    A CASE STUDY ON DEMAND FORCASAT: ELECTRICITY IN BANGLADESH

    ABSTRACT:

    IN this case study we had tried to figure out the demand of service on future periods.

    For this we had select electricity sector of Bangladesh. We had collect data of demand on

    previous periods and had utilized it for projecting future demands. We used various

    quantitative methods like time series and trend analysis for predicting future demands and

    different error analysis also included. The results of the study are useful for the energy

    planning of the country.

    1. INTRODUCTION:Bangladesh is a country under development and moving towards the industrialization.

    Although Bangladesh is predominantly an agricultural country but a large number oflarge-scale Industries based on both indigenous and imported raw materials have been set

    up. With huge population and limited resources Bangladesh is facing notable crisis ofenergy. Energy is the main factor that makes every machinery run and electricity is the

    main source of energy. Day by day the demand for electricity is increasing but production

    is not enough. Effort on decreasing System losses and increasing production capacity has

    been a major matter to be focused for Bangladesh.

    2. Current situation of Bangladesh:

    Only around 20% of the population (25% in urban areas and 10% in rural areas)

    has access to electricity, and per capita commercial energy consumption is amongthe lowest in the world.

    Surface Area: 144, 0 1000 sq kmPopulation: 164, 7 Millions of inhabitants - 2009 (estimates after 2007)

    Current GDP: 67, 8 Billions of Euros - 2009 (estimates after 2008)

    GDP per capita: 411, 4 Euros - 2009 (estimates after 2007)

    Electricity - production by source:

    fossil fuel: 93.7%

    hydro: 6.3%

    nuclear: 0%other: 0% (2001)

    Electricity - consumption: 14.25 billion kWh (2001)

  • 8/6/2019 A Case Study on Demand Forcasat

    2/17

    3. About forecasting:

    Forecasting is the process of making statements about events whose actual outcomes

    (typically) have not yet been observed. A commonplace example might be estimation ofthe expected value for some variable of interest at some specified future date. Prediction

    is a similar, but more general term. Both might refer to formal statistical methods

    employing time series, cross-sectional or longitudinal data, or alternatively to less formal

    judgmental methods. Usage can differ between areas of application: for example in

    hydrology, the terms "forecast" and "forecasting" are sometimes reserved for estimates of

    values at certain specific future times, while the term "prediction" is used for more

    general estimates, such as the number of times floods will occur over a long period. Risk

    and uncertainty are central to forecasting and prediction; it is generally considered goodpractice to indicate the degree of uncertainty attaching to forecasts. The process of

    climate change and increasing energy prices has led to the usage of Egain Forecasting of

    buildings. The method uses Forecasting to reduce the energy needed to heat the building,thus reducing the emission of greenhouse gases. Forecasting is used in the practice of

    Customer Demand Planning in every day business forecasting for manufacturingcompanies. The discipline of demand planning, also sometimes referred to as supply

    chain forecasting, embraces both statistical forecasting and a consensus process. An

    important, albeit often ignored aspect of forecasting, is the relationship it holds with

    planning. Forecasting can be described as predicting what the future will look like,whereas planning predicts what the future shouldlook like.There is no single right

    forecasting method to use. Selection of a method should be based on your objectives and

    your conditions (data etc.).A good place to find a method, is by visiting a selection tree.

    An example of a selection tree can be found here.

    There are four steps to forecasting:

    1

    Set objectives for forecast - what decisions will forecast influence, and how - what

    aspects of plan are vulnerable to surprise - how accurate must forecast be to be of any

    use?

    2 Obtain forecast - from existing sources or commissioned study.

    3

    Evaluate forecast, including assessing the sensitivity of planned actions on the

    accuracy of the forecast - what exactly is being forecast - what assumptions does the

    forecast itself make - source of forecast and past reliability - what objectives of

    forecasters, and how do they compare with your own?

    4 Disseminate the forecast, persuade others of its accuracy and appropriateness.

  • 8/6/2019 A Case Study on Demand Forcasat

    3/17

    4.FORECASTING TECHNIQUES WE HAVE USED:

    FOR the projection of future demand on the data we had collected, we find time series

    analysis and casual model best fits. Forecast model we selected is illustrated on following

    flow chart.

    4.1 Time series analysis:

    4.1.1 Simple moving average: Moving average techniques forecast demand bycalculating an average of actual demands from a specified number of prior periods each

    new forecast drops the demand in the oldest period and replaces it with the demand in the

    most recent period; thus, the data in the calculation "moves" over time

    Time series analysis Casual model

    Simple moving average Linear regression

    TRENDANALYSIS

    DATA COLLECTION

    Fig; Forecasting model

  • 8/6/2019 A Case Study on Demand Forcasat

    4/17

    simple moving average:

    where N = total number of periods in the average

    forecast for period t+1: Ft+1 = At

    Key Decision: N - How many periods should be considered in the forecast

    Tradeoff: Higher value of N - greater smoothing, lower responsiveness

    Lower value of N - less smoothing, more responsiveness

    - the more periods (N) over which the moving average is calculated, the less susceptible

    the forecast is to random variations, but the less responsive it is to changes

    - a large value of N is appropriate if the underlying pattern of demand is stable

    - a smaller value of N is appropriate if the underlying pattern is changing or if it is

    important to identify short-term

    4.1.2 Trend analysis: There are no proven "automatic" techniques to identify trendcomponents in the time series data; however, as long as the trend is monotonous

    (consistently increasing or decreasing) that part of data analysis is typically not very

    difficult. If the time series data contain considerable error, then the first step in the

    process of trend identification is smoothing.

