2014 annual report for qsn pipeline -...
TRANSCRIPT
2014 Annual Report for QSN Pipeline
Pipeline Licence 18
APA (SWQP) Pty Limited ACN 066 656 219
Version: 1
Released: 11 June 2015
An
nu
al
Rep
ort
QS
N P
ipe
lin
e –
Pip
eli
ne L
ice
nc
e 1
8
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 2 of 30
Table of Contents
1 PURPOSE .................................................................................................................................................... 4
2 SCOPE ......................................................................................................................................................... 4
3 TECHNICAL ASPECTS .............................................................................................................................. 4
4 REGULATED ACTIVITIES .......................................................................................................................... 6
5 OPERATION AND MAINTENANCE ACTIVITIES ...................................................................................... 6
5.1 Corrosion Control .............................................................................................................................. 6
5.1.1 Cathodic Protection System .............................................................................................. 6
5.1.2 CP Validation Survey ........................................................................................................ 6
5.2 Pipeline Patrol Activities ................................................................................................................... 6
5.3 Electrical & Instrumentation Maintenance Activities ......................................................................... 6
5.4 Mechanical Maintenance Activities ................................................................................................... 7
5.5 Communications/SCADA.................................................................................................................. 7
5.6 Leakage Detection ............................................................................................................................ 7
5.7 Risk Management Review ................................................................................................................ 7
5.8 Training ............................................................................................................................................. 7
6 EMERGENCY RESPONSE ......................................................................................................................... 8
7 PIPELINE CONSTRUCTION ....................................................................................................................... 8
7.1 Licence Variation .............................................................................................................................. 9
8 HEALTH SAFETY AND ENVIRONMENT ................................................................................................... 9
9 LAND MANAGEMENT ................................................................................................................................ 9
9.1 Land Owner Liaison & Public Safety Awareness ............................................................................. 9
9.2 Pipeline Location and Referral services ........................................................................................... 9
10 ENVIRONMENTAL MANAGEMENT........................................................................................................... 9
10.1 Monitoring ....................................................................................................................................... 10
10.2 Projects ........................................................................................................................................... 10
11 MANAGEMENT SYSTEM AUDITS ........................................................................................................... 10
11.1 Management System Audits ........................................................................................................... 10
11.2 Health and Safety Audits ................................................................................................................ 10
12 COMPLIANCE ........................................................................................................................................... 10
13 REPORTS .................................................................................................................................................. 11
13.1 Incident Reports .............................................................................................................................. 11
13.1.1 Incident date .................................................................................................................... 11
13.1.2 Incident Location ............................................................................................................. 11
13.1.3 DSD Incident Classification ............................................................................................. 11
13.1.4 Incident Description ......................................................................................................... 11
13.1.5 Root Cause ..................................................................................................................... 11
13.1.6 Corrective Actions ........................................................................................................... 11
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 3 of 30
13.1.7 Status .............................................................................................................................. 11
14 THREAT PREVENTION AND MITIGATION ............................................................................................. 11
14.1 Overview of Risk Management ....................................................................................................... 12
14.2 Risk Management ........................................................................................................................... 12
14.3 Specific Asset Risks ....................................................................................................................... 12
15 FUTURE WORK PROGRAM .................................................................................................................... 13
16 EXPENDITURE STATEMENT ................................................................................................................... 13
17 PIPELINE OPERATION ............................................................................................................................ 13
18 CONCLUSION ........................................................................................................................................... 13
APPENDIX 1 – ASSESSMENT OF DECLARED OBJECTIVES .................................................................... 14
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 4 of 30
1 PURPOSE
This report is submitted in accordance with the requirements of Pipeline Licence 18, the Petroleum & Geothermal Energy Act 2000 (SA) and the Petroleum & Geothermal Energy Regulations 2013 (SA).
2 SCOPE
The portion of the QSN Link & QSNE pipelines (QSN pipeline) located in South Australia is a 92 kilometre looped pipeline that runs from the Queensland / South Australian border to Moomba.
The QSN pipeline natural gas transmission pipeline system is owned, operated and maintained by the APA Group (APA).
This report is applicable to APA’s activities on Pipeline Licence 18 (the South Australia Section of the QSN Pipeline) during the period 1st January 2014 to 31 December 2014.
3 TECHNICAL ASPECTS
Table 1 QSN Link Pipeline Technical Information
Date Constructed 2008
Date Commissioned January 2009
Length 182km (90km within SA)
External Diameter 406.4mm
Wall Thickness
- Normal
- Heavy Wall (creek beds, roads)
8.1 mm
9.7 mm
Pipe Grade API 5L X70
MAOP 15,300kPa
Fluid Natural Gas
Coating 3LPE
Main Line Valves Single MLV at KP 102
Scraper Stations Scraper facilities installed within Moomba
Pressure Reduction Station (MPRS)
Meter Stations Single Meter Station at Moomba – provides
gas to both MAP & MSP
Compressor Stations Connection to Moomba Compressor Station (MCS) comprising 3 x Solar Mars 90 gas turbine compressor sets
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 5 of 30
Table 2 QSNE Pipeline Technical Information
Date Constructed 2010/2011
Date Commissioned 2011
Length 182km (90km within SA)
External Diameter 457mm
Wall Thickness
- Normal
- Heavy Wall (creek beds, roads)
9.1 mm
10.8 mm
Pipe Grade API 5L X70
MAOP 15,300kPa
Fluid Natural Gas
Coating 2FBE
Main Line Valves Single MLV at KP 102
Scraper Stations Scraper facilities installed within Moomba
Meter Station
Meter Stations Single Meter Station at Moomba – provides
gas to both MAP & MSP
Compressor Stations Connection to Moomba Compressor Station (MCS) comprising 3 x Solar Mars 90 gas turbine compressor sets
Table 3 Moomba Interconnect Pipeline (MIP) Technical Information (PL 18 component)
Date Constructed 2014
Date Commissioned 2014
Length 374 metres (chainage 821.74 to 1196.20)
External Diameter 660 mm
Wall Thickness 8.7 mm
Pipe Grade API 5L X70
MAOP 7.24 MPag
Fluid Natural Gas
Coating Trilaminate
Main Line Valves Nil
Scraper Stations Scraper facilities installed at Moomba Scraper Station (in PL 7 section of MIP) and at APA MCS
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 6 of 30
Note: The DN650 MIP has two sections. KP 0.000 to KP 0.821 is part of PL 7 and was originally constructed as the MSP Loop in the early 1980s. This component of the MIP is reported separately in the PL 7 annual report.
