64. overview of waste management acg project â€" azerbaijan
TRANSCRIPT
Overview of waste management ACG Project – Azerbaijan Business Unit Bill Boulton (BP), Annette Watlow (BP), Steve Bell (Enviros Consulting)
AIOC – operated by BP
• Azeri-Chirag-Gunashli (ACG) PSA signed September 1994
• February 1995 Azerbaijan International Operating Company established
• AIOC consortium of 11 international oil companies
• October 1995 ACG early oil project sanctioned
• November 1997 First oil produced from Chirag
• August 2001 Phase 1 of the full field development sanctioned
• February 2005 first oil from Phase 1 Central Azeri
SOCAR
10.00%Amoco Caspian
Sea Petroleum
Limited
17.01%
BP Exploration
(Caspian Sea)
Limited
17.13%
Amerada Hess
2.72%
Devon Energy
Caspian
Corporation*
5.63%
Turkiye Petrolleri
A.O.
6.75%
Unocal Khazar,
Ltd.
10.28%
Statoil Apsheron
a.s.
8.56%
Exxon Azerbaijan
Limited
8.00%
ITOCHU Oil
Exploration
(Azerbaijan) Inc.
3.92%
Inpex Southwest
Caspian Sea, Ltd
10.00%
AIOC consortium of 11 international oil
companies
ACG Project – Scope & Scale
• Capex: $9bn total / $6m / day• 90,000 te topsides• 90,000 te jackets• 1000 km offshore pipelines
• 80% of man-hours in Azerbaijan• 20% across another 10 countries• New Workforce - 8000 Azeris
• One of world’s largest terminals• 7 years to execute• 74 million man-hours total so far• Over 3 million man-hours/month
Vision
AzBU in 2004 AzBU In the Future
Assets: EOP + Projects People: 2000 BP staff + 1400 agency
Infrastructure: •2 export pipelines•Sangachal EOP Terminal
Gross Production: •132 mbd
8+ operating platforms + Projects >2200 BP staff
• 4 export pipelines• One of the biggest terminals in the
world
• 1mmbd in 2009
GROWTH Capital Spend 2004: $12m/
day
GROWTH Capital Spend 2004: $12m/
day
SangachalSangachal
Chirag l
ChiragEast Azeri
2007Central Azeri
2005
West Azeri2006
Shah Deniz Stage 12006
Shah Deniz Stage 2
ACG Phase 32008
InamAlov
• 7bcma in 2009
Project Schedules
2001 2002 2003
1H 2H 1Q 2Q 3Q 4Q 1H 2H 2004 2005 2006 2007 2008
BTC
ACG Phase 1
ACG Phase 2
ACG Phase 3
DefineDefineDefineDefine
1st Oil
ExecuteExecuteExecuteExecute
SelectSelect SelectSelect1st Oil
DefineDefineDefineDefineAppraiseAppraiseAppraiseAppraise ExecuteExecuteExecuteExecute
Operation
DefineDefineDefineDefine ExecuteExecuteExecuteExecuteSelect Select Select Select
Select Select Select Select DefineDefineDefineDefine
1st Oil
West Azeri
ExecuteExecuteExecuteExecute
1st Oil
East Azeri
ACG Project E&S management
EBRD and IFC provided financial support to a number of AIOC PSA partners for Phase 1 of the ACG Project
To ensure commitments in the ESIA’s are implemented, an environmental and social management system developed
4 level system developed
To date 3 audits completed by the Lender Group’s Independent Environmental Auditors
POLICY
ACG Phase 1 Environmental and Social Management
System
Contractor Control Plans
Contractor Implementation Plans
& Procedures
LEVEL I: BP / AIOC
LEVEL II: PROJECT
LEVEL III: DELIVERY UNITS
LEVEL IV: CONTRACTOR
COMMITMENTS REGISTER
COUNTRY
Source Documents
Waste Overview – 2004 waste data
ACG Project Monthly Non-Hazardous Waste Volumes, m3
2004
0
1,000
2,000
3,000
4,000
5,000
6,000
Jan
Feb
Mar
Ap
r
May
Jun
Jul
Au
g
Sep Oct
No
v
Dec
ACG Project Monthly Hazardous Waste Volumes, m3
2004
0
50
100
150
200
250
300
350
400
450
500
Jan
Feb
Mar
Ap
r
May
Jun
Jul
Au
g
Sep Oct
No
v
Dec
Key waste typesVolume
m3 Key waste typeVolume
m3 Key waste typesVolume
m3 Key waste typeVolume
m3DomesticWastes
29,743.0Paper& Card
777.2Bilge/Oily
water1,747.7 Diesel/contaminated 159.1
Wood/waste timber
8,281.6 Drums 161.8PaintCans
930.8 Foam buoys 72.0
Canteenwaste
7,888.2Electrical
Cables124.6
Hydraulic Oil/Lubricants/
Used oil261.6
Paintssludges & thinners
84.71
Metal Ferrous 4,364.6 Plastic 112.2Oilyrags
137.8 Oily soils 43.5
Blasting grit 1,327.5Stainless
Steel82.6 Drums 118.7
Soilcontam.
