Page 1: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

2014 budget report, draft budget request for 2015 and future outlook

Martyn Davenport

22 October 2015

CAST FRC-D 2015-037

Page 2: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

CAST Financial Report October 2015

Update to 2013 Budget Report

2014 Budget report – Status of the Common Fund T297400

Draft Budget Request 2015

Future Outlook 2016 Running and Beyond

Page 3: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Update to 2013 budget report

Small changes to written report

Last minute M&O B numbers included in presentation at FRC in 2014

Not in written report

Page 4: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Update of 2013 budget report

Table 5: Category B (type b) Investment in development, construction, testing, installation

and alignment of new detectors or systems in 2013

Institute

X-ray detector orX-ray detector

M&Osub-system  

[kCHF]

IRFU-Saclay, France Microbulk MM 6.87

UZ, SpainConstruction new detectors SRMM and associated systems. New Veto for SSMM.

44.8

NCSR,Greece X-Y microbulk MM  

U BonnInvestment in new InGrid (detector, gas & vacuum components, electronics)

19.57

CERN, Switzerland

Big SDD and preamp, detector vacuum housings, peltier cooling systems, PX5 pulse processor. PCB and electrical work. Electron beam welding. UPS.

49.1

U Patras

Nano windows development. PhD student, consumables (solvents , acids..), constructions in mechanical workshops

17.0

LLNL, Columbia USA, New XRT 160

DTU-Space Denmark

TOTAL    297.4

Page 5: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Update of 2013 budget report

Category2013

Fraction[kCHF]

Category A (I) 145.2 0.25

Category A (II) 81.3 0.14

Category B (a) 50.9 0.09

Category B (b) 297.4 0.52

Total 574.8 1.00

Table 6: Summary of Category A contributions and Category B expenditure in 2013

Page 6: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

2014 Budget report

Vacuum Run in 2014 –Phase IV

Status of Contributions 2014

Status of Expenditure in 2014

Magnet operation costs 2014

The status of the CAST Common Fund end 2014

End of Addendum No4

Page 7: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Program for 2014 Phase IV - Vacuum Run

2014 schedule Complete repair work on Main Compressor gear box bearings Cool magnet & test magnet at 13kA Install MPE XRT after calibration in PANTER

Align XRT Align InGrid detector target.

X Install InGrid detector and shieldingX Possible contamination with vacuum grease?X Retest MPE-XRT at Panter Rebuild vacuum system with new or cleaned parts

Install new full coverage veto counter for Sunset MM Full survey GRID measurement Take data for 2 months with SSMM (No InGrid) Install new LLNL XRT in September 2014 Align LLNL XRT & SRMM target Install SRMM detector and final heavy shielding Run 2 months SRMM + XRT LLNL. No InGrid No SSMM Check alignment of MPE-XRT 6 weeks data taking run with complete Phase IV detector system up to November Stop data taking due to CV intervention at LHC8 mid-November 2014.

Page 8: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Outstanding contributions 2011,12 & 2013

At the end of 2013 473kCHF Outstanding from Add No4 Contributions

Out-standing

Out-standing

Out-standing Out-standing

year year year sum2011 2012 2013 2011+12+13

(kCHF) (kCHF) (kCHF) (kCHF)Institute

CERN 4.9 -40.1 -7.4 -42.6IRFU-Saclay, France 0.2 0.0 18.0 18.2Greek Delegation 50.0 125.0 125.0 300.0UP, Greece -21.1 -21.7 9.0 -33.8UTH, Greece 0.0 5.0 5.0 10.0NCSR, NTUA, Greece 0.0 3.0 3.0 6.0TU-Darmstadt, MPE UFRA, Germany 5.2 4.4 30.4 39.9MPP, Germany 1.4 5.0 -5.0 1.4Columbia U., USA 0.0 5.0 5.0 10.0DTU-Space, Denmark 0.0 5.0 5.0 10.0UD, Turkey 10.0 10.0 -12.0 8.0U Bonn, Germany 0.0 10.0 -10.0 0.0INR, Russia 0.0 6.0 3.0 9.0LLNL, USA 7.6 10.1 15.0 32.7UBC, Canada 5.0 5.0 5.0 15.0RBI, Croatia 0.0 15.0 -15.0 0.0UZ, Spain 21.6 -10.0 -6.4 5.2UT, Italy 0.1 3.7 4.5 8.3MPS, Germany 0.0 0.0 0.0 0.0CAPP, Korea        TOTAL 84.9 140.5 172.1 397.4Total (excluding overpayments)       473.7

