2012-091 bwr vessel & internals project (bwrvip) · 2012-091 bwr vessel & internals project...

221
ELECTRIC POWER RESEARCH INSTITUTE 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville Pike Rockville, MD 20852 Attention: Andrew Hon Subject: Project No. 704 - BWR Vessel and Internals Inspection Summaries for Spring 2011 Outages Enclosed are five (5) copies of the document entitled "BWR Vessel and Internals Project, Vessel Internals Inspection Summaries for Spring 2011 Outages, April 2012." The information provided in the enclosed document identifies the BWR internal components inspected and generally includes the date or frequency of inspection, the inspection method used and a summary of results including repair or replacement activities. The enclosed document is being provided to the NRC for information only. The information contained in the enclosed document was developed by the individual utilities and has been compiled into the enclosed document by the BWRVIP. The BWR VIP plans to continue to gather such information and to provide periodic updates such as in the enclosed document. Representatives of the BWRVIP would be pleased to meet with the NRC staff to discuss any comments or questions related to the enclosed document. If you have any questions on the enclosed document or the general subject of inspection results, please call Chuck Wirtz, BWRVIP Integration Committee Technical Chairman, FirstEnergy, at 440.280.7665. Sincerely, Dave Czufin Exelon Chairman, BWR Vessel and Internals Project Together... Shaping the Future oF Electricity PALO ALTO OFFICE 3420 Hillview Avenue, Palo Alto, CA 94304"1395 USA * 6 50.55. 2 000 * Customer Service 800.313.3774 * www.epri.com AM 1-k a f co(iAL

Upload: others

Post on 24-Jul-2020

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

ELECTRIC POWERRESEARCH INSTITUTE

2012-091 BWR Vessel & Internals Project (BWRVIP)

May 2, 2012

Document Control DeskU. S. Nuclear Regulatory Commission11555 Rockville PikeRockville, MD 20852

Attention: Andrew Hon

Subject: Project No. 704 - BWR Vessel and Internals Inspection Summaries for Spring 2011Outages

Enclosed are five (5) copies of the document entitled "BWR Vessel and Internals Project, VesselInternals Inspection Summaries for Spring 2011 Outages, April 2012."

The information provided in the enclosed document identifies the BWR internal componentsinspected and generally includes the date or frequency of inspection, the inspection method usedand a summary of results including repair or replacement activities. The enclosed document isbeing provided to the NRC for information only.

The information contained in the enclosed document was developed by the individual utilitiesand has been compiled into the enclosed document by the BWRVIP. The BWR VIP plans tocontinue to gather such information and to provide periodic updates such as in the encloseddocument.

Representatives of the BWRVIP would be pleased to meet with the NRC staff to discuss anycomments or questions related to the enclosed document. If you have any questions on theenclosed document or the general subject of inspection results, please call Chuck Wirtz,BWRVIP Integration Committee Technical Chairman, FirstEnergy, at 440.280.7665.

Sincerely,

Dave CzufinExelonChairman, BWR Vessel and Internals Project

Together... Shaping the Future oF Electricity

PALO ALTO OFFICE3420 Hillview Avenue, Palo Alto, CA 94304"1395 USA *

6 50.55.2 000 * Customer Service 800.313.3774 * www.epri.com

AM 1-k a f co(iAL

Page 2: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

BWR Vessel and Internals Project

Vessel Internals Inspection Summariesfor Spring 2011 Outages

April 2012

Page 3: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Table of Contents

Plant Page

1. Browns Ferry Nuclear Plant: Unit 2 32. Brunswick Unit 2 223. Columbia Generating Station 354. Cooper Nuclear Station 415. Hatch Unit 2 606. LaSalle 2 717. Limerick Generating Station, Unit 2 828. Monticello 1109. Nine Mile Point Unit #1 13310. Perry Nuclear Power Plant 14511. Pilgrim 16012. Quad Cities Unit 1 17713. River Bend 19414. Susquehanna Unit #2 202

2

Page 4: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Reactor Internals Insvection History

Plant: Browns Ferry Nuclear Plant: Unit 2

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Inspection Results, Repairs,

Inspection Used Replacements, Reinspections

Core Shroud 1994 UT Baseline (1994) per GE SIL No. 572 forcircumferential seam welds - indicationsfound in several welds (H2, H3, H5).

1996 UT Reinspection (1996) per GE SIL No. 572- indications found in H 1, H6, and H7welds along with previous indications.Full structural margins on flawed weldsfor at least one additional operatingcycle. Vertical welds not inspected.

1997 UT Reinspection (1997): UT examination ofH1, H2, H3, H4, H5, H6, & H7performed per BWRVIP I&E guideline.Six new indications recorded. All otherindications recorded in earlier outagesexhibited no significant flaw growth.Satisfactory structural margins on theflawed welds for at least one additionaloperating cycle. Vertical welds notinspected. All seven horizontal weldswill be reinspected in 2007, along withany required vertical welds.

2007 UT Reinspection (2007): UT examination ofHI (single-sided) and H2, 1-13, H4, H5,H6, H7, V7, and V8 (two-sided)performed per BWRVIP-76. The lengthof the weld inspected was at least 50percent of the weld circumference in allcases. Flaws observed in six (H 1, H2,H3, H4, H5, & H7) horizontal weldswere less than 20 percent of examinedlength. Barring license renewal impacts,all seven horizontal welds (along withany required vertical welds) will not bereinspected until 2017.

Shroud Support [1996 1 EVT-1, UT I(1996): Access Hole Cover Welds at 00

Page 5: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

1999

2005

2009

2011

EVT- I

EVT-1, UT

EVT-I, UT

EVT- I

and 1800 UT examined in both the radialand circumferential directions per therequirements of GE SIL No. 462. Noreportable indications on either cover.

Baseline (1999): EVT-I inspection perBWRVIP-38 for Shroud Support WeldsH-8 and H-9 at 0 and 180 degreelocations. No reportable indications.

Reinspection (1999): UT inspection ofaccess hole cover locations at 0 and 180degrees. No reportable indications.

Reinspection (2005) of access hole coverlocations at 0 and 180 degrees per GESIL No. 462 RI (EVT-1). No reportableindications were found.

Reinspection (2005) of Shroud SupportWelds H-8 (EVT-1) and H-9 (manualUT) per BWRVIP-38, -104. Noreportable indications were found.

(2009): Baseline UT inspection usingphased array per BWRVIP-180 of accesshole cover locations at 0 and 180degrees. Supplemental EVT-1examinations performed of those areasthat were not accessible for UT. Norelevant indications.

Reinspection (2011) of Shroud SupportWeld H-8 (EVT-l) per BWRVIP-38. Norelevant indications.

Core Spray Piping 1996

1997

1999

EVT- 1,VT- 1,VT-3

EVT-I,UT, VT- I

EVT-I

(1996): Inspection per IEB 80-13/GESIL No. 289 R1S2 of piping and welds inannulus. No reportable indications.

Baseline inspection (1997) per BWRVIP-18: Inspected all accessible welds (T-Box, welds on Downcomers "A", "B","C", & "D") with UT and inaccessiblewelds (Piping Bracket (PB) welds) withVT. No reportable indications.

(1999) Inspected Piping Bracket (PB)welds; P4d, P8a, P8b welds on "A", "B","C", "D" downcomers) per BWRVIP-18

4

Page 6: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

(EVT- 1). No reportable indications.

2001 EVT-1, Reinspection (2001) per BWRVIP-1 8:UT, VT-I EVT-1 visual examination of T-Box

welds. No reportable indications. UTexamnination of Downcomer "A" elbowwelds and Downcomer "A", "B", "C", &"D" sleeve welds. No reportableindications.

2003 EVT-I, Reinspection (2003) per BWRVIP-18:UT, VT-I EVT-I visual examination of T- Box

welds. No reportable indications.

2005 EVT-1, Reinspection (2005) per BWRVIP-18:UT, VT-I EVT-1 visual inspections (T-Box welds

@ 120 degrees and 240 degrees). Noreportable indications. UT examinationof Downcomer "B" elbow welds andDowncomer "A", "B", "C", & "D"sleeve welds. No reportable indications.

2007 EVT-I, Reinspection (2007) per BWRVIP-18:UT, VT-I EVT-I visual examinations (T-Box

welds @ 120 and 240 degrees, PipingBracket (PB) welds @ 15, 110, 130, 165,195, 230, 250, and 345 degrees). Noreportable indications.

2009 EVT-1, Reinspection (2009) per BWRVIP-18,UT, VT-I Rev. 1: EVT-1 visual inspections (T-

Box welds @ 120 and 240 degrees). Noreportable indications. UT examinationof Downcomer "C" elbow welds andDowncomer "A", "B", "C", & "D"sleeve welds (supplemental EVT-1 onWelds 8a and 8b). No relevantindications.

2011 EVT-I Reinspection (2011) per BWRVIP-18,Rev. 1: EVT-i visual inspections (T-Box welds @ 120 and 240 degrees,Downcomer "C" elbow welds (P4a-d)and Downcomer "A"-"D" sleeve welds(P8a and P8b)). No relevant indications.

Core Spray Sparger 1996 EVT-I, (1996): Inspection per IEB 80-13 ofVT-I, welds on sparger. One small indication inVT-3 lower tack weld of the nozzle to "B"

sparger in Nozzle 3B. No other

5

Page 7: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

indications were recorded.

1997 EVT-1, Reinspection (1997): No reportableVT-1, indications found. Small linearVT-3 indication on tack weld for Nozzle 3B

observed during 1996 exam was notfound upon reexamination.

1999 EVT-1, Reinspection (1999) per BWRVIP-I18:VT-1, EVT-1 and VT-3 of sparger welds. NoVT-3 reportable indications found.

2003 EVT-1, Reinspection (2003) per BWRVIP-18:VT-1, EVT-I (SI, S2, S4) and VT-1 (S3a, S3b,VT-3 S3c, SB) inspections of sparger welds.

No reportable indications.

2007 EVT-1, Reinspection (2007) per BWRVIP-18:VT-1, EVT-1 (SI, S2, S4) and VT-1 (S3a, S3b,VT-3 $3c, SB) inspections of sparger welds.

Upper Sparger bracket at 273 degrees isdisplaced from the lower brackets.Otherwise, no reportable indications.

2011 EVT-I,ý Reinspection (2011) per BWRVIP-1 8,VT-1, Rev. 1: EVT-I (Si, S2, S4) and VT-IVT-3 (S3a, S3b, $3c, SB) inspections of

sparger welds. No relevant indications.

Top Guide (Rim, etc.) 1996 EVT-1, (1996): Lower side of beams (in cellsVT-1, where fuel and blade guides areVT-3 removed) VT-3 inspected in accordance

with GE SIL No. 554. No indicationswere recorded.

1997 EVT-1, Reinspected (1997): Top GuideVT-i, Alignment Pins & Bolts visuallyVT-3 inspected per SIL 588. No indications

found.

1999 EVT-1, Baseline inspection (1999) per BWRVIP-VT-I, 26: Inspected Rim Welds (Location 11)VT-3 (EVT-1) and Aligner Pins (Locations

2/3) (VT-I) at 2 locations. No reportableindications found.

2001 EVT-1, Expanded baseline inspection (2001) perVT-I, BWRVIP-26: Locations 1, 4, 6, 10, 12,VT-3 13, 15, and 16 EVT-1 inspected; no

reportable indications

2003 EVT-1, Reinspection (2003) per BWRVIP-26:

6

Page 8: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

VT-1, Locations 2 and 3 (VT-I) and LocationVT-3 II (EVT-i) examined on two adjacent

aligner assemblies with no reportableindications.

2007 EVT-I, Reinspection (2007) per BWRVIP-26:VT-1, Locations 2 and 3 (VT-1) and Location

11 (EVT-I) examined on two adjacentaligner assemblies with no reportableindications.

2011 EVT-1, Baseline (2011) per BWRVIP-183:VT-I Location I (Grid Beam and Beam-to-

Beam Crevice Slot) inspected (EVT-1)for two grid beam cells; no reportableindications. Reinspection (2011) perBWRVIP-26: Locations 2 and 3 (VT-1)and Location II (EVT-1) examined ontwo adjacent aligner assemblies with noreportable indications.

Core Plate (Rim, etc.) 1996 VT-3 (1996): The core plate bolts werevisually inspected in accordance with GESIL No. 588. No indications wererecorded.

1997 VT-3 Reinspected (1997) per BWRVIP-25with one plug not seated; otherwise noindications found.

1999 VT-3 (1999): Inspected core plate bolts (VT-3)at accessible locations per BWRVIP-25with no reportable indications.

2001 VT-3 Reinspection (2001) per BWRVIP-25:Holddown Bolts (Location 10) VT-3inspected with no reportable indications.Plugs (Location 13) VT-3 inspected withno reportable indications. Aligner PinSocket to Rim Welds (Location 8) wereinaccessible.

2003 VT-3 Reinspection (2003) per BWRVIP-25:All thirty-four (34) holddown bolts(Location 10) were VT-3 inspected withno reportable indications. Fifteen (15)plugs (Location 13) were VT-3 inspectedwith no reportable indications.

7

Page 9: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2005 VT-3 Reinspection (2005) per BWRVIP-25:All thirty-four (34) holddown bolts(Location 10) were VT-3 inspected withno reportable indications. Thirty-three(33) plugs (Location 13) were VT-3inspected with no reportable indications.

2007 VT-3 Reinspection (2007) per BWRVIP-25:All thirty-four (34) holddown bolts(Location 10) were VT-3 inspected withno reportable indications. Sixteen (16)plugs (Location 13) were VT-3 inspectedwith no reportable indications.

2009 VT-3 Reinspection (2009) per BWRVIP-25:All thirty-four (34) holddown bolts(Location 10) were VT-3 inspected withno relevant indications. Core plate plugs(Location 13) adjacent to three (3)control rod guide tubes inspected with norelevant indications.

2011 VT-3 Reinspection (2011) per BWRVIP-25:All thirty-four (34) holddown bolts(Location 10) were VT-3 inspected fromabove with no relevant indications.

SLC Prior to 2005 VT-2 (Prior to 2005): Nozzle is leak checkedevery outage and volumetric exams areconducted per ASME Section XI coderequirements. No indications noted.

2005 EVT-2 (2005): Bare metal examination (EVT-2)performed per BWRVIP-03, -27. Noreportable indications found.

2007 EVT-2 (2007): Bare metal examination (EVT-2)performed per BWRVIP-03, -27. Noreportable indications found.

2009 EVT-2 (2009): Bare metal examination (EVT-2)performed per BWRVIP-03, -27. Norelevant indications found.

2011 EVT-2 (2011): Bare metal examination (EVT-2)performed per BWRVIP-03, -27. No

8

Page 10: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

relevant indications found.

UT (2011): UT performed on SLC InjectionNozzles N 10 (stainless steel safe end-to-pipe weld); no recordable indicationsnoted.

Jet Pump Assembly 1996

1997

1999

EVT-I,MVT-1,VT-i,VT-3

EVT- 1,MVT-1,VT-1,VT-3

EVT- 1,VT-1,VT-3

(1996): VT-3 inspection of sensing linesper GE SIL No. 420 - no indicationsrecorded. Jet pump throats inspected perGE SIL No. 465 for Jet Pumps 11 & 12 -build-up found in inlet mixer that mayrequire internal cleaning during nextrefueling outage. Riser braces for JetPumps 11-20 VT-I inspected per GE SILNo. 551 - no indications were recorded.Jet pump adjusting screws VT-Iinspected per GE SIL No. 574 - minorindications on set screw tack welds forJet Pumps 1, 11, & 12 that wereevaluated and determined to be irrelevantdue to their small size. NOTE: Group 1jet pump beams were replaced withGroup 11 beams (that are high temp.annealed and have a reduced preload)during the Cycle 4 Outage (1983).

Reinspected (1997): Jet Pumps I thru 20- Adjusting Screws (VT-3), Riser ElbowWelds (MVT-1), & Sensing Lines. JetPumps I thru 10 - Riser Braces. GE SILNos. 574, 551, 60, 420, & RICSIL 078used as guidance. Previous indication onset screw tack weld for Jet Pump I notfound. Previous indication on set screwtack welds for Jet Pumps 11 & 12unchanged. Slight gap observed onshroud-side set screw for Jet Pump Nos.7 & 16, vessel-side set screw for JetPump No. 14. No other reportableindications.

Baseline (1999) per BWRVIP-41: VT-3of holddown beam locations BB-I andBB-2 to verify proper function of beam(all 20 jet pumps) - no indications.EVT-I of High Priority Locations RS-1,

9

Page 11: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

RS-2, RS-3, DF-2, AD-1, AD-2, AD-3a,AD-3b (all 20 jet pumps); no reportableindications.

2001 EVT-1, Baseline (2001) per BWRVIP-41:VT- I EVT-1 of Medium Priority Locations

RB-Ia-d, RB-2a-d; no reportableindications.

2003 EVT-1, Baseline (2003) per BWRVIP-41:VT- I EVT-1 of holddown beam locations BB-

I and BB-2 (Jet Pumps 11 thru 20) - noreportable indications. EVT-1 ofMedium Priority Locations RS-6, RS-7,RS-8, RS-9, IN-4, MX-2, DF-l (JetPumps II thru 20); no reportableindications. VT-I of Medium PriorityLocation WD-1; wear noted on inlet-mixer wedge and restrainer bracket padfor Jet Pump Nos. 13, 14, 17 (the mostsevere), and 20. Scope expanded toperform VT-I of WD-1 for Jet Pumps Ithru 10; wear noted on inlet-mixerwedge/restrainer bracket pad for JetPump No. 4. Reinspection (EVT-1) ofRiser Brace Welds RB-la-d and RiserPipe Weld RS-1 (Jet Pumps 3/4, 13/14,17/18, 19/20), along with additionalbaseline inspection (EVT-1) of RiserPipe Welds RS-8 and RS-9 (Jet Pumps3/4) performed per Justification forContinued Operation (JCO) issued forcontinued operation of Jet Pumps 4, 13,14, 17, and 20 through U2C 13 FuelCycle; no reportable indications. VT-1of Set Screw Locations AS-I and AS-2performed for Jet Pumps 4 (additionalscope) and 11 thru 20; previousindications on vessel-side set screw (JetPump 11) and shroud-side set screw (JetPump 12) observed with no changes,previous set screw gap on vessel-side setscrew for Jet Pump 14 not observed,previous set screw gap on shroud-side setscrew for Jet Pump 16 observed - gap isapproximately 1/5 of a thread width.

10

Page 12: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2005 UT, Baseline (2005) per BWRVIP-41, -138:VT- I UT (newly-qualified technique) of

holddown beam locations BB-1, BB-2,and BB-3 (Jet Pumps I thru 20) - noreportable indications.

Reinspection (2005) per BWRVIP-41:VT-I of Medium Priority Location WD-I (Jet Pumps 1 thru 20); wear noted oninlet-mixer wedge and restrainer bracketpad for Jet Pump Nos. 4, 7, 13, 14, 17(the most severe), and 20. No additionalwear noted since 2003 inspection.Wedge rod wear noted for Jet Pump Nos.4, 8, 17, and 20. Dimensional problemswith slip joint clamps prevented theirscheduled installation on five (5)jetpumps. Qualitative Assessment justifiedcontinued operation of jet pumps throughU2C14 Fuel Cycle. VT-I of Set ScrewLocations AS-I and AS-2 performed forJet Pumps I thru 20. Backlightingidentified ten (10) set screw gaps rangingfrom 8 to 44 mils in width. Onereportable linear indication identified onoutboard shroud-side set screw tack weldfor Jet Pump No. 12. Nine (9) auxiliarywedges installed on Jet Pumps 1, 2, 4, 5,10, 12, 14, 16, and 20.

2007 EVT-1, Baseline (2007) per BWRVIP-41:VT- I EVT- I of Medium Priority Locations

RS-6 & RS-7 (Jet Pumps I thru 10), RS-8 & RS-9 (Jet Pumps 1, 2, 5 thru 10), IN-4, MX-2, & DF- 1 (Jet Pumps I thru 10);no reportable indications.

Reinspection (2007) per BWRVIP-41:EVT-I of Medium Priority LocationsRB-la-d, RB-2a-d (Jet Pumps I thru 6),RS-8 & RS-9 (Jet Pumps 3 & 4); noreportable indications.

EVT-I of High Priority Locations RS-1,RS-2, RS-3, DF-2, AD-I, AD-2, AD-3a,

11

Page 13: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

& AD-3b (Jet Pumps I thru 10); noreportable indications.

VT-I of Medium Priority Location WD-I (Jet Pumps I thru 20); vibration-induced wear noted on inlet-mixer wedgeand restrainer bracket pad for Jet PumpNos. 3 (new) along with 4, 13, 14, 17,and 20 (existing but unchanged since2003 inspection). Slip joint clampsinstalled on these six (6)jet pumps.Service-induced wear noted on inlet-mixer wedge for Jet Pump Nos. 4(existing but unchanged since 2005inspection) along with 5, 12, 16, and 19(new). Minor rod wear observed for JetPump Nos. 3, 5, 13, & 15 (new) alongwith 4, 8, 17, & 20 (existing, butunchanged since 2005).

VT-I of Set Screw Locations AS-I andAS-2 performed for Jet Pumps I thru 20.Backlighting identified four (4) set screwgaps ranging from 7 to 12 mils in width.Vessel-side gap on Jet Pump 9 grew from9 to 19 mils following attempts to reseatinlet-mixer. One reportable linearindication identified on inboard vessel -side set screw tack weld for Jet PumpNo. 15. Nine (9) auxiliary wedgesinstalled in 2005 inspected to verifycontact; no reportable indications.

2009 EVT-1, Reinspection (2009) per BWRVIP-41,VT- I Rev. I:

VT- I of Medium Priority Location WD-I (Jet Pumps I thru 20); vibration-induced wear noted on inlet-mixer wedgeand restrainer bracket pad for Jet PumpNos. 7 and 18 (new) along with 3, 4, 13,14, 17, and 20 (existing but unchangedfrom previous inspections). Slip jointclamps installed on Jet Pumps 7 and 18.Service-induced wear noted on inlet-mixer wedge for Jet Pump Nos. 5, 6, 8, 9,

12

Page 14: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

10, 12, and 16.

VT-I of Set Screw Locations AS-I andAS-2 performed for Jet Pumps 1 thru 20.Backlighting identified three (3) setscrew gaps that exceeded the 15-milcriteria for installation of an auxiliaryspring wedge. Auxiliary spring wedgesinstalled on shroud-side set screw for JetPump No. 7 and the vessel-side set screwfor Jet Pump Nos. 9 and 13. Threerelevant weld indications were noted onthe inboard vessel-side set screw tackwelds for Jet Pump Nos. 11 (firstidentified during U2C7 Refueling Outage(RFO) in 1994), 13, and 15 (firstidentified during U2C13 RFO in 2005).

Six (6) slip joint clamps installed in 2007inspected to verify hardware remains asinstalled; no relevant indications.

VT-3 visual examination of sensing lineclamps installed during U2C14 RFO(2007) on Jet Pumps 1-5 and 11-15performed to confirm that all of therepair hardware is in place and that thehardware has not shifted or changed fromthe as-installed condition. No relevantindications were observed.

2011 UT, Reinspection (2011) per BWRVIP-41EVT-I, R3, -138 RI: UT ofholddown beamVT-I locations BB-I and BB-2, (Jet Pumps I

thru 20) - no reportable indications.

EVT-l of Medium Priority LocationsRS-8 and RS-9 (Jet Pumps 1 thru 20)performed in accordance with BWRVIPLetter No. 2009-202 ("Interim Guidancefor Accelerated Inspections of Jet PumpRiser to Riser Brace Welds andWedges"); no reportable indications.

VT-I of Medium Priority Location WD-1 (Jet Pumps I thru 20); no additional

13

Page 15: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

I vibration-induced wear noted.

VT-I of Set Screw Locations AS-I andAS-2 performed for Jet Pumps I thru 20.Backlighting identified two new setscrew gaps, one of which (Jet Pump 18Vessel-Side set screw (VS-SS)) exceededthe 15-mil criteria for installation of anauxiliary spring wedge. Justification forContinued Operation (JCO) was preparedand concluded that Jet Pump 18 isacceptable as-is for one fuel cycle. Tworelevant weld indications were noted onthe outboard VS-SS tack weld for JetPump 11 (first identified during Unit 2Refueling Outage 7 (U2R7) in 1994) andthe inboard VS-SS tack weld for JetPump 15 (first identified during U2RI3in 2005); indications were unchanged.

VT-3 of two slip joint clamps and threeauxiliary spring wedges installed in 2009was performed to inspected to verifyhardware remains as-installed; norelevant indications.

Jet Pump Diffuser N/A N/A N/A

CRD Guide Tube 2005 EVT-I, Baseline (2005) per BWRVIP-47: 10VT-3 control rod guide tubes examined. VT-3

visual examination of Locations CRGT-1and FS/GT-ARPIN-1, EVT-I visualexamination of Locations CRGT-2 andCRGT-3; no reportable indications.

2007 EVT-1, Baseline (2007) per BWRVIP-47: 3VT-3 control rod guide tubes examined. VT-3

visual examination of Locations CRGT-1and FS/GT-ARPIN-I, EVT-1 visualexamination of Locations CRGT-2 andCRGT-3; no reportable indications.

2009 EVT-1, Baseline (2009) per BWRVIP-47: 3VT-3 control rod guide tubes examined. VT-3

visual examination of Locations CRGT-1and FS/GT-ARPIN-1, EVT-I visualexamination of Locations CRGT-2 and

14

Page 16: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

CRGT-3; no relevant indications.

2011 EVT-1, Baseline (2011) per BWRVIP-47: 3VT-3 control rod guide tubes examined. VT-3

visual examination of Locations CRGT-Iand FS/GT-ARPIN-1, EVT-I visualexamination of Locations CRGT-2 andCRGT-3; no relevant indications.

CRD Stub Tube N/A N/A A general area inspection was performedin 1991 while a jet pump was removed.The periphery stub tubes and housingwere visible. No indications orabnormalities were noted.

In-Core Housing N/A N/A N/A

Dry Tube 1994 VT Dry tubes inspected during U2C7Refueling Outage per the requirements ofGE SIL No. 409. Cracking wasobserved; tubes replaced with modifieddesign which is resistant to crackingduring U2C7 Reftieling Outage.Inspections will be scheduled after drytubes have reached the expected 20-yearlife (2013).

Instrument 2009 VT-2 Visual leak check is performed duringPenetrations each refueling outage. No reportable

indications reported to date.

UT UT performed on RPV InstrumentNozzles N II A/B, N 12A/B, and N 16A/Bin response to indication found on N I I Bsafe end-to-pipe weld during U1C7Refueling Outage. Flaw was found inN 12A austenitic stainless steel safe endmaterial approximately 0.5" from safeend-to-pipe weld. Full structural weldoverlay was applied to maintain pressureboundary integrity.

2011 VT-2 Visual leak check performed duringU2R 16. No reportable indicationsreported.

UT UT performed on RPV InstrumentNozzles NI I A/B, N 12B, and N 16A/B

15

Page 17: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

(stainless steel safe end-to-pipe weld)and Nozzle NI12A (weld overlay appliedduring U2R15 (2009)); no recordableindications noted.

Vessel ID Brackets 1996 EVT- 1, (1996): The dryer support brackets,VT-1, guide rod brackets, feedwater spargerVT-3 brackets, core spray piping brackets, jet

pump riser support bracket, and shroudsupport were visually inspected inaccordance with BFN SurveillanceInstruction 2-SI-4.6.G. No indicationsrecorded to date.

1997 Reinspection (1997): No reportableindications.

2001 Reinspection (2001): No reportableindications.

2003 Reinspection (2003): No reportableindications.

2007 Reinspection (2007): Core Spray Piping(VT-3) and Jet Pump Riser Brace (EVT-1) visually examined; no reportableindications. EVT-I/VT-3 examinationperformed of all twelve (12) FeedwaterSparger End Brackets. Minor wearobserved under the retaining pin for theend bracket at eight (8) locations.Qualitative assessment performed toaccept-as-is for one cycle. Additionalinspections during the U2C 15 RFO in2009 will be scheduled to determine theextent of any additional wear.

2009 EVT-1, Reinspection (2009): VT-3 visualVT- 1, examination performed of all twelve (12)VT-3 Feedwater Sparger End Brackets. Minor

wear observed under the retaining pin forthe end bracket at eight (8) locationsduring previous inspection in 2007 wasunchanged. Qualitative assessmentperformed to accept-as-is for one cycle.Additional inspections during the U2C 16Refueling Outage in 2011 will be

16

Page 18: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2011 EVT- 1,VT-I,VT-3

scheduled to determine the extent of anyadditional wear. A contingencymodification will also be developed inthe event that the inspection resultsdictate that repair of the end bracket isrequired for continued operation.

Reinspection (2011): VT-3 visualexamination performed of all twelve (12)Feedwater Sparger End Brackets. Minorwear observed under the retaining pin forthe end bracket at eight (8) locationsduring previous inspection in 2009 wasunchanged. Additional inspectionsduring Unit 2 Refueling Outage 17(U2R1 7) in 2013 will be scheduled todetermine the extent of any additionalwear. A contingency modification willalso be developed in the event that theinspection results dictate that repair ofany end brackets is required forcontinued operation.

LPCI Coupling N/A N/A Not applicable to this plant

Steam Dryer 1989 VT-3 (1989): During Unit 2 Restart, crackingwas found in 3 of 8 Unit 2 Steam DryerDrain Channel to Skirt AttachmentWelds. Repair of the cracked welds andreinforcement of all 8 welds for futuremitigation performed.

1994 VT-3 (1994): Welds associated with DrainChannel #4 (Azimuth 3 100) visuallyinspected (VT-3) in accordance withvendor requirements. No reportableindications were noted.

1997 VT- 1, (1997): Welds associated with DrainVT-3 Channel #1 (Azimuth 500) were visually

inspected (VT-3) in accordance withvendor requirements. No reportableindications were noted.

2001 VT-1, (2001): Welds associated with DrainVT-3 Channel #2 (Azimuth 1300) were

visually inspected (VT-3) in accordance

17

Page 19: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

with vendor requirements. No reportableindications were noted.

2005 VT-i, (2005): The following locations wereVT-3 visually inspected (VT-1) in accordance

with BWRVIP-139 and GE SIL 644 RI:* Horizontal and vertical welds which

outline the steam dryer outer bank* Cover plate between the outer hood

vertical plate and the support ring" Weld seams associated with the outer

side of the inner banks* Dryer manway @ 90'No reportable indications were noted.

* Stabilizer/Tie Bars - Deformationnoted on center tie bars betweenBanks 3 & 4: All 3 locations (00,center, 180'). Evaluation performedto accept-as-is for next fuel cycle(U2C14 Fuel Cycle), which is thefinal fuel cycle prior to ExtendedPower Uprate (EPU) implementation.

The following locations were inspectedin accordance with INPO OE:* Leveling screw tack welds @ 50 &

185' - No reportable indications werenoted.

" Dryer surfaces - Light to heavy NobleMetal coating observed in manyareas, some with flaking (NRI).Also, a metal abrasion was notedabove the lower guide bracket (NRI).

Welds associated with Drain Channel #3(Azimuth 2300) visually inspected (VT-3) i.a.w. vendor requirements. Noreportable indications were noted.

2007 VT-I Stabilizer/Tie Bars - No apparent changeto deformation noted on center tie barsbetween Banks 3 & 4: All 3 locations(0', center, 180'). Small deformationnoted for Tie Bar 4/5-1. In addition, theDryer Center Bank Divider was observedto be bent. Evaluation performed toaccept-as-is until Extended Power Uprate

18

Page 20: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

(EPU) implementation.

Pre-EPU inspection of Steam SeparatorStandpipe Welds performed to look forfatigue cracking; no reportableindications.

Pre-EPU inspection of all 48 ShroudHead Bolts performed to look for wear inlocking pin window and on mid-span andtop support ring gussets; no reportableindications.

2009 VT-1, (2009): The "green" weld locationsVT-3 (locations associated with field cracking

throughout the BWR fleet) were visuallyinspected (VT-I) in accordance withBWRVIP-139. 9 anomalies wereidentified:* 3 tie bars severed at one end (TBs-

3/4-01, -02, & -03)* TB-4/5-02 contained an indication on

the SE end of the bar in the weld* 4 tie bars were slightly bowed (TBs-

1/2-01, -02, 5/6-01, -02)* Center Divider (Baffle) Plate between

Banks 3 and 4 was deformedWeld was repaired for TB-4/5-02 andseven (7) broken/damaged tie barsreplaced with EPU-qualifiedreplacements.

Scope was expanded to visually inspect(VT-I) all "red" weld locations (locationsimportant to dryer integrity) inaccordance with BWRVIP-139. Inaddition, high stress weld locations asidentified in the steam dryer analysis forEPU were VT-i inspected as well aslocations subject to load increase oncethe center tie bars failed (due to vanebank displacement). During the courseof these additional scope exams, threevertical welds (2V01, 2V10, and 5V10)on the ends of the 3/8-inch plate attachedto the vane bank dryer units were found

19

Page 21: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

to have no weld metal present forapproximately six inches at the top of thewelds. These three welds were repairedand restored to their original designcondition.

All repairs will be inspected during theU2C16 RFO in 2011 to ensure thatstructural integrity of the dryer ismaintained. Additionally, any originaltie bars that have not yet been replacedwill be replaced during the U2C16 RFOin preparation for initiation of EPUoperation during the U2C17 Fuel Cycle.Dryer Drain Channel Welds associatedwith Drain Channels 1-4 and DryerManway Cover were VT-I inspected inaccordance with BWRVIP-139. Norelevant indications were observed.Seismic Lugs at 90 and 270 degrees wereVT-3 inspected for general overallcondition. No relevant indications wereobserved.

The following locations were inspectedin accordance with INPO OE:* Leveling screw tack welds at 5 and

185 degrees were VT-1 inspected -No relevant indications noted.

