45371-007: madhya pradesh irrigation efficiency ... · madhya pradesh irrigation efficiency...

119
Land Acquisition and Resettlement Plan December 2019 Project Number: 45371-007 IND: Madhya Pradesh Irrigation Efficiency Improvement Project Pipeline Distribution System of Zone 3 for Command Area CCA 63548-ha – Left Bank Prepared by the Madhya Pradesh Water Resource Department with the assistance of the Project Contractor (L&T Construction, India) for India and the Asian Development Bank. This land acquisition and resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Upload: others

Post on 15-Oct-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

Land Acquisition and Resettlement Plan

December 2019 Project Number: 45371-007

IND: Madhya Pradesh Irrigation Efficiency

Improvement Project Pipeline Distribution System of Zone 3 for Command Area CCA 63548-ha – Left Bank

Prepared by the Madhya Pradesh Water Resource Department with the assistance of the Project Contractor (L&T Construction, India) for India and the Asian Development Bank. This land acquisition and resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 2: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

Land Acquisition & Resettlement Plan (This document is prepared in accordance to the ADB Resettlement Plan Requirement as described in ADB Safeguard Policy Statement, 2009)

Document Stage: Final Draft

India: Madhya Pradesh Irrigation Efficiency Improvement Project

Subproject:

Pipeline Distribution of Zone 3 for Command Area CCA 63548

ha of Kundalia Irrigation Project- Left Bank

December 2019

Page 3: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

2

CURRENCY EQUIVALENTS (As of 31st December 2019)

Currency unit – Indian Rupee (Rs) INR 1.00 = $ ------------------ $ 1.00 = ---------------------

ABBREVIATIONS

ADB : Asian Development Bank AH : Affected Households AP : Affected People BSR : Basic Schedule of Rate CSC : Construction Supervision Consultant DC : Distribution Chamber DMS : Detailed Measurement Survey DP : Displaced People DPR : Detailed Project Report EA : Executive Agency FGD : Focus Group Discussion GOMP : Government of Madhya Pradesh GRM : Grievance Redress Mechanism GRC : Grievance Redress Committee IA : Implementing Agency IP : Indigenous People KIP : Kundalia Irrigation Project LAR : Land Acquisition and Resettlement LVC : Land Valuation Committee MFF : Multi Tranche Financing Facility MPIEIP : Madhya Pradesh Irrigation Efficiency Improvement Project NGO : Non Governmental Organization PIU : Project Implementation Unit PPTA : Project Preparatory Technical Assistance PS : Pumping Station RF : Resettlement Framework ROW : Right of Way LARP Land Acquisition and Resettlement Plan R&R : Resettlement and Rehabilitation SC : Scheduled Caste SIA : Social Impact Assessment SPS : Safeguard Policy Statement ST : Scheduled Tribe WRD : Water Resources Department WUA : Water User Association

Page 4: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

1

CONTENTS

Page

I. EXECUTIVE SUMMARY 5

A. Introduction 5

B. Scope of Land Acquisition 5

C. Land Acquisition Impacts 6

D. Consultations with DPs and their Participation 7

E. Legal Framework 7

F. Entitlements, Assistance and Benefits 7

G. Land Acquisition Budget and Financing Plan 8

H. Grievance Redress Mechanism 8

I. Institutional Arrangement 8

J. Implementation Schedule 9

K. Monitoring and Reporting 9

II. PROJECT DESCRIPTION 10

A. Introduction 10

B. General Profile of the Subproject Area 12

C. Subproject Impacts and Benefits 12

D. Minimizing Land Acquisition 13

E. Scope and Objectives of Preparation of Land Acquisition and Resettlement Plan (LARP) 13

F. Methodology adopted for Socio-economic Survey 14

III. SCOPE OF LAND ACQUISITION AND RESETTLEMENT 16

A. Land Acquisition Requirement 16

B. Resettlement Impacts 17

C. Loss of Private Land in Subproject. 17

D. Loss of Structures in the Subproject 18

E. Loss of other Assets in the Subproject 18

F. Loss of Livelihood in the Subproject 18

G. Significance of Impact on Land Owners 18

IV. SOCIO-ECONOMIC INFORMATION AND PROFILE 20

A. Census Socioeconomic Survey 20

B. Demographic Profile of DPs 20

C. Socio-economic Profile 23

D. Key Socio-economic Indicators 26

V. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION 28

A. Public Consultations 28

B. Methods of Consultation 28

C. Outcome of the Consultations 30

D. Conclusions of the Group Consultations 34

E. Plan for further Consultation in the Project 34

F. Information Disclosure 35

VI. GRIEVANCE REDRESS MECHANISMS (GRM) 36

Page 5: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

2

VII. LEGAL FRAMEWORK 38

A. Introduction 38

B. Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act (RFCT in LARR), 2013 38

C. Legal and Policy Frameworks of Madhya Pradesh State: 39

D. ADB’s Safeguard Policy Statement (SPS), 2009 40

E. Comparison of Government and ADB Policies 41

F. R&R Policy Framework for the Subproject 45

G. Valuation of Assets 48

VIII. ENTITLEMENTS, ASSISTANCE AND BENEFITS 51

A. Introduction 51

B. Cut-off-Date for Entitlement 51

C. Subproject Entitlement 51

D. Loss of land 52

E. Loss of Structures 52

F. Loss of trees and crops 52

G. Additional assistance to vulnerable households 52

H. Loss of community infrastructure/common property resources 53

I. Temporary Impacts 53

J. Entitlement Matrix 53

IX. RELOCATION, INCOME RESTORATION AND REHABILITATION 66

A. Basic Provision for Relocation 66

B. Income Restoration and Rehabilitation 66

C. Provisions for Loss of Livelihood 67

D. Additional Support from Ongoing Poverty Reduction Programs 67

X. LAND ACQUISITION BUDGET AND FINANCING PLAN 69

A. Introduction 69

B. Compensation Payment 69

C. Compensation for Community Property Resources 70

D. LAP Implementation and Support Cost 70

E. Sources of Funding and Fund Flow Management 70

XI. INSTITUTIONAL ARRANGEMENTS AND CAPACITY DEVELOPMENT 72

A. Institutional Requirement 72

B. Executing Agency 72

C. Land Acquisition Management at PIU/PMU 72

D. Capacity Building on RP in the EA 75

XII. IMPLEMENTATION SCHEDULE 76

A. Introduction 76

XIII. MONITORING AND REPORTING 78

A. Need for Monitoring and Reporting 78

B. Monitoring by PIU 78

C. Monitoring Indicators 78

D. Reporting Requirements 79

Page 6: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

3

TABLES :

Table 1 : Summary of Impacts on Properties ......................................................................... 6

Table 2: Details of Components of the Subproject ...............................................................11

Table 3: Land Acquisition Requirements ..............................................................................16

Table 4: Ownership of Land Affected in the Subproject ......................................................17

Table 5: Details of Displaced Persons in the Subproject .....................................................17

Table 6 : Significance of Land Impact ...................................................................................18

Table 7 : All Displaced Persons by Sex .................................................................................20

Table 8 : Displaced Household by Religion ..........................................................................21

Table 9 : Displaced Household by Social Category ..............................................................22

Table 10 : Family Size of the Household ...............................................................................22

Table 11 : Age Group of DPs ..................................................................................................23

Table 12 : Educational level of DPs .......................................................................................23

Table 13 : Occupation of DPs .................................................................................................24

Table 14 : Monthly Household Income of DHs ......................................................................25

Table 15 : Vulnerable (mutually exclusive) ...........................................................................25

Table 16 : Key Socio-economic Indicators ............................................................................27

Table 17: Consultation Methods ............................................................................................28

Table 18: Consultation Locations ..........................................................................................29

Table 19 : Summary of the Consultation Outcome ...............................................................33

Table 20: Format for Public Consultation and Disclosure Plan ...........................................35

Table 21: The Comparison of ADB and GOI Policy ..............................................................41

Table 22: Entitlement Matrix ...................................................................................................54

Table 23: Estimated Budget for Implementation of the RP ..................................................71

Table 24: Agencies Responsible for Resettlement Implementation ....................................73

FIGURES : Figure 1: Schematic of Kundalia Irrigation Project Left Bank .............................................11

Figure 2: An Overview of the Grievance Redress Mechanism.............................................37

ANNEXURES : Annexure 1 : Summary of Affected Persons and Common Property Resources ...............80

Annexure 2 : Summary of Affected Persons and Common Property Resources ...............85

Annexure 3 : Summary of Affected Persons and Common Property Resources ...............89

Annexure 4 : Summary of Affected Persons and Common Property Resources ...............90

Annexure 5 : Summary of Affected Persons and Common Property Resources ...............91

Annexure 6 : Summary of Affected Persons and Common Property Resources ...............94

Annexure 7 : Summary of Affected Persons and Common Property Resources ...............98

Annexure 8 : Summary of Affected Persons and Common Property Resources ............. 101

Annexure 9 : Summary of Affected Persons and Common Property Resources ............. 104

Annexure 10 : Summary of Affected Persons and Common Property Resources ........... 105

Annexure 11 : Summary of Affected Persons and Common Property Resources ........... 106

Page 7: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

4

Annexure 12 : Approved Collector Rates of Agriculture Land of Nalkheda Tehsil, Agar Malwa District ........................................................................................................................ 109

Annexure 13 : MSP Rates By MP Govt. ............................................................................... 114

Annexure 14 : Memorandum of Understanding (MOU) to document foregone compensation for temporary land use ................................................................................ 115

Page 8: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

5

I. EXECUTIVE SUMMARY

A. Introduction

1. Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to

achieve high irrigation efficiency and water productivity in the State. The MPIEP includes the

development of the Kundalia Irrigation Project (KIP), which is a pressurized pipeline distribution

system for 1, 30,690 hectares (ha) cultivable command area (CCA) and for supply of water for

potable and industrial use.

2. Government of Madhya Pradesh has received loan from Asian Development Bank for

implementation of the Project. The Water Resource Department (WRD) of Madhya Pradesh is

the Implementing Agency (IA) for the Project. Presently L&T Construction as a DBO Contractor

has been engaged for construction and to manage the scheme operation and maintenance for

an initial period of 5 years, with support to hand-over the long term management to a joint

management organization comprised of WRD, a private contractor, and a project-level Water

User Association (WUA).

3. In compliance with the applicable Government of India, State Government legal and

policy framework and ADB SPS 2009, a Land Acquisition and Resettlement Plan (LARP) for this

subproject covering Distribution Pipeline and Outlet Management Syatem (OMS) of Zone 3 of

Left Bank is prepared as per the detailed design. The LARP also complies with the Land

Acquisition Framework (LAF) for the project agreed between WRD and ADB.This subproject is

considered as Category-B as per Involuntary Resettlement (IR) categorization is concerned.

4. The objective of this LARP is to assist the affected people to improve, or at least restore

their living standards to the pre-project level. The document describes the magnitude of impact,

mitigation measures proposed, method of valuation of land, structure and other assets, eligibility

criteria for availing benefits, baseline socio-economic characteristics, entitlements based on

type of losses and tenure, the institutional arrangement for delivering the entitlements and

mechanism for resolving grievances and monitoring.

B. Scope of Land Acquisition

5. There will be Outlet Management System (OMS) of 235 outlets of 1X2 Meter each and

distribution pipelines ranging from Diameter 400 mm to 1700 mm, to be laid in 12 Villages of

Tehsil Nalkheda of District Agar Malwa.For laying of underground distribution pipelines there will

be involvement of only temporary acquisition of land.

6. The Distribution Pipeline of different Diameters will be laid in 12 affected Villages for

which 5.777 ha of private land and 0.737 ha of Government land needs to be acquired

temporarily till the laying of the underground pipelines for a maximum duration of 6 months.

7. For construction of all the above components of the subproject of Zone 3, there will be

total requirement of 6.561 Ha of land which includes 5.824 ha of private land and 0.737 ha of

Page 9: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

6

Government land. For construction of permanent structures of 235 OMS, 0.047 ha of private

land will be acquired permanently.

C. Land Acquisition Impacts

8. The land requirement for all the temporary and permanent structures of this subproject,

land has been divided into two categories, that is private land of 5.824 ha and 0.737 ha of

Government Land. The OMS of 235 outlets may require 0.047 ha of land permanently.

Therefore total requirement of private and government land will be 6.561 ha for this subproject.

9. The land will be acquired temporarily as per the provisions of Pipeline Act 2013 of

GOMP for the alignment of the pipeline. But for permanent acquisition of land, it will be as per

Consent Land Purchase Policy’ 2013 of the State. In case of failure of negotiations, the land will

be acquired as per the provisions of RFCTLARR Act 2013. In case of any negotiated

settlement, an independent external party engaged by the EA, namely Prof. Vivek Bhatt of

Water & Land Management Institute (WALMI) will document the negotiations and settlement

processes as per ADB norms.

10. There are 403 affected households comprising a population of 2347 APs in all the 12

Villages. Among other impacts, there is 1 timber tree, 3 other fruit bearing trees and parts of

some standing orchard trees are also being impacted which have been divided in three

categories for paying compensation to AHs. However, the above impacts will be permanent for

which compensation will be paid for the loss incurred to them.

11. There is no Community Property Resources (CPR) being affected in this subproject.

There are mainly bushes found on the impacted government land due to scarcity of water in the

area. There are no informal settlers found living or cultivating land in the subproject area. The

Summary of impacts on the properties is presented in the following Table No. 1 which indicates

that there is no significant impact on land and livelihood of the AHs due to temporary acquisition

of land:--

Table 1 : Summary of Impacts on Properties

S. No.

Type of Impact AHs APs

Type of Ownership

of Land

Land Acquis

(Ha)

Physically Displaced Yes / No

Significance of Impact

1 Temporary

403

2347 Private Revenue

5.777

No

Insignificant Impact less than

10% on the properties of AHs

2 Temporary 0 0 Government Land

0.737 No -------

2 Permanent (235 OMS)

- - Private Revenue

0.047 No

Insignificant Impact less than

10% on the properties of AHs

Total 403 2347 6.561

Page 10: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

7

D. Consultations with DPs and their Participation

12. Aside from direct consultations with DHs / DPs during socio-economic survey, Group

Consultations were held in 11 impacted Villages in 3 phases. All relevant aspects of project

designs, details of impact to their private properties were physically assessed and discussed

with the stakeholders and affected communities. In all 402 persons (69 females and 333 males)

participated in the group consultations, held in 11 Villages of Nalkheda Tehsil on 13th

November’2018, 14th to 16th April’ 2019 and 24thto 26th June’ 2019. The Elected People’s Representatives of the affected areas also took part in these group consultations.

13. The affected population is very much concerned about the early completion of the

project looking to the long term benefits of this project. Information will be disseminated to APs

at various stages. Information including magnitude of loss, detailed asset valuations,

entitlements and special provisions, grievance procedures, timing of payments, Civil works

schedule was discussed and LAP will be disclosed during project implementation. This will be

done through public consultations and made available to APs as brochures, leaflets, or booklets

in Hindi being the local language. The Hindi version of a summary of LAP along with Entitlement

Matrix and structure and process of grievance redressal will be disclosed.

E. Legal Framework

14. The legal framework and principles adopted for addressing land acquisition and

resettlement issues in the Project have been guided by the existing legislation and policies of

the GOI, the Government of Madhya Pradesh, Asian Development Bank and the Land

Acquisition Framework (LAF) adopted for the project. Prior to the preparation of the LARP, a

detailed analysis of the existing national and state policies was undertaken and a RF has been

prepared for the entire program. This subproject LARP is prepared based on the review and

analysis of all applicable legal and policy frameworks of the Country and ADB Policy

requirements. The gaps between the Polices have been identified and addressed to ensure that

the LARP adheres to the SPS (2009) requirements. All compensation and other assistances will

be paid to all DPs prior to their physical / economic displacement.

15. The State Government of Madhya Pradesh has come up with a “Consent Land Purchase Policy’ 2013 for direct purchase of land through negotiations. In case of failure of any

negotiations, the permanent land acquisition in this subproject context will be according to the

process and provisions of RFCTLARR Act’2013. Since the land may be acquired compulsorily if

the negotiations of the Consent Land Purchase Policy fail so the Safeguard Requirement 2 of

ADB SPS 2009 will be applicable for all the provisions to be implemented in this subproject.

F. Entitlements, Assistance and Benefits

16. In case of land acquisition, the date of publication of preliminary notification for

acquisition under section Right to Fair Compensation and Transparency in Land Acquisition,

Rehabilitation and Resettlement Act, 2013 (RFCT in LARR Act – 2013) will be treated as the

cut-off date. For non-titleholders, the cut-off date will be the end of the census survey which is

Page 11: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

8

30th June’ 2019. Land and structures affected under the subproject will be compensated at

replacement cost. DPs who settle in the affected areas after the cut-off date will not be eligible

for any compensation. They, however, will be given sufficient advance notice and requested to

vacate premises and dismantle affected structure, if any, prior to subproject implementation.

17. The EA will provide adequate and appropriate replacement of land and structures or

cash compensation at full replacement cost for lost land and structures, adequate compensation

for partially damaged structures, and relocation assistance, according to the Entitlement Matrix.

The EA will compensate to the non-title holders for the loss of assets other than land, such as

dwellings, and also for other improvements to the land, at full replacement cost. Besides

payment of compensation amount, the entitled DHs will be given Rehabilitation Assistance and

Grants for Skill development of their wards if there is permanent and significant impact on their

properties. The entitlements to the non-titleholders will be given only if they occupied the land or

structures in the subproject area prior to the cut-off date.

G. Land Acquisition Budget and Financing Plan

18. The WRD will make funds available as required to cover all compensation, resettlement

assistance cost and grant for skill upgradation from its budgetary provisions. The proposed

budget rates, as well as the costs, are based on field level information and experience in

resettlement management. The cost estimates for the implementation of LAP for this subproject

is Rs. 4.91 Million.

H. Grievance Redress Mechanism

19. During implementation of LARP of the Project as a whole, some grievances may arise

so there is always a need of some mechanism to redress the grievances of the affected

population. Therefore a project level combined GRM is in place for addressing social,

environmental and project related grievances. The GRC has been formed vide order dated

24.10.2019. Other than disputes relating to ownership rights and apportionment issues on which

the LARR Authority has jurisdiction, the GRC reviews grievances involving all resettlement

benefits, relocation and payment of assistances. No grievance has been received by GRC till

date.

I. Institutional Arrangement

20. The Executing Agency (EA) for the Project is the Ministry of Water Resources,

Government of Madhya Pradesh, and the Implementing Agency (IA) is Water Resources

Department, GOMP. The PMU was established at Rajgarh and remains functional since

16.04.2018 and shall remain functional for the whole subproject duration. The existing Camp

Office at Zeerapur Tehsil Head Quarter has already been established which is the Project

Implementation Unit (PIU). This office will be functional for the whole Subproject duration.

Page 12: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

9

J. Implementation Schedule

21. The time for implementation of LARP will be scheduled as per the overall subproject

implementation. After the detailed design completed, requirement of updating of LARP will be

checked by L&T Constructions. If updated LARP is required, the approval from the EA should

be obtained prior paying compensation to the affected people. The contractor will pay

compensations for all temporary land acquisition but EA will pay the compensation for

permanent acquisition of impacted land. The commencement of work will only be undertaken on

the lands and properties, where compensations have been fully paid.

K. Monitoring and Reporting

22. Land Acquisition and Resettlement Plan (LARP) implementation for the subproject will

be closely monitored by the EA, which is Water Resources Department of GOMP. Keeping in

view the significance of resettlement impacts of the overall project, the monitoring mechanism

for this project will have monitoring by Project Management Unit (PMU) / PIU and monitoring by

an external resettlement expert. The position of resettlement expert has been advertised and

sufficient numbers of EOI have been received. PMU will be responsible for overall supervision

and implementation of the LARP. PIU will prepare monthly progress reports on resettlement

activities and submit to PMU. The Project Management Unit (PMU) of MPWRD will submit semi-

annual reports to ADB.

Page 13: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

10

II. PROJECT DESCRIPTION

A. Introduction

23. Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to

achieve high irrigation efficiency and water productivity in the State. The MPIEP includes the

development of the Kundalia Irrigation Project (KIP), which is a pressurized pipeline distribution

system for 1, 30,690 hectares (ha) cultivable command area (CCA) and for supply of water for

potable and industrial use.

24. Government of Madhya Pradesh has received loan from Asian Development Bank for

implementation of the Project. The Water Resource Department (WRD) of Madhya Pradesh is

the Implementing Agency (IA) for the Project.Presently L&T Construction as a DBO Contractor

has been engaged for construction and to manage the scheme operation and for maintenance

for an initial period of 5 years, with support to hand-over the long term management to a joint

management organization comprised of WRD, a private contractor, and a project-level Water

User Association (WUA).

25. The main pumping stations will be located at the end of concrete-lined approach

channels constructed on the left bank of the reservoir. The DCs are proposed on the nearby

hills and the water from pumping stations will be pumped through raising mains (pipelines) to

the DCs. Water will be discharged from DCs through pressurized secondary pipelines to the

designated command areas. All pipelines under this Project will be underground only. The total

area to be irrigated by Kundalia Pipeline Irrigation Project will be 1,30,690 ha of agriculture land

in Agar Malwa and Rajgarh District of Madhya Pradesh. Out of the proposed land to be

irrigated, there will be a CCA 63548 ha of land from the Left Bank in Agar Malwa District.

26. This Land Acquisition and Resettlement Plan has been prepared for one of the

subproject of Zone 3 of Left Bank of Kundalia Irrigation Project which comprises of Pipeline

Distribution System to be passing through 12 Villages in Tehsil Nalkheda of District Agar Malwa

and 235 OMS of 1 X 2 Meter each. The components of this subproject, proposed to be

constructed are depicted in the following Figure: 1 and described in Table No. 2:

Page 14: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

11

Figure 1: Schematic of Kundalia Irrigation Project Left Bank

Table 2: Details of Components of the Subproject

COMPONENTS OF THE SUBPROJECT DETAILS OF THE SUBPROJECT

235 Outlet Management System of

1 Meter X 2 Meter Each

235 OMS will require 0.047 ha of land

permanently. Each OMS will be constructed in

between a Block of Land of 30 Ha of land.

Distribution Pipeline System-

417 Meters of Pipeline - Diameter 1100 mm

3728 Meters of Pipeline - Diameter 1000 mm

946 Meters of Pipeline - Diameter 900 mm

3876 Meters of Pipeline - Diameter 800 mm

1350 Meters of Pipeline - Diameter 700 mm

2334 Meters of Pipeline - Diameter 600 mm

977 Meters of Pipeline - Diameter 500 mm

4415 Meters of Pipeline -Diameter 450 mm

18298 Meters of Pipeline-Diameter 400 mm

The Underground Distribution Pipelines of

different diameters ranging from 400 mm to 1700

mm will be passing through an area of 6.514 ha

of land. These Distribution Pipelines will be

passing through the Land Holdings of 403 DHs

and 2347 DPs, in 12 Villages of Tehsil Nalkheda

of Distt. Agar Malwa.

Page 15: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

12

27. In compliance with the applicable Government of India, State Government and ADB

legal and policy framework, a Land Acquisition and Resettlement Plan (LARP) for these above

mentioned components is prepared as per its detailed design. The LARP also comply with the

Land Acquisition Framework (LAF) for the Project agreed between WRD and ADB. This

subproject is considered as Category-B as per Involuntary Resettlement (IR) categorization is

concerned.

B. General Profile of the Subproject Area

28. The subproject area lies in 12 Villages in Nalkheda Tehsil of Agar Malwa District. Agar

Malwa District became the 51st District of Madhya Pradesh on 16 August 2013. It was carved

out of the existing Shajapur District. Agar town is its administrative headquarters Agar Malwa

District has two Sub Divisions, Agar Malwa Division and Susner Division. There are four Tehsils

that is Agar Malwa, Badod, Susner and Nalkheda in Agar Malwa District.

29. The total population of Agar is 5, 71,278 out of which 2, 93,052 are males and 2, 78,226

are females. As per the Census 2011, the literacy rate of Agar is 80.3%. Thus Agar has higher

literacy rate compared to 69.1% of Shajapur District. The male literacy rate is 87.8% and the

female literacy rate is 72.31% in Agar. There is Schedule Caste (SC) constitutes 13.8% while

Schedule Tribe (ST) are only 1.3% of the total population in Agar Malwa.

C. Subproject Impacts and Benefits

30. At the moment the area is suffering acute shortage of water for irrigation and drininking

purposes. The proposed pressurized pipeline will give long-term benefits of irrigation to the local

population of the area. Once the project is completed they will be able to take two crops in a

year, which will improve their economic condition. This subproject has many positive impacts on

the local population of the area which will be benefitted immensely by this upcoming project.

31. Due to availability of water they will have an increased irrigation potential. The irrigation

will be through underground-pressurized distribution pipelines so there will not be any

evaporation of water and that may prove to be a low maintenance scheme of irrigation. Once

the benefitted population will be able to take two crops in a year they will have better living

standards. Due to sustained availability of water there will be increased green cover in the area.

The increased green cover in the area will help in conservation of the forest.

32. The Subproject area is mainly dependent on farming and therefore with the availability of

irrigation facilities in the area the yield of the crop will be doubled and the quality of the grains

will also improve. To sell the surplus grains there will be improved market facilities in the area.

The availability of better marketing facilities in the adjoining areas will improve their economic

condition resulting into better life style, status and in confidence building.

33. The proposed subproject can be viewed as boosting economic growth and poverty

reduction which will bring substantial social and economic development in the region. The social

benefits arising due to the subproject will be triggered off to improved irrigation potential and

better market facilities, which will also open up wider work and opportunities for increased

Page 16: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

13

frequency of interaction with outsiders. This will increase the awareness level of the people in

the villages with regard to their health and nutrition, lesser rate of mortality, value of education

and proper utilization of available resources.

