accelerator/organisation mats lindroos and john weisend ii april 22, 2015

32
Accelerator/Organisation Mats Lindroos and John Weisend II www.europeanspallationsource.se April 22, 2015

Upload: amos-johnson

Post on 26-Dec-2015

216 views

Category:

Documents


0 download

TRANSCRIPT

Accelerator/Organisation

Mats Lindroos and John Weisend II

www.europeanspallationsource.seApril 22, 2015

Overview

• The Accelerator at ESS• Accelerator division• Staff plan• Project organization• CCB levels and governance structure• Tools• High level schedule• Risk analyses

2

Accelerator Technical performances

3

Design Drivers:

High Average Beam Power

5 MW

High Peak Beam Power

125 MW

High Availability

> 95%

Key parameters:-2.86 ms pulses-2 GeV-62.5 mA peak-14 Hz-Protons (H+)-Low losses-Minimize energy use-Flexible design for mitigation and future upgrades

Spokes Medium β High βDTLMEBTRFQLEBTSource HEBT & Contingency Target

2.4 m 4.6 m 3.8 m 39 m 56 m 77 m 179 m

75 keV 3.6 MeV 90 MeV 216 MeV 571 MeV 2000 MeV

352.21 MHz

704.42 MHz

• The scope contingency for the accelerator project consists of the RF sources and installation costs (after 2019) for the high beta-part of the linac

• The fully equipped cryomdoule for the high-beta linac are IK contributions and are not part of the scope contingency. The infrastructures needed for the construction of these are only available during ESS construction.

In-kind

ATOMKICEACNRSCockcroft InstDaresbury LabElettraESS-BilbaoGSIHuddersfield UnivIFJ PANINFN CataniaINFN LegnaroINFN MilanNCBJRALRHULTallinn UTTU LodzUniv OsloWarsaw UTWroclaw UT

Paid contracts

Aarhus UnivDESYLund UnivPSIUppsala Univ

Accelerator Selected technologies

ESS ADPARTNERS

Accelerator DivisionMats Lindroos

Head of Division

BEAM PHYSICSHåkan Danared – GLMohammad Eshraqi

– Deputy GLRenato De Prisco

Ryoichi MiyamotoMarc Munoz

Christine DarveYngve Levinsen

SPECIALIZED TECHNICAL SERVICESJohn Weisend II – GL

Wolfgang Hees - Deputy GLFrithiof Jensen

Anton Lundmark Evangelia VaenaMatthew Conlon

Georg HullaGunilla JacobssonWalter Wittmer

CRYOGENICS SECTIONPhilipp Arnold – SL

Xilong WangJaroslaw Fydrych

John JurnsXiaotao Su (50%)

Ali Farsian

VACUUM SECTIONPeter Ladd – SL

Marcelo Juni

FerreiraHilko Spoelstra

Giobatta LanfrancoSimone Maria

Scolari (fr 18 May)

RFAnders Sunesson – GL

Morten Jensen - Deputy GLRihua Zeng

Rafael Montano

RF SOURCES SECTION

Morten Jensen – SLChiara Marrelli

Rutambhara YogiStevo Calic

Solid State source Engineer

RF EngineerRF Technician

POWER CONVERTERS

SECTIONCarlos de Almeida

Martins – SLGöran GöranssonElectromechanical Technical Engineer

BEAM INSTRUMENTATION(incl. Safety 3p)

Andreas Jansson – GLThomas Shea - Deputy GL

Benjamin Cheymol Irena Dolenc KittelmannHooman Hassanzadegan

Cyrille ThomasHinko Kocevar

Maurizio DonnaViatcheslav Grishin Michal Jarosz (oPAC)

Charlotte Roose (oPAC)Lali Tchelidze

Luigi Esposito (temp)Duy Phan

Beam Diagnostics Engineer

Beam Diagnostics Engineer

Scientist

INTEGRATIONDavid McGinnis - GL

Stephen Molloy – Deputy GLEugene TankeNikolaos Gazis

Håkan Danared – Deputy Head of DivisionJohn Weisend II – Deputy Head of Acc Projects

David McGinnis – Chief EngineerLali Tchelidze – Safety

Steve Peggs (C)

Caroline Prabert - Personal AssistantGunilla Jacobsson - Divisional Planning A.