KP 0.821 to KP 1.196 is part of PL 18 and runs parallel to the QSN/E pipelines described above. The PL18 section of the MIP was newly constructed and commissioned in 2014.
4 REGULATED ACTIVITIES
This report a summary of the regulated activities conducted under the licence during the year.
5 OPERATION AND MAINTENANCE ACTIVITIES
APA operates and maintains the QSN natural gas transmission pipeline and its associated facilities in accordance with AS2885.3 and other relevant standards.
All Preventative, Corrective and Reactive maintenance activities are managed within APAs Works Management System. Preventative and corrective works are scheduled and monitored for completion using this system through the generation of work orders for maintenance staff to complete.
A description of the Operations and Maintenance activities for 2014 is provided below.
5.1 Corrosion Control
5.1.1 Cathodic Protection System
The original CP system including CPUs and ground-beds on the QSN pipeline was installed in 2008. As part of the construction project for the QSNE a new integrated cathodic protection system was commissioned. It was determined the existing anode ground-beds were sufficient to provide adequate capacity to accommodate the new integrated design. The impressed current cathodic protection systems in the SA portion of the pipeline are located at Moomba and at KP 102 MLV.
5.1.2 CP Validation Survey
The most recent CP survey found that the cathodic protection system is able to provide full protection when the set points and all units are functional. The construction of the new compressor station at Moomba has required one cathodic protection unit to be switched off temporarily. Protection is provided by the other two units in the vicinity.
5.2 Pipeline Patrol Activities
In 2014 routine helicopter patrols and the scheduled annual roads patrol were completed on the QSN pipeline in accordance with the maintenance plan.
Maintenance activities including inspections of above ground pipe coating condition, fences, gates, padlocks, signage, fire extinguishers, weeding and other housekeeping activities are addressed at the meter station and pressure reduction facility associated with the pipeline.
5.3 Electrical & Instrumentation Maintenance Activities
Accuracy Verification Tests were carried out in line with APA’s maintenance management system. Meter validations and calibrations occur on a 3 monthly maintenance schedule.
Electrical compliance testing was carried out on all portable electrical equipment and residual current devices (RCD’s) at all sites.
Meter Stations Metering undertaken within Santos MGP
Connection to metering facilities at APA MPRS
Compressor Stations Connection to Moomba Compressor Station (MCS) comprising 3 x Solar Mars 90 gas turbine compressor sets
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 7 of 30
Routine six monthly meter station maintenance was carried out in this reporting period. This involved calibration of all non-billing transmitters, testing all remotely operated valves, calibration of all switches and testing of all associated systems. Minor equipment failures have occurred within the reporting period with gas and moisture analysers at Moomba Inlet Station, compounding into some lost data in some cases. These issues have been resolved in early 2014.
No significant issues were reported or other significant maintenance was carried out during this period.
5.4 Mechanical Maintenance Activities
Routine mechanical maintenance activities were completed as per the maintenance schedule for the QSN pipeline system. This work involved MLV servicing, station filter inspection/replacement, vessel door closure maintenance, coalescing filter inspection/maintenance and pig launcher/receiver maintenance.
Routine inspection and maintenance activities were carried out on the pressure regulation/pressure relief systems and ESD valves at all Meter Stations on a 6 monthly basis. Maintenance tasks for the pressure control systems consisted of the inspection/overhaul of regulator seats, pilots and instrumentation filters to ensure correct operation of set points of the active/monitor and bypass regulation systems.
Pressure Safety Valves were also checked to confirm correct set point, operation and alarming functions. Where applicable, overpressure isolation valve functions are tested to ensure satisfactory operation.
All buildings and structures are inspected and maintained as part of routine maintenance procedures and confirmed in sound condition.
No significant issues were reported or other significant maintenance was carried out during this period, minor reactive faults where tended to as soon as practicable without incident.
5.5 Communications/SCADA
SCADA continued to function correctly throughout the year without incident.
5.6 Leakage Detection
APA monitors the QSN pipeline for leakage remotely from the Pipeline Control Centre and during the routine ground patrols as staff travel along the pipeline. Field staff inspect for signs of gas leakage such as dust plumes, the sound of escaping gas and dead or dying vegetation while staff at the Control Centre monitors the system pressures, flows and alarms.
During 2014, other than the reportable incident noted in section 13.1 below, there were no instances of any material leaks on valves or equipment on the QSN pipeline.
5.7 Risk Management Review
The QSN Link pipeline was constructed in 2008, and formal risk assessments, reviews and analysis were completed as part of the design, construction and commissioning process. All the action items raised in that original risk assessment were completed.
The QSNE Link pipeline was constructed and commissioned in 2011. Again, the necessary formal risk assessments, reviews and analysis were completed as part of the design, construction and commissioning process. All the action items raised in that original risk assessment were completed.
A SMS / risk assessment was conducted for the QSN Pipeline in August 2013. This assessment took place in the APA Brisbane office and was attended by the appropriate APA operational and engineering staff. The safety management study concluded that the QSN Link Pipeline meets the requirements for Safety Management Studies of AS2885.1-2012
5.8 Training
APA is committed to developing the skills of all employees and contractors to meet the operational and technical needs of its business.
During 2014 staff training was conducted in-house using a number of techniques which included training courses developed specifically for APA.
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 8 of 30
In addition to internal training, staff attended a range of external courses, conferences and seminars selected to further enhance their knowledge of the natural gas and liquid hydrocarbon pipeline transmission industry.
The range of training staff attended during 2014 included, but was not limited to;
• Clear SCADA training • APA Permit to Work • Emergency response • Drugs & alcohol policy • Isolation • 4WD training • Fire Prevention & Control • First aid • Field Induction • Excavation of Pipelines • Gas detection, Instrumentation • JHA
6 EMERGENCY RESPONSE
An emergency response exercise was conducted on pipeline licence 18 during the reporting period.
The mobilisation exercise provided practice of the procedures for handling the various implications, technical and otherwise, of a major complex event which has the potential to adversely affect the environment, public health and safety and the security of supply of natural gas and also the company’s performance, value, or reputation. In particular the exercise was conducted in order to:
• Verify the role played by the control room to ensure the safety of travelling staff; • Verify the notification and escalation processes, including mobilisation, command, and operation of
the APA Group Operations within the Queensland Transmission division; • Practise the use of all relevant procedures, guidelines, and checklist actions contained in the APA
Group Queensland Transmission emergency response plan and review their effectiveness; • Practise preparation of outgoing messages and handling of calls in an emergency, including
dealing with key stakeholders, emergency services, and relatives / next of kin of injured staff; and review their effectiveness;
• Test the adequacy of the various facilities, equipment, and infrastructure required to respond, including the support which may be required from emergency services and other parts of the organisation.