34. Due to their exposure with adjoining developed areas and interaction with the

government, non-government and other development agents will help people to gain new

knowledge on improved farming, land development, development and maintenance of natural

resources through the formation of various economic and social development groups. All these

developments in the area will open new horizons of their economic development and confidence

building not only for them but even for the next generations.

D. Minimizing Land Acquisition

35. Efforts have been made through appropriate project design to minimize adverse social

impacts and to reduce disruption of livelihood by avoiding any physical displacement of the

affected households. Due measures were taken to reroute the alignment of the pipeline to save

any shelters and other permanent structures in the impacted area. Under the subproject, land

acquisition of private land will be there because of laying of Distribution Pipeline and

construction of 235 OMS. But the significance of the impact on their properties and livelihood

will be less than 10% as indicated in the following Table No. 6 regarding Significance of impact.

36. The 235 Outlet Management System of 1X2 M each, will be permanent structures so a

minimal 0.047 ha of land will be acquired permanently. The Outlet Management System will be

constructed in between a Chak (Block of Land) of 30 Ha of land. Therefore, there will be total

need of 0.047 ha of private land to be acquired for 235 outlet management system.

37. There will be alignment of Distribution Pipeline net work of different diameters of pipes to

be laid underground ranging from 1700 mm, 1600 mm, 1500 mm, 1400 mm, 1300 mm, 900

mm, 800 mm, 700 mm, 600 mm, 500 mm, 450 mm and 400 mm. The impacted lands of these

AHs will be acquired temporarily for a maximum period of 6 months for laying of these

underground pipelines.

38. There will be only temporary impact on the properties of 403 AHs as 5.777 ha of private

land and 0.737 ha of Government land will be impacted. During construction period the

temporarily AHs will get double crop compensation as well as 15% cost of the impacted land as

per the Pipeline Act of the State. Once the construction work is over the temporarily impacted

land will be brought back to its pre project scenario and handed over to the AHs.

E. Scope and Objectives of Preparation of Land Acquisition and Resettlement Plan (LARP)

39. The objective of this LARP is to assist the affected people to improve, if possible, or at

least restore their living standards to the pre-project level. The document describes the

magnitude of impact, mitigation measures proposed, method of valuation of land, structure and

other assets, eligibility criteria for availing benefits, baseline socio-economic characteristics,

Page 17: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

14

entitlements based on type of losses and tenure, the institutional arrangement for delivering the

entitlements and mechanism for resolving grievances and monitoring.

40. Implementation of the Subproject will involve total land acquisition of 6.561 ha of land in

which there will be 5.824 Ha of Private Land of 403 households and 0.737 ha of Government

Land. Because for Laying of underground distribution pipeline, there will be only temporary

acquisition of land.This LARP has been prepared on the basis of subproject census and

socioeconomic survey findings and in consultation with various AHs and DPs.

41. The LARP comply with ADB Safeguard Policy Statement-2009 designed by ADB to

protect the rights of the affected persons and communities. The issues identified and addressed

in this document are as follows:-

(a) Type and extent of loss of land / non-land assets, loss of livelihood, loss of common property resources and social infrastructure;

(b) Impacts on vulnerable groups like poor, women and other disadvantaged sections of society including non-title holder DPs,

(c) Public consultation and peoples participation in the subproject; (d) Existing legal and administrative framework and formulation of resettlement (e) Preparation of entitlement matrix, formulation of relocation strategy and

restoration of businesses / income; (f) R&R cost estimate including provision for fund and; (g) Institutional framework for the implementation of the plan, including grievance

redress mechanism, monitoring & reporting.

F. Methodology adopted for Socio-economic Survey

42. For preparation of LARP, Socio-economic survey was carried as 403 households

comprising a population of 2347 APs are being affected due to construction of the components

of this subproject. All the permanent structures are proposed to be constructed on private and

government land as mentioned in Table No.3 of this LARP.

43. The census survey includes the (i) Inventory of 100% losses of land and non-land

assets, (ii) Categorization and measurements of potential loss, (iii) Physical measurements of

the affected assets / structures, (iv) Identification of trees and crops, (v) Collection of information

on household characteristics, including social, economic and demographic profile.

44. In this Subproject private property of 403 households and 2347 APs in 12 Villages is

being affected so group consultations were held with stakeholders, people’s representatives,

general public, women, Government officials and the concerning Officials of L&T Construction in

11 impacted Villages in 3 phases.

45. The primary data for the study was collected through group discussion/ interviews with

the Project Affected Persons (PAPs) and peoples representative with the help of a pre-tested

and well-structured questionnaire. Important aspects covered in the questionnaire are the

identification particulars of PAPs, Family details of the respondent, assets and irrigation

facilities, details of infrastructures, land utilization, cropping pattern, commercial / self

Page 18: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

15

employment activities, household income, expenditure, type of effects, losses and status of

women. There was extensive observation of the life and culture of the respondents while having

group consultations and Interviews with the PAFs.

46. To ensure peoples’ participation in the planning phase and aiming at promotion of public

understanding and fruitful solutions of developmental problems such as local needs of farmers

and prospects of resettlement, various sections of stakeholders were consulted through group

consultations, individual interviews, formal and informal consultations.

Page 19: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

16

III. SCOPE OF LAND ACQUISITION AND RESETTLEMENT

A. Land Acquisition Requirement

47. The component of this subproject is of temporary nature which involves construction of

Distribution Pipelines to be laid underground in 12 Villages of Tehsil Nalkheda of District Agar

Malwa. There will be only temporary impact on the properties of 403 AHs so the private land of

5.777 ha and 0.737 ha of Government Land has to be acquired temporarily till the construction

work is completed in maximum durartion of 6 months.

48. There will be 235 OMS of 1M X 2 M which may require 0.047 ha of land which will be

acquired permanently because these 235 OMS will be permanent structures and each outlet

valve will be constructed in between a chak (Block of land) of 30 ha of land. For construction of

these 235 OMS there will be requirement of 0.047 ha of private land. The detailed land

requirements of this subproject are presented in Table: 3.

Table 3: Land Acquisition Requirements

Sl. No. Components Nature of Acquisition Area (in Ha)

1 5538 meters of 1700 mm pipelines Temporary 0.352

2 1899 meters of 1600 mm pipelines Temporary 0.087

3 1804 meters of 1500 mm pipelines Temporary 0.119

4 185 meters of 1400 mm pipelines Temporary 0.444

5 1367 meters of 1300 mm pipelines Temporary 0.463

6 4559 meters of 900 mm pipelines Temporary 0.789

7 4934 meters of 800 mm pipelines Temporary 0.821

8 3308 meters of 700 mm pipelines Temporary 0.355

9 3696 meters of 600 mm pipelines Temporary 0.052

10 1191 meters of 500 mm pipelines Temporary 0.541

11 968 meters of 450 mm pipelines Temporary 0.608

12 4398 meters of 400 mm pipelines Temporary 1.883

13 *235 Outlet Management System Permanent 0.047

Total 6.561 *235 Outlet Management System of 1m X 2m in size

Page 20: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

17

B. Resettlement Impacts

49. There will be alignment of distribution pipelines of different diameters ranging from 400

mm to 1700 mm to be laid in 12 Villages of Tehsil Nalkheda, which will be acquired temporarily.

Therefore total requirement of private and government land for this purpose will be 6.514 ha.

The minimal land of 0.047 ha for 235 Outlet Management System has to be acquired

permanently as per the Consent Land Purchase Policy’ 2013 of Government of Madhya

Pradesh or as per the RFCTLARR Act 2013, if negotiations fails.

50. There will be impact on private agriculture land of 5.777 ha of 403 affected households

and 0.737 ha of Government land which needs to be acquired temporarily for laying of

distribution pipeline. Besides this 0.047 ha of private land will be acquired permanently for 235

outlet management system. These 403 affected households comprise a population of 2347

Affected Persons. The details of ownership and the type of land is being summarized in the

following Table: 4

Table 4: Ownership of Land Affected in the Subproject

Sl. No. Type of Ownership Household Permanent Temporary Total

(in Ha) (in Ha) (in Ha)

1 Private Revenue 403 0.047 5.777 5.824

2 Government 0 0 0.737 0.737

Total 403 0.047 6.514 6.561

C. Loss of Private Land in Subproject

51. Most of the losses are of temporary nature so may require temporary land acquisition

and the impacted properties will have to be duly compensated as per the provisions of the

Pipeline Act of the State. The land of 403 affected households and 2347 APs will be affected

temporarily. The inventory of losses of the land and other assets for each affected household

has been prepared based on the losses to be incurred to them due to construction of the

distribution pipeline in this subproject. The total land of 6.561 ha area to be impacted and its

utilization has been indicated in the following Table No.5.

Table 5: Details of Affected Persons in the Subproject

Sl. No. Type of Impacts Affected Households Affected Persons

1 Temporary Use 403 2347

Total 403 2347

Page 21: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

18

D. Loss of Structures in the Subproject

52. There is no loss of any shelters or any permanent structures in the impacted area. There

is no impact on any other commercial land or Community Property Resources (CPR) also which

is being utilized by the local population of the affected area.

E. Loss of other Assets in the Subproject

53. Among other impacts, there are 3 Fruit bearing trees and 1 Timber Tree and some parts

of Orange Orchards trees, which have been divided in three categories. These trees will also be

permanently impacted under this subproject. These impacts are due to laying of distribution

pipeline in the impacted area. However, the impacts will be permanent for which due

compensation will be paid for the loss incurred to them. The cash compensation will be paid for

all these losses for which the inventory of the losses has been prepared based on the physical

census survey of the area.

F. Loss of Livelihood in the Subproject

54. The properties of 403 DHs are being impacted temporarily for laying of underground

distribution pipeline. After construction work is over, they get their land back in its prior

condition. Besides this, as per the provisions of Pipeline Act of GOMP for temporary acquisition

of land, they will get double crop compensation and 15% of the cost of the impacted land based

on the prevailing cost of the land as per Collector’s Guideline of the land in that area. No

physical displacement will occur of these DPs because their houses are not impacted.The

amount of compensation will give them an opportunity to develop their other properties and to

start any small scale work for income generation. Besides this, the proposed project will give

them assured irrigation benefits enabling them to have at least two crops in a year for their

economic upliftment and better standard of living.There is no significant impact on the properties

and livelihood of 403 DHs so there is no need to arrange any Skill up-gradation training for this

category of DHs. Even then, they can be encouraged to take the benefits of the ongoing skill up-

gradation training programs conducted by the State Government and GOI.

G. Significance of Impact on Land Owners

55. The analysis of significance of impact on the properties of AH’s indicates that out of total 403 affected households and 2347 affected persons, the peroperties of all 403 households are

being impated less than 10% which has been presented in the following Table No.-6.

Table 6 : Significance of Land Impact S.No. Scale of Impact Household Persons %HH

1. Insignificant Impact on the

properties of Temporary 403 AHs

which is less than 10% Impact

403

2347

100.00

Total 403 2347 100.00

Page 22: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

19

56. The analysis of the above Table no. 6 itself indicates that there is insignificant impact,

which is less than 10% on the properties of all 403 affected households so the amount of

compensation due to the AHs is also not much. Therefore’ there is lack of interest in taking that meager amount of compensation by AH, due to the hassles of lengthy formalities of the

Government. Secondly, there may be more than 3-5 shareholders in the family for that little

amount of Compensation which includes their married sisters too. The whole procedure of

getting that amount of compensation may cost more than the amount of compensation they may

get, so the AHs don’t find it feasible to take much pains for such little amount of compensation.

In such type of cases it was decided that, the AH, if wants to forego the amount of

compensation has to sign a Memorandum of Understanding (MOU) to be documented, to

forego that amount of compensation. But before signing of the MOU by the AH, the amount of

compensation due to the AH will be informed to the respective family for them to take a rationale

decision in the matter. The Format of the MOU is at Annexure 14.

Page 23: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

20

IV. SOCIO-ECONOMIC INFORMATION AND PROFILE

A. Census Socioeconomic Survey

57. The Census field survey enumerated all private assets / properties and common

property resources within the proposed alignment of the distribution pipeline in 12 villages

located in Nlakheda Tehsil of District Agar Malwa. For every Affected Household (AH), a pre-

tested structured questionnaire was administered during the socio-economic survey and

inventory of losses. The conducted survey recorded details of (i) identification of the Displaced

Households (DH); (ii) type, use and extent of losses of the AHs; and (iii) enumerating their

losses based on their entitlement matrix

58. In addition to recording the above information, detailed socio-economic characteristics,

including a demographic profile of members of the household, standard of living, inventory of

physical assets, vulnerability characteristics, indebtedness level, health and sanitation, and

ascertaining perceptions about project, resettlement options and compensation, was collected

from all Project Affected 403 households living in 12 villages of Nalkheda comprising a

population of 2347 Affected Persons in Tehsil Nalkheda. Details of Common Property

Resources (CPR) within the alignment were also recorded.

59. The DPs are categorized in two categories that is either temporary or permanent impact

on their properties. Out of 403 affected households, all 403 households will be temporarily

affected.The impact of loss of properties of 403 households is mainly of temporary nature which

is being acquired temporarily mainly for distribution pipeline alignment.

B. Demographic Profile of DPs

1. Sex Ratio amongst the DPs

60. In this subproject the pipeline is passing through the properties of 403 affected

households having 2347 affected persons. Therefore amongst all 403 surveyed affected

households there is 52.96% of male population and 47.04% of female population. Out of all 403

surveyed households, the males in 402 AHs are heading the family and there is only one

women headed household in these 12 affected surveyed Villages of Nalkheda Tehsil of District

Agar Malwa.

Table 7 : All Displaced Persons by Sex

Name of village Male Female Total Percentage

Bhaisoda 99 103 202 8.61

Deharigujar 34 33 67 2.85

Dharola 350 299 649 27.65

Dokapura 69 57 126 5.37

Gudrawan 120 122 242 10.31

Molyakhedi 29 25 54 2.30

Page 24: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

21

Najarkheda 114 96 210 8.95

Nalkheda 60 54 114 4.86

Padana 148 133 281 11.97

Pheti 75 64 139 5.92

Pilwas 88 66 154 6.56

Semali 57 52 109 4.64

Total 1243 1104 2347 100.00 Percentage 52.96 47.04 100.00

2. Household by Religion

61. 403 Affected Households were also surveyed based on religion and the data analysis

indicates that there are 364 Hindu AHs comprising 90.32% of the surveyed population. There

are 27 AHs comprising 6.70% of Surveyed Households follow Muslim faith. There are 12 AHs

following Jainism. No Christian families found living in these 12 affected villages.

Table 8 : Displaced Household by Religion

Name of village Hindu Muslims Jain Total Percentage

Bhaisoda 34 0 2 36 8.93

Deharigujar 12 0 0 12 2.98

Dharola 117 0 0 117 29.03

Dokapura 10 6 1 17 4.22

Gudrawan 43 0 0 43 10.67

Molyakhedi 4 7 0 11 2.73

Najarkheda 19 5 0 24 5.96

Nalkheda 10 7 2 19 4.71

Padana 52 0 0 52 12.90

Pheti 16 2 7 25 6.20

Pilwas 27 0 0 27 6.70

Semali 20 0 0 20 4.96

Total 364 27 12 403 100.00 Percentage 90.32 6.70 2.98 100.00

3. Household by Social Group

62. The Social Category of the AHs was also judged by the socio-economic survey, which

indicates that there is majority of Other Backward Caste and General Caste population

comprising 70.72 % and 14.14% respectively of the total population in these 12 villages. The

Scheduled Caste representation is of 13.15 % and only 1.99% are belonging to ST Community

amongst these 403 affected households.

Page 25: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

22

Table 9 : Displaced Household by Social Category

Name of village SC ST OBC General Total Percentage

Bhaisoda 1 0 32 3 36 8.93

Deharigujar 2 0 10 0 12 2.98

Dharola 34 0 74 9 117 29.03

Dokapura 0 0 12 5 17 4.22

Gudrawan 1 0 41 1 43 10.67

Molyakhedi 0 0 11 0 11 2.73

Najarkheda 5 0 10 9 24 5.96

Nalkheda 0 0 17 2 19 4.71

Padana 4 4 44 0 52 12.90

Pheti 1 4 9 11 25 6.20

Pilwas 5 0 6 16 27 6.70

Semali 0 0 19 1 20 4.96

Total 53 8 285 57 403 100.00 Percentage 13.15 1.99 70.72 14.14 100.00

4. Household by Size of Family

63. Family of size 1-5 members account for 55.83% followed by 24.07% having 6-7

members in the family. There is 10.67% of families having more than 8 or 9 Members and

9.43% families are having more than 10 Members in the family. Therefore common size of the

family is of 1-5 Members.

Table 10 : Family Size of the Household Name of village 1 to 5

Members 6 or 7

Members 8 or 9

Members Above 10 Members

Total Percentage

Bhaisoda 23 6 3 4 36 8.93

Deharigujar 6 5 0 1 12 2.98

Dharola 67 30 13 7 117 29.03

Dokapura 6 3 4 4 17 4.22

Gudrawan 24 10 6 3 43 10.67

Molyakhedi 7 4 0 0 11 2.73

Najarkheda 6 6 5 7 24 5.96

Nalkheda 9 6 2 2 19 4.71

Padana 32 13 2 5 52 12.90

Pheti 17 5 3 0 25 6.20

Pilwas 15 5 3 4 27 6.70

Semali 13 4 2 1 20 4.96

Total 225 97 43 38 403 100.00 Percentage 55.83 24.07 10.67 9.43 100.00

Page 26: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

23

5. Age Group of DPs

64. 28.67% of DPs are in the age group of 21 years and below followed by 29.87% coming

under the age group of 22-35 years, followed by 22.67% coming under the age group of 36-50

years, 13.93% belonging to age group of 51-65 years of age and only 4.86 % of APs are more

than 65 years of age. The analysis indicates that the life expectancy in these affected villages is

still not very high due to lack of awareness regarding good health.

Table 11 : Age Group of DPs

Name of village Upto 21

Years

22 to 35

Years

36 to 50

Years

51 to 65

Years

Above 65

Years

Total Percentage

Bhaisoda 58 57 42 37 8 202 8.61

Deharigujar 29 14 11 8 5 67 2.85

Dharola 192 187 159 75 36 649 27.65

Dokapura 27 38 37 22 2 126 5.37

Gudrawan 65 84 48 33 12 242 10.31

Molyakhedi 18 14 14 5 3 54 2.30

Najarkheda 84 65 30 22 9 210 8.95

Nalkheda 24 43 17 20 10 114 4.86

Padana 68 88 69 46 10 281 11.97

Pheti 33 39 32 30 5 139 5.92

Pilwas 43 42 44 13 12 154 6.56

Semali 32 30 29 16 2 109 4.64

Total 673 701 532 327 114 2347 100.00 Percentage 28.67 29.87 22.67 13.93 4.86 100.00

C. Socio-economic Profile

1. Educational level of DPs

65. The data analysis of educational level indicates that 44.35% of APs are still not

educated, followed by 14.10% who are only primary school passed, followed by 14.96% who

are 6th to 8th Class passed, 14.83% are 9th to Class 12th passed. There are 8.86% APs who are

graduates followed by 2.90 %who are post graduates and none are Diploma Holders.

Table 12 : Educational level of DPs

Name of village

Upto 5th

6th - 8th

9th - 12th

Graduate

Post Graduat

e

Illiterate

Total Percentage

Bhaisoda 39 36 37 20 2 68 202 8.61

Page 27: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

24

Deharigujar 8 5 2 1 0 51 67 2.85

Dharola 88 110 81 61 17 292 649 27.65

Dokapura 20 17 22 12 17 38 126 5.37

Gudrawan 29 48 30 29 2 104 242 10.31

Molyakhedi 11 8 13 2 2 18 54 2.30

Najarkheda 44 22 20 16 1 107 210 8.95

Nalkheda 22 18 35 6 6 27 114 4.86

Padana 18 36 22 3 1 201 281 11.97

Pheti 15 16 31 27 15 35 139 5.92

Pilwas 21 25 33 20 4 51 154 6.56

Semali 16 10 22 11 1 49 109 4.64

Total 331 351 348 208 68 1041 2347 100.00 Percentage 14.1

0 14.96 14.83 8.86 2.90 44.35 100.0

0

2. Occupation of DPs

66. The occupation of DP’s indicates that 22.11% are cultivators followed by 6.43% who are

agricultural laborers, 68.98% are not in any work force. 0.81% are in Government Jobs, 0.98%

are in Private Jobs and only 0.68 % are Shopkeepers. Therefore majority of population belongs

to agricultural sector either as land owner / cultivator or as agriculture laborers.

Table 13 : Occupation of DPs

Name of village

Cultivators Agricultural Laborer

Govt. Job

Private Job

Shop-keeper

Not in Workforce

Total Percentage

Bhaisoda 37 12 1 1 2 149 202 8.61

Deharigujar 15 3 0 2 0 47 67 2.85

Dharola 148 44 7 10 0 440 649 27.65

Dokapura 28 5 0 0 3 90 126 5.37

Gudrawan 72 5 3 0 0 162 242 10.31

Molyakhedi 11 4 2 0 0 37 54 2.30

Najarkheda 24 28 0 4 0 154 210 8.95

Nalkheda 21 9 2 1 2 79 114 4.86

Padana 90 12 0 3 0 176 281 11.97

Pheti 25 6 1 0 6 101 139 5.92

Pilwas 28 18 2 0 3 103 154 6.56

Semali 20 5 1 2 0 81 109 4.64

Total 519 151 19 23 16 1619 2347 100.00 Percentage 22.11 6.43 0.81 0.98 0.68 68.98 100.00

Page 28: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

25

3. Income of Household

67. Household income of 53.35% affected population is up to Rupees Rs10,000 per month

followed by 33.50% having income of Rs 10,001 to 20,000 per month. 7.44% affected

population having monthly income as Rs 20,001 to 25,000 per month followed by 5.71% having

monthly income more than Rs. 25,000 per month.The Villagers being either illetrate or less

educated are not able to give their exact monthly income but even then they are economically in

a better condition than the AHs of Right Bank due to better yield and cost of the crops sown..

Table 14 : Monthly Household Income of DHs

Name of village

Upto 10000

10001 to 20000

20001 to 25000

Above 25000

Total Percentage

Bhaisoda 21 13 2 0 36 8.93

Deharigujar 5 6 1 0 12 2.98

Dharola 66 36 9 6 117 29.03

Dokapura 7 3 3 4 17 4.22

Gudrawan 24 14 1 4 43 10.67

Molyakhedi 9 1 1 0 11 2.73

Najarkheda 14 7 2 1 24 5.96

Nalkheda 12 5 1 1 19 4.71

Padana 30 20 0 2 52 12.90

Pheti 12 8 2 3 25 6.20

Pilwas 12 9 5 1 27 6.70

Semali 3 13 3 1 20 4.96

Total 215 135 30 23 403 100.00 Percentage 53.35 33.50 7.44 5.71 100.00

4. Impact to Vulnerable Households (mutually exclusive)

68. The vulnerable population was also assessed amongst 403 DHs. The weakest section

representing 15.14% is Below Poverty Line (BPL), there is only 1 women headed household

having represention of 0.25% found living amongst these 403 surveyed households. There is

near about 13.15% of SC population and 1.99% of Scheduled Tribe population was found

amongst these 403 AHs. The vulnerable status of AHs in the Project, which is mutually

exclusive in the order of priority as presented in the following table is given below:

Table 15 : Vulnerable (mutually exclusive)

Name of village

Women HH

BPL ST SC Not Applicable

Total Percentage

Bhaisoda 0 5 0 1 30 36 8.93

Deharigujar 0 3 0 2 7 12 2.98

Dharola 0 14 0 34 69 117 29.03

Page 29: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

26

Dokapura 0 3 0 0 14 17 4.22

Gudrawan 0 4 0 1 38 43 10.67

Molyakhedi 0 7 0 0 4 11 2.73

Najarkheda 0 8 0 5 11 24 5.96

Nalkheda 1 5 0 0 13 19 4.71

Padana 0 2 4 4 42 52 12.90

Pheti 0 2 4 1 18 25 6.20

Pilwas 0 5 0 5 17 27 6.70

Semali 0 3 0 0 17 20 4.96

Total 1 61 8 53 280 403 100.00 Percentage 0.25 15.14 1.99 13.15 69.48 100.00

D. Key Socio-economic Indicators

69. The key socio-economic indicators established, based on the socio-economic survey

carried out in the months of March and April’ 2019 presented in the following table.The data

analysis of the socio-economic indicators represents that average monthly income of the family

in Bhaisoda Village is Rs. 9872 with 2 earners, Deharigurjar Village it is Rs. 11180 per month

with 2 earners, in Dharola Village it is Rs 12079 per month with 3 earners, in Dokapura it is Rs.

18210 with 3 earners, in Gudrawan it is 12746 with 2 earners, in Molyakhedi it is Rs.8825 with 2

earners, in Najarkheda it is Rs. 9496 with 2 earners, in Nalkheda it is Rs. 9846 with 2 earners, in

Padana it is Rs.11878 with 3 earners, in Pheti it is Rs.12950 with 3 earners, in Pilwas it is

Rs.12530 with 3 earners and in Semali it is Rs. 17708 with 3 earners.

70. In Village Bhaisoda 14 households are having separate kitchens, 35 AHs are having

Separate Toilet, 36 have separate bath, 36 have electricity, 36 have drinking water facility, 36

households have LPG Cooking Connection and no Women headed household in this Village. In

Village Deharigurjar no households have separate kitchen, 7 households have separate toilet,

12 have separate bath, 12 AHs have electricity and drinking water facility and 10 LPG Gas

Connections. In Village Dharola 46 households are having separate kitchen, 89 are having

separate toilet, 113 are having separate bath, 127 are having electricity, 117 have drinking

water facility and 112 households have LPG Connection with no Women headed household.

