49423-005: bangladesh power system enhancement and
TRANSCRIPT
Social Monitoring Report
Project No. 49423-005 Semestral Report (January-June 2021) July 2021
Bangladesh: Bangladesh Power System Enhancement and Efficiency Improvement Project
UP-GRADATION, REHABILITATION, AND INTENSIFICATION OF DISTRIBUTION SYSTEM (DMCS & RRKB DIVISIONS)
Prepared by Bangladesh Rural Electrification Board (BREB) for the Asian Development Bank.
This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgments as to the legal or other status
of any territory or area.
Social Safeguard Monitoring Report
Bangladesh Power System Enhancement and Efficiency Improvement Project
UP-GRADATION, REHABILITATION, AND INTENSIFICATION OF
DISTRIBUTION SYSTEM (DMCS & RRKB DIVISIONS) ADB Loan No. 3522-BAN
Prepared by the Bangladesh Rural Electrification Board for the Asian Development
Bank
This social safeguard monitoring report is a document of the borrower and made publicly available in accordance
with ADB’s Public Communications Policy 2011 and the Safeguard Policy Statement 2009. The views expressed
herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff.
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
2
Project Name UP-GRADATION, REHABILITATION, AND INTENSIFICATION OF DISTRIBUTION SYSTEM
(DMCS & RRKB DIVISIONS)
Report Name SOCIAL SAFEGUARD MONITORING REPORT FROM JANUARY’21 TO JUNE’21.
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
3
Contents
List of Abbreviations ................................................................................................................................................................ 4
Executive Summary ............................................................................................................................. 5
Introduction ............................................................................................................................................................................. 6
Scope of Report ....................................................................................................................................................................... 6
Brief Project Description .......................................................................................................................................................... 7
Project Status ......................................................................................................................................................................... 12
Status of Project Implementation .......................................................................................................................................... 12
Status of Project Monitoring Activities .................................................................................................................................. 14
Occupational Health and Safety Monitoring .......................................................................................................................... 18
2.3 Implementation Schedule ................................................................................................................................................ 20
Performance Monitoring ....................................................................................................................................................... 21
Compliance with Legal and Policy Requirements .................................................................................................................. 21
Compliance with Social Safeguard Covenants ....................................................................................................................... 21
Compliance with Resettlement Plan Requirements .............................................................................................................. 23
Implementation of the Grievance Redress Mechanism ........................................................................................................ 25
Grievance Redressal Mechanism ........................................................................................................................................... 25
Status of Implementation of the GRM ................................................................................................................................... 26
Stakeholder Engagement ....................................................................................................................................................... 27
Stakeholder Engagement Process .......................................................................................................................................... 27
Consultations ......................................................................................................................................................................... 28
6.0 Conclusion and Recommendations .................................................................................................................................. 31
Annex A: Line construction progress of URIDS (DMCS & RRKB) project up to December 2020. ........................................... 32
Annexure-B: Photographs of consultations-KIIs with stakeholders ..................................................... 33
Annexure-C: Participant list of FGDs ...................................................................................................................................... 34
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
4
List of Abbreviations
ACRE- Area Coverage Rural Electrification
ADB- Asian Development Bank
APs- Affected Persons
BREB- Bangladesh Rural Electrification Board
DCP- Disclosure, Consultation and Participation
DMCS- Dhaka, Mymensingh, Chittagong and Sylhet divisions
DPP- Development Project Proposal
EA- Executive Agency
EMP- Environmental Management Plan
FGD- Focus group discussion
GM- General Manager
GoB- Government of Bangladesh
GRM- Grievance Redressal Mechanism
IEE- Initial Environmental Examination
KII- Key Informant Interview
kV- Kilo Volt
NGO- Non-Government Organization
PAM- Project Administrative Manual
PBS- Palli Bidhyut Samity
PCM- Public Consultation meeting
PGCB- Power Grid Company of Bangladesh
PIMC- Project Implementation & Monitoring Consultant
PPE- Personnel Protective Equipment
RoW- Right of Way
RP- Resettlement Plan
RRKB- Rangpur, Rajshahi, Khulna and Barishal divisions
SPS2009- Safeguards Policy Statement 2009
URIDS- Up-gradation, Rehabilitation, and Intensification of Distribution System’
V- Volt
XEN- Executive Engineers
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
5
Executive Summary
Up to June 2021, the line construction progress is 25,998 km for URIDS (DMCS) project including up-
gradation, rehabilitation and extensions of distribution line which is 96.29% covering the total
target of 27000 Km.
On the other hand, for URIDS (RRKB) project, the total progress is 23,288 km for line construction
(up-gradation/rehabilitation and extension), representing 99.10% of the total target of 23,500 Km.
The average line construction progress of both projects is 97.60%. The civil construction progress is
100% for both project.
In response to COVID-19 pandemic, labors, workers, and other project staff are using mask, hand
sanitizers and disinfection spray at each and every site. Social distancing conceivably maintained at
the construction sites as well. The hard barricade was used to limit the local entry into the project
sites.
Labor camps are established with access to safe drinking water supply & sanitary latrines, dust bins
are made available to keep the household waste and disposed of in a safe place selected by
BREB/PBS.
Tree plantation event was carried out at each PBS areas to celebrate the Bangabandhu’s birth
century following the government directions. Free saplings were distributed among the consumer
level for home-ground planting, covering the project affected people also.
The major outcomes in this reporting period are as follows
No complaints received from the consumer or project affected people (PAPs)
No community people received accident or wounded due to the project activities.
No workers were wounded or received accident till date.
No one was economically displaced or economic activities of the local people were not
obstructed.
Due to project activities, small business opportunities have been expanded locally
No workers were affected by COVID-19, etc.
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
6
Introduction
Accelerating the steps of generating electricity across the country is the top priority of the
Government of Bangladesh. Government is committed to having good access to electricity in the
rural areas of Bangladesh. Bangladesh Rural Electrification Board (BREB) is one of the important
institutions that has the proximity to providing quality-electricity to consumers without disruptions
that could have a tremendous impact on country’s economic growth.
