2014 pv distribution system modeling workshop: pro-active, high penetration pv studies on...
DESCRIPTION
2014 PV Distribution System Modeling Workshop: Pro-active, high penetration PV studies on distribution systems: Jonathan Flinn, DNV GLTRANSCRIPT
DNV GL © 2013 May 6th 2014 SAFER, SMARTER, GREENER DNV GL © 2013
May 6th 2014
Jonathan Flinn
Pro-Active, High Penetration PV Analysis on Distribution Systems
1
PV Distribution System Modeling Workshop
Santa Clara, CA
DNV GL © 2013 May 6th 2014
Contents
Introduction
Objectives of Analyses
Overview of Approach
Technical Criteria
Analysis in SynerGEE
Modeling Advanced Inverter Functions in SynerGEE
Conclusion
2
DNV GL © 2013 May 6th 2014
Introduction – DNV GL
Merger of brands, consolidation of experience and expertise
3
DNV GL © 2013 May 6th 2014
An energy technology powerhouse
4
Offshore wind Strong expertise in offshore wind, its support vessels and connection to the electricity grid
Innovation Strategic research in energy storage, smart grids and super grids; developments of new standards through joint industry projects
Testing Global leader in testing, inspecting and certifying high-power and renewable energy equipment with world class laboratories
Expert advice In onshore and offshore wind power, solar, smart grids, super grids, infrastructure resilience, energy markets, regulations and use
Power player A strong player across the value chain: renewable and conventional power generation, transmission & distribution and sustainable energy use
DNV GL © 2013 May 6th 2014
Introduction – Jonathan Flinn
MEng Mechanical Engineering with Aeronautics, University of Strathclyde, 2004
MSc Safety, Risk and Reliability Engineering, Heriot-Watt University, 2005
9 years in DNV GL
Worked with pipelines, wind energy, arctic operations, wave and tidal energy
Worked in transmission and distribution since 2011
5
DNV GL © 2013 May 6th 2014
Introduction – Pro-Active Approach
Developed in co-operation with HECO
Aim to streamline PV interconnection process
Objectives:
– Improve PV interconnection process
– Identify limits on a circuit-specific basis
– Facilitate efficient network planning
– Identification of limits in advance
– Identify existing risks
– Compare limits with existing PV penetrations
– Identify future limits to PV integration
– Run hypothetical future PV scenarios up to high PV penetrations
– Identify appropriate mitigation measures
– Developed from list of potential mitigation measures
6
DNV GL © 2013 May 6th 2014
CA Rule 21
7
Complete application received
Screen 1: Connection to distribution system?
Screen 2: Connection to network
Screen 3: Export power causes reverse flow at
voltage regulation devices
Screen 4: Is the aggregate generating facility on
the line section <=15% of line section peak load
Screen 5: Is voltage flicker and/or voltage drop
due to project within IEEE 519 limits
Screen 6: DG <= 10kW
Screen 7: Inverter-based DG <= 250kW meets IEEE 1547 & UL 1741
Screen 8: SCCR within acceptable limits
Screen 9: Interconnection compatible with line
configuration
Perform
Supplemental Review
Does not qualify for
interconnection under Rule
21
Does supplemental
review determine
requirements?
Company provides the
cost estimate and
schedule for IRS to
determine requirements
Generating Facility
qualifies for
interconnection subject
to requirements, if any,
determined by
supplemental review
Generating
Facility qualifies
for Simplified
Interconnection
no
no
no
yes yes
no
no
yes
yes
yes
yes
no
no
no
no
yes
yes
yes
yes no
DNV GL © 2013 May 6th 2014
CA Rule 21
8
Complete application received
Screen 1: Connection to distribution system?
Screen 2: Connection to network
Screen 3: Export power causes reverse flow at
voltage regulation devices
Screen 4: Is the aggregate generating facility on
the line section <=15% of line section peak load
Screen 5: Is voltage flicker and/or voltage drop
due to project within IEEE 519 limits
Screen 6: DG <= 10kW
Screen 7: Inverter-based DG <= 250kW meets IEEE 1547 & UL 1741
Screen 8: SCCR within acceptable limits
Screen 9: Interconnection compatible with line
configuration
Perform
Supplemental Review
Does not qualify for
interconnection under Rule
21
Does supplemental
review determine
requirements?