71. 11 households in Village Dokapura are having separate Kitchen, 17 of them have

separate toilets, 17 of them have separate bath, 17 have electricity, 17 of them have Drinking

water facility, 17 have LPG connection and no women headed household in this Village. In

Village Gudrawan 10 households are having separate kitchen, 40 have separate toilet, 42 have

separate bath, 43 of them have Electricity and Drinking water facility,39 of them have LPG

connection with no women headed household in this village. In Molyakhedi Village 8 households

have separate Kitchen, 9 have separate toilets, 11 of them have separate Bath, electricity and

drinking water facility and 10 of them have LPG connection but no women headed family was

found amongst these surveyed families. In Najarkheda surveyed village, there is 1 separate

Kitchen, 19 separate Toilet, 24 of them have separate bath, electricity and drinking water facility

Page 30: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

27

and 21 have LPG connection with no women headed household. In Village Nalkheda 9 have

separate kitchen, 19 have separate toilet, 19 have separate bath, 19 of them have electricity

and drinking water facility, 19 have LPG connection and 1 women headed household. In Village

Padana there are 3 separate Kitchen, 45 separate toilet and 50 separate bath, 52 of them have

electricity and drinking water facility, 39 of them have LPG connection. In Village Pheti, there

are 13 separate Kitchen, 24 separate toilet, 25 separate bath, 25 of them have electricity and

drinking water facility, 24 have LPG connection.

72. In Pilwas Village, there are 7 separate kitchen, 24 separate Toilet, 27 separate bath and

27 have the facility of electricity, drinking water and LPG connection. In Village Semali, there are

3 separate kitchen, 20 separate toilet, bath, electricity, drinking water facility and LPG

connection. The analysis of the data indicates that there is awareness about having separate

kitchens, separate toilets and separate bath in their houses. They have electricity and drinking

water facility. 374 households have LPG Cooking Medium in their house, which is making their

life much easier than before. This habit of cooking on LPG is helping in the conseravtion of our

valuable forest though there is not much wood available in the area due to scarcity of water in

these 12 impacted and other adjoining villages of this area.

Table 16 : Key Socio-economic Indicators

Name of village

Monthly

Family Income

Number of

Earners

Permanent

Having Sepa rate

Kitchen

Having Sepa rate

Toilet

Having Sepa rate Bath

Having Electri

city

DrinkingWater HSC

LPG for

Cooking

Family Size

WomenHHs

Total

Bhaisoda 9872 2 1 14 35 36 36 36 36 5.61 0 10073.6

Deharigujar 11180 2 1 0 7 12 12 12 10 5.58 0 11241.6

Dharola 12079 3 1 46 89 113 127 117 112 5.55 0 12692.5

Dokapura 18210 3 1 11 17 17 17 17 17 7.41 0 18317.4

Gudrawan 12746 2 1 10 40 42 43 43 39 5.63 0 12971.6

Molyakhedi 8825 2 1 8 9 11 11 11 10 4.91 0 8892.91

Najarkheda 9496 2 1 1 19 24 24 24 21 8.75 0 9620.75

Nalkheda 9846 2 1 9 19 19 19 19 19 6.00 1 9960

Padana 11878 3 1 3 45 50 52 52 39 5.40 0 12128.4

Pheti 12950 3 1 13 24 25 25 25 24 5.56 0 13095.6

Pilwas 12530 3 1 7 24 27 27 27 27 5.70 0 12678.7

Semali 17708 3 1 3 20 20 20 20 20 5.45 0 17820.5

Total 147320 30 12 125 348 396 413 403 374 71.56 1 149494

Page 31: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

28

V. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION

A. Public Consultations

73. In order to engage with the community and enhance public understanding about the

Project and address the concerns and issues pertaining to compensation, rehabilitation and

resettlement, individual interviews and meetings were undertaken amongst the various sections

ofstakeholders and people’s representative. The consultations with the APs and other

stakeholders will continue throughout the LARP preparation and its implementation period.

B. Methods of Consultation

74. Consultations and discussions were held during socio-economic survey period with both

primary and secondary stakeholders. The primary stakeholders include Project AHs / APs,

project beneficiaries and implementing agency (MPWRD). The secondary stakeholder includes

revenue officers and elected representatives of the local bodies.

75. During the socio-economic survey, Direct Consultations were held with the AHs, APs,

Officials of District Administration, Officials of PIU (MPWRD) and Elected Members of the Local

Panchayats. The elected representatives of local bodies were also consulted regarding the

perception of the Project.

Table 17: Consultation Methods

Stakeholders

Consultation Methods

Affected Persons / Affected Households

Direct and Group Consultations

Local Communities

Group Consultations

Local Elected Members

Individual interview, discussions

Concerned Officials from Government

Individual meeting /interviews, discussions

Stake Holders and General Public

Consultation Meetings

Page 32: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

29

76. In addition to the web disclosure of the draft LARP, detailed consultations regarding the

extent of IR impact if any and the mitigation measures proposed in the draft LARP will be

disclosed to the APs and general public through public meetings held along the project. The

LARP disclosure meetings will be held to explain the contents and provisions of the Draft LARP

and obtain the feedback, suggestions and objections, if any, on the draft LARP and accordingly

make suitable amendments/corrections before finalizing the LARP.

77. All relevant aspects of project design, details of impact to private properties were

discussed with local communities in11 Villages of Tehsil Nalkheda on 13th November’2018, 14th

April to 16th April’ 2019 and from 24th and 26th June’2019. A total of 402 persons (69 females

and 333 males) participated in the consultations in these 11 Villages.The date, venue, number

of participants village wise and the photographs are provided below. The issues and concerns

raised during the consultations are summarized and provided in the following table:

Table 18: Consultation Locations

Location of villages

Nalkheda Tehsil, District Agar Malwa

Date Number of

Male

Participants

Number of

Female

Participants

Molyakhedi, Teh. Nalkheda, Distt. Agar Malwa 13.11.2018 67 13

Dehari Gurjar, Teh.Nalkheda, Distt.Agar Malwa 13.11.2018 26 0

Dharola, Teh. Nalkheda, Distt. Agar Malwa 14.04.2019 35 8

Dokapura, Teh. Nalkheda, Distt. Agar Malwa 14.04.2019 30 9

Gudrawan, Teh. Nalkheda, District Agar Malwa 15.04.2019 25 7

Pilwas, Teh. Nalkheda, District Agar Malwa 15.04.2019 29 4

Padana, Teh. Nalkheda, Distt. Agar Malwa 16.04.2019 38 7

Bhaisoda, Teh. Nalkheda, Distt. Agar Malwa 24.06.2019 24 8

Nalkheda, Teh. Nalkheda, Distt. Agar Malwa 25.06.2019 21 7

Semali, Teh. Nalkheda, Distt. Agar Malwa 25.06.2019 18 6

Najarkheda, Teh. Nalkheda, Distt. Agar Malwa 26.06.2019 20 0

Total 11 Villages Male 333+Female 69 = 402 -- 333 69

Page 33: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

30

Consultations with Villagers and People’s Representative

C. Outcome of the Consultations

78. The consultations were held with the Affected Households, Affected Persons, General

Public and the People’s Representatives in 11 Villages to provide information about the

proposed Project activities and expected impacts of the project and their concerns about the

upcoming project. Other key stakeholders include representatives of Government Entities

involved in the planning, design, implementation and operation of the Project, which includes

PIU (MPWRD) and Revenue Department of Government of Madhya Pradesh.

79. During Consultations the Officials of PIU and Engineers of L&T Constructions explained

them the technical aspects of the Project and Resettlement Specialist discussed with them, their

entitlements matrix as per the applicable policies of the State, RFCTLARRA’ 2013 and SPS 2009 of Asian Development Bank (ADB).The affected population was informed about the

inventory of their 100% losses being taken into account by the Census and Socio-economic

survey team. Therefore the affected population was requested that they should give full co-

operation in giving all the details of their properties and their family to the survey team so that

their rights and privileges can be taken care of as per their entitlement matrix.

80. Affected families and General Public of Village Molyakhedi were gathered in large

number in the leadership of their, the then Legislator Murlidhar Patidar and informed that they

are already taking two crops of Wheat, Soyabean, Gram and other pulses.in a year by lift

Page 34: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

31

irrigation from Lakhundar River. For this lift irrigation they have laid their personal pipes from

River Lakhundar to their agricultural fields. They wanted an assurance from the Company that

their pipeline should not be damaged while digging of the pipeline of the project. They also

demanded that after digging the trench for Laying of the pipeline it should be filled properly in

which the stone should go below and soil should come on top so that the impacted piece of land

becomes cultivable again. The AHs were assured that their demands will be taken care of by

the Company at the time of Laying of the pipeline. This Village has its own importance because

it is impacted at the time of Laying of the rising main as well as during the alignment of other

distribution pipelines. The residents of this Village have lots of Orange Orchards and they have

very good yield from these Orchards so they wanted that their Orange Orchards should be

saved and if they need to be impacted then they should get enough compensation. The people

were informed that they will get compensation of their impacted trees whether they are fruit

bearing trees or other type of tres. The Villagers are very well aware of the benefits of the

project as well as about their rights and priveleges.

81. There are near about 100 houses in the Village Dehari Gurjar. There is majority of Gurjar

population that’s why the Village is called Dehari Gurjar.They also informed that there is a Stop

Dam at Village Lakhundar so take the benefit of lift irrigation by their own pipeline system. The

Kundalia Dam constructed on Kalisindh River is also only 2 Km away from the Village. There is

only one Primary School in the Village and teachers come from outside and teach.These

Villagers are also keen that their personal pipeline should be saved at the time of construction

activities. Because the project benefits will be accrued permanently after 3 years so till then their

source of irrigation should be taken care of. The company assured to take care of the situation.

82. In Dharola Village there will be alignment of distribution pipeline causing temporary

impact on their properties. The AHs said that in Orange Orchards, if the trees come in the

alignment of the pipeline then they will be cut causing permanent loss to them. The Villagers

said that they plant the orange trees at a width of 16 feet in between two rows of the orange

trees. Therefore due efforts should be made that the alignment of the pipeline should be in such

a way that it should not damage their trees because there is enough space in between the two

rows of the trees. The crops grown in the area are Wheat, Soyabean, Masoor and Chana

Pulses as well as Onions as a cash crop. People’s representatives were also involved in public consultations and their perception about the proposed project was taken at length. The Group

Consultation was conducted in Dharola Village in which elders of the Village and other People’s Representative also took active part in the discussions.

83. The consultations were held in Village Gudrawan in which there is mixed population of

Patidars, Carpenters and Harijans. Devilal Harijan of the Village informed that Distribution

Pipeline is passing through this village. Padana Village is also affected in Zone 3 of this Project

in which there is Female Sarpanch Sugan Bai. Knahaiyalal Patidar informed that there is a

mixed population of OBC Sondhia Thakur, Patidars and some families of ST Bhil Thakur. The

Villagers of Dhokpura are very hopeful that upcoming irrigation project will bring manifold

benefits in their area. Consultations were held in Village Najarkheda in which there is alignment

of distribution pipeline causing only temporary impact for a period of 6 months on their

Page 35: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

32

properties. There are also many orange orchards in the area and people want that their orange

trees should not be cut and instead efforts should be made to save the fruit giving trees..

84. The Consultations were held with the people of Nalkheda in which 1 Women Headed

Household was found. There is near about 5500 population in Village Bhaisoda. Patidar

Community is in Majority and Beeram Malviya is the Sarpanch in this Village. There is a big

temple on the main road of the Village so people sit there and have religious and social talks

there.It is a source of recreation for them too.The people of the Villages were requested to give

full co-operation to the survey team for their proper socio economic survey and prepartion of

inventory of their losses which will be for their betterment in future. Since there is a positive

atmosphere regarding the project so people are willing to render their full co-operation at any

level of the project so that the benefits of the project are accrued to them at the earliest.

85. People were informed about their entitlement matrix during consultations and interviews

conducted in 11 affected villages. The interviews were conducted by the Resettlement

Specialist who made the affected population aware about the upcoming Kundalia Irrigation

Project and their entitlements as per the Pipeline Act of the State due to temporary acquisition

of their land. The local population is very well aware about the project and are more than willing

to render their 100% co-operation during implementation of the project as they know very well

about the forthcoming benefits of the project.

86. The community consultations indicated that local population had been suffering acute

shortage of water for drinking and irrigation purposes. Due to shortage of irrigation facilities,

they are not able to take two crops in a year and the crop yields are also not up to their

expectations. These factors have been the root cause of their low standard of living. The

upcoming Project will open new horizons for them when they will be able to take two good yield

crops every year. The proposed Project will not only improve the standard of living of the APs

but it will be a source of bringing over all development of the population living in the adjoining

areas also.

87. Consultations and participation with primary stakeholders will further be held in future to

ensure their understanding about the potential impacts of the Project on their livelihoods. To

understand the perception and attitude of the people about the Project, detailed interviews, and

group discussions have been developed and will be conducted by the Safeguard Resettlement

Specialist with stakeholders in future implementation of the Project. This will bring very fruitful

results when stakeholders will feel involved from the origination of the Project and even

throughout the implementing stage. They will consider themselves to be a part of the proposed

Project resulting into their 100% cooperation in its implementation. Their full-fledged cooperation

will enhance the speed of the implementation of the Project.

Page 36: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

33

Table 19 : Summary of the Consultation Outcome

Issues Discussions / Suggestion Mitigation Measures Proposed

Prior Notice regarding construction work to be given to the Affected Population

The AP’s should be given prior notice before taking up the Construction Work of the Subproject.

APs will be given prior information at least 60 days before starting the construction work. Due precautions will be taken so that no harm is caused to the affected and the local population residing in the area..

Benefits should be extended to the affected population as per their entitlement.

Planning should be made in such a manner so that the Local population should be benefited by the Project.

It will be ensured that the affected population is given priority in extending the benefits of the proposed project as per their entitlement matrix.

Local Labor should be given preference in the construction work.

The local labor should be engaged / employed in the Project related activities.

It will be ensured that the affected population is given preference in hiring of casual labor for construction work undertaken by the Contractor.

Home privacy, routine activities and safety of Women should be taken care of.

Home privacy, routine activities, safety and security of women should not be disturbed due to construction of the project.

Due measures will be taken to ensure that the privacy of women and girls should not be disturbed due to the construction of the Project. The Company will take due precautions in this regard.

Though their lands will be temporarily acquired for the project work but prior information should be given to them before taking possession of the said land.

Despite the temporary impacts on their properties, prior information should be given before commencement of the work so that DPs can harvest their crops before being damaged.

The APs will be informed at least 60 days before taking up the construction work in the agriculture fields so that they can harvest their crops if they are reaped. They will be given all the information regarding the impacts and benefits of the proposed project.

Construction work should be undertaken with due precautions to save their personal pipelines of lifting water for irrigation purposes till the completion of KIP.

In some of the Villages the villagers have their personal pipelines which they have been using for lift irrigation purposes which should not be damaged when the distribution pipelines of KIP will be laid.

The Villagers were assured that due care will be taken during construction activities so that their personal pipelines of lift irrigation are not being damaged.

Due care should be taken while filling up the trenches after laying of the pipeline

Villagers suggested that while filling up the trenches, the stones should go deep inside and soil comes on top so that the impacted strip of land becomes cultivable again.

The Villagers were assured that while refilling of the dug trenches, due care will be taken that the stone will be put in the down layer and soil is filled in the upper layer enabling the strip of the impacted land cultivable again.

Construction work should be undertaken with due precautions to save their pipelines of lift irrigation till the completion of KIP

In some of the Villages the villagers have their personal pipelines which they have been using for lift irrigation purposes which should not be damaged when the distribution pipelines of KIP will be laid.

The Villagers were assured that due care will be taken during construction activities so that their personal pipelines of lifting the water for irrigation purposes are not being damaged.

Page 37: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

34

D. Conclusions of the Group Consultations

88. From both direct and group consultations, it is noted that people are well aware about

the upcoming Project as various surveys have been going on and the news is spread by word of

mouth from each other. Despite this they were not aware of the extent of manifold benefits

proposed and the likely impacts of the Project on the local population. In this Project there is

mainly temporary impact on their properties and when the construction activities are over their

land will be brought back to its pre project condition. Therefore the stakeholders are well aware

of the fact that they will have some teething problems in the transition phase which is nothing in

comparison to the benefits they will get from the Project. There is no resistance found amongst

the affected population and the general public regarding the implementation of the Project

instead there is great acceptance of the upcoming project.

89. The Consultations held with stakeholders in three phases indicate that the stake holders

are very supportive about the Project and are more than willing to undergo the impact on their

properties for long-term benefits to be accrued by them through the KIP. The local population is

very well aware of the benefits of the proposed project and are willing to render their 100%

cooperation in the implementation of the project.

E. Plan for further Consultation in the Project

90. The effectiveness of the R&R program is directly related to the degree of continuing

involvement of those affected by the Subproject. Several additional rounds of consultations with

APs will form part of the further stages of subproject preparation and implementation. The

implementing Resettlement Specialist will be entrusted with the task of conducting these

consultations during LARP implementation, which will involve disclosure on compensation,

assistance options, and entitlement package and income restoration measures suggested for

the subproject. The consultation will continue throughout the subproject implementation period.

The following set of activities will be undertaken for effective implementation of the LARP:

(a) In case of any change in engineering alignment planning the APs and other stakeholders will be consulted in selection of pipe alignment for minimization of resettlement impacts, development of mitigation measures etc.

(b) Together with the Resettlement Specialist, the PIU will conduct information dissemination sessions in the subproject area and solicit the help of the local community/ leaders and encourage the participation of the AP’s in Plan implementation.

(c) During the implementation of LARP, Resettlement Specialist will organize public meetings, and will appraise the communities about the progress in the implementation of subproject works, including awareness regarding pipeline laying as per the proposed alignment and other construction works.

(d) Consultation and focus group discussions will be conducted with the vulnerable groups like Women, OBC, SC and ST population to ensure that the vulnerable groups understand the process and their needs are specifically taken into consideration.

(e) To make reasonable representation of Women in the subproject planning and implementation they will be specifically involved in consultation process.

Page 38: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

35

91. A Public Consultation and Disclosure Plan will be prepared by the PIU / Resettlement

Specialist for the smooth and speedy implementation of the Subproject in the following format

as mentioned below:

Table 20: Format for Public Consultation and Disclosure Plan

Proposed Activity

Task Assigned Responsible

Agencies

Public Notification

Notify eligibility cut-off date for Major Sons

PIU

Disclosure of LAP Translate LAP in Hindi and disclose at PIU Office and Village Council

PIU

Distribution of R&R information leaflet

Prepare R&R information leaflet and distribute to Aps

PIU

Internet disclosure of the LAP / RP

Post LAP / RP on ADB and / or EA website

ADB/PIU

Consultative meetings during joint measurement survey

Face to face meetings with APs

PIU

Disclosure of updated LAP / RP

Disclosure after joint measurement survey

PIU

Internet disclosure of the updated LAP

Updated LAP posted on ADB and/or EA website

ADB/PIU

F. Information Disclosure

92. The EA will provide relevant LARP information, including information from the above

mentioned documents in a timely manner, in accessible places such as PIU Office and

Panchayat / Village Gram Sabha translated in local language, if necessary.

93. LARP information will be disseminated to APs at various Stages. Information including

magnitude of loss, detailed asset valuations, entitlements and special provisions, grievance

procedures, timing of payments, displacement schedule, Civil works schedule will be disclosed

during LARP implementation.

Page 39: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

36

VI. GRIEVANCE REDRESS MECHANISMS (GRM)

94. There will be 403 households and 2347 persons to be affected due to this Subproject so

looking into the present and future needs of proper resettlement of the affected population of the

upcoming Irrigation Project as a whole, a GRM is proposed to be established to provide

avenues for AHs / APs to submit grievances that may arise from time to time. A two-tier GRM

for the Project is proposed which has been outlined as below:-.

95. The first tier Grievance Redressal Cell (GRC) at Project, PIU/PMU level will comprise of:

i. Sub Divisional Magistrate (SDM), Revenue Department as Chairperson ii. Executive Engineer (EE), PMU Level (WRD) as Secretary of GRC iii. R&R Officer, PMU Level (WRD) of GRC iv. A representative from local NGOs or a local person of repute and standing in

the Society or an Elected Representative from the locality. v. A representative from Displaced Persons.

96. The second tier GRC at District level will comprise of:

i. Project Director, PMU, WRD as Chairperson ii. Executive Engineer,(WRD) as Secretary of GRC at PIU Level iii. R&R Officer at PIU Level, (WRD) of GRC iv. A representative from local NGOs or a local person of repute and standing in

the Society or an Elected Representative/ Zila Parishad Member.

97. The GRC at PIU level will meet once every month during the implementation of RP, but

if necessary more meetings will be called for as required to resolve a complaint. The Assistant

Manager, PMU of project will act as the secretariat of GRC, and will keep records of all

complaints, such as: date of receiving complaint; meetings to resolve the complaint; action

taken and date of communication sent to complainant. The contractor’s site office and PIU office will display notices indicating whom to contact if anybody has any grievance. The APs will be

informed that they could submit grievances either to PIU office or to GRC secretary, or the

representative of APs. The GRC meeting will be at least convened once in a month, or as much

as needed when grievances need to be resolved. The complaint/grievance will be redressed in

one month’s time, and written communication will be sent to the complainant. The PIU will

continually coordinate with the secretary of GRC to record a complaint registered by GRC with

details of complaints lodged, date of personal hearing, action taken, and date of communication

sent to the complainant.

98. For the second tier GRC at District level, the EE will act as the secretary of GRC. The

second tier will focus on finding resolutions for the complainants, and with time frame not more

than 4 weeks. The second tier GRC is also expected to resolve a grievance that could not be

resolved by the first tier GRC. This GRM is not substitute or part of the Land Acquisition

Rehabilitation and Resettlement (LARR) authority; the complainants are free to approach the

jurisdictional LARR Authority to have their grievance resolved. The complainant can access the

Page 40: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

37

appropriate Land Acquisition Rehabilitation and Resettlement (LARR) Authority at any time and

not necessarily go through the GRC.

99. Other than disputes relating to ownership rights and apportionment issues on which the

LARR Authority has jurisdiction, the GRC will review grievances involving all resettlement

benefits, relocation and payment of assistances. The GRM should be in place at the time when

disclosure of the RP is initiated by WRD and should continue throughout the project

implementation period.

100. The GRC will aim to provide a time-bound and transparent mechanism to voice and

resolve social, environmental, and project related concerns linked to the project. The GRC is not

intended to bypass the government’s inbuilt redressed process, nor the provisions of the statute,

but rather it is intended to address APs concerns and complaints promptly, making it readily

accessible to all segments of the APs, and is scaled to the risks and impacts of the Project.

Figure 2: An Overview of the Grievance Redress Mechanism

Complaints by individual DP, Groups, or institutions

Complaints by People’s representatives: political,

religious, community

Stage-1 GRC Meeting at Project/PIU level

(Complaints to GRC in written form

Stage-1 GRC Meeting at District Level

Decision of Stage 2 GRC – Convey the decision to Public / Chairman and other members of Step

1GRC

Decision to be taken within one month of receipt

of complaint

Decision to be taken within one month of receipt

of complaint

GRC process ends

Simple

Complex issues

2 Months

Page 41: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

38

VII. LEGAL FRAMEWORK

A. Introduction

101. The legal framework and principles adopted for addressing resettlement issues in the

subproject have been guided by the existing legislation and policies of the Government of India

(GOI), the Government of Madhya Pradesh, Asian Development Bank and the Resettlement

Framework (RF) adopted for the project. Prior to the preparation of the LARP, a detailed

analysis of the existing national and state policies was undertaken and a RF has been prepared

for the entire program. The section below provides details of the various national and state level

legislations studied and their applicability within this framework. This LARP is prepared based

on the review and analysis of all applicable legal and policy frameworks of the country and ADB

policy requirements. A summary of applicable acts and policies is presented in the following

paragraphs and the detailed policy analysis is provided in the RF.

B. Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act (RFCT in LARR), 2013

102. The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation

and Resettlement Act, 2013 (RFCT in LARR Act - 2013) has been effective from January 1,

2014 after receiving the assent of the President of Republic of India.

103. The aims and objectives of the Act include: (i) to ensure, in consultation with institutions

of local self-government and Gram Sabhas established under the constitution of India, a

humane, participative, informed and transparent process for land acquisition for industrialization,

development of essential infrastructural facilities and urbanization with the least disturbance to

the owners of the land and other affected families; (ii) provide just and fair compensation to the

affected families whose land has been acquired or proposed to be acquired or are affected by

such acquisition; (iii) make adequate provisions for such affected persons for their rehabilitation

and resettlement; (iv) ensure that the cumulative outcome of compulsory acquisition should be

that affected persons become partners in development leading to an improvement in their post-

acquisition social and economic status and for matters connected therewith or incidental

thereto.

104. Section 27 of the Act defines the method by which market value of the land shall be

computed under the proposed law. Schedule I outlines the proposed minimum compensation

based on a multiple of market value. Section 31 of the Act specifies rehabilitation and

resettlement award for the affected families and the entitlements are defined in the Schedule II

and III. Under Schedule II various R&R assistance like house construction allowance, land

development assistance, option for annuity and employment, subsistance grant, transport

allowance etc. are made and under Schedule III it specifies various infrastructural facilities and

basis minimum amenities to be provided at new resettlement site in case of project based

relocation.

Page 42: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

39

C. Legal and Policy Frameworks of Madhya Pradesh State:

1) “Madhya Pradesh Bhumigat Pipeline, Cable Avan Duct (Bhumi ki Upyokta

ke Adhikaron Ka Arjan) Adhiniyam, 2012 (No. 5 of 2013)” – (To be referred as The Madhya Pradesh Pipeline Act, 2013)

RULES

(a) Assessment of Compensation –

105. The competent authority shall decide the loss of crop income, compensation of trees and

other losses from the land mentioned therein for the period of laying of underground pipeline,

cable or duct, in the following manner :-

i. Any un irrigated land shall be considered as single cropped and irrigated

land shall be considered as double cropped. If no crops are taken in last

three years, the land shall be deemed as “fallow land” and the loss of crop income shall not be calculated for such land. In other cases, the loss

of crop income shall be calculated as follows :-

Calculation of crop income

= Standard

outcome of crop X

Minimum support price of crop

X 2

ii. In addition to the compensation as referred under rule (1), if any the

compensation shall be payable at the rate of fifteen percent of market

value of that land on the date of publication of the declaration under sub-

section (1) of section 4.

iii. If the laying of underground pipeline, cable or duct is not completed within

the stipulated period by the State Government or the Corporation, as the

case may be, it shall be liable to pay the loss for such additional period

which was taken beyond the stipulated period and also be liable for

additional payment at the rate of five percent of the market value of that

land.