• Practice the activation of an Emergency Room and review its effectiveness.
The exercise was specifically designed not only to test these objectives but also to provide a constructive learning environment for all participants and was not conducted to test or highlight individual performance.
The exercise took place on 14 May 2014 on site at MLV102 – Moomba, South Australia and the emergency management team was based at the Spring Hill emergency response room, Queensland.
The findings of the exercise confirmed the adequacy of emergency response procedures and included positive observations and opportunities for improvement. In general, the emergency response process was executed fluently, with personnel involved understanding their role in the exercise.
7 PIPELINE CONSTRUCTION
Construction and commissioning of the Moomba compressor station, the expansion of Moomba Pressure Reduction Station and the Moomba Interconnect Pipeline was completed during the reporting period. The Station became operational in September 2014. This modification converted the QSN/E pipelines to allow bi-directional flow. Gas can now be transported from Queensland and supplied to the MSP and MAP (Western Haul), or transported from the Santos MGP into Queensland (Eastern Haul).
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 9 of 30
The compressor station also utilises a portion of the 660mm Moomba bypass pipeline (PL7) to feed gas from Moomba through to the compressor station. Following completion of the compressor station, works commenced in 2014 to install additional pipework and re-configure the station to facilitate the backhauling of gas from the Moomba Sydney Pipeline. This is known as the Moomba Compressor Station Variation 1 (V1) Scope.
7.1 Licence Variation
The Pipeline Licence was varied in respect of the above.
8 HEALTH SAFETY AND ENVIRONMENT
APA Group recorded no LTI, MTI or environmental incidents on the pipeline in South Australia during the reporting period.
APA has implemented a HSE Management System called Safeguard to comply with the national work health and safety requirements.
Safeguard provides a framework by which the processes relating to the company's Health, Safety and Environment (HSE) activities are written, approved, issued, communicated, implemented and controlled.
Safeguard applies to all HSE-related matters arising out of all activities and operations controlled by APA and its related companies (together the company) and the impact of those activities and operations on employees, contractors, the environment and the communities in which the company operates.
Additionally, Safeguard (Including HSE Policies) is also subject to review and improvement to ensure objectives and obligations are continually satisfied, including:
• Performance, measurement and reporting; • Management review; and • Audit and self-assessment.
The above requirements are supported by APA Group procedures. The HSE policy is a controlled document subject to three yearly reviews as a minimum.
9 LAND MANAGEMENT
9.1 Land Owner Liaison & Public Safety Awareness
The landowner liaison program includes a landowner package being sent to landowners and direct liaison as required.
Council and Emergency services are contacted and, where possible, gas awareness presentations delivered as per APA Stakeholder Management program.
9.2 Pipeline Location and Referral services
APA provides a free “dial before you dig” service which third parties can call to locate any pipeline infrastructure prior to undertaking any construction activities. The service is primarily used by other companies and third parties carrying out civil works in the vicinity of the pipelines and other buried utilities.
10 ENVIRONMENTAL MANAGEMENT
There were no environmental incidents during the report period.
An assessment of compliance against the SEO objectives in regards general maintenance activities is included in Appendix 1.
During the reporting period all environmental requirements as detailed in the Statement of Environmental Objectives were complied with.
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 10 of 30
10.1 Monitoring
Ongoing environmental monitoring of PL18 is intended to ensure effective rehabilitation has occurred along the pipeline route. The most recent monitoring included ground patrols and a helicopter flyover of the pipeline route to assess vegetation regrowth, erosion and subsidence and to confirm the effectiveness of previous subsidence repair work.
Overall it was determined that the QSN pipeline route was generally in good condition. Minor subsidence at Strezlecki Creek, KP120, will continue to be monitored and managed.
Right of Way maintenance, including minor subsidence and erosion identified between KP0 and KP160, is scheduled to occur between April and June 2015.
10.2 Projects
A CEMP was submitted setting out the environmental management practices and procedures to be implemented during construction of additional pipework at the Moomba Compressor Station to meet the environmental requirements of the Project. These requirements are documented in:
• the QSN Pipeline Statement of Environmental Objectives (SEO); and • the Moomba Compression Services Variation 1 (MCS V1) Project Construction Environmental
Management Plan.
11 MANAGEMENT SYSTEM AUDITS
APAs auditing program offers the opportunity to identify and promote continual improvement within APA.
11.1 Management System Audits
An independent audit of the APA Pipeline management System by external auditors Ken Cameron & Associates is scheduled to occur during June 2015.
APA completed a number of management system audits during the year under its internal audit program.
11.2 Health and Safety Audits
An internal audit schedule of the Safety Management System was maintained during 2014.
12 COMPLIANCE
APA ensures that the pipeline is operated in accordance with the relevant Acts of Parliament, licence conditions and the requirements of AS2885.
APA attends quarterly compliance meetings with DSD, where operational regulatory compliance is discussed in an open manner.
Changes in legislation are tracked and communicated through a The Technical regulatory Manager.
APA maintains a compliance database, MARCIS, which tracks legislative compliance throughout the organisation. Obligations are assigned to responsible staff, who must supply evidence that the obligation has been satisfied within a specified time period.
APA is not aware of any regulatory non-compliance for this pipeline, and believes it is fulfilling its obligations in relation to the following requirements:
• The Petroleum & Geothermal Energy Act 2000 • The Petroleum & Geothermal Energy & Regulations 2013 • Pipeline Licence (PL18) • The Statement of Environmental Objectives
APA Group maintains an action tracking system for improvements to its systems, which is fully traceable through to close out of individual items.
Significant items are reported through to DSD, and would be raised at the quarterly compliance meetings held between DSD and APA.
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 11 of 30
There have not been any significant regulatory compliance issues during this reporting period.
13 REPORTS
The following reports were generated and forwarded to DMITRE during the reporting period;
• PL18 2014 Annual report • MCS V1 Activity Notification • MCS V1 Design Basis Manual • MCS V1 Project AS2885 1 Design Compliance Register • MCS V1 CEMP • MCS V1 SIL Closeout report • MCS V1 HAZOP Closeout Report • MCS V1 SMS Closeout report • MCS V1 PL18 Licence Variation Application
13.1 Incident Reports
During the reporting period there were no “Serious Incidents” and one “Reportable Incident”. The reportable incident was reported later than required under Petroleum and Geothermal Energy Regulations 2013 s32(5). An overview of the reportable incident is provided below.
