8 capital costs - rockymountainrail.orgrockymountainrail.org/documents/rmrabp_ch8_capital... ·...
TRANSCRIPT
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐1
8 Capital Costs
8.1 Introduction
The study team conducted an engineering assessment of infrastructure needed in cooperation with
the RMRA, freight railroads, Colorado DOT and in coordination with both the FasTracks and
Colorado Freight Rail Relocation (R2C2) studies. Towards the end of this chapter, vehicle costs are
estimated based on the Operating Plan developed in Chapter 5 to develop the total Capital cost of
the project.
The engineering assessment provides an evaluation of the current condition of the proposed
highway, greenfield, and railroad right‐of‐way alignments; identifies improvements to existing rail
lines needed to support the 79/110/150‐mph passenger service scenarios; and develops estimates for
new greenfield alignments for the 220‐mph and 300‐mph options. The engineering assessment is
presented in Chapter 3 of this report.
In addition to the engineering assessment, the capital costing methodology identifies rolling stock
(equipment) costs and land costs. Land costs are presented separately, as a placeholder for access to
railroad rights‐of‐way and for procurement of additional privately owned property where required
to construct new passenger rail infrastructure.
The engineering assessment and its findings and recommendations are preliminary and have not
been discussed in detail with the railroads. As discussed earlier, the Study is at a feasibility level, the
project is un‐funded and formal negotiations with the railroads have not been initiated. Future
Engineering Assessments require considerably more discussion to ensure railroad concurrence.
Final design concepts and recommended capital plans depend on detailed operations and capacity
analyses, design coordination and in‐depth discussions with the freight railroads. As the project
moves beyond the feasibility phase, railroad involvement and coordination become increasingly
important.
The engineering assessment was conducted at a feasibility level of detail and accuracy. Exhibit 8‐1
highlights the levels of accuracy associated with typical phases of project development and
engineering design. A low level of accuracy is associated with the evaluation of project feasibility;
while the highest level of accuracy is achieved during final design and production of construction
documents. The RMRA Feasibility Study is only the first step in the project development process. As
shown in Exhibit 8‐1, the level of accuracy typically associated with a Feasibility Study is +/‐ 30
percent. It had been suggested that a 30 percent contingency be added to these costs to reflect a
worst‐case scenario. However, the error range already covers this contingency. The cost estimate is
intended to be a mid‐range projection with equal probability of the actual cost moving up or down.
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐2
Exhibit 8‐1: Engineering Project Development Phases and Levels of Accuracy Development
8.2 Engineering Assessment
The first step in the Engineering Assessment is to divide each corridor into segments. Route
segments for existing railroad rights‐of‐way generally begin and end at major railroad control points
or rail stations. For greenfield alignments, segments begin and end at station points. Typical
corridors are divided into three to five route segments. Field inspections of the corridors have been
conducted. Chapter 3 and the Existing Conditions Report highlight the findings of the field
inspections.
A systematic engineering planning process was used to conduct the engineering assessment using
the five basic costing elements that were defined in Chapter 3:
Guideway and Track Elements
Structures – Approaches, Flyovers, Bridges and Tunnels
Systems
Crossings
Stations and Maintenance Facilities
Three auxiliary costing elements have been defined in the chapter as follow:
Right‐of‐Way and Land
Vehicles
Professional Services & Contingencies
The engineering assessment was based on these eight costing elements. In addition to the field
inspections and extensive work with GIS and railroad track charts, the assessment included a
thorough review of the alignment studies and estimated costs presented in the I‐70 Mountain
Corridor Programmatic Environmental Impact Study. Sato Associates, the prime consultant for the
Development Phases
Approximate Engineering Design Level*
Approximate Level of Accuracy**
Feasibility Study 0% +/- 30% or worse
Project Definition/Advanced Planning
1-2% +/- 25%
Conceptual Engineering 10% +/- 20%
Preliminary Engineering 30% +/- 15%
Pre-Final Engineering 65% +/- 15%
Final Design/Construction Documents
100% +/- 10% or better
*Percent of Final Design. **Percent of actual costs to construct. Table prepared by Quandel Consultants, LLC
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐3
Mountain Study, was extremely helpful in understanding the details concerning the PEIS alignment
for the rail alternative and the estimated infrastructure costs associated with the rail alternative.
Although the PEIS alignment was used in segments of the I‐70 corridor, the capital costs were
estimated as part of this Feasibility Study. The PEIS capital cost estimates were within a reasonable
range of the Feasibility Study estimates when adjusted for inflation.
8.3 Development of Unit Construction Capital Costs
8.3.1 Base Set of Unit Costs
The study team developed unit costs in 2008 dollars for the design and construction of high‐speed
passenger rail and maglev infrastructure on a series of previous planning projects. Initially the unit
costs were applied to planned construction in the Midwest to implement the Midwest Regional Rail
Initiative. Later the costs were applied to capital cost estimates for high‐speed rail in Florida, Ohio,
Minnesota and California.
The base set of unit costs addresses typical passenger rail infrastructure construction elements
including: roadbed and trackwork, systems, facilities, structures, and grade crossings.
The unit costs have been evaluated by peer panels, freight railroads and contractors. The values
have been found to be reasonable for developing the capital costs under normal contractor bidding
procedures and under railroad force account agreements for construction. It should be noted that in
two cases the costs have not been sufficient, specifically:
DBOM procurement, where the contractor takes on large future operating risks and seeks to
front load the risk in the initial construction.
Rail alignments constructed in narrow highway medians under congested urban traffic.
The unit costs were developed and evaluated in the period between January 2000 and June 2002.
Two questions must be considered in applying these costs to high‐speed rail planning in Colorado:
1. Relative Costs: Are the costs reasonable for rail construction in Colorado considering local
costs of materials and labor?
