2014 annual report for qsn pipeline -...

30
2014 Annual Report for QSN Pipeline Pipeline Licence 18 APA (SWQP) Pty Limited ACN 066 656 219 Version: 1 Released: 11 June 2015 Annual Report QSN Pipeline – Pipeline Licence 18

Upload: lamthien

Post on 03-Sep-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report for QSN Pipeline

Pipeline Licence 18

APA (SWQP) Pty Limited ACN 066 656 219

Version: 1

Released: 11 June 2015

An

nu

al

Rep

ort

QS

N P

ipe

lin

e –

Pip

eli

ne L

ice

nc

e 1

8

Page 2: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 2 of 30

Table of Contents

1 PURPOSE .................................................................................................................................................... 4

2 SCOPE ......................................................................................................................................................... 4

3 TECHNICAL ASPECTS .............................................................................................................................. 4

4 REGULATED ACTIVITIES .......................................................................................................................... 6

5 OPERATION AND MAINTENANCE ACTIVITIES ...................................................................................... 6

5.1 Corrosion Control .............................................................................................................................. 6

5.1.1 Cathodic Protection System .............................................................................................. 6

5.1.2 CP Validation Survey ........................................................................................................ 6

5.2 Pipeline Patrol Activities ................................................................................................................... 6

5.3 Electrical & Instrumentation Maintenance Activities ......................................................................... 6

5.4 Mechanical Maintenance Activities ................................................................................................... 7

5.5 Communications/SCADA.................................................................................................................. 7

5.6 Leakage Detection ............................................................................................................................ 7

5.7 Risk Management Review ................................................................................................................ 7

5.8 Training ............................................................................................................................................. 7

6 EMERGENCY RESPONSE ......................................................................................................................... 8

7 PIPELINE CONSTRUCTION ....................................................................................................................... 8

7.1 Licence Variation .............................................................................................................................. 9

8 HEALTH SAFETY AND ENVIRONMENT ................................................................................................... 9

9 LAND MANAGEMENT ................................................................................................................................ 9

9.1 Land Owner Liaison & Public Safety Awareness ............................................................................. 9

9.2 Pipeline Location and Referral services ........................................................................................... 9

10 ENVIRONMENTAL MANAGEMENT........................................................................................................... 9

10.1 Monitoring ....................................................................................................................................... 10

10.2 Projects ........................................................................................................................................... 10

11 MANAGEMENT SYSTEM AUDITS ........................................................................................................... 10

11.1 Management System Audits ........................................................................................................... 10

11.2 Health and Safety Audits ................................................................................................................ 10

12 COMPLIANCE ........................................................................................................................................... 10

13 REPORTS .................................................................................................................................................. 11

13.1 Incident Reports .............................................................................................................................. 11

13.1.1 Incident date .................................................................................................................... 11

13.1.2 Incident Location ............................................................................................................. 11

13.1.3 DSD Incident Classification ............................................................................................. 11

13.1.4 Incident Description ......................................................................................................... 11

13.1.5 Root Cause ..................................................................................................................... 11

13.1.6 Corrective Actions ........................................................................................................... 11

Page 3: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 3 of 30

13.1.7 Status .............................................................................................................................. 11

14 THREAT PREVENTION AND MITIGATION ............................................................................................. 11

14.1 Overview of Risk Management ....................................................................................................... 12

14.2 Risk Management ........................................................................................................................... 12

14.3 Specific Asset Risks ....................................................................................................................... 12

15 FUTURE WORK PROGRAM .................................................................................................................... 13

16 EXPENDITURE STATEMENT ................................................................................................................... 13

17 PIPELINE OPERATION ............................................................................................................................ 13

18 CONCLUSION ........................................................................................................................................... 13

APPENDIX 1 – ASSESSMENT OF DECLARED OBJECTIVES .................................................................... 14

Page 4: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 4 of 30

1 PURPOSE

This report is submitted in accordance with the requirements of Pipeline Licence 18, the Petroleum & Geothermal Energy Act 2000 (SA) and the Petroleum & Geothermal Energy Regulations 2013 (SA).

2 SCOPE

The portion of the QSN Link & QSNE pipelines (QSN pipeline) located in South Australia is a 92 kilometre looped pipeline that runs from the Queensland / South Australian border to Moomba.

The QSN pipeline natural gas transmission pipeline system is owned, operated and maintained by the APA Group (APA).

This report is applicable to APA’s activities on Pipeline Licence 18 (the South Australia Section of the QSN Pipeline) during the period 1st January 2014 to 31 December 2014.

3 TECHNICAL ASPECTS

Table 1 QSN Link Pipeline Technical Information

Date Constructed 2008

Date Commissioned January 2009

Length 182km (90km within SA)

External Diameter 406.4mm

Wall Thickness

- Normal

- Heavy Wall (creek beds, roads)

8.1 mm

9.7 mm

Pipe Grade API 5L X70

MAOP 15,300kPa

Fluid Natural Gas

Coating 3LPE

Main Line Valves Single MLV at KP 102

Scraper Stations Scraper facilities installed within Moomba

Pressure Reduction Station (MPRS)

Meter Stations Single Meter Station at Moomba – provides

gas to both MAP & MSP

Compressor Stations Connection to Moomba Compressor Station (MCS) comprising 3 x Solar Mars 90 gas turbine compressor sets

Page 5: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 5 of 30

Table 2 QSNE Pipeline Technical Information

Date Constructed 2010/2011

Date Commissioned 2011

Length 182km (90km within SA)

External Diameter 457mm

Wall Thickness

- Normal

- Heavy Wall (creek beds, roads)

9.1 mm

10.8 mm

Pipe Grade API 5L X70

MAOP 15,300kPa

Fluid Natural Gas

Coating 2FBE

Main Line Valves Single MLV at KP 102

Scraper Stations Scraper facilities installed within Moomba

Meter Station

Meter Stations Single Meter Station at Moomba – provides

gas to both MAP & MSP

Compressor Stations Connection to Moomba Compressor Station (MCS) comprising 3 x Solar Mars 90 gas turbine compressor sets

Table 3 Moomba Interconnect Pipeline (MIP) Technical Information (PL 18 component)

Date Constructed 2014

Date Commissioned 2014

Length 374 metres (chainage 821.74 to 1196.20)

External Diameter 660 mm

Wall Thickness 8.7 mm

Pipe Grade API 5L X70

MAOP 7.24 MPag

Fluid Natural Gas

Coating Trilaminate

Main Line Valves Nil

Scraper Stations Scraper facilities installed at Moomba Scraper Station (in PL 7 section of MIP) and at APA MCS

Page 6: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 6 of 30

Note: The DN650 MIP has two sections. KP 0.000 to KP 0.821 is part of PL 7 and was originally constructed as the MSP Loop in the early 1980s. This component of the MIP is reported separately in the PL 7 annual report.