" Dryer hood exterior surfaces abovethe support ring were VT-3 inspected- light to heavy scale deposits found.

2011 VT-I (2011): Three areas (Welds B2V-01,B2V-l0, B5V-10) that were repairedduring U2RI5 (2009) and seven UpperBank Tie Bars (TB- 1/2-01, -02, TB-3/4-01, -02, -03, TB-5/6-01, and -02) thatwere replaced during U2RI5 (2009) wereexamined with no evidence of change.The six remaining original Upper BankTie Bars (TB-2/3-01, -02, -03, TB-4/5-01, -02, and -03) showed signs ofdistortion. An evaluation was performedto accept these tie bars as-is for one cycleof operation. These six original tie bars

20

Page 22: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

will be re-examined during U2RI7(2013). In the event of additionaldistortion and/or damage, a contingencyplan will be in place to replace theseoriginal tie bars with EPU-qualified tiebars.

Steam Separator 2011 VT-3 Steam Separator tie bars (cross bracing)examined for signs of cracking(Reference: INPO OE 30657). Norelevant indications were observed on thecross bracing.

DM Welds - 2009 N/A No Cat. C DM Welds were inspectedBWRVIP-75-A during Unit 2 Refueling Outage 15Cat. C (U2RI 5).

2011 N/A No. Cat. C DM Welds were inspectedduring Unit 2 Refueling Outage 16(U2R 16).

DM Welds - 2009 N/A No Cat. D DM Welds were inspectedBWRVIP-75-A during Unit 2 Refueling Outage 15Cat. D (U2R15).

2011 UT 2 welds inspected (DRHR-2-1 1, RCRD-2-50): PDI-qualified, automated exams.No flaws identified, no repairs.

21

Page 23: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Reactor Internals Insnection History

Plant: Brunswick Unit 2

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Inspection Results, Repairs,

Inspection Used Replacements, Re-inspections

Core Shroud 1993 EVT-1 and EVT-1 baseline, except UT on H4.UT Installed pre-emptive clamp repair on

H2/H3. Indications in severalcircumferential welds. Full structuralmargins on non-repaired welds.

1995 UT UT re-inspected H4 with no growth inindications. UT baseline H 1, H6A, H6Band H7. Several indications noted withfull structural margins maintained. VT-Iand VT-3 inspected 3 repair bracketswith no indications noted.

1997 UT UT re-inspected H4 and H6B (lower)with no growth in indications noted. Fullstructural margins maintained. UTbaseline H5 with no indications noted.VT-I and VT-3 inspected 3 repairbrackets with no indications noted.

1999 UT/EVT-1 UT re-inspected H1, H4 and H6B withno growth in indications noted. Fullstructural margins maintained. EVTvertical welds V3, V4, V5, and V6 withno indications. VT-I and VT-3 inspected3 repair brackets with no indicationsnoted.

2001 UT/EVT-I UT re-inspected 100% of H6b and twoselected areas of H4. Problems wereencountered with lift-off of the UTpackage. The inspection data is stillunder investigation. EVT-I of OD ofvertical welds V9, V 10, and VI I with noindications noted. VT-I /VT-3 inspected3 repair clamps with no indicationsnoted.

22

Page 24: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2003

2005

2007

2009

2011

EVT-1

VT- 1/VT-3

VT-i /VT-3

UT

'4

UT

VT- 1/VT-3

EVT-1

VT-I /VT-3

EVT-1

VT- 1/VT-3

EVT-1 of vertical welds VI and V2. Noindications noted.

VT-I /VT-3 of shroud repair clampsSRB225, SRB255, SRB285, andSRB315. No indications noted.

Four of 12 Shroud repair bracketsSRB105, SRB135, SRB 165, andSRB 195. No indications noted.

HI Upper - DeferredHI Lower 61.2% examinedH4 Upper 94.2% examinedH4 Lower 89.7% examinedH6a Upper 75% examinedH6a Lower 67.1% examinedH7 Upper & Lower DeferredNo significant growth of existing cracksor new cracking noted.

H I upper - 95% examined - 2% flawedH5 - 100% examined - 0% flawedH6b - 99% examined - 59% flawed -average flaw depth is 0.12"H7 - 83% examined - 3% flawedNo growth noted.

4 of the 12 Core Shroud repair clamps forH2&H3. No indications.V9, VI0, VII - one side only. ID isinaccessible. No indications.

4 of the 12 Core Shroud repair clamps forH2&H3. NRI(VI,V2)-OD,(V3,V4, & V6)-OD & IDI RI on V2, 5 Rl's on V6 all < 10%

4 of the 12 Core Shroud repair clamps forH2&H3. NRI

Shroud Support 1994 EVT-1 VT-I of access cover welds inspected -

no indications noted.

1996 UT H9 inspected with no indication noted.

23

Page 25: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

1991 and1994

1999

2001

2003

2005

2007

2009

2011

UT

N/A

N/A

EVT-1

UT

EVT-I

N/A

EVT-1

Access hole covers UT's for radial andcircumferential indications with noindications noted.

No inspections performed.

No inspections performed.

EVT-1 of both access hole covers. Noindications noted. H8 @ 0 & 180 (18%)NRI.

H9 - 60% examined, One relevantindication noted.

H8 & H9 at 0 & 180 degAccess Hole Covers at 0 and 180 degNo indications noted.

No inspections performed this outage.

H8 & H9 at 0 & 180 degAccess Hole Covers at 0 and 180 degNRI.

Core Spray Piping 1980's toPresent

1999

2001

2003

MVT-1and EVT- I

IEB 80-13 of piping and welds inannulus. One indication on annulusheader piping at the header to T-Boxweld. Welded brackets installed1991 with full structural marginsmaintained. First inspected perBWRVIP-18 in Fall 1996 with no newindications found. Re-inspected perBWRVIP-18 in Fall 1997 with no newindications found.

Performed inspections of selected corespray annulus piping welds in accordancewith BWRVIP-18 with no newindications noted.

Performed inspections of selected corespray annulus piping welds in accordancewith BWRVIP-1 8 with no newindications noted.

EVT-1 inspection of all P1, P2, P3, P5,

EVT- 1

EVT-1

EVT- I

24

Page 26: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2005

2007

2009

2011

EVT-1

EVT- 1

EVT-1

EVT-1

P6, P7, P8a and P8b welds, 25% of P4welds, 25% of piping bracket welds, and100% of existing repairs. No indicationsnoted.

Inspection of all P1, P2, P5, P6, P7, P11,P12, P8a and P8b welds and P3 @ 270degrees, 25% of P4 welds, 25% ofpiping bracket welds, and 100% ofexisting repairs. No indications noted.

Inspection of all PI, P2, P5, P6, P7, P11,P12, P8a and P8b welds and P3 @ 270degrees, 25% of P4 welds, 25% ofpiping bracket welds, and 100% ofexisting repairs. No indications noted.

Inspection of all P1, P2, P5, P6, P7, P1 1,P12, P8a, P8b, P3's@270. 25% of P4welds, 25% of piping bracket welds.Repair bracket welds on 90 deg T Boxfound flaws near the end of the T-Box.May come from creviced weld P2. UTnot possible.

Inspection of all P1, P2, P5, P6, P7, P1 1,P12, P8a, P8b, P3's@0a270, 25% of P4welds, 25% of piping bracket welds (PB-150). NRI. 90 deg Repair bracket T-Boxflaws showed no growth.

Core Spray Sparger 1980's toPresent

1999

MVT-1,EVT- l, andVT-3

PerBWRVIP-18

IEB 80-13 of welds on sparger. Oneindication in sparger to tee weld. Boltedclamp installed in 1982 and full structuralmargin maintained. One small indicationnoted in and near the heat affected zoneof Core Spray sparger support bracket toshroud plate weld. Structural integrity ofthe support maintained. First inspectedper BWRVIP-18 in Fall 1996 with nonew indications found. Re-inspected per.BWRVIP-18 in Fall 1997 with no newindications found.

Inspected spargers per BWRVIP-1 8 withno new indications noted and no changein previously identified indications.

25

Page 27: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2001 Per Inspected spargers per BWRVIP- 18 withBWRVIP- no new indications noted.18

2003 EVT-1/ Inspected 7 Core Spray Sparger bracketsVT-I and 25% of the sparger welds. No

indications noted.

2005 EVT-1/ Inspected 25% of the Sparger welds andVT-I 5 sparger brackets. Tee Repair bracket

also inspected. No indications noted.

2007 EVT-1/ Inspected 25% of the Sparger welds andVT- 1 5 sparger brackets. Tee Repair bracket

also inspected. No indications noted.

2009 EVT-I/ Inspected all SI, 25% of S2, S4, S3, andVT-I SD welds and 5 sparger brackets. No

indications noted.

2011 EVT-1/ Inspected all SI welds, 25% of S2, S3,VT-I S4, and SD welds and 5 sparger brackets.

NRI.

Top Guide (Rim, 1991-96 MVT-1, Examined 2 cells in 1992 with noetc.) VT-3 indications noted. 15 cells examined in

1995 with no indications noted. Did VT-3 of top guide hold downs examined in1996 with no indications noted.

1999 N/A No inspections performed.

2001 N/A Inspected 50% of the top guide holddown latches with no discrepanciesnoted.

2003 VT-I Inspected 50% of the top guide holddown latches. No indications noted.

2005 VT-I No Top Guide grid beams were inspectedthis outage.

2007 VT-I Two hold-down latchesEVT-1 Two Grid Beam Intersections in

conjunction with Dry Tubes (SIL-409)

26

Page 28: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

No indications noted

2009 EVT-l/ 2 hold-down latchesVT-I 3 cells - grid beams lower 2" &

intersection. No Indications noted.

2011 n/a No top guide inspections were performedthis outage. Will expand scope nextoutage to meet criteria.

Core Plate (Rim, 1993 VT- I Hold down bolts from topside and partialetc.) surface areas. No indications noted.

1999 UT UT from shroud outside surface to detectbolting presence. Detected presence of56 bolts out of a minimum needed of 54with no discrepancies noted.

2001 UT UT from shroud outside surface to detectbolting presence. Detected presence ofall 72 bolts with no discrepancies noted.

2003 N/A No inspections performed on Core Plate.

2005 N/A No inspection performed on Core Platebolts this outage.

2007 UT UT from shroud outside surface to detectbolting presence. Detected presence ofall 72 bolts with no discrepancies noted.

2009 N/A No inspections performed this outage.

2011 N/A No inspections performed this outage.

SLC 1988 LP No exams performed on internal piping.Section XI LP performed on nozzle tosafe end welds in 1988 with noindications noted.

2001 N/A No inspections performed.

2003 VT-2 Enhanced leakage examinationperformed on nozzle-to-safe end weld.No leakage noted.

2005 VT-2 Enhanced leakage examination

27

Page 29: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2007

2009

2011

VT-2

VT-2

VT-2

performed on nozzle-to-safe end weld.No leakage noted.

Enhanced leakage examinationperformed on nozzle-to-safe end weld.No leakage noted.

Enhanced leakage examinationperformed on nozzle-to-safe end weld.No leakage noted.

Enhanced leakage examinationperformed on nozzle-to-safe end weld.No leakage noted.

Jet Pump Assembly to present

1997

1999

2001

2003

VT- I andVT-3

VT- I andVT-3

EVT-I/MVT-l/VT- I /VT-3

EVTI/VT-I

EVT-1

Riser brace brackets done once perperiod. Wedges, set screws, tack welds,sensing lines and sensing line supportsVT per various SILs. Latest inspected in1996 with no indications noted. Jetpump beams replaced in 1993. Noindications noted, as well as in old jetpump beams.

MVT-1 of Riser welds and tailpipe weldson 5 Jet Pump Pairs with no indicationsnoted.

Performed inspections on 30 Riser welds,and 50% of the miscellaneous riser brace,inlet mixer, etc. welds. No indicationsnoted.

Performed inspections on representativesamples of riser pipe to restrainer bracketcirc. welds (RS-6, RS-7), riser pipe toprimary riser brace circ. welds (RS-8,RS-9), barrel to adapter welds (MX-2),wedge bearing surfaces (WD-1),connections between inlet and mixersections (IN-4), primary riser brace leafto vessel pad welds (RB-1), and primarybrace leaf to yoke welds (RB-2). Norecordable indications noted.

EVT-I of accessible areas of all 20 jetpump beams. No indications noted.

28

Page 30: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2005 UT Examined 100% of BB-1, BB2, & BB-3Type 2 Beams (20). No indicationsnoted.

VT-I Examined 10 WD-I locations. Noindications noted.

EVT-I Examined 4 IN-4 welds, 4 MX-2 welds,I Riser Brace, 2 RS-1, 2 RS-Ia, 2 RS-2,2 RS-3, and I RS-6, I RS-7, 1 RS-8, IRS-9: No indications noted.

2007 UT Examined 100% of BB-1, BB2, & BB-3Type 2 Beams (20). No indicationsnoted.

VT-I Examined 20 WD-I locations. Noindications noted.

EVT-1 Examined 4 IN-4 welds, 4 MX-2 welds,I Riser Brace, 4 RS-I, 4 RS-la, 2 RS-2,2 RS-3, and I RS-6, I RS-7, I RS-8, 1RS-9: No indications noted.

2009 EVT-1 2 IN-4, 2 MX-2, 2 WD-1, All RS-I,la,RS-8 & RS-9 welds. JPC Riser Brace &JPK RB-la-d welds. 3 Flaws found inHAZ of JPC RS-I weld, elbow side.Analysis good for two cycles. No otherindications noted.

2011 EVT-1 2 IN-4, 2 MX-2, 2 WD-1, 4 RS-1, 1 RS-la, I RS-8&9 welds, 3 Flaws re-identified in HAZ of JPC RS-I weld,elbow side. Analysis good for two cycles.No growth in indications noted. 2 RS-2,2 RS-3, I RS-6&7, 23 Riser Brace weldsNRI.

Jet Pump Diffuser to present VT-3 Adapter and diffuser welds inspectedonce per period with no indicationsnoted.

1999 EVT-I Inspected 50% of welds with noindications noted.

29

Page 31: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2001 N/A No inspections performed.2001 N/A No inspections performed.

2003 EVT-1 EVT'-I of AD-1, AD-2, and AD-4 weldson 10 jet pumps. No indications noted.

2005 EVT-1 6 DF welds, 8 AD welds, no indicationsnoted.

2007 EVT-1 4 AD- I, 4 AD-2, 2 DF- 1, 4 DF-2No relevant indications noted.

VT-I Jet Pump sensing lines. No RelevantIndications noted.

2009 EVT-I 2 DF-2, 1 DF-I, 2 AD-1, 2 AD-2, Norelevant indications noted.

2011 EVT-1 4 DF-2, 2 DF-1, 4 AD-1, 4 AD-2, NoNRI.

CRD Guide Tube VT-3 Access has not become available.

2001 EVT-1/ Performed inspections on 5% of CRDVT-3 guide tube sleeve-to-alignment lug welds

(CRGT-1), CRD guide tube body-to-sleeve welds (CRGT-2) and guide tubeand fuel support alignment pin-to-coreplate weld and pin (FS/GT-ARPIN-1).No recordable indications noted.

2003 EVT-1 EVT-I of CRGT-3 welds on 7 guidetubes. No indications noted.

2005 N/A No inspections this outage.

2007 VT-3 I alignment guide pinEVT-1 2 CRGT-1, 2 CRGT-2, I CRGT-3

NRI

2009 EVT-I/ 7 (Pins, CRGT-1, CRGT-2 & CRGT-3)VT-I NRI. Two of these performed from OD.

2011 N/A No guide tube inspections this outage.Baseline is complete.

CRD Stub Tube N/A N/A N/A

2007 VT-3 7 Stub Tube-to-vessel welds (30%)

30

Page 32: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

7 Stub Tube-to-CRD housing weldsNRI

2009 VT-3 8 stub tube to vessel welds8 stub tube to CRD housing welds2 CRD housing welds NRI

2011 VT-3 No bottom head inspections this outage

In-Core Housing N/A N/A N/A

2007 VT-3 2 ICH/RPV welds (30%)NRI

2009 VT-3 4 inst. Tubes to vessel welds. NRI

2011 N/A None

Dry Tube N/A Replaced in 1987. Scheduled forinspection in 2001.

2001 N/A BWRVIP does not require inspection ofdry tubes.

2003 N/A No inspections performed on dry tubes.

2005 N/A No inspections performed this outage.

2007 VT-1 2 Dry Tubes - upper two feet, NRI perGE SIL. No indications noted.

2009 VT-I 3 dry tubes - upper two feet from 2adjacent cells. No indications noted.

2011 VT-1/VT-3 No Dry Tube Inspections this outage

Instrument N/A N/A Examinations of instrument penetrationsPenetrations are performed in accordance with ASME

Section XI requirements.

Vessel ID Brackets to present VT-I in Section XI inspections of dryer,beitline feedwater sparger, core spray, andarea and surveillance capsule holder bracketsVT-3 in performed once per interval. Lastother areas inspections in 1997 with no indications

noted.

1999 VT-I/VT-3 Inspected Feedwater and Core Spray

31

Page 33: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2001

2005

2007

2009

2011

EVT1/VT-I/VT-3

EVT- 1/VT-3

EVT-I/VT-I

EVT- I/VT-I

EVT-l/VT-I

EVT-1/VT-I

attachment welds to RPV with noindications noted.

Inspected various jet pump riser bracearm pad to RPV welds, feedwater spargerend bracket to RPV welds, core spraybracket to RPV welds. No recordableindications noted

EVT-1/VT-3 of 2 core spray headerpiping brackets and 4 dryer supportbrackets. VT-3 of 2 guide rod bracketsand 4 steam dryer hold-down brackets.No indications noted.

2 Core Spray Brackets, 8 FeedwaterBrackets, 4 JP Riser Brace welds.No indications noted.

I Core Spray Bracket, 8 FeedwaterBrackets, 4 JP Riser Brace welds. 8Steam Dryer hold-down & supportBrackets, 6 Surveillance specimenbrackets. No indications noted

I Core Spray Piping Bracket, 2 jet pumpriser braces. No relevant indications.

I Core Spray Piping Bracket, 20 jetpump riser brace welds. Surveillancespecimen brackets at 30 deg. NRI

LPCI Coupling N/A Not applicable to Brunswick.

Feedwater Spargers 2003 EVT-I/VT- EVT-I of sparger tee welds, VT-I/VT-3I/VT-3 of sparger end bracket assemblies, VT-3

of sparger flow holes. EVT-I of selectedflow hole on each sparger. No changesin previously identified indications.

2005 EVT-I/VT- EVT-I of sparger tee welds, VT-I/VT-3I/VT-3 of sparger end bracket assemblies, VT-3

of sparger flow holes. EVT-I of selectedflow hole on each sparger. No changesin previously identified indications.

32

Page 34: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2007

2009

2011

EVT-1/VT-I

EVT-1/VT-1

EVT- 1/VT-1/VT-3

Same as above.

Same as above. No significant growthnoted.

VT-3 of spargers & end brackets. EVT-1of one hole on each sparger.Loose part found in "C" Sparger. Someminor hole damage to 4 holes, One areaof wear caused by loose part. Evaluatedas acceptable by GEH. No other RI's.

I -~

Steam Dryer 2003

2005

2007

2009

2011

VT- 1/VT-3

VT-I

VT-I

VT-I

VT-I

VT-I of circular plate welds (this is theplate that failed at Quad Cities), VT-i ofdrain channel welds and manhole cover,VT-3 of entire dryer assembly. Noindications noted.

Baseline of all steam dryer externalwelds. Two indications noted. BothIGSCC type cracking and both repaired.

95 welds inspected, (red & green areas asdenoted in BWRVIP-139) No indicationsnoted.

20% of assorted steam dryer weldsinspected. Flaws identified on I of 2 tackwelds of two lifting eyes to threaded rodconnections.

29 components (20%) inspected. Onearea on cover plate to upper support ringminor flaws (2). New flaw on skirt neardrain channel, limited to -3" max length.No significant flaws detected.

Dissimilar Welds 2009 Manual 3 Cat A - No FlawsIAW BWRVIP-75-A (2B1 IN2B-RPV-FWABA, 2BI IN2C-RPV-FWABA,

2B1 IN2D-RPV-FWABA)

2011 Phased Component IGSCC Cat

Array 2BI IN8A-RPV-SWAB C

Manual2E21FF-4-FWRN5A D

2E21 FF-8-FWRN6A D

2G3114-1-14-FW1949A D

33

Page 35: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2B32RECIRC-28-A- I E

2B32RECIRC-28-B-I E

2BI I N9-RPV-FW2CRD52 D

NRI

34

Page 36: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Reactor Internals Inspection History

Plant: Columbia Generatin2 Station

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Inspection Results, Repairs,

Inspection Used Replacements, Reinspections

Core Shroud 1994 UT 35% weld H3, 10% of weld H4. Noindication of cracking. Proactiveexamination as a category A plant.

1998 UT Baseline examination of all accessibleareas of welds H3, H4, H5 and H7. perBWRVIP-01. No cracking found.

2007 UT Examination of accessible portions ofH3, H4(upper), H6A and H7 perBWRVIP-76.H3 2.7% flawsH4 6.2% flawsH6A 0% flawsH7 0% flaws

Shroud Support 1994 VT-I- ASME Section XI includes access holecovers. No indications

2003 VT-I, VT-3 No indications

2005 UT H9 NRI (BWRVIP-38)EVT-1 H8 NRI (BWRVIP-38)

2007 EVT-l Access hole covers NRI (BWRVIP-1 80)

2011 EVT-1 H8 Top side NRI

Core Spray Piping 1985 to 1997 VT-I No indications of cracking. One milIEB 80-13 wire resolution

1998 MVT-I No indications of crackingIEB 80-13

1999 VT-I No indications of cracking. One milIEB-80-13 wire resolution

2001 EVT-I No indications of cracking

35

Page 37: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2003 EVT- I No indications of cracking(BWRVIP-18)

2005 EVT-I NRI

2007 EVT-1 NRI

2009 EVT-I NRI

2011 EVT-1 NRI

Core Spray Sparger 1985 to 1997

1998

1999

2001

2003

2005

2007

2009

2011

VT-IIEB 80-13

MVT-1IEB 80-13

VT-IIEB 80-13

VT-I

EVT-IVT-I

EVT-IVT-I

EVT-IVT-I

EVT-IVT-I

EVT-IVT-I

No indications of cracking. One milwire resolution

No indications of cracking

No indications of cracking. One milwire resolution

No indications of cracking

No indications of cracking18)

(BWRVIP-

No indications of cracking

No indications of cracking

No indications of cracking

IGSCC found around 9 of twelvesparger bracket azimuths. Indicationswere found around middle and lowerbrackets on the shroud side HAZ. Noindications were found around topbrackets.

Top Guide (Rim, 1994 VT-I, ASME Section XI. No indications

etc.) VT-3 Inspected 48 cells NRI

2005 VT-3 Top Guide C-Clamp NRI

2009 EVT-I Top Guide Beams NRI (BWRVIP-1 83)

36

Page 38: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Core Plate (Rim, etc.) NA NA NA

SLC NA NA SLC routed through HPCS system

2007 VT-2 Not required by BWRVIP-27. VT-2exam during hydro test. No recordableindications.

2009 VT-2 NRI

2011 VT-2 NRI

Jet Pump Assembly 1985-1997

1998

1999

2001

2003

2005

VT-I, VT-3,UT

VT-I

VT-I

EVT-I

EVT-I

EVT- I

JP Beams replaced 1994. No indicationsfound on old beams. Adjusting screws,wedges, sensing lines and clamps doneto various GE SILS. Found one sensingline cracked at support. Acceptable forservice. Found several adjusting screwswith gaps between screw and inletmixer. Reduced gaps by resetting JP andinstalling wedges. Found one adjustingscrew tack weld cracked on two JP.Acceptable for continued service.

Found one adjusting screw with gapsbetween screw and inlet mixer.Acceptable for continued service.

Found three adjusting screws with smallgaps between screw and inlet mixer.Acceptable for continued service.

BWRVIP-41 inspections. Found fivepumps with small gaps between screwand inlet mixer. 2 wedges had wear. Noindications on welds. RB-1, RB-2, RS-8, RS-9, RS-3 (JP 1-10)

Found 12 pumps with small gapsbetween screw and inlet mixer. Nochange noticed on wedge wear. Noindications on welds.

Found 7 pumps with gaps between setscrew and inlet mixer. Significantchange in wear on one wedge. Nochange noticed on 3 wedges wear. Slight

37

Page 39: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2007

2009

2011

EVT-I

EVT-1, UT

VT- 1, EVT-I

wear on 4 wedge rods. Installed slipjoint clamps on all jet pumps.

Found 2 pumps with gaps between setscrew and inlet mixer. Notable changein wear on one wedge. No change notedon 4 wedges. Minor wear noted on 9wedge rods. No change noted on 4wedge rods.

Inspected 100% wedges - evidence ofwedge "dropping" minor wear. Some setscrew gaps all within allowable. UT onbeams NRI, 50% Slip joint clamps NRI,JPSL exit line A loop NRI. Misc mixer,diffuser and adapter welds all NRI.

Inspected 100% wedges - evidence ofwedge "dropping" minor wear. Some setscrew gaps all within allowable. JPSLexit line B loop NRI. Misc mixer,diffuser and adapter welds all NRI.Recordable indication found on the JP17/18 RS-9 weld. Wear found on JP 5beam bolt from loose retainer plate.

CRD Guide Tube 2003 VT-3, EVT- VT-3 of pin and lug EVT-I of CRGT-2,1 3. 10 tubes examined No indications

2011 VT-3, EVT- Completed BWRVIP-47 scope. NineI tubes examined NRI

CRD Stub Tube NA NA NA

In-Core I-lousing 1985-1997 VT-2 ASME Section XI. No indications

1998 VT-2 ASME Section Xl. No indications

Dry Tube 1987-1997 VT- I Various degrees of erosion. Evaluatedacceptable

1998 VT- I No unacceptable indications noted

2001 VT- I No unacceptable indications noted

2005 VT-I No unacceptable indications noted

2009 VT-I NRI Two not fully seated

38

Page 40: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Instrument 1994 VT-2 ASME Section XL. No indicationsPenetrations

2005 VT-2 ASME Section XI. No indications

Vessel ID Brackets 1994 VT-I ASME Section XI. No indications

2001 EVT- 1 FW brackets. NRI (BWRVIP-48)

2003 EVT-I Jet Pump & Core Spray NRI

2005 EVT-1, Jet Pump, FW, Core Spray, SampleVT- 1, VT-3 Holder and Steam Dryer Support Lugs.

Existing wear from moving dryershowed no change from earlier outages.Surv. sample holder NRI

2011 EVT-I Jet Pump and Core Spray Attachmentwelds NRI

LPCI Coupling 1994 VT-I ASME Section XI. No indications

2003 EVT-1 Inspected NRI (BWRVIP-42)

2009 EVT- 1, VT- NRI1

2011 EVT-1, VT- NRII

Steam Dryer 2005 EVT- 1, VT- One tie bar to hood weld found 2 fatigueI cracks. Stop drilled.

IGSCC cracks found in base materialnear welds of 3 vertical hood welds.Damage associated with installing dryerfound on 0 degree lower guide bracket.

2007 EVT-1, VT- Tie bars inspected NRI. No additionalcrack propagation from prior stop drillrepair.

Additional IGSCC cracks found in basematerial near vertical hood weld.Similar to 2005 findings. Visible in '05video review but not recorded.

2009 VT-I No change in previous indications

39

Page 41: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2011 VT-I No change in previous indications

Steam Separator 2009 VT-I, VT-3 100% Exhaust pipes and top tie bars twominor dents, 25% gusset and rings NRI.36 Shroud Head Bolts some pin wear.

2011 VT-1, VT-3 Examined 25% gusset, rings and domewith NRI. Shroud Head Bolt pin andwindow wear from last outage re-examined with no change in wear.

DM Safe End Welds 2009 UT BWRVIP-75-A automated UT, sixCategory C DM welds inspected. Allcontain Alloy 82/182. One requiredsurface conditioning. No recordableindications.

2011 UT BWRVIP-75-A automated UT.Examined four Category C DM weldscontaining Alloy 82/182. No surfaceconditioning required. Three with norecordable indications, one with areflector evaluated as acceptable perASME Section XI.

40

Page 42: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Reactor Internals Inspection History

Plant: Cooper Nuclear Station

Component in Date of Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Inspection Results, Repairs,

Inspection Used Replacements, Re-inspections

Core Shroud Fall 1995(RE 15)

UT

Spring 2005(RE22)

UT

Baseline UT performed on welds HIthrough H7 per BWRVIP guidelines.Indications identified in 4circumferential welds. No examinationson vertical welds. No repair required.

UT examinations were performed onwelds H-I through H-4 including aportion of vertical weld V16.Examination of welds H5-H7 wasdeferred to fall 2006. Single sided UTexaminations were performed on weldsH-I through H-3 with welds H-4 andvertical weld (V-16) receiving dual sidedexaminations. Percentage of weldsexamined: HI (54.9%), H2 (55.7%), H3(63.9%), H4 (58.4%). The previouslyidentified eight (8) flaws in HI showed anet decrease in length. No new flaws inH2 were identified. The eight (8) flawsin H3 were reexamined with one (1) newflaw identified for a total increasedchange in flaw length relative to totalweld length of 7.5 %. Two (2) newminor flaws were discovered in the HAZof H4. In addition, a total of eleven (11)minor indications were identified in thebase metal adjacent to H4. Six (6) of theindications exhibited characteristicsassociated with Stress CorrosionCracking (SCC) in areas subjected tocold working during the shroudfabrication/installation process. Theremaining five (5) indications did notexhibit characteristics of SCC butappeared to exhibit characteristicscommonly observed from localized

41

Page 43: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

attachment removal sites. Theindications were determined to beacceptable by analysis. No indicationswere observed in the vertical weld.

Fall 2006 UT UT examinations were performed on(RE23) welds H5, H6a, H6b, and H7 using

phased array. Two (2) sidedexaminations were performed on allwelds except H7 that received a one-sided UT examination. Coverage wasestimated at greater than 72% for weldsH5, H6a, and 1H6b. H7 received greaterthan 53% coverage. A previouslyidentified indication in H5 was re-examined with no apparent change. Apreviously identified indication in H6awas re-examined with no apparentchange. A new minor indication wasdiscovered in weld H6b in an areapreviously scanned in RE16 (1995). Two(2) new minor indications werediscovered in weld H7, one in apreviously scanned location and theother in an area not previously scanned.

VT-3 VT-3 examination of shroud per ASMESection XI, B-N-2 requirements.Discovered an indication approximatelyten (10) inches long behind JP-19.Analyzed as acceptable.

Spring 2008 VT-3 Performed first ASME B-N-2 VT-3(RE24) successive examination of flaw

discovered in base metal behind JP-19.No changes in the indication.

Spring 2011 VT-3 Performed second ASME B-N-2 VT-3(RE26) successive examination of flaw

discovered in base metal behind JP-19.No changes in the indication.

Shroud Support/ 1993-1995 VT-I and VT-i examinations of welds on 50% ofAccess Hole Covers UT core plate each outage. No indications.

UT of access hole covers (AHC) in1993. No indications.

42

Page 44: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Spring 1997(RE17)

Fall 1998(RE18)

Spring 2000(RE 19)

Fall 2001(RE20)

Spring 2003(RE21)

Spring 2005(RE22)

Fall 2006(RE23)

Spring 2008(RE24)

VT-3

VT-I

VT-3

VT-I

VT-3

VT-I

EVT-l

UT

EVT-1

UT

EVT-1

EVT- I

VT-3 examinations on 50% of the coreshroud support plate. No indications.

VT-I examinations of AHC inaccordance with GE SIL 462. Noindications.

VT-3 examinations on 50% of the coreshroud support plate. No indications.

VT-I of AHC's in accordance with GESIL 462. No indications. VT-I of gussetplate welds between 0-180' to B-N-2.

VT-3 examinations on 50% of the coreshroud support plate. No indications.

VT- I examinations of AHC's inaccordance with GE SIL 462. Noindications.

EVT-1 examinations on 17% of the H8and H9 welds. EVT-1 examinations on6 gusset welds and AHC's. Noindications.

UT examination of AHC's. Noindications.

EVT-I examinations on four (4) gussetwelds. No indications.

UT examinations on greater than 10% ofthe H9 weld length. No indications

EVT-I examinations performed onapproximately 16% of H8 weld lengthwith no relevant indications. EVT-1examinations of AHC per SIL462. Noindications.

EVT-I examinations performed onaccessible lengths of welds on seven (7)gussets. No indications.

Core Spray Piping 1980's to VT-I/VT-3 IEB 80-13 examinations of piping and1995 welds in annulus. Three (3) indications

43

Page 45: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Spring 1997(RE 17)

Fall 1998(RE18)

Spring 2000(RE 19)

Fall200 1(RE20)

Spring 2003(RE2 1)

Spring 2005(RE22)

UT

EVT-I

UT

EVT-I

UT

EVT-I

UT

EVT-I

UT

EVT-I

EVT-I

identified in Fall 1995 outage by EVT-I.No repair required.

UT examination of CS P8a and P8bwelds. Indications on one P8a and P8bwelds (first discovery). Evaluated asacceptable.

EVT-I examinations on balance ofpiping.

UT examinations on the P8a and P8bindications were re-examined.

Balance examined by EVT-i. No visualindications.

UT examinations on P8a and P8b weldswith indications. No repair required.

EVT-I of P3, P4, P5, P6, and P7 welds.No visual indications.

UT examinations on P3's, three (3) P4's,P5's, P6's, P7's, P8a's and P8b's. EVTexaminations of thirty-one of the CSpiping welds.

EVT- I examinations on fifteen (15)welds. Indications re-examined on P8aweld and P8b welds.