13.1.1 Incident date
The incident occurred on 23rd October 2014.
13.1.2 Incident Location
The incident occurred at the MLV102 site located at KP 102 on the QSN pipeline, near Innamincka SA.
13.1.3 DSD Incident Classification
Design
13.1.4 Incident Description
The threaded cavity vent connector on a ball valve failed during operation of the ball valve, causing the cavity vent assembly to detach from the ball valve and leading to a localised release of gas. A second vent connector was also observed to have failed at a previous time.
13.1.5 Root Cause
The root cause of the failures was assessed as vibration-induced fatigue of the threaded connectors. The design of the cavity vent assembly was such that the connectors were subjected to bending loads and vibration from the adjacent pressure control valve.
13.1.6 Corrective Actions
• The site was initially made safe and the affected valves isolated and tagged out of service. • An engineering and metallurgical investigation was completed to assess the root cause. • Replacement cavity vent assemblies were sourced and installed using a modified design. • Overhaul and vibration assessment of the pressure control valve has commenced.
A review of similar sites has commenced to identify other valves that may be at risk of similar failure (cantilevered connector design and subject to vibration).
13.1.7 Status
In progress.
14 THREAT PREVENTION AND MITIGATION
There are no reasonably foreseeable threats on this pipeline.
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 12 of 30
14.1 Overview of Risk Management
APA Group recognises that risk management is an integral part of good management and that managing risk is a fundamental part of its business so that actions and activities do not unduly expose the asset, its personnel or the public or the environment to unacceptable risks.
The risk management process consists of well-defined steps which, taken in sequence, support better decision-making by contributing to a greater insight into risks and their impacts. The risk management process can be applied at many levels within APA Group and can be applied to specific projects, to assist with specific decisions or to manage specific recognised risk areas. APA Group recognises that risk management is a multi-faceted process, which is often best carried out by a multi-disciplinary team with an intimate knowledge of the pipeline.
APA Group’s risk management processes aligns with the Pipeline Integrity Management requirements as defined by AS2885.3 and comprises the following components:
• Technical risk management as per AS 2885; • Facilities HAZOPs/Internal Hazard Audits; • Risk management, including Health, Safety and Environmental (HSE) risk, as per APA Group’s
corporate policies; • Environmental Management Plan as per Australian Pipeline Industry Association (APIA) Code of
Environmental Practice and Queensland Environmental Acts; and • MAOP reviews as per AS 2885;
All facilities and equipment are currently being operated and maintained to AS 2885.3, Original Equipment Manufacturers (OEM) operation and maintenance recommendations and good industry practice.
14.2 Risk Management
The company has exposure to a wide variety of risks. The following are some of the most relevant:
• Frequent vehicle travel incident - Major (LTI or Vehicle write-off) • Lifting loads near the exposed pipeline • Hot work • Moveable plant in hazardous areas • Use of and maintenance of gas transportation facilities, other than high-pressure gas pipeline
lines • Isolating pipe work • Storms/lightning • Equipment theft and damage • Low operational availability (reduced availability of competent, skilled qualified personnel due to
sickness) • Corrosion and Stress Corrosion Cracking • CAD welding • Floods • Seismic events • Aviation travel • Third party excavation activities near buried pipelines • Electrical hazards on pipelines due to lightning or overhead powerlines
14.3 Specific Asset Risks
Risks of higher significance include:
• For remote pipelines, exposure to prolonged long-distance driving. This risk is mitigated by driver training courses coupled with stringent remote travel requirements including remote monitoring by the Control Centre.
Asset risks are mitigated and monitored via APA work programs and systems including but not limited to:
• Aerial Patrols • Landowner and Third Party Liaison • SCADA monitoring • Maintenance programs • Safeguard implementation
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 13 of 30
15 FUTURE WORK PROGRAM
All maintenance operations will continue to be completed as scheduled to ensure that the integrity of the pipeline system is being maintained, as well as the safety and efficiency of APA Group’s operations.
The following specific activities are planned for FY15:
• The modification of the Moomba Compressor Station by the installation of additional pipework and re-configuration of the station.
16 EXPENDITURE STATEMENT
17 PIPELINE OPERATION
12,077.69 TJ of natural gas was transported through the QSN pipeline during the 2014 period.
18 CONCLUSION
The maintenance and inspection programs carried out on the QSN Pipeline in 2014 have indicated the pipeline is in sound condition and is capable of operating at set parameters with no restrictions.
The CP Survey results indicate the protection levels are adequate to provide suitable protection for the pipeline.
The pipeline is considered to be in good working condition and well maintained.
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 14 of 30
APPENDIX 1 – Assessment of Declared Objectives
During the reporting period all activities were undertaken in accordance with APA Management Systems, Construction Management Plan, Environmental Line List and Procedures.
Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /
Not Achieved
Comments
1. To avoid or minimize adverse impacts on soils and terrain during construction and operation and to maintain soil stability / integrity on the easement
1.1 To minimize soil erosion and sedimentation as a result of pipeline construction and to remediate in a timely manner when due to operations
Alignment selection to avoid or minimise impacts on erodible soils and steep terrain
Construction Environmental Management Plans (CEMP’s) contains environmental work procedures (EWP) that specify soil management and reinstatement requirements
Implementation specific requirements based on soil type and erosion risk e.g. in gibber, minimise gibber disturbance, roll areas rather than clearing where traffic levels will not be high, carefully stockpile gibber and replace in reinstatement
Preventative measures implemented and monitored in susceptible areas
Erosion and sedimentation control structures installed and maintained in susceptible areas
Records of induction/training regarding CEMP’s/EWP requirements
Regular inspections of construction areas undertaken to look for evidence of erosion
The extent of soil erosion on the easement is consistent with surrounding land
0, +1 or +2 GAS criteria are obtained for borrow pit construction and restoration, as listed in Appendix 3
Achieved
The pipeline was
completely reinstated
following completion of
construction of the
QSN3.
A CEMP was
implemented for the
construction of the
Moomba Compressor
Station.