Page 43: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

40

i. The Madhya Pradesh Government Order No. F 12-2 / 2014 / 07 / 2A Dated 12.11.2014 regarding the ‘Consent Land Purchase Policy’

106. For the development of the State, different infrastructures are being constructed for

which the private land has to be acquired. The process of Land Acquisition is not only time

taking but involves heavy financial cost also. To save this cost and time a consideration amount

in lieu of impacted private properties is offered to the owner of the land and other properties

attached to it. The main conditions of this Circular are as follows:-

i. This Policy is applicable only where there is a need to acquire Private Land for construction of permanent structures for the project.

ii. This Policy of Land Purchase is not only cost effective but saves lot of time in Land Acquisition procedure.

iii. A lump sum compensation / grant / consideration amount is being given to the affected household and his private properties are purchased by the Government with the mutual consent of the affected person or affected household.

iv. If land is required for any developmental purposes the District Collector is approached for making such type of land available to the concerned Department. If suitable Government land is available for the purpose then the same land shall be transferred to the concerned Department. If such type of suitable Government land is not available for the purpose then the procedure of purchase of private land with mutual consent is adopted.

D. ADB’s Safeguard Policy Statement (SPS), 2009

107. The objectives of ADB's SPS (2009) with regard to involuntary resettlement are: (i) to

avoid involuntary resettlement wherever possible; (ii) to minimize involuntary resettlement by

exploring project and design alternatives; (iii) to enhance, or at least restore, the livelihoods of

all displaced persons in real terms relative to pre-project levels; and (iv) to improve the

standards of living of the displaced poor and other vulnerable groups.

108. ADB's SPS (2009) covers physical displacement (relocation, loss of residential land, or

loss of shelter) and economic displacement (loss of land, assets, access to assets, income

sources, or means of livelihoods) as a result of; (i) involuntary acquisition of land, or (ii)

involuntary restrictions on land use or on access to legally designated parks and protected

areas. It covers displaced persons whether such losses and involuntary restrictions are full or

partial, permanent or temporary.

109. The three important elements of ADB’s SPS (2009) are: (i) compensation at replacement

cost for lost assets, livelihood, and income prior to displacement; (ii) assistance for relocation,

including provision of relocation sites with appropriate facilities and services; and (iii) assistance

for rehabilitation to enhance, or at least restore, the livelihoods of all displaced persons relative

to pre-project level standard of living.

Page 44: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

41

E. Comparison of Government and ADB Policies

110. The new act ‘The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013’, which has integrated provisions of National Rehabilitation and Resettlement Policy (2007) with that of The Land Acquisition Act (LAA) of

1894 (as amended in 1984), recognizes title holders and non-titleholders affected by land

acquisition. Whereby, squatters and encroachers are excluded from the purview of the act.

111. RFCT in LARR Act – 2013 has come into effect from January 1, 2014. This Act is both

complement the revision of the NRRP (2007) and decrease significantly the gaps between the

LAA and ADB's SPS, 2009. The Act also expands compensation coverage of the principal act

by requiring that the value of trees, plants, or standing crops damaged must also be included

and Solatium being 100% of all the amounts inclusive. The Act furthermore has match ADB

requirements for all compensation to be paid prior to project taking possession of any land.

112. Therefore, the RFCT in LARR Act – 2013 has established near equivalence of the

Government’s policies with those of ADB's SPS, 2009. Adoption of the below principles for the

project has ensured that both are covered in their application to this project. A comparison of

ADB and GOI policy and measures to fill the gaps is presented in the Table: 21.

Table 21: The Comparison of ADB and GOI Policy Aspect ADB Safeguard

Requirement Fair Compensation and Transference in Land

Acquisition, Rehabilitation and Resettlement Act, 2013

Measures to Bridge the

GAP

1 Screen the project

Screen the project to identify past, present, and future involuntary resettlement impacts and risks. Conduct survey and/or census of displaced persons, including a gender analysis, specifically related to resettlement

4 (I) it is obligatory for the appropriate Government intends to acquire land for a public purpose to carry out a Social Impact Assessment study in consultation with concerned Panchayat, Municipality or Municipal Corporation, as the case may be, at village level or ward level in the affected area. The Social Impact Assessment study report shall be made available to the public in the manner prescribed under section 6.

Screening of all sub-projects in line with the IR checklist of ADB, towards enabling identification of the potential resettlement impacts and associated risks.

2 Consultation with stake holders and establish grievance redress mechanism

Carryout consultations with displaced persons, host communities and concerned NGOs. Inform all displaced persons of their entitlements and resettlement

Whenever a Social Impact Assessment is required to be prepared under section 4, the appropriate Government shall ensure that a public hearing is held at the affected area, after giving adequate publicity about the date, time and venue for the public hearing, to ascertain the views of the affected families to be recorded

No gap between SPS and RFCTLARR. Act 2013 Given A project level GRM will be included.

Page 45: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

42

Aspect ADB Safeguard Requirement

Fair Compensation and Transference in Land

Acquisition, Rehabilitation and Resettlement Act, 2013

Measures to Bridge the

GAP

options and included in the Social Impact Assessment Report. The Land Acquisition Rehabilitation and Resettlement Authority shall be established in each State by the concerned State Government to hear disputes arising out of projects where land acquisition has been initiated by the State Government or its agencies.

3. Improve, or at least restore, the livelihoods of all displaced, and payment at replacement cost

Improve or restore livelihoods of all DPs through: (i) land-based resettlement strategies; (ii) prompt replacement of assets with access to assets of equal or higher value, (iii) prompt compensation at full replacement cost for assets that cannot be restored, and (iv) additional revenues and services through benefit sharing schemes if possible.

The Collector having determined the market value of the land to be acquired shall calculate the total amount of compensation to be paid to the land owner (whose land has been acquired) by including all assets attached to the land. Livelihood losers are eligible for various rehabilitation grants.

No gap between SPS and FCTLARR. Assets to be compensated at replacement cost without depreciation and other Livelihood assistances and income restoration measures will be included.

4. Assistance for displaced persons

Provide physically and economically displaced persons with needed assistance

Schedule I, provides market value of the land and value of the assets attached to land. Schedule II provides R&R package for land owners and for livelihood losers including landless and special provisions for Scheduled Tribes.

No gap between SPS and FCTLARR. Entitlement Matrix outlines compensation and assistance for DPs.

5. Improve standard of living of displaced vulnerable

Improve the standards of living of the displaced poor and other vulnerable groups,

Special provisions are provided for vulnerable groups.

No gap between SPS and FCTLARR. Entitlement

Page 46: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

43

Aspect ADB Safeguard Requirement

Fair Compensation and Transference in Land

Acquisition, Rehabilitation and Resettlement Act, 2013

Measures to Bridge the

GAP

groups including women, to at least national minimum standards

Matrix outlines assistance for vulnerable groups.

6. Negotiated Settlement

Develop procedures in a transparent, consistent, and equitable manner if land acquisition is through negotiated settlement to ensure that those people who enter into negotiated settlements will maintain the same or better income and livelihood status

FCTLARR only apply in case of land acquired/purchased for PPP projects and for Private Companies. Section: 2. (2), and 46.

Provisions outlined in ADB SPS will be followed for the project.

7. Compensation For non-title holders

Ensure that displaced persons without titles to land or any recognizable legal rights to land are eligible for resettlement assistance and compensation for loss of non-land assets.

Non-titleholders on acquired land area is only included but not clear about non-titleholders in existing govt. land

Provisions outlined in ADB SPS will be followed for the project.

8. Requirement of RP

Prepare a resettlement plan / indigenous peoples plan elaborating on displaced persons’ entitlements, the income and livelihood restoration strategy, institutional arrangements, monitoring and reporting

Preparation of Rehabilitation and Resettlement Scheme including time line for implementation. Section: 16. (1) and (2). Separate development plans to be prepared. Section 41

No gap between SPS and FCTLARR. RP will be prepared for subprojects with impact.

Page 47: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

44

Aspect ADB Safeguard Requirement

Fair Compensation and Transference in Land

Acquisition, Rehabilitation and Resettlement Act, 2013

Measures to Bridge the

GAP

framework, budget, and time-bound implementation schedule.

9. Public disclosure

Disclose a draft resettlement plan, including documentation of the consultation process in a timely manner, before project appraisal, in an accessible place and a form and language(s) understandable to displaced persons and other stakeholders. Disclose the final resettlement plan and its updates to displaced persons and other stakeholders

Under clause 18, the Commissioner shall cause the approved Rehabilitation and Resettlement Scheme to be made available in the local language to the Panchayat, Municipality or Municipal Corporation. As the case may be, and the offices of the District Collector, the Sub-Divisional Magistrate and the Tehsil, and shall be published in the affected areas, in such manner as may be prescribed and uploaded on the website of the appropriate Government.

In addition to the publishing of the approved resettlement plan, the RF includes provision for disclosure of the various documents pertaining to RP implementation.

10. Cost of resettlement

Include the full costs of measures proposed in the resettlement plan and indigenous peoples plan as part of project’s costs and benefits. For a project with significant involuntary resettlement impacts and / or indigenous peoples plan, consider implementing the involuntary resettlement component of the project as a stand-alone operation.

16. (I) Upon the publication of the preliminary notification under sub-section (/) of section 11 by the Collector, the Administrator for Rehabilitation and Resettlement shall conduct a survey and undertake a census of the affected families, in such manner and within such time as may be Prescribed, which shall include: (a) particulars of lands and immovable properties being acquired of each affected family; (b) livelihoods lost in respect of land losers and landless whose livelihoods are primarily dependent on the lands being acquired; (c) a list of public utilities and Government buildings which are affected or likely to be affected, where resettlement of affected families is involved; (d) details of

No gap between SPS and FCTLARR. Cost of resettlement will be covered by the EA.

Page 48: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

45

Aspect ADB Safeguard Requirement

Fair Compensation and Transference in Land

Acquisition, Rehabilitation and Resettlement Act, 2013

Measures to Bridge the

GAP

the amenities and infrastructural facilities which are affected or likely to be affected, where resettlement of affected families is involved; and (e) details of any common property resources being acquired'

11. Taking over possession before Payment of compensation

Pay compensation and provide other resettlement entitlements before physical or economic displacement. Implement the resettlement plan under close supervision throughout project implementation.

38 (I) The Collector shall take possession of land after ensuring that full payment ofcompensation as well as rehabilitation and resettlement entitlements are paid or tendered to the entitled persons within a period of three months for the compensation and a period of six months for the monetary part of rehabilitation and resettlement entitlements listed in the Second Schedule commencing from the date of the award made under section 30.

No gap between SPS and FCTLARR.

12. Monitoring Monitor and assess resettlement outcomes, their impacts on the standards of living of displaced persons, and whether the objectives of the resettlement plan have been achieved by taking into account the baseline conditions and the results of resettlement monitoring. Disclose monitoring reports.

48 (I)The Central Government may, whenever necessary for national or inter-State projects, constitute a National Monitoring Committee for reviewing and monitoring the implementation of rehabilitation and resettlement schemes or plans under this Act.

For project, monitoring mechanism and frequency will follow ADB SPS based on categorization.

F. R&R Policy Framework for the Subproject

113. Based on the above analysis of Government provisions and ADB policy, the following

resettlement principles are adopted for this Project:

(a) Screen the project early on to identify past, present, and future involuntary resettlement impacts and risks if any. Determine the scope of resettlement

Page 49: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

46

planning through a survey and / or census of displaced persons, including a gender analysis, specifically related to resettlement impacts and risks. Measures to avoid and minimize involuntary resettlement impacts include the following: (i) explore alternative alignments or locations which are less impacting, (ii) ensure the appropriate technology is used to reduce land requirements, (iii) modify the designs, cross sections, and geometrics of components to minimize the ROW and ensure involuntary resettlement is avoided or minimized.

(b) Carry out meaningful consultations with displaced persons, host communities,

and concerned non government organizations. Inform all displaced persons of their entitlements and resettlement options. Ensure their participation in planning, implementation, and monitoring and evaluation of resettlement programs. Pay particular attention to the needs of vulnerable groups, especially those below the poverty line, the landless, the elderly, women and children, and indigenous peoples if any, and those without legal title to land, and ensure their participation in consultations. Establish a grievance redress mechanism to receive and facilitate resolution of the concerns of displaced persons. Support the social and cultural institutions of displaced persons and their host population. Where involuntary resettlement impacts and risks are highly complex and sensitive, compensation and resettlement decisions should be preceded by a social preparation phase.

(c) Improve, or at least restore, the livelihoods of all displaced persons through; (i)

land-based resettlement strategies when affected livelihoods are land based where possible or cash compensation at replacement cost for land when the loss of land does not undermine livelihoods, (ii) prompt replacement of assets with access to assets of equal or higher value, (iii) prompt compensation at full replacement cost for assets that cannot be restored, and (iv) additional revenues and services through benefit sharing schemes where possible.

(d) Provide physically and economically displaced persons with needed assistance,

including the following: (i) if there is relocation, secured tenure to relocation land, better housing at resettlement sites with comparable access to employment and production opportunities, integration of resettled persons economically and socially into their host communities, and extension of project benefits to host communities; (ii) transitional support and development assistance, such as land development, credit facilities, training, or employment opportunities; and (iii) civic infrastructure and community services, as required.

(e) Improve the standards of living of the displaced poor and other vulnerable

groups, including women, to at least national minimum standards. In rural areas provide them with legal and affordable access to land and resources, and in urban areas provide them with appropriate income sources and legal and affordable access to adequate housing.

(f) Develop procedures in a transparent, consistent, and equitable manner if land

acquisition is through negotiated settlement1 to ensure that those people who

1 ADB SPS 2009 (Safeguards Requirements 2) does not apply to negotiated settlements. The policy is

encourages acquisition of land and other assets through a negotiated settlement wherever possible, based on meaningful consultation with affected persons, including those without title to assets. A

Page 50: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

47

enter into negotiated settlements will maintain the same or better income and livelihood status.

(g) Ensure that displaced persons without titles to land or any recognizable legal

rights to land are eligible for all compensation, relocation and rehabilitation measures, except land. .

(h) Prepare a resettlement plan elaborating on the entitlements of displaced

persons, the income and livelihood restoration strategy, institutional arrangements, monitoring and reporting framework, budget, and time-bound implementation schedule. This resettlement plan will be approved by ADB prior to contract award.

(i) Disclose a draft resettlement plan, including documentation of the consultation

process in a timely manner, before project appraisal, in an accessible place and a form and language(s) understandable to displaced persons and other stakeholders. Disclose the final resettlement plan and its updates to displaced persons and other stakeholders.

(j) Conceive and execute involuntary resettlement as part of a development project

or program. Include the full costs of resettlement in the presentation of project’s costs and benefits. For a project with significant involuntary resettlement impacts, consider implementing the involuntary resettlement component of the project as a stand-alone operation.

(k) Pay compensation and provide other resettlement entitlements before physical or

economic displacement if any. Implement the resettlement plan under close supervision throughout project implementation.

(l) Monitor and assess resettlement outcomes, their impacts on the standard of

living of displaced persons, and whether the objectives of the resettlement plan have been achieved by taking into account the baseline conditions and the results of resettlement monitoring. Disclose monitoring reports.

(m) It is proposed to follow the provisions of Pipeline Act 2013 also because KIP

relates to mainly Pipeline Project. Though the implementation of this Pipeline Act 2013 is possible only if there is mainly temporary impact on the properties of the affected population. But if there is permanent impact on their properties due to construction of permanent structures then the land has to be permanently acquired by following RFCTLARRA’ 2013.

(n) But before going into long and time taking procedure of permanent Land

Acquisition, efforts should be made to follow the provisions of “Consent Land Purchase Policy” vide GOMP order dated 12.11.2014 in which the required land

negotiated settlement will offer adequate and fair price for land and/or other assets. Also, an independent external party will be engaged to document the negotiation and settlement processes. In cases where the failure of negotiations would result in expropriation through eminent domain or the buyer could acquire the property regardless of its owner’s decision to sell it or not, will trigger ADB’s involuntary resettlement policy. The Safeguard Requirements 2 will apply in such cases, including preparing a resettlement plan.

Page 51: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

48

is purchased by the Government with the Mutual Consent of the affected person. But if the negotiations fail for the purchase of land with mutual consent then the procedure of permanent LAQ has to be followed as per RFCTLARR Act’ 2013.

(o) Regarding the eligibility of compensation, all APs will be provided with

compensation and rehabilitation grant if their land is adversely affected, houses partially or fully demolished, and other properties such as crops, trees and other facilities or access to these properties will be damaged due to the project. Lack of legal documents of their customary rights of occupancy/titles shall not affect their eligibility for compensation. It also must be noted that during the project implementation stage, if there are any changes in the alignments, there by adversely affecting the land, livelihood or other assets of the people, the same shall be compensated in keeping within the applicable framework.

(p) The framework stipulates payment of compensation as per the assessed value of

the land and structure to the APs. In addition to compensation payments made by Land Acquisition Officer / competent authority, the APs will receive additional assistance in cash or kind to match replacement costs, which is the difference between the market value and the assessed value, if any, for lost assets (land and houses), transaction costs such as stamps / registration costs (in case of purchase of replacement land) and other cash grants and resettlement assistance such as shifting allowance, compensation for loss of work days / income due to dislocation. Female-headed households and other vulnerable households (such as Scheduled Tribes/Scheduled Castes, disabled, elderly) will be eligible for further cash assistance for relocation and house reconstruction provided they are permanently affected and displacement becomes inevitable..

(q) The Entitlement Matrix lists various types of losses, identification / eligibility and

entitlements and provides basic parameters for preparation of compensation and resettlement benefits. The matrix would apply to additional subprojects, based on the specific project impacts.

G. Valuation of Assets

114. The valuation of affected land and structures will be governed by the following process:

115. Land surveys for determining the payment of compensation would be conducted on the

basis of updated official records and ground facts. The land records containing information like

legal title, and classification of land will be updated expeditiously for ensuring adequate cost

compensation and allotment of land to the entitled displaced persons. In cases of areas, where

official land records don’t exist, formal land/property boundaries of private property owned by the tribal households can be determined through the process of community consultation and

discussion with village head and village council members.

116. Based on such information, land can be classified and land record can be updated and

compensation assessment can be made. Records as they are on the cut-off date will be taken

into consideration while determining the current use of land. The uneconomic residual land

remaining after land acquisition will be acquired as per the provisions of RFCT in LARR Act,

2013. The owner of such land/property will have the right to seek acquisition of his entire

Page 52: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

49

contiguous holding/ property provided the residual land is less than the average land holding of

the District.

117. The methodology for verifying the replacement cost for each type of loss will be as per

the provision made in the RFCT in LARR Act -2013. But before going into lengthy and time

taking procedure of LAQ it is advisable to negotiate with owner of the required land to sell his

land to the Concerned Government Department following the principle of “Consent Land

Purchase Policy” vide GOMP Circular dated 12.11.2014. But if negotiations fail with the owner of the required land then the land has to be acquired by RFCTLARR Act 2013.

1. Valuation of Land

118. The District Collector/Deputy Commissioner shall determine the market value of the land

with assessment of (a) the market value, if any, specified in the Indian Stamp Act, 1899 for the

registration of sale deeds or agreements to sell, as the case may be, in the area, where the land

is situated; or (b) the average sale price for similar type of land situated in the nearest village or

nearest vicinity area; or (c) consented amount of compensation as agreed upon, whichever is

higher.

119. Where the market value as per above section (1) cannot be determined for the reason

that: (a) the land is situated in such area where the transactions in land are restricted by or

under any other law for the time being in force in that area; or(b) the registered sale deeds or

agreements to sell for similar land are not available for the immediately preceding three years;

or(c) the market value has not been specified under the Indian Stamp Act, 1899; the appropriate

authority, the State Government concerned shall specify the floor price or minimum price per

unit area of the said land based on the Price calculated in the manner specified in the above

section (1) in respect of similar types of land situated in the immediate adjoining areas.

120. The market value calculated as per above section (1) shall be multiplied by a factor of

(a) 1 (one) to 2 (two) in rural areas based on the distance of project from Urban Area as notified

by the Government of Madhya Pradesh; and (b) one in urban areas.

121. Solatium amount equivalent to 100% of the market value calculated on the basis of

above (1 or 2) x 3.

Hence: The cost of land in rural areas = X + 100% of X, The cost of land in urban areas = X + 100% of X Where X = Market Value as determined above x 1 to 2.

2. Valuation of Building and Structure

122. The District Collector/Deputy Commissioner in determining the market value of the

building and other immovable property or assets attached to the land or building which are to be

acquired shall use the services of a competent engineer or any other Specialist in the relevant

Page 53: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

50

field, as may be considered necessary by him. The cost of buildings will be estimated based on

updated Basic Schedule of Rates (BSR) as on date without depreciation. Solatium of 100% will

be added to the estimated market value of the structure as per the provision of RFCT in LARR

Act 2013. For valuation of structure/building following parameters should be taken into account:

(a) From where they used to buy materials (b) Type of shops (Private or State-owned) (c) Distance to be traveled (d) Sources (local or foreign) and the cost of various materials (e) Who will build the structures (owner or contractor) and whether they will use the

hired labor or their own labor (cost of labor will be considered); (f) Obtaining cost estimates by meeting at least three contractors/suppliers in order

to identify cost of materials and labor (g) Identifying the cost of different types of houses of different categories and

compare the same with district level prices.

3. Valuation of Trees

123. Compensation for trees will be based on their full replacement cost. The District

Collector/Deputy Commissioner for the purpose of determining the market value of trees and

plants attached to the land acquired, use the services of experienced persons in the field of

agriculture, forestry, Horticulture, Sericulture, or any other field, as may be considered

necessary by him.

124. Even after payment of compensation, DPs would be allowed to take away the materials

salvaged from their dismantled houses and shops and no charges will be levied upon them for

the same. In case of any structures not removed by the DPs in stipulated 60 days period, a

notice to that effect will be issued intimating that DPs can take away the materials so salvaged

within 48 hours of their demolition; otherwise, the same will be disposed by the project authority

without giving any further notice.

125. Trees standing on the land owned by the Government will be disposed of through open

auction by the concerned Revenue Department/ Forest Department. DPs will be provided with

an advance notice of three months prior to relocation. Further, all compensation and assistance

will be paid to DPs at least 60 days prior to displacement or dispossession of assets.

126. For temporary impact on land and common property resources, any land required by the

project on a temporary basis will be compensated in consultation with land owners and will be

restored to previous status or better quality. Implementation issues can be found in the

Entitlement Matrix.

Page 54: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

51

VIII. ENTITLEMENTS, ASSISTANCE AND BENEFITS

A. Introduction

127. This subproject will have 403 DHs as 5.777 ha of private land and 0.737 ha of

Government land will be impacted due to construction of laying of Distribution Pipeline as

mentioned in Table 3 involving acquisition of Private and Government Land. Private Land of

0.047 ha will be acquired permanently for construction of 235 OMS. However, there will not be

any physical displacement under the subproject because there will be very insignificant impact

on the properties and livelihood of the affected population because there will be mainly

temporary acquisition of land. This section deals with the entitlement provisions as per the

anticipated impacts for the Kundalia Micro Irrigation Project.

B. Cut-off-Date for Entitlement

128. In case of land acquisition, the date of publication of preliminary notification for

acquisition under section 11 of the RFCT in LARR Act – 2013 will be treated as the cut-off date.

For non-titleholders, the cut-off date will be the end of the census survey which is 30th June’ 2019 in this subproject. The cut-off date for non-titleholders will be officially declared by the IA

along with the disclosure of RP and additionally notified in the project area through newspaper

and communicated to DPs during consultation. They, however, will be given sufficient advance

notice, requested to vacate premises and dismantle affected structures prior to subproject

implementation. Their dismantled structures materials will not be confiscated and they will not

pay any fine or suffer any sanction.

C. Subproject Entitlement

129. At present 6.561 ha of Private Land and Government Land will be affected temporarily

and permanently so entitlement of compensation of all the affected private properties as per

their entitlement matrix will be paid as mentioned in LAP/RP of the subproject. The provisions of

the entitlements of the project as a whole will also be followed in letter and spirit in phases

according to the upcoming subprojects of KIP-Left Bank. In accordance with the R&R measures

outlined in the project Resettlement Framework, all displaced households and persons will be

entitled to a combination of compensation packages and resettlement assistance depending on

the nature of ownership rights on lost assets and scope of the impacts including socio-economic

vulnerability of the displaced persons and measures to support livelihood restoration if livelihood

impacts are envisaged. The displaced persons will be entitled to the following five types of

compensation and assistance packages:

(a) Compensation for the loss of land, crops / trees at their replacement cost; (b) Compensation for structures (residential / commercial) and other immovable

assets at their replacement cost; (c) Assistance in lieu of the loss of business / wage income and income restoration

assistance; (d) Assistance for shifting and provision for relocation site (if required), and (e) Rebuilding and/ or restoration of community resources / facilities.