with paint26.9
Waste destinations 2004
Total Stored
1.5%
Total Recycled /
Re-used
23.7%
Total Treated &
Disposed
3.0%
Total Landfilled
71.9%
Waste Overview - 2004
Non – hazardous construction waste is disposed of to existing municipal facilities
Nearly ¼ of non-hazardous waste is recycled – includes steel, paper, ferrous and non ferrous metal, wood, paper
19 percent of hazardous waste stored at Serenga – BP hazardous waste facility
ACG Project waste infrastructure
Location User Activities Waste infrastructure
MCCI Topsides Construction of the drilling quarters (DQ) topsides
Bos-Shelf (Star Gulf)
Construction of the jackets for topsides facilities
Saipem
Upgrade of the heavy lift barge (DBA vessel) and transportation and installation of the drilling template and topsides
MCCI Subsea Upgrade of the pipelay barge and installation of the nearshore ACG Phase 1 pipelines
SPS
ACG Operations Offshore drilling and production
Waste transfer station Number of skips: 231 Average number of skips processed per day: 30 Number of people working on site: 55 Total volume of waste handled in 2004: 33,785 m3
Bibiheybat oilfield
Amec-Azfen-Tekfen (ATA)
Fabrication of topsides
Waste transfer station Number of skips: 20
Average number of skips processed per day: 7 Number of people working on site: 6 Total volume of waste handled in 2004: 7,285 m3
Tekfen-Azfen (TKaz)
Site preparation and construction for the expansion of the Sangachal Terminal Sangachal
Terminal Expansion
Project (STEP) Entrepose Tank construction for the STEP
Waste transfer station Number of skips: 128 Average number of skips processed per day: 16
Number of people working on site: 18 Total volume of waste handled in 2004: 18,816m3
ACG Project waste infrastructure
ACG Project waste infrastructure
ACG Project waste infrastructure
ACG Project waste infrastructure
Problem Wastes
Compacting Waste saves travel
A Problem Waste!
A Problem Waste!