KP 0.821 to KP 1.196 is part of PL 18 and runs parallel to the QSN/E pipelines described above. The PL18 section of the MIP was newly constructed and commissioned in 2014.

4 REGULATED ACTIVITIES

This report a summary of the regulated activities conducted under the licence during the year.

5 OPERATION AND MAINTENANCE ACTIVITIES

APA operates and maintains the QSN natural gas transmission pipeline and its associated facilities in accordance with AS2885.3 and other relevant standards.

All Preventative, Corrective and Reactive maintenance activities are managed within APAs Works Management System. Preventative and corrective works are scheduled and monitored for completion using this system through the generation of work orders for maintenance staff to complete.

A description of the Operations and Maintenance activities for 2014 is provided below.

5.1 Corrosion Control

5.1.1 Cathodic Protection System

The original CP system including CPUs and ground-beds on the QSN pipeline was installed in 2008. As part of the construction project for the QSNE a new integrated cathodic protection system was commissioned. It was determined the existing anode ground-beds were sufficient to provide adequate capacity to accommodate the new integrated design. The impressed current cathodic protection systems in the SA portion of the pipeline are located at Moomba and at KP 102 MLV.

5.1.2 CP Validation Survey

The most recent CP survey found that the cathodic protection system is able to provide full protection when the set points and all units are functional. The construction of the new compressor station at Moomba has required one cathodic protection unit to be switched off temporarily. Protection is provided by the other two units in the vicinity.

5.2 Pipeline Patrol Activities

In 2014 routine helicopter patrols and the scheduled annual roads patrol were completed on the QSN pipeline in accordance with the maintenance plan.

Maintenance activities including inspections of above ground pipe coating condition, fences, gates, padlocks, signage, fire extinguishers, weeding and other housekeeping activities are addressed at the meter station and pressure reduction facility associated with the pipeline.

5.3 Electrical & Instrumentation Maintenance Activities

Accuracy Verification Tests were carried out in line with APA’s maintenance management system. Meter validations and calibrations occur on a 3 monthly maintenance schedule.

Electrical compliance testing was carried out on all portable electrical equipment and residual current devices (RCD’s) at all sites.

Meter Stations Metering undertaken within Santos MGP

Connection to metering facilities at APA MPRS

Compressor Stations Connection to Moomba Compressor Station (MCS) comprising 3 x Solar Mars 90 gas turbine compressor sets

Page 7: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 7 of 30

Routine six monthly meter station maintenance was carried out in this reporting period. This involved calibration of all non-billing transmitters, testing all remotely operated valves, calibration of all switches and testing of all associated systems. Minor equipment failures have occurred within the reporting period with gas and moisture analysers at Moomba Inlet Station, compounding into some lost data in some cases. These issues have been resolved in early 2014.

No significant issues were reported or other significant maintenance was carried out during this period.

5.4 Mechanical Maintenance Activities

Routine mechanical maintenance activities were completed as per the maintenance schedule for the QSN pipeline system. This work involved MLV servicing, station filter inspection/replacement, vessel door closure maintenance, coalescing filter inspection/maintenance and pig launcher/receiver maintenance.

Routine inspection and maintenance activities were carried out on the pressure regulation/pressure relief systems and ESD valves at all Meter Stations on a 6 monthly basis. Maintenance tasks for the pressure control systems consisted of the inspection/overhaul of regulator seats, pilots and instrumentation filters to ensure correct operation of set points of the active/monitor and bypass regulation systems.

Pressure Safety Valves were also checked to confirm correct set point, operation and alarming functions. Where applicable, overpressure isolation valve functions are tested to ensure satisfactory operation.

All buildings and structures are inspected and maintained as part of routine maintenance procedures and confirmed in sound condition.

No significant issues were reported or other significant maintenance was carried out during this period, minor reactive faults where tended to as soon as practicable without incident.

5.5 Communications/SCADA

SCADA continued to function correctly throughout the year without incident.

5.6 Leakage Detection

APA monitors the QSN pipeline for leakage remotely from the Pipeline Control Centre and during the routine ground patrols as staff travel along the pipeline. Field staff inspect for signs of gas leakage such as dust plumes, the sound of escaping gas and dead or dying vegetation while staff at the Control Centre monitors the system pressures, flows and alarms.

During 2014, other than the reportable incident noted in section 13.1 below, there were no instances of any material leaks on valves or equipment on the QSN pipeline.

5.7 Risk Management Review

The QSN Link pipeline was constructed in 2008, and formal risk assessments, reviews and analysis were completed as part of the design, construction and commissioning process. All the action items raised in that original risk assessment were completed.

The QSNE Link pipeline was constructed and commissioned in 2011. Again, the necessary formal risk assessments, reviews and analysis were completed as part of the design, construction and commissioning process. All the action items raised in that original risk assessment were completed.

A SMS / risk assessment was conducted for the QSN Pipeline in August 2013. This assessment took place in the APA Brisbane office and was attended by the appropriate APA operational and engineering staff. The safety management study concluded that the QSN Link Pipeline meets the requirements for Safety Management Studies of AS2885.1-2012

5.8 Training

APA is committed to developing the skills of all employees and contractors to meet the operational and technical needs of its business.

During 2014 staff training was conducted in-house using a number of techniques which included training courses developed specifically for APA.

Page 8: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 8 of 30

In addition to internal training, staff attended a range of external courses, conferences and seminars selected to further enhance their knowledge of the natural gas and liquid hydrocarbon pipeline transmission industry.

The range of training staff attended during 2014 included, but was not limited to;

• Clear SCADA training • APA Permit to Work • Emergency response • Drugs & alcohol policy • Isolation • 4WD training • Fire Prevention & Control • First aid • Field Induction • Excavation of Pipelines • Gas detection, Instrumentation • JHA

6 EMERGENCY RESPONSE

An emergency response exercise was conducted on pipeline licence 18 during the reporting period.

The mobilisation exercise provided practice of the procedures for handling the various implications, technical and otherwise, of a major complex event which has the potential to adversely affect the environment, public health and safety and the security of supply of natural gas and also the company’s performance, value, or reputation. In particular the exercise was conducted in order to:

• Verify the role played by the control room to ensure the safety of travelling staff; • Verify the notification and escalation processes, including mobilisation, command, and operation of

the APA Group Operations within the Queensland Transmission division; • Practise the use of all relevant procedures, guidelines, and checklist actions contained in the APA

Group Queensland Transmission emergency response plan and review their effectiveness; • Practise preparation of outgoing messages and handling of calls in an emergency, including

dealing with key stakeholders, emergency services, and relatives / next of kin of injured staff; and review their effectiveness;

• Test the adequacy of the various facilities, equipment, and infrastructure required to respond, including the support which may be required from emergency services and other parts of the organisation.