Page 55: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

52

D. Loss of land

130. Loss of land will be compensated at replacement cost plus refund of transaction cost

(including land registration cost, and stamp duties) incurred for purchase of replacement land. If

the residual plot(s) is (are) not viable, i.e., the DP becomes a marginal farmer, three options are

to be given to the DP, subject to his acceptance which are (i) The DP remains on the plot, and

the compensation and assistance paid to the tune of required amount of land to be acquired, (ii)

Compensation and assistance are to be provided for the entire plot including residual part, if the

owner of such land wishes that his residual plot should also be acquired by the EA, the EA will

acquire the residual plot and pay the compensation for it and (iii) If the DP is from vulnerable

group, compensation for the entire land by means of land for land will be provided if AP wishes

so, provided that land of equal productive value is available. The replacement of land option will

be considered by the District Collector while acquiring land wherever feasible alternate land is

available. All fees, stamp duties, taxes and other charges, as applicable under the relevant

laws, incurred in the relocation and rehabilitation process, are to be borne by the EA.

131. The compensation measures suggested in this RP based on the LARR Act -2013, which

includes, market value, solatium, transition cost, interest in case of delay along with other

assistance items aligns with the criteria of replacement cost of the assets.

E. Loss of Structures

132. Loss of Structures will be compensated at replacement value with other assistance to

both titleholders and non-titleholders. The details of entitlement will be as:

(a) Compensation for structure at the replacement cost to be calculated as per latest prevailing basic schedules of rates (BSR) without depreciation.

F. Loss of trees and crops

133. Loss of trees and crops will be compensated by cash compensation. The entitlements to

the DPs losing trees and crops will be:

(a) Advance notice to harvest crops, fruits, and timbers. (b) Compensation for standing crops in case of such loss, based on an annual crop

cycle at market value (c) Compensation for trees based on timber value at market price, and

compensation for perennial crops and fruit trees at annual net product market value multiplied by remaining productive years; to be determined in consultation with the Forest Department for timber trees and the Horticulture Department for other trees/crops.

G. Additional assistance to vulnerable households

(a) Vulnerable households include BPL, SC, ST, WHH, Disabled, elderly and non-titleholders will be paid with special assistances as detailed below if they are impacted permanently due to construction of the subproject.

Page 56: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

53

(b) One time lump sum assistance of Rs. 25,000 to vulnerable households will be paid if they are experiencing permanent and singnificant impact on their properties and livelihood. This will be paid above and over the other.

(c) Receive preference in income restoration training program under the project. (d) Preference in employment under the project during construction and

implementation. (e) Access to basic utilities and public services.

H. Loss of community infrastructure/common property resources

134. Though there is no community infrastructure is being impacted in this subproject but in

case if there is any possibility in near future for this or other subprojects then the impacted,

Common Property Resources (CPR) will be compensated either by paying them compensation

at replacement cost of the property/structure to the community (registered trust, society or

village committee as appropriate) or by reconstruction of the community structure in consultation

with the affected community.

I. Temporary Impacts

135. Temporary impacts on agricultural land due to plant site for contractor etc will be eligible

for cash compensation for loss of income potential including:

(a) Any land required by the Project on a temporary basis will be compensated in consultation with the landholders.

(b) Rent at market value for the period of occupation (c) Compensation for assets at replacement cost (d) Restoration of land to previous or better quality (e) Location of construction camps will be fixed by contractors in consultation with

Government and local community. (f) 60 Days advance notice regarding construction activities, including duration and

type of temporary loss of livelihood. (g) Cash assistance based on the minimum wage/average earnings per month for

the loss of income/livelihood for the period of disruption, and contractor’s actions to ensure there is no income/access loss.

(h) Any unanticipated impacts due to the subproject will be documented during the implementation phase and mitigated based on provision made in the Entitlement Matrix of this Resettlement Plan.

J. Entitlement Matrix

136. An Entitlement Matrix has been developed, that summarizes the types of losses and the

corresponding nature and scope of entitlements; and is in compliance with National Laws and

ADB SPS-2009 (refer to Table 22). All compensation and other assistances will be paid to all

DPs prior to physical or economic displacement. After payment of compensation, DPs would be

allowed to take away the materials salvaged from their dismantled houses and shops and no

charges will be levied upon them for the same. The cost of salvaged materials will not be

deducted from the overall compensation amount due to the DPs. A notice to that effect will be

issued intimating that DPs can take away the materials.

Page 57: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

54

Table 22: Entitlement Matrix S.N. Type of

Loss Application Definition of

Entitled Person Compensation Policy Implementation

Issue

Responsible Agency

Land

1-a Loss of private land

Agricultural land2, homestead land or vacant plot

Legal titleholders/ Family with traditional titleholders3

• Compensation at

replacement cost or

land-for-land where

feasible.4If land-for-land

is offered, titles will be

in the name of original

landowners. • One time Resettlement

allowance5 of Rs.

50,000 per affected

family6

• Each affected family

shall be eligible for

choosing one time

assistance option from:

(i) Where jobs are

created through the

project, employment for

at least one member of

the affected family with

suitable training and

skill development in the

required field; or (ii)

One-time payment of

Rs. 500,000 per

affected family.

• Displaced

families7belong to

• Compensation

accounts for all

taxes and fees,

and does not

account for any

depreciation.

• Vulnerable

households will

be identified

during the

census.

• Re-titling to be

completed prior

to project

completion

• For option of

choosing job

created through

project, job will

be paid at living

wage and

monitored by

CSC.

District Collector/Deputy Commissioner shall determine the market value of the land and multiply by the factors and add 100% solatium as specified in LARR Act. PIU will ensure provision of notice. PIU will verify the extent of impacts through a 100% survey of APs, determine assistance, and identify vulnerable households.

2 The LARR, 2013 Act says no irrigated multi cropped land shall be acquired under this Act, except in exceptional

circumstances, as a demonstrable last resort. Wherever such land is acquired, an equivalent area of cultivable wasteland

shall be developed for agricultural purposes or an amount equivalent to the value of land acquired shall be deposited with

the appropriate Government for investment in agriculture for enhancing food-security. Such costing shall also reflect while

preparing Resettlement Budget. 3 Traditional land rights refer to households with customary rights to land, and shall be treated equivalent to

titleholders. The Scheduled Tribes and Other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006 defines “Forest Dwelling Scheduled Tribes” as the members or community of the Scheduled Tribes who primarily reside in andwho depend on the forests and forest lands for bona fide livelihood needs and includes the Scheduled Tribe pastoralist communities. The act provides right to in situ rehabilitation including alternative land in cases where the Scheduled Tribes and other traditional forest dwellers have been illegally evicted or displaced from forest land of any description without receiving their legal entitlement or rehabilitation prior to the 13th of December 2005.

4 Including option for compensation for non-viable residual portions. 5 The LARR Act–2013 specifies that each affected family shall be given one time Resettlement Allowance of Rs.50,000/- only. 6 ‘Family’ includes a person, his or her spouse, minor children, minor brothers and minor sisters dependent on him. Widows,

divorcees and women deserted by families shall be considered separate family. An adult of either gender with or without

spouse or children or dependents shall be considered as a separate family – as defined under LARR Act–2013. 7Displaced family" as defined by the LARR Act–2013, means any family, who on account of acquisition of land has to be

relocated and resettled from the affected area to the resettlement area. According to ADB SPS-2009, displaced persons are

those who are physically displaced (relocation, loss of residential land, or loss of shelter) and/or economically displaced

Page 58: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

55

Scheduled Caste (SC)

and Scheduled Tribe

(ST) of Scheduled

Areas will receive

additional one-time Rs.

50,000 as subsistence

allowance.

• Additional assistance to

Vulnerable Households

1-b Loss of private land

Agricultural land, homestead land or vacant plot

Tenants and leaseholders (whether having written tenancy/lease documents or not / Sharecroppers

• Compensation for rental deposit or unexpired lease (such amount will be deducted from the compensation of land owners).

• Displaced families belong to Scheduled Caste (SC) and Scheduled Tribe (ST) of Scheduled Areas will receive additional one-time Rs. 50,000 as subsistence allowance

• Additional assistance to Vulnerable Households

• Land owners will reimburse tenants and leaseholders land rental deposit or unexpired lease

• Vulnerable households will be identified during the census.

PIU will confirm land rental and ensure tenants and leaseholders receive reimbursement for land rental deposit or unexpired lease, and report to PIU. PIU will ensure provision of notice.

2-a Loss of Government land

Vacant plot, Agricultural land, homestead land

Leaseholders • Compensation for

rental deposit or

unexpired lease (such

amount will be

deducted from the

compensation of the

lessee).

• Displaced families

belong to Scheduled

Caste (SC) and

Scheduled Tribe (ST)

of Scheduled Areas will

receive additional one-

time Rs. 50,000 as

subsistence allowance.

• Additional assistance

to Vulnerable

Households

• Vulnerable households will be identified during the census.

PIU will ensure provision of notice and identify vulnerable households.

(loss of land, assets, access to assets, income sources, or means of livelihoods) as a result of (i) involuntary acquisition of

land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas. Thus, under

this RF, the subsistence allowance is applicable for all affected families losing land irrespective of their nature of physical or

economic displacement.

Page 59: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

56

2-b Loss of Government land

Vacant plot, Agricultural land, homestead land

Non-Title Holders/Squatters8, Encroachers9

• At least 60 days

advance notice to shift

from occupied land.

• Notice to harvest

standing seasonal

crops and

compensation.

• Displaced families

belong to Scheduled

Caste (SC) and

Scheduled Tribe (ST)

of Scheduled Areas will

receive additional one-

time Rs. 50,000 as

subsistence allowance

• Additional assistance

as Vulnerable

Households

• As per ADB SPS-2009, all NTH are considered as vulnerable households.

PIU will ensure provision of notice. PIU will identify vulnerable households.

Residential Structures10 3-a Loss of

residential structure

Residential structure and other assets11

Legal titleholders Family with traditional land right

Each affected family

shall be eligible for

choosing one time

assistance option from:

(i) Replacement

cost of the

structure and

other assets (or

part of the

structure and

other assets, if

remainder is

viable) without

depreciation;

Or

(ii) In Rural area,

the displaced

family will be

provided with the

option of

constructed

house as per

Indira

AwaasYojana

specifications in

lieu of cash

• Compensation

accounts for all

taxes and fees,

and does not

account for any

depreciation.

• Vulnerable

households will

be identified

during the

census.

• Wherevers DPs

opt for self-

construction,

land and

structures will

be

compensated at

replacement

cost

• Assessment of

viability of

remaining

structure will be

made in

consultation

District Collector/Deputy Commissioner shall determine the market value of the structure and add 100% solatium as specified in LARR Act. Valuation committee will verify replacement value. PIU will verify the extent of impacts through a 100% survey of AHs determine assistance, verify and identify vulnerable households.

8Squatters are those who have no recognizable rights on the land that they are occupying. 9 Encroachers are those who build a structure which is in whole or is part of an adjacent property to which he/she has no title. 10Some of the entitlements under section are the same as previous rows as it is structured separately for each

affected category and should not be duplicated in reading 11 Other assets include, but is not limited to walls, fences, sheds, wells, etc.

Page 60: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

57

compensation;

(iii) In Urban area,

the displaced

family will be

provided with the

option of

constructed

house of

minimum 50 sq.

m. plinth area in

lieu of cash

compensation.

• Fees, taxes, and other

charges related to

replacement structure.

• Right to salvage

materials from

structure and other

assets with no

deductions from

replacement value.

• One-time Resettlement

allowance of Rs.

50,000 per affected

household

• One time financial

assistance of Rs.

25,000 to the families

losing cattle sheds for

reconstruction

• All displaced families

will receive one time

shifting assistance of

Rs. 50,000 towards

transport costs etc.

• Displaced families

belong to Scheduled

Caste (SC) and

Scheduled Tribe (ST)

of Scheduled Areas will

receive additional one-

time Rs. 50,000 as

subsistence allowance.

• Additional assistance

to Vulnerable

Households

with DPs

3-b Loss of residential structure

Residential structure and other assets

Tenants and leaseholders

• Replacement cost of

part/whole of structure

constructed by the

tenant/leaseholder

Land/structure

owners will

reimburse tenants

and leaseholders

Valuation committee will verify replacement value. PIU will

Page 61: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

58

without depreciation,

and this will be

deducted from the

compensation amount

of the owner.

• Compensation for

rental deposit or

unexpired lease.

• Right to salvage

materials (of the

portion constructed by

tenants or

leaseholders) from

structure and other

assets

• One time Resettlement

allowance of Rs.

50,000 per affected

family

• One time financial

assistance of Rs.

25,000 to the families

losing cattle sheds for

reconstruction.

• All displaced families

will receive one time

Shifting assistance of

Rs. 50,000 towards

transport costs etc

• Displaced families

belong to Scheduled

Caste (SC) and

Scheduled Tribe (ST)

of Scheduled Areas will

receive additional one-

time Rs. 50,000 as

subsistence allowance.

• Additional assistance

to Vulnerable

Households

rental deposit or

unexpired lease.

Vulnerable

households will

be identified

during the

census.

verify the extent of impacts through a 100% surveys of AHs determine assistance, verify and identify vulnerable households.

3-c Loss of residential structure

Residential structure and other assets

Non-Title Holders/ Squatters, Encroachers

• Replacement cost of

structure constructed

by the squatter without

depreciation

• Right to salvage

materials from

structure and other

assets

• One time Resettlement

allowance of Rs.

Vulnerable

households will

be identified

during the

census.

PIU will verify the extent of impacts through a 100% survey of AHs determine assistance, verify and identify vulnerable households.

Page 62: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

59

50,000 per affected

family

• All displaced families

will receive one time

shifting assistance of

Rs. 50,000 towards

transport costs etc.

• Displaced families

belong to Scheduled

Caste (SC) and

Scheduled Tribe (ST)

of Scheduled Areas will

receive additional one-

time Rs. 50,000 as

subsistence allowance.

• Additional assistance

to Vulnerable

Households

Commercial Structures

4-a Loss of commercial structure

Commercial structure and other assets

Legal titleholders Family with traditional land right

• Replacement cost of

the structure and other

assets (or part of the

structure and other

assets, if remainder is

viable) without

depreciation

• Fees, taxes, and other

charges related to

replacement structure.

• Right to salvage

materials from

structure and other

assets with no

deductions from

replacement value.

• One time Resettlement

allowance of Rs.

50,000 per affected

family

• One time financial

assistance of Rs.

25,000 to the families

losing shop for

reconstruction of shop.

• All physically displaced

families will receive

one time shifting

assistance of Rs.

50,000 towards

transport costs etc.

• Compensation

accounts for all

taxes and fees,

and does not

account for any

depreciation.

• Vulnerable

households will

be identified

during the

census.

Valuation committee will determine replacement value. PIU will verify the extent of impacts through a 100% survey of AHs determine assistance, verify and identify vulnerable households.

Page 63: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

60

• Displaced families

belong to Scheduled

Caste (SC) and

Scheduled Tribe (ST)

of Scheduled Areas will

receive additional one-

time Rs. 50,000 as

subsistence allowance.

• Additional assistance

to Vulnerable

Households

4-b Loss of commercial structure

Commercial structure and other assets

Tenants and leaseholders

• Replacement cost of

part/whole of structure

constructed by the

tenant/leaseholder

without depreciation,

and this will be

deducted from the

compensation amount

of the owner.

• Compensation for

rental deposit or

unexpired lease.

• Right to salvage

materials (of the

portion constructed by

tenants or

leaseholders) from

structure and other

assets

• One time Resettlement

allowance of Rs.

50,000 per affected

family

• All displaced families

will receive one time

shifting assistance of

Rs. 50,000 towards

transport costs etc.

• Displaced families

belong to Scheduled

Caste (SC) and

Scheduled Tribe (ST)

of Scheduled Areas will

receive additional one-

time Rs. 50,000 as

subsistence allowance.

• Additional assistance

to Vulnerable

Households

Land/structure

owners will

reimburse tenants

and leaseholders

land rental

deposit or

unexpired lease.

Vulnerable

households will

be identified

during the

census.

Valuation committee will determine replacement value. PIU will verify the extent of impacts through a 100% survey of AHs determine assistance, verify and identify vulnerable households.

Page 64: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

61

4-c Loss of commercial structure

Commercial structure and other assets

Non-Title Holders/Squatters, Encroacher

• Replacement cost of

structure constructed

by the squatter without

depreciation

• Right to salvage

materials from

structure and other

assets

• One time Resettlement

allowance of Rs.

50,000 per affected

family

• All displaced families

will receive one time

shifting assistance of

Rs. 50,000 towards

transport costs etc.

• Displaced families

belong to Scheduled

Caste (SC) and

Scheduled Tribe (ST)

of Scheduled Areas will

receive additional one-

time Rs. 50,000 as

subsistence allowance.

• Additional assistance

to Vulnerable

Households

Vulnerable

households will

be identified

during the

census.

PIU will verify the extent of impacts through a 100% surveys of AHs determine assistance, verify and identify vulnerable households.

Livelihood 5 Loss of

livelihood Livelihood Legal titleholder

losing business/ commercial establishment Family with traditional land right Commercial tenant Commercial leaseholder Employee in commercial establishment Agricultural laborer (long term) Artisans Squatters

• One time financial

assistance of minimum

Rs. 25,000.

• Skill up-gradation

training to APs opted

for (one member of the

affected family) income

restoration.

• Preference in

employment under the

project during

construction and

implementation.

• Monthly Subsistence

allowance of Rs. 3,000

for one year (total Rs.

36,000) from the date

of award

• Displaced families

belong to Scheduled

Caste (SC) and

Vulnerable

households will

be identified

during the

census.

PIU will verify the extent of impacts through a 100% survey of AHs determine assistance, verify and identify vulnerable households. For Agricultural laborer (long timer) Only those who are in fulltime / permanent employment of the land owner will be eligible for this assistance. Seasonal

Page 65: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

62

Scheduled Tribe (ST)

of Scheduled Areas will

receive additional one-

time Rs. 50,000 as

subsistence allowance.

• Additional assistance

to Vulnerable

Households

experiencing significant

losses

agricultural laborers will not be entitled for this assistance.

Trees and Crops 6 Loss of

trees and crops

Standing trees and crops

Legal titleholder Family with traditional land right Agricultural tenant/ leaseholder Sharecroppers Non-Title Holders Squatter

• Advance notice to

harvest crops, fruits,

and timbers.

• Compensation for

standing crops in case

of such loss, based on

an annual crop cycle at

market value

• Compensation for trees

based on timber value

at market price, and

compensation for

perennial crops and

fruit trees at annual net

product market value

multiplied by remaining

productive years; to be

determined in

consultation with the

Forest Department for

timber trees and the

Horticulture

Department for other

trees/crops.

• Harvesting prior

to acquisition

will be

accommodated

to the extent

possible

• Work schedules

will avoid

harvest season.

• Seasonal crops

will be given at

least 60-day

notice. If notice

cannot be

given,

compensation

for standing

crops will be

compensated at

market value.

• Market value of

trees/crops has

to be

determined.

PIU will ensure provision of notice. Valuation Committee will undertake valuation of standing crops, perennial crops and trees, and finalize compensation rates in consultation with APs.

Vulnerable

7 Impacts on vulnerable APs

All impacts Vulnerable APs • Vulnerable households

experiencing losses

associated with items

1-a, 1-b, 2-a, 2-b, 3-a,

3-b, 3-c, 4-a, 4-b, 4-c, 5

and 6 will receive a

onetime lump sum

assistance of Rs. 25

0000. This vulnerability

assistance will be paid

to the vulnerable

household above and

over other

Vulnerable

households will

be identified

during the census

and

implementation of

project.

PIU will verify the extent of impacts through a 100% surveys of AHs determine assistance, verify and identify vulnerable households. The PIU with support from the CSC and

Page 66: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

63

compensation and

assistances provided.

• For vulnerable

households

experiencing temporary

and insignificant losses

described in items 8

and 9, the contractor

will ensure that any

land restrictions will not

adversely impact any

vulnerable household

members.12 For

example, senior and

disabled households

members will be

provided adequate

alternative access

roads where

construction has

restricted land access.

• Receive preferential in

income restoration

training program under

the project.

• Preference in

employment under the

project during

construction and

implementation

• Access to basic utilities

and public services

NGO13will conduct a training need assessment in consultations with the displaced persons so as to develop appropriate income restoration schemes. Suitable trainers or local resources will be identified by PIU and NGO in consultation with local training institutes.

Temporary Loss 8 Temporary

loss of land14

Land temporarily required for sub-project construction

Legal titleholders Family with traditional land right

• Any land required by

the Project on a

temporary basis will be

compensated as per

the Pipeline Act and in

consultation with DPs.

• Rent at market value

Assessment of

impacts if any on

structures, assets,

crops and trees

due to temporary

occupation.

Valuation Committee will determine rental value and duration of construction survey and consultation with

12 Significant losses include: (i) being physically displaced from housing, or (ii) losing 10% or more of an affected

households’ productive assets (income generating). 14 Temporary possession of land for project purpose can be taken only for three years from the date of

commencement of such possession/occupation. 13When suitable NGO is not available, the PIU will be staffed with qualified and experienced social workers to assist

the IA in RP implementation 14 Temporary possession of land for project purpose can be taken only for three years from the date of

commencement of such possession/occupation.

Page 67: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

64

for the period of

occupation

• Compensation for

assets at replacement

cost

• Restoration of land to

previous or better

quality15.

• Location of

construction camps will

be fixed by contractors

in consultation with

Government and local

community.

Site restoration.

Landowners

electing to decline

compensation

must sign the

MoU in the

Presence of a

third party

withness. All

Mou’s will be included in the

RP or Social

Monitoring Report

APs. PIU will ensure compensation is paid prior to site being taken-over by contractor. Contractor will be responsible for site restoration.

9 Temporary disruption of livelihood

Land temporarily required for sub-project construction.

Legal titleholders, non-titled Aps

• 60 days advance

notice regarding

construction activities,

including duration and

type of disruption.

• Cash assistance based

on the minimum

wage/average earnings

per month for the loss

of income/livelihood for

the period of disruption,

and contractor’s actions to ensure there

is no income/access

loss consistent with the

EMP.16

Assistance to mobile vendors/hawkers to temporarily shift for continued economic activity.17

• Identification of

alternative

temporary sites

to continue

economic

activity.

Valuation Committee will determine income lost. Contractors will

perform actions

to minimize

income/access

loss.

Common Resources 10 Loss and

temporary impacts on common resources

Common resources

• Communities • Replacement or

restoration of the

affected community

facilities – including

public water stand

posts, public utility

posts, temples,

Follow ADB SPS PIU and Contractor.

15 If the land has become permanently unfit to be used for the purpose for which it was used immediately before the

commencement of such term, and if the persons interested shall so require, the appropriate Government shall proceed under the Act to acquire the land as if it was needed permanently for a public purpose.

16 This includes: leaving spaces for access between mounds of soil, providing walkways and metal sheets to maintain access across trenches for people and vehicles where required, increased workforces to finish work in areas with impacts on access, timing of works to reduce disruption during business hours, phased construction schedule and working one segment at a time and one side of the road at a time.

17For example assistance to shift to the other side of the road where there is no construction.

Page 68: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

65

shrines, etc.

Other 11 Any other

loss not identified

• DPs

Communities

• Unanticipated

involuntary impacts will

be documented during

the implementation

phase and mitigated

based on provision

made in the RF.

PIU will finalize the entitlements in line with ADB’s SPS, 2009.

Page 69: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

66

IX. RELOCATION, INCOME RESTORATION AND REHABILITATION

A. Basic Provision for Relocation

137. There will be temporary impact on the properties of 403 households. Due measures will

be taken to take care of any situation which may arise at the later stages also. The EA will

provide adequate and appropriate replacement land and structures if available or cash

compensation at full replacement cost for lost land and structures, adequate compensation for

partially damaged structures, and relocation assistance, according to the Entitlement Matrix.

The EA will compensate to the non-titleholders for the loss of assets other than land, such as

dwellings, and also for other improvements to the land, at full replacement cost. The

entitlements to the non-titleholders will be given only if they occupied the land or structures in

the subproject area prior to the cut-off date. There will not be any displacement of population in

this Subproject but in case of any physical displacement, the EA will provide:

(a) relocation assistance, better housing at resettlement site*s with comparable access to employment and production opportunities, and civic infrastructure and community services as required;

(b) transitional support and development assistance, such as land development, credit facilities, training, or employment opportunities; and

(c) Opportunities to derive appropriate development benefits from the subproject such as direct employment, engagement as petty contractor, supplying raw materials etc.

B. Income Restoration and Rehabilitation

138. The impact of the Subproject will be temporary as it involves the construction of

alignment of Distribution Pipeline.There will be temporary and partial impact on the private

properties of the 403 affected households for which AHs will get due compensation as per the

provisions of Pipeline Act of the State. The provisions of the Pipeline Act of the State will be

extended for temporary acquisition of their impacted land and provisions of RFCTLARR or

Consent Land Purchase Policy of the State if there is any permanent acquisition of land.

139. There will not be any significant loss of their properties due to temporary acquisition of

land. Even then, they can develop their land with the compensation amount which they will get

against the loss of their impacted land. There is no community infrastructure being impacted in

this subproject but in case if there is any possibility in near future then the impacted Common

Property Resources (CPR) will be compensated either by paying them compensation at

replacement cost to the community (registered trust, society or village committee as

appropriate) or reconstruction of the community structure in consultation with the affected

community.

140. The objective of the R&R package included in the subproject entitlement matrix is to

support the DPs to improve or at least restore the livelihoods. There is no loss of any livelihood

because the impact on their properties is insignigficant due to temporary acquisition of land. In

case of business loss will also be easily restored by the DPS with the help of R&R assistance

Page 70: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

67

provided under the Subproject. The specific measure provided under the entitlement matrix of

this RP is listed below.

• Vulnerable households will receive preferential in income restoration training program under the project.

• Vulnerable households will have preference in employment under the project during construction and implementation.

• Project will ensure access to basic utilities and public services by vulnerable households

141. Though there will not be any significant impact on the properties and livelihood of DHs

due to temporary acquisition of their land, even then the wards of the APs will be encouraged to

take up ITI Courses in the adjoining Government run Industrial Training Institutes (ITI’s). After

taking such trainings they can start their self-employment avocations. As it is pressure on

agriculture land is increasing day by day as the number of family members is increasing in every

generation but the area of the land holding is still the same. Taking up some other job avenues

by the younger generation will be for the betterment of their families as it will reduce the extra

pressure on the agriculture land.

