1. Processing Steps
S.No
Details ofTransaction
Details Remarks
1 Production dataProcess wise productiondata is required.
1. Chips production qty (Activity code is P-LINE1)
2. Suppose if u have chips sales then chips packing qty isrequired in production data. Consider chips sales qtyas production qty of chips packed.
3. Denier wise Yarn production ( activity code isSPINDRAW-SDU)
4. Suppose if u have YARN sales then YARN packing qty isrequired in production data. Consider YARN sales qtyas production qty of YARN packed otherwise enter theqty . . Kindly use denier wise item code
5. Denier wise Cabling production qty (activity code isCABLING-TORAY)
6. Style code wise weaving production qty (activity codeis WEAVING-DORNIER-WW)
7. Fabric FG production qty (activity code is FAB-PACK)
8. Suppose if your getting any new FG items then need tocreate the following masters
a. Product masterb. Cost object masterc. Cost object BOM
Kindly run BOM missing report in export option andensure all BOM are linked.
2 Production driverData(Driver inputs toproduction)
For Cost allocation purposewe need process wisemachine hours/ productionqty in some places
1. Kindly prepare Driver data based on productionThe following data are requireda. Chips production (DRV011)b. Chips packing qty (DRV128)c. Denier wise spinning hours (DRV055)
d. Denier wise yarn packing qty(DRV077)
-
8/3/2019 Abis Processing Steps 18 02 11
2/9
e. Denier wise cabling hours (DRV103)f. Style wise Weaving hours (DRV117)g. Style wise packing qty(DR042)h. Chips packing qty, Yarn packing qty & style wise
packing qty(DRV003)
2. After preparing driver inputs to product data, kindlyuse VLOOKUP option between Driver inputs product
and production data to confirm all the entries areavailable in both files
Note : All production items should appear in driverinputs product data other wise cost will not beallocated to product hence that item will not appearin any of the reports
All driver inputs to product items should existin production data otherwise cost will not beallocated to product
3Cost objectproduction
Need this information formatching with SKU cost
1. All fabric, chips & yarn items code should linked withrelevant production route
2. Consider only packing qty for yarn & chips not totalyarn & chips qty
4Route wiseproduction
Need this information formatching with COC
3. All fabric, chips & yarn items code should linked withrelevant production route
4. Consider total production qty for yarn & chips items
5 Sales Data Customer & product wiseSales qty & sales value
1. Chips sales
2. Fabric Sales3. Yarn Sales (use denier wise code only i.e. YARN-840,
YARN-1260 , etc)
6 Cost object sales
Run cost object sales(transactiondata preparation andselect cost object sales option.
Note: Any changes in sales again need to run cost objectsales otherwise revised sales will not reflect the reports.
-
8/3/2019 Abis Processing Steps 18 02 11
3/9
7 I/O ratio Process wise I/O ratio
1. Ensure Route wise production, Sales, Cost objectsales(thru data preparation) , driver input to producthas been imported & data preparation
2. Use export option (Toolsdatabase maintenance
data exportsql List TransactionI/O working to
export product wise I/O details based on currentmonth production
3. Open exported file and first enter 1 in all norms (andthen enter actual I/O wherever required ) and import
the same thru Processingtransaction data importI/O ratio
8 Driver input toactivity
Utility and Service costallocation
Use quick updation option to transfer the data fromprevious month or export the data to excel and changePOWER, BOILER and utility units in that excel format andimport the revised data to current month. Further
updating made in April 2011
Driver Inputs to activity drivers are1. DRV094 MECHANICAL MAINTENANCE (Std
Ratio)2. DRV096 ELECTRICAL MAINTENANCE (Power
Norms)3. DRV042 Power Consumption Activitywise (Power
Norms)4. DRV098 INSTRUNMENTAL MAINTENANCE (std
Norms)
5. DRV062 TIME SPENT ACTIVITYWISE - CIVILMAINTENANCE (Std Norms)
6. DRV058 STEAM CONSUMPTION ACTIVITYWISE(Actual)
7. DRV001 A/C CONSUMPTIONACTIVITYWISE(Actual)
8. DRV006 AIR CONSUMPTIONACTIVITYWISE(Actual)
9. DRV034 NITROGEN CONSUMPTIONACTIVITYWISE(Actual)
10.DRV037 NO OF KWH GENERATED(Actual)
-
8/3/2019 Abis Processing Steps 18 02 11
4/9
11.DRV019 DM WATER COSNUMPTIONACTIVITYWISE (Std Norms)
12.DRV027 EFFLUENT TREATED ACTIVITYWISE13.DRV032 Allocated to weaving14.DRV118 SERVICE RELATED COST
ALLOCATION(Stagewise Total Production)15.DRV069 TIME SPENT ACTIVITYWSIE IT(Std
Norms)
16.DRV036 NO OF EMPLOYEES ACTIVITYWISE(StdNorms)
-
8/3/2019 Abis Processing Steps 18 02 11
5/9
9 Material Price
The following RM & material prices are required1. Lactam2. Weft3. Packing material4. Process chemical5. Other materials
10 Actual BOM
The following Actual BOM are required1. Lactam(Enter Lactam norms for fabric in ISBG-LATAM BOMEnter Lactam norms for Chips in ISBG-LATAM-C BOMEnter Lactam norms for Yarn in ISBG-LATAM-Y BOM)2. Weft3. Packing material4. Process chemical
Other materials
11 Trial BalanceCost centre, Account wiseExpenses
1. Remove 0 Cost centre from TB2. Note down the DG cost centre cost from TB and
remove the same data from TB3. If system identified new account code then do the
following stepsa. Create new account code in account code masterb. The same account code should grouped under one
cost element thru account code grouping master
12 Cost Model
Department to activity
allocation
1. Confirm TB has been imported2. Run data preparation3. Export previous month cost model data from ABIS4. Change to current process month and import.