Page 9: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

2014 Manpower and Team leaders

New arrival to the Collaboration CAPP (Add No 6)

Not yet signed by end of 2014 - Rijeka (Add No 5)

Institute

Team leader

Physicists

Minimum annual contribution assuming

5k/PhD

(CAST contact) [kCHF]

CERN M. Davenport 4 20

IRFU-Saclay, France I. Giomataris 3 15

UP, UTH, NCSR, NTUA, Greece K. Zioutas 7 35

U Bonn, Germany K. Desch 2 10

TUD, Germany D. Hoffmanm 2 10

UFRA, Germany J. Jacoby 1 5

MPP, Germany G. Raffelt 1 5

UD, Turkey S. A. Cetin 2 10

INR, Russia S. Gninenko 1 5

DTU-Space, Denmark F. Christensen 1 5

LLNL, USA M. Pivovaroff 3 15

UBC, Canada M. Hasinoff 1 5

Columbia U, USA C. Hailey 1 5

RBI, Croatia M. Krcmar 3 15

UZ, Spain I. Irastorza 6 30

UT, Italy G. Cantatore 2 10

MPS, Germany S. Solanki 1 5

CAPP / Korea Y. Semertzidis 2 10

TOTAL    44 220

Page 10: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Phase IV (2014) Promised and Actual Contributions Add No4

a CERN also paid 7.01 kCHF reimbursement for SDD design work wrongly charged to CF

b U Patras also paid 9.88 kCHF reimbursement for Patras expenses

c TUD also paid 4.28 kCHF reimbursements for servicing XRT gate valvesd U Zaragoza also paid 1.57 kCHF reimbursement for pump service

Addendum No4 for 2014 (kCHF) Actual contributions in 2014 (kCHF)

Add No 4 - Actual Contrib. (kCHF)Institute

Standard Special Total Standard Special Total

Cash in-kindCash or in-kind   Cash in-kind

Cash or in-kind

   2014 2014 2014 2014 2014 2014 2014 2014 2014

CERN 20 15   35 20.0 a 11.5 31.5 3.5

IRFU-Saclay, France 18     18 0.0 0.0 18.0

Greek Delegation 100   50 150 20.0     20.0 130.0

UP, Greece     30 30     0.0b 0.0 30.0

UTH, Greece     5 5       0.0 5.0

NCSR, NTUA, Greece     3 3       0.0 3.0

TU-Darmstadt, MPE UFRA, Germany

3.6 6   9.6 0.0 15c   15.0 -5.4

MPP, Germany 5     5 11.4     11.4 -6.4

Columbia U., USA 5     5 0.0     0.0 5.0DTU-Space, Denmark 5     5 15.0     15.0 -10.0

UD, Turkey 10     10 0.0 0   0.0 10.0

U Bonn, Germany 10     10 10.0     10.0 0.0

INR, Russia   6   6   3   3.0 3.0

LLNL, USA 15     15   7.6   7.6 7.4

UBC, Canada   5   5   3   3.0 2.0

RBI, Croatia 15     15 15.0     15.0 0.0

UZ, Spain 30 0   30 0.0 9d   9.0 21.0

UT, Italy   5   5   0.7   0.7 4.3

MPS, Germany 10     10 10.0     10 0.0

CAPP, Korea 80     80 80.0     80 0.0

TOTAL 326.6 37 88 451.6 181.4 49.8 0 231.2 220.4

60k earmarked for DM/DE

Page 11: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Outstanding contributions end Addendum No4 (2011-2014)

Out-standing Out-standing Out-standing Out-standing Out-standing year year year year years

2011 2012 2013 2014 2011+12+13+14(kCHF) (kCHF) (kCHF) (kCHF)  (kCHF)