C. Provisions for Loss of Livelihood

142. In cases where land acquisition affects commercial structures, affected business owners

are entitled to:

(a) the costs of re-establishing commercial activities elsewhere; (b) the net income lost during the transition period; and (c) the costs of transferring and reinstalling plant, machinery, or other equipment.

143. Business owners with legal rights or recognized or recognizable claims to land where

they carry out commercial activities are entitled to replacement property of equal or greater

value or cash compensation at full replacement cost. Non-titleholder households losing

business structure and livelihood will be compensated for the structure loss and receive

transitional assistance as well. The EA will ensure that no physical displacement or economic

displacement will occur until:

(a) compensation at full replacement will be paid to each displaced person for subproject components or sections that are ready to be constructed;

(b) other entitlements listed in the resettlement plan have been provided to displaced persons; and

(c) a comprehensive income and livelihood rehabilitation program, supported by an adequate budget, is in place to help displaced persons improve, or at least restore, their incomes and livelihoods.

D. Additional Support from Ongoing Poverty Reduction Programs

144. In addition to Subproject-sponsored programs, the implementing RS will play a proactive

role to mobilize DPs to get benefits from various government schemes and ensure their

accessibility particularly of vulnerable groups. In India, Panchayat Government Systems at the

Page 71: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

68

village, block and district levels are now responsible for planning and implementation of all anti-

poverty programs funded by the central and state governments. The implementing RS will work

with the Panchayat Governments to make available to the DPs benefits of some of the ongoing

pro-poor programs for poverty reduction of GOI.

Page 72: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

69

X. LAND ACQUISITION BUDGET AND FINANCING PLAN

A. Introduction

145. The land acquisition cost estimate for this subproject includes compensation for loss of

land, loss of structures, loss of trees and Rehabilitation Assistance / Grant as per their impacts

and eligibilities.

B. Compensation Payment

146. Compensation for Crop Loss: The private land of 5.777 ha, has to be acquired

temporarily for Laying of underground distribution Pipeline. Since there is only temporary

acquisition of land therefore the provisions of Pipeline Act of the State has been implemented

for payment of compensation.The provisions of Pipeline Act includes double crop compensation

to be paid to the AHs. The calculation of Crop Compensation is based on Standard outcome of

Soyabean Crop which is grown during the construction period to be under taken in sub-project

area of Zone-3 in Left Bank of KIP. The Standard Outcome of Soyabean Crop is estimated to be

approximately 20 Quintals production in One Hectare of Land in this area. The Double Crop

Compensation for temporary land acquisition is based on the Standard outcome of the crop to

be multiplied by the Minimum Support Price (MSP) as declared by Ministry of Agriculture &

Farmers Welfare, GOI.

147. Compensation for Temporary Land Acquisition: In addition to the compensation as

referred above, the compensation for temporary land acquisition of 5.777 ha shall be payable at

the rate of 15% of the market value of the impacted land. The compensation is based on 15

percent amount of an average cost of the market value of irrigated agriculture land as per the

Collector Guideline of the total 12 impacted villages of sub-project area of Zone-3 in Left Bank

of KIP.

148. Compensation for Permanent Land Acquisition: The 235 OMS of 1 X 2 Meter in size

will require 0.047 ha of private land which needs to be acquired permanently so Compensation

has to paid for 0.047 ha of private land.

149. Compensation for Trees: For cost estimate in LARP for affected private trees

enumerated during the census survey, a lump sum rate of Rs. 15,000/- for fruit bearing trees

and Rs. 3000/- for non fruit bearing trees has been considered based on the market

assessment. Compensation for standing Orange Orchard Trees will also be paid based on three

categories. In Category-A there are 128 Orange trees, in Category-B there are 63 orange trees

and only 7 Orange trees in C-Category to be impacted in sub-project. There are 3 other variety

of fruit bearing trees and 1 Timber private tree which may come in the alignment of the

distribution pipeline.

150. For Orange fruit trees in standing orchards, the trees have been divided in three

categories for compensation purposes in which Category-A includes presently fruit bearing trees

estimating their cost to be Rs. 15000 per tree based on their yearly production of Rs 3000 each

year for an estimated period of five years. Category-B includes those orange trees which will

Page 73: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

70

start giving fruits after 2-3 years estimating it to be Rs. 1000 yearly of one tree for a period of

five years and Category-C are the trees which have been planted recently estimating them to be

Rs.100 each tree.

151. Livelihood Resources: Due to temporary acquisition of impacted land, the impact on

the properties and livelihood of AHs will be insignificant so for skill development the AHs will be

encouraged to take Vovational Training from the Government ITI’s and take advantage of the

ongoing schemes of State and the Central Government.

C. Compensation for Community Property Resources

152. There will be impact only on 0.737 ha of Government Land. No Community Property

Resources are to be impacted due to the alignment of this subproject.

153. The required Public / Government land will be transferred in the name of WRD by

respective departments and therefore not included in the resettlement cost.

D. LAP Implementation and Support Cost

154. The WRD has decided to hire Resettlement Officer / Expert for implementation of RR

activities. The implementation support cost including Hiring of Resettlement Specialist,

conducting public consultation, grievance redress cost etc. will be borne by administrative

expenses of WRD. A 10% Contingency Charges has been added in this subproject in order to

hire the services of Resettlement Specialist for implementation purposes and for conducting GR

Meetings and to adjust any cost escalation during subproject implementation.

E. Sources of Funding and Fund Flow Management

155. The cost related to permanent land acquisition and resettlement will be borne by the

Executive Agency (EA) MPWRD. The EA will ensure allocation of funds and availability of

resources for smooth implementation of the subproject R&R activities. The EA will, in advance,

initiate the process and will try to keep the approval for the R&R budget in the fiscal budget

through the ministry of finance in GOMP. In the case of assistance and other rehabilitation

measures, the EA will directly or through the Contractor pay the money or any other assistance

as stated in the LAP to DPs. The implementing Resettlement Expert / Specialist will be involved

in facilitating the disbursement process and rehabilitation program. The cost estimate for the

LAP implementation of this Subproject is Rs 4.91 Million.

Page 74: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

71

Table 23: Estimated Budget for Implementation of the RP

Sl. No. Item Unit Rate Amount

A Compensation for Land in Ha/Rs in Rupees

1 Compensation for Private Land (235 Outlet Management System which has to be a concrete base of 1x2 meters each)

0.047 (Ha) 1454750 68373.25

2 100% Solatium of Permanent Private Land Acquisition for 235 OMS

68373.25 (Rs)

100% 68373.25

Subtotal A 136746.50

B Compensation For Temporary Acquisition and Crop Loss

in Ha/Nos Rupees in Rupees

1 Compensation for temporary land acquisition and standing crops for underground pipe lines, piped canals and distribution system18

5.777 (Ha) 135000 779895

In addition to the compensation of Crop Loss, 15% of the market value of that impacted land will be added as per Special Provision of Pipeline Act of GOMP 201319

5.777 (Ha) 218212 1260610.72

2 Compensation for standing orange orchard Trees (As classified in A-Category)

128 (Trees)

15000 1920000

3 Compensation for standing orange orchard Trees (As classified in B-Category)

63 (Trees)

5000 315000

4

Compensation for standing orange orchard (C-Category- including cost of planting material, manures and fertilizers, Insecticides and pesticides, land leveling, cost of labor and fencing etc.)

7 (Trees)

100 700

5 Other Fruit Bearing Tree 3 15000 45000

6 Timber Tree 1 3000 3000 Subtotal B 4324205.72

Total (A+B) 4460952.22

Contingency (10%)for Hiring RS, Conducting GR Meetings & Cost Escalation 446095.22

GRAND TOTAL 4907047.44

18 Sources : Considering Soyabean Crop Rates of Rs. 3399/- per Quintal from from the Ministry of Agriculture &

Farmers Welfare, GOI as Annexed at Annexure – 12.Average Production of Soyabean crops per year is 20 Quintal per Ha in this subproject area is taken from Preveious years crop production Data of Horticulture Department and discussions and feedback from the Farmers of the Subproject Area.

19 Srouce : Considered Agriculture Land cost from the Collertor Guideline of Nalkheda Tehsil, Agar Malwa District. Annexure – 11. As far as the land cost is concerned, it has been arrived by addining the land cost of all impacted Villages and after taking out an average cost of the area which is reasonaly high. The budget has been prepared based on 15% of the land cost for payment of compensation as per Pipeline Act which seems to be low.

Page 75: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

72

XI. INSTITUTIONAL ARRANGEMENTS AND CAPACITY DEVELOPMENT

A. Institutional Requirement

156. For implementation of LARP of the Project there will be a set of institutions involved at

various levels and stages of the subproject. For successful implementation of the LAP the

proposed institutional arrangement with their role and responsibility has been outlined in this

section. The primary institutions, which will be involved in this implementation process, are the

following:

(a) Project Implementation Unit (PIU)/ Project Management Unit (PMU)

(b) Land Valuation Committee (LVC)-Section 26 of the act defines the method by which market value of the land shall be computed under the proposed law. A Land Valuation Committee is formed under the Chairmanship of the concerned District Collector to assess the prevailing market value of the land. Based on this Collector’s Guideline is published based on a multiple of market value.

(c) Village Level Committee (VLC)- It is the duty of Gram Sabha to perform not

only functions of fixing accountability over the Panchayat but, also to make it an executive body with separate standing village level committees (VLC) entrusted with several functions for overall development of the Village.

(d) PMU Level Grievance Redress Committee

B. Executing Agency

157. The Executing Agency (EA) for the Project is the Ministry of Water Resources,

Government of Madhya Pradesh, and the Implementing Agency (IA) is Water Resources

Department, GOMP. The existing Branch Office at Zeerapur Tehsil Head Quarter has already

been established which will be the PIU/PMU. This office will be functional for the whole

Subproject duration.

C. Land Acquisition Management at PIU/PMU

158. PIU/PMU headed by a Project Director (PD) responsible for the overall execution of the

subproject. The PD will be responsible for (i) overall implementation of R&R activities according

to the RP and equally responsible for land acquisition and R&R activities in the field; (ii) ensure

availability of budget for R&R activities; (iii) liaison with district administration for support for land

acquisition and implementation of R&R.

159. The PIU/PMU will appoint/depute one full-time Manager level official as the

Resettlement Officer (RO) for the entire duration of resettlement activities, with relevant

experience in land acquisition and resettlement issues. The PIU will maintain all data base and

work closely with DPs and other stakeholders. Based on regularly updated data, a central

database will also be maintained by PIU.

Page 76: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

73

160. The PIU/PMU officials and RO will require to enhance their capacities in R&R

implementation. The staff will undergo an orientation and training in resettlement management

at the beginning of the project. . The training activities will focus on issues concerning (i)

principles and procedures of land acquisition, (ii) public consultation and participation, (iii)

entitlements and compensation disbursement mechanisms, (iv) Grievance Redressal, and (v)

monitoring of resettlement operation. The training would specifically focus on the differences

between provisions of ADB policy and the relevant country laws. The awareness of these

differences and the need to follow the provisions of the ADB *Policy are critical for successful

implementation of the LARP.

161. The RO will work closely with the District Collector to expedite the payments of

compensation for land acquisition and assistance to DPs. The RO will be assisted by the

support staff for planning and implementation of resettlement activities in the subproject. Some

of the specific functions of the PIU with regard to resettlement management will include:

(a) Overall responsibility of implementation and monitoring of R&R activities in the Project;

(b) Ensure availability of budget for R&R activities; (c) Liaison lined agencies support implementation of R&R; (d) Coordinating with line Departments. (e) Translation of RP in local language; (f) Liaison with district administration for dovetailing government’s income

generating and developmental programs for the DPs; (g) Ensure the inclusion of those DPs who may have not been covered during the

census survey; (h) facilitate the opening of accounts in local banks to transfer assistance to DPs,

and organize the disbursement of Cheque for assistance in the affected area in public;

(i) Monitor physical and financial progress on land acquisition and R&R activities; (j) Participate in regular meetings in GRC; and (k) Organize monthly meetings to review the progress on R&R.

162. The roles and responsibilities of various agencies to be involved in resettlement planning

process and implementation of resettlement activities are summarized in following Table 24

Table 24: Agencies Responsible for Resettlement Implementation Key Agency Responsibility

EA (WRD) • Make final decision on pipelines alignment to be included under the project

• Overall responsibility for project design, feasibility, construction and operation and guide PIU

• Ensure that sufficient funds are available to properly implement all agreed social safeguards measures

• Ensure that all subprojects comply with the provisions of ADB’s SPS 2009 and GOI’s policies and regulations

• Submit semi-annual safeguards monitoring reports to ADB Project Implementation Units/PMU

• Disseminate project information to the project affected community with assistance from DPR Consultant

• Ensure establishment of Grievance Redress Committee at the

Page 77: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

74

Key Agency Responsibility district level for grievance redress with assistance from DPR Consultant

• Approve LAP prepared by DBO contractor

• Disclosure of project information in public spaces and through relevant media.

• Disseminate project information to the community in coordination with DPR Consultants

• Facilitate the socioeconomic survey and census • Facilitate consultation by the civil works contractor with community

throughout implementation • Oversee land acquisition and coordinate with Deputy Commissioner • Supervise the mitigation measures during implementation and its

progress • Conduct internal monitoring and prepare reports

DBO Contractor

• Recruit R&R staff and establish LA team/unit. The team leader should have experience in R&R preparation and implementation based on the Government of India and ADB requirement

• Undertake consultations involving community and DPs • Prepare due diligence report if no land acquisition • Prepare LAP in accordance to the LAF, and obtain approval of LAP

from PIU/PMU prior implementing payment to DPs • Encourage community/ DPs to voluntarily participate during the

implementation • Consult community and PIU regarding location of construction

camps and sign agreement with titleholder for temporary use of land and restore the land to equal or better condition upon completion

• Pay compensation for temporary acquisition for laying pipeline based on LAP

• Commence construction only when alignment is free of encumbrance

• Respond in a timely fashion to recommendations from GRCs District level officials • Provide any existing socioeconomic information, maps and other

related information to DPR Consultant prior to the field data/information collection activities.

• Act as the local focal point of information dissemination • Execute land acquisition process

Community Based Organizations

• Ensure the community participation at various stages of the project • Coordination with stakeholder organizations • Assist in Monitoring of the project

Village Level Committee

• Provide correct data and information from project formulation stage • Assist the project team in redressal of grievances and to implement

the project smoothly • Arrange proper community participation

ADB • Review RF and due diligence / RP and endorse or modify the project classification

• Review planning documents and disclose the draft and final reports on the ADB’s website as required

Page 78: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

75

Key Agency Responsibility

• Monitor implementation through review missions • Provide assistance to the EA and IA of subprojects, if required, in

carrying out its responsibilities and for building capacity for safeguard compliance

• Monitor overall compliance of the project to ADB SPS

D. Capacity Building on RP in the EA

163. Water Resources Department of Government of Madhya Pradesh is a fully owned

Department of the Ministry of Water Resources, Government of Madhya Pradesh. WRD has

required experience in planning and managing land acquisition and R&R activities. The WRD

has already established a PIU headed by Executive Engineer who will be acting as the Project

Director and will be supported by a Resettlement Officer (RO) for dealing with the land

acquisition and resettlement for the subproject.

164. All concerned staff both at head office and field level involved in land acquisition

activities will undergo an orientation and training in ADB resettlement policy and management.

Broadly, the training will cover various topics such as (i) Principles and procedures of land

acquisition; (ii) Public consultation and participation; (iii) Entitlements and Compensation &

assistance disbursement mechanisms; Grievance redress; and (iv) Monitoring of resettlement

operations. These will be covered through a formal workshop by the consultant under the

ongoing technical assistance program. The specific components under the training will cover the

following:

(a) Understanding of the ADB Policy Guidelines and requirements and differences

between country policy and laws

(b) Understanding of the policy and procedure adopted for the Subproject

(c) Understanding of the Implementation Schedule activities step-by-step

(d) Understanding of the Monitoring and reporting mechanism

(e) Understanding of the economic rehabilitation measures

Page 79: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

76

XII. IMPLEMENTATION SCHEDULE

A. Introduction

165. Implementation of LAP mainly consists of compensation to be paid for affected land,

structures and rehabilitation and resettlement activities. The time for implementation of LAP will

be scheduled as per the overall subproject implementation. All activities related to the land

acquisition and resettlement must be planned to ensure that compensation is paid prior to

displacement and commencement of civil works. The EAs and PIU will ensure that no physical

or economic displacement of displaced households will occur until: (i) compensation at full

replacement cost has been paid to each displaced person for project components or sections

that are ready to be constructed; (ii) other entitlements listed in the resettlement plan are

provided to the displaced persons; and (iii) a comprehensive income and livelihood rehabilitation

program, supported by adequate budget, if any, should be in place to help displaced persons,

improve, or at least restore, their incomes and livelihoods.

166. If the detailed design for pumping station, rising man, and distribution chamber will be

revised during detailed design, the updated LAP will need to be prepared by the DBO contractor

and submit for approval by Government and ADB. The updated LAP will be disclosed prior to

implementation. Public consultation, monitoring will be undertaken routinely throughout the

subproject duration. However, the schedule is subject to modification depending on the

progress of the subproject activities.

Page 80: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

77

SL No.

Activity 2019 2020

June July December January February March Project Preparation

1 Identifications of DPs

2 Conduct socioeconomic survey, census

3 Prepare social safeguard documents

4 ADB and Government approval of RPs

5 Appointment of Resettlement Officer

Land Acquisition for Non-Sample Projects

6 Land Acquisition

7 Payment of Compensation

8 Relocate houses, shops, businesses Rehabilitation of DPs

9 Income Restoration (if required)

10 Restoration of Community Resources Construction

11 Issue Notice for Start of Civil Work

12 Civil works Ongoing Activities

13 Grievance Redressing 14 Consultations with DPs 15 Internal Monitoring

16 External Monitoring (if required)

Page 81: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

78

XIII. MONITORING AND REPORTING

A. Need for Monitoring and Reporting

167. Monitoring and reporting are critical activities in resettlement management in order to

ameliorate problems faced by the DPs and develop solutions immediately. Monitoring is a

periodic assessment of planned activities providing ongoing inputs. It facilitates change and

gives necessary feedback of activities and the directions on which they are going. In other

words, monitoring apparatus is crucial mechanism for measuring subproject performance and

fulfillment of the subproject objectives.

B. Monitoring by PIU

168. One of the main roles of PIU will be to see proper and timely implementation of all

activities in LAP. Monitoring will be a regular activity for PIU and Resettlement Officer at this

level will see the timely implementation of R&R activities. PIU will prepare monthly reports on

the progress of LAP Implementation. PIU will collect information from the subproject site and

assimilate in the form of monthly report to assess the progress and results of LAP

implementation and adjust work program where necessary, in case of delays or any

implementation problems as identified. This monitoring will form parts of regular activity and

reporting on this will be extremely important in order to undertake mid-way corrective steps. The

monitoring by PIU will include:

(a) administrative monitoring: daily planning, implementation, feedback and trouble shooting, individual DP database maintenance, and progress reports;

(b) socio-economic monitoring: case studies, using baseline information for comparing DP socio-economic conditions, evacuation, demolition, salvaging materials, morbidity and mortality, community relationships, dates for consultations, and number of appeals placed; and

(c) Impact monitoring: Income standards restored/improved, and socioeconomic conditions of the displaced persons. Monitoring reports documenting progress on resettlement implementation and RP completion reports will be provided by the PIU for review and approval from ADB.

C. Monitoring Indicators

169. The most crucial components/indicators to be monitored are specific contents of the

activities and entitlement matrix. The LAP/RP contains indicators and benchmarks for

achievement of the objectives under the resettlement program. These indicators and

benchmarks are of three kinds:

(a) Process indicators including subproject inputs, expenditures, staff deployment,

etc. (b) Output indicators indicating results in terms of numbers of affected people

compensated and resettled, training held, credit disbursed, etc and (c) Impact indicators related to the longer-term effect of the subproject on people's

lives.

Page 82: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

79

D. Reporting Requirements

170. Land Acquisition and Resettlemet Plan implementation for the subproject will be closely

monitored by the EA which is Water Resources Department of GOMP. Keeping in view the

significance of resettlement impacts of the overall project, the monitoring mechanism for this

project will have monitoring by the Project Management Unit (PMU). PIU is responsible for

implementation of the Land Acquisition and Resettlement Plan. PIU will prepare monthly

progress reports on resettlement activities and submit to PMU. The Project Management Unit

(PMU) of WRD will submit semi-annual monitoring reports to ADB. All the LARP-monitoring

reports will be disclosed to DPs as per procedure followed for disclosure of resettlement

documents by the EA. The monitoring reports will also be disclosed on ADB’s website.

Page 83: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

80

Annexure 1 : Summary of Affected Persons and Common Property Resources

MAIN PIPE LINE – 1700 mm

S.No Survey Number

Farmer Name (Zone-3 DY1) Village Name

Area (Ha)

Aff Area

Fuit Trees

Orange Category

Other Trees

1 721

GOVT. LAND, SER ALAM, SERGUL KHAN, LIYAJ KHAN, IKBAL, SARAFRAJ KHAN, BABULAL, KHUB CHAND, BAGIRATHA, YAKUB KHAN, LIYAKAT KHAN