It is included in the GoB’s seventh’s five-year plan to produce affordable and reliable electricity for
both economic development & poverty reduction and everyone will have good access to affordable
and reliable electricity by the year of 2021. In order to achieve vision of the government, Bangladesh
Rural Electrification Board (BREB) worked with a firm objective to boost the electrification program
throughout the country based on the concept of Area Coverage Rural Electrification (ACRE). The
ACRE idea leads to the development of a cooperative called Palli-Bidyut Samity (PBS) to provide
electric services to their member consumers. Since its creation, 80 nos of PBSs have been
established throughout the country under various projects from ACRE Phase-I to ACRE Phase-V.
After establishment of the PBSs, the distribution system of the PBSs has been gradually expanded
and strengthened under the various Intensification and Expansion Projects.
To improve the quality of the electricity, increase the capability of consumer growth, minimize the
system losses, connect new households, small industries etc. in the existing distribution network of
the said PBSs, according to the above study, the Scope of Work under the project of Up-gradation,
Rehabilitation, and Intensification of Distribution System (Dhaka, Mymensingh, Chittagong and
Sylhet divisions (DMCS) and Rangpur, Rajshahi, Khulna and Barishal divisions (RRKB)’’ is to construct
as 50,500 km of distribution lines for rehabilitation/ up-gradation and 6,465 km new lines.
Scope of Report
The objective of this social safeguard management and monitoring report is to record
resettlement and social impacts resulting from the project activities and to ensure
implementation of the earlier “mitigation measures” that were developed to mitigate adverse
effects and boost the positive impacts of specific project activities during the reporting period of
January 2021 to June 2021.
It would also provide measures to handle any unintended or unwanted social impacts that may
occur during the project’s construction and operation phases.
• The implementation of this plan enhanced the social control and monitoring of the project
activities to verify the compliance with all the indicators, limitation, and socio-economic
outcomes set out in the Environmental Management Plan (EMP), Initial Environmental
Examinations (IEEs) report, and Environmental Impact Assessment (EIA) report and minimized
the damaged caused by environmental and social works.
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
7
Brief Project Description
Table 1: Basic Information of URIDS (DMCS &RRKB) project.
Items URIDS (DMCS) URIDS(RRKB)
Project Construction Period July 2016 to June 2021
Total Length (km) of 33kV, 11KV, and
below voltage
20,500 18,000
Length of New Line (km) of 11kV and
below voltage
6,500 5,500
No. of Division Dhaka, Mymensingh,
Chittagong, Sylhet
Rajshahi, Rangpur, Khulna and
Barishal
No. of District covers 33 districts 28 districts
No of Customers to be Covered 500,000 450,000
Line Type 33kV, 11kV, 440/240 volt
Number of Palli Bidyut Samities (PBSs)
Covered
44 36
Material Requirements • Conventional overhead pole-
mounted distribution
transformers 6.35/0.23 kV –
37,090 kVA transformers will be
procured
• Porcelain insulators 6.35/0.23
kV
• Poles – SPC/Wooden/Steel –
425,863 poles will be procured
• Insulated cable 6.35/0.23 kV-
14,361 km of conductor will be
procured.
• Bare conductor – 69,553 km of
conductor will be procured.
Conventional overhead
pole-mounted distribution
transformers 6.35/0.23 kV –
31,624 kVA transformers
will be procured
Porcelain insulators
6.35/0.23 kV
• Poles – SPC/Wooden/Steel –
poles will be procured
• Insulated cable 6.35/0.23 kV
and
Bare conductor –69,552 km
of conductor will be
procured.
Typical Pole Size 15.00 m
No. of Transformers to be installed 37,090 31,624
Transformer Capacity 489 MVA 391 MVA
Conductor 83,914 69,552
Meter 500,000 450,000
(Source: Revised DPP)
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
8
Table 2: Electrical works target of URIDS (DMCS&RRKB) Project.
Sl.
No.
Upgrades/ Rehabilitation/ Conversion
(km of line)
New Lines (Short Extensions of
about One Hundred Meters)
(km)
33 kV 11 kV and bellow New Grand total
1 790 19,710 6,500 27,000 Km
for DMCS
2 820 17,180 5,500 23,500 Km
for RRKB
Sub- total 1,610 36,890 12,000 50,500 Km
Civil Construction Works:
Civil Construction works of URIDS (DMCS) Project:
Under the DMCS project, a total of 35 residential and office building will be constructed, which are
mostly consists of two to three storied buildings. Table 3 shows the detail of the building types and
their PBS locations.
Table 3: Civil Construct Works under URIDS (DMCS) Project:
Sl.
No
Types of works undertaken by URIDS (DMCS)
project
Nos of
works
Location/ PBS
1 Construction of 3-storied Head Quarter Office
Building cum Warehouse including Land
development
1 Chandpur PBS-2
2 Construction of C-Type Residential Building for
Zonal Office Complex including Land
Development
2 Chandpur PBS-2 H/Q
Ukhyia in Cox’s Bazar PBS.
Construction of D-Type Residential Building for
Zonal Office Complex including Land
Development
6 Chandpur PBS-2H/Q.
Moheskhali in Cox’s Bazar PBS
Ukhyia in Cox’s Bazar PBS
Nandail in Kishoreganj PBS.
Chatak in Sunamganj PBS.
Fulgazi in Feni PBS.
Construction of E-Type for Zonal Office
Complex Residential Building including Land
Development
6 Chandpur PBS-2H/Q.
Moheskhali in Cox’s Bazar PBS
Ukhyia in Cox’s Bazar PBS
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
9
Sl.
No
Types of works undertaken by URIDS (DMCS)
project
Nos of
works
Location/ PBS
Nandail in Kishoreganj PBS.
Chatak in Sunamganj PBS.
Fulgazi in Feni PBS.