Solveig Aas - Team Assistant

ENGINEERING SECTION

Stephen Molloy – SL

Aurélien PontonEnric Bargalló

Edgar SargsyanInigo Alonso

Lead Engineer

58 employees (2015-04-01)

Finalized & ongoing recruitments in orange

G.Jacobsson

6

Accelerator Staff Plan at ESS

Accelerator Division Staff per Group

7

2014 2015 2016 2017 2018 20190

20

40

60

80

100

120

Spec. Technical Services

RF

Beam Instrumentation

Beam Physics

Integration

Divisional

Staff number

Number of Accelerator Division employees at the end of each year.

Accelerator Division Staff per Category

8Number of Accelerator Division employees and Operators at the end of each year.

2014 2015 2016 2017 2018 2019 2020 2021 2022 20230

20

40

60

80

100

120

140

Operators

Technicians

Engineers

Scientists

Admin

Management

Staff number

9

Accelerator Staff Plan

Accelerator Project organization

10

WP# WP TITLE WP LEADER EXT. WP?

DEPUTY WP LEADERs FOR

EXTERNAL WPs

WP01 MANAGEMENT J.G. WEISEND II NO

WP02 ACCELERATOR PHYSICS M. ESHRAQI NO

WP03 NORMAL CONDUCTING FRONT END

S. GAMMINO YES W.WINTER

WP04 SPOKE CRYOMODULES S. BOUSSON YES C. DARVE

WP05 ELLIPTICAL CRYOMODULES P. BOSLAND YES C. DARVE

WP06 BEAM DELIVERY SYSTEMS S. MØLLER YES P. LADD

WP07 BEAM DIAGNOSTICS A. JANSSON NO

WP08 RF SYSTEMS A. SUNESSON MIX A. SUNESSON

WP99 ACCEL INFRASTRUCTURE & INSTALLATION

D. MCGINNIS NO

WP10 TEST STANDS W. HEES MIX W. HEES

WP11 CRYOGENICS P. ARNOLD NO

WP12 VACUUM P. LADD NO

WP13 SAFETY L. TCHELIDZE NO

WP14 ACCELERATOR INTEGRATION S. MOLLOY NO

WP15 ELECTRICAL SUPPORT F. JENSEN NO

WP16 COOLING SUPPORT A. LUNDMARK NO

WP17 POWER CONVERTERS C. MARTINS NO

Weekly ESS management team:1. Mats Lindroos, Project leader

2. John Weisend, Deputy project leader

3. David McGinnis, Chief engineer

4. Håkan Danared, In-kind manager

5. Lali Tchelidze, Safety including radiation safety

6. Anders Sunesson, RF systems

7. Luisella Lari, Head planner

8. Andreas Jansson, Beam instrumentation

9. Matthew Conlon, QA/QC

Quarterly Technical Board:1. Weekly ESS management team2. All WP leaders and deputies3. Representatives of all contracted

institutes if not already a WP leader

Collaboration Board:1. ESS Technical Director2. Project leader3. Representatives of all contracted

institutes (one elected as chair)

Control Change Boards (CCB) & control flow for Accelerator

11

ESS governance

ESS Board / STC

CEO / ESS CCB

ACCSYS Mngt Team

CCB-A

CCB-B

CCB-C’

via ACCSYS (deputy) Project Leader

weekly minutes, actions & ACCSYS Control Log

via CEO

status report at meeting,ACCSYS Control Log

ACCSYS TB

Collaboration board

CCB-C

reports

delegates, approves

ACCSYS Project Leadervia EPG and through CEO

Quarterly

1-2/year

via ACCSYS (deputy) Project leader

13

Accelerator cost per WP

Total budget: 510 M€

14

Accelerator Budget Profile

Total budget: 510 M€

15

Accelerator Budget Profile

EVM Graph

20132014 JAN 2015

Cost variance mainly due to late

invoices

FEB 2015

EVM Graph - Comments

Schedule variance = Earned Value – Planned Value

The schedule variance (-2.8 Million Euro) is mainly due to:

• -1.5 M€ New Vacuum plan not still in place in P6 (WP12)• -1.3 M€ Delay of ACCP contract signature ~1 week due to continued

contractual fine tuning (Cryo WP11) This has no impact on the final delivery date or on the beam delivery milestone

Behind Schedule

EVM Graph - Comments

Cost Variance = Earned Value – Actual Value

The cost variance (+0.7 Million Euro) is mainly due to:

