6. project management. project a set of partially ordered, interrelated activities that must be...
TRANSCRIPT
Project A set of partially ordered, interrelated activities
that must be completed to achieve a goal
Project Management Decision-making, choosing between alternatives,
managing activities as a part of the project Planning
goal setting, project definition, team organization Scheduling
relating people, money, and supplies to specific activities and activities to one and other
Controlling monitoring resources, costs, and quality; revising plans
and shifting resources to meet time and cost demands
Role of Project Manager All necessary activities are finished in order
and on time The project comes in within budget The project meets quality goals The people assigned to the project receive
motivation, direction, and information
Project Scheduling Identifying precedence relationships Sequencing activities Determining activity times & costs Estimating material and worker
requirements Determining critical activities
Scheduling Techniques Gantt chart Network models
Critical Path Method (CPM) Program Evaluation and Review Technique
(PERT) Identify the longest time-consuming path
through a network of activities required to complete a project
Gantt Chart: Service for a Delta Jet
Passengers
Baggage
Fueling
Cargo and mail
Galley servicing
Lavatory servicingDrinking water
Cabin cleaning
Cargo and mail
Flight services
Operating crewBaggagePassengers
DeplaningBaggage claimContainer offloadPumpingEngine injection waterContainer offloadMain cabin doorAft cabin doorAft, center, forwardLoadingFirst-class sectionEconomy sectionContainer/bulk loadingGalley/cabin checkReceive passengersAircraft checkLoadingBoarding
00 1515 3030 4545 6060MinutesMinutes
Key Terms for Network Models Forward pass
To compute the earliest start (ES) and finish (EF) times for each activity
Backward pass To compute the latest start (LS) and finish (LF)
times for each activity without delaying the completion of the entire project
Slack The length of time an activity can be delayed
without delaying the entire project LS-ES or LF-EF
Key Terms for Network Models
A
Activity Name or Symbol
Earliest Start ES
Earliest FinishEF
Latest Start
LS Latest Finish
LF
Activity Duration
2
Key Terms for Network Models Critical path
Zero slack for every activity on the path The longest path through the network The shortest time in which the project can be
completed Any delay in critical path activities delays the
project There may be several critical paths
CPM and PERT Procedures Develop relationships among the activities -
decide which activities must precede and which must follow others
Draw the network connecting all of the activities
Assign time and/or cost estimates to each activity
Compute the longest time path through the network – this is called the critical path
Use the network to help plan, schedule, monitor, and control the project
CPM Example
Activity DescriptionImmediate
PredecessorsTime
(Weeks)
A Build internal components — 2
B Modify roof and floor — 3
C Construct collection stack A 2
D Pour concrete and install frame A, B 4
E Build high-temperature burner C 4
F Install pollution control system C 3
G Install air pollution device D, E 5
H Inspect and test F, G 2
Continued
E
4
F
3
G
5
H
2
4 8 13 15
4
8 13
7
13 15
10 13
8 13
4 8
D
4
3 7
C
2
2 4
B
3
0 3
Start0
0
0
A
2
20
42
84
20
41
00
PERT PERT uses a probability distribution for
activity times to allow for variability while CPM assumes fixed time estimate
PERT uses two or three time estimates for each activity a: optimistic time, b: pessimistic time, m: most
likely time Uniform distribution approximation
expected time = (a+b)/2, variance = (b–a)2/12 Beta distribution approximation t = (a+4m+b)/6, v = (b–a)2/36
PERT Example
Activity a m b t v
A 1 2 3 2.11B 2 3 4 3
.11C 1 2 3 2
.11D 2 4 6 4
.44E 1 4 7 4
1.00F 1 2 9 3
1.78G 3 4 11 5
1.78H 1 2 3 2
.11
Probability of Project Completion Project variance is computed by summing
variances of critical activities σ2 = .11+.11+1.00+1.78+.11 = 3.11 Total project completion times follow a
normal probability distribution Probability to finish the project within 16
weeks?Pr(T<16) = Pr(Z<(16-15)/1.76)) = Pr(Z<0.57) = 0.716
(Dis)Advantages of CPM/PERT Especially useful for large projects Straightforward concept and not
mathematically complex Graphical networks help to perceive
relationships among project activities Critical path pinpoints activities that need
to be closely watched Time estimates tend to be subjective Too much emphasis on the critical path
Project Crashing Shortening the duration of the project Steps:
Compute the crash cost per time period Identify the critical path and activities Select an activity on the critical path that can
be crashed with the smallest crash cost Repeat until the desired due date is reached
An Example
Time (Wks) Cost ($) Crash Cost CriticalActivity Normal Crash Normal Crash Per Wk ($) Path?
A 2 1 22,000 22,750 750 YesB 3 1 30,000 34,000 2,000 NoC 2 1 26,000 27,000 1,000 YesD 4 2 48,000 49,000 1,000 NoE 4 2 56,000 58,000 1,000 YesF 3 2 30,000 30,500 500 NoG 5 2 80,000 84,500 1,500 YesH 2 1 16,000 19,000 3,000 Yes
Video Case Study Develop the network for planning and
construction of the new hospital at Arnold Palmer.
What is the critical path and how long is the project expected to take?
Why is the construction of this 11-story building any more complex than construction of an equivalent office building?
What percent of the whole project duration was spent in planning that occurred prior to the proposal and reviews? Prior to the actual building construction? Why?