UT examinations on all P8a and P8bwelds. Identified three (3) flawindications on one P8b weld and one (1)flaw indication on one P8a weld. Nochange in length.

EVT-1 examinations on both junctionbox covers and accessible portions ofboth P1's, 2 - P2's, 4- P3's, 1-P4a, I-P4b, I-P4c, I-P4d. EVT-1 all P8a andP8b welds. No indications.

EVT-I examinations of both P1's . Theexamination revealed that the P1 weld is

44

Page 46: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

not a creviced weld based on thepresence of an external weld on the teebox near the nozzle thermal sleeve.EVT-1 examinations were performed onboth P2 welds, the four (4) P3 welds, the4a - 4d welds at 1900 , the P5's, P6's,and P7's, the four (4) P8a's, and four(4) P8b's.

UT examinations of P8b welds. Previousindications showed no change in size.

Fall 2006(RE23)

Spring 2008(RE24)

Fall 2009(RE25)

Spring 2011(RE26)

UT

EVT-1

EVT-1

EVT- I

UT

EVT- I

EVT-1 examinations of piping welds andbracket attachment welds. No newrelevant indications observed.

EVT-I of indication near P1 at 90'. Nochange. EVT-1 of P1 at 270'. EVT-I ofP2's and P3's at 90' and 2700. EVT-I ofP4a, -b, -c, and -d at 1700EVT-I of P5's, P6's, and P7's at 10',1700, 1900, and 3500.

EVT-i examinations near PIwelds at 90'and 270'. No change with the indicationnear the P 1 at 900 (Loop A). EVT-lexaminations of the four (4) P3, P5, P6and P7 welds, EVT-I examinations ofdowncomer welds P4a, P4b, P4c, andP4d at 10' . EVT-I examninations offour (4) P8a and P8b welds. No changewith visual indication of P8b at 100.

UT performed on all four (4) P8a andP8b welds. Previously identifiedindications on the P8a at 190' (Loop B)and the P8b at 100 (Loop A) did notshow any change.

EVT-I of area and indication adjacent toPIweld at 900 (Loop A). No change tothe indication.

EVT-I of area adjacent to Plweld at2700. No indications.

45

Page 47: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

EVT-1 of the P2 welds at 900 and 2700.EVT-1 of the four (4) P3, P5, P6, and P7welds. EVT-I of downcomer welds P4a,P4b, P4c, and P4d at 190'. Noindications.

I- I- +

Core Spray Sparger 1980's to1995

Spring 1997(RE 17)

Fall 1998(RE 18)

Spring 2000(RE 19)

Fall 2001(RE20)

Spring 2003(RE21)

Spring 2005(RE22)Fall 2006(RE23)

Spring 2008

VT-I/UT

EVT-I

EVT- l

EVT- I

VT-I

EVT-I

VT-I

EVT-1

N/A

VT-I

EVT-I

VT- I

IEB 80-13 of welds on sparger. Noindications.

EVT- I examinations of sparger weldsand brackets per BWRVIP-18. Debris(wire) in C-sparger Nozzle 15Cidentified. No other indications.

EVT- 1 examinations of sparger weldsand brackets inspected in accordancewith BWRVIP-18. Debris (wire) in C-sparger Nozzle 15C was reconfirmed.No other indications.

EVT-I examinations of sparger andbrackets. Five (5) indications evaluatedas acceptable.

VT-I of 25% of S3a, S3b, and $3cwelds. No indications.

EVT-I examninations of all S 1, S2, andS4 welds examined with no indications.

VT-I of 25% of S3a & S3b's and allbracket welds. No indications.

EVT-I examinations of two S l,s, twoS2,s, both XTRW welds near t-boxes,and four (4) S4 welds. No indications.

Sparger examinations deferred to fall2006 (RE23).VT-I on 50% of the S3a, S3b, and $3cwelds and 100% on sparger brackets.No indications.

EVT-I on 100% of Sl's and S2's andS4's. No indications.

VT-I on 25% of the S3a, S3b, and $3c

46

Page 48: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

(RE24)

Fall 2009(RE25)

Spring 2011(RE26)

EVT-I

VT-I

EVT-1

VT-I

EVT-I

welds. VT-I of SB's at 900, 920, 1190,1490, 2100, 2410 and 2680.

EVT-I examinations of SI's and S2's at1700 and 1900. EVT-1 examinations ofS3a, S3b at 920 to 2690. EVT-Iexaminations of S3c at 99'. EVT-Iexaminations of S4's at 910 and 2690.

VT-I on 25% of the S3a, S3b, and S3cwelds. VT-I of SB's at 2720, 2990, 300,3290, 610, 880 and 2700.

EVT-I examinations of SI and S2 and at100 and 3500. EVT-1 examinations oftwo (2) additional welds near the 3500tee-box S2 welds.

VT-I on 25% of the S3a, S3b, and S3cwelds. VT-I of sparger brackets at 900,920, 1190, 149.50, 210.50, 2410 and2680. No indications.

EVT-I on C Sparger, SI @ 1700, S2 @168-&1720,$4@91'&269'. Noindications.

EVT-I on D Sparger, SI @ 1900, S2 @188- & 192-, $4@ 91' & 269'. Noindications.

Top Guide (Rim, etc.) 1991-1995

Spring 1997(RE 17)

VT

VT -1

VT of top guide beams of fifty (50) cellswas performed in 1991 per RICSIL 059.No indications. VT exams of themembers in the load path between thetop guide and core shroud in 1995 perSIL 588. One (1) indication on the 900aligner pin keeper was observed andevaluated as acceptable (indication noton load bearing portion of assembly).

VT- I re-examination of Top GuideAligner Pin located at 900 in accordancewith SIL 588, Ri. Indication on alignerpin keeper did not appear to change insize.

47

Page 49: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Spring 2000 VT -1 VT-I of two (2) hold down assemblies.(RE 19) No indications.

Fall 2001 VT -1 VT-I of two (2) horizontal aligner pins(RE20) with no new indications. VT-I of four

(4) hold down assemblies.

EVT- I EVT-I examinations of accessible areasof the Rim weld.

Fall 2006 VT-I VT-I on two (2) hold down assemblies(RE23) and aligner pin assemblies at 900 and

270'. A previous indication identified onthe non-load bearing keeper of thealigner pin assembly at the 900 locationwas observed with no apparent change.However, two (2) new but similar typeindications were also observed on thesame keeper. Three (3) new indicationswere observed on the non-load bearingaligner pin keeper at the 2700 location.Indications were evaluated as acceptable.

VT-3 VT-3 examinations performed onaccessible areas of top guide per B-N-2.No indications.

Spring 2008 VT-I VT-I examinations performed on hold(RE24) down and aligner assemblies at 0 and

180'. One (1) new indication identifiedon non-structural keeper at 1800. Similarto indications in keepers seen at 90' and2700. Evaluated as acceptable.

EVT- I EVT-i examinations of accessible areasof Rim weld.

VT-3 VT-3 examinations performed ofaccessible top guide hold downassemblies, rim pins per B-N-2.

Fall 2009 VT-I VT-I examinations performed on hold(RE25) down and aligner assemblies at 900. No

change in the indication at the 900aligner pin keeper.

48

Page 50: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

EVT-1 EVT-I examinations of 10% or fourteen(14) of top guide grid beams perBWRVIP-183. No indications.However, only eight (8) were credited asquality examinations.

VT-3 VT-3 examinations of accessible areas oftop guide per B-N-2.

Spring 2011 VT-3 VT-3 of accessible areas of Top Guide(RE26) per B-N-2. No indications.

VT-I VT-I for BWRVIP-26 credit wasperformed on the Hold Down assembliesand Aligner Pin assemblies at 2700. Anindication not previously reported wasobserved adjacent to the attachment weldadjoining the Aligner Block to the TopGuide. Indication appears to be amanufacturing remnant that was notcompletely removed during construction.Previously identified indications werealso observed with no changes.

Scope was expanded to include theremaining other three (3) Aligner Pinassemblies located at 00, 900, and 1800.VT-3 for Sect. XI B-N-2 and VT-I forBWRVIP-26 credit was performed.Aligner Pin assembly at 00 was found tohave seven (7) previously unidentifiedindications, with four (4) identified in theAligner Pin Keeper and three (3)identified in the Aligner Block. Reviewof previous inspection video showedfaint presence of indications. Evaluatedas acceptable.

Aligner Pin assembly at 900 was foundto have one (1) previously unidentifiedindication located on the Aligner PinKeeper. Review of previous inspectionvideo showed a faint presence of theindication. Three (3) previouslyidentified indications were also observedwith no changes. Evaluated as

49

Page 51: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

acceptable.

Aligner Pin assembly at 1800 was foundto have two (2) previously unidentifiedindications located on the Aligner PinKeeper. Review of previous inspectionvideo shows presents of indications.Three (3) previously identifiedindications were also observed with nochanges. Evaluated as acceptable.

EVT-1 examinations of accessible areasof the Rim weld.

EVT-1 of two (2) top guide cell locationsper BWRVIP-183. No indications.

EVT-1

-I I I

Core Plate (Rim, etc.) Fall 1995

Spring 2000(RE 19)

Fall 2001 toFall 2009(RE20 -RE26)

VT-3

VT -3*

VT-3

VT-3 examinations of Hold down boltsexamined in 1995 per SIL 588. Noindications.

VT-3 examninations of 48 bolts examinedfrom top side.*(Bolts are not accessible for EVT-1)

VT-3 examinations performed onaccessible areas per B-N-2. Noindications.

A I I

SLC 1986-2001

Spring 2003(RE23)

Spring 2005(RE22)

Fall 2006(R23)

VT-2

EVT-2

EVT-2/UT

EVT-2

VT-2 examninations of SLC penetrationduring Class I RPV pressure test eachoutage.

Enhanced VT-2 examinations duringClass 1 pressure test. No indications.

Enhanced VT-2 performed of safe-endand penetration in conjunction withASME Section X1 Class I pressure test.Manual UT to Appendix VIII performedon nozzle to safe-end weld. Noindications.

Enhanced VT-2 examninations of safe-end and penetration performed inconjunction with ASME Section Xl

50

Page 52: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Spring 2008(RE24)

Fall 2009(RE25)

Spring 2011(RE26)

EVT-2

EVT-2

EVT-2

Class I system leakage test. Noindications.

Enhanced VT-2 examinations performedof safe-end and penetration inconjunction with ASME Section XlClass 1 system leakage test. Noindications.

Enhanced VT-2 examinations of safe-end and penetration performed inconjunction with ASME Section XlClass I system leakage test. Noindications.

Enhanced VT-2 examinations of safe-end and penetration performed inconjunction with ASME Section XlClass I system leakage test.No indications.

Jet Pump Assembly 1986-1995

Spring 1997(RE 17)

Fall 1998(RE 18)

Spring 2000(RE 19)

Fall 2001(RE20)

VT- I /VT-3/UT

VT- I /VT-3

VT -I /VT-3

N/A

VT-3

VT- I

EVT- I

VT examinations on ten (10) Jet Pumpseach outage. Exam includes applicableGE SILS. Jet pump beams replaced in1985. Jet pump beam UT firstperformed in 1993.

Ten (10) jet pumps VT examined. Examincludes applicable GE SILs. Noindications.

Ten (10) jet pumps VT examined. Examincludes applicable GE SILs. Noindications.

Examinations deferred to Fall 2001.

VT-3 examinations on all 20 jet pumpnozzle inlets per SIL 465. Noindications.

VT-I examinations on all WD-I's. Noindications.

EVT-I examinations on BB-I and BB-2onJP's 1-10. EVT-l onMX-2'son

51

Page 53: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

JP's 1 - 10. EVT-I on RB-I's and RB-2's on JP's 1/2, 3/4, and 5/6. Noindications. EVT-I on RS-1's, RS-2's,and RS-3's on JP's 1 - 10. EVT-I onRS-6's on JP's I, 3, and 5. EVT-I onRS-7's on JP's 2, 4, and 6. EVT-I onRS-8's and RS-9's on JP's 1/2, 3/4, and5/6. No indications.

Spring 2003 VT-3 VT-3 examinations on the JP nozzle inlet(RE21) mixers on JP's 1 I - 20 per SIL 465. VT-

3 examinations of set screws, gaps, andtack welds on JP's 1 - 20 per SIL 574.No indications.

EVT-1 EVT-I examinations on the IN-4 onJP's 5, 6, 11, 12, 13, and 14. EVT-Iexaminations on the MX-2 on JP's 11,12, 13, and 14. EVT-1 examinations onthe RB-I's and RB-2's, on JP's 11/12and 13/14. EVT-I examinations on RS-1and RS-2 on JP's 11/12, 13/14, 15/16,and 17/18; RS-6 on JP's 11 and 13; RS-7's on JP's 12 and 14; RS-8's and RS-9's on JP's 11/12, 13/14. No indications.

UT UT examinations on the BB-1 's and BB-2's for JP's 1 - 20. No indications.

Spring 2005 VT-3 VT-3 on the JP nozzle inlet mixers on JP(RE22 s I - 10 per SIL 465. No indications.

VT-I VT-I examinations on JP set screws,gaps and tack welds on JP's 1, 2, 15, and16 per SIL 574. No indications.

EVT-I EVT-I examinations on RS-I, RS-2, andRS-3 welds on JP's I and 2 and the IN-4welds on JP's 7, 8, 9, and 10. Noindications.

Fall 2006 VT-I VT-I per SIL574 of adjustment screw(RE23) and gap and tack welds on JPs 9, 10. VT-

I of WD-I at JP's 9, 10. No indications.

EVT-I of RS-1 and RS-2 on JP's 15/16

52

Page 54: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

EVT-I and 19/20.EVT-1I and 19/20.

Spring 2008(RE24)

Fall 2009(RE25)

Spring 2011(RE26)

EVT- I

UT

VT-3

VT-I

EVT- I

VT-3

VT-I

EVT-I examinations of IN-4's at JP's 19and 20. EVT-I examinations of RB-la's,-Ib's, -Ic's, and -Id's between JP's 9/10and 19/20. EVT-I examinations of RB-2a's, -2b's, -2c's, and -2d's between JP's9/10 and 19/20. EVT-I examination ofRS-3 between JP's 19/20. EVT-1examinations of RS-6 at JP's 9 and 19.EVT-I examination of RS-7 at JP's 10and 20. EVT-1 examinations of RS-8and RS-9 at JP's 19/20 and 9/10. Noindications.

UT of BB-1, -2 and -3 on all 20 JPbeams. No indications. UT of MX-2 (andAD-1, AD-2, DF-I, DF-2, DF-3 note inDiffuser Section) on all 20 jet pumps.

VT-3 of JP nozzle inlets per SIL465 onJP's 15, 16, 17 and 18. No indications.

VT-I per SIL574 of adjustment screwand gap and tack welds on JPs 10. 15,16, 19, and 20. VT-I of WD-I at JP's 17,and 18. No indications.

EVT-1 examinations of IN-4 on JP's 15,16, 17, and 18. EVT-I examinations ofRB-I's and RB-2's on JP's 7/8, 15/16,and 17/18. EVT-I examinations on RS-l's and RS-2's on JP's 11/12 and 17/18.EVT-lexaminations on RS-3's on JP'sI 1/12, 15/16, and 17/18. EVT-Iexaminations on RS-6's on JP's 7, 15,and 17 and RS-7's on JP's 8, 16, and 18.EVT-I examinations on RS-8's and RS-9's on JP's 7/8, 15/16, and 17/18. Noindications.

VT-3 of JP nozzle inlets on JP 9 and 10.No indications.

VT-I of the JP Restrainer Wedge (WD-1) at JP-I thru JP-20. No indications of

53

Page 55: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

movement or wear observed.

EVT-1 EVT-I of RS-8 and RS-9 on JP-1 thruJP-14, JP-19, and JP-20. No indications.

EVT-1 of JP-9 and JP-10's IN-4, RB-Ia,RB-Ib, RB-Ic, RB-Id, RB-2a, RB-2b,RB-2c, RB-2d, RB-3, RS-1, RS-2. EVT-I ofJP-9's RS-6 and JP-O's RS-7. Noindications.

EVT-I of JP-7 and JP-8's RS-3. Noindications.

I. I. t

Jet Pump Diffuser 1986-1998

Spring 1997(RE 17)

Fall 1998(RE 18)

Spring 2000(RE 19)

Fall2001(RE20)

Spring 2003(RE21)

Spring 2005

VT -3

VT -1/VT-3

VT-I /VT-3

N/A

EVT-I

VT-3

VT-I

EVT-I

VT-3

10 Jet Pumps VT-3 examined eachoutage. No indications. No indications.

Ten jet pumps VT examined. Examincludes applicable GE SILs. Noindications.

VT examinations on ten (10) jet pumps.Exam includes applicable GE SILs. Noindications.

Exams deferred to Fall 2001.

EVT-I examinations on ten (10) jetpumps (5 assemblies). Identified anindication thought to be a broken jetpump sensing line upper bracketretaining weld. Evaluated as acceptable.

VT-3 on JP sensing lines for all jetpumps per SIL 420. No indications.

VT- I on sensing line brackets for all jetpumps per SIL 420. Previously reportedcracked bracket weld was determined notto be cracked. No indications.

EVT-I examinations of AD-1, AD-2,AD-3a, AD-3b welds on JP's 11 through20. No indications.

VT-3 on JP sensing lines for JP's I - II

54

Page 56: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

(RE22)

Fall 2006(RE23)

Spring 2008(RE24)

Fall 2009(RE25)

Spring 2011(RE26)

and 14 per SIL 420. No indications.

VT-I

EVT-I

UT

EVT-1

EVT-1

VT-I on JP sensing line brackets for JP's1- I 1 and 14. No indications.

EVT- 1 on AD-I on JP's 1, 2, and 5.EVT-I examinations on AD-2, AD-3a,AD-3b, DF-1 on JP-15, 16, 17, 18, 19,and 20 and DF-2 on JP's 15, 16, 19, and20. No indications.

UT on AD-1, AD-2, DF-1, DF-2, andDF-3 (and MX-2). One (1) indication onDF-I at JP-14. EVT-I examinations onDF-1 at JP-14 in addition to UT.Appeared to be a defect from originalconstruction.

EVT-I examinations of indication to DF-1 on JP-14 identified during the previousoutage. No change.

EVT-i re-examination of indicationlocated on the inside surface of JP-14 atthe DF-1 weld. Indication was found tohave no changes.

CRD Guide Tube Fall 1995

Spring 1997(RE 17)

Fall 1998(RE 18)

Spring 2000(RE 19)

Fall 2001(RE20)

VT -3

VT -3

VT -3

VT-3

EVT-I

VT-3

VT-3 exams of accessible guide tubes.No indications.

VT-3 exams of accessible guide tubes.No indications.

VT-3 exams of accessible guide tubes.No indications.

VT-3 examinations of eighteen (18) anti-rotation pins and eleven (11) CRGT-1welds. No indications.

EVT-I examinations of four (4) CRGT-2and CRGT-3 welds. No indications.

VT-3 examinations of thirteen (13) anti-rotation pins and thirteen (13) CRGT-1welds. No indications.

55

Page 57: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

EVT -1

Spring 2005(RE22)

Fall 2006(RE23)

Spring 2008(RE24)

EVT-1

EVT-I

EVT-1

EVT-1 examinations of five (5) CRGT-2and CRGT-3 welds. No indications.

EVT-1 examinations on one (1) CRGT-2weld and one (1) CRGT-3 weld. Noindications.

EVT-1 examinations of one (1) CRGT-2weld and one (1) CRGT-3 weld. Noindications.

EVT-I examinations of two (2) CRGT-2welds and three (3) CRGT-3welds. Noindications.

EVT-1 examinations on one (1) CRGT-2weld and two (2) CRGT-3welds. Noindications.

Fall 2009(RE25)

EVT-1

CRD Stub Tube N/A N/A No record of examination.

In-core Housing NA NA No record of examination back to 1996

Dry Tube 1989-1991 VT VT exam in 1989, 1990, and 1991 perSIL409R1. All dry tubes replaced in1993.

Spring 2005 VT Replaced one (1) dry tube.(RE22)

Instrument 1986-2000 VT-2 VT-2 examination performed duringPenetrations RPV system leakage test each outage for

all six (6) instrument nozzlepenetrations. No indications.

Spring 2000 PT PT examination of N16A instrument(RE 19) penetration nozzle to safe-end weld.

Fall 2001 VT-2 VT-2 examination performed during(RE20) RPV system leakage test. No indications.

Spring 2003 VT-2 VT-2 examination performed during(RE2 1) RPV system leakage test. No indications.

Spring 2005 VT-2 VT-2 examination performed during(RE22) RPV system leakage test. No indications.

UT UT examination of Nl6 nozzle to safe-end per Risk-Informed ISI Program and

56

Page 58: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Fall 2006(RE23)

Spring 2008(RE24)

Fall 2009(RE25)

Spring 2011(RE26)

VT-2

VT-2

VT-2

VT-2

Appendix VIII. No indications.

VT-2 examination performed duringRPV system leakage test. No indications.

VT-2 examination performed duringRPV system leakage test. No indications.

VT-2 examination performed duringRPV system leakage test. No indications.

VT-2 examination performed duringRPV system leakage test. No indications.

+ +

Vessel ID Brackets 1986-1995

Spring 1997(RE17)

Fall 1998(RE 18)

Spring 2000(RE 19)

Fall 2001(RE20)

VT -1/VT-3

VT -I/VT-3

VT -1/VT-3

EVT- I

VT-3

VT-I

EVT-I

EVT-l

ASME XI VT-3 (non-beltline) and VT-I(beltline examinations) ofjet pump riserbrace, dryer, FW Sparger, Core Spray,guide rod, and surveillance capsuleholder brackets performed once perinterval. No indications.

VT- 1/VT-3 ASME Section XIexaminations on five (5)jet pump riserbrackets, FW brackets and weldsexamined. No indications.

VT-I/VT-3 ASME Section XIexaminations on five (5) jet pump riserbrackets, FW brackets and weldsexamined. No indications.

EVT-1 examinations on four (4) CSbracket attachment welds. Noindications.

VT-3 examinations of guide rodattachment welds. No indications.

VT-I on FW sparger brackets. Noindications.

EVT- I examinations on CS bracketattachment welds. No indications.

EVT-1 examinations on all FW spargerbracket attachment welds and all dryersupport attachment welds. No

57

Page 59: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Spring 2003(RE2 1)

Spring 2005(RE22)

Fall 2006(RE23)

Spring 2008(RE24)

Fall 2009(RE25)

Spring 2011(RE26)

EVT-1

VT-3

EVT-1

VT-3

EVT-1

EVT- I

EVT-1

indications.

EVT-1 examination of on JP riser bracepad attachment weld at 150'. Noindications.

VT-3 examination of steam dryer holddown brackets.

EVT-1 of eight (8) FW sparger bracketsand four (4) CS piping bracketattachment welds. No indications.

VT-3 of guide rod attachment welds. Noindications.

EVT-1 examinations of JP riser bracepad attachment welds at 300, 1500, 2100,270', and 3300. EVT-1 examinations ofsteam dryer support bracket attachmentwelds at 215' and 3250. No indications.

EVT-1 examinations of JP riser bracepad attachment welds at 600, 90', and1200. No indications.

EVT-t of the JP riser brace padattachment welds, JP-RBPAD-ATTWLDS A 30'. No Indications.

LPCI Coupling N/A N/A Not applicable to this plant.

Steam Dryer Fall 2001 VT-I VT-I of twenty four (24) drain channel(RE20) welds per SIL 474.

Spring 2003 EVT-1 EVT-I of twenty four (24) drain channel(RE21) welds per SIL 474.

Spring 2005 VT-I VT-I of leveling screws per OE 16110(RE22)

Fall 2006 VT-I Performed baseline VT-I examinations(RE23) w/Character to BWRVIP-139 and SIL 644, Rev 2.

Card Re-examined five (5) minor indicationspreviously identified per SIL 474adjacent to several drain channels. Two(2) new indications were observed in a

58

Page 60: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

weld adjacent to a drain channel andboth tack welds on one (1) lifting lugwere observed. The indications wereevaluated as acceptable.

Fall 2009(RE25)

VT-I examinations on seven (7)previously identified indications ondryer. With additional cleaning, six (6)of the indications disappeared with onlyone (1) remaining (i.e., the cracked tackwelds on one (1) lifting lug - no changein the lifting lug).

Dissimilar metal Spring 2008 UT Automated UT performed on four (4)welds (RE24) CAT A welds per Appendix VIII.

Manual UT performed on two (2) CATA welds. All welds included in Risk-Informed ISI Program. No indications.

Spring 2011 UT Manual UT inspection performed on one(RE26) (1) CAT D nozzle to cap weld (CRD

Return) per Appendix VIII and Risk-Informed ISI Program. No indications.

59

Page 61: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Reactor Internals Inspection History

Plant: Hatch Unit 2

Component in Date of Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Inspection Results, Repairs,

Inspection Used Replacements, Re-inspectionsCore ShroudHorizon d 1994 UT UT H-I through H-4. Indications on all

VT-I (.001) four (4) welds. Safe for continuedoperation.VT-I (.00 1) with brushing on sampleareas of H-5, H-6A(B), & H-7) at 1900and 3500. No indications. Installed four(4) Shroud Tie Rods in "95" whichexempts horizontal welds H-I through H-8 from inspection.

Core ShroudTie Rods

1995

1997

1998

2007

Spring 2009(2R20)

Spring 2011

VT-3

VT-3 &Tightness

VT-3 &Tightness

EVT- 1, VT-3 &

Tightness

EVT-l.VT-3.

EVT- 1,VT-3

Installed four (4) Shroud Tie Rods '95.Performed baseline. No indications.

Performed first cycle inspections on all 4Shroud Tie Rods. No indications.

Shroud Tie Rod at 225 degrees. Noindications.Future Shroud Tie Rod Inspections not toexceed 10 years.

All Tie Rods-No indications. UpperSupports & Tie Rod Nuts have beendetermined to be susceptible to IGSCC.This will make corrective action necessaryby next outage.

All four tie rod assemblies modified withreplacement component items designed tonot be susceptible to IGSCC. Allcomponent items replaced with theexception of the lower collet and clevispin.

Post tie-rod modification inspections onall 4 tie rods were successfully performedwith no indications noted.

Core Shroud 1995 EVT-1 Bottom ID/OD six (6) inches of V-3, V-

60

Page 62: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Vertical Welds 4. Top ID/OD six (6) inches of V-3, V-4.Top ID/OD Twenty-four (24) inches of V-5 & V-6. No indications. Inspections tosupport the Shroud Tie Rod installation.

1997 EVT-1 Performed baseline all verticals from theoutside surface per BWRVIP-07. Noindications.

2000 EVT-1 Performed baseline all verticals from theoutside surface per BWRVIP-07. Noindications.

2001 EVT-1 Performed EVT-l examinations from theoutside surface for welds V-I, V-2, V-9,V-10, & V-1 1. No Reportable Indications.These welds are scheduled inapproximately six year intervals for singlesided coverage per BWRVIP-63

2005 EVT-1 Performed EVT-1 examinations on theinside & outside surfaces of vertical weldsV-3, V-4, V-5, V-6, & V7. Inside surfaceindication was found on V-6 at the upperintersection (H-4) which parallels H-4.Also examined the outside surfaces ofvertical welds V-12, V-13, V-14 with noindications.

2007 EVT-1 Performed EVT-I examinations from theoutside surface for welds V- 1, V-2, V-9,V-,10 & V-1Il. No Reportable Indications.V-6 Inside surface indication was found in2005 on at the upper intersection (H-4)which parallels H-4. Was re examined todetermine if this indication had changed.No changes were recorded.

2011 EVT-I Performed EVT-1 examinations from theoutside surface for welds V-12, V-13, andV-14. No reportable indications.

Core Shroud Ring N/A N/A Hatch 2 does not have Ring SegmentSegment Welds Welds

Core Shroud 1995 EVT-1 Horizontal surfaces of Shroud SupportSupport 1 1,,___L__de: Examined four (4) locations

61

Page 63: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

1997

1998

2007

VT-3

VT-3

VT-3

(450,1350, 2250, & 315') between JetPumps on top surface adjacent tolocations where Shroud Tie Rods to beinstalled. No indications.

H-9: Examined 25% of accessible topsurfaces. No indications.

H-9: Examined 75% of accessiblesurfaces from top per BWRVIP-38. Noindications.

H-9: Examined 100% of accessiblesurfaces from top per BWRVIP-38. Noindications.

Core Spray InternalPiping

1980-97

1997

1998

2000

2001

2003

2005

2007

Spring 2009(2R20)

Spring 2011(2R21)

VT-I (.001)

EVT-1

EVT-I

EVT-1

EVT-1

EVT-I

EVT-1

EVT-1

EVT-I

EVT-1

IEB 80-13/NUREG CR-4523. Examined100% each outage prior to 96. Noindications.

Baseline per BWRVIP-18. NoIndications.

Reinspection per BWRVIP-18. NoIndications.

Reinspection per BWRVIP-18. NoIndications.

Reinspection per BWRVIP-1 8. NoIndications.

Reinspection per BWRVIP-18. NoIndications.

Reinspection per BWRVIP-18. NoIndications.

Reinspection per BWRVIP-18. NoIndications.

Reinspection per BWRVIP-1 8. NoIndications.

Reinspection per BWRVIP-18-A. Noindications.I I

62

Page 64: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Core Spray Sparger 1980-96

1997

1998

2000

2001

2003

2005

VT-I (.001)

CSVT-I

CSVT-IVT-3 (1/32)

EVT-IVT-I

EVT-IVT-I

EVT-IVT- I

EVT-IVT-I

IEB 80-13/NUREG CR-4523. Examined100% each outage prior to '97.Indications reported in four (4) SpargerBracket to shroud welds first reported in1994, safe for continued operation.Indications reported on four more SpargerBracket to shroud welds in 1995. Eight(8) locations total. Safe for continuedoperation.

Examined all previously reported SpargerBracket indications. No change.

Re-inspection per BWRVIP-1 8. Nochange in previously reported SpargerBrackets indications from 1994/1995. Cannot clean or get a good close look at theseindications to classify.

Began sampling Sparger inspections as"Geometry Critical" instead of "GeometryTolerant".No new indications. No change inpreviously reported eight (8) SpargerBrackets indications from 1994/1995. Cannot clean or get a good close look at theseindications to classify.

No new indications. No change inpreviously reported eight (8) SpargerBrackets indications since1994/1995. Cannot clean or get a good close look at theseindications to classify.

No new indications. No change inpreviously reported eight (8) SpargerBrackets indications since 1994/1995. Cannot clean or get a good close look at theseindications to classify.

No new indications. Could not find someof the previously reported sparger bracketindications despite relooks. No change inthe observed Sparger Bracket indicationssincel994/1995. Can not clean or get agood close look at these indications to

63

Page 65: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

classify.

Spring 2009(2R20)

Spring 2011

EVT- IVT-I

VT-I

New sparger bracket-to-shroud indicationat 272'. Previous sparger bracket-to-shroud indications tracked since 1994remain unchanged. New indicationrecorded is acceptable and similar toprevious indications.

Reinspection of sparger bracket-to-shroudindication at 272 degrees. Additionalindications noted in the same area, similarto previous indications. This indication isthought to be older, and revealed due tomore efficient cleaning methods used forthe first time in this area. All otherbracket locations were inspected in 2009with no changes since 1994.

Top GuideBWRVIP-26, 1997

Hatch 2 Top Guidehas wedges

1992

1994

1995

1997

2001

2005

VT-1 (.001)

VT-I (.001)

VT-3

VT-I (.001)VT- 1/3

VT-I

VT- 1/3

Grid/beams: SIL-554, VT-I (.001)bottom of intersections. Examined 28cells in '92. No indications.

Grid/beams: SIL-554, VT-i (.001)bottom of intersections. Examined 10cells in '94. No indications.Hold downs & aligners: SIL-588,examined 2 of 4 1994. No indications.

Wedges (24): No indications.

Grid/beams: SIL-554, VT-1 (.001)bottom of intersections. Examined 6 cellsin '97. No indications.Rim, upper/lower plates, bolting:Examined in 1997. No indications.

Hold-downs and attachments to theshroud (2 of 4) 1800 apart every otheroutage. No relevant indications. Theprevious analysis was no longer validsince power & extended power up-rate.

Grid/beams: SIL-554, Examined 16 cellsin '05. No indications.Rim, upper/lower plates, bolting:Examined 50% in 2005. 100% Grid

64

Page 66: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2007

Spring 2009(2R20)

Spring 2011

VT-I

VT-i

VT-I

Beams VT-3 from top surfaces.No indications.

Hold-downs and attachments to theshroud (2 of 4) 1800 apart every otheroutage. No relevant indications.

Grid/beams: SIL-554, Examined bottomsurfaces of 14 cells. No indications.

Hold-downs and attachments to theshroud (2 of 4) 1800 apart every otheroutage. No relevant indications.

Grid/beams: BWRVIP-183. Examinedbottom 2" from sides and grid beamintersections of 8 cells. No indications.

Core Plate 1994 VT-3 Surfaces: Examined accessible areas1995 during CRB replacement. No

indications.Hold down bolts: No indications.

No BWRVIP inspections are required.Core Plate wedges installed in 1995.

Standby Liquid 1980-96 VT-2 Not accessible from inside. PortionControl visible during '94 access hole cover

replacement. Examined for leakage fromoutside during RPV leakage test eachoutage. No indications.

2000 Direct VT-2 Safe-end & Extension : RPV Support2001 Skirt was found to have an inspection2003 cover to gain access during leakage test.

No Leakage. Looking at performing UTin the future.

2005 UT Safe-end & Extension per ASMESupplement 10. No indications.

Jet Pump Assembly 1980-1998 UT Hold down beamns: UT each outage in '80- 88 outages - indications in I beamn,replaced with original design. Replacedall beams in '89 with improved design.

