Costs L.S. 1 $6,000.00 $6,000 $0 $6,000

    Construction Cost $125,240 $0 $125,240

    Contingency Engineering, Legal, & Administrative Costs (25%) $31,300 $0 $31,300

    Subtotal - Construct Auto Parking Area $156,540 $0 $156,540

    9. INSTALL WILDLIFE PERIMETER FENCE

    Mobilization L.S. 1 $10.00 $1 $9 $10

    Clearing L.S. 1 $10,000.00 $1,000 $9,000 $10,000

    Fence (8' Chain Link) L.F. 23,500 $16.00 $37,600 $338,400 $376,000

    Access Gate Each 3 $1,000.00 $300 $2,700 $3,000

    Construction Cost $38,901 $350,109 $389,010

    Contingency Engineering, Legal, & Administrative Costs (25%) $9,700 $87,500 $97,300

    Subtotal - Install Wildlife Perimeter Fence $48,601 $437,609 $486,310

    K:\2000-312\Amp\AMP-calc\cost estimates\cost.xls 6/3/2004 Page 3

  • 8/6/2019 Airport Master Plan Update aD

    11/14

    Unit Local FAA Total Cost

    Project Description Unit Quantity Cost Cost Cost (100%)

    AIRSIDE IMPROVEMENTS

    1. OVERLAY RUNWAY 11-29 (4,600' X 75')

    Mobilization L.S. 1 $60,000.00 $6,000 $54,000 $60,000

    Temporary Marking, Lighting and Barricades L.S. 1 $10,000.00 $1,000 $9,000 $10,000

    Pavement Marking Removal S.F. 30,000 $1.00 $3,000 $27,000 $30,000

    Joint and Crack Repair L.F. 4,600 $2.00 $920 $8,280 $9,200

    Bituminous Surface Course (3") Ton 6,690 $50.00 $33,450 $301,050 $334,500

    Bituminous Tack Coat Gal. 3,840 $2.00 $768 $6,912 $7,680

    Pavement Marking S.F. 30,000 $0.75 $2,250 $20,250 $22,500

    Miscellaneous Construction Costs L.S. 1 $30,000.00 $3,000 $27,000 $30,000

    Construction Cost $50,388 $453,492 $503,880

    Engineering, Administrative & Legal Costs (25%) $12,600 $113,400 $126,000

    Subtotal - Overlay Runway 11-29 $63,000 $566,900 $629,900

    2. INSTALL MALSF TO RUNWAY 29

    MALSF System L.S. 1 $200,000.00 $20,000 $180,000 $200,000

    Construction Cost $20,000 $180,000 $200,000

    Engineering, Administrative & Legal Costs (25%) $5,000 $45,000 $50,000Subtotal - Install MALSF to Runway 29 $25,000 $225,000 $250,000