• +0.7 M€ Effect of re-plan in January of the whole Beam Instr. WP (BI WP07)• +0.1 M€ Delay in payment to CNRS (Spoke WP04)• +0.3 M€ Effect of re-plan (NC linac WP03)• +0.5 M€ Delay in payment to CEA (Elliptical WP05)

• -0.5 M€ Effect of some re-plan on-going (RF WP08)• -0.3 M€ Uppsala University Invoice Q4 2014, coming in 2015 (Test stand

WP10)• -0.1 M€ Some discrepancies due to invoices for on-going 2014 contract

booked on the old PCC i.e. WP8 at the place of WP17 (Power Converters WP created on Sept 2014)

• Some other little fluctuations in all the WPs (mainly to salaries)

Under Budget

High Level Master Schedule

There are many “close critical path” in the project, notably RFQ, DTL, Cryomodules and RF systems

MB transport to Lund

HB inst. & Comm.

Lund Test Stand 2 – Medium Beta Cryomodule series testing

Fabrication of Medium Beta CM

RF – Klystron Prototyping for Test Stand 2 & Medium Beta HPA

Critical Path - Accelerator

Ground break First installations on-site (Accsys)

Permits

ConvFLicensing

ConvF

20

AccSys

Machine* – Ready for first beam on Target

MB Comm.

Sep 2016 Jun 2019

Accsys ready for570 MeV bean On Target

Jun 2014

Early Access G04 Cryo-Compressor Bldg (Conventional power 220V&400V)

Medium Beta Cryomodule Installation

Sep 2022

21

Critical Path - Accelerator

Accelerator Risks

– ACCSYS is currently tracking 182 risks including many detailed technical ones

– Most of these risks have treatment plans (the remaining ones are being developed)

– The nature of these risks is that most exist throughout the length of the project

– The Exonaut Risk software and database works well– Our ability to accurately estimate the costs of the risks is

limited

22

Accelerator Risks

• The likelihood of a few risks has been reduced since the 2013 Review due to experience to date. These include:– Lack of appropriate design and Product Data Management (PDM) tools’.

• This previously high-ranking risk has been re-assessed. Probability of this occurrence reduced significantly due to visit by D. Ferguson and due to resulting Lab-wide review of tools by a committee which made recommendations on improvements. This may be reassessed once the lab working group finishes implementing the recommendations (Q2 2015)

– ‘Political and financial considerations overrule technical considerations for IKC assignments.’

• Reduced probability of occurrence due to positive experiences of the last 12 months.

• An example of a retired risk is: ‘Decisions not made in time’– Risk retired due to ongoing experience with ACCSYS decision process. Mechanisms

exist for decisions being made in a timely manner • The fixed price for the ACCP (coming in under budget) helps reduce the cost risk to the

project)23

Accelerator Top Risks

• The top 5 risks for ACCSYS are:– Unidentified design faults cause failure during production– Suppliers do not meet scope and schedule requirements– In-kind contributors do not meet scope & schedule requirements– Inability to deal with on-site adjustments to components– Electrical machinery not powered down during maintenance (safety risk)

– Treatment plans (including design reviews, close communication with IKCs and suppliers, development of onsite installation and adjustment capabilities) are underway. The last risk will be dealt with via a site wide lockout/tagout procedure.

– In reality, the biggest single risk for success (this risk is held at the ESS level) remains retention of staff – Hiring has generally gone quite well, the real challenge is to avoid burn out

24

Next Six Months

• Hardware testing facility in Lund operational• Technical verification program full launched

• Audits and Reviews

• Integration and coordination of accelerator project• Review of all Level 4 requirements• Finalize IK contracts• Continue recruitment of staff to AD• Continue project work according to plan

25

Accelerator Summary

• The accelerator project is in a phase of intense prototyping and reviewing and will soon see most major systems in construction• Large part of prototyping and design done by in-kind partners• Essential to get in-kind contracts agreed and signed in 2015 to permit construction of all systems

to start in earnest• Work on (parts of the) RF design, modulators, beam instrumentation and cryogenic design done

in Lund

• Coordination, integration and verification represent a major part of the work done today by the accelerator division at ESS in Lund

• The accelerator division is recruiting according to plan and will be 2018 have 110 staff with some 40 being technicians

• The project schedule has many close critical paths which makes it sensitive to delays, even in activities which not necessarily are being seen as critical

• A testing facility which presently is the home of he reduced scal modulator prototype exists and will be further extended in the coming years

• The goal is to build and train the accelerator division so that it can assume full responsibility for operation and maintenance of the accelerator systems in 2019

26

Extra slides

27

Staff Planning 2015-2019 – Growth per Group

28

Number of Accelerator Division employees at the end of each year. 2014 actuals, in blue.

