document38
TRANSCRIPT
![Page 1: Document38](https://reader031.vdocuments.mx/reader031/viewer/2022030114/589beba41a28aba5108b76d9/html5/thumbnails/1.jpg)
Cost Performance Index (CPI) and Schedule Performance Index (SPI):
5. SPI greater than 1 is good/favourable (ahead of schedule).
Estimate to complete (ETC): Your estimate of the amount of funds required to complete all work still remaining to be
done on the task
6. The following calculations are operative:
5. A tolerance of 10% has been built into the coloration indicators against the Planned Value
EBI Program Reporting: Earned Value Guidance
Schedule variance (SV) = Earned value (EV) – Planned value (PV)
Cost variance (CV) = Earned value (EV) – Actual cost (AC)
Schedule performance index (SPI) = Earned value (EV) / Planned value (PV)
Cost performance index (CPI) = Earned value (EV) / Actual cost (AC)
Estimate at completion (EAC): Your estimate today of the total cost of the task
1. The principle must hold that all money spent accounts against the value of the Asset - including all CAPEX and OPEX
2. Baselines must be set and be monitored against for EV to have any value
Rules & Principles:
3. Used but undestributed budged must be accounted i.e. all accruals immediately accounted as actual costs
4. Re-forcasting should not change the Planned Value baseline - only CR's that fundamentally change the constraints
3. CPI = 1 means that the cost of completing the work is right on plan (good);
4. CPI > 1 means that the cost of completing the work is less than planned (good or sometimes bad).
Planned Value (PV) is the authorized budget assigned to work to be accomplished for an activity or WBS component. Also known as Budgeted Cost of Work Scheduled (BCWS)
Actual Cost (AC) is the total cost actually incurred in accomplishing work performed for an activity or WBS component.” Also known as Actual Cost of Work Performed (ACWP)
Earned Value (EV) is the value of work performed expressed in terms of the approved budget assigned to that work for an activity or WBS component. Also known as Budgeted Cost of Work Performed (BCWP)
1. CPI greater than 1 is good/favourable (under budget)
2. CPI < 1 means that the cost of completing the work is higher than planned (bad)
Ea
rne
d V
alu
e R
ep
ort
ing
1
PA
DO
P3M
Version 1.0 ………
![Page 2: Document38](https://reader031.vdocuments.mx/reader031/viewer/2022030114/589beba41a28aba5108b76d9/html5/thumbnails/2.jpg)
Reporting Date: 2016/09/05
Budget at Completion
$2,833,896
Estimate at Completion
$3,102,283
Cost Variance at Completion$268,387
Schedule Variance
-$769,028
Cost Variance
-$672,116
SV=EV-PV
CV=EV-AC
0.9
EV=F $450,384
PV=D $2,833,896
AC=H $1,122,500
CPV $1,219,412
Planned Value(PV) ----
$1,219,412Actual Cost (AC) ----
$1,122,500Earned Value (EV) ----
$450,384
CPI
0.91
SPI
0.885121984
CPI=EV/AC (CPI>1 is Good)
SPI=EV/PV (SPI>1 is Good)
EBI Program Reporting: Earned Value
0.00
500,000.00
1,000,000.00
1,500,000.00
2,000,000.00
2,500,000.00
3,000,000.00
--- Planned Value --- Earned Value ---Actual Cost
0.60
0.80
1.00
1.20
S C H E D U L E P E R F O R M A N C E I N D E X ( S P I )
0.80
0.85
0.90
0.95
1.00
1.05
C O S T P E R F O R M A N C E I N D E X ( C P I )
Ea
rne
d V
alu
e R
ep
ort
ing
1
PA
DO
P3
M
Version 1.0
………