1994 VT-1/3 1994: Riser Brace Pads & Arms,Restrainers. No Indications

65

Page 67: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

1995 VT-1/3 1995: All adjusting screw tack welds,sensing lines & support brackets, pads &arms. No Indications.

1997 VT-I (.001) 4 assemblies: ( riser brace pad, restrainer& VT-3 adjusting screw tack welds, riser brace

arm tack welds, inlet mixer, sensing line,restrainer set screw gaps). No indications.

Hold down beams: All 20 Hold downbeams examined in '98 per BWRVIP-41.No indications.

Thermal Sleeve to Elbow Welds: All 10.No indications.

1998 MVT-1 All High Priority Welds (not TS to el.):per BWRVIP-41. Two small indicationsreported on one (1) RS-3 & one (1) DF-Iweld. Possibly non-relevant. Dispositionacceptable, examine next outage.

2000 EVT-1 Re-examination of two (2) previousindications reported in 1998, one (1) RS-3& one (1) DF-l weld.Indications determined to be non-relevant.

2001 VT-I 50% of the medium priority welds per& BWRVIP-41. RS-6 to RS-7's, RS-8 to

EVT-1 RS-9's, RB-I's, RB-2's, MX-I's, WD-l's,DF-I's. No relevant indications.

2003 EVT-I Thermal Sleeve to Elbow Welds (RS-1):50% of the population. No indications

2005 EVT-1 Performed 50% of the RS-2, RS-3, DF-2,AD-I, AD-2, RB-la(b)(c)(d) & RB-2a(b)(c)(d). No indications.

2007 VT-I Performed VT-I 100% of the WD-l's.EVT-I Performed 100% UT of BB-l, BB2, &

UT BB-3. Performed EVT-1 50% of RS-8 toRS-9's, IN-4's, MX-2's, DF-I's, RS-6,s& RS-7's. No indications.

66

Page 68: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Spring 2009(2R20)

Spring 2011(2R21)

EVT-1,VT-I

EVT-1,VT-I

Performed 2 l0 50% reinspection of RS-1,RS-2, RS-3, DF-2, AD-I & AD-2.Inspected (2) RB-I locations. Noindications.

Performed VT-I of 100% of the WD-lpopulation. Performed EVT- I of 100% ofRS-8 to RS-9 welds. Performed EVT-l of4 total RB-I weld locations and 3 totalRB-2 weld locations. Performed VT-I of2 jet pump sensing line brackets. Norelevant indications.

Guide Tubes 1994

2001

VT-3

EVT-1&

VT-I

Examine when accessible once/interval.Not normally accessible from inside.Portions visible during '94 access holecover replacement - no indications.Examined 14 in '94. No indications.

Guide Tube Welds: Examined CRGT-1,2, & 3 in 14 guide tubes withAnti/Rotation Pins.(14% of thepopulation) per BWRVIP-47. No relevantindications. Future inspections based onindustry inspection results. Also examined14 Anti/Rotation Pins

Instrument 1980-2005 VT-2 2NI 1, 2N12, 2N16 Nozzles. ExaminedPenetrations during RPV leakage test each outage. No

indications.Hatch ASME exempt.

*RPV Interior 1989 VT-I, VT-3 Feedwater sparger brackets: NUREG-Attachments 0619, Examine every fourth outage.(BWRVIP-48) Examined in '89, '92 & '97. Mechanical

damage on I bracket in '83 - bracket*Other Attachments replaced. No new indications.examined by otherBWRVIP 1992 VT-I, VT-3 Guide rod brackets: Examinedocuments. once/interval. Examined in '92.

Mechanical damage on I bracket in '92 -safe for continued operation.

Steam dryer hold down brackets:Examine once/interval. Examined in '92.No indications.

Steam dryer support brackets: Examine

67

Page 69: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

once/interval. Examined in '92, '94 &'97. Raised metal indications on 2brackets in '92 - metal removed, safe forcontinued operation.

Surveillance specimen brackets: Examineonce/interval. Examined in '92, '97 &'98. No indications. BWRVIP-48 in '98.

2001 EVT-I Feedwater sparger brackets: 50% of theVT-I brackets. No relevant indications. Once/10

years.Surveillance specimen brackets: 1 of 3brackets. No relevant indications.Once/I 0 years.

2003 EVT-1 Steam Dryer Support Brackets:Scheduled 2 of 4. 1 had piece missingnear corner. Expanded scope to all 4 andfound another to be cracked on corner.Cracking was determined to be caused byfatigue. Cracked piece was removed.Future corrective action to be determined.Re-examine next outage.

2005 EVT-I Steam Dryer Support Brackets: Foundanother with a piece missing on a corner.Modifications were made by flat topingall 4 brackets by EDM. All 4 SteamDryer seating surfaces were also flattenedby EDM. To examine next outage.

Feedwater sparger brackets: examined 2of 4. No indications

2007 VT-3 All Guide Rod Brackets: VT-3. 30' UpperSurveillance Specimen Brackets: VT-3.30°Lower Surveillance SpecimenBrackets: EVT-1. All Steam DryerSupport Brackets EVT-I. No Indications.

Spring 2009 EVT-1 Inspected (2) RB-I locations, (2) PB(2R20) VT-I locations, and upper & lower surveillance

VT-3 specimen at 300' location. No indications.

Spring 2011 VT-3 Inspected I of 3 surveillance specimen

68

Page 70: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

(2R21) EVT-1 brackets at 1200 location, and 4 Jet PumpRiser Brace (RB-1) locations. No relevantindications.

LPCI Coupling Not N/A N/A(BWRVIP-42) Applicable

to Hatch

2007Steam Dryer(BWRVIP-139)

VT-I

VT-I (89)

BWRVIP-1392 - Steam Dryer Cover Plate HorizontalWelds at 00 & 1800 - No indications2 - Steam Dryer Upper Hood HorizontalWelds - No indications2 - Steam Dryer Radial Cover plateWelds at 90' & 2700 -No indications8 - Steam Dryer Drain Channel Welds -No indicationsI - Steam Dryer Manway Cover Weld at270 degrees - No indications49 - Steam Dryer Vertical End Plate &Partition Welds- No indications28 - Steam Dryer Tie Bars & Welds - NoindicationsI - Steam dryer Upper Support Ring0-360' (Top & Vert Surfaces) Minorindications on upper support ring side aremonitored for change.4 - Steam Dryer lifting eye andattachment welds

Asset Manaaement4 - Steam Dryer Seismic Brackets -Minor indications on uipper support ringside are monitored for change.2 - Steam Dryer Lower Support Ring (24"either side of guides at 00 & 1800) - NoindicationsI - Steam dryer Upper Guide at 1800 -

No indications

Inspected all four steam dryer seismicbrackets and uipper support ring top andvertical surfaces 0-3600 - Minorindications on upper support ring sidewere being tracked for changes. Nodiscernable changes.

Spring 2009(2R20)

69

Page 71: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Spring 2011 VT-i (89) Inspected steam dryer upper support ring(2R21) top and vertical surfaces (0-360'). Minor

indications on upper support ring sidewere being tracked for changes. Nodiscernable changes.

Moisture Separator Spring 2009 VT- 1 (89) Lifting eye, rod brackets and attachment(2R20) weld at all four locations. Guide rod

brackets at both locations. Lower supportring gussets 0-360' (18 locations). Noindications.

Spring 2011 VT-I (89) Inspected moisture separator guide rod

removable guide pins at 0' and 1800(2R2 1) locations. Non-relevant indications noted

on guide pins as well as gouge indicationson brackets. No discernable change inwear from previous outage. To bereinspected in 6 years.

DM Welds Spring 2009 UT 18 DM weld examinations using(2R20) automated Appendix VIII qualified UT.

3 SM alloy 182 weld examinations usingautomated Appendix VIII qualified UT.

3 examinations using manual AppendixVIii qualified UT.

One axial flaw was identified in the "2G"recirculation riser nozzle-to-safe endweld. The flaw was characterized as IDconnected in the weld butter on the safeend side and 0.26" (out of 1.22"thickness) deep. Analyzed as acceptablefor one cycle of operation.

Spring 2011 Repair Weld Overlay performed successfully on(2R21) N2G nozzle to safe end weld.

70

Page 72: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Reactor Internals Inspection History

Plant: LaSalle 2

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Inspection Results, Repairs, Replacements,

Inspection Used Reinspections

Core Spray Piping L2R13 (2011)

L2R 12 (2009)

L2Rll (2007)

EVT-I

UT

EVT-I

EVT-i

API, AP2, AP3, AP4a, AP4b, AP4c AP4d,AP8a, BP3, BP4a, BP4b, BP4c, BP4d,BP8a, CPI, CP2, CP3, CP4a, CP4b, CP4c,CP4d, CP8a, CP8b, DP3, DP4a, DP4b,DP4c, DP4d, DP8a, and DP8b. NRI. Threenew longitudinal welds identified locatedadjacent to CP4a at 187. All examined byEVT-i with NRI.

UT of 34 welds; API, AP2, AP3, AP4a,AP4b, AP5, AP6, AP7, AP4c, AP8b, BP3,BP4a, BP4b, BP5, BP6, BP7, BP4c, BP8b,CPI, CP2, CP3, CP4a, CP4b, CP5, CP6,CP7, CP4c, DP3, DP4a, DP4b, DP5, DP6,DP7 and DP4c. Existing flaw on BP5determined to be geometry. All othersNRI. Four new welds identified, (AP4c-1,BP4c-1, CP4c-1, and DP4c-1) locatedbetween P4c and P7 (OE28372). Allexamined by UT with NRI.

API, AP2, AP3, AP4a, AP4b, AP4c, AP4c-1, AP4d, AP8a, AP8b, BP3, BP4a, BP4b,BP4c, BP4c-1, BP4d, BP5, BP8a, BP8b,CP I, CP2, CP3, CP4a, CP4b, CP4c, CP4c-1, CP4d, CP8a, CP8b, DP3, DP4a, DP4b,DP4c, DP4c-1, DP4c-2, DP4d, DP5, DP8a,and DP8b. NRI. Five new welds identified,(AP4c-1, BP4c-1, CP4c-1, DP4c-1 andDP4c-2) located between P4c and P7. Allexamined by EVT-1 with NRI.

Visual examinations of core spray pipingwelds for which the UT is notdemonstrated. No indications (NRI).

8 pipinz brackets; NRI.

71

Page 73: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

L2RI0 (2005)

L2R09 (2003)

L2R08 (2000)

UT

EVT-I

EVT- I

UT

EVT- I

UT of 34 welds; API, AP2, AP3, AP4a,AP4b, AP5, AP6, AP7, AP4c, AP8b, BP3,BP4a, BP4b, BP5, BP6, BP7, BP4c, BP8b,CP1, CP2, CP3, CP4a, CP4b, CP5, CP6,CP7, CP4c, DP3, DP4a, DP4b, DP5, DP6,DP7 and DP4c. Existing flaw on BP5 re-sized with no growth. All others NRI.

Welds for which UT is not demonstrated:API, AP4d, AP8a, BP5, BP4d, BP8a, CP1,CP4d, CP8a, CP8b, DP4d, DP8a, andDP8b. NRI.

2 core spray piping brackets; NRI.

Visual examinations of those core spraypiping welds for which the UT technique isnot demonstrated. No indications.

UT for those welds for which the UT tool isqualified.

8 piping brackets; NRL.

Core Spray Sparger VT-IL2R13 (2011)

EVT-I

6 sparger brackets; NRI.

S3B-a, S3B-b and S3B-c from 172.5 to268', S3C-a and S3C-b from 187 to 2680;bent sparger nozzle deflector identified inL2RJ I unchanged. All others NRI.

SIA, S2A (Left and right), S4A, S IB, S2B(Left and right), S4B, SIC, S2C (Left andright), S4C, S ID, S2D (Left and right),S4D. NRI.

6 sparger brackets; NRI.

S3A-a, S3A-b and S3A-c from 268 to 7.5',S3A-a, S3A-b and S3A-c from 7.5 to 880,S3B-a, S3B-b, and S3B-c from 172.5 to2680 and S3B-a, S3B-b, and S3B-c from 88to 172.50; bent sparger nozzle deflectoridentified in L2R1 I unchanged. All othersNRI.

L2R12 (2009) 1 VT-I

72

Page 74: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

L2RI1 (2007) VT-i

EVT-I

VT-i

VT-IL2RI0 (2005)

L2R09 (2003) 1 EVT-1

S3D-a, S3D-b and S3D-c from 352 to 880and S3C-a, S3C-b and S3C-c from 7.5 to88'; one bent sparger nozzle deflector; allothers NRI. Bent nozzle accepted for onecycle.

S I A, S2A (Left and right), S4A, S I B, S2B(Left and right), S4B, S I C, S2C (Left andright), S4C, S I D, S2D (Left and right),S4D. NRI.

6 sparger brackets; NRI.

S3A-a and S3A-d from 268 to 0080 andS3D-a and S3D-b from 352 to 268; NRI

6 sparger brackets; NRI.

Visual inspection of half of the core spraysparger welds. NRI.

6 sparger brackets; NRI.

100% of all sparger welds. NRI.

12 sparger brackets. NRI.

Lower surveillance capsule bracket at 1(20;NRI.

Upper surveillance capsule bracket at 120f;NRI.

(See jet pump and core spray sections ofthis report.)

Steam dryer attachment welds, fourlocations, NRI

Upper bracket attachment welds forsurveillance baskets at three locations, NRI.

Lower bracket attachment welds forsurveillance baskets at three locations.Basket disengaged at 1200 location andaccepted for one cycle. All others NRI.

L2R08 (2000) VT-I

EVT-I-I 4

Attachment Welds L2R13 (2011)

L2Rll (2007)

L2R10 (2005)

VT-I

VT-3

EVT- 1

VT-3

VT-I

73

Page 75: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

L2R09 (2003)

L2R08 (2000)

EVT-1

EVT-I

VT-I

VT-3

VT-I

All feedwater sparger attachment welds;NRI.

All feedwater sparger attachment welds;NRI.

Steam dryer attachment welds, four

locations, NRI

Guide Rod attachments at 0' and 180; NRI.

Upper surveillance capsule brackets at threelocations: NRI.

Lower surveillance capsule brackets atthree locations; NRI.

Core Shroud L2RI 1 (2007) VT-3 Surfaces of the shroud for ASME SectionXI. NRI.

(Note: LaSalle has two L2RI0 (2005) UT UT of welds H3, H5, H6, and H8beltline horizontal All welds are NRI.welds and therebyunique designation). L2R07 (1996) UT UT of H5, H6, and H8. NRI.

L2R06 (1995) UT UT of H3, H4, H5, H6, and H8. NRI.

Shroud Support L2R13 (2011) EVT-1 H8a weld (BWRVIP weld H8) for >10%--NRI.

L2R12 (2009) EVT-1 Access Hole Covers at 0 and 180°--NRI

L2RI 1 (2007) VT-3 Access Hole Covers at 0 and 180' forASME Section Xl. NRI

Accessible portions of the top of the shroudsupport plate for ASME Section Xl. NRI.

Top of H9 weld (accessible locations) forASME Section Xl. NRI

L2RIO (2005) VT-I Access Hole Covers at 0 and 180°--NRI

VT-3 Inspection of the general condition of theRPV interior surface from the RPV closureflange elevation to the Steam Dam, 3600

around the RPV interior. NRI.

74

Page 76: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

EVT-1

VT-3

UT

VT-3

Inspection of the general condition of thecladding at the steam dam elevation, 360'around the RPV interior. NRI.

Examined RPV cladding from below coreplate to shroud support plate due to removalof the inlet mixers. NRI.

H8a weld (BWRVIP weld H8) for >10%--NRI

Inspection of the general condition of weldH9 from below the shroud support platedue to removal of all jet pump inlet mixers.NRI.

UT of 100% of H9 from the RPV OD.NRI.

Inspection of the general condition of theRPV interior surface from the RPV closureflange elevation to the Steam Dam, 360'around the RPV interior. NRI.Inspection of the general condition of thecladding at the steam dam elevation, 3600around the RPV interior. NRI.

L2R09 (2003)

+ 4 4

Top Guide L2R 3 (2011)

L2RI I (2007)

L2R10 (2005)

VT-3

EVT-I

VT-3

C-clamp at 090 and 18(f locations-NNRI

Lower Beam and Slot Intersections of 19cells-NRI.

C-clamp at 0'. NRI

Accessible portions of the top guide forASME Section XI. NRI

VT-3 C-clamps at 4 locations-NRI

SLC L2R12 (2009) VT-2 Visual inspection of the partial penetrationweld to the bottom head during the SectionXI system leak test. NRI.

L2R11 (2007) VT-2 Visual inspection of the partial penetrationweld to the bottom head during the SectionXI system leak test. NRI.

75

Page 77: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

L2RI 0 (2005)

L2R09 (2003)

L2R08 (2000)

UT

VT-2

VT-2

PT

VT-2

UT of the partial penetration weld and heataffected zone. NRI.

Visual inspection of the partial penetrationweld to the bottom head during the SectionXl system leak test. NRI.

Visual inspection of the partial penetrationweld to the bottom head during the SectionXI system leak test. NRI.

Surface examination. NRI.

Visual inspection of the partial penetrationweld to the bottom head during the SectionXl system leak test. NRI.

.4. -4- -

Jet Pump Assembly L2R13 (2011) VT-I

L2R12 (2009) VT-I

WD-I on all 20 pumps; three wedgesshowed movement with no change in wearfrom previous examinations; five rodsshowed new wear; accepted as-is.

Four auxiliary wedges examined, twovessel side and two shroud side. Onevessel side auxiliary wedge had new minorwear at the contact point with the bellyband and movement; accepted-as-is. Otherauxiliary wedges were NRI.

WD-I on 9 pumps; all showed minor wearwith most unchanged from previousexaminations.

Three auxiliary wedges examined, twovessel side and one shroud side. One vesselside auxiliary wedge had minor wear. Setscrew on same pump confirmed to be incontact with the belly band and tack weldsintact. Other auxiliary wedges were NRI.

WD-I wedges on all 20 pumps; 7wedges/rods showed minor wear; accepted-as-is. Auxiliary wedges installed at fourlocations on 3 pumps to compensate forobserved gaps.

L2R 11 (2007) 1 VT-I

________________________ I ________________ L _____________ L

76

Page 78: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

VT-3

L2RI0 (2005) VT-I

L2R09 (2003)

L2R08 (2000)

Examination of ratchet teeth engagementon 13 jet pump hold down beams due tofitup issues in the previous outage. NRI

All 20 inlet mixers were replaced with newinlet mixers with labyrinth seals in the slipjoint area, and with new non-stellite mainwedges. New hold down beams wereinstalled on 17 pumps. After replacement,three point contact verified at all locations(AS-I shroud side, AS-1 vessel side, andWD-1). NRI.

Replacement of 3 beams. After a review ofmaterial certification paperwork thatidentified them as Group I beams, threeholddown beams were replaced with lowstress beams.

WD-I on 3 pumps; NRI.

Installed 3 aux. Wedges to ensure threepoint contact for three pumps.

UT exam of 10 beams at the BB- 1 and BB-2 locations. NRI.

Exam of WD-1 on all 20 pumps; NRI.Exam of all set screw to belly band contactpoints; installed 7 auxiliary wedges tomaintain three point contact; all others NRI.

VT-I

UT

VT-3

Jet Pump Diffuser L2R13 (2011)

L2R11 (2007)

L2R10 (2005)

EVT-I

EVT-I

EVT- I

IN-I on 5 pumps; NR1.IN-2 on 5 pumps; NRI.

AD-2 on 6 pumps; NRI.DF-I on 10 pumps; NRI.

AD-2 on 4 pumps; NRI.DC-3 on 10 pumps; NRI.DF-2 on 10 pumps; NRI.DF-3 on 10 pumps; NRI.

AD-2 on 4 pumps; NRI.DF-I on 4 pumps; NRl.DF-2 on 4 pumps; NRI.DF-3 on 4 pumps; NRI.

L2R09 (2003) 1 EVT-I

77

Page 79: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

IN-I on 10 pumps; NRI.IN-2 on 10 pumps; NRI.

L2R08 (2000) EVT-1 AD-2 on 6 pumps; NRI.DF-1 on 6 pumps; NRI.DF-2 on 6 pumps; NRI.

UT DF-3 on 6 pumps; NRI.

Jet Pump Riser L2R13 (2013)

L2R12 (2009)

L2RIl (2007)

EVT-I

EVT- 1

EVT-1

All RS-I welds (including pup piece welds)on 2 risers; NRI.RS-2 on 3 risers; NRI.RS-3 on 5 risers; NRI.RS-6 on 2 risers; NRI.RS-7 on I riser; NRJ.RS-8 on all 10 risers; NRI.RS-9 on all 10 risers; NRI.RB-I on 5 jet pumps; NRI.RB-2 on 5 jet pumps; NRI.Strain relief welds on four risers; NRI.

All RS-t welds (including pup piece welds)on 8 risers; Re-sized flaw on RS-Ic on19/20; no change in length. All others NRI.

Re-sized flaw on RS-lc on 19/20; nochange in length.RS-1 on 2 risers; NRI.RB-I on 12 jet pumps; NRI.

Examined strain relief welds on all 10risers. NRIRe-sized flaw on RS-lc on 19/20; nochange in length.RS-2 on 3 risers; NRI.RS-3 on 5 risers; NRI.RS-6/7 on 10 jet pumps; NRI.RS-8/9 on all 20 jet pumps; NRI.RB-I on 10jet pumps; NRI.RB-2 on all 20 jet pumps; NRI.

Re-examined flaws on two RS-I welds;that on the 1/2 riser was determined to benon-relevant; those on the 19/20 riser werere-sized, with no change since L2R07(1996).MX-2 on 4 pumps; NRI.

L2RIO (2005) EVT-I

L2R09 (2003) 1 EVT-I

78

Page 80: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

RS-6/7 on ten pumps; NRI.

L2R08 (2000) UT UT exam of MX-2 on 6 pumps; NRI.

L2R07 (1996) VT-I RS-1 on all ten risers; two indications; oneon the 1/2 riser and the second on the 19/20riser; both accepted for two cycles.RS-2 on all ten risers. NRI.RS-3 on all ten risers. NRI.

Steam Dryer L2R13 (2011) VT-i

L2R12 (2009) 1 VT-i

One vertical weld on the 2700 side; NRI.One horizontal weld on the 90°side; NRIUpper and lower guide bracket at 1800 andlower guide bracket at 00. Previousindications showed no change.Two tie bars. Previous indications on tiebars reviewed and unchanged.Four tie rods; one previous indication re-confirmed with no change. All others NRI.Upper support ring from 0-360'; previousindication re-confirmed with no change.

11 vertical welds on the 90' side, all NRI.6 horizontal welds; all NRI.Upper and lower guide bracket at 1800 andlower guide bracket at 00. All RI as wasthe top of the guide rod at 180'. Conditionsaccepted as-is.Upper guide bracket at 00; NRI.15 tie bars. Previous indications on tie barsreviewed and unchanged. All others NRI.Two tie rods; one previous indication re-confirmed with no change. Second tie rodwas NRI.Upper support ring from 0-360'; top andside RI; bottom NRI. All indicationsaccepted as-is.

All welds recommended by BWRVIP-139and SIL 644 Revision 2 for a curved hooddryer on the 900 side of the dryer, tie rodson both sides, upper support ring externalsurfaces, upper and lower guide at 1800,(indication on the lower guide bracketaccepted for one cycle), lifting lugs andlifting assembly brackets at 45 and 1350,and 18 tie bars. Previous indications on tie

L2R 11 (2007) 1 EVT-I

79

Page 81: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

L2R10 (2005) VT-I

bars reviewed and no change in sizes. Allother welds NRI.

All welds recommended by SIL 644Revision I for a curved hood dryer on the270' side of the dryer, horizontal bankwelds on both the 90' and 270' sides, allfour lifting lugs; lifting assembly bracketsat 225' and 3150 locations, and all tie bars.Indications found on three tie bars andaccepted for one cycle. Upper strap onlifting assembly at 2150 found broken andwas removed. All other welds NRL.

Vessel L2R1O (2005) VT-3 Inspection of the general condition of theRPV interior surface from the RPV closureflange elevation to the Steam Dam, 360'around the RPV interior. NRI.

L2R09 (2003) VT-3 Inspection of the general condition of thecladding at the Steam Dam elevation, 360'around the RPV interior. NRI.

LPCI L2R13 (2011) EVT-1 Examined welds 45-12 and 45-3b at 1350;NRI.

VT-I Examined weld 45-8a,b,c,d at 135'. NRI.

VT-3 Examined bolts 45-6a,b,c,d at 1350; NRI.

L2RI 1 (2007) EVT-I Examined welds 45-12a, b, c, d and45-03a-d coupling at 315'; NRI.

VT- I Examined weld 45-08a,b,c,d at 315'. NRI.

VT-3 Examined bolts 45-06a,b,c,d coupling at315'; NRI.

L2RI0 (2005) EVT-I Examined welds 45-12a, b, c, d and 45-03a,b, c, d at 45, 135, and 315';NRI.

VT-I Examined weld 45-08a,b,c,d at 45, 135, and3150. NRI.

VT-3 Examined bolts 45-06a,b,c,d at 45, 135, and3150; NRI.

80

Page 82: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

L2R08 (2000) EVT-I BWRVIP-42, visual examination of allthree LPCI couplings. No indicationsdetected.

L2R07 (1996) VT-3 (Every other outage) VT-3 of all threecouplings; NRI.

Lower Plenum L2RI0 (2005) VT-I Examined all areas below the core platemade accessible by disassembly of 20 jetpumps. Areas examined includedCRD/ST-I, ST/RPV-1, 1-18a, H9, HIO, HI 1,H12, ICH/RPV-I, and bottom headcladding. NRI for all twenty locations.

L2R09 (2003)VT-3 / Visual examination of the fuel supportEVT-1 guide tube pins (FS/GT-ARPIN-1) at 4

locations, CRGT-l at 4 locations, CRGT-2at 21 locations, and CRGT-3 at 21locations. No indications.

L2R08 (2000) VT-3 Visual examination of the fuel supportguide tube pins (FS/GT-ARPIN-1) at 14locations, CRGT-I at 15 locations. Noindications.

DM Welds- L2R13 (2011) UT Eight welds examined by manual UT; noBWRVI P-75-A flaws.Category B

DM Welds- L2RI3 (2011) UT Two welds examined by manual UT; noBWRVIP-75-A flaws.Category D

L2R12 (2009) Two previous un-identified Category Dwelds were identified and the spoolpiece onwhich the welds were located was replacedwith a spoolpiece with non-IGSCCsusceptible welds.

Other L2R13 (2011) VT-3 Verified engagement of surveillancecapsule basket at 030(.

L2RI 1 (2007) VT-3 Removal of the surveillance capsule basketfrom 120° due to a broken spring.

81

Page 83: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Reactor Internals Inspection History

Plant: Limerick Generatin2 Station, Unit 2

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Inspection Results, Repairs,

Inspection Used Replacements, Reinspections

Core Shroud 1999 (2R05) UT A UT baseline of H3, H4, H5 and H7 wasperformed. H4 was the only shroud weldexamined from two-sides. Indicationsidentified on 1.D. of H3, H5, and on O.D.of H3, H4, and H5. No indicationsidentified at H7. Scope expanded toinclude UT of all remainingcircumferential welds (HI, H2, and H6).Indications identified on I.D. of HI, H2,and H6 and on O.D. of HI. Shroud wasreclassified as a Category C, un-repairedshroud.

Full structural margin was calculatedusing one cycle of crack growth.Structural analysis was re-performed in2R06 and again in 2R07. Re-examination was scheduled for H 1, H2,H3, H4, and H6 in 2R08 per site-specificevaluations. H5 and H7 are scheduled forre-examination in 2R10.

UT was performed on H I and H6 fromone-side with approximately 60%coverage. A two-sided UT wasperformed on H2, H3, and H4 withapproximately 60-63% coverage.Approx 21.5% of the ring-side scanswere obtained for H2 and H[3 with a newphased array technique.

Due to equipment problems, verticalwelds could not be screened by UT perBWRVIP-76. As a result, all verticalwelds were assumed to "screen in", andan EVT-1 was performed on these weldsfrom the shroud OD. Reinspection of thevertical welds, either UT or two-sidedEVT-1. is scheduled for 2007(2R09).

2005 (2R08) I UT

EVT-I

82

Page 84: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2007 (2R09) I EVT-1 Fuel was removed from areas surroundingthe shroud vertical welds, and an EVT-Iexamination was performed from the IDand the OD surfaces of the shroud on fourvertical welds V 15, V 16, V 17, and V 18.No indications were identified.

Another analysis of the indications foundin 2R08 (2005) on horizontal welds HI,H2, H3, H4, and H6 was performed todemonstrate that structural margins aremaintained until 2009 (2RI 0). Theanalysis demonstrated acceptable safetyfactors are maintained and a reinspectionby UT is scheduled for 2R10.

UT was performed on H3, H4, H5 and H7from two-sides. A one-sided UT wasperformed on H2 ring-side concurrentwith H3 ring-side exam. Coverage andresults are as follows:

2009 (2R10) 1 UT

H-2 LKUPH-3 LKDNH-3 LKUPH-4 LKDNH-4 LKUPH-5 LKDNH-5 LKUP-H-7 LKDNH-7 LKUP

- 83.3% - 0.7% flawed-83.3% - 0% flawed- 91.0% - 70% flawed- 97.7% - 39.9% flawed- 98.2% - 35.4% flawed- 77.2% - 12.8% flawed- 76.6% - 0% flawed-63.2%- 0% flawed-63.5%- 0% flawed

A re-analysis of the H 1, H2, and -16welds was performed prior to this refueloutage and the results supported a 10-year reinspection. Therefore, these threewelds are scheduled for inspection in2015 (2R13).

The structural analysis performed at theend of2R10 only supports one-cycle ofoperation for the H3, H4, and H5 welds.A site-specific analysis is currently inprogress to justify additional cycles ofoperation prior to reinspection. Since the

83

Page 85: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2011 (2RI1) I EVT-1

H7 weld had no flaws identified andcoverage was greater than 50%, thereinspection interval was determined tobe 10 years per BWRVIP-76 Table 2-1.

Due to multiple tooling issues andfailures, portions of the H5 and H7 weldswere also visually examined via EVT-Imethod from the OD surface only.Visual coverage on the H5 welds is19.5% of the weld length with norecordable indications identified. Visualcoverage on the H7 welds is 13.2% of theweld length with no recordableindications identified.

UT was performed on all 8 vertical welds(V7, V8, VI5, V16, V17, V18, V25, andV26). One indication was identified onthe ID of V17 and was 1.4 inches inlength. Coverage ranged from 77% to96% due to various configurationinterferences.

In addition, a structural re-analysis wasperformed for several horizontal welds.Additional cycles were justified and thenext re-examination is as follows:HI -2R13, H2-2R13, H3 -2R15, H4-2R15, H5 - 2R15, H6 - 2R13, H7 -

2R15. Verts - 2R16

UT

Shroud Support/Access Hole Covers

1991 (2R01)

1993 (2R02)

1995 (2R03)

1999 (2R05)

VT-3

VT-3

VT-3

EVT-1

VT-3 examination of accessible portionsof H-8 and H-9 welds from annulus. VT-3 examination of both access hole coversand welds. No indications identified.

VT-3 examination of shroud support legwelds at Azimuth 300 deg throughdisassembled jet pump # 18. Noindications identified.

VT-3 examination of both access holecovers and welds. No indicationsidentified.

EVT-I examination 10% of the weld H-8

84

Page 86: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2003 (2R07)

2005 (2R08)

2007 (2R09)

VT-3

UT

VT-3

EVT-1

VT-1

& H-9 length; in areas of 0 & 180 degaccess hole covers. No indicationsidentified.

VT-3 examination of both access holecovers and welds. No indicationsidentified.

UT of 10% of weld H-9 length. Noindications identified.

VT-3 examination of both access holecovers and welds. No indicationsidentified.

EVT-1 examination of 10% of weld H-8length. No indications identified.

VT-I examination of both access holecovers and welds. All three welds wereexamined on the 180 deg Top Hat. Noindications identified.

Best effort VT-I / VT-3 of the lower sideof H-8 and H-9, and six shroud supportlegs (3 welds H 10, H 11, H 12 on each leg)were examined via access through thedisassembly of Jet Pumps 1, 12, and 17.No indications were identified.

EVT-l examination was performed onboth the 0 and 180 degree access holecovers. These completed the baselineexam requirements of BWRVIP-180. Allthree welds were examined on the 180degree Top Hat configuration. Noindications identified.

EVT-I examination was performed on14% of the H-8 weld. No indicationsidentified.

Best effortVT-I/VT-3

2011 (2RI 1) EVT-I

Core Spray Piping 1991 (2R01) VT-I Enhanced VT-I (I mil resolution)- 1995 examination performed every refueling(2R03) outage on piping and welds per IEB 80-

13. No indications identified.

85

Page 87: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

1997 (2R04)

1999 (2R05)

2001 (2R06)

2003 (2R07)

2005 (2R08)

2007 (2R09)

2009 (2R 10)

EVT-1

UT

EVT-1

EVT-1

UT

EVT- I

EVT-1

UT

EVT- 1

EVT-1

EVT-I (1/2 mil resolution) examinationof welds per IEB 80-13 and BWRVIP-18baseline. No indications identified.

UT examination of welds (P1 thru P8)per BWRVIP-18 baseline UT. Noindications identified.

EVT-1 supplemental examination onP4dA, P4dB, P4dC, P4dD, P8aA, P8aB,P8aC, and P8aD. No indicationsidentified.

EVT-I of P4dA, P8aA, P8aB, P8aC, andP8aD. No indications identified.

UT examination of welds (P1 thru P8)with the exception of P4a, P4b, P4d andP8a welds. No indications identified.

EVT-I of P4dB, P8aA, P8aB, P8aC, andP8aD. No indications identified.