• Practice the activation of an Emergency Room and review its effectiveness.

The exercise was specifically designed not only to test these objectives but also to provide a constructive learning environment for all participants and was not conducted to test or highlight individual performance.

The exercise took place on 14 May 2014 on site at MLV102 – Moomba, South Australia and the emergency management team was based at the Spring Hill emergency response room, Queensland.

The findings of the exercise confirmed the adequacy of emergency response procedures and included positive observations and opportunities for improvement. In general, the emergency response process was executed fluently, with personnel involved understanding their role in the exercise.

7 PIPELINE CONSTRUCTION

Construction and commissioning of the Moomba compressor station, the expansion of Moomba Pressure Reduction Station and the Moomba Interconnect Pipeline was completed during the reporting period. The Station became operational in September 2014. This modification converted the QSN/E pipelines to allow bi-directional flow. Gas can now be transported from Queensland and supplied to the MSP and MAP (Western Haul), or transported from the Santos MGP into Queensland (Eastern Haul).

Page 9: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 9 of 30

The compressor station also utilises a portion of the 660mm Moomba bypass pipeline (PL7) to feed gas from Moomba through to the compressor station. Following completion of the compressor station, works commenced in 2014 to install additional pipework and re-configure the station to facilitate the backhauling of gas from the Moomba Sydney Pipeline. This is known as the Moomba Compressor Station Variation 1 (V1) Scope.

7.1 Licence Variation

The Pipeline Licence was varied in respect of the above.

8 HEALTH SAFETY AND ENVIRONMENT

APA Group recorded no LTI, MTI or environmental incidents on the pipeline in South Australia during the reporting period.

APA has implemented a HSE Management System called Safeguard to comply with the national work health and safety requirements.

Safeguard provides a framework by which the processes relating to the company's Health, Safety and Environment (HSE) activities are written, approved, issued, communicated, implemented and controlled.

Safeguard applies to all HSE-related matters arising out of all activities and operations controlled by APA and its related companies (together the company) and the impact of those activities and operations on employees, contractors, the environment and the communities in which the company operates.

Additionally, Safeguard (Including HSE Policies) is also subject to review and improvement to ensure objectives and obligations are continually satisfied, including:

• Performance, measurement and reporting; • Management review; and • Audit and self-assessment.

The above requirements are supported by APA Group procedures. The HSE policy is a controlled document subject to three yearly reviews as a minimum.

9 LAND MANAGEMENT

9.1 Land Owner Liaison & Public Safety Awareness

The landowner liaison program includes a landowner package being sent to landowners and direct liaison as required.

Council and Emergency services are contacted and, where possible, gas awareness presentations delivered as per APA Stakeholder Management program.

9.2 Pipeline Location and Referral services

APA provides a free “dial before you dig” service which third parties can call to locate any pipeline infrastructure prior to undertaking any construction activities. The service is primarily used by other companies and third parties carrying out civil works in the vicinity of the pipelines and other buried utilities.

10 ENVIRONMENTAL MANAGEMENT

There were no environmental incidents during the report period.

An assessment of compliance against the SEO objectives in regards general maintenance activities is included in Appendix 1.

During the reporting period all environmental requirements as detailed in the Statement of Environmental Objectives were complied with.

Page 10: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 10 of 30

10.1 Monitoring

Ongoing environmental monitoring of PL18 is intended to ensure effective rehabilitation has occurred along the pipeline route. The most recent monitoring included ground patrols and a helicopter flyover of the pipeline route to assess vegetation regrowth, erosion and subsidence and to confirm the effectiveness of previous subsidence repair work.

Overall it was determined that the QSN pipeline route was generally in good condition. Minor subsidence at Strezlecki Creek, KP120, will continue to be monitored and managed.

Right of Way maintenance, including minor subsidence and erosion identified between KP0 and KP160, is scheduled to occur between April and June 2015.

10.2 Projects

A CEMP was submitted setting out the environmental management practices and procedures to be implemented during construction of additional pipework at the Moomba Compressor Station to meet the environmental requirements of the Project. These requirements are documented in:

• the QSN Pipeline Statement of Environmental Objectives (SEO); and • the Moomba Compression Services Variation 1 (MCS V1) Project Construction Environmental

Management Plan.

11 MANAGEMENT SYSTEM AUDITS

APAs auditing program offers the opportunity to identify and promote continual improvement within APA.

11.1 Management System Audits

An independent audit of the APA Pipeline management System by external auditors Ken Cameron & Associates is scheduled to occur during June 2015.

APA completed a number of management system audits during the year under its internal audit program.

11.2 Health and Safety Audits

An internal audit schedule of the Safety Management System was maintained during 2014.

12 COMPLIANCE

APA ensures that the pipeline is operated in accordance with the relevant Acts of Parliament, licence conditions and the requirements of AS2885.

APA attends quarterly compliance meetings with DSD, where operational regulatory compliance is discussed in an open manner.

Changes in legislation are tracked and communicated through a The Technical regulatory Manager.

APA maintains a compliance database, MARCIS, which tracks legislative compliance throughout the organisation. Obligations are assigned to responsible staff, who must supply evidence that the obligation has been satisfied within a specified time period.

APA is not aware of any regulatory non-compliance for this pipeline, and believes it is fulfilling its obligations in relation to the following requirements:

• The Petroleum & Geothermal Energy Act 2000 • The Petroleum & Geothermal Energy & Regulations 2013 • Pipeline Licence (PL18) • The Statement of Environmental Objectives

APA Group maintains an action tracking system for improvements to its systems, which is fully traceable through to close out of individual items.

Significant items are reported through to DSD, and would be raised at the quarterly compliance meetings held between DSD and APA.

Page 11: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 11 of 30

There have not been any significant regulatory compliance issues during this reporting period.

13 REPORTS

The following reports were generated and forwarded to DMITRE during the reporting period;

• PL18 2014 Annual report • MCS V1 Activity Notification • MCS V1 Design Basis Manual • MCS V1 Project AS2885 1 Design Compliance Register • MCS V1 CEMP • MCS V1 SIL Closeout report • MCS V1 HAZOP Closeout Report • MCS V1 SMS Closeout report • MCS V1 PL18 Licence Variation Application

13.1 Incident Reports

During the reporting period there were no “Serious Incidents” and one “Reportable Incident”. The reportable incident was reported later than required under Petroleum and Geothermal Energy Regulations 2013 s32(5). An overview of the reportable incident is provided below.