Institute  CERN 4.9 -40.1 -7.4 3.5 -39.1IRFU-Saclay, France 0.2 0.0 18.0 18.0 36.2Greek Delegation 50.0 125.0 125.0 130.0 430.0UP, Greece -21.1 -21.7 9.0 30.0 -3.8UTH, Greece 0.0 5.0 5.0 5.0 15.0NCSR, NTUA, Greece 0.0 3.0 3.0 3.0 9.0

TU-Darmstadt, MPE UFRA, Germany 5.2 4.4 30.4 -5.4 34.5MPP, Germany 1.4 5.0 -5.0 -6.4 -5.0Columbia U., USA 0.0 5.0 5.0 5.0 15.0DTU-Space, Denmark 0.0 5.0 5.0 -10.0 0.0UD, Turkey 10.0 10.0 -12.0 10.0 18.0U Bonn, Germany 0.0 10.0 -10.0 0.0 0.0INR, Russia 0.0 6.0 3.0 3.0 12.0LLNL, USA 7.6 10.1 15.0 7.4 40.1UBC, Canada 5.0 5.0 5.0 2.0 17.0RBI, Croatia 0.0 15.0 -15.0 0.0 0.0UZ, Spain 21.6 -10.0 -6.4 21.0 26.2UT, Italy 0.1 3.7 4.5 4.3 12.5MPS, Germany 0.0 0.0 0.0 0.0 0.0CAPP, Korea       0.0 0.0TOTAL 84.9 140.5 172.1 220.4 617.8Total excluding overpayments         665.6

Page 12: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Contributions M&O A 2014

• Balance end 2013 76.0 kCHF

• Cash Contributions for 2014 181.4 kCHF• In Kind contributions 2014 49.8 kCHF

Total 231.2 kCHF

• Income to Common fund (181.4+22.7) 204.1 kCHF

• Total promised in 2014 451.6 kCHF

• Outstanding contributions 2011+12+13+14 665.6 kCHF

• Finance report vs CAST: Income 197.1 c.f. 204.1 kCHF Expenditure 177.1 c.f. 184.1 kCHF

Page 13: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

M&O B X-RAY Detectors and sub-systems

a) Detector & sub-system M&O 2014

Institute

X-ray detector or X-ray detector M&O

sub-system 2014

[kCHF]

UZ, Spain Support and maintenance of MM detectors

9.6

U Bonn, Germany InGrid detector support and test measurements 3

LLNL, U Columbia, USA Support for XRT. 10

DTU Support for XRT 5

CERN, Switzerland

X-ray Lab upgrades (preamplifier, vacuum gauges (6.0)). Consumables and Epool (5.1). Grease contamination clean up (6.6k)

17.7

TOTAL    45.3

Page 14: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

M&OB X-RAY Detectors and Sub-systemsb) Detector & subsystem investment, development, construction, testing, installation &

alignment.

• Sizeable construction costs in 2014 New XRT : DTU & & LLNL SRMM : Zaragoza

InstituteX-ray detector or X-ray detector M&O

sub-system 2014 [kCHF]

UZ, SpainEnd of construction new detectors SRMM and associated systems.

41.2

U Bonn, Germany Development of InGrid systems 5.0LLNL, Columbia USA, XRT construction, installation

and alignment.90

 

DTU-Space Denmark XRT construction, installation and alignment.

70

CERN, Switzerland

Design work on miniature SDD vacuum housing, new pcb design and fabrication, vacuum wiring and feedthroughs, cleaning and testing at PNDetector

21.1

TOTAL    227.3

Page 15: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

M&OB Radiation Pressure and Relics

a) Detector & sub-system M&O 2014

Institute

Radiation pressure detector , relic detector or M&O

sub-system 2014

[kCHF]

U Trieste, Italy   6.1

U Rijeka, Croatia Work at Trieste on KWISP system

1.5

U Patras, Greece   1.2

TOTAL    8.8

Page 16: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

M&OB Radiation Pressure and Relicsb) Detector & subsystem investment, development, construction, testing, installation & alignment.