    3. SEAL RUNWAY 7-25 (3,700' x 60')

    Mobilization L.S. 1 $14,000.00 $1,400 $12,600 $14,000

    Temporary Marking, Lighting and Barricades L.S. 1 $5,000.00 $500 $4,500 $5,000

    Pavement Marking Removal S.F. 30,000 $1.00 $3,000 $27,000 $30,000

    Joint and Crack Repair L.F. 7,400 $2.00 $1,480 $13,320 $14,800

    Slurry Seal S.Y. 24,700 $2.00 $4,940 $44,460 $49,400

    Pavement Marking S.F. 30,000 $0.75 $2,250 $20,250 $22,500

    Miscellaneous Construction Costs L.S. 1 $7,000.00 $700 $6,300 $7,000

    Construction Cost $14,270 $128,430 $142,700

    Engineering, Administrative & Legal Costs (25%) $3,600 $32,100 $35,700

    Subtotal - Seal Runway 7-25 $17,870 $160,530 $178,400

    4. CONSTRUCT SOUTH PARTIAL PARALLEL TAXIWAY TO RUNWAY 11-29

    Mobilization L.S. 1 $40,000.00 $4,000 $36,000 $40,000

    Temporary Marking, Lighting and Barricades L.S. 1 $5,000.00 $500 $4,500 $5,000

    Pavement Removal S.Y. 1,000 $4.00 $400 $3,600 $4,000

    Earthwork C.Y. 15,000 $2.50 $3,750 $33,750 $37,500

    Subgrade Stabilizing Geotextile S.Y. 7,700 $2.00 $1,540 $13,860 $15,400

    4" Crushed Aggregate Base Course S.Y. 7,700 $4.00 $3,080 $27,720 $30,800

    PCCP (6") S.Y. 7,700 $35.00 $26,950 $242,550 $269,500

    Pavement Marking L.F. 1,000 $0.75 $75 $675 $750

    Erosion Control, Seeding & Marking L.S. 1 $10,000.00 $1,000 $9,000 $10,000

    2-4" PVC Concrete Encased Electrical Duct L.F. 90 $20.00 $180 $1,620 $1,800

    Electrical Cable and Trench L.F. 5,000 $2.50 $1,250 $11,250 $12,500

    Taxiway Edge Lights (MITL) (in Pavement) Each 6 $600.00 $360 $3,240 $3,600

    Taxiway Edge Lights (MITL) Each 50 $500.00 $2,500 $22,500 $25,000

    Non-Lighted Guidance Sign Each 2 $1,500.00 $300 $2,700 $3,000

    Miscellaneous Construction Costs L.S. 1 $20,000.00 $2,000 $18,000 $20,000

    Construction Cost $47,885 $430,965 $478,850

    Contingency Engineering, Legal, & Administrative Costs (25%) $12,000 $107,700 $119,700

    Subtotal - Construct South Partial Parallel Taxiway to Runway 11-29 $59,885 $538,665 $598,550

    5A. SEAL TAXIWAYS A, B, C, D, F, AND RUNWAY 25 ENTRANCE TAXIWAYMobilization L.S. 1 $14,000.00 $1,400 $12,600 $14,000

    Temporary Marking, Lighting and Barricades L.S. 1 $5,000.00 $500 $4,500 $5,000

    Pavement Marking Removal S.F. 21,625 $1.00 $2,163 $19,463 $21,625

    Joint and Crack Repair L.F. 8,900 $2.00 $1,780 $16,020 $17,800

    Slurry Seal S.Y. 36,900 $2.00 $7,380 $66,420 $73,800

    Pavement Marking S.F. 21,625 $0.75 $1,622 $14,597 $16,219

    Miscellaneous Construction Costs L.S. 1 $7,000.00 $700 $6,300 $7,000

    Construction Cost $15,544 $139,899 $155,444

    Engineering, Administrative & Legal Costs (25%) $3,900 $35,000 $38,900

    Subtotal -Seal Taxiways A,B,C,D,B, and Runway 25 Entrance Taxiway $19,444 $174,899 $194,344

    ESTIMATED PROJECT COSTS AND FUNDING

    BOWERS FIELD AIRPORT - PHASED DEVELOPMENT PLAN

    PHASE 3 (11-20 YEARS)

    K:\2000-312\Amp\AMP-calc\cost estimates\cost.xls 6/3/2004 Page 1

  • 8/6/2019 Airport Master Plan Update aD

    12/14

    Unit Local FAA Total Cost

    Project Description Unit Quantity Cost Cost Cost (100%)

    ESTIMATED PROJECT COSTS AND FUNDING

    BOWERS FIELD AIRPORT - PHASED DEVELOPMENT PLAN

    PHASE 3 (11-20 YEARS)

    5B. SEAL NORTH PARTIAL PARALLEL TAXIWAY TO RUNWAY 11-29

    Mobilization L.S. 1 $5,000.00 $500 $4,500 $5,000Temporary Marking, Lighting and Barricades L.S. 1 $1,000.00 $100 $900 $1,000

    Pavement Marking Removal S.F. 1,600 $1.00 $160 $1,440 $1,600

    Joint and Crack Repair L.F. 1,600 $2.00 $320 $2,880 $3,200

    Slurry Seal S.Y. 12,300 $2.00 $2,460 $22,140 $24,600

    Pavement Marking S.F. 1,600 $0.75 $120 $1,080 $1,200

    Miscellaneous Construction Costs L.S. 1 $2,500.00 $250 $2,250 $2,500

    Construction Cost $3,910 $35,190 $39,100

    Engineering, Administrative & Legal Costs (25%) $1,000 $8,800 $9,800

    Subtotal -Seal North Partial Parallel Taxiway to Runway 11-29 $4,910 $43,990 $48,900