2. Cost Escalation: How should the costs be escalated from the nominal June 2002 values to
current values considering the historical changes in construction costs?
A variety of indices are employed to monitor construction costs throughout the United States.
However, no publicly available index exists for rail construction. In addition, relatively few recent
examples of completed intercity passenger rail construction are found. This is especially true for
high‐speed applications.
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐4
8.3.2 Relative Costs
The Engineering News Record tracks a Building Cost Index (BCI) and a more general Construction
Cost Index (CCI) in major cities and averages the values to produce national indices. It is reasonable
to assume that the CCI is a better indicator of regional cost differences for a transportation project
than the BCI. The CCI is calculated as the sum of 200 hours of local (union) common labor including
fringes plus the local cost of 1.128 tons of Portland cement plus the national average price of 25cwt
of fabricated structural steel. The CCI’s from 1990 to 2008 indicate that construction costs in Denver
have typically been 20‐30 percent lower than national construction costs, and 25‐40 percent lower
than the average of costs in the Midwest. There is however, considerable variability in the Midwest
costs between cities: for example, Kansas City has had an even lower CCI than Denver over the
period.
To some extent, the construction cost of relatively specialized products and systems is independent
of local regional costs. In the case of railroad construction, the costs of key materials such as rail,
concrete ties and signal equipment are relatively uniform throughout the country. Similarly, the
cost of skilled labor and mechanized track laying systems will be similar in all locations. These
factors tend to diminish the regional construction cost differences.
8.3.3 Cost Escalation
Many State DOTs prepare periodic highway construction cost indices based on the tabulated bid
prices of earthwork, asphalt pavement, concrete pavement, structural concrete, reinforcing steel and
structural steel to assemble a composite index tied to base year costs in 1987. The State of
Washington publishes the indices for the states of Washington, California, Colorado, Oregon, South
Dakota, Utah and an FHWA composite. (The FHWA discontinued preparing the composite index in
2006). This data cannot be used to compare the absolute costs of highway construction among
states, but may be used to compare the price trends. Comparing the indices over the 6 year period
from 2002 to 2008, the Colorado index has outpaced the others, increasing by a factor of 2.21
compared to an average of 1.91 for the six states.
The Bureau of Labor Statistics prepares a variety of monthly, national Producer Price Indices, which
are often used for escalation cost adjustments in construction projects. Two such indices may be
suitable for our application, the Highway and Street Construction Index (PCUBHWY) and the Other
Heavy Construction Index (PCUBHVY). A computation of escalation from June 2002 to January
2009 using either index yields similar results (HWY=51%, HVY=44%), but as the highway index is
heavily influenced by the costs of petroleum products such as asphalt, it is reasonable to assume that
the Other Heavy Construction Index is more suitable for our purpose.
8.3.4 Unit Price Adjustment
Based on the available data, it is reasonable to believe that the June 2002 unit costs developed for the
Midwest can be adjusted downward for use in Colorado during the same time period. Considering
the regional CCI difference and the relative uniformity of railroad material prices, an adjustment
factor of 0.85 is reasonable.
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐5
While the BLS PPI suggests a national escalation factor of 1.44 for the period, the coincident
Colorado DOT highway cost escalation factor of 2.21 is significant and suggests that construction
cost escalation in Colorado exceeds that represented in the BLS value. The State of Colorado DOT
has attributed much of the highway cost escalation to a regional shortage of Portland cement and
high worldwide demand for asphalt, petroleum products and steel.
While the cost of rail construction is energy intensive due to the requirement for extensive grading
to achieve desirable grades and curves, it is less so than highway construction, which uses
petroleum products such as asphalt as a construction material. While a precise methodology for
discounting the observed Colorado highway cost inflation does not exist, it is reasonable to believe
that the regional escalation factor for rail construction over the period lies somewhere between the
BLS PPI value of 1.44 and the CDOT value of 2.21. An average of the two values yields 1.825. The
Unit Price Regional and Escalation Analysis is included in Appendix F.
Therefore the unit cost adjustment value considering regional cost differences and inflation from
June 2002 to December 2008 is computed as follows:
Colorado Unit Cost (2008) = MWRRI Unit Cost (2002) x 0.85 x 1.825
8.3.5 Unit Capital Costs for Colorado – Steel Wheel/Steel Rail
Trackwork and Land Acquisition
The FRA requires that passenger trains operating on the general railroad system comply with
stringent crashworthiness standards. Neither the FRA nor the Federal Highway Administration
(FHWA) has addressed requirements for mode separation of high‐speed passenger rail equipment
operating in close proximity to highway traffic. Similarly, the FRA has not developed general rules
for non‐compliant passenger equipment operating in railway corridors adjacent to freight rail tracks.
For the purposes of defining requirements necessary to proceed with the study and in order to
develop planning level capital costs, it has been assumed that highway traffic and adjacent high‐
speed vehicles will be separated by concrete barriers. On tangent highway and track segments, there
exists a small probability that automotive vehicles will leave the highway. Thus, protection against
highway traffic incursions into the high‐speed rail median would be provided using NCHRP Report
350 Level 5 highway concrete barrier walls. In curved median segments, where accidents are more
likely, we have planned for NCHRP Level 6. It is anticipated that high‐speed rail systems in the
freight rail corridors will be separated by at least 25 ft between track centers, minimizing any need
for physical protection. Chain link fencing will be provided throughout the system in all corridors to
prevent the intrusion of trespassers and animals. These planning assumptions may be subject to
modification as a result of federal or state rule making.