Institute

Radiation pressure detector , relic detector or X-ray detector M&O

sub-system  

[kCHF]

TU Darmstadt, GermanyKWISP Instrumentation (acoustic-optical modulator, flange with a wedged window )

1.5

U Trieste, Italy   12.2

U Rijeka, Croatia Membranes 1.5

TOTAL    15.2

Page 17: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Summary M&O A & B Contributions 2014

• Total contributions in 2014 were 530.8 kCHF• 44% M&O A : 56% M&O B

Category

2014

Fraction[kCHF]

Category A (I) 181.4 0.34

Category A (II) 49.8 0.10

Category B (a) 54.1 0.10

Category B (b) 245.5 0.46

Total 530.8 1.00

Page 18: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Status Expenditure 2014

• Expenditure 184.1kCHF (CF) + 49.8k In-Kind• Expenditure 92% Budget request• Very low expenses on Subsistence thanks to support of CERN & PH Dept• Enough contingency in budget

To cope with extra expenses of clean up after grease contamination problems • Over-page details of expenditure

M&O A 2014

2014 Budget estimate(kCHF)

Actual expenditure

(kCHF)

General M&O    

Industrial services and subsistence 64.3 47.1

Experimental operation costs 112 144.6

Experimental upgrades    

Common Investments 41 28.7

Low energy detector and window development 31 5.6

MFB platform 7 7.8

Total 255.3 233.9

Page 19: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

2014 detailed budget versus actual expenditure    2014

Actually spent

  GENERAL M&O    

  a) Industrial services and subsistence (kCHF) (kCHF)

1 Students 27 28.52 Spokesman 3 7.13 External support for CFD 16.7 4.14 External support for Slow Control 12.65 Mechanical support (FSU) 5 7.36 sub total 64.3 47.1   b) Experimental operation costs7 Stores 8 18.08 Cars 12 8.79 Phones/printing/transport costs 8 18.0

10 Gas/cryo liquids 211 Epool 7 6.612 Mechanical workshops and materials (CERN plus Institutes ) 413 Subsistence/expenses (data taking) 16 16.614 GRID + XRT alignments 12 13.915 expenses for analysis, clean and replacements for silicone contamination 10 36.816 Slow Control(computers/monitors/tapes) 6 0.417 Repairs, maintenance on pumps& gauges & RGA 5 15.818 Mechanical movement maintenance & running costs 2 0.019 Electrical work and cabling workshop 220 Safety (chemical cupboard) 4 0.021 Divers(vacuum cleaning/ cleaning/ outreach/ courses/ trips /Patras workshop grant) 5 2.8

22 Payment AB for FSU for power converter +3He PLC maintenance 5 5.023 Contract with ABB (1.9k + contingency for call outs) 4 1.9  sub total 112 144.6

24 Total 176.3 191.7     

Page 20: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

2014 detailed budget versus actual expenditure (cont.)    2014   Experimental upgrades (kCHF)   a) Common Investments  

25 Vacuum run Windows, wedges to straighten MFB pipework 0 26 XRTs in PANTER 30 15.027 Webcam System/sunfilming upgrades/alignment monitors 0 28 3He standby maintenance and eventual system removal 0 29 3He system to refill LLNL bottle and shipment back to LLNL 0 3.030 Tree clearance for sun filming 0 31 Instrumentation 4 6.532 Cable sheath repairs 3 33 Storage/ barrack outside SR8 for (e.g. Barbe/INGRID/LLNL-XRT) 0 34 New lifting jacks for magnet movement 4 4.2  0

35 sub total 41 28.7      b) Low Energy Detector and Window development  

36 Support physicists for studies on radiation pressure detector 6 5.637 Support for chameleon and relic axion activities 20 ->2015 38 Low Energy Windows, prototypes and tests 5    

39 sub total 31 5.6      c) MFB Platform  

40 Design - new loading calculations, study to strengthen XRT platform. 0 41 Design - integration on XRT platform 3 7.842 New MFB XRT platform or strengthening of the existing one 0 43 Mechanical work for mounting new instruments/shielding on CAST 2 44 Electrical work & cabling on new instruments/new detector 2    

45 sub total 7 7.846 Total 79 42.2   

47 Grand Totals 255.3 233.9

Page 21: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Magnet Operation in 2014