1.2 To reinstate soil and terrain as near as practicable to pre-construction contours and conditions
Implement reinstatement requirements specified in CEMP’s and EWP Records of induction/training regarding CEMP’s/EWP requirements Regular inspections undertaken of easement and construction areas Installation and monitoring of photo points (environmental monitoring points)
Surface contours consistent with adjacent land
0, +1 or +2 GAS criteria are obtained for borrow pit restoration, as listed in Appendix 2
Achieved Ongoing monitoring shows that reinstatement has occurred along the length of the pipeline route.
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 15 of 30
Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /
Not Achieved
Comments
1.3 To mitigate soil compaction if necessary by remedial action
Ripping of identified compacted areas where appropriate to soil type and erosion risk (i.e. generally avoid ripping in gibber)
Regular inspections undertaken of easement and construction areas to look for evidence of soil compaction
No visual evidence of soil compaction following remediation of pipeline easement (e.g. hard soil, local water pooling)
Achieved No evidence of compaction.
1.4 To prevent soil inversion
CEMP’s/EWP requirements include separate stockpiling of topsoil and sub-surface material during excavation
Records of induction/training regarding CEMP’s/EWP requirements
Reinstatement of stockpiles in appropriate order during backfill
No evidence of subsoil on surface (colour).
Vegetation cover consistent with surrounding land.
No reasonable landholder complaints
Achieved No reasonable landholder complaints were received during the reporting period.
Annual land survey to look for soil discolouration, success of vegetation return as an indicator.
Disturbance checklist signed off to indicate top soil/subsoil are stockpiled separately and soil profiles appropriately reinstated following the re-instatement of works/excavations
Vegetation cover is consistent with surrounding land
No evidence of subsoil on surface (colour)
No reasonable landholder complaints
1.5 To remediate erosion or subsidence as a result of pipeline operations in a timely manner
Timed photo points or regular land survey, specifically to look at evidence of erosion, subsidence, vegetation loss on easement & compare to adjacent land
Inspections undertaken as part of regular patrols, following specific works, following significant storm events
Preventative measures implemented and monitored in susceptible areas
No un-remediated subsidence
The extent of soil erosion on the easement is consistent with surrounding land
No excessive erosion on areas adjacent to corridor as a result of easement
No reasonable landholder complaints
Achieved Areas of soil erosion and subsidence have been identified and documented. These are in the process of being managed.
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 16 of 30
Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /
Not Achieved
Comments
2. To minimise and manage impacts to water resources
2.1 To minimize short term, and prevent long-term, interruption or modification to surface drainage patterns
Alignment selection to minimize impacts to water resources e.g. select watercourse crossing locations that minimize erosion potential and impacts to the watercourse
Management requirements specified in CEMP’s/EWP
Records of induction/training regarding CEMP’s/EWP requirements
Installation and subsequent removal of appropriate temporary watercourse crossing measures
Regular inspections undertaken of easement and construction areas specifically to look at watercourse crossings
Installation and monitoring of photo points (environmental monitoring points)
No adverse impacts (for example to downstream ecology or land use) resulting from watercourse flow reductions or diversions as a result of pipeline construction activities
No evidence of altered watercourse flows following reinstatement
No evidence of project related erosion of watercourses intersecting or adjacent to the pipeline easement
Surface drainage profiles restored
Drainage is maintained to pre-existing conditions or better
Achieved Subsidence at
Strezlecki Creek
(KP120.4) is in the
process of being
managed.
2.2 To minimize the amount of sediment entering surface water features
CEMP’s/EWP specify management requirements including:
No stockpiling of materials in watercourses/ flowlines (note: trench spoil may be stockpiled in dry watercourse beds for very short periods e.g. less than a day)
- Use of appropriate sediment and silt capturing devices
- Installation of permanent berms on slopes - Minimising period between clearing and
reinstatement at or near watercourses - Stabilisation and reinstatement of watercourses
and drainage lines Records of induction/training regarding CEMP’s/EWP requirements
Compliance with EPA Environment Protection
(Water Quality) Policy 2003
Achieved Permanent erosion controls have been installed where appropriate to manage sedimentation issues.
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 17 of 30
Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /
Not Achieved
Comments
2.3 To minimise disruption to third party use of surface waters
Alignment selection to avoid or minimise disturbance to third party uses e.g. stock watering points
Liaison with third party users regarding potential disruptions
Minimising period of disturbance and prompt reinstatement in sections of easement intersecting or adjacent to water bodies
Installation and subsequent removal of appropriate temporary watercourse/water body protection measures to prevent flow interruptions
No reasonable complaints received from landholders or third party users in relation to use of surface waters
Achieved During the reporting period there were no complaints from landholders or third parties in relation to the use of surface water.
Minimizing period of disturbance for any excavation or land disturbance and prompt reinstatement of easement in sections of easement intersecting or adjacent to water bodies
2.4 To maintain current surface drainage patterns
Regular patrols and survey undertaken to look for evidence of erosion, windrow development, abnormal vegetation growth or death or any changes to the easement which could change surface hydrology conditions, particularly in the Strzelecki Creek wetland area
Observations also to be undertaken following significant storm events
Use of disturbance checklist and photo points before, during & after excavations, CP installation, construction activities, etc.
For excavations, surface drainage profiles restored
For existing easement, drainage is maintained to pre-existing conditions or better.
For borrow pits, surface drainage profiles are not disturbed.
Achieved No excavations were carried out in 2014.
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 18 of 30
Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /
Not Achieved
Comments
3. To avoid land or water contamination
3.1 To prevent spills occurring and if they occur minimize their impact
Regular inspections for evidence of soil or water discolouration, vegetation or fauna death
Use of spill protection methods where work is completed within or adjacent to environmentally sensitive areas
Spill response/cleanup procedures, requiring spills to be:
- reported - contained - cleaned-up - cause investigated and corrective and/or
preventative action implemented
Spills/contamination remediated in consultation with regulatory agencies and landholder
Ensuring personnel are trained in spill response procedures Appropriate spill response equipment is available on site Compliance with fuel and hazardous waste standards
Containment of all fuel, oil, hazardous substances and liquid waste in appropriate vessels/containment areas (e.g. polythene lined, bunded areas or on bunded pallets)
Bunded areas must have sufficient freeboard (e.g. to hold a 1:100 year, 24hr rainfall event)
Bunded areas in accordance with EPA Guideline for Bunding and Spill Management 080/12.
Incident / Spill reports
Prevention program including pigging, intelligent pigging and pipe maintenance.
No soil or water contamination as a result of spills during pipeline construction activities.
Compliance with Environment Protection Act
Achieved There were no reported spill incidents in SA in 2014.