Land acquisition costs for right‐of‐way owned and controlled by the railroad industry is always an
issue when attempting to introduce new passenger rail service. Since its inception, Amtrak has had
the statutory right to operate passenger trains over freight railroad tracks and rights‐of‐way. When
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐6
using freight tracks, Amtrak is required to pay only avoidable costs for track maintenance along
with some out‐of‐pocket costs for dispatching1.
Amtrak’s payments do not include any access fee for the use of a railroad’s tracks or its rights‐of‐
way. Amtrak’s federal statutory right‐of‐access has never required such a payment, and therefore,
Amtrak avoids paying a fee or “rent” for occupying space on privately held land and facilities.
In the case of the RMRA high‐speed rail routes, Colorado Department of Transportation has already
begun a discussion with the freight railroads on the development of a bypass for Denver, Colorado
Springs, and as far south as Pueblo and Trinidad. (See the CDOT Rail Relocation Implementation
Study, Jan. 2009). While these discussions are still embryonic, there is clearly a case for providing a
negotiated swap of right‐of‐way with one or perhaps both of the freight railroads.
While the RMRA may choose a different course, the final determination of what a Colorado
passenger rail system will pay host freight railroads for use of their tracks and rights‐of‐way will
ultimately be accomplished through negotiations.
This study assumes that a cost for access based on estimated across‐the‐fence land values would be
included as part of the up‐front capital expense, and would be used to purchase the rights to use the
underlying railroad rights‐of‐way for the passenger service. It is assumed that railroads would
receive this compensation in cases where the construction of a dedicated high‐speed passenger track
is on their property. If new track cannot be constructed within the existing railroad rights‐of‐way,
then this cost would fund the possible acquisition of adjacent property.
Elsewhere land will need to be purchased directly from land owners. Where highway rights‐of‐way
were used, the study assumed that right of way or air rights access would be granted by Colorado
Department of Transportation at no cost to the rail system.
The outright purchase of land is not the only method whereby railroads could receive compensation
for access to railroad rights‐of‐way. Commuter rail development provides examples of various types
of payments for access rights. Some of these projects involved the purchase of the railroad rights‐of‐
way while others provide up‐front capital improvements in return for access to a railroad’s tracks.
The actual methods of payment remain to be determined during negotiation, and may depend on
the importance of the track to the freight railroad as well as the level of capital to be invested by the
passenger rail authority.
1 However, these payments do not cover all of the freight railroads’ incremental costs associated with dispatching Amtrak’s passenger trains. Railroad costs increase due to delays caused by Amtrak’s tightly scheduled trains. Track capacity constraints and bottlenecks create unreliable conditions where train delays often become unavoidable. While federal regulations give passenger trains dispatch priority, railroad dispatchers often encounter congestion where it becomes difficult to control traffic and adhere to Amtrak’s timetables. In some cases, Amtrak will offer the railroads a payment to provide on-time passenger train performance. On heavily used line segments, however, these incentive payments only partially compensate a railroad for the costs of increased delay, and some railroads simply refuse to accept incentive payments. On lightly used lines, the economic rationale for making these payments is questionable since passenger trains cause very little delay on such tracks.
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐7
One area of possible concern is the freight railroads’ ability to retain operating control over their
rights‐of‐way. Whenever transit systems have paid full price to acquire a freight rail line, as on some
commuter rail projects, the transit agencies have assumed operating control over the property.
However, this study has assumed that the freight railroads would retain dispatching control over
these rights‐of‐way. The railroads would have the right to use the increased capacity provided by
the passenger system for its high‐speed freight services.
For budgetary purposes, this study assumes an over‐the‐fence methodology for appraising the
maximum value of railroad rights‐of‐way. To estimate land values, two land uses alongside each
corridor are identified:
Rural (e.g., farmland),
Urban (e.g., high density residential, commercial, and industrial areas)
The value of a 50‐foot wide right‐of‐way was established for each land use and the total land cost of
the railroad corridor was estimated. Urban land rates were used in mountain resort areas such as
Vail and Avon that have very high real estate prices. In the case of Vail no additional land cost
needed to be assumed because the proposed rail alignment would be elevated over the existing I‐70
highway alignment, thus was assumed to be granted to the project in that specific location.
Right‐of‐way cost was developed for the greenfield alternatives using the conceptual alignments
and general land use designations. A 100 foot right‐of‐way was assumed. Where the alignment falls
within an existing publicly‐owned right‐of‐way, such as a highway or street alignment, no cost to
the project for that particular right‐of‐way has been assumed. Where the geometric requirements
take the alignment outside of the public right‐of‐way, impacted parcels were evaluated and a square
foot quantity calculated. A unit cost per acre was developed in conjunction with other studies.
Exhibit 8‐2 shows the unit cost for track work and land acquisition in 2008 dollars by project
element.