13.1.1 Incident date

The incident occurred on 23rd October 2014.

13.1.2 Incident Location

The incident occurred at the MLV102 site located at KP 102 on the QSN pipeline, near Innamincka SA.

13.1.3 DSD Incident Classification

Design

13.1.4 Incident Description

The threaded cavity vent connector on a ball valve failed during operation of the ball valve, causing the cavity vent assembly to detach from the ball valve and leading to a localised release of gas. A second vent connector was also observed to have failed at a previous time.

13.1.5 Root Cause

The root cause of the failures was assessed as vibration-induced fatigue of the threaded connectors. The design of the cavity vent assembly was such that the connectors were subjected to bending loads and vibration from the adjacent pressure control valve.

13.1.6 Corrective Actions

• The site was initially made safe and the affected valves isolated and tagged out of service. • An engineering and metallurgical investigation was completed to assess the root cause. • Replacement cavity vent assemblies were sourced and installed using a modified design. • Overhaul and vibration assessment of the pressure control valve has commenced.

A review of similar sites has commenced to identify other valves that may be at risk of similar failure (cantilevered connector design and subject to vibration).

13.1.7 Status

In progress.

14 THREAT PREVENTION AND MITIGATION

There are no reasonably foreseeable threats on this pipeline.

Page 12: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 12 of 30

14.1 Overview of Risk Management

APA Group recognises that risk management is an integral part of good management and that managing risk is a fundamental part of its business so that actions and activities do not unduly expose the asset, its personnel or the public or the environment to unacceptable risks.

The risk management process consists of well-defined steps which, taken in sequence, support better decision-making by contributing to a greater insight into risks and their impacts. The risk management process can be applied at many levels within APA Group and can be applied to specific projects, to assist with specific decisions or to manage specific recognised risk areas. APA Group recognises that risk management is a multi-faceted process, which is often best carried out by a multi-disciplinary team with an intimate knowledge of the pipeline.

APA Group’s risk management processes aligns with the Pipeline Integrity Management requirements as defined by AS2885.3 and comprises the following components:

• Technical risk management as per AS 2885; • Facilities HAZOPs/Internal Hazard Audits; • Risk management, including Health, Safety and Environmental (HSE) risk, as per APA Group’s

corporate policies; • Environmental Management Plan as per Australian Pipeline Industry Association (APIA) Code of

Environmental Practice and Queensland Environmental Acts; and • MAOP reviews as per AS 2885;

All facilities and equipment are currently being operated and maintained to AS 2885.3, Original Equipment Manufacturers (OEM) operation and maintenance recommendations and good industry practice.

14.2 Risk Management

The company has exposure to a wide variety of risks. The following are some of the most relevant:

• Frequent vehicle travel incident - Major (LTI or Vehicle write-off) • Lifting loads near the exposed pipeline • Hot work • Moveable plant in hazardous areas • Use of and maintenance of gas transportation facilities, other than high-pressure gas pipeline

lines • Isolating pipe work • Storms/lightning • Equipment theft and damage • Low operational availability (reduced availability of competent, skilled qualified personnel due to

sickness) • Corrosion and Stress Corrosion Cracking • CAD welding • Floods • Seismic events • Aviation travel • Third party excavation activities near buried pipelines • Electrical hazards on pipelines due to lightning or overhead powerlines

14.3 Specific Asset Risks

Risks of higher significance include:

• For remote pipelines, exposure to prolonged long-distance driving. This risk is mitigated by driver training courses coupled with stringent remote travel requirements including remote monitoring by the Control Centre.

Asset risks are mitigated and monitored via APA work programs and systems including but not limited to:

• Aerial Patrols • Landowner and Third Party Liaison • SCADA monitoring • Maintenance programs • Safeguard implementation

Page 13: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 13 of 30

15 FUTURE WORK PROGRAM

All maintenance operations will continue to be completed as scheduled to ensure that the integrity of the pipeline system is being maintained, as well as the safety and efficiency of APA Group’s operations.

The following specific activities are planned for FY15:

• The modification of the Moomba Compressor Station by the installation of additional pipework and re-configuration of the station.

16 EXPENDITURE STATEMENT

17 PIPELINE OPERATION

12,077.69 TJ of natural gas was transported through the QSN pipeline during the 2014 period.

18 CONCLUSION

The maintenance and inspection programs carried out on the QSN Pipeline in 2014 have indicated the pipeline is in sound condition and is capable of operating at set parameters with no restrictions.

The CP Survey results indicate the protection levels are adequate to provide suitable protection for the pipeline.

The pipeline is considered to be in good working condition and well maintained.

Page 14: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 14 of 30

APPENDIX 1 – Assessment of Declared Objectives

During the reporting period all activities were undertaken in accordance with APA Management Systems, Construction Management Plan, Environmental Line List and Procedures.

Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /

Not Achieved

Comments

1. To avoid or minimize adverse impacts on soils and terrain during construction and operation and to maintain soil stability / integrity on the easement

1.1 To minimize soil erosion and sedimentation as a result of pipeline construction and to remediate in a timely manner when due to operations

Alignment selection to avoid or minimise impacts on erodible soils and steep terrain

Construction Environmental Management Plans (CEMP’s) contains environmental work procedures (EWP) that specify soil management and reinstatement requirements

Implementation specific requirements based on soil type and erosion risk e.g. in gibber, minimise gibber disturbance, roll areas rather than clearing where traffic levels will not be high, carefully stockpile gibber and replace in reinstatement

Preventative measures implemented and monitored in susceptible areas

Erosion and sedimentation control structures installed and maintained in susceptible areas

Records of induction/training regarding CEMP’s/EWP requirements

Regular inspections of construction areas undertaken to look for evidence of erosion

The extent of soil erosion on the easement is consistent with surrounding land

0, +1 or +2 GAS criteria are obtained for borrow pit construction and restoration, as listed in Appendix 3

Achieved

The pipeline was

completely reinstated

following completion of

construction of the

QSN3.

A CEMP was

implemented for the

construction of the

Moomba Compressor

Station.

1.2 To reinstate soil and terrain as near as practicable to pre-construction contours and conditions

Implement reinstatement requirements specified in CEMP’s and EWP Records of induction/training regarding CEMP’s/EWP requirements Regular inspections undertaken of easement and construction areas Installation and monitoring of photo points (environmental monitoring points)

Surface contours consistent with adjacent land

0, +1 or +2 GAS criteria are obtained for borrow pit restoration, as listed in Appendix 2

Achieved Ongoing monitoring shows that reinstatement has occurred along the length of the pipeline route.