EVT-1 of P4dA, P4dC, P8aA, P8aB,P8aC, and P8aD. No indicationsidentified.

UT examination ofPl, P2, P3a, P3b, P4b,P5, P6, P7, and P8b welds wasperformed. No indications wereidentified.

EVT-1 of the far side of Pl, P2, P3a, P3b,P4b, and P8b welds, as well as an EVT-Iexamination of P4dD and P8a welds wasperformed.

A small piece of raised metal wasidentified and evaluated as acceptable onthe P8aC weld. Also, a small indentationon the collar near the P8aD weld wasidentified and evaluated as acceptable.

EVT-I of the far side ofPl, P2, P3a, P3b,P4b, and P8b welds, as well as an EVT-Iexamination of P4dA and P8a welds was

86

Page 88: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

performed. No indications wereidentified. Previously identifiedindications on P8aC and P8aD could notbe found in 2R10.

2011 (2R1 1) EVT-I EVT-I was performed on both near andfar sides of the following locations: PI,P2, P3a, P3b, P4a, P5, P6, P7, P8a, andP8b welds. In addition, EVT-1 wasperformed on P4dB. No indicationsidentified.

Core Spray Piping 1999 (2R05) EVT-I EVT-I of 2 piping support brackets PB-7Brackets & PB-8. No indications identified.

2001 (2R06) EVT-I EVT-I of 2 piping support brackets PB-7and PB-8. No indications identified.

2003 (2R07) EVT-i EVT-1 of 3 piping support brackets PB-4,PB-5, and PB-6. No indicationsidentified.

2005 (2R08) EVT-I EVT- I of 3 piping support brackets PB- 1,PB-2, and PB-3. No indicationsidentified.

2007 (2R09) EVT-I EVT-I of 2 piping support brackets PB-7and PB-8. No indications identified.

2009 (2R 10) EVT-I EVT-I of 2 piping support brackets PB-5and PB-6. No indications identified.

2011 (2R1 I) EVT-I EVT-I of 2 piping support brackets PB3and PB4. No indications identified.

Core Spray Sparger 1991 (2R01) VT-I Enhanced VT-I (I rnil resolution)- 1995 examnination performed every refueling(2R03) outage on piping and welds per IEB 80-

13. No indications identified.

1997 (2R04) EVT-I EVT-I (1/2 mil resolution) examinationof welds per IEB 80-13 and BWRVIP-18baseline. No indications identified.

1999 (2R05) EVT-I EVT-i examination of welds SIA, SIB,S2aA, S2bA, S2aB, S2bB S4aA, S4bA,S4aB, and S4bB per BWRVIP-18. No

87

Page 89: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

indications identified.

2001 (2R06)

2003 (2R07)

2005 (2R08)

2007 (2R09)

VT-I

EVT-I

VT-I

EVT-I

VT-I

EVT-1

VT-I

EVT- I

VT-I

VT-I examination of welds S3aXXA,S3bXXA, and S3dXXA on nozzles I Athru 65A. No indications identified.

EVT-I examination of welds SIC, SID,S2aC, S2bC, S2aD, S2bD, S4aC, S4bC,S4aD, and S4bD per BWRVIP-18. Noindications identified.

VT- I examination of welds S3aXXB,S3bXXB, and S3dXXB on nozzles lBthru 65B. VT-I examination of weldsS3c4B, S3d4B, S3c62B, and S3d62B.No indications identified.

EVT-I examination of welds SIA, SIB,S2aA, S2bA, S2aB, S2bB S4aA, S4bA,S4aB, and S4bB per BWRVIP-18. Noindications identified.

VT-I examination of welds S3aXXC,S3bXXC, and S3dXXC on nozzles ICthru 65C. No indications identified.

EVT-I examination of welds SIA, SIC,SID, S2aA, S2aC, S2bC, S2aD, S2bD,S4aA, S4bA, S4aB, S4bB, S4aC, S4bC,S4aD, and S4bD per BWRVIP-18. Noindications identified.

VT-I examination of welds S3aXXD,S3bXXD, and S3dXXD on nozzles IDthru 65D. VT-I examination of weldsS3c4D, S3d4D, S3c62D, and S3d62D.No indications identified.

EVT- I of S I A, S 1B, S2aA. S2aB, S2bA,S2bB, S4aA, S4aB, S4bA. and S4bB wasperformed. No indications wereidentified

VT-I examination of welds S3aXXA,S3bXXA, and S3dXXA on nozzles IAthru 65A was performed. No indications

88

Page 90: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2009 (2R 10)

2011 (2R11)

EVT-I

VT-i

EVT-l

VT-I

identified.

EVT-I examnination of welds SIC, SID,S2aC, S2bC, S2aD, S2bD, S4aC, S4bC,S4aD, and S4bD was performed. Noindications identified.

VT-I examination of welds S3aXXB,S3bXXB, and S3dXXB on nozzles I Bthru 65B was performed. VT-Iexamination of welds S3c4B, S3d4B,S3c62B, and S3d62B was performed. Noindications identified.

EVT-I examination of welds SIA, SIB,S2aA, S2aB, S2bA, S2bB, S4aA, S4aB,S4bA, and S4bB was performed. Noindications were identified.

VT-I examnination of welds S3aXXC,S3bXXC, and S3dXXC on nozzles ICthru 65C was performed. No indicationsidentified.

Core Spray SpargerBrackets

1999 (2R05)

2001 (2R06)

2003 (2R07)

2005 (2R08)

2007 (2R09)

VT-I

VT-I

VT-I

VT-I

VT- I

VT-I examination of sparger bracketsSBI, SB2, and SB3. No indicationsidentified.

VT-I examination of sparger bracketsSB4 through SB 12. No indicationsidentified.

VT-I examination of sparger bracketsSBI through SB6. No indicationsidentified.

VT- I examination of sparger bracketsSB7, SB8, and SB9. One indication, aslightly bent sparger bracket, wasidentified on SB8 and was evaluated asacceptable.

VT- I examination of sparger bracketsSB1, SB2, SB3, SB4, SB5. SB6, SB8,SB10, SB 1I, and SB12 was performed.

The middle bracket of SB5 was identified

89

Page 91: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2009 (2R10)

2011 (2RI 1)

VT-I

VT-I

as being offset to the right of the topbracket. This was evaluated asacceptable. SB8 was re-inspected withno change in condition from 2R08.

VT-I examination of sparger bracketsSB7, SB8, SB9, SB 10, SBI 1, and SBI2was performed. One additional scrape onpipe at SB8 bracket was identified andevaluated as acceptable. No otherindications were identified.

VT-I examination of sparger bracketsSB1, SB2, SB3, SB4, SB5, SB6, and SB8was performed.

The middle bracket of SB5 was identifiedwith a small scrape from pipe movement.This was evaluated as acceptable. SB8was re-inspected with no change incondition. No other indications identified.

Top Guide (Rim, etc.) 1991 (2R01)

1993 (2R02)

1995 (2R03)

1999 (2R05)

2005 (2R08)

VT-3

VT-3

VT-I

VT-3

VT-3

VT-3

EVT-1

VT-3 examination of accessible weldsand surfaces. No indications identified.

VT-3 examination of accessible weldsand surfaces. No indications identified.

VT- I examination of accessible weldsand surfaces at cells 14-23, 22-3 1, 22-39,38-23, and 38-47.

VT-3 examination of 32 wedges, bolts,and keepers. No indications identified.

VT-3 examination of surfaces at celllocations 26-27 & 30-31 and VT-3examination of radial restraints, 32wedges, bolts, and keepers. Noindications identified.

VT-3 examination of all four Top GuideC-Clamps. No indications identified.

EVT-1 examination of 5 top guide celllocations: 34-27, 34-51, 42-15, 46-55,and 58-39. These inspections are

2011 (2R11)

________________________ I ± _____________ I

90

Page 92: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

credited as baseline exams for BWRVIP-183. No indications identified.

Core Plate (Rim, etc.) 1995 (2R03) VT-3 VT-3 examnination of accessible weldsand surfaces at core locations 14-23, 22-31, 22-39, 38-23, and 38-47. Noindications identified.

1999 (2R05) VT-3 VT-3 examination of accessible welds &surfaces at core plate location 30-3 1. Noindications identified.

SLC N/A, SLC connects to Core SpraySystem.(See summary of InstrumentPenetrations)

Jet Pump Assembly 1991 (2R01)

1993 (2R02)

1995 (2R03)

1999 (2R05)

2001 (2R06)

VT-3

VT-3

VT-3

VT-3

UT

EVT- I

EVT- I

VT-3 examnination of all 20 Jet Pumpassemblies. No indications identified.

VT-3 examination of all 20 Jet Pumpassemblies. No indications identified.

VT-3 examination of all 20 Jet Pumpassemblies. No indications identified.

VT-3 examnination of all 20 Jet Pumpassemblies. No indications identified.

UT examination of all 20 Jet Pump holddown beamns per BWRVIP-41. Noindications identified.

EVT-I examnination of welds RS-1, RS-2and RS-3 per BWRVIP-41 on Jet Pumps1 - 20. No indications identified.

EVT-I examination of RB-I and RB-2welds on Jet Pumps I - 4.

EVT-I examination of IN-4 and MX-2welds on Jet Pumps 2 - 4.

EVT-1 examination of RS-1, RS-2, RS-6,RS-7, RS-8, and RS-9 welds of JetPumps 3 - 4.

No indications identified.

91

Page 93: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2003 (2R07)

2005 (2R08)

EVT-I

UT

EVT-I

VT-I

EVT-I examination of welds RS-1 andRS-2 welds on Jet Pumps 1, 2, 5, and 6.

EVT-I examination of RS-3 welds on JPs1 -10.

EVT-I examination of welds RS-6, RS-7,RS-8, and RS-9 on Jet Pumps 1, 2, 5, 6,and 11 - 14.

EVT-I examination of IN-4 and MX-2 onJet Pumps 1, 5, 6, and 11 - 14.

No indications identified.

UT examination of all 20 Jet Pump holddown beams (BB-I, BB-2, and BB-3) perBWRVIP-41. Supplemental EVT-1 ofthe BB-2 location on Jet Pumps I and 2due to UT fixture seating issues on the90-degree placement only.No indications identified.

EVT-I examination of RS-3 welds on JetPumps 11 - 14.

EVT-I examination of RB-IPumps 7 through 10.

welds on Jet

EVT-I examination of RB-2 welds on JetPumps 7 and 8.

EVT-I examination of RS-1, RS-2, RS-6,and RS-7 welds of Jet Pumps 7 - 10.

EVT- I examination of IN-4 and MX-2welds of Jet Pumps 7 and 8.

EVT-I examination of RS-8 and RS-9welds of Jet Pumps 1 - 4, 7- 14, and 17-20.

No indications identified.

A VT-I examination of 8 wedges (WD-I

92

Page 94: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

on Jet Pumps 2, 6 - 10, 16, and 18) in theoriginal scope identified significantwedge wear. The scope was expanded toall remaining wedges and setscrew gaps(AS-I and AS-2) were measured on all20 Jet Pumps. Jet Pumps 1, 2, 4, 8, 10 -14, 17, 19, and 20 showed main wedgewear and set screw gaps were identifiedon all Jet Pumps with the exception of JetPump 3, 6, and 7. The largest setscrewgap was 31 mils on Jet Pump 18 (with nowear). For those wedges that hadidentified wear, MX-7, WD-2a/b, RS-8,and RS-9 welds were examined with nofurther degradation identified. Jet Pumpslip joint clamps were installed on all 12Jet Pumps with identified wear. Also, 13Auxiliary wedges were installed wheregaps exceeded the acceptance criteria.

2007 (2R09) EVT-1 EVT-1 inspection was performed on theRS-6 welds of JP 1, 9, 11, 17, and 19 andon the RS-7 welds of JP 2, 4, 8, 12, 14,and 20.

EVT-1 inspection was performed on theRS-8 and RS-9 welds of JP 1/2, 3/4, 7/8,9/10, 11/12, 13/14, 17/18, and 19/20.

EVT- I inspection was performed on RB-2 welds on JP 9/10, and RB-I and RB-2welds on JP 15/16. Also, RB-la and RB-Ic welds on JP 17/18 were examined byEVT-1.

EVT-1 inspection was performed on RS-I and RS-2 welds on JP 17/18.

No indications were identified.

VT-I A VT-I examination of all 20 mainwedges (WD-1) was performed. Themain wedges associated with JP 1, 12, 17,and 20 were replaced with an oversizedwedge and the corresponding restrainerbrackets were resurfaced. 10 of 12 jet

93

Page 95: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

pumps with previously identified wedgewear from 2R08 showed minor additionalwedge wear in 2R09 even though a slipjoint clamp was installed. JP 9 mainwedge was identified with new wedgewear (low) but had no wedge wearidentified in the previous cycle.

All setscrews were inspected for gaps,except for JP 14. Gaps were identified onthe vessel side of JP 4, 5, 7, 9, and 20with the largest gap being 0.030 inch (JP7).

For those wedges that had newlyidentified wedge wear (JP 9) or additionalwedge wear (JP 1,2,4,8, 11, 12, 14, 17,19, and 20), the MX-7, WD-2a/b, RS-6 orRS-7, RS-8 and RS-9 welds, asapplicable, were examined as requiredexpanded scope. Minor wedge rod wearwas identified on JP 2, 4, 9, 11, and 19.No other indications were identified.

VT-3 A VT-3 examination was performed onall previously install Auxiliary Wedges(AW) and Slip Joint Clamps (SJC).

Minor wear was identified on the AWinstalled on JP 1, 10, 11, and 13.

Aux wedges were removed and notreinstalled on JP I and 17.

Aux wedges were installed on both thevessel side and shroud side of JP 2, 4, 11,14, and 19. One aux wedge was installedon the vessel side of JP 7 and 9, and onewas installed on the shroud side of JP 12after reassembly identified a 0.043 inchgap.

Jet Pump SJC were inspected by VT-3with no indications and were installed onJP 3, 5, 6, 7, 9, 15, 16, and 18. All 20 jetpumps now have a SJC installed.

94

Page 96: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2009 (2R10) EVT-I EVT-I inspection was performed on theRS-3 welds of JP 15/16, 17/18, and19/20.

EVT-I inspection was performed on theRS-6 welds ofJP 3 and 15 and on the RS-7 welds of JP 4, 6, 12, 14, 16, 18, and 20.

EVT-I inspection was performed on theRS-8 and RS-9 welds of JP 3/4, 5/6,11/12, 13/14, 15/16, 17/18, and 19/20.

EVT- I inspection was performed on theIN-4 and MX-2 welds of JP 9, 10, 15, 16,17, 18, 19, and 20.

EVT-1 inspection was performed on RB-2 welds on JP 17/18 and 19/20, and RB-Iwelds on JP 19/20. Also, RB-Ib and RB-Id welds on JP 17/18 were EVT-1examined.

EVT-I inspection was performed on RS-1 and RS-2 welds on JP 19/20.

No indications were identified.

VT-I A VT-I examination of all 20 mainwedges (WD-1) was performed. Themain wedges associated with JP 2, 8, 14,and 19 were replaced with a standardreplacement wedge (wider than original)and the corresponding restrainer bracketshad repair plates installed to increase thewedge bearing surface. In addition,restrainer bracket repair plates were alsoinstalled on JP 12 to raise the height ofthe main wedge to an acceptable level.

JP 4 and 14 had previously identifiedwedge wear from 2R09 and showedminor additional wear in 2RI0. JP 3, 6,and 18 were identified with new wedgewear but had no wedge wear identified inthe previous cycle. JP 1, 12, and 20 had

95

Page 97: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

main wedge movement identifiedbetween 2R09 and 2R10.

All set screws were inspected for gaps.Gaps were identified on the vessel side(VS) ofJP 3 and JP 5 of 0.012 inch. Oneauxiliary wedge was required to beinstalled on the VS setscrew of JP 3.

For those wedges that had new oradditional wedge wear or movement (JP3, 4, 6, 12, 14, 18, and 20), the MX-7,WD-2a/b, RS-6 or RS-7, RS-8 and RS-9welds, as applicable, were examined asrequired expanded scope.

No change in minor wedge rod wear onJP 2, 4, 9, and 14. New wedge rod wearidentified on JP 3, 6, 12, 18, and 20.Minor additional rod wear identified onJP II and 19.

Slip joint clamps (SJC) were inspected onall 20 jet pumps. JP 1, 4, and 11 SJCswere identified with wear of the centerstrut into the diffuser collar. JP 1 and 11SJCs were repositioned during 2R]0. JP7 SJC was identified as being improperlyinstalled but acceptable. JP 12 SJC wasidentified as having moved during theprevious cycle but was acceptable as-is.

No other indications were identified.

VT-3 VT-3 examination was performed on JP1, 12, 17, and 20 hold down beams afterone cycle of installation as a post-modexam.

VT-3 examination was performed on thefollowing vessel side (VS) or shroud side(SS) auxiliary wedges either as a post-mod exam or as part of expanded scopedue to wedge wear: JP 2 VS, JP 2 SS, JP4 VS, JP 4 SS, JP 7 VS. JP 8 VS, JP 8 SS,JP 9 VS, JP 10 VS, JP 11 VS, JP I1 SS,

96

Page 98: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

JP 12 SS, JP 13 VS, JP 14 VS, JP 14 SS,JP 18 VS, JP 19 VS, and JP 19 SS. Nochange in auxiliary wedge wear wasidentified on JP 10 VS or JP 13 VS.Movement was identified on JP 11 VSand JP 11 SS auxiliary wedges.

No other indications were identified.

UT UT examination of 16 of 20 Jet Pumphold down beams (BB-1, BB-2, and BB-3) was performed. The remaining 4beams are of the group 3 design and notyet required to be examined. Noindications identified.

2011 (2R1I) EVT-I EVT-I examination was performed on all10 Jet Pump RS-9 welds. One indicationwas identified on the RS-9 weld of JP 1/2riser. The indication was 0.43 inches andwas evaluated to be acceptable.

EVT-I exam on IN-4 welds of JP I and 2.

EVT-I exam on RB-I and RB-2 welds onJPI/2 riser.

EVT-I exam of RS-1, RS-2, RS-3, RS-6,RS-7, and RS-8 welds on Jet Pump 1/2riser.

EVT-I exam of RS-8 weld on JP 7/8 and9/10 risers.

EVT- I exam of RS-I and RS-2 onJP15/16 riser.

No indications identified, except onenoted above.

VT-I A VT-I examination of all 20 mainwedges (WD-1) was performed. Themain wedges associated with JP 4, 9, 10,and I'3 were replaced with a standardreplacement wedge (wider than original)and the corresponding restrainer brackets

97

Page 99: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

had repair plates installed to increase thewedge bearing surface. In addition,restrainer bracket repair plates were alsoinstalled on JP I and JP 17 to restore therestrainer pad bearing surface contact.

No new main wedge wear was identified.No change in previous wedge wear on JP2, 3, 4, 6,10, 11, 17, 18, and20. JP 1, 9,13, and 19 had -main wedge movementidentified in 2R1 1.

All unmodified setscrews were inspectedfor gaps. A gap of 0.014 inch wasidentified on the vessel side (VS) of JP 5.One auxiliary wedge was required to beinstalled on the VS setscrew of JP 6 torepair a 0.022 inch gap.

No change in minor wedge rod wear onJP 3, 6, 11, 18, and 20. New wedge rodwear identified on JP 1, 2, 5, 16, and 19.Minor additional rod wear identified onJP 4, 12, and 13.

Slip joint clamps (SJC) were inspected onall 5 jet pumps: JP 1,4, 7, 11, and 12. Nochange in previous conditions noted.

No other indications were identified.

VT-3 VT-3 examination was performed on thefollowing vessel side (VS) or shroud side(SS) auxiliary wedges as part of re-inspection requirements: JP 2 VS, JP 2SS, JP 3 VS, JP 8 VS, JP 8 SS, JP 10 VS,JP II VS, JP II SS, JP 12 SS, JP 13 VS,JP 14 VS, JP 14 SS, JP 19 VS, and JP 19SS. No change in auxiliary wedge wearwas identified on JP 10 VS or JP 13 VS.Minor movement noted in JP 11 VS auxwedge.

VT-3 examination also performed onrestrainer bracket plate hardware afterone cycle of operation on JP 2, 8, 12, 14,

98

Page 100: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

and 19.

No other indications were identified.

Jet Pump Diffuser 1991 (2R01)

1993 (2R02)

1995 (2R03)

1999 (2R05)

2001 (2R06)

2003 (2R07)

2005 (2R08)

2007 (2R09)

2009 (2R10)

2011 (2Rl1)

VT- 3

VT- 3

VT- 3

VT-3

EVT-I

EVT-I

EVT- 1

EVT-I

EVT- 1

UT

UT

VT-3 examination of all 20 Jet Pumpassemblies. No indications identified.

VT-3 examination of all 20 Jet Pumpassemblies. No indications identified.

VT-3 examination of all 20 Jet Pumpassemblies. No indications identified.

VT-3 examination of all 20 Jet Pumpassemblies. No indications identified.

EVT-l examination of DF-1, DF-2, AD-1, and AD-2 welds on Jet Pumps 2 - 4.No indications identified.

EVT-I examination of DF-1, DF-2, AD-1, and AD-2 welds on Jet Pumps 1, 5, 6,and 11 - 14. No indications identified.

EVT-I examination of DF-1, DF-2, AD-I, and AD-2 welds on Jet Pumps 7 and 8.No indications identified.

EVT-l examination of DF-1, DF-2, AD-1, and AD-2 welds on JP 9, 10, and 15.No indications identified.

EVT-I inspection was performed on theAD-I, AD-2, DF-l, and DF-2 welds of JP16, 18, and 19. No indications identified

EVT-l inspection was performed on theDF-I and DF-2 welds of JP 17 and DF-Ionly of JP 20. No indications identified.

UT examination was performed on JP 17AD-I and AD-2 welds, as well as JP 20AD-I, AD-2, and DF-2 welds. Noindications identified.

UT examination was performed on all 20jet pumps at weld locations AD-I, AD-2,

99

Page 101: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

DF- 1, DF-2, and MX-2, except for fourDF-I welds on JP 3, 8, 14, and 18. Thesefour locations could not be UT examineddue to vertical weld crown height issueson these jet pump diffusers. Noindications identified.

I I -t

CRD Guide Tube 1991 (2R01)

1993 (2R02)

1995 (2R03)

1999 (2R05)

2003 (2R07)

2007 (2R09)

2009 (2R10)

VT-3

VT-3

VT-3

VT-3

EVT- 1/VT-3

EVT- 1/VT-3

EVT- I/VT-

VT-3 examination of control rodassemblies at core positions 22-14 and14-31. No indications identified.

VT-3 examination of control rodassembly at core location 34-07. Minorscratches noted.Acceptable for continued service.

VT-3 PSI examination of replacementCRDs at core locations 06-19, 10-27, 10-47, 14-39, 18-03, 18-15, 18-55, 22-35,22-39, 30-51, 34-47, 38-15, 38-27, 38-39,42-43, 46-39, 46-43, 50-15, and 54-35.No indications identified.

VT-3 examination of CRD guide tubeaccessible surfaces of 26-27 from ID and30-31 from OD. No indicationsidentified.

CRD guide tube welds were examined atcore locations 06-19, 06-43, 18-43, 22-31, 30-23, 30-39, 38-31, 42-19, 42-43,and 54-43. This includes a VT-3 ofCRGT-I welds, an EVT-I of CRGT-2and CRGT-3 welds, and a VT-3 ofCR/FS/GT - ARPIN-I welds for theabove locations. No indicationsidentified.

CRD guide tube welds were examined atcore locations 18-27, 18-35, 26-27, 42-27, and 42-35. This includes an EVT-Iof CRGT-2 and CRGT-3 welds. A VT-3of the CRGT-I and ARPIN-I welds wascredited via CRB removal/re installationprocedure. No indications identified.

CRD guide tube welds were examined at

100

Page 102: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

3 core locations 06-31, 18-19, 26-43, and34-43. This includes an EVT-I ofCRGT-2 and CRGT-3 welds. A VT-3 ofthe CRGT-I and ARPIN-1 welds wascredited via CRB removal/reinstallation_procedure. No indications identified.

CRD Stub Tube 1993 (2R02) VT-3 VT-3 examination of stub tube to vesselweld and stub tube to housing weld atazimuth 300 deg. No indicationsidentified.

1999 (2R05) VT-3 VT-3 examination at core location 30-3 1,30-35, 26-31 & 34-3 1. No indicationsidentified.

2007 (2R09) Best effort Best effort VT-I / VT-3 of stub tube toVT-I / VT- vessel welds and stub tube to housing3 welds at core locations 02-39, 02-43, 06-

47, 10-11, 14-07, 14-11, 38-59, 42-59,and 46-55 were examined via accessthrough the disassembly of Jet Pumps 1,12, and 17. No indications wereidentified.

In-Core Housing 1999 (2R05) VT-3 VT-3 examination of housings, guidetubes, stabilizers & housing to RPVwelds at core locations 24-29 & 32-29.No indications identified.

Dry Tube 1995 (2R03) VT-I VT-I examination of accessible portionsof upper 2 feet of dry tube at corelocations 16-21, 40-21, 40-45, 24-29, 24-37, and 32-37. No indications identified.

1999 (2R05) VT-I VT-i examination of accessible portionsof upper 2 feet of dry tube at corelocations 24-29 & 32-29. No indicationsidentified.

2005 (2R08) VT-I VT-I examination of accessible portionsof upper 2 feet of dry tube at corelocations 16-13, 16-21, 16-45, 24-29, 40-21, and 48-13. No indications identified.

2007 (2R09) Replaced IRM 24-29, 24-37, 32-39, 48-53, andSRM 16-45, 40-21 were replaced withnew universal style dry tubes. The

101

Page 103: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

remaining 6 are scheduled forreplacement in 2009 (2R10).

2009 (2R10) Replaced IRM 16-13, 16-53, 32-37, 48-13, andSRM 16-21, 40-45 were replaced withnew universal style dry tubes.

Instrument 1991 (2R01) VT-3 VT-3 examination of interior attachmentPenetrations of instrument nozzles NI IA, NI I B, and

N12A through N12D. No indicationsidentified.

PT PT examination performed on allinstrument nozzle to safe end welds onceper interval, per Section XI (IncludesN 10 Core Differential Pressurepenetration). No indications identified.

1999 (2R05) UT/PT UT & PT examination of jet pumpinstrument nozzle to safe end N8A &N8B. No indications identified.

2009 (2R10) VT-2 VT-2 examinations of instrument nozzlesNI IA-B, N12A-D, and NI6A-D wereperformed during the system leakage test.

2011 (2R1 1) VT-2 VT-2 examinations of instrument nozzlesNI IA-B, N12A-D, and NI6A-D wereperformed during the system leakage test.

Vessel ID Brackets 1991 (2R01) VT-I/VT-3 VT-I or VT-3 performed on all IDbracket welds once every other outageper Section XI. No indications identified.

1993 (2R02) VT-I/VT-3 VT-I or VT-3 performed on all IDbracket welds once every other outageper Section XI. No indications identified.

1995 (2R03) VT-I/VT-3 VT-I or VT-3 performed on all IDbracket welds once every other outageper Section XI. No indications identified.

1997 (2R04) VT-I/VT-3 VT-I or VT-3 performed on all IDbracket welds once every other outageper Section XI. No indications identified.

1999 (2R05) VT-3 VT-3 examination of feedwater sparger

102

Page 104: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2001 (2R06) I EVT-1

2003 (2R07) EVT-1

VT-I

brackets (5, 55, 65, 115, 125, 175, 185,235, 245, 295, 305 & 355 DEG),including bracket weld to RPV. Noindications identified.

EVT-1 examination of feedwater spargerbrackets at 5 degrees and 175 degrees,and core spray sparger brackets at 274.5degrees and 345 degrees. No indicationsidentified.

EVT- 1 examination of feedwater spargerbrackets at 65 degrees and 115 degrees;core spray sparger brackets at 165degrees, 195 degrees, and 247.5 degrees;steam dryer support brackets at 4 degreesand 94 degrees; and jet pump riser bracearm attachment welds at jet pumps 1/2,3/4, 5/6, 11/12, and 13/14. Noindications identified.

VT-I examination of the 30 degreesurveillance sample holder attachment tovessel weld. No indications identified.

EVT-1 examination of feedwater spargerbrackets at 55 degrees and 125 degrees;core spray sparger brackets at 15 degrees,85.5 degrees, and 112.5 degrees; and jetpump riser brace arm attachment welds atjet pumps 7/8 and 9/10. No indicationsidentified.

VT-3 examination of guide rod bracketattachment welds at 0 degrees and 180degrees. No indications identified.

EVT-1 examination was performed forcore spray piping brackets at 274.5 Az.and 345 Az, feedwater sparger endbrackets at 185 Az. and 235 Az., and jetpump riser brace arm attachment welds atJP 15/16. No indications were identified.

VT-I examination was also performed onjet pump riser brace arm attachment

2005 (2R08) EVT-1

VT-3

2007 (2R09) EVT-1

VT-I

103

Page 105: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

VT-3

2009 (2R10) EVT-I

welds at JP 15/16 (for Code credit), andat the upper and lower surveillancespecimen brackets at 120 Az. and 300Az.

VT-3 examination was also performed oncore spray piping brackets at 274.5 Az.and 345 Az, and feedwater sparger endbrackets at 185 Az. and 235 Az.(for Codecredit). No indications were identified.

EVT- 1 examination was performed forcore spray piping brackets at 1950 and247.5', feedwater sparger end brackets at2450, 2950, 3050, and 3550, jet pumpriser brace arm attachment welds at JP17/18 and 19/20, and steam dryer supportbrackets at 1840 and 2740. Noindications were identified.

EVT-I examination was performed forcore spray piping brackets at H12.50 and1650, feedwater sparger end brackets at50, 550, 650, and 1150, and jet pump riserbrace arm attachment welds at JP 1/2 and11/12. No indications were identified.

VT-I exam of the upper attachment weldand VT-3 of lower attachment weld forthe 30 deg surveillance specimen holder.No indications identified.

2011 (2R11) 1 EVT-1

VT-I /VT-3

LPCI Coupling 1991 (2R01)

1995 (2R03)

1999 (2R05)

2001 (2R06)

2003 (2R07)

VT-3

VT-3

VT-3

EVT-l

EVT-1

VT-3 examination of all 4 couplings.No indications identified.

VT-3 examination of all 4 couplings.No indications identified.

VT-3 examination of all 4 couplings.No indications identified.

EVT-I examination of'C' and 'D' LPCI45-3b welds. No indications identified.

EVT-I examination of'A' and 'B' LPCI45-3b welds and EVT-I examination of

104

Page 106: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2005 (2R08)

2007 (2R09)

2009 (2R10)

2011 (2R11)

EVT-I

VT-3

VT-I

EVT-1

VT-3

VT-I

EVT-I

VT-3

VT-I

EVT- I

VT-3

'A', 'B', 'C', and 'D' LPCI 45-12 welds.No indications identified.

EVT-I examination of'A', 'B', 'C', and 'D'LPCI 45-3b and 45-12 welds. Noindications identified.

VT-3 examination of'D' LPCI 45-6athrough 45-6d welds. No indicationsidentified.

VT-I examnination of'D' LPCI 45-8athrough 45-8d welds. No indicationsidentified.

EVT-I examination of'C' and 'D' LPCIcouplings (45-3b and 45-12) welds wasperformed. No indications identified.

VT-3 examnination of'C' LPCI 45-6athrough 45-6d welds. No indicationsidentified.

VT-I examination of'C' LPCI 45-8athrough 45-8d welds. No indicationsidentified.

EVT-I examnination of'B' LPCI coupling(45-3b and 45-12) welds was performed.No indications identified.

VT-3 examnination of'B' LPCI 45-6athrough 45-6d welds. No indicationsidentified.

VT-I examination of'B' LPCI 45-8athrough 45-8d welds. No indicationsidentified.

EVT-I exam of'A' LPCI coupling (45-3band 45-12) welds was performed. Noindications identified.

VT-3 exam of'A' LPCI 45-6a through45-6d welds. No indications identified.

105

Page 107: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

VT-1 VT-I exam of'A' LPCI 45-8a through45-8d welds. No indications identified.

Steam Dryer 1995 (2R03) VT-3

1997 (2R04) I UT

1999 (2R05)

2001 (2R06)

2003 (2R07)

2005 (2R08)

VT-3

VT-3

VT-I

VT-3

VT-I

VT-I

VT-3 examination of overall Steam Dryerassembly. Linear indications wereidentified in the support ring during theVT-I of the adjacent drain channel welds.These indications were accepted byengineering evaluation.

UT examination performed to determinebaseline crack depth of indicationsobserved visually between 0 degreeazimuth and 41 degree lifting eye during2R03. Results show crack to be 0.384inches in depth. These indications wereaccepted by engineering evaluation.

VT-3 examination of overall Steam Dryerassembly. No indications identified.

VT-3 examnination of overall Steam Dryerassembly. Examination revealedcracking in uipper support ring at 135degree and 3 15 degree lifting lugs. Theseindications were accepted by engineeringevaluation.

VT-I examnination of Steam Dryer DrainChannel welds. No indicationsidentified.

VT-3 examination of overall Steam Dryerassembly. No indications identified.

VT- I examination of Steam Dryer DrainChannel welds. No indicationsidentified.

VT- I examination of Steam Dryer DrainChannel welds. VT-i examination ofSteam Dryer Hood Bank #1 and Bank #6seam welds. VT-I examnination of SteamDryer Cover Plate welds at 90 degree and270 degree. No indications identified.