• Magnet Power converter operation low in 2014 several months either evening only or morning only running

Actual Projected values

Item Dept   2014 2015    Units    

Cryogenics M&O EN (kCHF) 180 180         

Cryogenics power   (hours) 5112 5496

EN (kCHF) 141 151         

Power Converter power   (hours) 1057 2416

EN (kCHF) 8 17

FSU maintenance (TE)       

CAST (kCHF) 5 5

Yearly TOTAL CERN (kCHF) 328 348

Page 22: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Status Common Fund end 2014

• Balance 96.0 kCHF

• End of 2014 was end of Addendum No4 2015 covered by Addendum No7 (see later)

• Summary of 2012-2014 Promised and Paid shown in A5 (overpage)

• Outstanding Contributions extremely high 665.6 kCHF

• CAST decision : for 2015 onwards cancel most of outstanding contributions except for :

Institute Outstanding ContributionsCarried Over into 2015

Total 2015 Contributiondue

  [kCHF] [kCHF]

Greek Delegation (430 kCHF outstanding ) 50.0 50.0+15.0 = 65.0LLNL/ U Columbia 55.1 55.1+20.0 = 75.1

Total 105.1 140.1

Page 23: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Promised versus actual contributions 2012 to 2014 (A5)

 

OutsCont

Standard (kCHF) Special (kCHF) TotalPAYMENTS 2012-2014

2011-2014 Outst

Cash In-Kind Cash or in-kind

2011 2012 2013 2014 2012 2013 2014 2012 2013 2014 CashIn

Kind Total Total  

CERN 4.9 20 0 20 20 20 20 15 75.1 15 22.4 15 11.5 105 40.0 109.0 149.0 -39.1  

IRFU-Saclay, France 0.2 18 18 184 0 184 0 54 18.0 0.0 18.0 36.2  Greek Delegation 50 100 25 100 25 100 20 50 0 50 0 50 0 450 70.0 0.0 70.0 430.0  UP, Greece -21.1 30 51.7 304 21 304 0 90 72.7 0.0 72.7 -3.8  UTH, Greece 0 54 0 54 0 54 0 15 0.0 0.0 0.0 15.0  NCSR, NTUA, Greece 0 34 0 34 0 34 0 9 0.0 0.0 0.0 9.0  

TU-Darmstadt, MPE UFRA, Germany

5.153.6 3.6 3.6 9.25 3.6 0 6 1.55 36 0 6 15 58.8 12.9 16.6 29.4 34.6  

 

MPP, Germany 1.4 5 0 5 10 5 11.4 15 21.4 0.0 21.4 -5.0  

Columbia U., USA 0 54 0 54 0 54 0 15 0.0 0.0 0.0 15.0  

DTU-Space, Denmark 0 54 0 54 0 54 15 15 15.0 0.0 15.0 0.0  

UD, Turkey 10 104 0 104 0 104 0 22 30 0.0 22.0 22.0 18.0  U Bonn, Germany 0 104 0 104 20 104 10 30 30.0 0.0 30.0 0.0  INR, Russia 0 6 0 6 3 6 3 18 0.0 6.0 6.0 12.0  LLNL, USA 7.6 15 4 0 154 0 154 0 4.9 0 7.6 45 0.0 12.5 12.5 40.1  UBC, Canada 5 5 0 5 0 5 3 15 0.0 3.0 3.0 17.0  RBI, Croatia 0 15 0 15 30 15 15 45 45.0 0.0 45.0 0.0  UZ, Spain 21.6 0 10 0 0 304 0 27 27 27 33.4 9 84 10.0 69.4 79.4 26.2  UT, Italy 0.1 0 0 0 54 1.3 54 0.5 54 0.7 15 0.0 2.5 2.5 12.6  MPS, Germany 0 10 10 10 10 104 10 30 30.0 0.0 30.0 0.0   CAPP, Korea x x x 80 80 x x 0 80 80.0 0.0 80.0 0.0  

TOTAL 216.6 216.6 326.6 64 94 37 88 88 88 1218.8 445.0 241.0 686.0 665.7  

Page 24: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Draft Budget request 2015