Page 15: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 15 of 30

Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /

Not Achieved

Comments

1.3 To mitigate soil compaction if necessary by remedial action

Ripping of identified compacted areas where appropriate to soil type and erosion risk (i.e. generally avoid ripping in gibber)

Regular inspections undertaken of easement and construction areas to look for evidence of soil compaction

No visual evidence of soil compaction following remediation of pipeline easement (e.g. hard soil, local water pooling)

Achieved No evidence of compaction.

1.4 To prevent soil inversion

CEMP’s/EWP requirements include separate stockpiling of topsoil and sub-surface material during excavation

Records of induction/training regarding CEMP’s/EWP requirements

Reinstatement of stockpiles in appropriate order during backfill

No evidence of subsoil on surface (colour).

Vegetation cover consistent with surrounding land.

No reasonable landholder complaints

Achieved No reasonable landholder complaints were received during the reporting period.

Annual land survey to look for soil discolouration, success of vegetation return as an indicator.

Disturbance checklist signed off to indicate top soil/subsoil are stockpiled separately and soil profiles appropriately reinstated following the re-instatement of works/excavations

Vegetation cover is consistent with surrounding land

No evidence of subsoil on surface (colour)

No reasonable landholder complaints

1.5 To remediate erosion or subsidence as a result of pipeline operations in a timely manner

Timed photo points or regular land survey, specifically to look at evidence of erosion, subsidence, vegetation loss on easement & compare to adjacent land

Inspections undertaken as part of regular patrols, following specific works, following significant storm events

Preventative measures implemented and monitored in susceptible areas

No un-remediated subsidence

The extent of soil erosion on the easement is consistent with surrounding land

No excessive erosion on areas adjacent to corridor as a result of easement

No reasonable landholder complaints

Achieved Areas of soil erosion and subsidence have been identified and documented. These are in the process of being managed.

Page 16: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 16 of 30

Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /

Not Achieved

Comments

2. To minimise and manage impacts to water resources

2.1 To minimize short term, and prevent long-term, interruption or modification to surface drainage patterns

Alignment selection to minimize impacts to water resources e.g. select watercourse crossing locations that minimize erosion potential and impacts to the watercourse

Management requirements specified in CEMP’s/EWP

Records of induction/training regarding CEMP’s/EWP requirements

Installation and subsequent removal of appropriate temporary watercourse crossing measures

Regular inspections undertaken of easement and construction areas specifically to look at watercourse crossings

Installation and monitoring of photo points (environmental monitoring points)

No adverse impacts (for example to downstream ecology or land use) resulting from watercourse flow reductions or diversions as a result of pipeline construction activities

No evidence of altered watercourse flows following reinstatement

No evidence of project related erosion of watercourses intersecting or adjacent to the pipeline easement

Surface drainage profiles restored

Drainage is maintained to pre-existing conditions or better

Achieved Subsidence at

Strezlecki Creek

(KP120.4) is in the

process of being

managed.

2.2 To minimize the amount of sediment entering surface water features

CEMP’s/EWP specify management requirements including:

No stockpiling of materials in watercourses/ flowlines (note: trench spoil may be stockpiled in dry watercourse beds for very short periods e.g. less than a day)

- Use of appropriate sediment and silt capturing devices

- Installation of permanent berms on slopes - Minimising period between clearing and

reinstatement at or near watercourses - Stabilisation and reinstatement of watercourses

and drainage lines Records of induction/training regarding CEMP’s/EWP requirements

Compliance with EPA Environment Protection

(Water Quality) Policy 2003

Achieved Permanent erosion controls have been installed where appropriate to manage sedimentation issues.

Page 17: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 17 of 30

Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /

Not Achieved

Comments

2.3 To minimise disruption to third party use of surface waters

Alignment selection to avoid or minimise disturbance to third party uses e.g. stock watering points

Liaison with third party users regarding potential disruptions

Minimising period of disturbance and prompt reinstatement in sections of easement intersecting or adjacent to water bodies

Installation and subsequent removal of appropriate temporary watercourse/water body protection measures to prevent flow interruptions

No reasonable complaints received from landholders or third party users in relation to use of surface waters

Achieved During the reporting period there were no complaints from landholders or third parties in relation to the use of surface water.

Minimizing period of disturbance for any excavation or land disturbance and prompt reinstatement of easement in sections of easement intersecting or adjacent to water bodies

2.4 To maintain current surface drainage patterns

Regular patrols and survey undertaken to look for evidence of erosion, windrow development, abnormal vegetation growth or death or any changes to the easement which could change surface hydrology conditions, particularly in the Strzelecki Creek wetland area

Observations also to be undertaken following significant storm events

Use of disturbance checklist and photo points before, during & after excavations, CP installation, construction activities, etc.

For excavations, surface drainage profiles restored

For existing easement, drainage is maintained to pre-existing conditions or better.

For borrow pits, surface drainage profiles are not disturbed.

Achieved No excavations were carried out in 2014.

Page 18: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 18 of 30

Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /

Not Achieved

Comments

3. To avoid land or water contamination

3.1 To prevent spills occurring and if they occur minimize their impact

Regular inspections for evidence of soil or water discolouration, vegetation or fauna death

Use of spill protection methods where work is completed within or adjacent to environmentally sensitive areas

Spill response/cleanup procedures, requiring spills to be:

- reported - contained - cleaned-up - cause investigated and corrective and/or

preventative action implemented

Spills/contamination remediated in consultation with regulatory agencies and landholder

Ensuring personnel are trained in spill response procedures Appropriate spill response equipment is available on site Compliance with fuel and hazardous waste standards

Containment of all fuel, oil, hazardous substances and liquid waste in appropriate vessels/containment areas (e.g. polythene lined, bunded areas or on bunded pallets)

Bunded areas must have sufficient freeboard (e.g. to hold a 1:100 year, 24hr rainfall event)

Bunded areas in accordance with EPA Guideline for Bunding and Spill Management 080/12.

Incident / Spill reports

Prevention program including pigging, intelligent pigging and pipe maintenance.

No soil or water contamination as a result of spills during pipeline construction activities.

Compliance with Environment Protection Act

Achieved There were no reported spill incidents in SA in 2014.