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 19 of 30
Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /
Not Achieved
Comments
3.2 To ensure that rubbish and waste material are disposed of in an appropriate manner
Waste management requirements specified in CEMP’s/EWP, including: - Provision of covered bins for the collection, storage and transport of wastes; - Waste disposal at an approved waste facility
Regular inspection to look for evidence of rubbish, spills (soil discolouration)
Waste disposal records, chemical manifests. Appropriately licensed contractors used for any hazardous waste disposal and records are maintained for all hazardous waste disposal
No pipeline related rubbish or litter on easement or at facilities or on surrounding land
Waste material is contained and disposed of in accordance with Environment Protection Act and approved procedures.
Achieved Regular inspections and monitoring have been undertaken to ensure that waste materials been disposed of.
Waste is managed in accordance with APA Waste Management Procedures.
Hazardous waste is collected by licensed carriers and Waste Transport Certificates filed.
3.3 To prevent impacts as a result of hydro test water, trench water and waste water (e.g. wash-down water) disposal
Water disposed of in a manner that prevented discharge or runoff to watercourses or environmentally sensitive areas
Water discharged onto stable ground, with no evidence of erosion as a result of discharge
Records on source of water and discharge method/location
Investigation of water quality prior to release/disposal of trench water and waste water. Testing of hydro test water if potentially harmful chemicals added.
Inspection of water disposal sites for evidence of water entering a watercourse or environmentally sensitive area.
Compliance with the Environment Protection (water quality) Policy.
Discharge water meets appropriate ANZECC and EPA criteria for point of disposal
No evidence of impacts to soil, water and vegetation as a result of water disposal (e.g. soil erosion, dead vegetation, water discoloration)
Achieved No wastewater was disposed to land in 2014
No activities were undertaken by APA on the QSN Link that would cause any impact on land or water resources quality on the pipeline during the reporting period
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 20 of 30
Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /
Not Achieved
Comments
3.4 To ensure the safe and appropriate disposal of camp wastewater (grey water, sewage)
All wastewater disposed in accordance with the South Australian Public Health (Wastewater) Regulation 2013.
The method of disposal for wastewater must
a) comply with the SA Health On site Wastewater Systems Code; or
b) be to the satisfaction of the Department for Health and Ageing, see Objective 11 below as well.
Treated sewage wastewater disposed of onto land, well away from any place from which it is reasonably likely to enter any waters in accordance with the Environment Protection (water quality) Policy.
Waste water disposal system must comply with the e SA Health On site Wastewater Systems Code; or be to the satisfaction of the Department for Health and Ageing.
Achieved All wastewater is
disposed of by a
licensed carrier.
4.To minimize adverse impacts to vegetation and fauna
4.1 To minimise clearing of remnant vegetation
Alignment selection to minimise crossings of drainage lines and ephemeral wetlands and avoid or minimise impacts to vegetation with high habitat values (e.g. large trees)
CEMP’s and alignment sheets identify remnant vegetation requiring management / avoidance
Flagging/marking of remnant vegetation requiring management /
avoidance
Retain trees on Easement where possible
Trim vegetation in lieu of removal where possible
Restrict disturbance to the Easement and approved access and work areas
Reduction of ROW width during construction in identified significant areas
Obtain any permits / clearance consent required
Vegetation clearing is in accordance with the
Native Vegetation Act 1991
Vegetation clearance minimised
No unauthorised clearance of flora identified to be retained
0, +1 or +2 GAS criteria are obtained for borrow pit construction and restoration, as listed in Appendix 3
Achieved There was no vegetation clearance in 2014.
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 21 of 30
Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /
Not Achieved
Comments
4.2 To minimize disturbance to fauna
Implement previous measures to minimise impacts to native vegetation
Identification and flagging of significant fauna habitats (e.g. large trees) that require management/avoidance during construction and implementation of management requirements
Alignment selection to minimise/avoid impacts to important habitats
Provision of fauna ramps at regular intervals in open trench
Daily inspection of open trenches and removal and identification recording of trapped fauna by appropriately trained and experienced biologists
Prompt reinstatement of easement
Borrow pits are restored to minimise water holding capacity where agreements are not in place with stakeholders
No domestic pets allowed at camps or worksites
No feeding of wildlife (e.g. dingoes)
Native fauna casualties associated with construction restricted to as low as reasonably practical
Achieved No impacts to fauna from activities in 2014.
4.3 To appropriately rehabilitate the easement to pre-construction condition, as reasonably practical
Implement reinstatement requirements specified in CEMP’s and EWP Timely response to rehabilitation
Installation and monitoring of photo points (environmental monitoring points)
Vegetation on the easement is reasonably consistent with the surrounding areas
Note: assessment of the consistency with surrounding areas will take into account that regrowth is a time and rainfall dependent process
0, +1 or +2 GAS criteria are obtained for borrow pit restoration, as listed in
Achieved Environmental monitoringpoints were installed at 14 locations along the QSN Link.
There is evidence of vegetation regrowth along the length of the ROW.
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 22 of 30
Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /
Not Achieved
Comments
Appendix 3
No reasonable complaints received from landholders in relation to regrowth of vegetation on the easement
4.4 To achieve a significant environmental benefit for native vegetation clearance
Work (or payment to Native Vegetation Fund) undertaken to achieve a significant environmental benefit, as required by Native Vegetation Regulation 5(1)(zd)
Significant Environmental Benefit (SEB) requirement either:
- determined using the “Methodology for calculating total SEB requirements” outlined in the Guidelines
3, or
- negotiated with the Native Vegetation Council where SEB calculation differs from the standard methodology in the Guidelines. (Note: The Guidelines have provision for case-by- case assessment of significant environmental benefit by the NVC in some circumstances e.g. where SEB capping or additional mitigation measures apply)
Significant environmental benefit approved by DMITRE (where delegated authority applies) or Native Vegetation Council
Significant environmental benefit obligation satisfied / implemented
Achieved There was no vegetation clearance in 2014.
4.5 To promote and maintain regrowth on the easement to be consistent with surrounding area
Annual land survey to assess vegetation rehabilitation and look for evidence of disturbance to vegetation on easement (apart from access tracks)
Disturbance Checklist (including timed and photos) signed off to indicate adequate steps taken to facilitate regrowth
Follow-up rehabilitation work undertaken where natural regeneration is inadequate
Species abundance and distribution on the easement is reasonably consistent with surrounding areas
Note: assessment of the consistency with surrounding areas will take into account that regrowth is a time and rainfall dependent process
Achieved Regrowth on the
easement is observed
to be consistent with
the surrounding
environment.