  2014 2015 2016 2017 2018 2019 Growth

Accelerator Division 52 70 84 109 110 110 58

Divisional 4 4 4 4 4 4 0

Beam Instrumentation 10 14 16 19 19 19 9

Spec. Technical Services 15 20 26 37 37 37 22

Beam Physics 7 9 9 9 9 9 2

RF 9 13 19 30 31 31 22

Integration 7 10 10 10 10 10 3

Staff Planning 2015-2019 – Growth per Category

29

Number of Accelerator Division employees at the end of each year. 2014 actuals, in blue.

  2014 2015 2016 2017 2018 2019 Growth

Accelerator Division 52 70 84 109 110 110 58

Management 6 6 6 6 6 6 0

Scientists 14 16 16 16 16 16 2

Engineers 29 42 43 43 43 43 14

Technicians 3 16 41 42 42 42

Admin 3 3 3 3 3 3 0

Staff Planning 2015-2019 – Recruitments of Technicians

30

  2015 2016 2017 2018 2019 Total

Accelerator Division 3 13 25 1 42

Divisional - - - - - -

Beam Instrumentation - 2 3 - - 5

Spec. Technical Services 1 5 11 - - 17

Beam Physics - - - - - -

RF 2 6 11 1 20

Integration - - - - - -

Staff Planning 2015 – Recruitments Overview (per group)

31

   

Safety Engineer: Duy Phan Beam Instrumentation 2015-02-23

BD Engineer, Electronics (Analog) Beam Instrumentation 2015-Q2

Scientist ('replace Christian') Beam Instrumentation 2015-Q3

BD Engineer Beam Instrumentation 2015-Q3

     Cryogenics Engineer (50%): Xiaotao Su STS / Cryogenics 2015-01-19

Mechanical Engineer: Ali Farsian STS / Cryogenics 2015-02-02

Senior Engineer: Walter Wittmer STS 2015-04-01

Vacuum Systems Eng: Simone M Scolari STS / Vacuum 2015-05-18

Vacuum Technician STS / Vacuum 2015-Q3

     PhD in Acc Physics Beam Physics 2015-Q2

Scientist ('replace Edgar') Beam Physics 2015-Q3

     Electromech. Technical Engineer RF / Power Converters 2015-Q2/Q3

RF Technician RF Sources 2015-Q2/Q3

RF Engineer RF Sources 2015-Q2/Q3

Solid State source engineer RF Sources 2015-Q2/Q3

     Lead Engineer: Inigo Alonso Integration / Engineering 2015-01-07

Lead Engineer Integration / Engineering 2015-Q3

Lead Engineer Integration / Engineering 2015-Q3

     

Totally 18 recruitments:

Staff Planning 2015 – Recruitments Status (2015-04-01)

32

Finalized recruitments (6):    

Inigo Alonso, Lead Engineer Integration / Engineering 2015-01-07

Xiaotao Su, Cryogenics Engineer (50%) STS / Cryogenics 2015-01-19

Ali Farsian, Mechanical Engineer STS / Cryogenics 2015-02-02

Duy Phan, Safety Engineer Beam Instrumentation 2015-02-23

Walter Wittmer, Senior Engineer STS 2015-04-01

Simone Maria Scolari, Vacuum Systems Engineer STS / Vacuum 2015-05-18

Ongoing recruitments (7):    

BD Engineer, Electronics (Analog) Beam Instrumentation 2015-Q2

PhD in Acc Physics Beam Physics 2015-Q2

Lead Engineer Integration / Engineering 2015-Q3

Electromech. Technical Engineer RF / Power Converters 2015-Q2/Q3

RF Technician RF Sources 2015-Q2/Q3

RF Engineer RF Sources 2015-Q2/Q3

Solid State source Engineer RF Sources 2015-Q2/Q3

Planned recruitments (5):    

Vacuum Technician STS / Vacuum 2015-Q3

Scientist ('replace Christian') Beam Instrumentation 2015-Q3

BD Engineer Beam Instrumentation 2015-Q3

Lead Engineer Integration / Engineering 2015-Q3

Scientist ('replace Edgar') Beam Physics 2015-Q3