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐8
Exhibit 8‐2: Unit Capital Costs, Track work and Land Acquisition, in $2008
Item No. Description Unit Unit Cost
(Thousands of $2008)
1.1 HSR on Existing Roadbed (Single Track) per mile $1,174.90
1.2 HSR on Existing Roadbed (Double Track) per mile $2,350.00
1.3 HSR on New Roadbed & New Embankment (Single Track) per mile $1,765.30
1.4 HSR on New Roadbed & New Embankment (Double Track) per mile $3,163.90
1.5 HSR Double Track on 15' Retained Earth Fill per mile $16,711.30
1.6 Timber & Surface w/ 33% Tie replacement per mile $262.70
1.7 Timber & Surface w/ 66% Tie Replacement per mile $391.60
1.8 Relay Track w/ 136# CWR per mile $418.90
1.9 Freight Siding per mile $1,079.10
1.10 Passenger Siding per mile $1,628.10
1.11 NCHRP Class 6 Barrier (on curves) lineal ft $1.30
1.12 NCHRP Class 5 Barrier (on tangent) lineal ft $0.20
1.13 Fencing, 4 ft Woven Wire (both sides) per mile $60.30
1.14 Fencing, 6 ft Chain Link (both sides) per mile $181.00
1.15 Fencing, 10 ft Chain Link (both sides) per mile $207.10
1.16 Decorative Fencing (both sides) per mile $466.20
1.17 Drainage Improvements (cross country) per mile $78.10
1.18 Drainage Improvements in Median or along highway per mile $624.70
1.19 Land Acquisition Urban and Resort (100’ of ROW) per mile $386.90
1.20 Land Acquisition Rural (100’ of ROW) per mile $129.00
1.21 #33 High-Speed Turnout each $672.00
1.22 #24 High-Speed Turnout each $532.40
1.23 #20 Turnout Timber each $146.70
1.24 #10 Turnout Timber each $81.60
1.25 #20 Turnout Concrete each $294.60
1.26 #10 Turnout Concrete each $139.60
1.27 #33 Crossover each $1,344.10
1.28 #20 Crossover each $590.00
1.29 Elevate & Surface Curves per mile $68.60
1.30 Curvature Reduction per mile $465.00
1.31 Elastic Fasteners per mile $97.00
Structures: Approaches, Flyovers, Bridges, and Tunnels
A complete inventory of bridges has been developed for each existing rail route from existing track
charts. For estimating the cost of new bridges on either green field alignments or along existing rail
beds, conceptual engineering plans were used for a bridge to carry either single or double tracks
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐9
over highways, streams, valleys, and rivers. Some bridges require rehabilitation on the abutments
and superstructure. This type of work includes pointing of stone abutment walls, painting of
bridges, and replacement of bearings. Many of the major bridge cost estimates will be estimated only
as placeholders, which will be subject to more detailed engineering analysis in the future.
Rail route alternatives through the Rocky Mountains require a significant amount of tunneling to
maintain operable grades, avoid areas prone to rock falls and avalanches, and to provide the
shortest routes. Several tunnel configurations were considered. For this study, a two bore tunnel
with cross passages is used for long and deep tunnels, whereas a single bore tunnel is used where
the length is 1000 feet or less. Tunneling costs lie within the $20‐73 thousand per linear foot range
cited in Appendix G, where the higher cost was from the long undersea English Channel tunnel; but
the estimates in Exhibit 8‐3 are considered more appropriate benchmarks for the probable cost of
Colorado tunnels. Exhibit 8‐3 details the unit costs in 2008 dollars.
Exhibit 8‐3: Unit Capital Costs, Structures in $2008
Item No. Description (Bridges-under) Unit
Unit Cost (Thousands of
$2008)
2.1 Four Lane Urban Expressway (Rail over Highway) each $5,720.80
2.2 Four Lane Rural Expressway (Rail over Highway) each $4,762.40
2.3 Two Lane Highway (Rail over Highway) each $3,613.50
2.4 Rail (New Rail over Existing Rail) each $3,613.50
2.5 Minor river each $958.40
2.6 Major River each $9,581.60
2.7 Double Track High (50') Level Bridge per LF $14.40
2.8 Rehab for 110 per LF $16.60
2.9 Convert open deck bridge to ballast deck (single track) per LF $5.50
2.10 Convert open deck bridge to ballast deck (double track) per LF $11.10
2.11 Single Track on Flyover/Elevated Structure per LF $5.00
2.12 Single Track on Approach Embankment w/ Retaining Wall per LF $3.50
2.13 Double Track on Flyover/Elevated Structure per LF $8.00
2.14 Double Track on Approach Embankment w/ Retaining Wall per LF $6.50
2.15 Ballasted Concrete Deck Replacement Bridge per LF $2.50
2.16 Land Bridges per LF $3.10
2.17 Four Lane Urban Expressway (Highway over Rail) each $2,469.40
2.18 Four Lane Rural Expressway (Highway over Rail) each $3,465.60
2.19 Two Lane Highway (Highway over Rail) each $2,251.60
2.20 Rail (Existing Rail over New Rail) each $7,229.40
2.21 Two Bore Long Tunnel route ft $44.00
2.22 Single Bore Short Tunnel lineal ft $25.00
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐10
Systems
The capital cost estimates for this study include costs to upgrade the train control and signal
systems. Unit costs for system elements are shown in Exhibit 8‐4. Under the 79‐mph scenario, capital
costs include the installation of Centralized Train Control (CTC) with interlockings and electric locks
on industry turnouts and a PTC overlay suitable for operation at that speed. Under the 110‐mph or
higher speed scenarios, the signal improvements include the added costs for a vital PTC signal
system.
Most U.S. railroads that allow or provide passenger and freight service operate under manual
control with wayside signals. Centralized traffic control or CTC signaling is provided on busy
corridors including Amtrak’s Northeast Corridor. FRA requires that passenger service exceeding 79
mph operate with cab signaling/automatic train protection or automatic train stop to provide
protection against operator errors. In addition, FRA is currently sponsoring demonstration projects
to develop a universal communications based train control system, known as positive train control
or PTC. New high‐speed passenger service will include sophisticated signal systems to comply with
FRA mandates and provide safe, reliable operations. Such signal systems include train borne
components and wayside equipment such as track circuits, switch operators, and wayside detectors
for protection against intrusion, high water, hot bearings and dragging equipment.
Modern signal systems rely on digital communication systems for data transmission using radio,
fiber optic cables or a combination or the two. In addition, the communication system provides radio
for operations, supervisory control and data acquisition for power systems, passenger station public
address, etc. Wayside space must be provided for ducts and enclosures to house signal and
communication components.