Performed Best Effort VT-I inspections2007 (2R09) I Best Effort

106

Page 108: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

VT-I of bottom hood seam welds (SDBH l a-b,2a-b, 3a-b, 4a-b, 5a-b, 6a-b), end bankwelds (SDEB I a-d, 2a-d, 3a-d, 4a-d, 5a-d, 6a-d), guide bracket at 0 Az (SDGB),hood vertical seam welds (SDHS 2b-d,3b-d, 4b-d, 5b-d), hood reinforcementwelds (SDHSR 2a-d, 3a-d, 4a-d, 5a-d),welds on all four lifting rods (SDLRx Ia-c, 2a-b, 3a-b, 4a-b, CP, LE, TW), manway welds (SDMW a-d), plenumpartition welds (SDPP 2a-b, 3a-b, 4a-b,5a-b), support ring (SDSR), and tie bars(SDTB 1-5, 8-9, 17, 22-24).

Minor IGSCC identified on the supportring and evaluated as acceptable. A smallpiece of raised metal was identified onSDTB 3 and evaluated to be acceptable.One indication approximately 1.5 inchesin length was identified and evaluated asacceptable on SDHS4c weld near theintersection of the bottom of the hoodseam and the horizontal joining plate.

No other indications identified.

2009 (2R10) Best Effort Performed Best Effort VT-I inspectionsVT-I of guide bracket at 180 Az (SDGB), hood

vertical seam welds (SDHS Ia-d, 2b-d,4c), hood reinforcement welds (SDHSR2a-d), plenum partition welds (SDPP 2a-b), top horizontal welds (SDTH 1, 6),drain channel welds (SDDC I a-c), coverplate welds (SDCP 7a-b), and tie bars(SDTB 3, 6, 7, 10-16, 18-21, 25-37).

No change noted in IGSCC identified onthe support ring during the cover plateexam or on the small piece of raisedmetal identified on SDTB03.

One of two tack welds was identified ascracked on the 221.5 Az. lifting rodbetween the lifting rod and the eye duringa VT-I examination performed for thesite heavy loads program (non-BWRVIP

107

Page 109: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2011 (2Rl1) VT-I

exam). This indication was evaluated asacceptable for continued operation.

One indication on SDHS4c weld near theintersection of the bottom of the hoodseam and the horizontal joining plateshowed minimal growth of 0.2 inches.This indication was evaluated asacceptable for another cycle of operation.

No other indications identified.

Performed VT- 1-89 inspections of hoodvertical seam welds (SDHS 2c, 3b-d, 4b-d, 5c), hood reinforcement welds(SDHSR 3a-d, 4a-d), plenum partitionwelds (SDPP 3a-b, 4a-b), bottomhorizontal welds (SDBH la-b, 2a-b),drain channel welds (SDDC 2a-c), coverplate welds (SDCP I a-b), end bank welds(SDEB I a-d, 2a-d), support ring (SDSR),lifting rod A (SDLRA all welds), and tiebar (SDTB 3).

No change noted to previous support ringindications, but two new indicationsidentified and evaluated as acceptable.No change noted in previous tie barindication (SDTB 3), hood seamindication (SDHS4c), or lifting rod tackweld indication (SDLRCTW).

One new indication identified on hoodseam (SDHS3c). Indication is 3/4 inchesin length and was evaluated asacceptable. Two new indicationsidentified on end bank welds. SDEB2ahas one indication approx. 1.5 inches inlength and SDEB Id has one indicationapprox. 3 inches in length. Both wereevaluated as acceptable.

No other indications identified.

DM Welds - 2007 (2R09) UT 2 welds inspected: PDI qualified,BWRVIP-75-A Cat. automated exams, no flaws identified, noA repairs

108

Page 110: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

DM Welds -

BWRVIP-75-A Cat.B

2007 (2R09)

2009 (2R10)

2011 (2R11)

UT

UT

UT

2 welds inspected with 82/182: PDIqualified, automated exams, no flawsidentified, no repairs

2 welds inspected with 82/182: PDIqualified, manual exams, no flawsidentified, no repairs

0 welds inspected with 82/182.2 welds inspected without 82/182: PDIqualified, manual exams, no flawsidentified, no repairs

109

Page 111: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Reactor Internals Inspection History

Plant: Monticello

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Inspection Results, Repairs,

Inspection Used Replacements, Reinspections

Core Shroud 1994-1996 UT andVT-I

Baseline per BWRVIP-01 andreinspected per BWRVIP-07. Indicationsin several circumferential welds asidentified below:HI 17% flawed over 307.6" total scan

length.H2 1% flawed over 287.7" total scan

length.H3 28% flawed over 263" total scan

length.H4 6% flawed over 289.1" total scan

length.H5 0% flawed over 298.4" total scan

length.H6 4.5% flawed over 298.4" total scan

length.H7 0% flawed over 291.7" total scan

length.Note: 1. All flaws identified were less

than 1/2 T deep.2. Scan coverage for each weld

was greater than 50%.3. Differences in inspection

methodology did not permit arigorous correlation of the1994 and 1996 data.

4. Full structural margins existon all welds.

VT-I of accessible vertical welds & ringsegment welds. Minor indicationidentified on ring segment weld @ 73deg azimuth between H5 and H6.Visually examined 2 feet of the followingvertical welds; V3, V4, V5, and V6.Minor indications were observed on V3and V6.

Baseline per BWRVIP-0I and2005 UT and

110

Page 112: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

VT-I reinspected per BWRVIP-76. Indicationsin several circumferential welds asidentified below:H1 75.51% Inspected, 16.21% Flawed

H2 59.26% Inspected, 6.02% Flawed

H3 71.56% Inspected, 27.19% Flawed

H4Upper 68.46% Inspected, 8.33% FlawedLower 68.46% Inspected, 5.02% Flawed

H5 68.46% Inspected, 0.5% FlawedH6 68.88% inspected, 2.52% FlawedH7 68.88% Inspected, 0% Flawed

V2CW 63.3% Inspected, 0% flawedCCW 83.6% Inspected, 23.74% flawed

V3CCW 42.5% Inspected, 0% Flawed

V4EVT-1: Top 18" to H3, No indications

2007 EVT-I Visual inspection of the v4 and v3 fromthe shroud ID

Shroud Support 1994-1996 VT-I & VT of H8 and H9 from the annulus haveVT-3 been performed. No reportable

indications to date.VT of access hole covers, performedevery other outage per the IVVI program.No indications have been reported todate.In 1984, two CRD guide tubes wereremoved which allowed access below thecore plate. A VT-3 inspection wasperformed on the shroud support legs.No problems were observed.Note: Monticello has an oval shaped

access hole cover. This design issuperior to the round design inthat it provides more shroudsupport plate material between the

III

Page 113: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

access hole cover welds and thevessel wall.

2000 EVT-1 Core Plate Support Ring at 650, 1850, and3050

EVT-I H8 and H9 Welds at Manway CoverAreas

VT-I Access Hole Cover Plate Welds at 0'and 1800

VT-3 Shroud Support Legs (14)

* Crack indication in the 2100 shroudsupport leg to shroud supportcylinder weld. The majority of theindication appears to be containedwithin the weld material, with thelower tip extending into the shroudsupport leg base material.

2001 VT-3 Re-inspection of the 210 degree locationof the shroud support leg. No change incondition.

EVT-1 Core Plate support ring at 65, 185, and305 degrees. No indications.

VT- I Access hole cover plate welds at 0 and180 degrees. No reportable indications.

2003 VT-3 Re-inspection of the 210 degree locationof the shroud support leg. No change incondition.

2005 EVT-1 H8 and H9 from 338 degree to 22 degreeand 158 degree to 202 degree, NRI

VT-3 Accessible areas of ledge for AMSEsection Xl, NRI

2009 VT-3 Previously discovered indication on H 10weld at210 degrees was examined and nochange was found. However a new

112

Page 114: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

indication was discovered on the 200degree side of the H10 weld at 210degrees. This discovery promptedfurther inspection of H 10, H 11 and H 12welds on all 14 support legs.

New indications were discovered on H110welds on 12out of 14 support legs. The legs at 90degrees and 350did not have any indications. The crackindications were confined to H10 weldsonly.

All indications that could be furtherexamined were only in the weld materialand not through-wall.

2011 VT-3 Re-examined previously recordedindications on the H 10 weld at thefollowing locations: 100, 300, 60', 1200,1500, 1700, 190', 2100, 2400, 2700, and3000. No change was observed in theindications. Three new indications werediscovered on the H 10 weld at the 90',3300 and 3500 locations. All newindications were confined to the H 10welds and did not go through wall.

VT-3 Examined accessible areas of both topand underside of shroud support plateand H8 and H9 welds. Duringinspections of the previously recordedindications on the VI 10 welds, newrelevant indications were also discoveredon the H8 and H9 welds on the undersideof the shroud support plate. Noindications were discovered on the topside of the H8 and H9 welds or thesupport plate. Examined all shroudsupport legs at the following locations:10, 300, 600, 900, 1200, 1500, 1700,1900, 2100, 2400, 2700, and 3000, 3300and 3500.

EVT- I H8 and H9 weld at the 0 and 180 de2ree

113

Page 115: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

locations.

Additional Inspection of low alloy basemetal described in "Other Exams"Section

Core Spray Piping 1980's to1996

1998

VT-I

UT

IEB 80-13 of piping and welds inannulus. No indications reportedvisually.UT of slip joint welds per BWRVIP-18in 1996 identified one indication on theID of the B core spray pipe.Note: Although the flaw was not

through-wall, the evaluationconservatively treated the flaw asthrough wall. As a result, theevaluation determined that theoperability of the core spraysystem was not impaired.Therefore no repair is scheduledat this time.

UT of the following welds in 1998 wereperformed per the BWRVIP-18guidelines:

13.5 deg location

P4A, 42% coverageP4B, 43% coverageP5, 100% coverageP6, 100% coverageP7, 64% coverageP4D, 54% coverage

166.5 deg location

P4A, 41% coverageP4B, 72% coverage

193.5 deg location

P4A, 26% coverageP4B, 43% coverage

346.5 deg location

114

Page 116: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

T T T

P4A, 44% coverageP4B, 62% coverage

Flaws identified during the 1998 RFOinspection were all located at the 13.5deg location and are listed as follows:Weld/ I Start Location IFlaw # 1 Start End I Flaw LengthP5/I 313 013510 1.83"P6/i 343 0 370 2.78"P6/2 55 0 740 0.97"P6/3 87 0 980 0.54"P6/4 295 0 3270 1.65"

P6/5 199012790 4.19"P6/6 1120 1450 1.71"P6/7 175 0 1870 0.60"

NOTE: Flaws I and 4 on P6 are the onlyflaws that appear to be throughwall.Flaws 1,2,3,8 on P6 are on thetop side of the weld and flaws4,5,6,7,9 on P6 are on thebottom side of the weld.

EVT-I An enhanced visual examnination wasperformed on all target welds that werenot UT examined. No reportableindications were identified visually.

2000 VT-1 Header Piping Brackets to Vessel Wall

VT-I Bracket Bolt Head Tack Welds

VT-3 General Condition of Brackets

VT-I Clamp Assemblies on Tee Box Junctions

EVT-I Flaw at 900 Tee Box for Crack Extension

EVT-1 Welds P5, P6, P7, P8a, P8b on all 4Downcomers, and P4a, P4b, P4c, P4d on"A" Downcomer (130)

The crack indication in the 900 core spray

115

Page 117: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

tee box to header weld was estimated tobe five inches in length during the RF 18Refuel Outage. Image overlayingtechniques along with pixel countingsoftware were used to measure theindication during the RFI9 RefuelOutage. These more reliable methods ofmeasurement found the indication to be2.25 inches in length.

2001 VT-I Header piping to wall brackets.

VT-I Bracket Bolt Tack Welds

VT-3 General condition of Brackets

EVT-1 Flaw at 90 degrees tee box for crackextension. No change.

EVT-I Welds P5,P6,P7,P8a, P8b on all 4downcorners. P4 (a-d) on "B"downcomer". No indications

2003 UT UT of the following welds in 1998 wereperformed per the BWRVIP-18guidelines:

13.5 deg location

P5, 100% coverageP6, 100% coverage

166.5 deg location

P5, 100% coverage

Flaws identified during the 2003 RFOinspection were all located at the 13.5deg location and are listed as follows:Weld/ I Start Location IFlaw # I Start End I Flaw LengthP5/1 312.5 1344.10 1.53"P6/I 54.9 ° 73.00 0.96"P6/2 86.5 ° 199.90 0.71"P6/3 106.60 1 145.6- 2.06"P6/4 153.7 0 1269.60 6.13"

116

Page 118: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

P6/5 286.7 0 1317.4- 1.62"P6/6 347.7 ° 144.30 2.99"

NOTE: Flaws 1,2,3,6 on P6 are on thetop side of the weld and flaws4,5 on P6 are on the bottom sideof the weld.

An enhanced visual examination wasperformed on all target welds that werenot UT examined. No reportableindications were identified visually.

EVT-l of P4(a-d) of"C" leg(193Degrees). All P5, P6, P7, P8(a,b). Noindications.

VT Visual inspection of core spray T-BoxRepair. No change in previous indicationat 90 degrees.

2005 VT EVT-I of P4(a-d) of"D" leg(13Degrees). All P5, P6, P7, P8(a,b) Welds.No indications.

Visual inspection of core spray T-BoxRepair. No change in previous indicationat 90 degrees.

2007 VT EVT-I of P4(a-d) of"A" leg(193Degrees). All P5, P6, P7, P8(a,b) Welds.No indications.

Visual inspection of core spray T-BoxRepair. No change in previous indicationat 90 degrees.

2009 EVT-I PI and P2 at 90 and 270 degrees. P3A-DP4Ba-d, P5A-D, P6A-D, P7A-D,P8Aa-b, P8Ba-b, P8Ca-b, P8Da-b. Pipingbrackets at 30, 150, 210 and 330.

VT-3 Header repair clamp. Piping brackets at

30,150, 210, 330.

No change to previously identified

117

Page 119: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2011 EVT-1

VT-I

indication in header repair clamp. Nonew indications.

Examinations: P1 and P2 welds at the 90and 270 degree locations. P3 (A thru D)at 800, 1000, 2600, 2800 locations. P4-C(a-d) at 1930, P5, P6, P7 and P8 (a-b) at13°, 1660, 1930, 3460 locations. No newindications.

The previously recorded indication thatwas repaired with the repair clamp at theP3A weld at the 900 location was alsoexamined and no change was noted.

The pipe clamp assemblies at the 900 and270' locations were also examined. Noindications were observed.

+ I.

Core Spray Sparger 1980's topresent

2000

2001

VT-I

EVT- I

VT-I

EVT- 1

VT-3

EVT- I

IEB 80-13 of welds on sparger. Duringthe 1993 refueling outage, acircumferential crack indication on thecore spray loop B header where thepiping and the T-box meet wasidentified. A repair was installed duringthe 1994 outage. The repair is inspectedevery refueling outage. No problemshave been identified to date.

Tee Box Cover Plate (S I), SpargerBranch Welds to Tee Box (S2), SpargerEnd Caps (S4)

Mounting Brackets and End Brackets(SB)

Nozzle Welds (S3a, S3b)

Spargers9 No reportable indications identified.

Tee box cover plate (S 1), Sparger Branchwelds to tee box (S2), Sparger End caps(S4). "B" and "C" spargers. Noindications.

118

Page 120: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

VT-I Brackets on "B" and "C" Spargers. Noindications.

EVT-I Nozzle welds S3a and S3b on B and C.No indications.

VT-3 Spargers B and C. No indications.

2003 EVT- I Upper S4-1 @272', Upper S2-1 @344',Upper S1@346°, Upper S2-2@348°,Upper S4-2@87°, Lower S4-1 @2720,

Lower S2-1@1 A °, Lower S'@ 13',Lower S2-2@15', Lower S4-2@ 870:No indications found.

VT-I Upper & lower S3(a&b) from 272' to870, Upper & lower S3c-1 &-2, 272' SB,306° SB, 346° SB, 130 SB, 54- SB, 87°SB: No indications

2005 Upper S4-2@267°, Upper S2-2@195',Upper S1@193', Upper S2-1@a191,Upper S4-1 @93', Lower S4-2@267',Lower S2-2@ 168', Lower S I@ 166',Lower S2-I@164', Lower S4-I@ 930:No indications found.

Upper & lower S3(a&b) from 930 to2670, Upper & lower $3c-l &-2, 930 to267 degree

930 SB, 1260 SB, 1660 SB, 1930 SB,

2340 SB, 2670 SB: No indications

2007 EVT- I Upper S4-1 @272°, Upper S2-1 @c344°,Upper S 1 @346', Upper S2-2@348°,Upper S4-2@87°, Lower S4- I @272',Lower S2-1@11F, Lower SI@ 130,Lower S2-2@15', Lower S4-2@ 87' :Noindications found.

VT-I Upper & lower S3(a&b) from 272' to870, Upper & lower $3c-I &-2, 2720 SB,3060 SB, 3460 SB, 13° SB, 540 SB, 870

119

Page 121: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

SB: No indications

2009 EVT-I SIB, SIC, S2B1, S2B2, $2C1, S2C2,S4B1, S4B2, S4C1, and S4C2 welds.

VT-I BS3C-1, BS3C-2, BS3A, BS3B, CS3C-1, CS3C-2, CS3A and CSB

Core Spray Sparger Brackets at 93, 126,166, 193, 234 and 267 degrees.

No indications found.

2011 EVT-1 Examinations: SIA & D at 13' and 346',S2A-I & 2 at 110 and 15'. S2D-I & 2 at3440 and 3480. S4A-1 & 2 and S4D-1 &2 at 870 and 2720. No indications.

VT-I Examinations: AS3A & B and DS3A &

B at 870 and 2720 locations. AS3C- I &AS3C-2 sparger drain plug welds. Upperand lower sparger brackets at 130, 540,870, 2720, 3060, 3460 locations. Noindications.

Top Guide (Rim, etc.) 1993 and VT-I A VT-I inspection was performed at 151994 cell locations which were considered to

be high fluence areas. No descrepancieswere identified.

1996 to Also inspected every outage are the Holdpresent Down Latches, Top Guide Ring Bolts

and Top Guide Beams. No indicationshave been identified to date.

2000 VT- I Ring Bolts (80 Total)

VT-I Hold Down Latches

EVT-I Rim Welds at 4 Locations Adjacent toGuide Blocks

VT-3 Guide Blocks and Aligner Pins

120

Page 122: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

No problems identified

2003 VT-I Top Guide Aligner Pin and SocketAssemblies ( 2520 and 3410): Noindications

Top Guide Hold Down Latches ( 18' &1980): No Indications

2007 VT-I Top Guide Aligner Pin and SocketAssemblies ( 72' and 1620): Noindications

2009 Top Guide Grid Beams (B-N-I):

06-19, 06-27, 06-35, 10-11, 10-43, 14-11, 14-15, 14-19, 14-35, 18-07, 18-31,18-43, 22-03, 22-07, 22-11,22-23,22-31,22-43, 26-03, 26-11, 26-47, 30-23,30-31, 34-07, 34-15, 34-39, 34-4, 38-11,38-15, 42-11,42-15, 14-07, 38-07

Top Guide Perimeter 360 degrees around

No indications found.

2011 EVT-1 & Examinations of Top Guide cells: 38-VT-3 07,34-35, 34-19, 30-39, 18-35, 18-19,

14-11, 14-07. No indications.

VT-I Examinations: Top Guide Aligner Pinsand Sockets at 720 and 1620. Noindications.

VT-3 Examination of Top Guide accessibleareas. No indications.

Core Plate (Rim, etc.) N/A N/A N/A

2009 Tops of accessible fuel support channels.

Core Plate (B-N-1, B-N-2): 06-19, 06-27,06-35, 10-11, 10-43, 14-11, 14-15, 14-19, 14-35, 18-07, 18-31, 18-43, 22-03,

121

Page 123: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

22-07, 22-11, 22-23, 22-31, 22-43, 26-03, 26-11,26-47, 30-23, 30-31, 34-07,34-15, 34-39, 34-47, 38-11,38-15, 42-11,42-15,14-07, 38-07

No indications found.

Examinations of accessible areas in celllocations 38-07,34-35, 34-19, 30-39, 18-35, 18-19, 14-11, and 14-07. Noindications.

2011 VT-3

SLC 1984 & 1989

2003

2005

2007

LP

EVT-2

EVT-2

EVT-2

Section XI performed baseline in 1984and reinspected in 1989, of the followingwelds:Nozzle number 10 was inspected at theinner radius to vessel weld, safe endweld, and tee to safe-end weld.

Inspections have identified minorindications which appear to have beendetermined to be manufactured induced.

No Indications

No Indications

No indications

Jet Pump Assembly-20 Assemblies

1993-1996 VT-I VT-1 of the following componentsperformed every refueling outage foreach jet pump:

I. Beam Bolt & Tack Welds.2. Lock Plate, 2 Plug Welds, 4 Tack

Welds.3. Hold Down Beam (Latched Position)4. Inlet.5. Inlet Mixer Coupling.6. Wedge and Restrainer.7. Set Screw Tack Welds.8. Transition Piece.9. Upper (Original) Brace & Reclad

Area.10. Lower (Modification) Brace &

Reclad Area.

122

Page 124: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

11. Sensing Lines.Item 7 above had Several tack weldscracked. Weld repair performed on 11set screws during 1994 outage. Tackwelds on jet pump #10 vessel side werediscovered to be cracked during the 1996outage. An evaluation was performedwhich justified operability of the setscrew with the cracked tack welds. Norepair was performed.A preemptive repair of the jet pumphold-down beams was performed duringthe 1982 refueling outage.During the 1989 refueling outage, ajetpump riser brace for jet pump # 7 and # 8was discovered to be cracked. Anevaluation was performed to justifyoperating with the cracked riser brace.Each refueling outage the crack isreinspected and compared with previousinspection results. To date, no crackgrowth has been reported.

1998 EVT An Enhanced Visual Exam wasperformed on the high priority riserwelds (RS-1, RS-2, RS-3) for Jet PumpsJP-3/4, JP-5/6, JP-7/8 JP-9/10, and JP-17/18. No reportable indications wereidentified.

The following flaws were identified as aresult of the IVVI exam:

JP-14, Beam Bolt Retainer Tack Weldcrack like indication.JP-18, Crack like indication on upper leafto yoke weld.JP-19, Beam Bolt Retainer Tack Weldcrack like indication.

All 20 Jet Pump Hold Down Beams wereUT examined per the BWRVIP-41document. JP-10 had an indication andwas replaced. All other beams had noreportable indications.

123

Page 125: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2000 VT-I Beam Bolt Keeper and Tack Welds

VT-I Lock Plate, Flat Head Screws, and TackWelds

VT-3 Hold Down Beam

VT-3 Beam Bolt Retainer

VT-3 Rams Head and Inlet Suction Area

VT-I Riser Brace Attachments to Vessel Pad(RB-I on Primary and Secondary RiserBraces)

VT-I Riser Brace Leaf to Yoke Welds (RB-2on Primary and Secondary Riser Braces)

VT-I Riser Brace to Riser Welds (RS-8 to RS-II on Primary and Secondary RiserBraces

VT-3 Inlet to Mixer Clamp Bolting (IN-5)

VT-I Wedge Assembly

VT-I Restrainer Bracket, Set Screws, andWelds, Including Gaps

VT-I Slip Joint

VT-I Sensing Line Attachment Welds toBrackets

VT- I Bracket to Diffuser Welds

* Crack indication in the #17 Jet pumpbeam bolt retainer tack weld.

* Crack indication in the #10jet pumpvessel side restrainer set screw

" Crack indication in the jet pump #19secondary riser brace lower leaf toblock weld. The indication appearsto travel approximatelv 50% across

124

Page 126: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

the width of the leaf and is containedwithin the block material. It alsoappears to have propagated radiallyinto the block to reactor vessel padweld.

The examinations performed alsoreconfirmed previously recorded andunrepaired relevant indications in thefollowing reactor vessel internalcomponents:

* Crack indication in the #14jet pumpbeam bolt retainer tack weld.(CR19980794)

* Crack indication in the #19 jet pumpbeam bolt retainer tack weld.(CR19980794)

* Crack indication in the 3250 steamdryer jacking bolt tack weld.(CR19980794)

* Crack indication in the #8 jet pumpsecondary riser brace lower leaf tovessel block weld. No apparent crackgrowth was observed. (SRI 89-028)

Due to enhanced inspection andmeasurement techniques, evaluation ofthe previously recorded indications onthe following components has changedsince the RF 18 Refueling Outage:

The crack indication previously reportedin the # 18 jet pump secondary riser bracetipper leaf to yoke weld has beendetermined to be weld geometry. AnRCS 600 color camera, along withauxiliary lighting was used to reinspectthe previously recorded indication duringthe RFI9 Refuel Outage. This techniqueclearly showed the indication to be thejuncture of two weld passes.

125

Page 127: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2001 VT-I

VT-I

VT-3

VT-3

VT-3

EVT-1(II -18,20)VT-I (1-10,19)

EVT-I(I 1-18,20)VT-I (I-10,19)

EVT-I(I I-18,20)VT-1 (1-10,19)

VT-I

EVT-I

VT-I

Beam Bolt Keeper and Tack Welds

Lock Plate, Flat Head Screws, and TackWelds.

Hold Down Beam

Beam Bolt Retainer

Rams Head and Inlet Suction Area

RB-I

RB-2

RS-8 to RS-I I

Restrainer bracket, Set Screws, andwelds (Including gaps)

JP#1 (MX-1, MX-2, MX-4)JP#2 (MX-1, MX-2, MX-4)JP#3 (MX-1, MX-2, MX-4)JP#4 (MX-1, MX-2, MX-4)JP#5 (MX-1, MX-2, MX-4)Riser@30' (RS-1, RS-2. RS-3)Riser@240' (RS-1, RS-2, RS-3)Riser@330° (RS-1, RS-2, RS-3)JP# 19 (RB-4d): No New IndicationsTransition region of all beamsinspectedEVT-I no cleaning: NoIndications

JP#20 (WD-1), JP#19 (WD-1), JP#10(WD-1): No Indications

2003

126

Page 128: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2005 VT JP#6 (MX-l, MX-2, MX-4)JP#7 (MX-I, MX-2, MX-4)JP#8 (MX-I, MX-2, MX-4)JP#9 (MX-1, MX-2, MX-4)JP#10 (MX-1, MX-2, MX-4)Riser@30° (RS-4, RS-5)Riser@60' (RS-4, RS-5)Riser@90' (RS-4, RS-5)Riser@150' (RS-4, RS-5)Riser@2 10' (RS-I, RS-2, RS-3)Riser@270° (RS-1, RS-2, RS-3)

No Indications

2007 UT BB-1, BB-2 and BB-3 of all 20

Holddown Beams

2009 EVT-1 JP# 1I (MX- l, MX-2, MX-4)

JP# 12 (MX- 1, MX-2, MX-4)JP#13 (MX-1, MX-2, MX-4)JP#14 (MX-l, MX-2, MX-4)

Riser@30 degrees (RS-1, RS-2, RS-3)Riser@60 degrees (RS-1, RS-2, RS-3)Riser@90 degrees (RS-1, RS-2, RS-3)Riser@2 10 degrees (RS-4, RS-5)Riser@240 degrees (RS-4, RS-5)

No indications found.

2011 EVT-I JP# I thru 20: RS-8, RS-9, RS-10, RS -11JP# 6 thru 10: RS-1, RS-2, RS-3JP# 14 thru 20: RS-4 and RS-5JP# 15 thru 20: MX-I, MX-2 and MX-4No indications.

VT-I JP# I thru 20: riser brace to padattachment welds and WD- 1. Noindications.

Jet Pump Diffuser 1996 VT-I Perform VT-I inspection per the IVVIprogram each refueling outage. Noindications have been identified to date.

127

Page 129: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

1998 UT The following Jet Pump Diffuser weldswere UT examined from the ID per theBWRVIP-41 guidelines:

Jet Pump Weld # Coverage ResultsJP-14 DF-2 100% NRI

DF-3 100% NRIAD-3A 100% NRIAD-3B 100% NRIAD-2 100% NRI

JP-16 MX-2 100% NRIMX-4 100% NRIDF-2 100% NRIDF-3 100% NRI

AD-3A 100% NRIAD-3B 100% NRIAD-2 100% NRI

JP-17 DF-2 100% NRIDF-2 100% NRI

AD-3A 100% NRIAD-31B 100% NRI

AD-2 100% NRI

An Enhanced Visual Exam from the IDEVT was performed on the high priority

diffuser welds (DF-2, DF-3 and AD-2)for Jet pumps JP-I 1, JP-12, JP-13, JP-15,JP-18, JP-19 and JP-20. No reportableindications were identified.

2003 EVT-1 JP#1 (DF- , DF-2, AD-3a, AD-2)JP#2 (DF-l, DF-2, AD-3a, AD-2)JP#3 (DF-l, DF-2, AD-3a, AD-2)JP#4 (DF- , DF-2, AD-3a, AD-2)JP#5 (DF-l, DF-2, AD-3a, AD-2)

2005 EVT-I JP#6 (DF-l, DF-2, AD-3a, AD-2)JP#7 (DF-1, DF-2, AD-3a, AD-2)JP#8 (DF-1)JP#9 (DF-1, DF-2, AD-3a, AD-2)JP#10 (DF-I, DF-2, AD-3a, AD-2)JP#20 (DF-2)

2007 VT-I Wedge Inspection (JP 11-20)AD-I (JP 1-20)

128

Page 130: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2009 EVT-I JP#1 I (DF-I, DF-2, AD-3a, AD-2)JP#12 (DF-1, DF-2, AD-3a, AD-2)JP#13 (DF-I, DF-2, AD-3a, AD-2)JP#14 (DF-1, DF-2, AD-3a, AD-2)JP#15 (DF-I, DF-2, AD-3a, AD-2)

2011 EVT-I P# 16 thru 20: DF-1, DF-2, AD-2, AD-3a, AD-3b. No indications.

CRD Guide Tube 2003

2005

2009

2011

VT-3

EVT- 1

VT-3

EVT- 1

EVT- I

VT-3

VT-3

CRGT-1 (30-11, 26-11, 26-27, 26-07, 30-07,10-15)

ARPIN-1(30-11, 26-11, 26-27,26-07,30-07, 10-15)

CRGT-2(30-l1, 26-11,07,10-15)

CRGT-3(30-11, 26-11,07, 10-15)

26-27, 26-07,30-

26-27, 26-07, 30-

CRGT-1(22-27, 22-47, 26-27, 26-47, 30-47, 34-19, 34-35, 34-43, 46-27, 2-3 1, 18-19, 18-35, 18-47, 22-43)

ARPIN-(22-27, 22-47, 26-27, 26-47, 30-47, 34-19, 34-35, 34-43, 46-27, 2-31, 18-19, 18-35, 18-47,22-43)

CRGT-2(22-27)

CRGT-3(22-27)

CRGT-2 (10-11,22-31, 30-23)

CRGT-3 (10-11,22-31)

CRGT-1 (10-11,22-31, 30-23)

14-15, 18-07,22-23,

14-15, 18-07, 22-23,

14-15, 18-07, 22-23,

ARPIN (10-11, 18-07, 22-23, 22-31, 30-23, 38-15, 30-31, 34-07, 34-15, 42-11)

Examinations of guide tubes in cell

129

Page 131: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

locations 38-07,34-35, 34-19, 30-39, 18-35, 18-19, 14-11, 14-07. No indications.

CRD Stub Tube N/A N/A N/A

In-Core Housing N/A N/A N/A

Dry Tube 80's to VT In 1987, 6 out of 12 dry tubes werepresent replaced with a new improved design.

Visual inspection performed on theremaining 6 old style dry tubes everyother refueling outage. No problemshave been observed to date.

2011 VT-I Examinations of spring and upper 2 feetof the following: IRMs at core locations20-33, 28-23, 20-41, 12-41, 36-41, 12-09, 28-25, 20-25. SRMs at core locations12-25, 28-17, 36-09, 36-33. Noindications.

Instrument VT-I Visual inspection of the instrument linesPenetrations and penetrations performed per the IVVI

program. No indications observed todate.

Vessel ID Brackets VT-I VT-I inspections ofjet pump riser brace,dryer, feedwater sparger, core spray,guide rod bracket and surveillancecapsule holder brackets, performed everyrefueling outage. No problems identifiedto date. In 2005, one surveillance bracket(empty) was identified as bent, no furtheraction.

VT- I Surveillance Sample Holder LowerBrackets at 30', 120' and 3000. Guiderod vessel attachment welds at 1750 and3550. No indications.

VT-3 Examinations: Feedwater sparger endbrackets and attachment welds at 00, 900,1800, 2700 locations. SurveillanceSample Holder Upper Brackets at 300,1200 and 300'. Surveillance sampleholder at 120'. Guide Rod brackets at1750 and 355'. Steam Dryer supportbracket and weld at 350, 1450, 2150,3250. Indication was discovered on guide

130

Page 132: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

rod at 175'.

LPCI Coupling N/A N/A Not applicable to this plant.

Steam Dryer 2005 VT

2007

2009

VT

VT-I

VT-3

Performed OD visual inspection of allaccessible welds. Three indications foundbehind the lifting lugs. Eachapproximately 1- 1/2 inches long. Oneindication found in the support blockguide channel to skirt weld (-0.75 incheslong).

Dryer ID inspection. Found a IGSCC inthe weld surrounding a square drainchannel access panel.

Reinspected OD welds with indications.No reportable change.

Previous Dryer OD Indication:

V3 @ 900, VIO @ 90-, V1O @ 2700,Jacking Bolt @ 325', Vertical Guide @2150

Previous Dryer ID Indication:

DC-F Cover Plate @ 0 degrees

Steam Dryer Hold Down Brackets @350, 1450, 2150, 3250

No changes in previous indications. Nonew indications.

New model steam dryer installed.2011 N/A

Dissimilar Metal 2009 None No BWRVIP-75 DM weld exams wereWelds performed during the 2009 RFO.