Company provides the
cost estimate and
schedule for IRS to
determine requirements
Generating Facility
qualifies for
interconnection subject
to requirements, if any,
determined by
supplemental review
Generating
Facility qualifies
for Simplified
Interconnection
no
no
no
yes yes
no
no
yes
yes
yes
yes
no
no
no
no
yes
yes
yes
yes no
Pro-active approach identifies at which PV penetrations this will occur for each feeder/transformer
DNV GL © 2013 May 6th 2014
CA Rule 21
9
Complete application received
Screen 1: Connection to distribution system?
Screen 2: Connection to network
Screen 3: Export power causes reverse flow at
voltage regulation devices
Screen 4: Is the aggregate generating facility on
the line section <=15% of line section peak load
Screen 5: Is voltage flicker and/or voltage drop
due to project within IEEE 519 limits
Screen 6: DG <= 10kW
Screen 7: Inverter-based DG <= 250kW meets IEEE 1547 & UL 1741
Screen 8: SCCR within acceptable limits
Screen 9: Interconnection compatible with line
configuration
Perform
Supplemental Review
Does not qualify for
interconnection under Rule
21
Does supplemental
review determine
requirements?
Company provides the
cost estimate and
schedule for IRS to
determine requirements
Generating Facility
qualifies for
interconnection subject
to requirements, if any,
determined by
supplemental review
Generating
Facility qualifies
for Simplified
Interconnection
no
no
no
yes yes
no
no
yes
yes
yes
yes
no
no
no
no
yes
yes
yes
yes no
Pro-active approach identifies specific limitations for each feeder/cluster due to different criteria (thermal loading, voltage violations, etc.),
DNV GL © 2013 May 6th 2014
CA Rule 21
10
Complete application received
Screen 1: Connection to distribution system?
Screen 2: Connection to network
Screen 3: Export power causes reverse flow at
voltage regulation devices
Screen 4: Is the aggregate generating facility on
the line section <=15% of line section peak load
Screen 5: Is voltage flicker and/or voltage drop
due to project within IEEE 519 limits
Screen 6: DG <= 10kW
Screen 7: Inverter-based DG <= 250kW meets IEEE 1547 & UL 1741
Screen 8: SCCR within acceptable limits
Screen 9: Interconnection compatible with line
configuration
Perform
Supplemental Review
Does not qualify for
interconnection under Rule
21
Does supplemental
review determine
requirements?
Company provides the
cost estimate and
schedule for IRS to
determine requirements
Generating Facility
qualifies for
interconnection subject
to requirements, if any,
determined by
supplemental review
Generating
Facility qualifies
for Simplified
Interconnection
no
no
no
yes yes
no
no
yes
yes
yes
yes
no
no
no
no
yes
yes
yes
yes no
Identification of areas of risk/interest for the feeder, allows focus of analysis on circuit-specific issues
DNV GL © 2013 May 6th 2014
System Boundaries
11
Example of system
boundary
One sub-transmission
line, plus all
connected distribution
feeders
DNV GL © 2013 May 6th 2014
Analysis Approach
Model load independently of solar
– Requires some manipulation of
demand data
Find peak and minimum daytime load
days
Run analyses with varying penetrations
of PV
Use linear interpolation to find
technical limits
12
DNV GL © 2013 May 6th 2014
Analysis Approach
Use combinations of load profile and PV penetration
13
Load Scenarios
1. Peak Daytime Load
Day
2. Minimum Daytime Load Day
PV Penetration Scenarios
1. No PV 2. Existing PV 3. Existing + Queued PV 4. PV = 15% of Peak Load 5. PV = 30% of Peak Load 6. PV = 50% of Peak Load 7. PV = 75% of Peak Load 8. PV = 100% of Peak Load 9. PV = 135% of Peak Load
DNV GL © 2013 May 6th 2014
Technical Criteria
14
Technical Criterion Limit or Trigger
Steady-State Voltage V > 1.05 p.u. or V < 0.95 p.u.