Construction of F-Type of Residential Building
for Zonal Office Complex including Land
Development
6 Chandpur PBS-2H/Q.
Moheskhali in Cox’s Bazar PBS
Ukhyia in Cox’s Bazar PBS
Nandail in Kishoreganj PBS.
Chatak in Sunamganj PBS.
Fulgazi in Feni PBS.
3 Internal Road
Boundary Wall
Gate
Security Post
Master Drain
Sewerage System (Septic tank)
Shaded Store Yard
Open Store Yard
Store Yard fencing
Garage
Ansar Barrack & Miscellaneous Works.
7 Chandpur PBS-2H/Q
Moheskhali Zonal Office in Cox’s Bazar PBS.
Ukhiya Zonal Office in Cox’s Bazar PBS..
Nandail Zonal Office in Kishoreganj PBS.
Chatak Zonal Office in Sunamganj PBS.
Damuda Zonal Office in Shariatpur PBS.
Fulgazi Zonal Office in Feni PBS.
4 Construction of 2-storied Rest House Building
with 3-storied Foundation
1 Chandpur PBS-2.
5 Construction of Zonal office complex including
Land Development Office Building cum Ware
House (3-storied Building with 5-storied
foundation)
6 Moheskhali, Cox’s Bazar PBS.
Ukhyia, Cox’s Bazar PBS.
Nandail, Kishoreganj PBS.
Chatak, Sunamganj PBS.
Damuda,Shariatpur PBS.
Fulgazi, Feni PBS.
(Source: Revised DPP)
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
10
Civil Construction works of URIDS (RRKB) Project:
Under the RRKB project, a total of 23 structures including rest house, office, and workshop buildings
will be constructed, which are mostly consists of two to three storied buildings. Table-4 shows the
detail of the building types and their PBS locations.
Table 4: Civil Construct Works under URIDS (RRKB) Project:
Sl.
No
Types of works undertaken by URIDS (RRKB)
project
Nos of
works
Location/ PBS
1 Construction of PBS head quarters 3 Sirajgonj PBS-2
Naogoan PBS-2
Bagura PBS-2
2 Construction of zonal office complex 11 Ataikula, Pabna PBS-2
Potia, Natore PBS-1
Dupchaciya, Bogra PBS-1
Pirgonj, Thakurgaon PBS
Ranigonj & Parbotipur, DinajpurPBS-2
Hikorgasa, Jessore PBS-1
Gornodi, Barisal PBS-2
Bauphal, Patuakhali PBS
Shener Bazar, Khulna PBS
Lalmohan, Bhola PBS
Vertical extension of office building (1 floor) 3 Thakurgaon PBS HQ
Dinajpur PBS-2
Jhenaidah PBS HQ
Vertical extension of office building (2 floor) 1 Patuakhali PBS HQ
Construction of 3-storied store cum workshop
& boundary wall
1 Thakurgaon PBS HQ
3 Construction of 2- storied rest house building 1 Magura PBS HQ complex
4 Construction of 2-storied office building 1 Kushtia PBS HQ
5 Vertical extension of C-type, D-type & E-type (1
floor)
1 Patuakhali PBS HQ complex
6 Repair & renovation works at Central
warehouse
1 Khulna PBS
Total Structure 23
(Source: Revised DPP)
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
11
Project location:
The project consists of eight administrative divisions of Dhaka, Mymensingh, Chattogram and Sylhet
divisions (DMCS) and Rajshahi, Rangpur, Khulna, and Barishal divisions (RRKB). Figure 1 shows the
locations of the study area.
Figure 1: Location Map of the Project Areas
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
12
Project Status
Status of Project Implementation
Table 5: Line construction Progress of URIDS Project up to December 2020.
Key Point URIDS, DMCS URIDS, RRKB TOTAL
Project Target (km) 27,000 23,500 50,500
Total Line Constructed (km) 25,998 23,288 49,286
Consumer Status (km) 500,000 450,000 950,000
Progress up-to June 2021 (%) (km) 96.29% 99.10% 97.60%
(Source: BREB)
Table 6: Civil construction progress of URIDS project up to December 2020.
Name of PBS Location of construction
site
Type of civil
construction
Construction progress
(%)
URIDS (DMCS)
Chandpur PBS-2 Chandpur PBS-2 H/Q Construction of head
quarter building &
residential building.
100%
Cox’s Bazar PBS
Ukhiya, Cox’s Bazar Construction of
Residential Building for
Zonal Office Complex in
Ukhiya, Cox’s Bazar.
100%
Moheskhali, Cox’s Bazar Construction of office
Building & residential
building for Zonal Office
Complex in Moheskhali,
Cox’s Bazar.
100%
Kishoreganj PBS Nandail, Mymensingh Construction of
Residential Building &
office building for Zonal
Office Complex in
Nandail, Kishoreganj.
100%
Sunamganj PBS Chatak, Sunamganj Construction of
Residential Building &
office building for Zonal
Office Complex in
Chatak, Sunamganj.
100%
Shariatpur PBS Damuda, Shariatpur Construction of E &F type
buildings for Damuda
zonal office,
Shariatpur.
100%
Feni PBS Fulgazi, Feni Construction of 100%
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
13
Name of PBS Location of construction
site
Type of civil
construction
Construction progress
(%)
Residential Building &
office building for Zonal
Office Complex in
Fulgazi, Feni.
URIDS(RRKB)
Jhenaidah pBS Jhenaidah PBS H/Q Construction of
extension of office
building 1st floor.
100%
Magura PBS Magura PBS H/Q Construction of rest
house building.
Jashore PBS-1 Jikorgacha, Jashore Construction of Zonal
Office Complex.
Kushtia PBS Kushtia PBS H/Q Construction of two
storied office building.