Page 19: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 19 of 30

Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /

Not Achieved

Comments

3.2 To ensure that rubbish and waste material are disposed of in an appropriate manner

Waste management requirements specified in CEMP’s/EWP, including: - Provision of covered bins for the collection, storage and transport of wastes; - Waste disposal at an approved waste facility

Regular inspection to look for evidence of rubbish, spills (soil discolouration)

Waste disposal records, chemical manifests. Appropriately licensed contractors used for any hazardous waste disposal and records are maintained for all hazardous waste disposal

No pipeline related rubbish or litter on easement or at facilities or on surrounding land

Waste material is contained and disposed of in accordance with Environment Protection Act and approved procedures.

Achieved Regular inspections and monitoring have been undertaken to ensure that waste materials been disposed of.

Waste is managed in accordance with APA Waste Management Procedures.

Hazardous waste is collected by licensed carriers and Waste Transport Certificates filed.

3.3 To prevent impacts as a result of hydro test water, trench water and waste water (e.g. wash-down water) disposal

Water disposed of in a manner that prevented discharge or runoff to watercourses or environmentally sensitive areas

Water discharged onto stable ground, with no evidence of erosion as a result of discharge

Records on source of water and discharge method/location

Investigation of water quality prior to release/disposal of trench water and waste water. Testing of hydro test water if potentially harmful chemicals added.

Inspection of water disposal sites for evidence of water entering a watercourse or environmentally sensitive area.

Compliance with the Environment Protection (water quality) Policy.

Discharge water meets appropriate ANZECC and EPA criteria for point of disposal

No evidence of impacts to soil, water and vegetation as a result of water disposal (e.g. soil erosion, dead vegetation, water discoloration)

Achieved No wastewater was disposed to land in 2014

No activities were undertaken by APA on the QSN Link that would cause any impact on land or water resources quality on the pipeline during the reporting period

Page 20: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 20 of 30

Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /

Not Achieved

Comments

3.4 To ensure the safe and appropriate disposal of camp wastewater (grey water, sewage)

All wastewater disposed in accordance with the South Australian Public Health (Wastewater) Regulation 2013.

The method of disposal for wastewater must

a) comply with the SA Health On site Wastewater Systems Code; or

b) be to the satisfaction of the Department for Health and Ageing, see Objective 11 below as well.

Treated sewage wastewater disposed of onto land, well away from any place from which it is reasonably likely to enter any waters in accordance with the Environment Protection (water quality) Policy.

Waste water disposal system must comply with the e SA Health On site Wastewater Systems Code; or be to the satisfaction of the Department for Health and Ageing.

Achieved All wastewater is

disposed of by a

licensed carrier.

4.To minimize adverse impacts to vegetation and fauna

4.1 To minimise clearing of remnant vegetation

Alignment selection to minimise crossings of drainage lines and ephemeral wetlands and avoid or minimise impacts to vegetation with high habitat values (e.g. large trees)

CEMP’s and alignment sheets identify remnant vegetation requiring management / avoidance

Flagging/marking of remnant vegetation requiring management /

avoidance

Retain trees on Easement where possible

Trim vegetation in lieu of removal where possible

Restrict disturbance to the Easement and approved access and work areas

Reduction of ROW width during construction in identified significant areas

Obtain any permits / clearance consent required

Vegetation clearing is in accordance with the

Native Vegetation Act 1991

Vegetation clearance minimised

No unauthorised clearance of flora identified to be retained

0, +1 or +2 GAS criteria are obtained for borrow pit construction and restoration, as listed in Appendix 3

Achieved There was no vegetation clearance in 2014.

Page 21: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 21 of 30

Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /

Not Achieved

Comments

4.2 To minimize disturbance to fauna

Implement previous measures to minimise impacts to native vegetation

Identification and flagging of significant fauna habitats (e.g. large trees) that require management/avoidance during construction and implementation of management requirements

Alignment selection to minimise/avoid impacts to important habitats

Provision of fauna ramps at regular intervals in open trench

Daily inspection of open trenches and removal and identification recording of trapped fauna by appropriately trained and experienced biologists

Prompt reinstatement of easement

Borrow pits are restored to minimise water holding capacity where agreements are not in place with stakeholders

No domestic pets allowed at camps or worksites

No feeding of wildlife (e.g. dingoes)

Native fauna casualties associated with construction restricted to as low as reasonably practical

Achieved No impacts to fauna from activities in 2014.

4.3 To appropriately rehabilitate the easement to pre-construction condition, as reasonably practical

Implement reinstatement requirements specified in CEMP’s and EWP Timely response to rehabilitation

Installation and monitoring of photo points (environmental monitoring points)

Vegetation on the easement is reasonably consistent with the surrounding areas

Note: assessment of the consistency with surrounding areas will take into account that regrowth is a time and rainfall dependent process

0, +1 or +2 GAS criteria are obtained for borrow pit restoration, as listed in

Achieved Environmental monitoringpoints were installed at 14 locations along the QSN Link.

There is evidence of vegetation regrowth along the length of the ROW.

Page 22: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 22 of 30

Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /

Not Achieved

Comments

Appendix 3

No reasonable complaints received from landholders in relation to regrowth of vegetation on the easement

4.4 To achieve a significant environmental benefit for native vegetation clearance

Work (or payment to Native Vegetation Fund) undertaken to achieve a significant environmental benefit, as required by Native Vegetation Regulation 5(1)(zd)

Significant Environmental Benefit (SEB) requirement either:

- determined using the “Methodology for calculating total SEB requirements” outlined in the Guidelines

3, or

- negotiated with the Native Vegetation Council where SEB calculation differs from the standard methodology in the Guidelines. (Note: The Guidelines have provision for case-by- case assessment of significant environmental benefit by the NVC in some circumstances e.g. where SEB capping or additional mitigation measures apply)

Significant environmental benefit approved by DMITRE (where delegated authority applies) or Native Vegetation Council

Significant environmental benefit obligation satisfied / implemented

Achieved There was no vegetation clearance in 2014.

4.5 To promote and maintain regrowth on the easement to be consistent with surrounding area

Annual land survey to assess vegetation rehabilitation and look for evidence of disturbance to vegetation on easement (apart from access tracks)

Disturbance Checklist (including timed and photos) signed off to indicate adequate steps taken to facilitate regrowth

Follow-up rehabilitation work undertaken where natural regeneration is inadequate

Species abundance and distribution on the easement is reasonably consistent with surrounding areas

Note: assessment of the consistency with surrounding areas will take into account that regrowth is a time and rainfall dependent process

Achieved Regrowth on the

easement is observed

to be consistent with

the surrounding

environment.

No borrow pits were utilised during the reporting year.