Storage of Paint Waste
Planning improvements to disposal of non-hazardous waste
Two existing municipal landfills close to Baku
SUMQAYIT and BALAKHANY
Standards at both poor: No engineered containment
Poor environmental nuisance control – fire, scavenging & litter control
Waste acceptance criteria not followed by all users
Planning improvements to disposal of non-hazardous waste
Existing municipal landfills close to Baku
Fast track improvement required
ACG Project initiated series of studies to evaluate environmentally preferable option for disposal of non-hazardous waste Comparative audit of both existing municipal landfill sites
Waste characterisation of waste sent to landfill
Treatment & disposal options assessment
Review of recycling market
Waste characterisation
Assessment of general waste skip composition completed in August 2004
Findings:
– Nearly 70% of the contents of the general waste skips considered as non recoverable
– Remaining 30% represented recoverable wood offcuts, paper and card packaging and metal
Proportions of Recyclable and Non-recyclable Non-Hazardous Waste in General Waste Skips
Wood15%
Metals6%
Paper/Card6%
Residues55%
Miscellaneous items9%
Office Waste4% Used PPE
2%
Plastics3%
Options for Non Hazardous Waste
Zero waste: At-source segregation not practical for recyclable materials – a material
reclamation facility (MRF) is required
At present, local markets for reclaimed materials are either very limited or non-existent
Significant investment for MRF and seeding recycling facilities required
Not considered sustainable at present
Interim storage: Recommended by lender auditors
Not acceptable for putrescible waste, unless frozen will become a health hazard
High CAPEX and OPEX costs do not justify this ‘short term fix’
Options for Non Hazardous Waste
Disposal - Incinerate everything: Operational reliability questionable & constant challenge – lessons
learnt from BTC Down time storage/solutions required Permitting issues Process residues still require disposal Alternative stand-by option required for downtime
High CAPEX and OPEX
Disposal – Construct New Landfill to meet EU Landfill Directive requirements: Existing landfill sites expressed interest in developing new
improved facilities New landfill could provide a reliable long term solution Higher landfill disposal prices will provide greater financial incentive
to reduce volumes of waste sent to landfill
Options for Non Hazardous Waste
Disposal - Treat food waste in sewage treatment plant: ACG Project workforce 10,000+
All sites operate canteens
Existing treatment plants do not have sufficient capacity to accommodate additional load
Initial review of food waste volumes indicate capex costs high
Treatment temperature not inline with EU animal by-products regulation requirements
Recycling - Composting: Compliance with EU animal by products regulations requires
technically advanced plant
Compostable canteen waste only represents 20% by volume of the waste currently sent to landfill – partial fix
Options for Non Hazardous Waste
Key constraints: Government priority has been hazardous waste – World Bank funded
Hazardous waste landfill
Ensuring sustainability & minimising reliance on external support
Lack of established in-country recycling facilities
Contrast in HSE standards – AIOC vs developing recycling industry
Non-metallic waste has little value – no landfill tax
Punitive and complicated legislative system - waste legislation still evolving
Plus the following generic constraints: Technical
Financial
Social
Economic
Institutional
Options Selected
Interim improvements to existing municipal landfill – particularly on control and monitoring
Continue to explore recycling/reuse options
Construct New Landfill compliant with best practice
Detailed ITT developed for turnkey design, construct and operate contract to best practice
Approach presented to Azerbaijan Ministry of Environment and Natural Resources (MENR), who expressed strong support for the initiative
Interim Improvements at existing municipal landfill
Site investigation completed of 3 new tipping areas within site boundary
An unused area adjacent to the previously used tipping face selected
Scope of improvements
Secure and upgrade site (basic civil engineering work)
• Landscape improvement – grading and covering existing waste, improve access to tipping area
• Improve fencing
• Segregation of site into clearly identifiable working areas
• Quarantine area established – mobile bunded skid mounted trays
Day to Day operations
– New offices and facilities
• Plant – bulldozer, back up generator
• Labour – Security 24hr, Supervisor, HSE office and labour
Ground water monitoring
Construction site based improvements
Improved tracking in what goes into the general skip:
Waste acceptance criteria developed
Notification reporting improved, tracked and widely reported
‘Name and shame’ contractors with poor segregation
Additional labelling of skips – do’s and don’ts
Site waste lists & waste register reported and verified on regular basis
Construction contractors created site waste teams to routinely check all skips
Construction site skip tracking, utilisation and placement tracked
Posters and awareness leaflets
Waste minimisation review completed and initiatives currently being developed
Waste awareness course provided to site teams – BP & construction contractors
New landfill
Tender development; August September 2004; key issues:
Technical requirements for landfill design, construction and operation explicitly stated in ITT documentation
Bridging gap between
• Well developed and proven UK and EU legislation & planning process and
• National legislation & planning process whilst being sensitive to ITT audience
Waste forecasting for the whole of the Azerbaijan Business Unit – multiple PSA’s and activities
Ensuring cross Azerbaijan Business Unit buy-in and support
Competitive Tender was issued Mid October 2004
A technically viable tender selected for design, construction and operation of landfill to EU standards and interim agreement issued end of February 2005
Construction and commissioning should be completed in 2nd and 3rd quarters operations starting in fourth quarter 2005