Patuakhali PBS Patuakhali PBS H/Q Vertical extension of
office, C- type, D-type &
E-type at Patuakhali PBS
HQ
100%
Bauphol, Patuakhali Construction of Bauphol
Zonal Office, Patuakhali
Bhola PBS Lalmohon, Bhola Construction of
Lalmohan Zonal Office of
Bhola PBS
Barishal PBS-2 Gornodi, Barishal Construction of Gornodi
Zonal Office, Barishal.
Khulna PBS Shenerbazar, Khulna Construction of
Shenerbzar Zonal office,
Khulna
100%
Khulna Repair and renovation of
central warehouse,
Khulna
Sirajgonj PBS-2 Sirajgonj, Construction of Sirajgonj
PBS-2 H/Q
100%
Pabna PBS-2 Ataikhula, Pabna Construction of Zonal
Office at Ataikhula,
Pabna.
Natore PBS-1 Potia, Natore Construction of Potia
Zonal Office, Natore.
Naogaon PBS-2 Naogaon Construction of Noagoan
PBS-2 H/Q.
100%
Bogura PBS-2 Bogura Construction of Bogura
PBS-2 H/Q.
Dupchaciya, Bogura. Construction of
Dupchaciya Zonal Office,
Bogura.
Bogura PBS-1 Bogura 100%
Thakurgaon PBS Thakurgaon Construction of Vertical
extension of office
building (1 floor),
Thakurgaon.
100%
Dinajpur PBS-2 Dinajpur Vertical extension of
office building (1 floor)
at PBS H/Q.
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
14
Name of PBS Location of construction
site
Type of civil
construction
Construction progress
(%)
Construction of Zonal
Office Complex at
Ranigonj, Dinajpur.
Construction of Zonal
Office Complex at
Parbotipur, Dinajpur
Construction of Pirgonj
Zonal Office Complex,
Dinajpur.
(Source: BREB)
Status of Project Monitoring Activities
Monitoring results were measured by field visits by PIMC experts, and progress data collected from
field, BREB and PBS which performed the integration of social safeguard issues into the project
activities. BREB is responsible for implementation, and monitoring of compliance issues and take
necessary actions if any issues are found non -complied.
Site Visits
The Project Director, Deputy Project Director accompanied by representatives of BREB/PBS officials
visited the following PBSs during this reporting period. The visits were conducted in the new line
constructions, up-gradation/ renovation sites, and civil construction sites. Necessary
recommendations were provided to the contractors/ sub-contractors for taking corrective measures
to fulfill the social requirements.
However, meetings were held with the following PBSs and BREB staff and discussed on reinforcing
the social issues regarding the project activities. Details are provided in stakeholder engagement
chapter.
Table 7: List of sites visited during this reporting period.
No. Name of PBSs Date of Site Visit Persons met during the site visit
1 Jashore PBS-1 03.06.2021 to 06.06.2021
(DPD)
Executive Engineer of BREB, Contractor’s
representative, Assistant Engineers of BREB,
General Manager of PBS, Deputy General
Manager (Technical) of PBS.
2 Khulna PBS
3 Naogaon PBS-1
03.06.2021 to 08.06.2021
(PD)
4 Naogaon PBS-2
5 Bogura PBS-1
6 Bogura PBS-2
7 Natore PBS-1
8 Natore PBS-2
10 Magura PBS 17.05.2021 to 21.05.2021
(PD)
11 Jashore PBS-1
12 Natore PBS-1 01.05.2021 to 04.05.2021
(PD)
13 Magura PBS
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
15
No. Name of PBSs Date of Site Visit Persons met during the site visit
14 Kusthia 01.05.2021 to 04.05.2021
(PD)
15 Jashore PBS-1
16 Chandpur PBS-2 18.06.21 (PD)
17 Sariatpur PBS 18.06.21-19.06.21 (DPD)
19 Cox’s Bazar PBS 27.05.21-29.05.21 (DPD)
20 Narayongonj PBS
1/2 08.06.21 (PD)
Executive Engineer of BREB, Contractor’s
representative, Assistant Engineers of BREB,
General Manager of PBS, Deputy General
Manager (Technical) of PBS.
21 Narsindi PBS-1/2 07.06.21 (PD)
22 Gazipur-1/2 07.06.21 (DPD)
23 Gazipur-1/2 25.05.21 (DPD)
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
16
Civil construction sites:
The safeguard monitoring team (Project Director, Deputy Project Director accompanied by
representatives of BREB/PBS officials) also visited the following civil construction sites during this
reporting period, details are provided in Table-8.
Table 8: List of civil construction sites visited during this reporting period
Name of PBS Location of construction site Date of inspection
Chandpur PBS-2 Chandpur PBS-2 H/Q 07.05.21, 28.05.21, 18.06.21 (PD)
Cox’s Bazar PBS
Ukhiya, Cox’s Bazar 27.05.21 (DPD)
Moheskhali, Cox’s Bazar 27.05.21 (DPD)
Shariatpur PBS Damuda, Shariatpur 18.06.21-19.06.21 (DPD)
Magura PBS Magura PBS H/Q 17.05.21-21.05.21 (PD)
Jashore PBS-1 Jikorgacha, Jashore 01.05.21-04.05.21 (PD)
Kushtia PBS Kushtia PBS H/Q 01.05.21-04.05.21 (PD)
Patuakhali PBS Patuakhali PBS H/Q 10.02.21-14.02.21 (PD)
Bauphol, Patuakhali 10.02.21-14.02.21 (PD)
Bhola PBS Lalmohon, Bhola 10.02.21-14.02.21 (PD)
Barishal PBS-2 Gornodi, Barishal 25.03.21-30.03.21 (PD)
Khulna PBS Shenerbazar, Khulna 03.06.21-06.06.21 (DPD)
Natore PBS-1 Potia, Natore 03.06.21-08.06.21 (PD)
Naogaon PBS-2 Naogaon 03.06.21-08.06.21 (PD)
Bogura PBS-2 Bogura 03.06.21-08.06.21 (PD)
Dupchaciya, Bogura 03.06.21-08.06.21 (PD)
Bogura PBS-1 Bogura 03.06.21-08.06.21 (PD)
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
17
Pictures of the construction sites:
Photo-1: Construction of E & F type building at
Dupchachiya, Bogura PBS-2
Photo-3: Construction of D-type building at Bhola PBS.