Molyakhedi

7.15, 0.153, 1.007, 1.007, 1.007, 1.007, 0.487, 0.488, 0.488, 0.993, 0.993 0.218

2 654 BADRILAL LAKSHMINARAYAN

Deharigujar 2.04 0.037

3 654 1.Ghanasyam F. Lakshminarayan, 2.Badrilal F. Lakshminarayan

Deharigujar 0.4, 1.64

0.017

4 652 Govt. Land Deharigujar 2.72 0.002

5 651 Radhesyam, Ghansyam, Atmaram, Govind F. Narayana

Deharigujar 1.04 0.026

6 650 Govt. Land Deharigujar 0.75 0.019

7 649 Govt. Land Deharigujar 0.05 0.005

8 648/1 Tolaram F. Ramratan Deharigujar 0.87 0.020 1 A

9 648/2 Bondarsingh F. Samandarsingh

Deharigujar 0.6 0.000

10 215

GANGA RAM, PREMNARAYANA, DHIRAPA SINGH, RAMCHARANA, BALAHABAPRASADA, RAJAKUMBARA BAI, DURGA LAL

Dharola

0.687, 0.687, 0.687, 0.687, 3.156, 1.045, 1.675

0.017

Page 84: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

81

11 215

GANGA RAM, PREMNARAYANA, DHIRAPA SINGH, RAMCHARANA, BALAHABAPRASADA, RAJAKUMBARA BAI, DURGA LAL

Dharola

0.687, 0.687, 0.687, 0.687, 3.156, 1.045, 1.675

0.051

12 640 Lakshminarayana F. Tholaram Deharigujar 1.21 0.022

13 620 Chhamabai H. Dayaram Deharigujar 0.35 0.000

14 619 1.Hokamsingh F. Banshilal 2.Badrilal F. Lala

Deharigujar 0.23, 0.15

0.019

15 618 Sharadabai H. Vallabh Deharigujar 0.36 0.024

16 617 Govt. Land Deharigujar 0.19 0.005

17 615 Govt. Land Deharigujar 0.23 0.005

18 548 1.Sitaram F. Gangaram, 2.Prahlad F. Gangaram

Deharigujar 0.17, 0.36

0.020

19 547 1.Madanlal F. Bheru, 2.Bahadarsingh F. Nanuram

Deharigujar 0.19, 0.38

0.010

20 190 NANU RAM Dharola 1.442 0.019

21 191 DURGA LAL Dharola 0.355 0.009

22 192 GOBARDHANA, HAKAMASINGH, MADANA

Dharola 0.14, 0.215, 0.345

0.031

23 193 SHITA BAI Dharola 0.575 0.005

24 194 MUTHARA LAL, SAGITA BAI, RODU LAL

Dharola 0.326, 0.364, 0.774

0.032

25 182 GOVT. LAND Dharola 0.512 0.024

26 179 GIRI RAJA, KALU RAM Dharola 0.157, 0.564

0.017

27 178 SURESH CHANDRA Dharola 1.494 0.031

28 177 SHITA BAI Dharola 1.212 0.017

29 177 SHITA BAI Dharola 1.212 0.009

30 176 SHITA BAI Dharola 0.961 0.017

31 174 SHANTI BAI, GIRI RAJ BADRILAL

Dharola 0.219, 0.438

0.001

32 175 RODU LAL RATAN LAL Dharola 0.314 0.026 2 B

33 770 GIRI RAJ BHAWAR LAL, SHANTI BAI

Dharola 0.408, 0.710

0.034 3 B

34 141 BABU LAL BHAWAR LAL, RODU LAL RATAN LAL

Dharola 0.428, 0.418

0.017 2 B

35 771 BALLABH PRASAD GIRI RAJ, GORDHAN KALURAM

Dharola 0.428, 0.428

0.039

Page 85: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

82

36 776 GOVT. LAND Dharola 0 0.019

37 775 1.Govt. Land, 2.Dariyavbai H. Bhanwarlal

Dharola 0, 0.084 0.007

38 780 Nanuram F. Gangaram Dharola 0.669 0.013

39 781 Govt. Land Dharola 0 0.007

40 782 Govt. Land Dharola 0.188 0.002

41 742 1.Nanuram F. Gangaram, 2.Babulal, Giriraj F. Jagadhish

Dharola 0.115, 0.405

0.024

42 869 Govt. Land Dharola 0.031 0.007

43 867 Govt. Land Dharola 0 0.024

44 866 Bhanwarbai H. Kesharsingh Dharola 0.94 0.007

45 883 Mahendrasingh F. Bhagawansingh

Dharola 0.073 0.007 4 A

46 882

1.Govt. Land, 2.Ranjithsingh, Harisingh, Suratsingh, Gokalsingh F. Karansingh

Dharola 0.031, 0.01

0.003

47 865 Mahendrasingh F. Bhagawansingh

Dharola 0.909 0.014

48 885 Chattarsingh F. Chandarsingh Dharola 0.763 0.029

49 885 Chattarsingh F. Chandarsingh Dharola 0.763 0.005

50 889 Govt. Land Dharola 0.261 0.003

51 892 Govt. Land Dharola 0 0.010

52 893 Govt. Land Dharola 0 0.002

53 891 1.Sharada H. Shivlal, 2.Pannalal F. Ghisa

Dharola 0.23, 0.199

0.005 2,6 C,A

54 890 Govt. Land Dharola 0.261 0.003

55 904 Dinesh F. Balchand Dharola 0.115 0.003

56 905 Govt. Land Dharola 0.418 0.005

57 906 Govt. Land Dharola 0.188 0.006

58 907 Shantibai H. Pirulal Dharola 0.774 0.022

59 908 Pannalal F. Ghisa Dharola 1.264 0.034

60 1000 1.Purabai H. Badrilal, 2.Lalithabai H. Banshilal

Dharola 0.868, 0.867

0.031 2,2 B,C

61 999 Govt. Land Dharola 0.449 0.007

62 991 Balu, Tulsiram F. Mangu Dharola 0.125 0.005

63 990 Siddnath, Ramprasad F. Devisingh

Dharola 0.105 0.009

64 970 1.Kedar F. Bhagchand, 2.Nandram, Radhesyam F. Badrilal

Dharola 0.052, 0.355

0.030

65 969 Govt. Land Dharola 0.46 0.015

66 958 Pannalal F. Shivlal Dharola 0.031 0.003

Page 86: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

83

67 959 Rameswar, Ramkaran, Vishnulal, Badrilal F. Bapulal

Dharola 0.533 0.020

68 952 1.Siddnath, Ramprasad F. Devisingh, 2.Sundarlal F. Dhulichand

Dharola 0.084, 0.125

0.009

69 1142 Govt. Land Dharola 0.167 0.007

70 1132 Govt. Land Dharola 0.282 0.005

71 1143 1.Mohanlal F. Ramchandra, 2.Govt. Land

Dharola 0.24, 0.355

0.002

72 1144 Govt. Land Dharola 0.261 0.004

73 1161 1.Sithabai H. Gopilal, 2.Govt. Land

Dharola 1.045, 0.575

0.034

74 1131 Govt. Land Dharola 0.219 0.003

75 1130 Govt. Land Dharola 0.993 0.029

76 1126 Siddhu F. Chitha Dharola 0.094 0.003

77 1238 1.Shankarlal F. Narsingh, 2.Kamal F. Ukarlal

Dharola 1.045, 0.24

0.015

78 1234 1.Mohanlal F. Ramchandra, 2.Satyanarayana F. Ramchandra

Dharola 0.504, 0.505

0.017

79 1235 1.Govt. Land, 2.Trilokchand F. Siddardh

Dharola 0, 0.8 0.026

80 1235 1.Govt. Land, 2.Trilokchand F. Siddardh

Dharola 0, 0.8 0.005

81 1236 1.Balu F. Amara, 2.Mohanlal F. Dhannalal

Dharola 1.672, 0.470

0.061 12 A

82 1233 1.Govt. Land, 2.Jagannath F. Bapulal

Dharola 0.69, 2 0.005

83 1252 Govt. Land Dharola 0.449 0.003

84 1253 1.Govt. Land, 2.Badrilal F. Manna

Dharola 1.923, 1.045

0.043

85 1263 Sri Ram Mandir Dharola 1.411 0.031

86 1264 Rameswar F. Kanwarlal Dharola 1.902 0.038 9 B

87 1547 Kousalyabai H. Rameswar Dharola 0.585 0.015

88 1546 Kousalyabai H. Rameswar Dharola 0.282 0.015

89 1545 Badrilal F. Gordhanlal Dharola 0.272 0.010

90 1544 Bherulal F. Badrilal Dharola 0.272 0.015

91 1537 Bherulal F. Badrilal Dharola 0.554 0.017

92 1519 1.Gopal, Babulal F. Banshilal, 2.Mohanlal F. Dhannalal

Dharola 0.763, 0.575

0.032

93 1693 Githabai H. Banshilal Dharola 0.345 0.027

94 1690 1.Githabai H. Banshilal, 2.Yuvrajsingh F. Lalsingh

Dharola 0.364, 0.282

0.027 6 A

Page 87: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

84

95 1704 1.Yuvrajsingh F. Lalsingh, 2.Narayansingh F. Banesingh

Dharola 0.464, 0.581

0.031 6 A

96 1686 Govt. Land Dharola 0.92 0.003

97 1730 1.Rameswar, Syam, Omkarlal F. Rajaram, 2.Gangabai H. Mohanlal

Dharola 0.588, 0.144

0.063

98 1731 1.Sangitha Bai H. Dineshkumar, 2.Govindsingh F. Banesingh

Dharola 0.47, 0.4

0.041 6 A

99 1732 1.Syamlal F. Mathuralal, 2.Munnibai H. Chothmal

Dharola 0.105, 0.344

0.019 3 C

100 1656 1.Syamlal F. Mathuralal, 2.Dilip F. Syamlal

Dharola 0.671, 0.024

0.003 4 B

Page 88: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

85

Annexure 2 : Summary of Affected Persons and Common Property Resources

MAIN PIPE LINE – 1600 mm

S.No Survey Number

Farmer Name (Zone-3 DY1) Village Name

Area (Ha)

Aff Area

Fruit Trees

Orange Category

Other Trees

1 1656 1.Syamlal F. Mathuralal, 2.Dilip F. Syamlal

Dharola 0.671, 0.024

0.031

2 1659 Dilip F. Syamlal Dharola 0.69 0.026

3 1660 Chothmal F. Mathuralal Dharola 0.721 0.021 8 A

4 1661 1.Munnibai H. Chothmal, 2.Govt. Land

Dharola 0.355, 0.637

0.018

5 1651 1.Syamlal F. Mathuralal, 2.Rodmal F. Mathuralal

Dharola 0.209, 0.679

0.026 6 A

6 1650 GOVT. LAND Dharola 2.142 0.019

7 1650 GOVT. LAND Dharola 2.142 0.043

8 1835 GOVT. LAND Dharola 0.23 0.042

9 1834

BHABAR LAL, AMRA, SIBANARAYANA, RODU, KALU, HINDU, BADRI LAL, GANGARAM, LALU

Dharola

0.627, 0.053, 0.617, 0.627, 0.418, 0.627, 0.617, 0.627, 0.418

0.016

10 1834

BHABAR LAL, AMRA, SIBANARAYANA, RODU, KALU, HINDU, BADRI LAL, GANGARAM, LALU

Dharola

0.627, 0.053, 0.617, 0.627, 0.418, 0.627, 0.617, 0.627, 0.418

0.037

11 1857 GOVT. LAND Dharola 0.094 0.008

12 1645 GOVT. LAND Dharola 18.709 0.046

Page 89: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

86

13 219 RAMA NARAYANA, SITA RAMA, RADHESYAMA, RAMA PRASAD

Padana

0.209, 0.08, 0.11, 0.019

0.028

14 221 KAMALESH Padana 2.067 0.022

15 221 KAMALESH Padana 2.067 0.021

16 226 SRI MAHA DEV Padana 0.993 0.040

17 225 CHANDRA, KALU, RAMEH CHANDRA

Padana 0.518, 0.411, 0.419

0.051 1 A

18 225 CHANDRA, KALU, RAMEH CHANDRA

Padana 0.518, 0.411, 0.419

0.005

19 223 GOVT. LAND Padana 0 0.026

20 254 KAMALESH Padana 1.055 0.038

21 258 GOVT. LAND Padana 0.46 0.022

22 518

MAHESH, KALU RAMA, NANDA RAMA, LALA SINGH, BHABARA LAL, CHANDRA SINGH

Padana 0.073, 0.627,

0.016 4 B

23 517 MAHESH Padana 0.105 0.006

Page 90: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

87

Annexure 3 : Summary of Affected Persons and Common Property Resources

MAIN PIPE LINE – 1500 mm

S.No Survey Number

Farmer Name (Zone-3 DY1) Village Name

Area (Ha)

Aff Area

Fruit Trees

Orange Category

Other Trees

1 517 MAHESH Padana 0.105 0.006

2 516 SIBA LAL Padana 0.293 0.012

3 513 RAMA CHANDA Padana 0.941 0.053

4 504 RAMCHAND F. KANIRAM Padana 0.314 0.000

5 513 Ramchand F. Kaniram Padana 0.941 0.000 9 A

6 504 Ramchand F. Kaniram Padana 0.314 0.018 2 A 1

7 505 Govt. Land Padana 0.282 0.006

8 505 Govt. Land Padana 0.282 0.019

9 499 Ramlal F. Shivsingh Padana 0.324 0.026

10 489 Ramchandra F. Kaniram Padana 0.209 0.009 5 B

11 455 1.Bherusingh F. Motilal, 2.Ramsingh F. Motilal

Padana 0.084 0.007

12 487 Jasodabai, Leelabai, Bhulibai, Syamubai, Rukmabai F. Banwarlal

Padana 0.282 0.007 4 B

13 487 Jasodabai, Leelabai, Bhulibai, Syamubai, Rukmabai F. Banwarlal

Padana 0.282 0.008

14 483 Siddnath F. Mangilal Padana 0.11 0.012

15 479 1.Govt. Land 2.Sanjay F. Badrilal

Padana 0,

0.079 0.013

16 477 1.Siddnath F. Mangilal, 2.Govt. Land

Padana 0.094,

0 0.009

17 476 Balusingh F. Parbatsingh Padana 0.219 0.004

18 475 1.Andarsingh F. Bhuwan, 2.Karansingh F. Indarsingh

Padana 0.115, 0.115

0.004

19 473 1.Dheerajsingh, Kishan F. Udhesingh, 2.Bherusingh F. Motilal

Padana 0.178, 0.094

0.003

Page 91: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

88

20 473 1.Dheerajsingh, Kishan F. Udhesingh, 2.Bherusingh F. Motilal

Padana 0.178, 0.094

0.008

21 471 1.Pursingh F. Karansingh, 2.Mathurabai H. Gokulsingh

Padana 0.102, 0.204

0.015

22 469 Govt. Land Padana 0.009

23 460 1.Gangaram F. Bhagawansingh, 2.Ramlal F. Mangilal

Padana 0.011, 0.021

0.000

24 459 Mangilal F. Dhula Padana 0.219 0.012 8 A

25 463 Govt. Land Padana 0.073 0.011

26 462 Govt. Land Padana 0 0.001

27 464 1.Tejsingh F. Antharsingh, 2.Devisingh F. Bherusingh

Padana 0.113, 0.185

0.007

28 607 Govt. Land Padana 0.836 0.009

29 608 Govt. Land Padana 0.293 0.002

30 605 Durgesh F. Devilal Padana 0.835 0.041

31 620 1.Govt. Land 2.Ayodyabai H. Pannalal

Padana 0,

0.157 0.018

32 622 Ayodyabai H. Pannalal Padana 0.502 0.015

33 623 Niranjan F. Kanhaiyalal Padana 0.627 0.008

34 1069 1.Ayodyabai H. Pannalal, 2.Bardibai H. Ramsingh

Padana 1.881 0.006

35 1069 1.Ayodyabai H. Pannalal, 2.Bardibai H. Ramsingh

Padana 1.881 0.066

36 1006 1.Seethabai, Banshilal 2.Parbatsingh F. Omkarsingh

Padana 0.094, 0.063

0.011

37 1007 Seethabai, Banshilal Padana 0.732 0.030

38 1003

1.Devisingh, Gokulsingh F. Bherulal, 2.Dheerajsingh, Kishan F. Udhesingh

Padana 0.46, 0.356

0.060

Page 92: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

89

Annexure 3 : Summary of Affected Persons and Common Property Resources

MAIN PIPE LINE – 1400 mm

S.No Survey Number

Farmer Name (Zone-3 DY1) Village Name

Area (Ha)

Aff Area

Fruit Trees

Orange Category

Other Trees

1 1003

1.Devisingh, Gokulsingh F. Bherulal, 2.Dheerajsingh, Kishan F. Udhesingh

Padana 0.46, 0.356

0.034

2 1001 Tejbai H. Ramnarayana Padana 0.763 0.018

3 1000 1.Balusingh F. Parbatsingh, 2.Pursingh F. Karansingh

Padana 1.091, 0.545

0.000

Page 93: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

90

Annexure 4 : Summary of Affected Persons and Common Property Resources

MAIN PIPE LINE – 1300 mm

S.No Survey Number

Farmer Name (Zone-3 DY1) Village Name

Area (Ha)

Aff Area

Fruit Trees

Orange Category

Other Trees

1 1000 1.Balusingh F. Parbatsingh, 2.Pursingh F. Karansingh

Padana 1.091, 0.545

0.046

2 999 Pursingh F. Karansingh Padana 0.432 0.014

3 969 1.Mangilal, Balusingh F. Amara 2.Narayana F. Raysingh

Padana 0.972, 0.941

0.068

4 968 Govt. Land Padana 0.105 0.002

5 950 1.Mangilal F. Dhula, 2.Antarsingh F. Mangilal

Padana 1.212, 0.095

0.051

6 950 1.Mangilal F. Dhula, 2.Antarsingh F. Mangilal

Padana 1.212, 0.095

0.010

7 946 1.Mangilal, Balchand F. Kalu, 2.Fathesingh, Abhaysingh F. Dhariyav

Padana 0.282, 0.282

0.008

8 932 1.Dayaram F. Nanda 2.Ramlal F. Devisingh

Padana 0.874, 0.251

0.068 4 B

9 932 1.Dayaram F. Nanda 2.Ramlal F. Devisingh

Padana 0.874, 0.251

0.018 1 B

10 940 1.Madhusudhan F. Ramchand, 2.Asharam F. Kalu

Padana 1.066, 0.324

0.014

11 945 Govt. Land Padana 0.261 0.003

12 944 1.Asharam F. Kalu, 2.Kanhaiyalal F. Nandram

Padana 0.094, 0.836

0.029

13 943 Govt. Land Padana 2.424 0.026

Page 94: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

91

Annexure 5 : Summary of Affected Persons and Common Property Resources

MAIN PIPE LINE – 900 mm

S.No Survey Number

Farmer Name (Zone-3 DY1) Village Name

Area (Ha)

Aff Area

Fruit Trees

Orange Category

Other Trees

1 654 BADRILAL LAKSHMINARAYAN

Deharigujar 2.04 0.005

2 651 RADHESHYAM DHANSHYAM NARAYAN

Deharigujar 1.04 0.011

3 219 BISHUNU DASH, RADU Dharola 0.865, 1.135 0.014

4 220 KALU RAM, BHAGIRATHA Dharola 0.667, 0.667 0.042

5 221 CHANDARA SINGH, PRAVULAL, BANESINGH, RAMCHARANA

Dharola

1.861, 1.861, 0.93, 0.93 0.005

6 222 GOVT. LAND Dharola 0.251 0.002

7 223 CHANDARA SINGH Dharola 1.274 0.012

8 224 PREMCHAND, RADU, GORILAL, RAMA PRASADA, PRABALA KUMARA, ISWARA

Dharola

3.344, 1.077, 5.333, 0.941, 1.306, 2.019 0.018

9 211 GOVT. LAND Dharola 0.031 0.009

10 210 BABU, SHIDDHI BAI Dharola 2,

1.492 0.063

11 210 BABU, SHIDDHI BAI Dharola 2,

1.492 0.068

12 237 RADU, PREMA CHANDRA, GORI LAL, PURA LAL, NARMADA BAI

Dharola

0.282, 0.094, 2.33,

0.784, 2.09 0.028

Page 95: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

92

13 237 RADU, PREMA CHANDRA, GORI LAL, PURA LAL, NARMADA BAI

Dharola

0.282, 0.094, 2.33,

0.784, 2.09 0.035

14 246 RODU Dharola 0.366 0.021

15 293 GOVT. LAND Dharola 0.721 0.001

16 279 SANGITA BAI Dharola 0.46 0.001

17 278 SANGITA BAI Dharola 0.554 0.007

18 278 SANGITA BAI Dharola 0.554 0.001

19 317 GIRI RAJA Dharola 0.24 0.005

20 321 GIRI RAJA Dharola 0.324 0.002

21 322 GHISHA LAL, DINESHA Dharola 1.704, 0.941 0.022

22 363 DHAPU BAI, GOPALA Dharola 0.063, 0.303 0.005

23 362 DHAPU BAI Dharola 0.752 0.012

24 361 GHANASYAMA Dharola 0.721 0.012

25 360 BABU LAL Dharola 0.105 0.005

26 359 DEVI SINGH Dharola 0.836 0.005

27 379 BABU LAL, DEVI SINGH, KALU RAM

Dharola 0.167, 0.157, 0.021 0.001

28 379 BABU LAL, DEVI SINGH, KALU RAM

Dharola 0.167, 0.157, 0.021 0.006

29 398 GOVT. LAND Dharola 0.784 0.002

30 407 SURESHA KUMAR, UMILI BAI, DEVI SINGH, BISHNU

Dharola

1.912, 0.7,

0.956, 0.956 0.032

31 408 GHANASYAMA Dharola 0.773 0.059

32 2778 GOVT. LAND Dharola 5.351 0.023

33 2779 GOVT. LAND Dharola 0.073 0.002

34 2791 RODU, VERU, MOHAN Dharola 2,

0.836, 0.418 0.041

35 2792 GOVT. LAND Dharola 0.105 0.002

36 2796 GOVT. LAND Dharola 3.396 0.029

37 2793 MOHAN Dharola 1.359 0.000

38 2799 MOHAN Dharola 1.359 0.023

39 2801 RAM KARAN GANGARAM, BHAGIRATH GANGARAM

Dharola 1.583, 1.583 0.037

Page 96: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

93

40 2802 RAMKARAN, BALU, DEBA, GIRDHARI, RAMESH CHANDRA, BALDEB

Dharola

0.436, 0.436, 0.873, 0.872, 0.982, 0.508 0.004

41 2803 GOVT. LAND Dharola 0.261 0.004

42 2804 BAGIRATHA, AMRA, RODU, SANKAR, DEBA

Dharola

1.15, 0.765, 0.765, 0.766, 0.766 0.032

43 504 RAMCHAND F. KANIRAM Padana 0.314 0.005 3 B

44 509 RAMCHAND F. KANIRAM Padana 0.178 0.009

45 508 1.RAMCHAND F. KANIRAM 2.KANHAIYALAL F. MATHURALAL

Padana 1.641, 0.418

0.023 4 A

46 493 1.KANHAIYALAL F. MATHURALAL 2.RAMLAL F. SHIVSINGH

Padana 0.14, 0.299

0.009 1 A

47 592 GOVT. LAND Padana 0.199 0.003

48 594 KARANA SINGH Padana 0.92 0.015

49 600 GOKULA SINGH, RAMA SINGH, BABU SINGH, CHANDRA SINGH

Padana

0.06, 0.06, 0.06, 0.06, 0.06

0.009

50 1115

1.JAMALSINGH, GOKULSINGH, BANESINGH 2.BALU, RUGNATH, SIDDU, KALU

Padana 2.055, 1.17

0.045

Page 97: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

94

Annexure 6 : Summary of Affected Persons and Common Property Resources

MAIN PIPE LINE – 800 mm

S.No Survey Number

Farmer Name (Zone-3 DY1) Village Name

Area (Ha) Aff Area

Fruit Trees

Orange Category

Other Trees

1 2804 BAGIRATHA, AMRA, RODU, SANKAR, DEBA

Dharola 1.15, 0.765,

0.765, 0.766, 0.766 0.016

2 2614 JANAKILAL, RODMAL, GIRIRAJ, NARAYANA, KISAN LAL, SAMBHU LAL

Dharola 1.812, 1.275, 1.625, 0.93, 0.841, 0.841 0.028

3 486 JANAKILAL KANHAEIYALAL Pheti 1.87 0.030

4 493 BIKRAM BHAWARLAL, RADHESHYAM NATHULAL

Pheti 2.2 0.015

5 494 DEVISINGH NATHULAL, BHEIRULAL BHAWARLAL, RADHESHYAM NATHULAL

Pheti 2.26

0.015

6 509

SHIBANARAYAN SIDHANATH, NANADKISHORE SIDHANATH, BADRILAL KUWARLAL

Pheti 1.25

0.019

7 508

SHIBANARAYAN SIDHANATH, NANADKISHORE SIDHANATH, BADRILAL KUWARLAL

Pheti 1.59

0.035

8 506 MANGILAL NARAYAN Pheti 0.34 0.008

9 505 PRABHULAL NARAYAN, MAGILAL NARAYAN

Pheti 1.67 0.009

10 505 PRABHULAL NARAYAN, MAGILAL NARAYAN

Pheti 1.67 0.008

11 500 DILLIPKUMAR TARACHANDRA

Pheti 1.1 0.017 1

12 501 MANGILAL KANHAEIYALAL, MANJUDEVI ABHAYAKUMAR

Pheti 2.09 0.008

13 557 MANGILAL BASANTILAL, MANJUDEVI ABHAYAKUMAR

Pheti 1.04 0.002

Page 98: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

95

14 557 MANGILAL BASANTILAL, MANJUDEVI ABHAYAKUMAR

Pheti 1.04 0.007

15 556 RAMAKUWARBAI RAMSINGH

Pheti 0.41 0.018

16 558 MANGILAL RAMACHANDRA, AMBARAM KANHAEIYALAL

Pheti 0.4 0.004

17 546 HARILAL GYARSILAL Pheti 0.56 0.008

18 692

DIPAK ISWAR SURESH SONABAI, RAMPRASAD GOPILAL, KANHAEIYALAL KALU

Pheti 2.3

0.024

19 689 RAMKUWARBAI RAMSINGH Pheti 0.3 0.004

20 688 KISHANLAL KANIRAM Pheti 0.3 0.014

21 687 DUGESH SHIBALAL Pheti 0.3 0.004

22 686 GOVT. LAND Pheti 0.3 0.004

23 684 DAKHABAI DIPCHAND Pheti 3.65 0.030

24 681 ABHAYAKUMAR TARACHAND

Pheti 1.94 0.006

25 681 ABHAYAKUMAR TARACHAND

Pheti 1.94 0.002

26 229/3 1.Dinesh F. Ramchandra, 2.Mangilal F. Motilal

Dokapura 0.331, 0.209 0.016

27 229/4 Rugnath F. Ramchandra Dokapura 0.993 0.014

28 229/4 Rugnath F. Ramchandra Dokapura 0.993 0.010

29 231/2 Govt. Land Dokapura 0.627 0.002

30 228 1.Govt. Land, 2.Krushi Upamandi Nalkheda

Dokapura 2.948, 6.8 0.011

31 259/1 Prakashchand F. Soubhagmal

Dokapura 1.996 0.023

32 259/1 Prakashchand F. Soubhagmal

Dokapura 1.996 0.003

33 256/3 Prakashchand F. Soubhagmal

Dokapura 0.214 0.006

34 256/2 Not Available Dokapura 0.597 0.008

35 256/5 Neha Karthika F. Vittal Das Dokapura 0.281 0.006

36 256/1 Anshul F. Vittal Das Dokapura 0.314 0.000

37 246/1 Kasthurchand F. Khuba Dokapura 0.836 0.007

38 246/1 Kasthurchand F. Khuba Dokapura 0.836 0.006

39 248 Jagadhish, Bhagawansingh, Radhesyam F. Kunwarlal

Dokapura 1.233

0.019

40 247 1.Mangilal, Leelabai, Sanjubai F. Puralal 2.Abdul Alim F. Mushi Khan

Dokapura 0.293, 0.627

0.005

Page 99: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

96

41 1115

1.JAMALSINGH, GOKULSINGH, BANESINGH 2.BALU, RUGNATH, SIDDU, KALU

Padana 2.055, 1.17 0.015

42 1117 GOVT. LAND Padana 0.261 0.002

43 1118

BANESINGH HAJARILAL, DULESINGH GHANSI, KAILASH AMARSINGH, GIRDHARILAL DHANNA

Padana 0.209, 0.836, 0.251, 0.251

0.053

44 1118

BANESINGH HAJARILAL, DULESINGH GHANSI, KAILASH AMARSINGH, GIRDHARILAL DHANNA

Padana 0.209, 0.836, 0.251, 0.251

0.030

45 160 Mukesh F. Rajaram Gudrawan 0.58 0.014

46 159/1 Shantibai Gudrawan 0.34 0.002

47 159/2 Rugnath F. Deepa Gudrawan 0.45 0.002

48 152/2 Mangilal, Ramlal, Girdhari, Rajaram F. Bhagawansingh

Gudrawan 0.105 0.016 2 A

49 152/1 Jamalsingh, Banesingh, Gokulsingh F. Hajarilal

Gudrawan 0.43 0.008

50 43 Balu F. Deepa Gudrawan 0.4 0.000

51 151 Kevalsingh F. Gokalsingh Gudrawan 0.32 0.016

52 44 Bhimsingh F. Motisingh Gudrawan 1 0.004

53 49 1.Rampyari F. Banshilal, 2.Sampath Bai H. Kamalsingh

Gudrawan 1.52, 1.52 0.016

54 49 1.Rampyari F. Banshilal, 2.Sampath Bai H. Kamalsingh

Gudrawan 1.52, 1.52 0.006

55 50/3 Narbadhabai H. Harinarayana

Gudrawan 1.21 0.012

56 50/2 Narbadhabai H. Harinarayana

Gudrawan 1.21 0.008

57 51 1.Kanhaiyalal F. Gangaram, 2.Ramchandra F. Gangaram

Gudrawan 0.24, 0.24 0.012

58 98 1.Gopal F. Radhesyam 2.Kamal F. Radhesyam

Gudrawan 0.14, 0.38 0.010

59 111 1.Ramprasad F. Lala 2.Suresh F. Durgalal

Gudrawan 0.35, 0.13 0.001

60 99 Jayantibai H. Hiralal Gudrawan 0.18 0.005

61 110 Jayantibai H. Hiralal Gudrawan 1.42 0.000

62 109/1 Jayantibai H. Hiralal Gudrawan 1.01 0.006

63 109/2 Hamsabai H. Manishkumar Gudrawan 0.94 0.004 5 B

Page 100: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

97

64 109/2 Hamsabai H. Manishkumar Gudrawan 0.94 0.004

65 108/1 Devisingh F. Hiralal Gudrawan 1.1 0.013

66 335 Govt. Land Gudrawan 2.29 0.003

67 352 Jayantibai H. Hiralal Gudrawan 1.19 0.020

68 349 Govt. Land Gudrawan 0.31 0.002

69 350 Premchand F. Mathuralal Gudrawan 0.5 0.002

70 350 Premchand F. Mathuralal Gudrawan 0.5 0.006 1 B

71 391 Premchand F. Mathuralal Gudrawan 0.6 0.010

72 390 Omprakash F. Mathuralal Gudrawan 0.61 0.014

Page 101: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

98

Annexure 7 : Summary of Affected Persons and Common Property Resources

MAIN PIPE LINE – 700 mm

S.No Survey Number

Farmer Name (Zone-3 DY1) Village Name

Area (Ha)