Page 23: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 23 of 30

Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /

Not Achieved

Comments

4.6 To minimize additional clearing of native vegetation as part of operational activities

Annual land survey to look for evidence of disturbance to vegetation on easement (apart from access tracks)

Use of Disturbance Checklist and photo points before, during & after any excavation or land disturbance activity

Vegetation trimmed rather than cleared where possible

Consideration of sensitive vegetation, including large old trees, during vegetation trimming and / or clearing activities. Obtain any clearance consent required

Location of temporary camps in naturally clear areas or on previously cleared sites.

Vegetation clearing within the easement or on land adjacent to the easement is limited to previously disturbed areas, unless prior regulatory approval obtained under the Native Vegetation Act 1991

Achieved There was no additional clearing in 2014 for operational purposes.

4.7. To ensure operational maintenance activities are planned and conducted in a manner that minimizes impacts on native fauna

Use of Disturbance Checklist and photo points before, during & after any excavation or land disturbance activity

In the event of excavations, open trenches monitored regularly and left open for the minimum time practical

Procedures or management plans implemented for significant fauna species

Provision of fauna ramps at regular intervals in open trench

Daily inspection of open trenches in areas adjacent to remnant vegetation

Prompt reinstatement of easement

Native fauna casualties associated with operations restricted to as low as reasonably practical

Achieved During the reporting period no operational activities were undertaken that would cause disturbance to native fauna on the pipeline.

Page 24: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 24 of 30

Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /

Not Achieved

Comments

5. To avoid the spread of weeds and pathogens

5.1 To avoid the introduction or spread of weeds and pathogens and undertake control where required

Vehicles and machinery cleaned and inspected before entry to project area

Identification of weeds and pathogens on easement and adjacent land

Implementation of control measures of weeds and pathogens on easement and liaison with the regional Native Resources Management (NRM) Board and the landholder as necessary

Records of outbreaks found, weed control activities and photo- monitoring of significant outbreaks

Vehicle cleaning/wash-down register

Regular patrols undertaken to look for evidence of weeds on easement and adjacent land (if weeds on easement but not adjacent land must implement control to prevent spread).

The presence of weeds on the easement is consistent with or better than adjacent land

No new outbreak or spread of weeds or pathogens as a result of pipeline activities

Achieved No weed outbreaks have been identified on the QSN Link.

No declared or non declared weed species were observed along the easement.

6. To minimize and manage impacts to heritage sites and values during construction, operations and maintenance

6.1 To ensure that identified heritage sites are not disturbed

Alignment selection to avoid heritage sites, including archaeological and ethnographic heritage, built heritage and culturally significant vegetation

Identification of known heritage sites on easement prior to construction

Measures undertaken to protect heritage sites on or near the easement

Implement appropriate protocols for dealing with accidental discovery of cultural heritage material during construction

Obtain all necessary approvals in the event of an accidental/unavoidable site disturbance

Seek advice from relevant authorities for remediation of

No impact to known sites without approval under the Aboriginal Heritage Act 1998 or the Heritage Places Act 1993

Any new sites identified are reported to appropriate authority and recorded

0, +1 or +2 GAS criteria are obtained for borrow pit construction and restoration, as listed in Appendix 2

Achieved There are a number of

cultural heritage sites

on the QSN Link.

Flagging and signage at

known heritage sites

adjacent to the

easement was removed

in 2012.

An electronic

management system

was developed and

implemented to ensure

sites are protected from

harm. Field personnel

received face to face,

Page 25: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 25 of 30

Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /

Not Achieved

Comments

site, if required

Induction/training to include heritage management requirements

- Incident reports

Consultation with relevant heritage groups if operations occurring outside known surveyed areas

Site examined for cultural heritage material prior to work involving disturbance outside known surveyed areas

Records of site locations in Operations GIS

Use of Disturbance Checklist and photo points before, during & after any excavation or land disturbance activity

intensive training

regarding cultural

heritage responsibilities

and control measures.

There have been zero cultural heritage breaches.

7. To minimise noise due to construction and operations

7.1 To minimize noise impacts associated with the movement and operation of construction vehicles and equipment

Regular maintenance of construction vehicles and equipment

Incident reports

Facilities designed to meet the noise requirements under the Environment Protection Act

Incident reports

Monitoring results, where deemed necessary (e.g. frequent complaints)

Construction activities comply with noise regulations under the Environment Protection (Noise) Policy 2007.

Operation activities comply with noise regulations under the Environment Protection (Noise) Policy, 2007.

No reasonable complaints received

Achieved No reasonable complaints received in relation to noise management during the project.

No operational activities were undertaken that would cause any impact on environmental noise and emissions on the pipeline

Page 26: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 26 of 30

Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /

Not Achieved

Comments

8. To minimize atmospheric emissions

8.1 To minimize the generation of dust

Management requirements specified in CEMP’s/EWP including use of water trucks and sprayers if necessary

Compliance with EMS and operations procedures

Records of induction/training regarding CEMP’s/EWP requirements

Incident reports

Compliance with Environment Protection Act or to the satisfaction of the EPA.

No reasonable complaints received

Achieved No incident reports or complaints were received during the reporting period in relation to dust.

8.2 To eliminate uncontrolled atmospheric emissions

Maintenance procedures

Incident reports

No uncontrolled atmospheric emissions (e.g. due to malfunction or mis-operation)

Achieved During the reporting period no operational activities were undertaken that would cause any impact on the environment due to uncontrolled emissions on the pipeline

8.3 To comply with air quality requirements

Compliance with Environment Protection (Air Quality) Policy 1994.

Compliance with Environment Protection (Air Quality) Policy 1994. No non-compliances noted or received.

Achieved No non-compliances were noted or received during the reporting period.

Page 27: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 27 of 30

Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /

Not Achieved

Comments

9. To minimize disturbance to third party infrastructure, landholders and land use

9.1 To minimize disturbance or damage to infrastructure / land use and remediate where disturbance cannot be avoided

Alignment selection to avoid or minimise impacts to infrastructure / land use and visual impact

Formal easement agreements outlining the legal responsibilities of APA Group and landholders

Management requirements specified in CEMP’s/EWP

Restrict disturbance to the ROW and approved access and work areas

Identification of utilities present on or near the easement on alignment sheets

Records of communications with landholders / third party prior to and during construction activities

Incident reports

Compliance with the National Parks and Wildlife Act 1972 and Regulations pertaining to correct conduct in a Regional Reserve

No pets or firearms brought into Regional Reserve

Management of fuel, oil and spills (if they occur) to meet landholder requirements for Quality Assurance programs (e.g. Cattlecare)

Records of communications with adjacent landholders / third party prior to and during maintenance work

Landholder contact records database

Use of Disturbance Checklist (including photo points) or inspection reports, specifically to look at: removal of waste products, re- instatement of soil profiles, adequate re-contouring of surface profile, return of land use

Measures undertaken to minimize third party use right-of-way where necessary

Where disturbance is unavoidable or accidental, infrastructure or land use is restored to the satisfaction of the landholder/owner or as near as practicable to undisturbed condition

Duration of disturbance does not exceed agreed timeframe

No disturbance outside the ROW and approved access and work areas

No reasonable complaints received

Adverse impacts to Innamincka Regional Reserve operations or conservation values are minimized

Achieved Records of ongoing liaison with landholders maintained.