Photo-5: Construction of head quarter building &
residential building at Chandpur PBS-2
Photo-2: Construction of head quarter office building of Kushtia
PBS.
Photo-4: Construction of office building at Nandail, Kishoreganj
PBS
Photo-6: Up-gradation line works at Chittagong PBS-3
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
18
Occupational Health and Safety Monitoring
On the construction sites, Occupational Health and Safety (OHS) issues are prioritized to reduce the
causality in the work place. PIU tracks the OHS issues at the line construction and civil construction
sites responsibly and provides the necessary advice, suggestions & guidance to keep the site safe.
Till date (up to June 2021), there is no accident or incident received at the sites. Moreover, in order
to reduce the risks of COVID-19, hand sanitizers or soap, disinfection spray is made available at the
construction sites and frequently used by the workers and other staff. Possibly maintained social
distancing both at the working sites and Labor camp sites.
Moreover, numbers of awareness sessions were conducted between workers, & laborers in different
working sites such as Chandpur PBS-2, Cox’s Bazar PBS, Kishoreganj PBS, Sunamganj PBS, Shariatpur
PBS, Feni PBS, Jhenaidah PBS, Magura PBS, Jashore PBS-1, Kushtia PBS, Patuakhali PBS, Bhola PBS,
Barishal PBS-2, Khulna PBS, and Sirajgonj PBS-2. The summary of status of OHS are provided in table-
9.
Table 9: Status of Occupational health & Safety issues.
Trainings/Drills/
Inspections
Number and
Position of
Participant/s
Location/s and Date/s Remarks
On site discussion on safety
procedures for civil
construction of zonal
offices
85
January, March &
May 2021
PPE is now accessible at the
constructions sites and using by
workers.
Hand sanitizer, mask is using
regularly
Staying at the campsite after
works to avoid public gathering
Inspection of up-gradation
works sites
73
February, April,
June, 2021
Inspection of labour camp
sites
49
February,
March, April &
June 2021
Till date, no under age 18
labors (child) are recruited at
the site.
Dustbins are using for
collection of kitchen wastes
Camp has access to clean water
supply and sanitary latrines.
No illness was occurred till
date.
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
19
Table 10: The status of Occupational Accident and its Corrective Action.
Occupational
Accident
Number and
Position of
Person/s Involved
Location/s and
date/s of incident
Description of
incident
Corrective Actions.
Fatality 0 - - -
Non-fatality 0 - - -
Near-miss 0 - - -
Illness 0 - - -
Other incidents 0 - - -
Note: Till date, no occupational accidents were occurred in the project areas. If any found, that could be
reported in the next report properly.
Table 11: Overall implementation status of the project.
Sl.
No
Monitoring
Activities
Indicators Status Remarks
1 Livelihood and
Employment
Opportunity
Employment
opportunity,
income, wage etc.
Being complied Local people are getting the
opportunity to work in this project,
but the number of employments is
low.
2 Community
Health, Safety and
Security
Community health
condition, Safety and
Security Status, threats
for Community health
and safety
Being complied. No grievances were found from the
consumers/APs or community
people regarding the risk of their
health due to project activities.
3 Occupational
Health and Safety
Status of labour
health, accidental
status, medical
equipment (i.e., First
Aid Box, Ambulance),
and status of safety
tools and instruments
(i.e., gumboots,
earmuffs, hard
helmets, gloves, etc.)
Being complied Labours are using PPE while working
on the sites. Safety belt and safety
boot are commonly used during
extension or rehabilitation of the
distribution line.
5 Resettlement Plan
(RP)
Considering the
Resettlement Plan
following the ADB SPS
2009
Being complied No need for RP implementation as
this project does not need acquire
any land.
6 Compensation on
land purchase/
Compensation of land
acquisition, land
purchase, for civil
Being complied The project will be performed in the
existing distribution lines and there
is no need to account for land
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
20
Sl.
No
Monitoring
Activities
Indicators Status Remarks
procurement/acqu
isition etc.
construction following
the Acquisition and
Requisition of
Immovable Property
Act 2017.
requirements.
But, in civil construction works,
some pieces of land have been
purchased following the Acquisition
and Requisition of Immovable
Property Act 2017.
2.3 Implementation Schedule
The Work Schedule has been prepared which indicates how and when key components of the work
will be completed. The Project will be completed and commissioned within the period of 60 months
(4.5 years). The completion of works is proposed to take place in 48 months as indicated below in
Table 12.
Table 12: Project Implementation Schedule.
Particul 2016 2017 2018 2019 2020 2021
ars Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
Bidding
Bid
Evaluation/
Award
Impleme
ntation
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
21
Performance Monitoring
Compliance with Legal and Policy Requirements
Table 13: Compliance with Legal and Policy Requirements.
GoB Rules and Regulations Summary of Act Compliance with Act
Acquisition and Requisition of
Immovable Property Act 2017.
The purpose of an acquisition and
requisition law is to empower the
acquiring authority to acquire
land only for a public purpose
affecting proprietary right of
citizens.
The idea of this provision is that a
citizen shall not be deprived of his
land otherwise than in
accordance with law and if he is
deprived of for public purposes,
compensation at the market rate
is given to him.
However, once compensation has
been paid there remains no right
in any person to get back the land
acquired. Property validly
acquired and vested in the
requiring body cannot be claimed
by the original acquisition.
After the Acquisition and
Requisition of Immovable
Property Act, 2017, all land
acquisition for civil construction
of zonal, sub-zonal, extension
and main building, will be
made.
BREB shall strictly follow the
acquisition rule, the purchase of
land shall be made and
compensation shall be duly paid
by the BREB authority if
needed.