Other Exams 2011 UT UT of approximately 72" of the RPVLAS adjacent to H9 from the RPV OD,but not considered a BWRVIP exam as itwas not performed lAW BWRVIP-104requirements. No credit was taken forUT of the H9 weld. The purpose of theexamnination was to interrogate the basemetal near H9 to determine if there was

131

Page 133: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

evidence that the visual indications foundon the underside of the H9 weld weregrowing into the base metal. Theexamination utilized PDI qualifiedprocedures and personnel. The examsdid not find any indication of flawsgrowing into the base metal.

132

Page 134: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Reactor Internals Insnection History

Plant: Nine Mile Point Unit #1

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Used Inspection Results, Repairs,

Inspection Replacements, Reinspections

Core Shroud 4/11 VT-1/VT-3 Shroud repair clamps at V9 and V 10 -No& Shroud Repairs indications noted

4/09 EVT-1/UT EVT-1 on four ring segment welds V1, V2,V5 and V6. No indications noted.

UT on Ten vertical welds with no significantchange as compared to previous data.

EVT-I/VT-3 Performed a detailed inspection on all fourtie rods. Addressed lack of contact at tie rodlower spring clevis pin to lower support hooklocations.

3/07 EVT-I Replaced tie rod upper supports and nuts.Performed EVT-l of high stress locations.No Indications noted. No shroud inspectionsperformed.

3/05 No shroud inspections performed.

3/03 EVT-I Weld H4 (adjacent to V7) was visuallyexamined to confirm previously identifiedUT indications. No change noted ascompared to UT data for location.

3/03 Tierod inspection resulted in having to re-position 2 tierods due to wedge movement.

3/01 EVT-i V-4 ID only (no indications noted).

3/01 VT-3 Inspections performed on all 4 tierods and[VT-I V9 & VI0 repair clamps.

1999 UT Completed repair of V9 & V 10 based on UTresults showing crack growth. All verticalwelds were located and examined (includingring segments) using UT.

133

Page 135: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

95-97 EVT and UT Tie rod repair (for BWRVIP) for horizontalwelds H1-H7. EVT on i.D. of certain vertweld locations. No indications on vert welds(1995). 1997 (per BWRVIP) re-inspectionof 2 vert welds found extensive flaws.Inspection scope expanded to include allaccessible vert welds and some horizontalwelds. Flaws found at several locations.Structural re-analysis performed (perBWRVIP) shroud expected to be acceptablewith tie rod repair.

Shroud Support 4/11

4/09

3/07

3/05

3/03

3/01

1999

UT

VT-3

UT

UT

UT

EVT-I

Examined 100% of the accessible weldlength on H8 & H9. Coverage achievedequivalent to 2001 baseline UT (80%).Evaluated previous indications for changewith no significant change noted aftercomparison of difference in UT methods.

No examinations performed.

Examined 100% of the accessible weldlength on H8 & H9. No indications noted(ASME section XI code inspection).

H9 weld ultrasonically examined from theOD utilizing a crawler for a total length of85".

H9 weld ultrasonically examined from theOD utilizing an OD crawler. Approximately45" was examined to confirm no propagationinto low alloy steel. No indications noted inlow alloy steel.

H8 (conical ring to shroud) 80% of weldcompleted one sided coverage. 3 indicationsnoted.

H9 (conical ring to vessel) 80% of weldcompleted from ID, one sided coverage. 34indications noted.

H8 & H9 100% EVT-I examined. Nochange in previous indications.

134

Page 136: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

95-97 EVT and UT 1996 H8 inspected by EVT and UT, minorindications noted full structural margin. H9EVT at 4 locations no indication. 1997 H8re-inspected with increased scope. Previousindications no change. One new indicationfound by EVT in previously uninspectedarea. Full structural margin. H9 re-inspectedEVT at one location, no indications noted.

Core Spray Piping 4/11

4/09

3/07

UT

EVT-1

EVT-1

EVT- I

EVT- I

EVT- I

EVT-I

EVT- 1

Eight (8) piping welds (P5,P,6,P7 and P8)were ultrasonically examined using samemethods as deployed in 2003, no indicationsnoted. UT confirmed the visual indicationfrom 2009 as non relevant scratch / rub mark.Subsequent additional cleaning and visualconfirmed no indication.

Target welds (18) utilizing EVT-1. Noindications noted

Examined one annulus pipe support bracketattached to the shroud.

Target welds and 25% sample planimplemented utilizing EVT-1. Relevantindication noted on P6-U3A weld.Dispositioned indication as a scratch andapplied BWRVIP-18 evaluation guidance todemonstrate structural integrity for one cycle.UT planned for next outage to confirm ascratch.

Examined one annulus pipe support bracketattached to the shroud.

Target welds and 25% sample planimplemented utilizing EVT-1. Noindications noted.

Examined one annulus pipe support bracketattached to the shroud. A 1.5 inch linearindication was found in the shroud supportring above the pipe support bracket.

EVT-1 of P4-a access limited to single sidedaccess and limited to less than 10%circumference. Considered a partially hidden

135

Page 137: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

weld.

3/05

3/03

3/03

3/01

1980's topresent

EVT-I

EVT- I

UT

EVT- 1

EVT-I

4 .4-

Core Spray Sparger 4/11

4/09

3/07

3/05

3/03

3/01

3/99

EVT-I

EVT- I/VT- I

EVT- I

EVT- I

EVT-I

EVT-I

Target welds and 25% sample planimplemented utilizing EVT-1. Noindications noted.

Target welds and 25% sample planimplemented utilizing EVT-1.

3 - P8 welds (shroud side only) and both setsof slip joints (P5, 6, & 7) were examinedultrasonically. No indications noted.

Re-inspection per BWRVIP- 18.

IEB 80-13 of piping and welds in annulus.No indications noted. EVT per BWRVIP-I 8in 1997. No indications noted. 1999examined target welds and 25 % sample.

Examined 3 Sparger T Box welds and 3previously identified indications, no changefrom previous inspections.

Examined "A through D" Sparger T-boxwelds, end caps, support brackets, nozzlesand welds and 3 previously identifiedindications on "A" sparger nozzles. Nochange from previous inspections.

Examined 3 previously identified indicationson "A" sparger nozzles. No change fromprevious inspections.

Examined 100% of spargers and 3 previouslyidentified indications, no change fromprevious inspections.

Examined lower sparger brackets and 3previously identified indications, no changefrom previous inspections.

No growth noted on 2 previous indicationsbeing monitored.

1999 examined target welds and 25%sample.

136

Page 138: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

1980's to EVT-I IEB 80-13 of piping and welds on spargers.present Two indications found, analyzed, and re-

inspected. No repairs needed. Inspected toBWRVIP-18 in 1997. No new indicationsfound.

Top Guide 4/11 EVT-I Examined 2 previously identified indications(Rim, etc.) in Top Guide grid beams. No significant

change from previous inspection results.

VT-I Examined 2 Top Guide Hold Down Devices-No indications noted

4/09 EVT-I Examined 3 previously identified indicationsin Top Guide grid beams. No significantchange from previous inspection results.

3/07 EVT-I Examined I previously identified indicationin Top Guide Grid Beam #33. No changefrom previous inspection.

VT-I VT-I of 2 top guide hold downs (upper andlower). No indications noted.

3/05 UT A total of 79 non-geometric indicationsidentified, 13 associated with attachmentwelds adjoining the ribs, 60 indicationsassociated with assembly slots generally <1/2" and 6 indications on the grid beambottom mid span sized at <2.5" in length.

3/03 EVT-I Examined 8 top guide grid beam celllocations based on SIL-554. One crackidentified 1.375" long through beamthickness.

3/01 No inspections performed.

1993 to present VT-I 1999 VT-I of 2 top guide hold downs. Noindications.

1993 VT- I of selected locations on undersideat mid-span locations. No indications noted.VT-1, 1995, from underside to confirmlateral spacers in place.

137

Page 139: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Core Plate(Rim. etc.)

4/11

4/09

3/07

3/05

3/01

3/01

1995

VT-3

VT-I

VT-3

VT-I

100% of the accessible core plate surface andcore plate bolts from the top surface. Noindications noted

Examined 2 Fuel Support Piece Castings -

no indications noted

Inspected 16 core plate bolts from the topsurface. No indications noted.

No inspections performed.

No inspections performed.

No inspections performed.

No inspections performed.

1995 hold down bolts from top side. Noindications.

4 i

SLC 4/11

4/09

5/99

EVT-2

UT

UT

Enhanced visual in accordance withBWRVIP-27-A.

UT of N 12 safe-end to nozzle weld andaccessible portions of adjacent base metalusing PDI qualified technique. Noindications found.

UT of N 12 safe-end to nozzle weld andaccessible portions of adjacent base metalusing PDI qualified technique. Noindications found.

Enhanced visual in accordance with

BWRVIP-27-A.

Section Xi performed each refueling.

1995 to present I EVT-2

1970's toPresent

VT-2

CRD Flow Shield 4/11 No examinations performed.

4/09 No examinations performed.

3/07 EVT-I Examined the CRD return line flow shield-to-thermal sleeve weld. No indicationsnoted.

138

Page 140: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Jet Pump Assembly N/A N/A Not applicable to this plant.

Jet Pump Diffuser N/A N/A Not applicable to this plant.

CRD Guide Tube 4/11 EVT-1/VT-3 Examined 2 available locations-Noindications noted.

4/09 No examinations performed, however duringcontrol blade change out a loose OFS/CGRTalignment pin was identified duringinstallation of the OFS.

3/07 EVT-1/VT-3 Examined 2 available locations. Noindications noted.

3/05 EVT-I 2 guide tubes were removed from core plateto facilitate lower plenum inspections, wasable to examine both from the OD. Noindications noted.

3/03 EVT-1 Examined 2 available locations. No

indications noted.

3/01 EVT-1 4 guide tubes made accessible for inspection.

1997 EVT- 1 1997 commenced inspection of select guidetube. 3 guide tubes examined. Noindications.

CRD Stub Tube 4/11 No examninations performed

4/09 EVT-I Examined accessible portions of lowerplenum during bottom head drain foreignmaterial inspection. Areas such as the stubtube to RPV weld, CRD housing, CRDhousing to stub tube weld, bottom headcladding and ICH (see below) wereexamined. Indications noted in the stub tubebase metal at two core locations.

3/05 EVT-I Completed VT-3 / VT-I on a portion of thelower plenum, no new flaws were identified.

UT 3 stub tube J-weld areas examined.Augmented UT exams performed eachoutage at different locations in support of rollrepair program.

139

Page 141: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

3/03

3/01

UT

UT

2 stub tube J-weld areas examined.Preemptive UT exams performed eachoutage at different locations.

2 stub tube J-weld areas examined.Preemptive UT exams performed eachoutage at different locations.

1984-1997 VT-2 and UT Stub tube leakage found periodically since1984. Condition corrected by roll repair. UTinspection before and after each repair. Pre-emptive inspection and rolling commencedin 1997 on selected stub tubes.

In-Core Housing 4/11 No examinations performed

4/09 EVT-I Examined accessible portions of incoreVT-I/VT-3 housing guide tube weld, RPV weld, cap to

tube weld, support hardware, clamps andtack welds at 2 core locations.No indications noted.

3/05 VT-3 Inspections obtained on 2 housing.

Dry Tube 4/11 EVT-I Examined 5 dry tubes. No indications noted.

4/09 EVT-I Examined 3 dry tubes. No indications noted.

3/07 EVT-I Examined 9 dry tubes. No indications noted.

3/05 EVT-1 3 dry tubes examined, no indications noted.

3/03 No inspections performed.

Instrument Penetrations 4/11 VT-2 Performed VT-2 exam on all instrumentpenetration nozzles. No leakage noted.

4/09 VT-2 Performed VT-2 exam on all instrumentpenetration nozzles. No leakage noted.

3/07 VT-2 Performed EVT-2 exam on all instrumentpenetration nozzles. Inspections performedsatisfactorily.

3/05 VT-2 Performed EVT-2 exam on all instrumentpenetration nozzles. Inspections performed

140

Page 142: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

satisfactorily.

3/03

3/01

1993

VT-2

VT-2

LP or MT

Performed EVT-2 exam on all instrumentpenetration nozzles. Inspections performedsatisfactorily.

Performed EVT-2 exam on all instrumentpenetration nozzles. Inspections performedsatisfactorily.

Section XI performed once per interval. Lastinspection was 1993. No indications.

Vessel ID Brackets 4/1!

4/09

3/07

3/05

3/03

3/01

EVT-1

VT-3

VT-3

VT-I

EVT-I

EVT- I

EVT- I

Examined 4 Steam Dryer Support Brackets.Indications recorded on 3 of 4 brackets.Informational UT performed to obtain depthmeasurements.

Examined 8 Feedwater Sparger brackets to

the RPV wall - No indications noted

No examinations performed.

0 and 180 degree Guide Rod brackets to theRPV wall. No indications noted.

Surveillance specimen holder attachmentwelds (6) to the RPV wall. No indicationsnoted.

No inspections performed.

Examined 10 attachment welds per BWRVIPrequirements. No indications noted.

3 of 4 steam dryer brackets completed withno indications noted.

Section Xl performed once per interval.Dryer, surveillance capsule holder.

1988, 1993,and 1997

VT-i andVT-3

LPCI Coupling N/A N/A Not applicable to this plant.

Steam Dryer 4/11 VT-I VT-I of 4 hold-down assemblies. Noindications noted.

VT-I Examined 11 lower tie bars between banks -

141

Page 143: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

VT-I

VT- I/EVT- I

UT

EVT- IVT- I /VT-3

VT-I

EVT- I/VT- I

4/09

3/07

I indication found evaluated acceptable forservice based on BWRVIP-139 guidance.

Examined existing indications on inner bankvertical seam welds and hold down assemblyslot- no changes noted

Examined existing indications on the 225degree lifting rod to lifting lug tack welds -new indication found. Expanded scope toinclude all 4 rods. Indications noted onexpanded scope lifting rod to lifting lug tackwelds. All indications evaluated acceptablefor I cycle of operation without repair.

UT examined visual indication identified in2009 in base of 225 degree lifting rod. Depthof indication confirmed to be shallow. UTexamined the 135 deg lifting rod to liftinglug tack weld indication. Confirmed depth tobe shallow.

Performed examinations to complete theBWRVIP-139 baseline inspection scope.This included the drain channel weldsunderneath the dryer. New indications werenoted on the inner bank vertical seam weldson the vane side and two indications on the225 degree lifting lug.

Examined several existing indications forchange, no change noted from previousinspection results.

VT-i of 4 hold down assemblies. Noindications noted.

Inspected all previous dryer bank repairlocations. Inspections included boltedrepairs, bank clips, repair clips, lowerstiffeners and previous stop holes. Two newindications were noted. Steam Dryer Bank 5,Clip 6 has a 1.12 inch indication in the weldHAZ and repair area Bank 4, Clip 6 has ahole (weld defect) approximately 1/8 inch indiameter in the existing clip weld. All other

142

Page 144: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

repair areas remain unchanged from previousexaminations.

VT-3 Performed a VT-3 on all accessible areas(repair areas), hold-down and support lug,lifting eye, horizontal and vertical welds,upper/lower support ring and guides, dryerbanks, manway covers and stabilizer bars.No indications noted.

Moisture Separator 4/11 EVT- I/VT-I Examined standpipe #102 and all associatedwelds, tie bars and support components. Nochange in previously reported indications.

4/09 EVT-I/VT-I Examined retired in place LVI tubing andsupports. No indications noted.

Examined standpipe # 102 and all associatedwelds, tie bars and support components.Indications noted on all four gusset plates.

Examined six shroud head bolts for surfacecondition change and cracking at the lowershaft to tee head weld. No indications noted.

3/07 VT-3/ VT-I Performed a VT-3/VT-I on all accessibleareas, standpipe gussets, SHB-Pin-Sleeve, tiestraps and separator internals. Two newindications were noted. One tie strap wasfound bent between standpipes 43 and 50 anda second gusset was found cracked onstandpipe #102. No other indications werenoted.

BWRVIP-75-A 4/11 UT NIC, Category D, Manual Exam. PreviouslyDissimilar Metal Welds recorded acceptable midwall indications

were observed with no change noted. 100%ASME and 100% Full Volume coverageachieved.

NID, Category D, Manual Exam. (1) ASMEXI IWB-3514-2 acceptable axial planar flaw(0.5" L x 0.05" D) in the safe end I.D.Additional surface preparation wasperformed this outage. 97.5% ASME and91.75% Full Volume coverage achieved.

143

Page 145: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

N IE, Category D, Manual Exam. Previouslyrecorded acceptable mnidwall indicationswere observed with no change noted. 97.5%ASME and 89.2% Full Volume coverageachieved.

N2D, Category D, Auto Exam. (1) ASMEXI IWB-35 14-2 unacceptable planar flaw(1.29" L x 0.27"D) recorded at Ni 1R9-second re-look performed with no growthnoted.

N5B, Category D, Manual Exam. NoRecordable Indications. 94.3% ASME and93.1% Full Volume coverage achieved.

N6A, Category D, Manual Exam. NoRecordable Indications. 100% ASME and100% Full Volume coverage achieved.

4/09 UT NIA, Category D, Auto Exam: (2) ASMEXI IWB-3514-2 acceptable planar flaws inthe safe end I D

N IB, Category D, Auto Exam: (3) ASMEXI IWB-3514-2 acceptable planar flaws inthe safe end ID

N2D, Category E, Auto Exam: (1) ASMEXl IWB-3514-2 unacceptable planar flaw(1.29" L x 0.27" D) recorded atNIR19(2007) -- re-look performed with no growthnoted

N5A, Category D, Manual Exam: NRI

144

Page 146: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Reactor Internals Inspection History

Plant: Perry Nuclear Power Plant

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Inspection Results, Repairs,

Inspection Used Replacements, Reinspections

Core Shroud (VIP- 1994 (RF4) VT-3 and In RF4, VT-3 of entire shroud interior76) EVY-1 and EVT-I of the H-3 and H-4 weld

inside surfaces at 4 appx I ft long samplelocations. No indications.

1997 (RF6) EVT-1 In RF6, a Code VT-3 exam wasperformed on all accessible shroudexterior areas. No indications.

1999 (RF7) UT In RF7, UT examination of the H-3, H-4,H-6A and H-7 welds was performed inaccordance with the Category B Plantguidelines ofBWRVIP-01. Noindications.

2005 (RFI0) UT In RFI0, UT examinations of the H-3and H-4 welds with the Tecnatom ID tooland H-6A and H-7 with the GE ODTracker. H-4 and H-6A were two sidedexams and H-3 and H-7 were one-sidedexams. Shallow cracking was found inH-7. It was less than 10% of theinspected length of 67% of the weld.

Shroud Support (VIP- 1990 (RF2) VT-3 & In RF2, VT-3 of shroud support plate and38) VT-I VT-I of the shroud support plate access

hole cover. No indications.

1996 (RF5) VT-3 & In RF5, VT-3 of shroud support plate andVT-I VT-I of the shroud support plate access

hole cover. No indications.

1999 (RF7) EVT-I In RF7, baseline EVT-1 exams of the H-8 and H-9 were performed in accordancewith BWRVIP-38. No Indications.

2001 (RF8) VT-I In RF8, re-seating ofjet pump no. 5provided access to the H-10, H-Il and H-12 welds of the shroud support leg at 90

145

Page 147: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2007 (RF 11)

2011 (RFI3)

EVT-1 &VT-I

EVT-1,VT-I, &VT-3

degrees and approximately 10 degrees ofthe underside of H-8 and H-9 so theywere visually examined with at least VT-I resolution. No indications.

In RF 10, jet pump no. 6 was removedand re-seated due to excess leakage at thetransition piece. While disassembledapproximately 10 degrees of theunderside of H-8 and H-9 were examinedwith at least VT-I resolution. Also, theH-10, H-I I and H-12 welds of the shroudsupport legs at 90 and 120 degrees wereexamined with EVT-I resolution.Coverage was approximately 35-50% forthe welds of the 90 degree leg and 25%for the welds of the 120 degree leg.

In RF13, H8 was inspected from abovethe core plate in the open areas betweenjet pumps at 0 and 180 degrees. EVT-Iresolution was obtained with 15%coverage of the circumference. Inaddition all accessible areas of the shroudsupport plate were examined, VT-3,meeting ASME B-N-I requirements.There were no relevant indications.

Additionally in RF 13, jet pump numbers15 and 16 were disassembled with themixer assemblies replaced with a widerwedge installed on the new mixers. Thewider wedges were installed due towedge/restrainer bracket degradationfound in jet pump 15. Whiledisassembled, approximately 20 degreesof the underside of H-8 and H-9 wereexamined with EVT-1 equivalentresolution. Also, the H-10, H-1 I and H-12 welds of the shroud support leg at 270degrees were examined with EVT-Iequivalent resolution. Coverage wasapproximately 35-50% for the welds ofthe 270 degree leg. There were norelevant indications.

146

Page 148: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Core Spray Piping(VIP-] 8A)

1989-1996(REF thruRF5)

1997 (RF6)

1999 (RF7)2001 (RF8)2003 (RF9)

CVT-I

EVT- I

EVT-1EVT-1EVT-1

2005 (RF10) EVT-I

I mil wire resolution VT-I (i.e., CVT-1)exams of the core spray internal pipinghas been performed every outage sincestartup in accordance with IEB 80-13.No indications.

In RF6, Baseline BWRVIP-18 EVT-Iexaminations were performed on all thecore spray piping welds. No indications.

In RF7, RF8, and RF9 core spay pipingweld exams were performed inaccordance with the re-inspectionrequirements of BWRVIP-18. Noindications. Note that after a coupleoutages without having re-clean thewelds, all the welds inspected in RF9were pre-cleaned by hydrolasing

Examined in accordance with the re-inspection requirements of BWRVIP-18.Exams did find one cracked tack weld onone of the 6-bolt core spray pipingshroud flange to shroud connections (P8).

Examined in accordance with the re-inspection requirements of BWRVIP-1 8.Re-examination of cracked tack weld onone of the 6-bolt core spray pipingshroud flange to shroud connections (P8)found in RE 10 found no changes.

Examined in accordance with the re-inspection requirements of BWRVIP-18.No indications.

Examined in accordance with the re-inspection requirements of BWRVIP- 18.No indications.

2007 (RF 11) EVT- 1

2009 (RF12)

2011 (RFI3)

EVT- I

EVT- I

Core Spray Sparger 1989-1996 CVT-1 I mil wire resolution VT-I (i.e., CVT-1)(VIP-18A) (REI thru exams of the core spray spargers has

RF5) been performed every outage sincestartup in accordance with IEB 80-13.No indications.

147

Page 149: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

1997 (RF6)

1999 (RF7)

2001 (RF8)

2003 (RF9)

2005 (RFIO)

2007 (RF 11)

2009 (RF12)

2011 (RFI3)

EVT- I &CVT-1

EVT- I &MVT-l

EVT- 1 &VT-IEVT- I &VT-I

EVTI &VT-I

EVT-I &VT-I

EVT-1 &VT-I

EVT- I &VT-I

In RF6, Baseline BWRVIP-1 8 EVT-I &CVT-1 examinations were perfomed onall the core spray sparger welds. Noindications.

In RF7 core spay sparger weld examswere performed in accordance with there-inspection requirements of BWRVIP-18. No indications.

In RF8 and RF9 core spay sparger weldexams were performed in accordancewith the re-inspection requirements ofBWRVIP-18. No indications. Note thatafter a couple outages without having re-clean the welds, all the welds inspectedin RF9 were pre-cleaned by hydrolasing

Examined in accordance with the re-inspection requirements of BWRVIP-1 8.No indications.

Examined in accordance with the re-inspection requirements of BWRVIP-I 8.No indications.

Examined in accordance with the re-inspection requirements of BWRVIP- 18.No indications.

Examined in accordance with the re-inspection requirements of BWRVIP-1 8.No indications.

+ I. I

Top Guide (Rim, etc.)(VIP-26-A) & TopGuide Grid (VIP-] 83)

1989 (RFI)

1994 (RF4)

1999 (RF7)

VT-3

VT-3

VT-I &VT-3

Top Guide periphery, including 90 studsand tack welds, examined in RFI. Noindications.

Top Guide Grid examined in RF4. Noindications.

In RF7, performed VT-3 of the TopGuide assembly in accordance withASME Category B-N-2 and VT-I of thestuds and tack welds in accordance withBWRVIP-26. No indications.

148

Page 150: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2005 (RF 10) 1 VT-3

2011 (RF13) I VT-3

Code B-N-2 exam of accessible portionsof Top Guide grid. Due to ID CoreShroud exams, a significant number ofthe grid cells were vacated and accessiblefor inspection.

Examined in accordance with the re-inspection requirements of BWRVIP-26and ASME Code B-N-2. No indications.

Baseline BWRVIP-183 exams performed(i.e., rim areas containing grid weld andtwo cells in the same plane as the gridweld). No Indications.

EVT-I

I I I

Core Plate (Rim, etc.)(VIP-25; notapplicable toBWR/6s)

1989 (RFI)

1994 (RF4)

1999 (RF7)

VT-3

VT-3

VT-3

Accessible core plate areas and fuelsupport castings examined in RF 1. Noindications.

All of the hold down bolts examinedfrom shroud interior in RF4. Noindications.

In RF7, performed VT-3 exam of thecore plate areas made accessible byreplacement of 5 Control Rod blades inaccordance with ASME Category B-N-2.No indications.

SLC (VIP-27-A) N/A N/A Not applicable to this plant

Jet Pump Assembly 1989-1996 VT-I & Examine jet pump braces, hold down(VIP-41, Rev 1) (RF I thru VT-3 beams, sensing lines, restrainer bracket

RF5) set screws and mixer assemblies inaccordance with various GESILs/RICSILs. Set screw gaps identifiedin RF5 and RF6.

1997 (RF6) EVT-I In RF6, baseline EVT-I exams wereVT-3 performed on all the jet pump riser elbow

welds. No crack indications.

1999 (RF7) EVT-I & In RF7, the jet pump mixers wereVT-3 removed and cleaned with ultra high

pressure. Augmented VT-3examinations were performed on the jetpump mixer throats (pre and postcleaning) and the restrainer bracket set

149

Page 151: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2001 (RF8)

2003 (RF9)

2005 (RF 10)

EVT- I &VT-3

EVT- 1,VT-3 &UT

EVT- I &VT-I

screws. Most of the gaps detected inRF5 and RF6 were eliminated upon re-seating the mixers. The couple thatremain are very minor and within the "nofatigue" acceptance criteria.

With the exception of the IN-I and IN-2welds of 6jet pumps, in RF8, baselineBWRVIP-41 EVT-I exams wereperformed on all of the low, medium andhigh priority exam points of jet pumps Ithrough 10,. No indications. Also VT-3examined all the jet pump set screws forgaps. II of the 20 jet pumps had gapswere found to have gaps that were lessthan 0.0020" in one or more of their setscrews. Gaps evaluated as operable forat least one cycle with long term remedyto be determined.

In RF9, performed EVT-I exams of theIN-I and IN-2 welds of jet pumps Ithrough 10 not examined in RF8.Additionally, baseline EVT-I exams ofthe remaining High priority welds (RS-3on jet pumps II through 20 were alsoperformed). Performed VT-3 exams ofthe jet pump set screws and wedges.Gaps similar to previous outages werefound and evaluated for continuedoperation. Also performed UT of the jetpump hold-down beam BB-1 and BB-2locations (Note: PNPP's jet pump beamswere replaced with Type 2 beams inRF4). Supplemental EVT-i exams wereperformed on the BB-3 areas. With theexception of the set screw gaps, noindications.

In RF 10, performed re-examination(EVT-1) of the riser elbow welds on jetpumps I through 10. No indications.Also performed VT-I examination of all20 jet pump wedge assemblies. Foundminor wear on the wedge of JP-I 5.Expanded scope in accordance with

150

Page 152: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2007 (RF 11)

2009 (RF 12)

2011 (RF13)

EVT- I &VT-I

EVT- I &VT-I

EVT- I &VT- I

BWRVIP-41 and found no otherindications. The wear was evaluated asacceptable for one cycle of operation.

In RFI 1, performed examination of theall the high and medium priority weldson the reactor recirculation Loop B jetpumps (i.e., 11 - 20). No indications.Also performed VT-I examination of all20 jet pump wedge assemblies. Foundthe minor wear on wedge of JP-I 5 thatwas first identified in RF10 to beunchanged. Also performed VT-3examinations on the instrument lineattachment welds of all 20 jet pumps.

In RF12, performed examination ofmixer inlet areas for crud buildup on jetpumps 3 & 13, RS-3's for jet pumps 1-10, and RSI & RS2's for jet pumps 11-16. Also performed VT- I examinationof all 20 jet pump wedge assemblies.New wedge wear found on jet pumps 6and 13. Further expanded scopeinspections ofjet pumps in accordancewith BWRVIP-41 found set screw gapson jet pumps 5, 13 & 14. Gaps wereanalyzed and jet pumps 5, 13 & 14 werejustified for continued operation. Alsoperformed VT-3 examinations on theinstrument line attachment welds of jetpumps 1-10.

In RF 13, performed inspection of mixerinlet areas for crud buildup on jet pumps3 and 13, RS-8 & RS-9's jet pumps 1/2,3/4, 7/8, 9/10, 11/12, 15/16, 17/18, and19/20 (5/6 and 13/14 examined underscope expansion in RF12), WD-I pumps1-20, WD-2 pumps 1-20, AS-1 and AS-2pumps 5, 6, 13, & 14, and additionalexamination of the set screws andwedges on jet pumps 15 and 16 beforeand after the replacement of the mixersand the jet pump 15 & 16 wedges as aresult of wedge wear identified during

151

Page 153: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

the initial IVVI (OE33556).

Jet Pump Diffuser 2001 (RF8) EVT-I In RF8, baseline BWRVIP-41 EVT-I(VIP-41, Rev 1) exams were performed on all of the

diffuser welds of jet pumps I through 10.No indications.

2007 (RFII) EVT-i In R-I0, baseline BWRVIP-41 EVT-Iexams were performed on all of thediffuser welds ofjet pumps II through20. No indications.

CRD Guide Tube(VIP-47-A)

1999 (RF7)

2001 (RF8)

2005 (RF10)

2007 (RF 11)

VT-I &EVT-I

VT-i &EVT-1

VT-I &EVT- I

VT-I &EVT- I

In RF7, performed VT-I of alignmentpins and EVT-1 of the welds of 5 ControlRod Guide Tubes in accordance withBWRVIP-47. No indications.

In RF8, performed VT-I of alignmentpins and EVT-I of the welds of anadditional 4 Control Rod Guide Tubes inaccordance with BWRVIP-47 to meet the5% completion requirements ofBWRVIP-47. No indications.

In RF10, performed VT-I of alignmentpins and EVT-I of the welds of anadditional 5 Control Rod Guide Tubes inaccordance with BWRVIP-47. Noindications. The final CRD Guide Tubeexams to meet the total of 10%requirement (4 more), are scheduled forRFI 1.

In RFI 1, performed VT-I of alignmentpins and EVT-i of the welds of anadditional 4 Control Rod Guide Tubes inaccordance with BWRVIP-47 to meet theultimate 10% completion (i.e., 18 out of177) requirements of BWRVIP-47. Noindications.

CRD Stub Tube N/A N/A Not applicable to this plant.

In-Core Housings 2003 (RF9) VT-3 In RF9, performed VT-3 of a random(LPRMs) 10% sample of the LPRM's in response

to Revision 2 to SIL 409. No indications.

2005 (RF 10) VT-3 In RF10, performed VT-3 of a random

152

Page 154: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2007 (RF 11)

2009 (RF12)

2011 (RFI3)

VT-3

VT-3

VT-3

10% sample of the LPRM's in responseto Revision 2 to SIL 409. No indications.

In RF 11, performed VT-3 of a random10% sample of the LPRM's in responseto Revision 2 to SIL 409. No indications.

In RF 12, performed VT-3 of a random10% sample of the LPRM's in responseto Revision 2 to SIL 409. No indications.

In RF 13, performed VT-3 of a random10% sample of the LPRM's in responseto Revision 2 to SIL 409. No indications.Replaced 6 LPRM dry tubes to addressstuck detectors and the potential forcracking as these components havereached end of life. (Additionalreplacements planned for subsequentoutages.)

Dry Tubes (IRMs &SRMs)

1989 (RF 1)1990 (RF2)1994 (RF4)1999 (RF7)

2001 (RF8)2003 (RF9)2005 (RF 10)2007 (RF 11)2009 (RF12)2011 (RF13)

VT-3VT-3VT-3VT-3

VT-3VT-3VT-3VT-3VT-3VT-3

In RFI, RF2, RF4 and RF7, performedVT-3 of upper 2 ft of all IRMs and SRMsin accordance with SIL 409 and RICSIL73. No indications.

In RF8, RF9, RF10, RFI 1, RFI2, andRFI3 performed VT-3 of upper 2 ft ofhalf the IRM's and SRM's in eachoutage. No indications.

InstrumentPenetrations (VIP-49-A)

1989-2005(RF I thruRF10)

2005 (RFI0)

2007-2011(RFI 1,RF12, &

VT-2

PT

VT-2

Undervessel (i.e., through the skirtmanway) and inside the bioshield directvisual examination for leakage performedevery refueling outage. No indications.

SIL 571 surface examinations of thesocket weld connection and all accessiblepenetration base metal surfaces for twoof the 14 level instrumentpenetrations. No indications.

Undervessel (i.e., through the skirtmanway) and inside the bioshield directvisual examination for leakage performed

153

Page 155: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

RF13) every refuelinv outne. No indications.RE 13) every refueling outage. No indications.4 I.

Vessel ID Brackets(VIP-48-A)

1989 (RFI)1994 (RF4)1996 (RF5)

1999 (RF7)

2001 (RF8)

2003 (RF9)

2009 (RF12)

2011 (RFI3)

VT-I &VT-3VT-l &VT-3VT-I &VT-3

MVT-l

EVTI

VT-3 &EVT1

VT-3

EVT- I &VT-3

Section XI examinations of the jet pumpriser brace, feedwater sparger bracket,core spray piping bracket, surveillancespecimen capsule bracket, steam dryer,and guide rod vessel attachment welds.Scheduled such that each attachmentweld is examined once an interval. Thelast welds to be examined were thesurveillance capsule bracket attachmentwelds in RF5. No indications.