Electrified high‐speed rail options require traction power substations and distribution facilities. It is
assumed that the existing Colorado electrical grid and generating facilities contain sufficient
capacity to support an electrified rail system. Similarly, the electric utility is expected to provide
substations, transmission equipment and connections to the utility network with such costs covered
in the utilization charges. As such, it is assumed that the electric utility would amortize the costs for
bringing power to the substations, so the costs of modifications to the utility’s grid are not included
in the electrification cost estimate. Neither has the potential benefit from the electric utilities’
potential ability to use the rail or maglev right‐of‐way for power transmission been assessed. (Such
joint development could largely offset the utility’s cost for connecting the rail or maglev system into
the power supply.) Typical requirements for electrification include substations at 25 mile intervals
and distribution conductors. In the case of electrified rail systems, overhead catenary conductors
provide power to the train pantograph and the rails serve as return conductors. The catenary
conductors are supported by poles and cross arms spaced at roughly 100‐150 foot intervals. The
catenary system contact wire is generally located 17.5 to 23 ft above the top of the rail. Additional
electrical clearance or high voltage insulation is required to overhead bridge structures.
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐11
Exhibit 8‐4: Unit Capital Costs, Systems, in $2008
Item No. Description Unit
Unit Cost (Thousands of
$2008)
3.1 Signals for Siding w/ High-Speed Turnout each $1,500.30
3.2 Install CTC System (Single Track) per mile $216.50
3.3 Install CTC System (Double Track) per mile $355.00
3.4 Install PTC System per mile $171.00
3.5 Electric Lock for Industry Turnout each $121.90
3.6 Signals for Crossover each $828.20
3.7 Signals for Turnout each $473.30
3.8 Signals, Communications & Dispatch per mile $1,539.70
3.9 Electrification (Double Track) per mile $3,079.50
3.10 Electrification (Single Track) per mile $1,539.70
Crossings
The treatment of grade crossings to accommodate 110‐mph operations on existing rail is a major
challenge to planning a high‐speed rail system. Highway/railroad crossing safety plays a critical role
in future project development phases. A variety of devices were considered to improve safety
including roadway geometric improvements, median barriers, barrier gates, traffic channelization
devices, wayside horns, fencing and the potential closure of crossings. Greenfield routes were
developed with grade separations at street and roadway crossings. Exhibit 8‐5 details the unit costs
for highway and railroad grade crossings. Chapter 4 contains additional information concerning the
crossing costs.
Exhibit 8‐5: Unit Capital Costs, Crossings, in $2008
Item No. Description Unit
Unit Cost (Thousands of
$2008)
4.1 Private Closure each $98.20
4.2 Four Quadrant Gates w/ Trapped Vehicle Detector each $582.10
4.3 Four Quadrant Gates each $340.80
4.4 Convert Dual Gates to Quad Gates each $177.50
4.5 Conventional Gates single mainline track each $196.40
4.6 Conventional Gates double mainline track each $242.60
4.7 Convert Flashers Only to Dual Gate each $59.20
4.8 Single Gate with Median Barrier each $213.00
4.9 Convert Single Gate to Extended Arm each $17.70
4.10 Precast Panels without Roadway Improvements each $94.70
4.11 Precast Panels with Roadway Improvements each $177.50
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐12
Station/Maintenance Facilities
Passenger stations include platforms, escalators/elevators and other circulation elements, passenger
ticketing and waiting facilities, lighting security, and station administration facilities.
The terminal stations may require four tracks for passenger boarding, train layover and light
maintenance.
A maintenance facility with sufficient capacity to service the fleet is required. The facility must
provide space and equipment to service the rolling stock and maintain the track structure and
systems. Storage tracks can be expanded as the fleet grows. Sophisticated component repair may be
subbed out to contract shops. It is anticipated that the maintenance facility for a non‐electrified
system will be less sophisticated than that of an electrified rail system. Exhibit 8‐6 shows the unit
costs for types of stations, terminals, and maintenance facilities
Exhibit 8‐6: Unit Capital Costs, Railroad Station/Maintenance Facilities, in $2008
Item No. Description Unit
Unit Cost (Thousands of
$2008)
5.1 Full Service - New - Low Volume - 500 Surface Park each $5,000.00
5.2 Full Service - Renovated - Low Volume- 500 Surface Park each $4,000.00
5.3 Terminal - New - Low Volume - 500 Surface Park each $7,500.00
5.4 Terminal - Renovated - Low Volume - 500 Surface Park each $6,000.00
5.5 Full Service - New- High Volume - Dual Platform - 1000 Surface Park each $10,000.00
5.6 Terminal - New- High Volume - Dual Platform - 1000 Surface Park each $15,000.00
5.7 Maintenance Facility (non-electrified track) each $80,000.00
5.8 Maintenance Facility (electrified track) each $100,000.00
5.9 Layover Facility lump sum $10,000.00
8.3.6 Unit Costs for Colorado – Maglev
Magnetic Levitation Technology Systems
Capital costs were developed for two types of magnetic levitation technologies as follows:
High‐speed magnetic levitation (LSM) technology, represented by the German TransRapid
system with speeds from 250 to 300 mph. The system will be constructed in new, fully grade
separated corridors and will not share right‐of‐way with the freight railroads.
Urban magnetic levitation (LIM) technology, represented by Japanese CHHST, with speeds
up to 125 mph. The system will be constructed in new; fully grade separated corridors and
will not share right‐of‐way with the freight railroads.
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐13
For the purposes of this study, the only difference in unit costs between the two types is the systems
unit costs as further detailed below.
Right‐of‐Way Costs
Maglev right‐of‐way costs were developed for each alternative using the conceptual routes. A 100‐
foot‐wide right‐of‐way was assumed. Where the route fell within an existing public right‐of‐way,
such as highway, street, or rail, no cost to the project for that particular right‐of‐way is assumed.