Compliance with Social Safeguard Covenants
Table 14: Compliance status with Social Safeguard Covenants.
Indicators Issues Activities Compliance
Status
Remarks
Implementation
Arrangement
Arrangement is
set forth in the
PAM of ADB.
National Safeguards
Specialist is
engaged for social
monitoring
Being complied BREB has followed
the ADB loan
covenants.
Environment,
Health and Safety
Safeguard
All the laws and
Regulations related
to the environment
health and safety is
applicable.
Review of existing
laws and
regulations
(National and ADB
Safeguard Policy).
Being complied The national
safeguard specialist
has prepared the
compliance
monitoring report
based on EMP and
reviewing the
existing laws and
regulations.
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
22
Indicators Issues Activities Compliance
Status
Remarks
Human and
Financial
resources to
implement
safeguard
requirements
BREB should make
available or cause
the project
executing agency to
make available
necessary
budgetary and
Human resources
to completely
implements the
EMP.
BREB has made
some contracts
with the
contractors which
have available
manpower, budget
and other
resources for the
implementation of
EMP.
Being complied BREB has followed
the ADB safeguard
requirement of
Human and
Financial resources
to implement
safeguard
requirements.
Bidding
documents of
works and work
contract
Comply with the
measures and
requirements
related to the
contractor set forth
in the IEE and EMP,
make available
budget for all such
environmental and
social measures.
The national
safeguard expert
and BREB monitor
the construction
activities regularly.
Being complied All safeguard
related provisions
incorporated in
bidding document
of works and work
contracts.
Environmental
and social
safeguard
monitoring and
reporting
Any anticipate
results that were
not considered in
the IEE and the
EMP promptly
inform ADB and
proposed for
mitigation in
corrective action
plans.
The monitoring and
the reporting would
be completed and
any potential
breach of
compliance with
the measures and
requirements set
forth in the EMP.
Reviewed EMP
provided in the IEE.
All compliance
status prepared
based on selected
indicators provided
in the check list.
Being complied Environmental and
Social Safeguards
Monitoring reports
are submitted by
BREB on semi-
annual basis.
Labour Standard Comply with all
applicable labour
law, treaty
obligations of the
borrowers and child
labour law of
Bangladesh.
Provided safe
working condition
Labour standard
has been
maintained at the
construction sites,
& labour campsites
and regularly
monitoring this
issue following the
ADB SPS 2009 and
Being complied
(Except women
workers at the
construction sites
due to
unavailability of
women workers it
is difficult to recruit
them for project
No child labour
is allowed to
work at the site
No HIV/AIDS
examination
are conducted
yet at the sites
but awareness
sessions are
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
23
Indicators Issues Activities Compliance
Status
Remarks
for male and
female workers.
Carry out HIV/AIDS
and Human
Trafficking
presentation and
awareness
campaigns in the
campsites and
corridor of
influences. Engage
women labours as
wage laborers
depending on their
skill, provide equal
wages.
other national laws. sites.) conducting
regularly
between
workers at the
labor camp and
construction
sites.
Project Reviews The project
progress has to be
assessed by the
ADB with necessary
midcourse
correction.
ADB is reviewing
the progress report,
social and
environmental
safeguards report
and other reports
and giving the
recommendation
for necessary
modification.
Being complied All comments/
recommendations
from the ADB have
been addressed
and submitted to
BREB and ADB
accordingly.
Compliance with Resettlement Plan Requirements
Table 15: Compliance with Legal and Policy Requirements on RP (Resettlement Plan).
Sl. No RP requirements Compliance Status
1 Land for civil constructions is required for the project, and all
project facilities made available to works contractors in
accordance with the schedule agreed under the related works
contract and all land acquisition and resettlement activities are
implemented in compliance with (a) all applicable laws, and
regulations of the Borrower relating to land acquisition, and
involuntary resettlement; (b) the involuntary Resettlement
Safeguards; (c) RF, and (d) all measures and requirements set
forth in the respective RP, and any Corrective Actions set forth
in the Safeguards Monitoring Report.
Being complied.
Land for civil construction have
been purchased following the
Acquisition and Requisition of
Immovable Property Act, 2017.
2 No physical or economic displacements takes place in
connection with the project until; (a) compensation, and other
entitlements have been provided to the affected people in
accordance with RP; (b) a comprehensive income and livelihood
restoration program has been established in accordance with
the RP.
Owing to project activities no
adjustment of physical or
economic displacement is
required.
3 The Borrower shall ensure, or cause the Project Executing
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
24
Sl. No RP requirements Compliance Status
Agency to ensure, that all bidding documents and contracts for
Works contain provisions that requires contractors to (a)
comply with the measures and requirements relevant to the
contractors set forth in the RP and any small ethnic community
people plan, and any corrective or preventive actions set out in
the safeguards monitoring report, (b) make available budgets
for all such social measures; (c) provide the Borrower with a
written notice of any unanticipated issues or small ethnic
community risks or impact that arise due to construction,
implementation or operation of the project that were not
considered in the RP, or any small ethnic community plan; (d)
adequately record the condition of road, agricultural land, and
other infrastructure prior to starting to transport materials, and
construction.
Being complied.
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
25
Implementation of the Grievance Redress Mechanism
Grievance Redressal Mechanism
In order to address any issues, BREB established a committee for a potential resolution. On behalf of
BREB, the committee consult properly with local people to ensure impacts are minimized to ensure
no / reducing the grievances arise. The committee consists of the following members.
Table 16: GRM Committee of PBSs for resolving the complaints.
Sl.
No.
Members Designation Responsibility
1 Elected Local PBS Director Convenor Organize monthly or
quarterly meeting
2 Member from Office of the Executive
Engineer, BREB
Member secretary Recorded all the issues and
circulated among the
interested people.
3 Member from PBS Member Summarized the grievances
relating to environmental
issues, construction related
issues, OHS and community
health and safety issues and
Gender Based Violence, etc.
