MDOT. I-94 Acclerated Construction Technology Detroit, Michigan April 17-19, 2007. ACTT WORKSHOP. MDOT ACTT WORKSHOP. UTILITIES/ RAILROAD COORDINATION Final Presentation. Utilities/Railroad Coordination. Team Members - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: ACTT WORKSHOP
Page 2: ACTT WORKSHOP

MDOT ACTT WORKSHOP

UTILITIES/ RAILROADCOORDINATION

Final Presentation

Page 3: ACTT WORKSHOP

Utilities/Railroad CoordinationTeam MembersMarion Leaphart, Utility Director, Coleman-Snow

Consultants, (Retired Utilities Manager, SC DOT) Veena Jasuja, MDOT, Detroit TSCNick Lefke, MDOT, Lansing, Real EstateBill Stonebrook, MDOT, Lansing, DesignSteve Rapp, MDOT, Lansing, DesignFacilitator:Anu Taneja, MDOT, Lansing, Contract ServicesNotes:Lynn Venturino, MDOT, Lansing, Design Support

Page 4: ACTT WORKSHOP

Utilities

Page 5: ACTT WORKSHOP

Designate a full time MDOT utilities coordinator

• Oversee all aspects of utility coordination, communication, and cooperation during design and construction

• Act as “go to” person for MDOT, utilities, and vendors

Page 6: ACTT WORKSHOP

Utilize Subsurface Utility Engineering (SUE)

• Have SUE provider available during design and construction

• Update current SUE data

• Utilize SUE deliverables effectively with stakeholders

• Expedites conflict resolution

Page 7: ACTT WORKSHOP

Identify and resolve municipal utility issues

• Early and often involvement of municipal utilities

• Early identification of potential “show stoppers”

• Identify all relocation and proposed new work

• Coordination with stakeholders

Page 8: ACTT WORKSHOP

Identify and resolve private/public utility issues• Early and often involvement of

private/public utilities• Early identification of potential

“show stoppers” • Identify all relocation and

proposed new work• Identify reimbursable relocations• Advanced utility relocations• Coordination with stakeholders

Page 9: ACTT WORKSHOP

Participate in preliminary engineering costs for private/public utilities

• Provides incentive to private/public utilities to cooperate in a timely manner

• Increases cooperation during design phase

Page 10: ACTT WORKSHOP

Railroads

Page 11: ACTT WORKSHOP

Form Steering Committee of officials from MDOT

and Railroads (RR)

• Authority to make high level decisions

• Expedite RR decision making (i.e. trackage rights, union work rules, etc.)

Page 12: ACTT WORKSHOP

Form a Design Engineering Committee

• Early and often involvement of railroads

• Early identification of design constraints

• Early identification of potential “show stoppers”

Page 13: ACTT WORKSHOP

Provide adequate time for RR coordination in the

MDOT process

• Two year minimum coordination time

• Coordination time begins from submittal of preliminary plans from MDOT to RR

Page 14: ACTT WORKSHOP

Contract with qualified vendor to perform RR

coordination • Vendor must be

knowledgeable in RR operations

• Effective in obtaining RR approvals

• Involve MDOT RR experts in vendor selection process

Page 15: ACTT WORKSHOP

Coordinate at-grade crossings with service roads

Diagnostic Team Review (DTR) meeting should take place well in advance of construction, if required

Page 16: ACTT WORKSHOP

Maintenance of RR traffic

• Early and often involvement of RR

• Construct temporary runaround “shoo-fly” tracks

• Part width bridge construction• Roll-in/lift-in superstructure • Build new permanent bridges

parallel to existing RR• Trackage rights agreements

between RR during construction

Page 17: ACTT WORKSHOP

Possible elimination of two RR structures over I-75

• RR approval required

Page 18: ACTT WORKSHOP

Questions