Where the geometric requirements for Maglev take the route of the public right‐of‐way, the costs
were determined for either rural or urban area. Units costs are based on a per mile basis using
average values of $10,750 per acre for rural and $32,000 per acre for urban land acquisition. The unit
costs on a per mile basis are shown in Exhibit 8‐7. This unit cost estimate is based only on the
current conceptual routes and will change as the project development progresses.
Exhibit 8‐7: Unit Capital Costs, Right‐of‐Way, in $2008
Description Unit
Unit Cost (Thousands of
$2008)
Land Acquisition Rural Mile $129.0
Land Acquisition Urban Mile $ 387.0
Guideway and Track Elements
Maglev guideway costs were developed for at‐grade, aerial and bridge structures and tunnels. The
guideway system is comprised of a concrete and/or steel guideway to support the vehicles, stator
packs, power rails, low‐speed switches and high‐speed switches. The types of guideways and tunnel
sections used in this estimate are detailed Chapter 4 of this report. All civil engineering costs
associated with the construction of the guideways are included in the unit costs
A unit cost of $3,400 per lineal foot is used for at‐grade guideways. A unit cost of $6,600 per lineal
foot is used for Type A aerial structures. A unit cost of $8,800 per lineal foot is used for the Type B
aerial structure. Type B is a straddle‐bent aerial structure needed to carry the guideway over public
roadways and other obstacles encountered on the alignment. The unit cost for these guideways
includes an allowance of 15 percent for special guideways required for project elements such as
crossovers between guideways and tail structures at end stations for storage of train sets in off‐peak
hours.
A unit cost of $25,800 per lineal foot is used for the bridge structure required to carry the guideway
over deep valleys and major rivers.
A unit cost of $33,600 per lineal foot is used for a Type A tunnel section consisting of two tunnels for
the guideway. A unit cost of $44,800 per lineal foot is used for a Type B tunnel section consisting of
two tunnels and a service/relief tunnel. Appendix G is a technical memorandum, Rail Tunnel
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐14
Evaluation that was prepared as a guide for this study. Exhibit 8‐8 summarizes the unit costs for
guideway and track elements.
Exhibit 8‐8: Unit Capital Costs, Maglev Guideway & Track, in $2008
Description Unit
Unit Cost (Thousands of
$2008)
At Grade Guideway LF $3.4
Aerial Guideway Type A (Low) LF $6.6
Aerial Guideway Type B (High) LF $8.8
Bridge LF $25.8
Tunnel Type A (Single Bore) LF $33.6
Tunnel Type B (Dual Bore) LF $44.8
Systems
Propulsion, control and communication systems include civil structures for substations and cable
trenches; propulsion blocks; propulsion equipment for low, medium, and high power; motor
windings; wayside equipment; propulsion maintenance equipment; operation control subsystems
for communication and data collection, and associated civil structures. A unit cost of $18,368,000 per
mile, as shown in Exhibit 8‐9, is used to estimate the cost of the very high‐speed maglev.
Exhibit 8‐9: Unit Capital Costs, Maglev Systems, in $2008
Description Unit
Unit Cost (Thousands of
$2008)
Propulsion, Command & Control Systems Mile $18,368
Power Distribution Mile $1,389
Power distribution unit costs were determined by a review of similar costs for the FRA
demonstration projects. The unit cost used for this project is $1,389,000 per mile for very high‐speed
systems.
The sum of the Propulsion, Command & Control Systems and the power unit costs is approximately
$19.7 Million per mile for very high‐speed systems using liner synchronous motor (LSM)
technology. The systems costs for the urban maglev is approximately $7.7 Million per mile based on
information provided by Sandia National Laboratories during the development of the I‐70 Mountain
Programmatic Environmental Study.
Maintenance Facilities
Maintenance facilities and storage yards include the construction and all equipment necessary to
properly maintain the fleet of vehicles. The size of the maintenance facility is related to the size of
the maglev fleet needed for this program. The unit cost of $3,080,000 per section (or car) of a maglev
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐15
train set for this study is determined by averaging the cost of the maintenance facilities for
Baltimore‐ Washington and the Pittsburgh projects adjusted to year 2008 dollars.
Exhibit 8‐10: Unit Capital Costs, Maglev Maintenance Facilities in $2008
Description Unit
Unit Cost (Thousands of
$2008)
Maintenance Facilities Sections $3,080
Stations and Parking
Stations and Parking Facilities include platforms, circulation, lighting, security measures and all auxiliary
spaces. Space is provided for ticket sales, passenger information, station administration, baggage
handling and commercial space. Exhibit 8‐11 provides unit costs for various station types.
Exhibit 8‐11: Unit Capital Costs, Stations & Parking in $2008
Description Unit
Unit Cost (Thousands of
$2008) Full Service - New - Low Volume - 500 Surface Park each $5,000
Full Service - Renovated - Low Volume- 500 Surface Park each $4,000
Terminal - New - Low Volume - 500 Surface Park each $7,500
Terminal - Renovated - Low Volume - 500 Surface Park each $6,000
Full Service - New- High Volume - Dual Platform - 1000 Surface Park each $10,000
Terminal - New- High Volume - Dual Platform - 1000 Surface Park each $15,000
8.4 Other Costs
8.4.1 Contingency
Contingency costs were added as an overall percentage of the total construction cost. Contingencies
are an allowance added to the estimate of costs to account for items and conditions that cannot be
realistically anticipated. The contingency is expected to be needed as the project develops. The
contingency is estimated at 30 percent of the construction cost elements. This contingency included
15%+ for design contingency and 15%+ for construction contingency.