Addendum No 7(2015)

Schedule 2015

Draft Budget request

Overall financial situation

Page 25: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Addendum No 7 (2015)• CAST Addendum No 7 covers 2015 only.• 2 new Institutes RiJeka, Freiburg• The Addendum is in the signing process• Status:

Institute

Team leader

Signed on

(CAST contact) Signed by if different from Team Leader

CERN M. Davenport

IRFU-Saclay, France I. Giomataris

UP, UTH, NCSR, NTUA, Greece K. Zioutas

U Bonn, Germany K. Desch

TUD, UFRA, Germany D. Hoffmann 08/08/15

MPP, Germany G. Raffelt 04/08/15 A. Caldwell

IBU, Turkey S. A. Cetin 18/09/15

INR, Russia S. Gninenko 03/08/15 V. Matveev

DTU-Space, Denmark F. Christensen 04/08/15 K. Pedersen

LLNL, USA M. Pivovaroff

UBC, Canada M. Hasinoff 03/08/15

Columbia U, USA C. Hailey

RBI, Croatia M. Krčmar

UZ, Spain I. Irastorza 18/08/15

UT, Italy G. Cantatore 14/08/15 G. Cantatore

MPS, Germany S. Solanki 18/08/15

Rijeka, Croatia M. Karuza

CAPP, Korea Y Semertzidis

UFR, Germany H. Fischer 04/08/15

TOTAL

Page 26: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Schedule 2015 (we are nearly at the end!)

All detectors in final configuration No installations needed

Vacuum maintenance Change troublesome chain clamps on MFB side

Not foreseen! Replace magnet movement Frequency Inverters with new models Old system since 2002 – end of operational lifetime Expensive – Mitsubishi technician costs Extensive testing afterwards

Magnet cooldown Cryo problems 8 weeks lost

Full survey GRID measurement Magnet electrical isolation test and quench training• Data taking for ~ 5 months

4 months already achieved • Parallel commissioning of KWISP off-magnet in SR8

Advanced state• Eventually make an upgrade to InGrid detector during run

Mesh signal and scintillator veto (foreseen in coming 2 weeks)X Eventual changeover of KWISP detector and InGrid detector

Will be done at end of run for data taking 1Q2016

Page 27: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Draft Budget Request 2015

• Budget to fulfil schedule above• Present budget request 265.9 kCHF (was 255.3 kCHF in 2014)

See Appendix A6 for detailed request (next page) Subsistence again reduced (92kCHF)

THANKS TO CERN FOR PERSONNEL SUPPORT Long data taking periods, support needed for some personnel for running CAST Personnel support also needed for intensive Radn Pressure development at SR8

M&O A 2015 2015 Budget Request

  [kCHF]

Industrial services and subsistence 95.0

Experimental operation costs 93.9

Common investments 12

Radiation Pressure and Relic detector and window development 61

MFB platform 4

Total 265.9

Page 28: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Detailed 2015 draft budget request DRAFT BUDGET REQUEST 2015

  GENERAL M&O    a) Industrial services and subsistence (kCHF)1 Students 322 Spokesman 103 PJAS ABB Upgrade 04 CAST Running/ Deputy Technical Coordinator 505 Mechanical support (FSU) 3     6 sub total 95.0       b) Experimental operation costs  7 Stores 88 Cars 99 Phones/printing/transport costs 8

10 Gas/cryo liquids 111 Epool 712 Mechanical workshops and materials (CERN plus Institutes ) 513 Subsistence/expenses (sun filming and data taking) 1614 GRID + XRT alignments 1015 expenses for analysis, clean and replacements for silicone contamination 016 Slow Control(computers/monitors/tapes) 617 Repairs, maintenance on pumps& gauges & RGA 818 Mechanical movement maintenance & running costs 219 Electrical work and cabling workshop 220 Safety 121 Divers(vacuum cleaning/ cleaning/ outreach/ courses/ trips /Patras workshop grant) 422 Payment AB for FSU for power converter +3He PLC maintenance 523 Contract with ABB (1.9k + contingency for call outs) 1.9  sub total 93.9

24 Total 188.9

Page 29: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Detailed 2015 draft budget request (cont.)