There have been no reported spill incidents.

During the reporting period no operational activities were undertaken that would cause any impact on third party infrastructure and landholder on the pipeline. No complaints were received.

Page 28: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 28 of 30

Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /

Not Achieved

Comments

9.2 To minimize disturbance to landholders

Restrict disturbance to the ROW and approved access and work areas

Landholder activities not restricted as a result of pipeline activities

Records of communications with landholders / third party prior to and during construction activities.

Records of communications with adjacent landholders / third party prior to and during maintenance work

Landholder contact records database

Use of Disturbance Checklist and photo points

No reasonable landholder complaints

Landholder activities not restricted or disturbed as a result of pipeline activities unless by prior arrangement

Achieved During the reporting period no operational activities were undertaken that would cause any impact on landholders on the pipeline

Records of ongoing liaison with landholders maintained. No reasonable complaints received.

9.3 To appropriately reinstate and rehabilitate the easement to allow continuation of current land use activities post-construction

Management requirements specified in CEMP’s and property line list Reinstatement of easement in accordance with CEMP’s/EWP Records of communications with landholders prior to and during construction activities

Installation and monitoring of photo points (environmental monitoring points)

Species abundance and distribution on the easement is reasonably consistent with surrounding areas

Note: assessment of the consistency with surrounding areas will take into account that regrowth is a time and rainfall dependent process

Achieved There is evidence of vegetation regrowth along the length of the ROW.

10. To minimize the

risk to public health

and safety

10.1 To prevent injury to general public and adequately protect public safety during operations

Construction area cordoned off, entry to construction area from general public prohibited. Warning signs, tape, markers used to warn of restricted access area. Job Hazard Analysis

Records of communications with adjacent landholder prior to and during maintenance work including advice of the nature and schedule of maintenance activities

Use of signage or bunting to identify all potentially hazardous areas

Site induction program for all personnel/visitors.

Adequate implementation of traffic management

No reports of general public in construction area No injuries or incidents involving the public

Achieved

Established safe systems of work including the use of approved work instructions and procedures, job hazard analysis, permit to work and experienced staff all contributes to APA meeting this objective

Page 29: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 29 of 30

Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /

Not Achieved

Comments

practices

Records of Annual Reports, Fitness for Purpose Reports, Risk Assessments and inspections

Records demonstrating compliance with AS2885

Records of emergency response plan induction/training for construction, operation and maintenance personnel.

Incident Reports

Job Hazard Analysis

During the reporting period there were no operational activities that impacted upon public safety on the pipeline

10.2 To avoid fires associated with pipeline maintenance activities

Records of regular fire safety and emergency response training for construction, operations and maintenance personnel and review of procedures.

Established procedures for minimizing fire risk during maintenance

Appropriate fire prevention/control equipment on site

Incident reports

No fires related to pipeline construction, operation or maintenance activities

Achieved During the reporting period there have been no pipeline related fires

10.3 To prevent unauthorized activity on the easement that may adversely impact on the pipeline integrity

Inspection/Patrol reports and records

Comprehensive landholder liaison program and records of all communications with landholders

Community education program and Dial Before You Dig (DBYD) number and web page available and widely advertised.

Clear identification of the pipeline by signs installed in accordance with AS2855.

All reports of unauthorized activity are reported and investigated

No unauthorized activity on the easement that has the potential to impact on the pipeline integrity

Achieved During the reporting period there have been no unauthorized activities.

Page 30: 2014 Annual Report for QSN Pipeline - Mineralsminerals.statedevelopment.sa.gov.au/__data/assets/pdf_file/0007/... · door closure maintenance, coalescing filter inspection/maintenance

2014 Annual Report – QSN Pipeline

Document: 2014 Annual Report for QSN Pipeline Version: 1 Date: 9/06/2015 Page 30 of 30

Objective Goal Guide to How Objectives Can Be Achieved2 Assessment Criteria Achieved /

Not Achieved

Comments

11. To minimize

risk to the public

from Wastewater

11.1 To ensure that all wastewater (not from industrial processes) is collected, treated and disposed of so as to not adversely impact on health or the environment

• All wastewater disposed in accordance with the South Australian Public Health (Wastewater) Regulation 2013.

• The method of disposal for wastewater must:

a) comply with the SA Health On site Wastewater Systems Code; or

b) be to the satisfaction of the Department for Health and Ageing, see Objective 11 below as well.

• Approval must be given by the Department for Health and Ageing or relevant authority (within a Local Government area).

Waste water disposal system must comply with the SA Health On site Wastewater Systems Code; or be to the satisfaction of the Department for Health and Ageing, or relevant authority.

Achieved No wastewater was disposed to land in 2014

No activities were undertaken by APA on the QSN Link that would cause any impact on land or water resources quality on the pipeline during the reporting period

11.2 To ensure that there is no untreated wastewater exposed to the open environment or discharged directly into the ground.

• All wastewater disposed in accordance with the South Australian Public Health (Wastewater) Regulation 2013.

• The method of disposal for wastewater must:

c) comply with the SA Health On site Wastewater Systems Code; or

d) be to the satisfaction of the Department for Health and Ageing, see Objective 11 below as well.

• Approval must be given by the Department for Health and Ageing or relevant authority (within a Local Government area).

Waste water disposal system must comply with the SA Health On site Wastewater Systems Code; or be to the satisfaction of the Department for Health and Ageing, or relevant authority.

Achieved No wastewater was disposed to land in 2014

No activities were undertaken by APA on the QSN Link that would cause any impact on land or water resources quality on the pipeline during the reporting period

1 Assessment criteria shown have been developed to be “black and white”. Professional judgment is required to assess whether non-compliance is minor or major. It is necessary to ensure that adequate information is available to enable this judgement to be made.

2 This column is provided for information only. Under the Petroleum Act 2000, only objectives and assessment criteria are approved.

3 Guidelines for a Native Vegetation Significant Environmental Benefit Policy For the clearance of native vegetation associated with the minerals and petroleum industry