Aff Area

Fruit Trees

Orange Category

Other Trees

1 247 1.Mangilal, Leelabai, Sanjubai F. Puralal 2.Abdul Alim F. Mushi Khan

Dokapura 0.293, 0.627

0.006

2 250 1.Amanabi H. Ajij Khan 2.Mangilal, Leelabai, Sanjubai F. Puralal

Dokapura 0.209, 0.543

0.002

3 590 Abdul Rashid, Abdul Vahid F. Abdul Hafij

Dokapura 1.045 0.004

4 589 1.Hemalatha Bai H. Mukesh, 2.Deva Ji F. Nathu

Dokapura 0.034, 0.009 0.016

5 589 1.Hemalatha Bai H. Mukesh, 2.Deva Ji F. Nathu

Dokapura 0.034, 0.009 0.008

6 588

1.Abdul Rahim, Abdul Jalil, Abdul Vakil F. Shakur Khan 2.Govt. Land

Dokapura 0.679, 0.272

0.013

7 586

1.Abdul Rahim, Abdul Jalil, Abdul Vakil F. Shakur Khan 2.Mahendrakumar, Chatar F. Kanhaiyalal

Dokapura 0.575, 0.944

0.008

8 585 1.Abdul Mukim F. Abdul Hakim, 2.Rustham Khan F. Mamraj Khan

Dokapura 0.554, 0.554

0.001

9 585 1.Abdul Mukim F. Abdul Hakim, 2.Rustham Khan F. Mamraj Khan

Dokapura 0.554, 0.554

0.011

10 574 Vishnuprasad Brujamohan Krishnavallabh F. Radha Krishna

Dokapura 0.355

0.001

11 578 GOVT. LAND Dokapura 0 0.001

12 577 GOVT. LAND Dokapura 0 0.001

13 577 GOVT. LAND Dokapura 0 0.001

14 579 GOVT. LAND Dokapura 0 0.007

15 481 GOVT. LAND Dokapura 0.334 0.000

16 580 PIR KHAN Dokapura 0.042 0.001

Page 102: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

99

17 508 GOVT. LAND Dokapura 1.275 0.001

18 509 GOVT. LAND Dokapura 0.366 0.004

19 518 SONERAB Dokapura 0.084 0.001

20 518 SONERAB Dokapura 0.084 0.006

21 526 MUBARIK KHAN, RAGHUNATHA RAB

Dokapura 0.739 0.005

22 1327 Saroja Devi H. Chintaman Nalkheda 0.073 0.002

23 1329 Saroja Devi H. Chintaman Nalkheda 0.188 0.002

24 1328 Saroja Devi H. Chintaman Nalkheda 0.178 0.008

25 1330 Ragunath Rao, Ashok Rao F. Balvanth Rao

Nalkheda 0.105 0.004

26 1325 Anshul F. Ragunath Rao Nalkheda 0.345 0.006

27 1325 Anshul F. Ragunath Rao Nalkheda 0.345 0.003 4 A

28 1313 Not Available Nalkheda 0.001

29 1266 Govt. Land Nalkheda 0 0.003

30 1265 Govt. Land Nalkheda 0 0.001

31 1264 Shabbir Khan F. Shakur Khan Nalkheda 0.387 0.006

32 1262 Shabbir Khan F. Shakur Khan Nalkheda 0.272 0.002

33 1261 1.Sardar Khan F. Noor Khan, 2.Aarif Khan F. Kamluddin Khan

Nalkheda 0.146, 0.157 0.006

34 1229 Jarinabai H. Jamaluddin Nalkheda 0.449 0.004

35 1230 Govt. Land Nalkheda 0 0.004

36 1250 Hasinabai H. Kamaluddin Nalkheda 0.303 0.001

37 1234 Jarinabai H. Jamaluddin Nalkheda 0.606 0.009

38 1239 Govt. Land Nalkheda 0.261 0.002

39 1023 Sardarbai H. Bhanwarlal Nalkheda 0.491 0.005

40 1023 Sardarbai H. Bhanwarlal Nalkheda 0.491 0.006

41 1022 Tilokchand, Syamlal F. Prabhulal

Nalkheda 0.439 0.015

42 729 Tilokchand, Syamlal F. Prabhulal

Nalkheda 0.031 0.002

43 728 Tilokchand, Syamlal F. Prabhulal

Nalkheda 0.052 0.002

44 726 Govt. Land Nalkheda 0 0.001

45 727 Abdul Jalil, Abdul Hanif F. Abdul Rashid

Nalkheda 0.439 0.000

46 727 Abdul Jalil, Abdul Hanif F. Abdul Rashid

Nalkheda 0.439 0.008

47 746 Kesharbai H. Bhanwarlal Nalkheda 0.334 0.010

48 747 Trilokchand F. Prabhulal Nalkheda 0.282 0.002

49 756 Bhanwaribai H. Prabhulal Nalkheda 0.356 0.001 3 B

50 757 Govt. Land Nalkheda 0.021 0.001

51 758 Govt. Land Nalkheda 0 0.001

Page 103: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

100

52 764 Govt. Land Nalkheda 0.042 0.002

53 765 Not Available Nalkheda 0 0.002

54 766 Not Available Nalkheda 0 0.008

55 390 Omprakash F. Mathuralal Gudrawan 0.61 0.004

56 561 Badrilal F. Harilal Gudrawan 0.6 0.009

57 554 Dholathram F. Ramlal Gudrawan 0.27 0.009

58 534 Sureshkumar F. Hiralal Gudrawan 0.22 0.009

59 531 Jagannath F. Rugnath Gudrawan 0.11 0.001

60 530 Kousalyabai H. Govardhanlal Gudrawan 0.11 0.001

61 473 Mohanlal F. Devisingh Gudrawan 0.82 0.014

62 640 Paramanand F. Bhuvaniram Gudrawan 0.69 0.001

63 640 Paramanand F. Bhuvaniram Gudrawan 0.69 0.010

64 663 Sitharam F. Ramlal Gudrawan 0.42 0.001

65 662 Narbadhabai H. Harinarayana Gudrawan 0.5 0.011

66 667 Shivnarayana F. Keshoram Gudrawan 0.68 0.007

67 666 Govind F. Rameswar Gudrawan 0.49 0.011

68 693 Tilokchand F. Dholathram Gudrawan 1.76 0.029

69 693 Tilokchand F. Dholathram Gudrawan 1.76 0.005

70 692 Tilokchand F. Dholathram Gudrawan 0.5 0.000

71 694 1.Tilokchand F. Dholathram, 2.Rameswar F. Keshoram

Gudrawan 1.4, 1 0.029

72 734 Govardhanlal F. Ramkaran Gudrawan 0.76 0.007

73 733 Govardhanlal F. Gopal Gudrawan 0.82 0.011 6 A

74 732 Ghansyam F. Ramprasad Gudrawan 0.24 0.006

75 731 1.Ghansyam F. Ramprasad, 2.Gopal F. Ramprasad

Gudrawan 0.15, 0.4

0.001 12 A

76 720 Ghansyam F. Ramprasad Gudrawan 0.33 0.007 8 A

77 723 Bapulal F. Keshoram Gudrawan 1.11 0.003

78 722 Bhuvaniram, Kanhaiahlal F. Keshoram

Gudrawan 1.09 0.010

79 6 Lakkha F. Chatara Gudrawan 0.7 0.001

80 721/1 Dhigvijaysingh F. Vikramsingh Gudrawan 1.2 0.006

81 721/2 Pujabai H. Suresh Gudrawan 0.68 0.021

82 8 Lakkha F. Chatara Gudrawan 0.62 0.006

83 104 CHANDAR BAI F. KANA JI Najarkheda 1.41 0.005

Page 104: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

101

Annexure 8 : Summary of Affected Persons and Common Property Resources

MAIN PIPE LINE – 600 mm

S.No Survey Number

Farmer Name (Zone-3 DY1) Village Name

Area (Ha)

Aff Area

Fruit Trees

Orange Category

Other Trees

1 766 Not Available Nalkheda 0 0.003

2 762 Govt. Land Nalkheda 0 0.002

3 700/3 Babulal F. Bhanwarlal Nalkheda 0.461 0.003

4 701 Govt. Land Nalkheda 0 0.004

5 700/1 Jabbarkhan, Ayayubkhan, Anisakhan F. Jhammankhan

Nalkheda 0.773

0.003

6 698/1 Jabbarkhan, Ayayubkhan, Anisakhan F. Jhammankhan

Nalkheda 0.314

0.009

7 697 Jabbarkhan, Ayayubkhan, Anisakhan F. Jhammankhan

Nalkheda 0.062

0.004

8 698/2/1 Not Available Nalkheda 0.073 0.002

9 696 Jabbarkhan, Ayayubkhan, Anisakhan F. Jhammankhan

Nalkheda 0.021

0.002

10 695 Habib Khan F. Rustham Khan Nalkheda 0 0.003

11 694 Habib Khan F. Rustham Khan Nalkheda 0.084 0.003

12 699 Govt. Land Nalkheda 0.073 0.001

13 812 Narayana F. Ghasiram Nalkheda 0.031 0.001

14 459 Mapi Mandir Sri Jayeswar Mahadev Ji

Nalkheda 0.899 0.007

15 481 Anisabi H. Ilak Khan Nalkheda 1.097 0.002 3 A

16 481 Anisabi H. Ilak Khan Nalkheda 1.097 0.005

17 462/2/3 Habib Khan F. Rustham Khan Nalkheda 1.035 0.016 4 B

18 462/2/2 Shaharaj Khan F. Rusthum Khan

Nalkheda 1.034 0.004

19 462/2/2 Shaharaj Khan F. Rusthum Khan

Nalkheda 1.034 0.010

20 474 1.Kamalabai H. Himmathmal, 2.Siddnath F. Bhavana

Nalkheda 0.680, 0.209

0.004

Page 105: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

102

21 473 1.Govt. Land, 2.Kamalabai H. Himmathmal

Nalkheda 0.509, 0.209

0.022

22 473/1578 Himmathmal F. Mathuramal Nalkheda 1.233 0.006

23 435 Kamalabai H. Himmathmal Bhaisoda 0.82 0.016

24 436 Rameshchand F. Nathulal Bhaisoda 0.42 0.003

25 433 1.Himmathmal F. Mathuramal, 2.Kamalabai H. Himmathmal

Bhaisoda 0.09, 1.5

0.001

26 433 1.Himmathmal F. Mathuramal, 2.Kamalabai H. Himmathmal

Bhaisoda 0.09, 1.5

0.004 2 B

27 438 Lakshmichand F. Nathulal Bhaisoda 1.25 0.010 6 A

28 441 SAMPATBAI DHULA Bhaisoda 0.76 0.006

29 439 LAXMICHAND BHERULAL Bhaisoda 0.96 0.015

30 440 NATHU MANGU Bhaisoda 0.21 0.004

31 432 GOVT. LAND Bhaisoda 2.55 0.007

32 240 RAMESWAR PIRULAL Bhaisoda 0.96 0.009

33 241 SIDABNATH RAMESWAR Bhaisoda 0.88 0.010

34 241 SIDABNATH RAMESWAR Bhaisoda 0.88 0.005

35 248 CHANDRASEKHAR LAXMINARAYAN

Bhaisoda 0.44 0.007

36 249 GANGABAI BADRILAL Bhaisoda 0.45 0.004

37 247 DHANSINGH NATHULAL Bhaisoda 0.63 0.006

38 251 SHYAMSUNDER KRUSHNABALLAVH, RAMPAL PRABHULAL

Bhaisoda 1.13, 0.73

0.015

39 252 BADRILAL BHERULAL Bhaisoda 1.07 0.001

40 104 CHANDAR BAI F. KANA JI Najarkheda 1.41 0.015

41 103 ISWAR SINGH SHIV SINGH Najarkheda 0.79 0.008

42 102 GOVT. LAND Najarkheda 0.16 0.004

43 100 SYAM SINGH UKAR SINGH Najarkheda 1.85 0.019

44 96 NOOR KHAN KARIM KHAN Najarkheda 0.5 0.006

45 95 VAJIR KHAN KARIM KHAN Najarkheda 0.44 0.005

46 93 VIKRAM SINGH RAM SINGH Najarkheda 0.61 0.006

47 92 BAL CHANDRA UKAR Najarkheda 0.32 0.008

48 183 SANTOSH RAM CHANDRA, RAM LAL PURA

Najarkheda 0.4, 1 0.004

Page 106: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

103

49 183 SANTOSH RAM CHANDRA, RAM LAL PURA

Najarkheda 0.4, 1 0.012

50 247 GOVT. LAND Najarkheda 2 0.003

51 246 NARAYANA MADHO Najarkheda 0.46 0.008

52 245 SRI RAM MANDIR Najarkheda 0.62 0.015

53 235 RAJENDRA VIKRAM SINGH Najarkheda 1.68 0.003

54 244 NARENDRA SINGH VIKRAM SINGH

Najarkheda 0.81 0.016

55 243 BHERU SINGH UDAY SINGH

Najarkheda 0.96 0.014

56 236 BHERU SINGH, RAMNATH SINGH UDAY SINGH

Najarkheda 1.79 0.005

57 239 UDAY SINGH, AMAR SINGH KESHAR SINGH

Najarkheda 0.63 0.016 1 A

58 242 NOT AVAILABLE Najarkheda 0.75 0.004

59 1249 LAXMI NARAYANA Pilwas 1.69 0.016

60 1250 GOVT. LAND Pilwas 0.42 0.004

61 1252 NOT AVAILABLE Pilwas 0.005

62 1271 GITA BAI Pilwas 0.83 0.008 5 A

Page 107: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

104

Annexure 9 : Summary of Affected Persons and Common Property Resources

MAIN PIPE LINE – 500 mm

S.No Survey Number

Farmer Name (Zone-3 DY1) Village Name

Area (Ha)

Aff Area

Fruit Trees

Orange Category

Other Trees

1 252 BADRILAL BHERULAL Bhaisoda 1.07 0.003

2 253 BAPULAL BHERU Bhaisoda 0.46 0.005

3 253 BAPULAL BHERU Bhaisoda 0.46 0.003

4 254 MURALI RAMPRASAD, GORDHANLAL MATHURALAL

Bhaisoda 0.59, 0.29

0.005

5 255 PIRULAL HARINARAYAN, LAXMICHAND GHASIRAM

Bhaisoda 0.44, 0.45 0.009

6 271 BHERULAL DEVISINGH Bhaisoda 0.9 0.010

7 277 PABANKUMAR BADRILAL Bhaisoda 0.42 0.008

8 276 KALURAM NARAYAN Bhaisoda 0.68 0.005

9 274 KOSALYABAI SIDABNATH Bhaisoda 0.99 0.003

10 275 ANIL BALKISHAN Bhaisoda 0.89 0.010

11 285 MOHANLAL PIRULAL Bhaisoda 0.68 0.005

12 287 KAMAL MANGILAL Bhaisoda 0.17 0.003

13 288 LAKHANLAL JAGANNATH Bhaisoda 0.17 0.005

14 378 GOVT. LAND Bhaisoda 1.5 0.004

15 1271 GITA BAI Pilwas 0.83 0.004

16 1272 KANHEIYA LAL Pilwas 0.41 0.007 6 B

17 1279 PUKHRAJ KUMAR Pilwas 1.08 0.017

18 1286/2 BHAMBAR LAL Pilwas 2.07 0.009

19 1277 BHAMBAR LAL Pilwas 0.51 0.001

20 1296 GOBINDA SINGH Pilwas 1.67 0.010

Page 108: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

105

Annexure 10 : Summary of Affected Persons and Common Property Resources

MAIN PIPE LINE – 450 mm

S.No Survey Number

Farmer Name (Zone-3 DY1) Village Name

Area (Ha)

Aff Area

Fruit Trees

Orange Category

Other Trees

1 378 GOVT. LAND Bhaisoda 1.5 0.001

2 372 RAMKARAN JAGANNATH Bhaisoda 0.34 0.001

3 371 DINESH KUWARLAL Bhaisoda 0.57 0.005

4 370 BHERULAL DEVISIJNGH Bhaisoda 0.88 0.002

5 366 LAKHANLAL JAGANNATH Bhaisoda 1.02 0.005

6 369 KAMAL MANGILAL Bhaisoda 0.43 0.001

7 367 BHERULAL DEVISINGH Bhaisoda 0.52 0.004

8 336 1.MANOHARSINGH BHARATSINGH, 2.RAJESHKUMAR SAGARMAL

Bhaisoda 0.31, 0.02

0.007

9 132 GOVT. LAND Bhaisoda 1.02 0.001

10 106 TEJKARAN BALCHANDRA Bhaisoda 0.5 0.001

11 130 GOVT. LAND Bhaisoda 0.96 0.007

12 111 BODIYA MAGU Bhaisoda 0.52 0.001

13 128 SIDABNATH PARBAT Bhaisoda 4.04 0.003

14 128 SIDABNATH PARBAT Bhaisoda 4.04 0.011

15 950 GOVT. LAND Bhaisoda 1.24 0.001

16 942 GOVT. LAND Bhaisoda 0.44 0.001

17 944 SIDHU SEBA Bhaisoda 0.42 0.001

18 939 GOVT. LAND Bhaisoda 1.5 0.001

19 960 GOVT. LAND Bhaisoda 2.69 0.002

20 975 GOVT. LAND Bhaisoda 7.33 0.005

21 1296 GOBINDA SINGH Pilwas 1.67 0.001

22 1292 SIMA KUMBAR Pilwas 1.1 0.005

23 1294 BALU Pilwas 0.71 0.007

24 1506 GOVT. LAND Pilwas 0.45 0.001

25 1507 BALU SINGH Pilwas 1.66 0.002

26 1518 JIBAN SINGH Pilwas 1.18 0.008

27 1516 ISWARA SINGH Pilwas 1.15 0.002

Page 109: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

106

Annexure 11 : Summary of Affected Persons and Common Property Resources

MAIN PIPE LINE – 400 mm

S.No Survey Number

Farmer Name (Zone-3 DY1) Village Name

Area (Ha)

Aff Area

Fruit Trees

Orange Category

Other Trees

1 1516 ISWARA SINGH Pilwas 1.15 0.003

2 1526 BHAGABAN SINGH Pilwas 0.28 0.004

3 1527 KESAR SINGH Pilwas 0.68 0.002

4 1529 KRUSNA BAI Pilwas 0.3 0.003

5 1530 KRUSNA BAI Pilwas 0.29 0.003

6 1531 MAN SINGH Pilwas 1.7 0.007

7 1534 SUVASACHAND,GANGA BAI

Pilwas 1.22 0.012

8 1535 GOVT. LAND Pilwas 3.5 0.007

9 1615 GOVT. LAND Pilwas 0.5 0.001

10 1616 GOVT. LAND Pilwas 1.01 0.003

11 1620 ANOP SINGH Pilwas 1.21 0.013

12 1624 GOVT. LAND Pilwas 1.4 0.005

13 1628 BHAGIRATHA Pilwas 0.41 0.004

14 1630 RAM LAL Pilwas 0.41 0.015

15 1631 MOHAN Pilwas 0.46 0.000

16 1632 DEBI LAL Pilwas 0.46 0.005

17 1643 UMADEBI Pilwas 0.62 0.003

18 1642 GIRI RAJ Pilwas 0.41 0.003

19 1641 BANSI LAL Pilwas 0.63 0.000

20 975 GOVT. LAND Bhaisoda 7.33 0.008

21 987 GOVT. LAND Bhaisoda 0.62 0.005

22 989 DEVISINGH MANGU Bhaisoda 0.26 0.004

23 988 SALIM KHAMMAN KHAN Bhaisoda 0.24 0.006

24 997 GOVT. LAND Bhaisoda 1.97 0.008

25 166 GOVT. LAND Semali 1.003 0.001

26 146 GOVT. LAND Semali 0.732 0.004

27 144 GIRI RAJ Semali 0.209 0.004

28 143 ATMARAM Semali 0.753 0.000

29 145 KESAR SINGHA, JAYA NARAYANA, AKHILESHA

Semali 0.068, 0.068, 0.366 0.007

Page 110: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

107

30 132

GIRI RAJ, GOVT. LAND, KAYLASA, FULCHAND, RAMPRASAD, RAMESHA, KANHEIYALAL

Semali

1.4, 0.073, 0.105, 0.105, 0.105, 0.104, 0.209 0.011

31 131 SHAKUNTALA BAI, SUNDAR BAI

Semali 0.209, 0.199 0.005

32 130 BHARAT SINGHA Semali 0.035 0.004

33 130 BHARAT SINGHA Semali 0.035 0.006

34 183 OM PRAKASH MADAN, RADHESYAM MADAN

Semali 0.331, 0.474 0.012

35 120 GANESHARAM Semali 0.867 0.002

36 189 RADHESYAM Semali 0.272 0.005

37 190 JAYA NARAYANA, BABU LAL, KAYLASHA

Semali 0.601, 0.737, 0.951 0.004

38 119 BHARAT SINGHA, LILA BAI, SIBA SINGHA, KANTI BAI

Semali

2.09, 0.637, 0.105, 0.658 0.007

39 108 NOT GIVEN, OM PRAKASHA, KRUSHNA BAI

Semali 0.036, 0.732, 0.732 0.005

40

183

SANTOSHA, RAM LAL, SIBA LAL, RUKHMANI BAI, SANGITA BAI, MANGU, NARAYANA, ISAK KHAN, RAIS KHAN, RAJAK KHAN, MANGI LAL

Najarkheda

0.4, 1, 0.8, 0.8, 0.51, 0.6, 0.4, 0.2, 0.2, 0.06,

0.2, 0.8 0.015

187 GOVT. LAND Najarkheda 0.11 0.001

188 GOVT. LAND Najarkheda 0.2 0.003

192 RAMESHA Najarkheda 0.4 0.012

191 NANURAM Najarkheda 0.4 0.002

63 MOHAN SINGH Najarkheda 1.71 0.006

41

557 MANGILAL BASANTILAL, MANJUDEVI ABHAYAKUMAR

Pheti 1.04 0.002

501 MANGILAL KANHAEIYALAL, MANJUDEVI ABHAYAKUMAR

Pheti 2.09 0.002

Page 111: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

108

543 RAEMMOHAMAD SARID KHAN

Pheti 1.57 0.005

554 BHERULAL AMARSINGH Pheti 0.16 0.000

551 CHANDANBALAL SANJAYAKUMAR

Pheti 0.63 0.008

544 SOHANBAI SAGARMAL Pheti 2.85 0.007

542 SUNILKUMAR SAGARMAL Pheti 0.26 0.000

541 SUNITABAI SUNILKUMAR Pheti 1.17 0.006

540 PRAKASHCHANDRA ROOPCHANDRA

Pheti 1.04 0.005

536 RAUF KHAN TURAB KHAN Pheti 8.47 0.020

42

681 ABHAYAKUMAR TARACHAND

Pheti 1.94 0.015

685 GOVT. LAND Pheti 5.73 0.002

679 GOVT. LAND Pheti 7.53 0.012

43

251

SHYAMSUNDER KRUSHNABALLAVH, RAMPAL PRABHULAL, PRABHULAL SHIBANARAYAN

Bhaisoda 2.06

0.001

252 BADRILAL BHERULAL Bhaisoda 1.07 0.006

254

MURALI RAMPRASAD, GORDHANLAL MATHURALAL, MISHRILAL MATHURALAL

Bhaisoda 1.18

0.004

257 BINOD RODMAL Bhaisoda 0.68 0.003 2 A

258 SATIBAI SHIBANARAYAN Bhaisoda 0.43 0.003

261 GOVT. LAND Bhaisoda 0.23 0.001

432 GOVT. LAND Bhaisoda 2.55 0.002

473 GOVT. LAND Bhaisoda 0.33 0.002

471 DEVISINGH BANSILAL Bhaisoda 0.5 0.004

472 PREMNARAYAN RAMLAL Bhaisoda 0.42 0.004

475 BADRILAL NATHULAL Bhaisoda 0.67 0.000

Page 112: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

109

Annexure 12 : Approved Collector Rates of Agriculture Land of Nalkheda Tehsil, Agar Malwa District

Page 113: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

110

Page 114: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

111

Page 115: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

112

Page 116: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

113

Page 117: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

114

Annexure 13 : MSP Rates By MP Govt.

Page 118: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

115

Annexure 14 : Memorandum of Understanding (MOU) to document foregone compensation for temporary land use

Page 119: 45371-007: Madhya Pradesh Irrigation Efficiency ... · Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to achieve high irrigation efficiency and water

116