Thermal Loading Loading > 100%
Backfeed Reversal of flow through transformer
Fault Current Available fault current exceeds breaker interrupt rating
Transient Voltage Voltage change > 3% during step change in PV output
Dynamic Voltage Overvoltage / undervoltage due to inverter trips during N-1
Dynamic Frequency Additional load shedding due to inverter trips during N-1
LTC Cycling Increase in LTC operations due to PV operation
DNV GL © 2013 May 6th 2014
LTC Cycling Studies
An increase in LTC cycling due to PV is not necessarily a significant problem
– If it causes 1 extra operation per week, still very small change
At some point it could become a problem, causing decrease in time between
maintenance, and LTC lifetime
– Number of increased operations per year can be calculated for each PV
penetration, and compared against a limit defined by utility
15
Number of Events
Change in Irradiance [W/m2s]
DNV GL © 2013 May 6th 2014
LTC Cycling Studies
A reverse effect must also be studied:
– PV operation causes reduced current through LTC compared to no-LTC case
– Reduced current may increase LTC contact lifetime
– This effect reverses past point of backfeed, where increased PV causes
increased current
– Chart below comes from Kaukesha UZD LTC Technical Manual
16
DNV GL © 2013 May 6th 2014
Analysis in SynerGEE – Model Setup
Load and generation on utilization circuits
aggregated to distribution transformers
PV modeled as generator in SynerGEE (not
negative load)
– Necessary for fault analysis
– Also allows use of irradiance profiles
Existing generators modeled in existing
locations
Hypothetical ‘future’ generators placed by
analyst to allow up to 150% PV Penetration
17
DNV GL © 2013 May 6th 2014
Analysis in SynerGEE – Recipe Scripts
SynerGEE allows use of automated
analysis
– Consecutive load flows run using
‘recipe’ commands
– Outputs saved to specified location
– Ideal for use with 24-hour load profiles
Model Cleanup scripts can be used to
make changes between analyses
18
DNV GL © 2013 May 6th 2014
Analysis in SynerGEE - Solver
SynerGEE add-on which further increases flexibility
Allows changes to be made to model (more than Recipe or ModClean)
Compiles and post-processes results
Requires some basic programming skills
Flexibility is useful in Advanced Inverter Modeling
19
DNV GL © 2013 May 6th 2014
Mitigation of PV Impacts
Mitigant Backfeed Loading Voltage LTC Cycling
Fault Current
Dynamics Transients
Energy Storage X X X X
Curtailment X X X X
Inverter power factor control
X
Inverter disconnection and re-closing control
X X
Equipment upgrades
X X X X
20
DNV GL © 2013 May 6th 2014
Energy Storage
21
Load > PV:
Load is fed by grid
PV > Load:
Load is fed by PV
PV > Load:
Excess PV charges
battery
Load > PV:
Load is fed
by battery
Mitigates: Backfeed Violations, Voltage Violations
Energy storage systems can be used to prevent backfeed from occurring
Simple model in SynerGEE
is to calculate total reverse
power flow and energy
New battery model in
SynerGEE 5.1 will allow
individual batteries to be
charged and discharged
DNV GL © 2013 May 6th 2014
Curtailments
Curtailment is a smart inverter function
Allows utility to either:
– Reduce output from generator to solve problem
– Disconnect generator completely
Cost to utility is cost of ‘lost’ energy to generator
Simple model in SynerGEE is same as for energy storage:
– Calculate total energy that would be curtailed to prevent backfeed
22
DNV GL © 2013 May 6th 2014
Inverter Power Factor Control
Increasing or decreasing VAR output from inverter can regulate local voltage
23
Single time-step can easily be
modified in SynerGEE
Automation can run multiple
time-steps consecutively and
identify local voltage problems
using Solver:
Run load flow
Voltage
violation?
Reduce inverter
power factor
Move
to next
time-
step
No
Yes
Complexity of process can be increased
In practice staged reduction in power factor will
be necessary to prevent over-correction
DNV GL © 2013 May 6th 2014
Inverter Disconnection and Re-Closing control
When trips and transient events happen, loss and return of all generators at once
can cause problems due to time delay on LTC
Smart inverters provide options:
– Ramp up of output
– Variable trip settings
– Variable re-closing settings
24
DNV GL © 2013 May 6th 2014
Comparison of Mitigation Techniques
25
DNV GL © 2013 May 6th 2014
Conclusion
Pro-Active Approach can help to streamline PV interconnection process
– Can also help to plan equipment upgrades
Analysis performed in SynerGEE allows flexibility to modify process
– Also allows automation of analysis and post-processing
Flexibility of SynerGEE also allows approximation of advanced and smart inverter
characteristics
– Integration with energy storage
– Curtailment
– Power factor control
– Output ramping
26
DNV GL © 2013 May 6th 2014
SAFER, SMARTER, GREENER
www.dnvgl.com
Thank you for your attention
27
Jonathan Flinn
(925) 327-3044