4 Member from Consultant Member Note discussions and
decisions of the meeting and
disseminate the information
about GRM and taking follow
up actions.
5 Member from Contractor Member Implementing the decision
with the help of PBS, & BREB.
When any issue will raise, the committee will meet and try to mitigate the issues raised by the
complaint. For instance, if the complaint asks not to install pole in the middle of his agricultural land
but on the back his land. Then the committee sit together and find out whether or not they can re-
align the line by installing few extra poles. In order to do this, the committee checks the availability
of extra poles and accessories with all technical departments and takes decision instantly. Table 17
has been developed to register complaint from PAPs.
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
26
Status of Implementation of the GRM
The summary of complaints received from consumers, APs and another stakeholder are provided in
table-17.
Table 17: Complaints status of the reporting period (January to June 2021).
Complainant/s or
Affected Persons
Location/s and
Date/s of
Complaint
Description of
Grievance/Complaint
Timeline* Remarks
Tree cutting/
trimming of trees
RoW clearing
both for new
line
construction &
Up-gradation.
Due to RoW clearing, it is
a common trend to either
cut down the trees or
trimming the trees of 10
ft from both side of the
electricity line but it is
objected by the
consumers since long.
Trimming of trees
takes twice a year.
Tree species/ free sapling
were distributed to the
affected households.
Shut down
problem
Up-gradation
and
rehabilitation
working areas
One of the most common
grievances is ‘power
shut-down’. It is difficult
to manage power shut
down during line
upgradation and
rehabilitation works
caused consumers are
not in favour of long
hours of power
interruptions.
Common
complaints in each
connection areas of
PBS.
BREB has made a PBS
wise ‘power outage
schedule’ whereas this
schedule is now
implemented in the
PBSs areas.
Hat/bazar days
excluded from the
power outage
schedule and no
outage is being
forwarded after
evening.
Excessive
electricity bill
Everywhere in
the PBS areas
Consumer believed that
sometimes they had to
pay an excessive amount
of bill.
Year-round
problem in some
areas of some PBS’s
To reduce this problem,
PBSs is now conducting
awareness session about
billing system, if any
overbilling is found, it has
been resolved by 3 (three)
consecutive days.
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
27
Stakeholder Engagement
Public Consultation is a regulatory process of any development project as per the ECR Amendment,
2010. ADB also requires disclosure, consultation and participation (DCP) in project processing to
ensure that adequate and timely information is made available to beneficiaries and affected people.
This process enables opportunity to voice opinions and concerns and participate in influencing
decision making and project processes. The SPS 2009 of ADB stresses the significance of
stakeholders DCP for ensuring formulation and execution of development projects in compliance
with environmental and social safeguards regulations. The SPS 2009 requires that the EA will
conduct meaningful consultations with displaced persons, their host communities, and civil society
organizations. Consultation, to be carried out throughout the project cycle, and timely disclosure of
relevant and adequate information has to be undertaken. Both men and women have to be
consulted and involved equitably in project design and implementation. All relevant views of
affected people and other stakeholders need to be considered in decision making, such as project
design, impact assessment, and mitigation measures, sharing of development benefits and
opportunities, and implementation.
Stakeholder Engagement Process
Stakeholders include all those who are affected by the Project. They can be groups of people,
organizations, institutions and individuals. Primary stakeholders of the Project are those who will be
directly affected or benefited. In this Project they include all potential households likely to benefit
from improved electricity supply. Primary stakeholders identified and consulted include
communities to benefit and/or affected by the Project, along with local leaders, community
members and local representatives.
Secondary stakeholders are those who may not be directly affected but have interests in this Project
i.e., concerned government departments, and line agencies, NGOs and the general public at large.
A participatory approach was followed for conducting the stakeholder consultation meetings;
To provide Project information and scope;
The consultants used a Checklist to maintain uniformity and relevancy in discussion and
properly recorded the opinions and views of participants; and
Institutional issues were discussed and participants provided their opinions and suggestions
freely.
Number of consultation exercises were conducted during this reporting period. The stakeholders
consulted include local People, community in the vicinity of project area, local elected
representatives and other external stakeholders such as government officials. The details of
consultations held with issues raised or discussed and suggestions provided by the respective
stakeholders are presented below.
A combination of mixed methods of information disclosure and consultation process was adopted at
this stage. The method selected for consultation was basically designed keeping in mind the profile
of the stakeholders, type of information desired and level of engagement required. In each
consultation session the consultant introduced themselves, introduced the project and the purpose
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
28
of engagement with the respective stakeholder. The primary methods followed in the consultation
process are:
Key informant interview (KII);
Face to Face Interview
Focus group discussion (FGD); and
Public Consultation meeting (PCM).
Consultations
During this reporting period, consultations were carried out with the officials of BREB, PBSs and local
consultants and consumers in the following PBSs when visiting the sites. The type of stakeholder
meeting was in table-18 only for Key Informant Interview (KIIs), & focused group discussion are
provided in Table-18.
During this reporting period, mainly KIIs and FGDs were conducted in the following PBS areas
Table 18: KIIs & FGDs were conducted in this reporting period (July to December 2020)
Sl.
No
Name of PBS Types of interviews
1 Chandpur PBS-2 KII (May 2021)
2 Cox’s Bazar PBS FGD
3 Bogura PBS-2 KII (March 2021)
5 Narayanganj PBS-1 FGD (june 2021)
6 Bhola PBS FGD (February 2021)
Table 19: Summary of KII discussions.
Issues discussed/raised Outcomes of the brief
Is adequate land available for this project? If no, is
land parcels available in surrounding areas for
acquisition/requisition of land?
No need to acquire land, as this project is being implemented
in the existing RoW (Right of Way). BREB has purchased
some sorts of land for construction of zonal, sub-zonal,
vertical extension of main buildings etc. from the landowners
for paying prevailing rate in line with the Land Acquisition,
Requisition and Immovable Property Act, 2017.