    Smoothing. Smoothing always involves some form of local averaging of data such that

    the nonsystematic components of individual observations cancel each other out. The most

    common technique is moving average smoothing which replaces each element of theseries by either the simple or weighted average ofn surrounding elements, where n is thewidth of the smoothing "window" (see Box & Jenkins, 1976; Velleman & Hoaglin,

    1981). Medians can be used instead of means. The main advantage of median as

    compared to moving average smoothing is that its results are less biased by outliers(within the smoothing window). Thus, if there are outliers in the data (e.g., due to

    measurement errors), median smoothing typically produces smoother or at least more

    "reliable" curves than moving average based on the same window width. The main

    disadvantage of median smoothing is that in the absence of clear outliers it may produce

    more "jagged" curves than moving average and it does not allow for weighting.

  • 8/6/2019 A Case Study on Demand Forcasat

    5/17

    In the relatively less common cases (in time series data), when the measurement error is

    very large, the distance weighted least squares smoothing or negative exponentiallyweighted smoothing techniques can be used. All those methods will filter out the noise

    and convert the data into a smooth curve that is relatively unbiased by outliers (see therespective sections on each of those methods for more details). Series with relatively few

    and systematically distributed points can be smoothed with bicubic splines.

    Fitting a function. Many monotonous time series data can be adequately approximated

    by a linear function; if there is a clear monotonous nonlinear component, the data first

    need to be transformed to remove the nonlinearity. Usually a logarithmic, exponential, or

    (less often) polynomial function can be used.

    4.2 Casual modeling:

    A reliable method of prediction becomes possible if you have, through research, obtained

    a model which not only describes (as in the previous section) the development of thephenomenon to be predicted but also explains it, in other words enumerates the reasons

    why it happens. In the best case the reasons and their outcomes are assembled as a model

    defining the dynamic invariance of change in the process to be predicted.

    The weather, for example, need today no more be predicted on the basis of a statisticalassociation of air pressure and weather only. The science of meteorology has lately

    advanced so much that we now know and can make use of the invariable structure ofmoving cyclones which explains the changes both in air pressure and in weather. Even

    the proverb about red skies has now been given an explanation:

    "Because the weather patterns in North America generally move from west to east, when

    clouds arrive overhead at sunrise the sky will appear red, signalling a storm "moving in".When the storm eventually passes, the sky will clear in the western sky. If sunset occurs

    simultaneously, the light will cast a red glow on the clouds above, now moving towardsthe east."

    The most elementary method of forecasting on the basis of a causal model is to use the

    model just like a statistical association, explained earlier. This is particularly easy when

    one of the variables in the model is time: then you just insert the right year into the

    model, and it immediately becomes the desired forecast.

    If time is not included in the causal model, the model may still be helpful, because you

    can often predict the development of the independent variable easier than the future of the

    dependent variable or of the entire system - not least because of the fact that a reason

    normally precedes its result and it is thus not so distant in the future as the outcome will

    be.

  • 8/6/2019 A Case Study on Demand Forcasat

    6/17

    When you know the causal relationships between the variables you will be able to use

    much more advanced methods of forecasting than mere statistical models would permit.These include:

    You can better assess whether the model remains valid also in the future.

    You can assess with sensitivity analysis the probable error of the forecast.

    You will also be able to modify the model, with a high degree of reliability,

    according to the requirements of the situation.

    If you want not only to forecast but also to change the future, you can pinpoint

    those changes in the independent variables that are needed to cause the desired

    change in the dependent variables.

    The causal model is often so complicated

    that it is best managed by using a

    computer. Even then, you will usually needan illustrative presentation of your modelto clarify your thinking and finally to be

    presented in the report. In such an

    illustration you will need a notation systemto describe the various logical relations

    between the variables. The computer

    program will often be able to print out the

    model, using its in-built notations. If you

    can find no suitable ready made notation

    systems, you can devise one.