No borrow pits were utilised during the reporting year.
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 23 of 30
Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /
Not Achieved
Comments
4.6 To minimize additional clearing of native vegetation as part of operational activities
Annual land survey to look for evidence of disturbance to vegetation on easement (apart from access tracks)
Use of Disturbance Checklist and photo points before, during & after any excavation or land disturbance activity
Vegetation trimmed rather than cleared where possible
Consideration of sensitive vegetation, including large old trees, during vegetation trimming and / or clearing activities. Obtain any clearance consent required
Location of temporary camps in naturally clear areas or on previously cleared sites.
Vegetation clearing within the easement or on land adjacent to the easement is limited to previously disturbed areas, unless prior regulatory approval obtained under the Native Vegetation Act 1991
Achieved There was no additional clearing in 2014 for operational purposes.
4.7. To ensure operational maintenance activities are planned and conducted in a manner that minimizes impacts on native fauna
Use of Disturbance Checklist and photo points before, during & after any excavation or land disturbance activity
In the event of excavations, open trenches monitored regularly and left open for the minimum time practical
Procedures or management plans implemented for significant fauna species
Provision of fauna ramps at regular intervals in open trench
Daily inspection of open trenches in areas adjacent to remnant vegetation
Prompt reinstatement of easement
Native fauna casualties associated with operations restricted to as low as reasonably practical
Achieved During the reporting period no operational activities were undertaken that would cause disturbance to native fauna on the pipeline.
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 24 of 30
Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /
Not Achieved
Comments
5. To avoid the spread of weeds and pathogens
5.1 To avoid the introduction or spread of weeds and pathogens and undertake control where required
Vehicles and machinery cleaned and inspected before entry to project area
Identification of weeds and pathogens on easement and adjacent land
Implementation of control measures of weeds and pathogens on easement and liaison with the regional Native Resources Management (NRM) Board and the landholder as necessary
Records of outbreaks found, weed control activities and photo- monitoring of significant outbreaks
Vehicle cleaning/wash-down register
Regular patrols undertaken to look for evidence of weeds on easement and adjacent land (if weeds on easement but not adjacent land must implement control to prevent spread).
The presence of weeds on the easement is consistent with or better than adjacent land
No new outbreak or spread of weeds or pathogens as a result of pipeline activities
Achieved No weed outbreaks have been identified on the QSN Link.
No declared or non declared weed species were observed along the easement.
6. To minimize and manage impacts to heritage sites and values during construction, operations and maintenance
6.1 To ensure that identified heritage sites are not disturbed
Alignment selection to avoid heritage sites, including archaeological and ethnographic heritage, built heritage and culturally significant vegetation
Identification of known heritage sites on easement prior to construction
Measures undertaken to protect heritage sites on or near the easement
Implement appropriate protocols for dealing with accidental discovery of cultural heritage material during construction
Obtain all necessary approvals in the event of an accidental/unavoidable site disturbance
Seek advice from relevant authorities for remediation of
No impact to known sites without approval under the Aboriginal Heritage Act 1998 or the Heritage Places Act 1993
Any new sites identified are reported to appropriate authority and recorded
0, +1 or +2 GAS criteria are obtained for borrow pit construction and restoration, as listed in Appendix 2
Achieved There are a number of
cultural heritage sites
on the QSN Link.
Flagging and signage at
known heritage sites
adjacent to the
easement was removed
in 2012.
An electronic
management system
was developed and
implemented to ensure
sites are protected from
harm. Field personnel
received face to face,
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 25 of 30
Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /
Not Achieved
Comments
site, if required
Induction/training to include heritage management requirements
- Incident reports
Consultation with relevant heritage groups if operations occurring outside known surveyed areas
Site examined for cultural heritage material prior to work involving disturbance outside known surveyed areas
Records of site locations in Operations GIS
Use of Disturbance Checklist and photo points before, during & after any excavation or land disturbance activity
intensive training
regarding cultural
heritage responsibilities
and control measures.
There have been zero cultural heritage breaches.
7. To minimise noise due to construction and operations
7.1 To minimize noise impacts associated with the movement and operation of construction vehicles and equipment
Regular maintenance of construction vehicles and equipment
Incident reports
Facilities designed to meet the noise requirements under the Environment Protection Act
Incident reports
Monitoring results, where deemed necessary (e.g. frequent complaints)
Construction activities comply with noise regulations under the Environment Protection (Noise) Policy 2007.
Operation activities comply with noise regulations under the Environment Protection (Noise) Policy, 2007.
No reasonable complaints received
Achieved No reasonable complaints received in relation to noise management during the project.
No operational activities were undertaken that would cause any impact on environmental noise and emissions on the pipeline
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 26 of 30
Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /
Not Achieved
Comments
8. To minimize atmospheric emissions
8.1 To minimize the generation of dust
Management requirements specified in CEMP’s/EWP including use of water trucks and sprayers if necessary
Compliance with EMS and operations procedures
Records of induction/training regarding CEMP’s/EWP requirements
Incident reports
Compliance with Environment Protection Act or to the satisfaction of the EPA.
No reasonable complaints received
Achieved No incident reports or complaints were received during the reporting period in relation to dust.
8.2 To eliminate uncontrolled atmospheric emissions
Maintenance procedures
Incident reports
No uncontrolled atmospheric emissions (e.g. due to malfunction or mis-operation)
Achieved During the reporting period no operational activities were undertaken that would cause any impact on the environment due to uncontrolled emissions on the pipeline
8.3 To comply with air quality requirements
Compliance with Environment Protection (Air Quality) Policy 1994.
Compliance with Environment Protection (Air Quality) Policy 1994. No non-compliances noted or received.
Achieved No non-compliances were noted or received during the reporting period.