    2015

  Experimental upgrades (kCHF)

  a) Common Investments  

25 XRTs in PANTER 0

26 Tracking system upgrade 6

27 Instrumentation 4

28 Sun filming upgrade 2

     

29 sub total 12

     

  b) Radiation Pressure detector and window development  

30 Radiation Pressure and Relic detectors development (DE/DM) 56

31 Low Energy Windows, prototypes and tests 5

32    

     

33 sub total 61

     

  c) MFB Platform  

34 Design - integration on XRT platform 2

35 Mechanical work for mounting new instruments/shielding on CAST 1

36 Electrical work & cabling on new instruments/new detector 1

     

37 sub total 4

38 Total 77

     

39 Grand Totals 265.9

Page 30: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Commitments Addendum No 7 (2015)• 3 new universities included in Addendum : Bilgi U Istanbul, Freiburg U, Rijeka U• Commitments low but more realistic• Budget 265.9kCHF - underfunded

 Cash In-Kind

Details In-KindTotal

2015 2015 (kCHF)CERN 20 (25)2 5 Technical support 25 (30)IRFU-Saclay, France 0     0Greek Delegation 151   15UP, Greece 101     10UTH, Greece 0     0NCSR, NTUA, Greece 0     0TU-Darmstadt, MPE UFRA, Germany 10   PANTER tests if needed 10MPP, Germany 0   Paid in 2014  0Columbia U., USA 5     5DTU-Space, Denmark 5   5Bilgi U, Turkey 5 2 Instruments purchased in Turkey 7U Bonn, Germany 10   10INR, Russia   5 Extra shifts 5LLNL, USA 15   15UBC, Canada   3 Shifts 3RBI, Croatia 15     15UZ, Spain 0     0UT, Italy   2   2MPS, Germany 10     10Rijeka, Croatia 5     5CAPP, Korea 25     25UFR, Germany 5     5

TOTAL 155 (160) 17   172 (177)

1 & 2 Subject to approval

Page 31: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Contributions so far in 2015

CASH CONTRIBUTIONS in 2015  20.09.2015

Date Institute Cash (CHF) Comments MPP   Paid in 2014

26.01.2016 BONN 10000 Degreasing vacuum pieces CAST 12.06.2015 MPS 9998 Contribution 2015 10.08.2015 TUD 10773 Contribution 2015 24.08.2015 CAPP 25000 Contribution 2015 10.09.2015 FREIBURG 5000 Contribution 2015 15.09.2015 BONN 10000 Contribution 2015

Total   70771  

• There have been 70.8 kCHF cash contributions (up to 20.09.2015) With 85 kCHF cash still outstanding from 2015

• Bilgi Istanbul, CERN, UP, DTU, LLNL/CU, RBI, Rijeka. Also 105 kCHF outstanding commitments carried over from Add No 4

IN KIND 2015  20.09.2015Institute   (CHF)   

CERN 10283 divers: ABB, Freq inverters,encoder,etcLLNL 2623 SDD chameleons publication $2623.20UBC 3000 shiftsINR 3000 shifts (perhaps 5000 tbd)

TRIESTE 500 Sun Filming Base PlateRBI/Rijeka 1500 Sun Filming Camera

Total 20906.2  

Page 32: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Overall Financial Situation

• At the end of 2015 with no further Contributions to the Common Fund… Balance will be ~ -48 kCHF

• Missing cash contributions for 2015 and Add No 4 carry over 2014 85 + 105 =190 kCHF

  (kCHF)

Balance start of 2015 96.0Cash Contributions in 2015 up to 20 September 2015 70.8

Total 166.8Expenditure up to 20 September 2013 127.2Balance 20 Sept 2015 39.6  Estimate of Outstanding Commitments 20 Sept 2015 5.0Estimated still to spend to end of 2015 82.5

Total 87.5 

Estimated balance end 2015 if no further contributions -48.0

Page 33: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Future Outlook – 2016 Running and beyond

Experimental Program - Phase V

Financial Outlook for Phase V and Beyond

Page 34: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Experimental Program - Phase V and Long Term Outlook