8.4.2 Professional Services and Environmental
The project elements included in the Professional Services category are design engineering, program
management, construction management and inspection, engineering during construction, and
integrated testing and commissioning. For a project of this size, an overall program manager with
several section designers is needed to provide conceptual engineering, preliminary engineering,
environmental studies, geotechnical engineering, final engineering and engineering during
construction. Field and construction management services and integrated testing services and
commissioning of various project elements also are required. Professional services and other soft
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐16
costs required to develop the RMRA project have been estimated as a percentage of the estimated
construction cost and are included in the overall cost estimates as a separate line item. These costs
include, as a percentage of construction cost:
Design engineering and related studies 10%
Insurance and Bonding 2%
Program Management 4%
Construction management and inspection 6%
Engineering services during construction 2%
Integrated Testing and Commissioning 2%
Erosion Control and Water Quality Mgt 2%
8.4.3 Placeholders
The capital costs include allocation for special elements (placeholders) as conservative estimates for
large and/or complex engineering projects that have not been estimated on the basis of unit costs
and quantities. Placeholders provide lump sum budget approximations based on expert opinion
rather than on an engineering estimate and are shown in the unit costs as lump sum items.
Placeholders are used where detailed engineering requirements are not fully known. These costs
will require special attention during the project development phase. The following list highlights
some of the key placeholder costs that are assumed in this analysis. Cost details are shown on the
detailed sheets in Appendix E:
Costs for new stations in densely built‐up urban areas, including Denver Union Station
improvements
Major tunnel improvements
Rail capacity expansion
Maintenance and layover facilities
8.5 Infrastructure Capital Costs
As route segments were examined in the field, general concepts were developed and assumptions
made regarding the capacity and operational improvements needed to accommodate future
passenger operations. The primary objective was to conceptualize infrastructure improvements that
would improve fluidity and enhance the reliability of both passenger and freight rail operations.
In order to account for the interactive analysis needed to optimize the trade‐off of capital costs with
operational consideration, the study corridors were further segmented to allow for a mix and match
scenario that was driven by technology consideration. Civil engineering quantities were developed
for each segment using the results of the field inspections combined with data derived from GIS and
railroad track charts. Infrastructure capital cost estimates by segment were prepared for each study
corridor for steel wheel/steel rail, very high‐speed maglev and urban maglev. Segments were
identified for existing rail routes and constrained and unconstrained greeenfield routes. The
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐17
following summarizes the key results of the initial screening of alternatives. The full screening
process is described in Chapter 9. For the purpose of this screening, a set of capital costs were
developed for each route/alignment option, or Representative Route as described in Chapter 4. The
detailed cost estimates by segment are in Appendix E.
Infrastructure costs, shown in Exhibit 8‐12, were developed for upgrading the existing rail lines in
the I‐25 corridor to 79‐mph and 110‐mph standards. Infrastructure costs for either 79 mph or 110
mph were thought to be practically identical, due to the need for heavy freight capacity mitigation in
the I‐25 corridor which requires extensive use of dedicated passenger infrastructure, regardless of
speed. The only real difference is in vehicles, which have a lower cost in the 79‐mph option, due
primarily to the lower level of service offered and corresponding fewer number of vehicles that
would need to be purchased.
Exhibit 8‐12: Incremental Rail in I‐25 Upgrade Costs
Capital Costs by Route and Technology (Billions $2008)
Capital Cost per Mile (Millions $2008)
Infrastructure costs, shown in Exhibit 8‐13, were developed for both electric rail options (150 mph
and 220 mph) and for maglev options (125 mph and 300 mph.) All of these costs were developed for
the full RMRA network including service to Grand Junction, Aspen, Craig and Black Hawk in the
west, and to Cheyenne and Trinidad in the north and south. It can be seen that development of
either of the two Maglev options would cost substantially more than would the rail options. As
shown in Exhibit 8‐13, a maglev system would cost two to three times that of a comparable rail
system for only a few minutes difference in running time performance. This is because curves and
the relatively short distances between stations fundamentally limit train performance, and maglev
systems guideway structures are much more expensive than railroad guideway structures.
Existing Rail I-25 79 mph 110 mph
Miles 347.50 347.50
Capital Cost per Mile $10.78 $11.08
Existing Rail I-25 79 mph 110 mph
Infrastructure $3.57 $3.57
Vehicle $0.18 $0.28
Total $3.75 $3.85
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐18
Exhibit 8‐13: High‐Speed Rail in Both I‐25 and I‐70 Upgrade Costs
It should be noted that the capital costs in Exhibit 8‐13 are very high, which led to difficulties with
Cost Benefit ratios in the initial screening of options. See Chapter 9. Accordingly, a strategy for
“truncating” or shortening the network as shown in Exhibit 8‐14 was developed, for reducing the
capital cost. (This schematic shows only the mainline that makes up the major costing segments,
without branch lines.)
* N/A means the train technology cannot operate over this alignment.
Capital Costs by Route and Technology (Billions $2008)
Constrained I-70 7% Route/ Greenfield I-25
125 mph 150 mph 220 mph 300 mph
Infrastructure $66.94 N/A $35.59 $75.93
Vehicle $1.92 N/A $1.02 $2.44Total $68.86 N/A $36.61 $78.37
Unconstrained I-70 4% Route/ Existing Rail I-25
125 mph 150 mph 220 mph 300mph
Infrastructure $72.86 $28.56 $28.56 $82.42
Vehicle $1.73 $0.66 $0.66 $2.32Total $74.59 $29.21 $29.21 $84.73
Capital Cost per Mile (Millions $2008)
Constrained I-70 7% Route/ Greenfield I-25
125 mph 150 mph 220 mph 300 mph
Miles 747.44 N/A 747.44 747.44
Capital Cost per Mile $92.13 N/A $48.98 $104.85Unconstrained I-70 4% Route/
Existing Rail I-25 125 mph 150 mph 220 mph 300 mph
Miles 795.54 795.54 795.54 795.54
Capital Cost per Mile $93.76 $36.72 $36.72 $106.51
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐19
Exhibit 8‐14: Major Capital Cost Segments
Costs estimates for the two network options, based on either an I‐70 Right‐of‐Way or I‐70
Unconstrained alignment, coupled with a new Greenfield alignment or Existing Rail in I‐25,
respectively, were developed based on the segmentation shown in Exhibit 8‐14. These results are
shown in Exhibits 8‐15 and 8‐16.