    5.2.1 Linear regression: simple linear regression is fitting a straight line to a set of

    paired observation.Mathematical expression for straight line is

    Y=mx+c

    Where

    Y=dependent variable

    m=slope of fitted linex=independent variable

    c=intercept on y axis

    This technique of fitting straight line can be used as forecasting model by plotting

    independent variable to figure out dependent variable. Slop and intercept of fitted line canbe determined by following formula

  • 8/6/2019 A Case Study on Demand Forcasat

    7/17

    m=(nxiyi-xiyi)/(nxi2-(xi)

    2) and

    c=yi/n-mxi/n

    5.3 Error calculations techniques:

    5.3.1 Mean absolute deviation:

    =

    =

    n

    t

    tt FDn

    MAD1

    1

    Wheren=number of observation

    Dt=current demandFt=current forecast

    5.3.2 Mean square error

    2

    1

    )(1

    t

    n

    t

    t FDn

    MSE = =

    Where

  • 8/6/2019 A Case Study on Demand Forcasat

    8/17

    n=number of observation

    Dt=current demandFt=current forecast

    5.3.3 Mean absolute percentage error:

    =

    =

    n

    t t

    tt

    D

    FD

    nMAPE

    1

    100

    Wheren=number of observation

    Dt=current demand

    Ft=current forecast

    5.3.4 Cumulative Sum of Forecast Error:

    5.3.5 Mean forecast error:

    )(1

    1 t

    n

    t t

    FDn

    MFE =

    =

    5.4 Tracking signal:

    6.OUR STEPWISE OPERATIONS:

    6.1 DATA COLLECTION;

    We had collected all data used in our forecasting model from published e-books,

    Bangladesh bureau of statistics and websites. We collected data on population, electricityproduction, system loss and load shedding previous periods.

  • 8/6/2019 A Case Study on Demand Forcasat

    9/17

    Fig: Data obtained

    6.2 FORMULATION OF DATA: We then calculate shortage and demand from this data.

  • 8/6/2019 A Case Study on Demand Forcasat

    10/17

    Fig: Calculated demand and shortage

    Fig: demand vs population

    6.3 TIMESERIES ANALYSIS:

    6.3.1 Simple moving average:

    We plotted obtained data with reference of time and used simple moving average of one

    period to forecast short period demand in future.

  • 8/6/2019 A Case Study on Demand Forcasat

    11/17

    Fig: Simple moving average

    Fig; Excel sheet for calculation of single period moving average

  • 8/6/2019 A Case Study on Demand Forcasat

    12/17

    6.3.2 Trend analysis: Further trend analysis had been done to obtain forecasting on

    long horizon.

    Fig; Excel sheet for trend analysis;

    Fig; Excel sheet for trend analysis;

  • 8/6/2019 A Case Study on Demand Forcasat

    13/17

    Fig : Trend analysis

    Fig: Yearly increasing demand

  • 8/6/2019 A Case Study on Demand Forcasat

    14/17

    6.3 Casual model:6.3.1 Linear regression:

    !"

    # $%&"'% !" %"% %"%

    $#"%' $%&"'% #"& "# $

    $%%%"$$ $#"%' %'"' &%"%& '

  • 8/6/2019 A Case Study on Demand Forcasat

    15/17

    $!!! $'&" $%%%"$$ '# '#" $"#

    $!! $'$"& $'&" &"& $!%"%# %"#

    $!!$ $#!"&' $'$"& #$&" "' '"#

    $!!' '!'#"% $#!"&' !&"# $"'& &

    $!!% '%$"# '!'#"% %%"$ $''"& "

    $!!& '"& '%$"# &"$ $'%"$$ #"$

    $!! '!'"$ '"& $$"## $'%"&% "$

    () '!'"'

    *+ $#"'

    ,-./ '!'"$

    3.6

    0 1

    $"$ $'%"&% #$#!" $'" !"!

    $ $ $ !'# '&" !"!

    ' %!$"#$ %!$"#$ '&" %"& !"'

    % %#"' %#"' $!&"# "%& !"&

    & $" $" %$%%"& #'"%% !"

    #&"' #&"' &&!&''"$ $"& !"$

    # #$"% #$"% ##!#"% !"& !"$&

    !$" !$" !%&$ $&$"'% !"$

    $'" $'" $ &"# !"'

    ! $$&"# $$&"# &!$$#'

    !"'

  • 8/6/2019 A Case Study on Demand Forcasat

    16/17

    6.3.2 Demand vs. population regression analysis:

    Fig: Excel sheet

    Fig: scatter plot demand vs.. Population

    Fig: After adding trend line

  • 8/6/2019 A Case Study on Demand Forcasat

    17/17

    Conclusion :The most sensitive issue corresponding to modern human civilization is electricity

    except which everything will be destroyed. By our forecasting case study we haveevaluate trend of electricity demand after 14th periods (2020) is nearly seven thousand

    megawatt per hour. Due to the lacking of exact data of previous periods our forecasted

    model might not be totally reliable. Our forecasting model is enough able to demonstrate

    the demand patterns of electricity.

    References:

    1.Bangladesh power sector data bookPrepared by: Engr. Abdur Rouf, Engr. KM Nayeem Khan, Engr. Shazibul HoquePublished date: june 2006

    2.3rd International Conference on Electrical & Computer EngineeringICECE 2004, 28-30 December 2004, Dhaka, Bangladesh

    3. Source: IndexMundi.com

    Software used for calculation and forecasting: Microsoft excel