5. Run Data preparation6. Go to cost model transaction and select cost centre code
& enter the ratio wherever the total is 0.
13Inclusion of normsactivity
For Remove & Addcategory items inAccount code grouping
1. Packing overheads(41413)2. Power(41421)3. Fuel(41424)4. Freight(41882)5. Depreciation(42313)
-
8/3/2019 Abis Processing Steps 18 02 11
6/9
14Inclusion of normsProduct
1. Process chemical cost chips & yarn denier wise(41122)2. Product wise freight cost for only MODI products(41471)
15Inclusion of normscustomer
1. Export Incentive(31393)2. Freight on sales (41472)
16 Processing
3. Kindly confirm all the above transaction data has beenimported
4. Run Data preparation
5. (After data preparation pls run Data preparation reportand ensure all overheads are added) suppose if urchanging or adding in TB or Inclusion on norms then plsrun data preparation again
6. Run processing with Prerequisite option and ensure no
error
7. if there is no error then continue the processing otherwise correct the error and run data preparation andprocessing again
17 Validation reports
After complete the processing Pls check the followingreports and ensure all TB & Inclusion on norms cost areallocated
1. Trial balance reconciliation report
2. reportsCheck listIntegrity Report
-
8/3/2019 Abis Processing Steps 18 02 11
7/9
2. Reports
Denier wise Fabric
cost/Yarn based on
production
ReportsCost
StatementSegment wise
cost
Select Report View : DefaultSelect PeriodSelect HierarchySelect Fabric or Yarn from product option
Select Denier from grouped bySelect Rs or Rs/Unit option and preview
Period wise cost
comparison based on
production
ReportsCost
StatementSegment wisecost
Select Report View : Period wiseSelect Period (For exp : From period Apr-2011 & To Period : May-2011Select HierarchySelect Rs or Rs/Unit option and preview
Denier wise Fabric
cost/Yarn based on
Sales(Pft & los)
ReportsProfit
StatementSegment wise
Profitability
Select Report View : DefaultSelect Period
Report Type : ProductSelect HierarchySelect Fabric or Yarn from product optionSelect Denier from grouped bySelect Rs or Rs/Unit option and preview
Note : %Sales Option reportSelect Report view : % Sales and all other parameters willbe same
Period wise cost
comparison based onSales(Pft & los)
ReportsProfit
StatementSegment wiseProfitability
Select Report View : Period wiseSelect Period (For exp : From period Apr-2011 & To Period : May-
2011Select HierarchySelect Rs or Rs/Unit option and preview
Customer wise report
(Pft & los)
ReportsProfit
StatementSegment wise
Profitability
Select Report View : DefaultSelect PeriodReport Type : CustomerSelect HierarchySelect Customer from grouped bySelect Rs or Rs/Unit option and preview
Note : %Sales Option reports
Select Report view : % Sales and all other parameters
-
8/3/2019 Abis Processing Steps 18 02 11
8/9
will be same
-
8/3/2019 Abis Processing Steps 18 02 11
9/9
Customer & product
wise report (Pft & Los)
ReportsProfit
StatementCustomer and
Cost object wise Profit
Select PeriodSelect Costobject from report orderSelect Report column : Cost ObectSelect Amount Type : Rs or Rs/unit and preview
Trial balance
Reconciliation
ReportsOther
ReportsTrial BalanceReconciliation
Select PeriodReport Type : Resource or Activity wise and Preview
Total Cost/Qty
consumption
individual Material
wise based on sales or
production
ReportsOther
ReportsCost object material
cost
Select PeriodSelect Production or Sales and Material cost from ReportsonSelect Summarized and Material from Report type then pressPreview.
Final SKU wise
Material cost( materials defined in
BOM)
ReportsOther
ReportsCost object Product
BOM
Select Period
Select Production or Sales from reports onSelect HierarchySelect Detail from Report Type and press preview button
Stage wise Cost SKU
wise (like COC format)
ReportsFlash ReportsCost
Summary
Select PeriodSelect HierarchySelect ProductionSelect cumulative from report typeSelect Process from report columnSelect specific from Activity optionSuppose if u want to see the fabric items then select Fab-Pack
from the Activity List. Select Yarn pack for yarn items.Press Preview button