• 2015 Solar Axions (SSMM,SRMM/XRT, InGrid/XRT) Solar Chameleon (InGrid/XRT)

• 2016 (Solar Chameleons + Relic Axions) 1Q2016 Solar Chameleon KWISP solar tracking no magnetic field 1H2016 Partial Upgrade of ABB cryo controls? 2Q2016

• Install and align InGrid (upgraded windows) behind MPE-XRT• Install Relic Axion cavity detectors in CAST cold bores at MRB end

July 2016 Cooldown 4 months data taking

• 2017 (Solar Chameleons + Relic Axions) 1Q2017 Upgraded Chameleon KWISP solar tracking no magnetic field 2Q2017 Install a number of Relic axion cavities (up to 9m) in cold bores 1H2017 second part of ABB upgrade ? July 2017 Cooldown 4 months data taking KWISP and Relics Axions

• 2018 (Solar Chameleons + Relic Axions) Either: Long Data taking run with Relics and KWISP Or: 11Q2018 Open cryostat and complete installation of Relic axion cavities 2Q2016 Pumpdown and cooldown of magnet 2H2018 Data taking with KWISP and Relic axion detectors

Page 35: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Long Term schedule summary

• Transformation of CAST from Solar Axion -> Solar Chameleon + Relic Axion

sunset Magnet bores sunrise

RADES L ~ 0.2m SRMM+XRT (low energy test)?2016

CAPP 2x 0.5m L ~ 1m plus tuning KWISP -> InGrid

RADES L ~O ( 1m) depends on 2016 results t.b.d2017

CAPP L ~ O (9m) plus tuning KWISP

RADES L ~O (m) plus tuning t.b.d2018

CAPP L ~ 9m plus tuning KWISP

Page 36: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Long Term Outlook

• Program of measurements 2016 -> at least 2018 Outlined to SPSC 2 days ago

• Need safe and efficient magnet & cryo operation over 3+ years• Cryogenics Control and Supervision system relies on >20 y.o ABB PLC system

CAST is the last old ABB system at CERN Need an Upgrade to standardise Cryo Controls system based on PLCs.

• Cost of migration 250kCHF 200kCHF control racks (Granted by IEFC consolidation funds) Manpower from TE-CRG (request made to TE-CRG Group leader) 50kCHF PJAS (from CAST) to oversee the project (split 25kCHF in 2016 and 25kCHF in 2017)

Page 37: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Summary M&OA 2010-2015

• Need a further 148kCHF to have a good working balance of 100kCHF by the end of 2015

2010 2011 2012 2013 2014 2015 2016(kCHF) (kCHF) (kCHF) (kCHF) 20.09.15

Budget 357 446 327 301 255 266

Cash + in kind contributions 251.2 320.4 228.1 226.5 231.2 91.7Cash 184.3 251.5 118.3 145.2 181.4 70.8Spent 297.3 351.9 295.9 228.4 233.9 148.1

Sum promised in Addendum 389.4 278.1 368.6 398.6 371.6 177

Balance at start of year 205.4 165.5 137.4 69.0 75.6 96.0 -48.0

Percentage spent/budget 0.83 0.79 0.90 0.76 0.92

Page 38: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Conclusions• Two new techniques coming to CAST

RF cavities and Radiation Pressure Cold Dark Matter and Dark Energy

• 2016 will be packed with physics activities Installations, Commissioning and Data taking

• Financially, unfortunately … to start the new era of CAST physics No new Addendum No 8 ready

• This will take time to produce The Common Fund balance small or even negative?

• Incoming funds will be slow to arrive without a signed Addendum No8 CAST has in principle the required resources , but …

• All Institutes urged to pay asap: Their 2015 contributions Their outstanding contributions from end of Add No4

Page 39: 2014 budget report, draft budget request for 2015 and future outlook Martyn Davenport 22 October 2015 CAST FRC-D 2015-037

Balance start 2015 Cash 2015 Missing contributions

CASH 2015

Missing Funds to

break even

Balance end 2014

CAST’s own dark matter….

Missing Funds 2015 ~ 48 kCHF to break even~ 148 kCHF to maintain healthy balance

The known unknowns of CAST Finances