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 27 of 30
Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /
Not Achieved
Comments
9. To minimize disturbance to third party infrastructure, landholders and land use
9.1 To minimize disturbance or damage to infrastructure / land use and remediate where disturbance cannot be avoided
Alignment selection to avoid or minimise impacts to infrastructure / land use and visual impact
Formal easement agreements outlining the legal responsibilities of APA Group and landholders
Management requirements specified in CEMP’s/EWP
Restrict disturbance to the ROW and approved access and work areas
Identification of utilities present on or near the easement on alignment sheets
Records of communications with landholders / third party prior to and during construction activities
Incident reports
Compliance with the National Parks and Wildlife Act 1972 and Regulations pertaining to correct conduct in a Regional Reserve
No pets or firearms brought into Regional Reserve
Management of fuel, oil and spills (if they occur) to meet landholder requirements for Quality Assurance programs (e.g. Cattlecare)
Records of communications with adjacent landholders / third party prior to and during maintenance work
Landholder contact records database
Use of Disturbance Checklist (including photo points) or inspection reports, specifically to look at: removal of waste products, re- instatement of soil profiles, adequate re-contouring of surface profile, return of land use
Measures undertaken to minimize third party use right-of-way where necessary
Where disturbance is unavoidable or accidental, infrastructure or land use is restored to the satisfaction of the landholder/owner or as near as practicable to undisturbed condition
Duration of disturbance does not exceed agreed timeframe
No disturbance outside the ROW and approved access and work areas
No reasonable complaints received
Adverse impacts to Innamincka Regional Reserve operations or conservation values are minimized
Achieved Records of ongoing liaison with landholders maintained.
There have been no reported spill incidents.
During the reporting period no operational activities were undertaken that would cause any impact on third party infrastructure and landholder on the pipeline. No complaints were received.
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 28 of 30
Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /
Not Achieved
Comments
9.2 To minimize disturbance to landholders
Restrict disturbance to the ROW and approved access and work areas
Landholder activities not restricted as a result of pipeline activities
Records of communications with landholders / third party prior to and during construction activities.
Records of communications with adjacent landholders / third party prior to and during maintenance work
Landholder contact records database
Use of Disturbance Checklist and photo points
No reasonable landholder complaints
Landholder activities not restricted or disturbed as a result of pipeline activities unless by prior arrangement
Achieved During the reporting period no operational activities were undertaken that would cause any impact on landholders on the pipeline
Records of ongoing liaison with landholders maintained. No reasonable complaints received.
9.3 To appropriately reinstate and rehabilitate the easement to allow continuation of current land use activities post-construction
Management requirements specified in CEMP’s and property line list Reinstatement of easement in accordance with CEMP’s/EWP Records of communications with landholders prior to and during construction activities
Installation and monitoring of photo points (environmental monitoring points)
Species abundance and distribution on the easement is reasonably consistent with surrounding areas
Note: assessment of the consistency with surrounding areas will take into account that regrowth is a time and rainfall dependent process
Achieved There is evidence of vegetation regrowth along the length of the ROW.
10. To minimize the
risk to public health
and safety
10.1 To prevent injury to general public and adequately protect public safety during operations
Construction area cordoned off, entry to construction area from general public prohibited. Warning signs, tape, markers used to warn of restricted access area. Job Hazard Analysis
Records of communications with adjacent landholder prior to and during maintenance work including advice of the nature and schedule of maintenance activities
Use of signage or bunting to identify all potentially hazardous areas
Site induction program for all personnel/visitors.
Adequate implementation of traffic management
No reports of general public in construction area No injuries or incidents involving the public
Achieved
Established safe systems of work including the use of approved work instructions and procedures, job hazard analysis, permit to work and experienced staff all contributes to APA meeting this objective
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 29 of 30
Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /
Not Achieved
Comments
practices
Records of Annual Reports, Fitness for Purpose Reports, Risk Assessments and inspections
Records demonstrating compliance with AS2885
Records of emergency response plan induction/training for construction, operation and maintenance personnel.
Incident Reports
Job Hazard Analysis
During the reporting period there were no operational activities that impacted upon public safety on the pipeline
10.2 To avoid fires associated with pipeline maintenance activities
Records of regular fire safety and emergency response training for construction, operations and maintenance personnel and review of procedures.
Established procedures for minimizing fire risk during maintenance
Appropriate fire prevention/control equipment on site
Incident reports
No fires related to pipeline construction, operation or maintenance activities
Achieved During the reporting period there have been no pipeline related fires
10.3 To prevent unauthorized activity on the easement that may adversely impact on the pipeline integrity
Inspection/Patrol reports and records
Comprehensive landholder liaison program and records of all communications with landholders
Community education program and Dial Before You Dig (DBYD) number and web page available and widely advertised.
Clear identification of the pipeline by signs installed in accordance with AS2855.
All reports of unauthorized activity are reported and investigated
No unauthorized activity on the easement that has the potential to impact on the pipeline integrity
Achieved During the reporting period there have been no unauthorized activities.
2014 Annual Report – QSN Pipeline
Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 30 of 30
Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /
Not Achieved
Comments
11. To minimize
risk to the public
from Wastewater
11.1 To ensure that all wastewater (not from industrial processes) is collected, treated and disposed of so as to not adversely impact on health or the environment
• All wastewater disposed in accordance with the South Australian Public Health (Wastewater) Regulation 2013.
• The method of disposal for wastewater must:
a) comply with the SA Health On site Wastewater Systems Code; or
b) be to the satisfaction of the Department for Health and Ageing, see Objective 11 below as well.
• Approval must be given by the Department for Health and Ageing or relevant authority (within a Local Government area).
Waste water disposal system must comply with the SA Health On site Wastewater Systems Code; or be to the satisfaction of the Department for Health and Ageing, or relevant authority.
Achieved No wastewater was disposed to land in 2014
No activities were undertaken by APA on the QSN Link that would cause any impact on land or water resources quality on the pipeline during the reporting period
11.2 To ensure that there is no untreated wastewater exposed to the open environment or discharged directly into the ground.
• All wastewater disposed in accordance with the South Australian Public Health (Wastewater) Regulation 2013.
• The method of disposal for wastewater must:
c) comply with the SA Health On site Wastewater Systems Code; or
d) be to the satisfaction of the Department for Health and Ageing, see Objective 11 below as well.
• Approval must be given by the Department for Health and Ageing or relevant authority (within a Local Government area).
Waste water disposal system must comply with the SA Health On site Wastewater Systems Code; or be to the satisfaction of the Department for Health and Ageing, or relevant authority.
Achieved No wastewater was disposed to land in 2014
No activities were undertaken by APA on the QSN Link that would cause any impact on land or water resources quality on the pipeline during the reporting period
1 Assessment criteria shown have been developed to be “black and white”. Professional judgment is required to assess whether non-compliance is minor or major. It is necessary to ensure that adequate information is available to enable this judgement to be made.
2 This column is provided for information only. Under the Petroleum Act 2000, only objectives and assessment criteria are approved.
3 Guidelines for a Native Vegetation Significant Environmental Benefit Policy For the clearance of native vegetation associated with the minerals and petroleum industry