Coverage percent of electricity line The electricity coverage is more than 96%. After the
upgradation of distribution line, the coverage will be
increased to 100%.
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
29
Issues discussed/raised Outcomes of the brief
Average time for load shedding There is no load-shedding but due to upgradation works, or
other kind of maintenance, and tree cutting/ trimming, then
force-shedding method is applied to complete the works
properly and ensure the safety of the workers. Before that,
PBS announces locally about this force-shedding to avoid
public unrest.
Is there any incidental record? There is no incidental recorded for the last few years.
PBSs/BREB has worked for ensuring zero-causalities following
the BREB Health, Environment and Safety guideline properly,
and ADB safeguard policy also.
How resolve the grievance which comes from the
consumer/Affected Persons?
PBS has own Grievance Redress system, moreover, a GRM
committee headed by local elected PBS director is working for
looking after the project related issues. PBS and BREB is
serious about the public query and taking remedies within
24hrs or earliest.
Any concern of the local community that needs to be
communicated to BREB?
Tree branches are found to pose a threat to the distribution
line and should be trimmed to avoid danger. But local people
are not interested to trimming their trees that may cause
difficulties to ensure danger free distribution line during
monsoon.
Table 20: Summary of focused group discussions.
Participant’s Opinion, comments and Suggestions Response to Questions/Action Point
Participants are known about the project. They came to
know by changing the power cable, replacing electric
pole in different locations.
They opined that this electric line were 20/25 years old.
It’s a great initiative taken by PBS to change the exiting
line which was mandatory needed.
Consultant briefly discuss about the proposed project to
the participants.
They argued that they have to repair this transmitter by
their own money if fails to transmit power supply
properly.
PBS does not produce electricity, they buy from PDB
(Power Development Board), so, every cost is added in the
electricity connection.
Lack of quality power supply in some areas; industry was
not grown. Water pumping would be another source of
income. Rice mill and other economic activities will
continue and developed if quality electricity is available.
PBS representative confirmed, after up-gradation of
distribution line, quality power supply will be possible and
new consumers will be connected also. Then small
industries will be grown up with creating the job
opportunities locally.
During the winter session they have access to 18 hours
electricity supply but not quality power supply. Low
This situation will be developed after completion of URIDS
project.
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
30
Participant’s Opinion, comments and Suggestions Response to Questions/Action Point
voltage is a problem with them.
Power outage is problem, one more day in a week, they
went out of order of service due to maintenance of PBS
line, even, hat/bazar days and peak hours (at night when
children are studying) they have to suffer from load
shedding. Reasonable solution is required in this regard.
Before upgradation, rehabilitation intensification of
distribution system they will announce locally before
starting their work.
We have support on project activities and local people
will help anytime if they required.
PBS noted their suggestions and requested to consult with
Zonal office for any kind of complain.
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
31
6.0 Conclusion and Recommendations
During this reporting period, the social safeguard monitoring was rigorously carried out at different
locations/areas of the project. Both line construction and civil construction sites were inspected and
collected different types of data such as occupational risks/incident status, pole erection, line
construction/rehabilitation, pole stacked at the road sites, trimming of trees, complaints received,
dust emission, water pollution, waste management, deep tube well installation on the civil
construction sites (depth & test report), responding to the COVID-19 pandemic etc., aligned with the
mitigation measures given in the EMP and as well as fulfilling the requirement of the ADB safeguard
Policy Statement.
The current status of the social safeguard status is satisfactory without any incident or accident at
the construction sites. No complaints received from the consumer, or project affected peoples
(PAPs) relating to this project.
Labor camps are neat and tidy, good access to hygienic sanitation & clean water supply, dust bins
are using for collection of kitchen waste and disposed of in a safe place. There is no trapping and
haunting of wild animals or wild birds was occurred till date. No labor was reported for COVID-19
affected. Hand sanitizers & masks are being used by the workers at the site while working. Solid
wastes are now managed quickly after immediate completion of works at the site and disposed of in
a safe place selected by PBS/BREB.
In the meantime, there are no problems with the RP requirements, and compensation etc. The
project constructs several buildings for establishment of zonal office, sub-zonal office, vertical
extension of PBS main building at various locations etc. where land is required and purchased from
the local people to pay the prevailing rate in line with Acquisition and Requisition of Immovable
Property Act 2017.
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
32
Annex A: Line construction progress of URIDS (DMCS & RRKB) project up to December 2020.
SI
No.
Name of Zone Project Target
(km)
Line Constructe d (km) Progress as per
DPP (%)
1. Dhaka-N 5214 4427 85%
2. Dhaka-S 2894 2929 101%
3. Mymensingh 2588 2593 100%
4. Chittagong 3550 3344 94%
5. Cumilla 6704 6630 99%
6 Sylhet 2746 2746 100%
7 Faridpur 3304 3313 100%
8 Rangpur 3923 3933 100%
9 Rajshahi 3,849 3845 100%
10 Bogra 4,800 4705 98.02%
11 Jessore 6,829 6765 99.06%
12 Barishal 4099 4041 98.58%
Total 50,500 49,286 97.60%
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
33
Annexure-B: Photographs of consultations-KIIs with stakeholders
URIDS ।Social Safeguard Monitoring Report | June 2021 । Bangladesh Rural Electrification Board.
34
Annexure-C: Participant list of FGDs
Venue: Narayanganj PBS-1 area (Group-male)
Date & Time: 08/06/2021; 2:15
SI Name Age Occupation
1 Mohammad Rafiq 62 Day labour
2 Masuduzzaman 41 Service
3 Islam Mia 43 business
4 Abdur Razzak 67 Retired person
5 Baten Mia 35 Business
6 Moniruddin Mia 48 Business
7 Shafiqul Islam 25 Student
8 Zinnath Ali 43 Day labour
9 Hossen 32 unemployed
10 Yasin bhuiyan 52 Business
11 Malek member 58 UP member
12 Tansen Bhuiyan 53 business