    LANDSIDE IMPROVEMENTS

    6. SEAL APRON A-3 N/S TAXILANES

    Mobilization L.S. 1 $5,000.00 $500 $4,500 $5,000

    Temporary Marking, Lighting and Barricades L.S. 1 $1,000.00 $100 $900 $1,000

    Pavement Marking Removal S.F. 550 $1.00 $55 $495 $550

    Joint and Crack Repair L.F. 1,100 $2.00 $220 $1,980 $2,200

    Slurry Seal S.Y. 5,230 $2.00 $1,046 $9,414 $10,460

    Pavement Marking S.F. 550 $0.75 $41 $371 $413

    Miscellaneous Construction Costs L.S. 1 $2,500.00 $250 $2,250 $2,500

    Construction Cost $2,212 $19,910 $22,123

    Contingency Engineering, Legal, & Administrative Costs (25%) $600 $5,000 $5,500

    Subtotal - Seal Apron A-3 N/S Taxilanes $2,812 $24,910 $27,623

    7. SEAL APRON A-3 E/W TAXILANE

    Mobilization L.S. 1 $5,000.00 $500 $4,500 $5,000

    Temporary Marking, Lighting and Barricades L.S. 1 $1,000.00 $100 $900 $1,000

    Pavement Marking Removal S.F. 485 $1.00 $49 $437 $485

    Joint and Crack Repair L.F. 2,910 $2.00 $582 $5,238 $5,820

    Slurry Seal S.Y. 6,425 $2.00 $1,285 $11,565 $12,850

    Pavement Marking S.F. 2,425 $0.75 $182 $1,637 $1,819

    Miscellaneous Construction Costs L.S. 1 $2,500.00 $250 $2,250 $2,500

    Construction Cost $2,947 $26,526 $29,474Contingency Engineering, Legal, & Administrative Costs (25%) $700 $6,600 $7,400

    Subtotal - Seal Apron A-3 E/W Taxilane $3,647 $33,126 $36,874

    8A. OVERLAY APRON A-1 (200' X 80' Wash DNR HELIPAD AREA)

    Mobilization L.S. 1 $5,000.00 $500 $4,500 $5,000

    Temporary Marking, Lighting and Barricades L.S. 1 $1,000.00 $100 $900 $1,000

    Pavement Marking Removal L.S. 1 $1,500.00 $150 $1,350 $1,500

    Joint and Crack Repair L.F. 600 $2.00 $120 $1,080 $1,200

    Bituminous Surface Course (3") Ton 580 $75.00 $4,350 $39,150 $43,500

    Bituminous Tack Coat Gal. 330 $2.00 $66 $594 $660

    Pavement Marking L.S. 1 $1,000.00 $100 $900 $1,000

    Miscellaneous Construction Costs L.S. 1 $2,500.00 $250 $2,250 $2,500

    Construction Cost $5,636 $50,724 $56,360

    Contingency Engineering, Legal, & Administrative Costs (25%) $1,400 $12,700 $14,100

    Subtotal - Overlay Apron A-1 (Wash DNR Helipad Area) $7,036 $63,424 $70,460

    8B. OVERLAY APRON A-2 (1,435' X 250')

    Mobilization L.S. 1 $60,000.00 $6,000 $54,000 $60,000

    Temporary Marking, Lighting and Barricades L.S. 1 $1,000.00 $100 $900 $1,000

    Pavement Marking Removal S.F. 3,000 $1.00 $300 $2,700 $3,000

    Joint and Crack Repair (Concrete) L.F. 21,600 $1.25 $2,700 $24,300 $27,000

    Bituminous Surface Course (3") Ton 6,130 $50.00 $30,650 $275,850 $306,500

    Bituminous Tack Coat Gal. 3,520 $2.00 $704 $6,336 $7,040

    Pavement Marking S.F. 3,000 $0.75 $225 $2,025 $2,250

    Miscellaneous Construction Costs L.S. 1 $30,000.00 $3,000 $27,000 $30,000

    Construction Cost $43,679 $393,111 $436,790

    Contingency Engineering, Legal, & Administrative Costs (25%) $10,900 $98,300 $109,200