Comparing these two figures it can be seen that the I‐70 Right‐of‐Way (or Constrained) / I‐25
greenfield option in Exhibit 8‐16 generates substantially more revenue, primarily because of the
strength of the greenfield alignments both on I‐25 and on the Western extensions. Also, the same
exhibit shows that I‐70 costs from Denver to Eagle Airport comprise a lower percentage of total cost,
because of the very high costs of these greenfields on I‐25 and in the west.
The most important thing to note is the relatively high share of revenue (93 percent and 95 percent,
respectively) that is associated with a “Core” system that extends from Fort Collins to Pueblo, and
from Denver International Airport (DIA) to Eagle Airport. By eliminating the high‐cost extensions to
Trinidad, Cheyenne and the three western destinations, the cost of the system could be dramatically
reduced without losing much revenue. (Please note that these extensions were all costed as double‐
track electrified rail or maglev options. The possibility of providing a lower cost diesel service for
these Western extensions was not evaluated by this study.)
Zone 1 – I-25 Main
Zone 2 – DIA Branch
Zone 3 – I-70 Main
Zone 5 – I-25 Extensions
Zone 4 – I-70 Extensions
LEGEND
Zone 1 – I-25 Main
Zone 2 – DIA Branch
Zone 3 – I-70 Main
Zone 5 – I-25 Extensions
Zone 4 – I-70 Extensions
LEGEND
Zone 1 – I-25 Main
Zone 2 – DIA Branch
Zone 3 – I-70 Main
Zone 5 – I-25 Extensions
Zone 4 – I-70 Extensions
LEGEND
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐20
Exhibit 8‐15: Capital Cost Distribution for Unconstrained I‐70/Existing Rail on I‐25: 150‐mph Electric
Exhibit 8‐16: Capital Cost Distribution for I‐70 Right‐of‐Way/Greenfield on I‐25: 220‐mph Electric Rail
54% of Capital generates 95% of Revenue
17%
1%
36%
36%
10%
Zone 1- I-25 Main
Zone 2 - DIA Branch
Zone 3 - I-70 Main
Zone 4 - I-70 Extensions
Zone 5 - I-25 Extension
17%
1%
36%
36%
10%
Zone 1- I-25 Main
Zone 2 - DIA Branch
Zone 3 - I-70 Main
Zone 4 - I-70 Extensions
Zone 5 - I-25 Extension
Key
ER: I-25 Existing RailGF: I-25 GreenfieldRW: I-70 Right of Way 7%UC: I-70 Unconstrained 4%
Key
ER: I-25 Existing RailGF: I-25 GreenfieldRW: I-70 Right of Way 7%UC: I-70 Unconstrained 4%
2035 Revenues:
Full System $ 795 MTruncated System $ 754 M
93% of Revenue
10%1%
54%
31%
4%
Zone 1- I-25 Main
Zone 2 - DIA Branch
Zone 3 - I-70 Main
Zone 4 - I-70 Extensions
Zone 5 - I-25 Extension
Key
ER: I - 25 Existing RailGF: I - 25 Greenfield RW: I - 70 Right of Way 7%UC: I - 70 Unconstrained 4%
2035 Revenues:
Full System $ 586 M Truncated System $544 M
93% of Revenue
10%1%
54%
31%
4%
Zone 1- I-25 Main
Zone 2 - DIA Branch
Zone 3 - I-70 Main
Zone 4 - I-70 Extensions
Zone 5 - I-25 Extension
10%1%
54%
31%
4%
Zone 1- I-25 Main
Zone 2 - DIA Branch
Zone 3 - I-70 Main
Zone 4 - I-70 Extensions
Zone 5 - I-25 Extension
Key
ER: I - 25 Existing RailGF: I - 25 Greenfield RW: I - 70 Right of Way 7%UC: I - 70 Unconstrained 4%
Key
ER: I - 25 Existing RailGF: I - 25 Greenfield RW: I - 70 Right of Way 7%UC: I - 70 Unconstrained 4%
2035 Revenues:
Full System $ 586 M Truncated System $544 M
65% of Capital generates
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐21
8.6 Summary
This chapter has described the unit costing basis for the development of capital costs for this study.
Costs were developed initially for two main network options, a constrained route following I‐70
with 7 percent grades, and an unconstrained route having only 4 percent grades. These were paired
with greenfield and existing rail alignments on I‐25.
These two network options have been evaluated for the full RMRA system, but it was found that a
truncated system between Fort Collins and Pueblo and DIA and Eagle County Airport could still
capture a very high percentage of the projected revenue and ridership, at substantial capital cost
savings. Accordingly additional options will be developed for this core system.
Chapter 9 will define an “FRA Developed” option by combining segments of the original
constrained and unconstrained alignments using a mix‐and‐match approach. After this, a four‐phase
implementation plan will be developed in Chapter 10.
Rocky Mountain Rail Authority
High‐Speed Rail Feasibility Study
Business Plan
TEMS, Inc. / Quandel Consultants, LLC / GBSM, Inc. March 2010 8‐22
Page Intentionally Left Blank