    Subtotal - Overlay Apron A-2 $54,579 $491,411 $545,990

    K:\2000-312\Amp\AMP-calc\cost estimates\cost.xls 6/3/2004 Page 2

  • 8/6/2019 Airport Master Plan Update aD

    13/14

    Unit Local FAA Total Cost

    Project Description Unit Quantity Cost Cost Cost (100%)

    ESTIMATED PROJECT COSTS AND FUNDING

    BOWERS FIELD AIRPORT - PHASED DEVELOPMENT PLAN

    PHASE 3 (11-20 YEARS)

    8C. OVERLAY APRON A-3 (1,030' X 300')Mobilization L.S. 1 $40,000.00 $4,000 $36,000 $40,000

    Temporary Marking, Lighting and Barricades L.S. 1 $1,000.00 $100 $900 $1,000

    Pavement Marking Removal S.F. 3,000 $1.00 $300 $2,700 $3,000

    Joint and Crack Repair L.F. 8,000 $2.00 $1,600 $14,400 $16,000

    Bituminous Surface Course (3") Ton 4,250 $50.00 $21,250 $191,250 $212,500

    Bituminous Tack Coat Gal. 2,440 $2.00 $488 $4,392 $4,880

    Pavement Marking S.F. 3,000 $0.75 $225 $2,025 $2,250

    Miscellaneous Construction Costs L.S. 1 $20,000.00 $2,000 $18,000 $20,000

    Construction Cost $29,963 $269,667 $299,630

    Contingency Engineering, Legal, & Administrative Costs (25%) $7,500 $67,400 $74,900

    Subtotal - Overlay Apron A-3 $37,463 $337,067 $374,530

    8D. OVERLAY MIDSTATE AVIATION APRON/RAMP

    Mobilization L.S. 1 $10,000.00 $1,000 $9,000 $10,000

    Temporary Marking, Lighting and Barricades L.S. 1 $1,000.00 $100 $900 $1,000

    Pavement Marking Removal L.S. 1 $1,000.00 $100 $900 $1,000

    Joint and Crack Repair (Concrete) L.F. 3,000 $1.25 $375 $3,375 $3,750

    Cold Milling S.Y. 1,500 $2.00 $300 $2,700 $3,000

    Bituminous Surface Course (3") Ton 1,020 $50.00 $5,100 $45,900 $51,000

    Bituminous Tack Coat Gal. 580 $2.00 $116 $1,044 $1,160

    Pavement Marking L.S. 1 $1,000.00 $100 $900 $1,000

    Miscellaneous Construction Costs L.S. 1 $5,000.00 $500 $4,500 $5,000

    Construction Cost $7,691 $69,219 $76,910

    Contingency Engineering, Legal, & Administrative Costs (25%) $1,900 $17,300 $19,200

    Subtotal - Overlay Midstate Aviation Apron/Ramp $9,591 $86,519 $96,110

    9. CONSTRUCT T-HANGAR (12,500 S.F.)

    Mobilization L.S. 1 $5,000.00 $5,000 $0 $5,000

    Pavement Removal S.Y. 1700 $4.00 $6,800 $0 $6,800

    Construct Nested T-Hangar L.S. 1 $250,000.00 $250,000 $0 $250,000

    Utility Work L.S. 1 $5,000.00 $5,000 $0 $5,000

    Earthwork C.Y. 500 $10.00 $5,000 $0 $5,000

    Concrete Connections L.S. 1 $5,000.00 $5,000 $0 $5,000

    Miscellaneous Construction Costs L.S. 1 $1,000.00 $1,000 $0 $1,000

    Construction Cost $277,800 $0 $277,800

    Contingency Engineering, Legal, & Administrative Costs (25%) $69,500 $0 $69,500

    Subtotal - Construct T-Hangar $347,300 $0 $347,300

    10. CONSTRUCT COMMON CLEAR-SPAN HANGAR

    Mobilization L.S. 1 $5,000.00 $5,000 $0 $5,000

    Construct 70' x 70' Common Hangar L.S. 1 $100,000.00 $100,000 $0 $100,000

    Utility Work L.S. 1 $5,000.00 $5,000 $0 $5,000

    Earthwork C.Y. 200 $10.00 $2,000 $0 $2,000

    Concrete Connections L.S. 1 $2,500.00 $2,500 $0 $2,500

    Erosion Control, Seeding and Mulching L.S. 1 $500.00 $500 $0 $500

    Construction Cost $115,000 $0 $115,000

    Contingency Engineering, Legal, & Administrative Costs (25%) $28,800 $0 $28,800

    Subtotal - Construct Common Clear-Span Hangar $143,800 $0 $143,800

    11A. CONSTRUCT AIRPORT PASSENGER TERMINAL BUILDING

    Mobilization L.S. 1 $5,000.00 $5,000 $0 $5,000

    Construct Ai rpor t Passenger Terminal Building S.F. 3,200 $110.00 $352,000 $0 $352,000

    Utility Work L.S. 1 $5,000.00 $5,000 $0 $5,000

    Earthwork C.Y. 200 $10.00 $2,000 $0 $2,000

    Concrete Connections L.S. 1 $2,500.00 $2,500 $0 $2,500

    Erosion Control, Seeding and Mulching L.S. 1 $500.00 $500 $0 $500

    Construction Cost $367,000 $0 $367,000

    Contingency Engineering, Legal, & Administrative Costs (25%) $91,800 $0 $91,800

    Subtotal - Construct Airport Passenger Terminal Building $458,800 $0 $458,800

    K:\2000-312\Amp\AMP-calc\cost estimates\cost.xls 6/3/2004 Page 3

  • 8/6/2019 Airport Master Plan Update aD

    14/14

    Unit Local FAA Total Cost

    Project Description Unit Quantity Cost Cost Cost (100%)

    ESTIMATED PROJECT COSTS AND FUNDING

    BOWERS FIELD AIRPORT - PHASED DEVELOPMENT PLAN

    PHASE 3 (11-20 YEARS)

    11B. CONSTRUCT AIRPORT MAINTENANCE BUILDING

    Mobilization L.S. 1 $5,000.00 $5,000 $0 $5,000

    Construct Airport Maintenance Building L.S. 1 $60,000.00 $60,000 $0 $60,000

    Utility Work L.S. 1 $5,000.00 $5,000 $0 $5,000

    Earthwork C.Y. 100 $10.00 $1,000 $0 $1,000

    Concrete Connections L.S. 1 $2,500.00 $2,500 $0 $2,500

    Erosion Control, Seeding and Mulching L.S. 1 $500.00 $500 $0 $500

    Construction Cost $74,000 $0 $74,000

    Contingency Engineering, Legal, & Administrative Costs (25%) $18,500 $0 $18,500

    Subtotal - Construct Airport Maintenance Building $92,500 $0 $92,500

    11C. CONSTRUCT AUTO PARKING AREA

    Mobilization L.S. 1 $10,000.00 $10,000 $0 $10,000

    Demolition L.S. 1 $5,000.00 $5,000 $0 $5,000

    Earthwork L.S. 1 $5,000.00 $5,000 $0 $5,000

    4" Crushed Aggregate Base Course S.Y. 1,000 $4.00 $4,000 $0 $4,000

    Bituminous Surface Course (10") Ton 580 $75.00 $43,500 $0 $43,500

    Bituminous Prime Coat Gal. 500 $2.00 $1,000 $0 $1,000Bituminous Tack Coat Gal. 300 $2.00 $600 $0 $600

    PCC Curb L.F. 420 $18.00 $7,560 $0 $7,560

    Pavement Marking L.S. 1 $1,000.00 $1,000 $0 $1,000

    Parking Barricades Each 25 $200.00 $5,000 $0 $5,000

    Erosion Control, Seeding and Mulching L.S. 1 $1,000.00 $1,000 $0 $1,000

    Miscellaneous Construction Costs L.S. 1 $5,000.00 $5,000 $0 $5,000

    Construction Cost $88,660 $0 $88,660

    Contingency Engineering, Legal, & Administrative Costs (25%) $22,200 $0 $22,200

    Subtotal - Construct Auto Parking Area $110,860 $0 $110,860

    K:\2000-312\Amp\AMP-calc\cost estimates\cost.xls 6/3/2004 Page 4