In RF7, performed MVT-1 of theFeedwater Sparger brackets inaccordance with the normal frequency ofASME Category B-N-2, but utilized theMVT-1 method in accordance withBWRVIP-48. No indications.

In RF8, performed EVT-1 of the SteamDryer support brackets and Jet PumpRiser Brace attachment welds inaccordance with the normal frequency ofASME Categories B-N-2, but utilized theEVT- I method in accordance withBWRVIP-48 and BWRVIP-41. Noindications.

In RF09, performed VT-3 of theFeedwater Sparger brackets and EVT-Iof the Core Spray piping brackets. Noindications.

In RF 12, performed VT-3 of the Guiderod support bracket attachments,surveillance sample holder. Surveillancesample holder at 177' exhibited a bentbail handle, justified for continuedoperation.

In RF 13, performed EVT-I/VT-3 ofFeedwater sparger bracket to vesselwelds at 005, 055, 065, 115, 125, 175,185, 235, 245, 295, 305, and 355degrees. Also performed EVT-1 ofDryer Bracket to Vessel welds at 030,

154

Page 156: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

090, 150, 210, 270, and 300 degrees. Norelevant indications found.

LPCI Coupling(VIP-42-A)

1994 (RF4)

1997 (RF6)

1999 (RF7)

2003 (RF9)

VT-3

VT-3

MVT-I

EVT-I

2005 (RF 10) 1 VT-3

The LPCI deflectors (inside the coreshroud) were examined in RF4. Noindications.

The LPCI internal piping, including thecouplings, was examined in RF6. Noindications.

In RF7, performed MVT- I baselineexams on the welds of all three LPCIcouplings (A, B & C) in accordance withBWRVIP-42. No indications.

In RF9, performed EVT- I exams on thewelds of the LPCI "A" coupling inaccordance with BWRVIP-42. Noindications.

Although not required by BWRVIP,performed a VT-3 of the Low PressureCore Injection (LPCI) deflectors andattachment welds from inside the shroud.Performed while the periphery of theinside of the shroud was accessible dueto vacating the cells for the Tecnatom IDCore Shroud inspection tool. Noindications.

In RFI 1, performed EVT-I exams on thewelds of the LPCI "B" coupling inaccordance with BWRVIP-42-A. Noindications.

In RF 13, performed EVT-I exams on thewelds of the LPCI "C" coupling inaccordance with BWRVIP-42-A. Norelevant indications.

2007 (RFI 1) 1 EVT-I

2011 (RF13) I EVT-I

RPV Interior (not a 2003 (RF9) VT-3 The RPV Interior exam is performed inBWRV1P scope item) accordance with ASME Category B-N-I

every other outage and is not usuallyreported on herein. However, RF9'sexamination results are noteworthy as theRPV Interior exams identified deposits

155

Page 157: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2005 (RF 10)

2007 (RF 11)

VT-3

VT-3

on the vessel interior walls in the areasadjacent to the Main Steam nozzles.Subsequently in extent of conditionexams, similar deposits were found onthe Steam Dryer outside shroud surfacesin areas corresponding to the Main Steamnozzles. The deposits are extremely hard(i.e., cannot be scraped or hydrolasedoff). From a BWRVIP standpoint, thedeposits are considered significant asthey are a result of the mitigating waterchemistry (i.e., Hydrogen WaterChemistry with depleted Zinc andNobelChem).

Re-inspection of the upper vessel interior(steam region) to see if there was anychange in the unusual deposits that werefound in RF9. The unusual deposits werestill there, but they were essentiallyunchanged. from RF9 (i.e., no furtherdeposits noted).

Re-inspection of the upper vessel interior(steam region) to see if there was anychange in the unusual deposits that werefound in RF9. The unusual deposits werestill there, but they were essentiallyunchanged from RF9 (i.e., no furtherdeposits noted). Also performed theASME Code Category B-N-I VT-3inspections of the accessible interiorsurfaces. No indications.

Re-inspection of the upper vessel interior(steam region) to see if there was anychange in the unusual deposits that werefound in RF9. The unusual deposits werestill there, but they were essentiallyunchanged from RF9 (i.e., no furtherdeposits noted).

Re-inspection of the upper vessel interior(steam region) to see if there was anychange in the unusual deposits that werefound in RF9. The unusual deposits were

2009 (RF 12) 1 VT-3

2011 (RF 13) VT-3

156

Page 158: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

still there, but they were essentiallyunchanged from RF9 (i.e., no furtherdeposits noted). Also performed theASME Code Category B-N-I VT-3inspections of the accessible interiorsurfaces. No indications.

Steam Dryer (VIP-139)

1990 (RF2)

2003 (RF9)

VT-3

VT-3

2005 (RFI0) VT-3

2007 (RF11) VT-3

SIL 472 exams of the Steam Dryer drainchannels for cracking. No indications.

General exam of Steam Dryer exteriorlooking for extent of condition oftenacious crud found on the vesselinterior. Also used a Video-Raysubmersible to examine the Steam Dryerinterior. Other than heavy crud build-upon the 90 and 270 degree sides, therewere no indications.

General exam of Steam Dryer exteriorlooking for gross failures. Noindications. Detailed BWRVIP-139Steam Dryer baseline exams scheduledfor RF 11.

General exam of Steam Dryer exterior atthe 90 and 270 degree sides looking forgross failures and for any changes in thetenacious crud found in RFO9. Noindications. Detailed BWRVIP-139Steam Dryer baseline exams that wereoriginally scheduled for RFI I weredeferred to RFO 12.

Completed base line inspections perBWRVIP-139. Linear indications foundin LB3a (1450 lifting rod bracket), LA4(350 lifting lug tack weld), LD4 (325'lifting lug tack weld), a bent lower guiderod guide at 1800, and several smalllinear, horizontal, vertical, and radialindications in the upper support ring. Allindications were analyzed and justifiedfor continued operation. No change instucco crud deposits.

In RFI3 condition monitoring

2009 (RFI 2) 1 VT- I

2011 (RF 13) 1 VT- I

157

Page 159: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

inspections were performed as follow upto the RF12 base line inspections perBWRVIP-139. Linear indications foundin LB3a (1450 lifting rod bracket), LA4(350 lifting lug tack weld), LD4 (325'lifting lug tack weld), a bent lower guiderod guide at 1800, and several smalllinear, horizontal, vertical, and radialindications in the upper support ringfound in RFI2 were essentiallyunchanged. Several newly identified(i.e., may have previously existed andwere not detected during RFI2 baselineexams) very small linear indications werealso found in the upper support ring andwere justified for continued operation.No change in stucco crud deposits.

Access Hole Cover 1996 (RF5) VT-I VT-I examination of the access hole(VIP-I 80) cover welds in accordance with SIL-409.

2007 (RFI 1) EVT- I EVT- I examination of the access holecover welds in accordance with the draftBWRVIP AHC Inspection andEvaluation Guidelines. No indications.

Category C & E 2007 (RFI I) UT (Supp Examined 13 of Perry's 23 Category CDissimilar Metal 10 Exams) dissimilar metal welds (ten N2, two N9(DM) Weld Exams. and one N I Nozzle to SE welds). TherePerry has 23 Category were no unacceptable flaw indications.C DM welds, 2 One NI Nozzle to SE weld was notCategory E DM examined due to extreme hardship towelds (one weld access and dose concerns. Reliefoverlay repaired and Request submitted following the outageone just monitoring), to delete exam entirely based on a reviewand no Category D of previous examination data that wasDM welds. obtained with non-Suppnment 10

procedures but by techniques that werenear equivalent to Supplement 10.

2007 (RF 11) UT (Supp Examined Perry's Feedwater (N7)10 Nozzle to SE Category E dissimilar metalExam) weld that is not weld overlay repaired.

The flaw indications were found to beunchanged.

2009 (RF 12) UT (Supp Examined 9 of the remaining 10 Perry

158

Page 160: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

10 Exams) Category C dissimilar metal welds (fourN4, three N6 and two N5). Subsurface(i.e., fabrication) flaws identified in twoof the N6 Nozzle to SE welds prior toRFI2 by the required BWRVIP datareview, and which required an IWB-3600evaluation because they exceeded ASMEXl Table IWB-3514-1 acceptancecriteria, were found to be unchanged. Noother unacceptable flaw indications wereidentified. Note that prior to RFO 12, theRelief Request that was submitted for theN I Nozzle to SE weld that was notexamined in RFOI 1 was approved.Thus, Perry has completed all therequired Category C dissimilar metalweld Supplement 10 examinations.

2009 (RFI2) UT (Supp Examined Perry's Feedwater (N7)II Exam) Nozzle to SE Category E dissimilar metal

weld that is weld overlay repaired. Theoverlay exam found no unacceptableflaw indications.

159

Page 161: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Reactor Internals Insoection History

Plant: Pftrim

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Used Inspection Results, Repairs,

Inspection Replacements, Reinspections

CORE SHROUDShroud head bolts

Shroud

RFO 7

RFO 8

RFO 10

RFO 11

RFO 15

RFO 16

RFO 17

RFO 18

RFO 10(modif. andpartial VT),11 (UT of134" (25% oftotal) of vert.welds V 17and V18from shroudI.D.) 11(EVT- 1 of 14of 21 ringsegmentwelds)

UT

VT

UT

Replacement

Removal

VT-3

VT-3

VT-3 (89)

RFO 7 UT all 48 bolts

RFO 8 partial VT. No indications

RFO 10 UT of 100% of bolts, noindications

RFO 11 replaced 50% of bolts (even #bolts replaced per MR 19602446)

Removed 50% (24) of SHBs (odd #bolts) per ER 03114806 (MR 04116541)

Examined 25% (6) of shroud head boltswith one relevant indication noted anddispositioned

Examined 25% (6) of shroud head bolts;slight wear at SHB 18.

Re-examined (2) wear locations on SHBs4& 18

Shroud captured to limit extent underVT-3 exams of RPV Interior performedeach period. No indications. RFO 10PDC 94-43 VT exams only. RFO 11VT-3 of 315 degree tie rod and core platewedges, EVT- I of 315 degree gussetwelds.

160

Page 162: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

RFO 12

RFO 13

RFO 15

RFO 16

EVT-1

EVT-I

EVT-I

UT

EVT-I

EVT- 1/VT-1/VT-3

Examined V15, V16, V17, V18, V22 andV23. Total of vertical weld examinedfrom both sides by UT in RFO II andEVT I in RFO 12 is 46 %

With partial credit for one sidedexaminations the total is 51 %. This isthe maximum available with currenttooling. No indications.

Examined Ring Segment weld VI I fromthe OD. (no indications).

Examined 100% vertical/or radial weldsV9, V10, VI1I, V12, V13, V14 and V22(all OD side) with no relevant indicationsnoted (NRI's). Examined 70% weld V23(OD side) (NRI's). There was no ODside access to welds V7, V8, V30 andV3 1. Also, there was no ID side access towelds V7, V8, V22 and V23. TechnicalJustification #TJ-076-04, defers UTinspection of several vertical welds toRFO 16.

Examined 100% vertical welds V32 andV33 in shroud support cylinder (all ODside) (NRI's). There was no access tovertical weld V34.

Examined > 90% belt-line vertical weldsV15, V16, V17 & V18 (NRI's)

Examined 100% vertical welds V7 & V8(NRI's). There was no OD side access towelds V30 & V3 1. Also, there was noaccess to shroud support weld V34. Adeviation disposition will address theissuie

Examined the accessible surfaces,contact points, seating surfaces, lockingdevices and critical contact areas for thefour tie-rods per BWRVlP-76, industry

161

Page 163: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Shroud Tie Rods

RFO 17

RFO 10

RFO 16

RFO 17

RFO 18

UT

EVT- 1

EVT- 1/VT-1/VT-3

EVT- 1/VT-1/VT-3

EVT- I/VT-1/VT-3

EVT-I/VT-I/VT-3

OE's and repair vendor requirements.Replaced the upper supports at tie-rods450 and 2250 locations. Plans are toreplace in RFO1 7 the remaining twoupper supports at 135' and 315' (NRI's)

V30 & V31 examined with GE TS2 tool

V9, VIO, VI1, V12, V13, V14 in topguide support ring examined; V22examined in central mid-ring when 135tie rod was removed/replaced.

Installed 4 tie rods as pre-emptive repairfor shroud horizontal welds

Replaced upper supports at 45' and 2250tie rods due to Plant Hatch event.Examined the accessible surfaces,contact points, seating surfaces, lockingdevices and critical contact areas at all 4tie rods per BWRVIP-76, industry OE'sand repair vendor requirements.

Replaced entire tie rod at 1350 due tostuck nut and upper support only at 315'.Performed re-inspection of 45' and 2250tie rods from RFO 16 replacements.Examined the accessible surfaces,contact points, seating surfaces, lockingdevices and critical contact areas perBWRVIP-76, industry OE's and repairvendor requirements.

Re-inspected the RFO1 7-replacedhardware at tie-rod locations 1350 &3150 including entire 135 tie rodassembly and top assembly of 315 tierod. Added remainder of 315 tie rod toinspection scope for schedulingefficiency purposes.

SHROUD SUPPORTAccess Hole Covers 8 (UT), 9 UT exam in RFO 8 was for circ.

(VT), 10 (UT Cracking only. No indications. RFO 10radial of 0 visual indication at 0 degree coverdegree verified non-relevant by UT.

162

Page 164: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

cover), 10VT of 180degree cover)

RFO 14 EVT-I Examined at 00 and 1800 (NRI's)

RFO 16 VT-I Examined at 00 and 180' (NRI's)

Shroud Support Plate RFO 10 EVT-I Enhanced VT-I RFO 10. No indications.to RPV (H 1l) Weld

RFO 12 Examined 10 % of weld length with noindications.

RFO 15 EVT- I Examined 16% of weld length (top side)(N RI's).

VT-3 Examined 360' of weld length (top side)with NRI's.

RFO 17 EVT-1 Examined HI0 and H I between 128°-1420 when 1350 tie rod wasremoved/replaced.

RFO 18 EVT-i Examined HI 1 at 00 & 1800 between JPs20 & 01 and JPs 10 & 11.

Shroud Support Plate RFO 10 EVT-I/VT-I Enhanced VT-I RFO 10 of 4 gussetsGusset Welds (modification attach. Points), VT-I all

others (18).

RFO II EVT-1 No indications. RFO 11 EVT-I of gussetat 315 az.

RFO 12 EVT- 1 Examined gusset welds at 225,135, 45,15 and 345 degrees with no indications.

RFO 14 EVT- I Examined gusset welds at 75, 165,195,255,and 300 degrees.

RFO 15 EVT-I Examined all gusset welds at 30', 1200and 2400 (NRI's).

VT-3 Examined gusset-to-RPV welds at 300,600, 900, 105-, 1200, 1500, 210°, 240°,2700, 2850 and 3300 (NRI's).

163

Page 165: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

RFO 16 EVT-1 Examined gusset welds at 450, 135',2250 and 315' (NRI's)

RFO 17 EVT-1 6 gussets at 15', 60', 900, 1350, 2700 &315' examined.

RFO 18 EVT-I 4 gussets at 1350, 165', 315' & 345'examined.

CORE SPRAYPIPING

RFO 6, 7, 8,9, 10, 11

RFO 12

RFO 13

RFO 14

RFO 15

RFO 16

RFO 17

UT/EVT-i

EVT-I andUT

EVT-I

EVT- 1

EVT- I

EVT- I /VT-3

EVT- I

UT

3" long indications recorded previouslyin 1980, 81 and 84 on 'B' spargerbetween T-Box and B-25 nozzle. RFO 7and 8 exams show no indications. GEsuspected scale as possible source ofprevious indications. RFO II UTrevealed six cracked piping welds

EVT-1 of welds examined by EVT-I inRFO 11 revealed no indications. UT ofthe four P8b welds with indications fromRFO 11 revealed the indications to begeomnetric reflectors. All P9 welds wereexamined by UT with no indications. UTof 1 P5 and 3P5 , which had indications inRFO 11, revealed slight growth in theindication in IP5.

Examined all target welds excludingthose with RFO 12 ultrasonic results (noindications)

Examined target welds, no indications,one weld at lower, one mil, sensitivity.

Examined all creviced and tee box-to-pipe welds; and 25% rotating sample ofpipe elbow welds (NRI's)

Examined all piping brackets (4 total)support welds (NRI's)

Examined all creviced and tee box-to-pipe welds; and 25% rotating sample ofpipe elbow welds (NRI's)

Examined IP5 & 3P5 piping welds with

164

Page 166: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

pole-mounted GE CSI UT tool; previousindications from 1999 were determinedto be geometry.

EVT-I PlA, P2A, IP3, lP6, 1P7, IP8a, 1P8b,2P3, 2P4a, 2P4b, 2P5, 2P6, 2P7, 2P8a,2P8b, PI B, P2B, 3P3, 3P4a, 3P4b, 3P6,3P7, 3P8a, 3P8b, 4P3, 4P5, 4P6, 4P7,4P8a, 4P8b examined.

RFO 18 EVT-I PIA, PIB, P2A, P2B, 1P3, 2P3, 3P3,4P3, 2P5, 4P5, IP6, 2P6, 3P6, 4P6, 1P7,2P7, 3P7, 4P7, 1P8a, 2P8a,3P8a, 4P8a,I P8b, 2P8b, 3P8b, 4P8b, 1P4a, 4P4a,1P4b, 4P4b examined.

CORE SPRAY RFO 13 EVT-I All SI, S2, and S4 welds.SPARGER

VT-I All SB and 50% of the S3 welds, thesewere the upper sparger (no indications).

RFO 15 EVT-I All SI, S2, and S4 welds.

VT-I All SB and 50% of S3a,b welds; theseare the lower spargers (NRI's). No $3c(drains) were found.

RFO 17 EVT-I All SI, S2, and S4 welds.

VT-I S3a & S3b at 'A'(1 5°) & 'C' (1650) upperspargers examined. No $3c (drains)were found.

VT- I SB sparger brackets examined at all 4spargers

TOP GUIDE (RIM, RFO 6, 7, 8, Partial exams each outage. Someetc.) 9 scratches, wear marks; no cracking

found.

TOP GUIDE RFO 12 VT-I Examination of assemblies at 0 and 90ALIGNER degrees revealed no indicationsASSEMBLY

TOP GUIDE GRID RFO16 VT-I Examined accessible surfaces of gridBEAMS beams at six cell locations (most at high

fluence areas) (NRI's)

165

Page 167: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

RFO 18 EVT- I Examined 8 cells at locations 22-23, 26-23, 30-23, 30-27, 30-31, 34- 23, 34-19 &22-35 using GE automated TGIT tool.

CORE PLATE (RIM,etc.) RFO I Installed 104 core support plate plugs

(1974)

RFOI I Replaced all 104 core support plate plugs(1997)

RFO 16 VT-3 Examined all core plate wedges at 450,135', 225' and 315' (NRI's)

SLC RFO 13 VT-2 System Leakage Test (no leaks)

RFO 14 VT-2 System Leakage Test, insulationremoved, no indications.

RFO 15 PT Examined by PT. Exam was "accepted,no indications noted".

EVT-2 System Leakage Test, insulationremoved, no leaks detected.

RFO 16 EVT-2 System Leakage Test (no leaks)

RFO 17 PT Safe end weld and extension examined.

EVT-2 System Leakage Test, insulationremoved, no leaks detected.

RFO 18 UT Examined RPV-N14-1 safe end weld andentire safe end extension with GE manualphased array UT per BWRVIP-27A.

EVT-2 System Leakage Test, insulationremoved, no leaks detected.

JET PUMPASSEMBLYJet Pump Riser RFO 8, 10, VT No indications. RFO 10 100% done. DoBraces II 50% each RFO per OE item. RFO 11

VT-I of braces 5 through 14 (50%).

RFO 12 EVT-I All Riser Braces were examined at RB-1and RB-2 except for Jet Pump 3 and 5.No indications were found.

166

Page 168: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Jet Pump SensingLines

Jet Pump BeamAssemblies

Jet Pump AdjustingScrews

RFO 13

RFO 14

RFO 16

RFO 18

RFO 7, 8, 9

RFO 17

RF0 18

ReplacedRFO 6, RFO11 (UT, VT)

RFO 12

RFO 16

RFO 8, 10,I1

RFO 12

RFO 13

EVT-l

EVT-l

EVT-1

EVT-1

VT-3/VT-1

VT-3/VT- I

UT

UT

EVT- 1

UT

VT

VT-3

All RB l a,b & 2 a, b for RisersA,B,C,D,E,H and J(no indications)

Riser braces for pumps1,2,8,9,10,12,13,14,16,17 and 20.Noindications

Examined RB-Ia,b and RB-2a,b welds atJP #17/18 (NRI's)

Examined RB-la,b and RB-2a,b welds atJPs l, 2, 3, 4 & 5

No indications.

JPs I thru 10; sensing lines and bracketsupports per SIL 420 RI

JPs 11 thru 20; sensing lines and bracketsupports per SIL 420 Ri

RFO 11 (UT of 100%; VT of Jet Pumps5 through 14)

All beams examined at BB-1 and BB-2with no indications

Examined all twenty beams at BB-1, BB-2 and BB-3 (NRI's)

Examined beam at JP# 7 (NRI's)

No indications RFO 8. Gaps found RFO10, minor mech. Damage. Inspectiontied to Rise Brace cracking. RFO 11 VTof 100% of screws.

Gaps were measured for in all pumpsexcept for 5,6,7 and 11

Gaps were measured for on pumps1,4,6,7,8,9,16, and 17 (no change)

167

Page 169: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

RFO 16 VT-1/VT-3 Examined the "as found/as left" set screwgap measurements for aux wedgeinstallations at JP #01, 02, 8, 9, 11, 17 &20, including the aux wedge addition(NRI's)

RFO 17 VT- 1/VT-3 Re-inspected aux wedges (WD-1)installed in RFOI6 at JPs 01, 02, 8, 9, 11,17 & 20 (NRI's)

Jet Pump Restrainer RFO 11 VT-3 RFO 11 VT-3 of 100% of swing gates,Bracket and Swing wedges and screws. Found 10 out of 20Gate Assemblies swing gates in unlatched position.

RFO 12 VT-3 Inspected all Swing Gate assembliesexcept for 5 and 11

RFO 13 VT-3 Inspected assemblies for pumps1,4,6,7,8,9,16,and 17(no indications)

VT-3 Examined WD-I on pumps I to 10 (noindications)

RFO 15 VT-I Examined WD-I restrainer wedges on jetpumps #1, 2, 4, 6, 7, 8, 9, 10, 12, 13, 14,15, 16, 17, 19 and 20, with relevantindications noted only on JP-16 and JP-17. Examined RK-1, RK-2 and RK-3 atjet pumps #16 and #17 (NRI's).

RFO 16 VT-I Examined WD-1 restrainer wedges atJP's #3, 5, 11 & 18. Recordableindications were identified on the wedgehandle at JP's # 5 & 11. These weresatisfactorily dispositioned-Re-inspect inRFO- 17

Examined RK-1, 2 & 3 welds at JP#17(NRI's)

VT-3/VT-I Examined "as found/as left" ofexisting/replaced swing gates and wedgesat JP's #01, 4, 6, 7, 8, 9, 16 & 17 (NRI's)

RFO 17 VT-3/VT-1 Re-inspected swing gates replaced inRFO16atJPs 1,4,6,7,8,9,16&17

168

Page 170: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

(NRI's)

VT- I Re-inspected wedges (WD-l) replaced inRFO6 at JPs 1, 4, 6, 7, 8, 9, 16 & 17(NRI's). Also examined wedges (WD-l)and bent wedge handles (re-examined) atJPs5& 11.

RFO 18 VT-I Inspected wedges (WD- I) at JPs 2, 3, 10,12, 13, 14, 18, 19 & 20

Jet Pump Mechanical RFO II VT-I RFO II VT-3 of 50% of Jet Pumps (JetJoints Pumps 5 through 14) of rams head-to-

transition piece and lower slip joint-to-diffuser areas

RFO 12 VT-3 Inlet mixer to diffuser for I to 4 and 15 to20

RFO 13 VT-3 Examined rains head to transition pieceand lower slip joint to diffuser areas forpumps 1,4,6,7,8,9,16, and 17 (noindications)

RFO 16 VT-3 Examined slip joint at JP #17 (NRI's)

Jet Pump Riser Welds RFO 11 EVT-I All RS-I and RS-2 examined with noindications

RFO 12 EVT-I RS-3 of risers A to E examined with noindications.

RFO 13 EVT-I Examined RS-4, RS-5, RS-8 and RS-9for risers A,B,C,D and E (no indications)

RFO 14 EVT-I RS-3 of risers F to K no indications

RFO 16 EVT-I Examined the following JP riser weldswith NRI's:

RS-l, RS-2 and RS-3 at JP's 5/6RS-4 and RS-5 at JP's 15/16RS-8 and RS-9 at JP's 13/14 & 15/16

RFO 17 EVT-I Examined RS-1, RS-2 & RS-3 welds atJPs 1/2, 3/4, 7/8 & 9/10

169

Page 171: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Examined RS-4 & RS-5 welds at JPs11/12, 13/14, 17/18 & 19/20

Examined RS-8 & RS-9 welds at JPs11/12, 17/18 & 19/20. Also examinedadded scope RS-8 & 9 welds at JPs 5/6 &15/16 due to Laguna Verde event.

RFO 18 EVT-I Examined RS-I & RS-2 welds at JPs F,G, H, J & KExamined RS-8 & RS-9 welds at JPs A,B,D,E&GExamined RB-1 & RB-2 welds at JPs 1,2, 3,4 & 5

Jet Pump Diffusers RFO 13 VT-3 Examined IN-5 for pumps I to 10 (noindications)

EVT-1 Examined MX-1 for pumps I to 10 (noindications)

EVT-I and Examined MX-3, DF-I, DF-2, AD-3a, b,UT AD-1, AD-2 on pumps 13,14,15,16 and

17 by UT and pumps 11, 12, 18, 19and20 by EVT-1 (no indications)

RFO 14 EVT-1 Examined AD-2,AD-1,DF-2, and AD-3a,b for pumps I to 10, no indications.

RFO 16 VT-3 Examined IN-5 at JP #15 & 16 (NRI's)

EVT-I Examined MX-I at JP #15 & 16 (NRI's)Examined MX-3 and DF-I at JP #5 & 6(N RI's)

RFO 17 UT Examined (JPIT) DF-2, DF-3, AD-1,AD-2, DF- I & MX-3 welds at JPs 1-20.

EVT-I Examined MX-I at JPs 11-14 & JPs 17-20. Also did MX-I at JPs 8 & 9 due to135' tie rod removal/replacement.

VT-3 Examined IN-5 at JPs11,12,13,14,17,18,19,20. Also did IN-5atJPs 8 & 9 dueto 135' tie rod

170

Page 172: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

removal/replacement.

GUIDE TUBEHandle Attachment RFO 7

RFO 13

RFO 14

RFO 16

RFO 17

No indications

N/A FS/GT -ARPIN-1 at 8 locations

VT-3/EVT-I

VT-3/EVT- I

EVT- I/VT-3

CRGT1, 2 and 3 for 8 tubes, noindications

Examined FS/GT-ARPIN-1, CRGT-1, 2& 3 at 2 tubes (NRI's)

CRGT-1, CRGT-2, CRGT-3 & FS/GT-ARPIN-1 examined at cells 50-27, 50-31,50-39, 46-39 & 46-31.

CRD STUB TUBE RFO 7 No indications

RFO 16 VT-3 Examined accessible surfaces in lowerplenum at several locations (NRI's)

IN-CORE HOUSING RFO 16 VT-3 Examined accessible surfaces in lowerplenum at several locations (NRI's)

DRY TUBES RFO 16 VT-I Examined 4 (four) dry tubes per SIL-409,Rev 2 requirements (NRI's)

RFO 17 VT-I/VT-3 Replaced 6 dry tubes; performed PWTas-left exams of new dry tubes at SRM12-25, IRMs 12-41, 20-25, 28-25, 36-09& 36-41.

INSTRUMENT RFO 15 EVT-2 Enhanced system leakage test (insulationPENETRATIONS removed); no leakage detected)N15 & N16 partialpenetration nozzles RFO 16 EVT-2 Enhanced system leakage test (insulation

removed); no leakage detected)

RFO 17 EVT-2 Enhanced system leakage test (insulationremoved); no leakage detected)

RFO 18 EVT-2 Enhanced system leakage test (insulationremoved); no leakage detected)

VESSEL IDBRACKETS RFO 10 VT 3 locations. No indicationsSurveillanceSpecimen Brackets RFO 15 VT-I/VT-3 Examined attachment welds at all 3

171

Page 173: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Attachment Welds

Feedwater BracketAttachment Weld

Guide Rod BracketAttachment Welds

Steam Dryer SupportBracket

Steam Dryer Hold-Down Bracket Welds(on head)

Abandoned Start-upInstrumentationBrackets

RFO 17

RFO 14

RFO 18

RFO 10, 11(180 az guiderod)

RFO 15

RFO 7, 8, 9,10,11

RFO 15

RFO 10

RFO 15

RFO 11

RFO 17

VT-3

VT-3/EVT-1

VT-3/VT- I

VT-3

VT-3/EVT-1

VT-3

VT-I

VT-I

locations (NRI's). Re-engaged the lowerend of sample holder at 2100 back to theproper location (CR-PNP-2005-02137).

Re-examined surveillance sample holderlower bracket at 210' found dis-lodgedin 2005 (NRI).

Code and BWRVIP examination of allattachments

Code and BWRVIP examination of allFW bracket attachment welds.

No indications

Examined guide rod attachment welds at0' and 1800. No relevant indicationsnoted.

No Indications

Examined support bracket attachmentwelds at all four locations (NRI's).

Located underside of RPV head Noindications

Examined hold-down bracket attachmentwelds at all four locations (NRI's).

Brackets welded to RPV wall at 90 and150 az received VT-i in RFO 11

Bracket at 1500 cut back (EDM) toremove interference for future NI Bnozzle plug installation.

STEAM DRYERSteam Dryer Drain RFO 8, 9, 11 No indicationsChannels

RFO 12 VT-3 No indications

RFO 16 VT-I No indications

172

Page 174: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Steam Dryer Leveling R-F 7, 8, 9, Cracked tack welds RFO 7; no growthScrews 10, 11 observed in 8, 9 and 10. RFO 11 VT

showed increased cracking of tack weldsat 35 and 215 degree leveling screws,with 215 az screw loose.

RFO 12 VT-3 No change from RFO II

RFO 13 VT-3 No change from RFO 12

RFO 14 VT-3 Change in cracks

RFO 15 VT-I Examined leveling screws at 350, 145',215' and 3250. There was no change intack weld cracks at 350 and 2150 andNRI's at 1450 and 3250

RFO 16 VT-I Examined leveling screws at 350, 1450,2150 and 3250. There was no noticeablechange in tack weld cracks at 350 and215' and NRI's at 145' and 3250

RFO 17 VT-I (89) Examined leveling screws and liftinglugs at 350, 1450, 2150 and 3250. Nonoticeable change in tack weld cracks at350 and 215' and NRI's at 145' and3250

RFO 18 VT-I (89) Examined leveling screws and liftinglugs at 350, 145', 2150 and 3250. Nonoticeable change in tack weld cracks at350 and 2150 and NRI's at 1450 and 3250

Steam Dryer Baffle RFO 7, 11 VT-3 No indications.Plate

Steam Dryer Integrity RFO 14 VT-I SIL 644

RFO 15 VT-I Examined steam dryer integrity per SIL644, Rev. 1 guidelines on OD side abovedryer supporting ring. Examinationincluded all vertical welds, horizontalwelds at end banks and end welds at allten tie-bars. Relevant indications werenoted at an end weld of each tie-bar #3,

173

Page 175: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

RFO 16

RFO 17

RFO 18

VT-I /VT-3

VT-I (89)

VT-1 (89)

4, 5 and 9 (CR-PNP-2005-01608). Atotal of seven tie-bars were replaced andfurther examined to establish inspectionbaseline. These are #1, 2, 3, 4, 5, 9 and10.

Completed steam dryer integrityexaminations per requirements ofBWRVIP-139 (this included ID and ODside). Examined welds on the originaland replaced (RFO 15) tie-bars; guidechannels; guide followers; upper supportring; internal Hood A and E horizontaland vertical welds and internal drainchannels Relevant indications were foundon the ID side of the dryer at vane BankE weld and in the weld at divider plateanchor #5 between Bank C and D.Indications were satisfactorilydispositioned (Plan to re-inspect againthe indication in the divider plate anchor)

Examined all four lifting rod assembliesand attachment welds (NRI's)

Examined hood welds HA-6, HA-8 &HA-10 from the ID surface (air bubblesremoved)

Re-examined linear indication on steamdryer divider plate anchor #5 weld (nochange from RFO 16)

Re-examined linear indication on steamdryer divider plate anchor #5 weld (nochange from RFO 17)

MOISTURE RFO 16 VT-3 Examined all four lifting rod assembliesSEPARATOR and guide pins at two locations (NRI's)

RFO 17 VT-1 (89) Examined 4 upper and 4 mid-supportring gusset locations (NRI)

VT- 1 (89) Performed overview of separator tiestraps

RFO 18 VT-I/VT-3 Inspected all 4 separator lifting lug

174

Page 176: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

(89) assemblies (VT-I) and guide pins (VT-3). Cracking found on all 4 lifting lugs(lug azimuths in order of crackingseverity: 0080, 3000, 1880 & 120°). JCOdeveloped allowing 2 additional cycles ofoperation. Repair planned for next outage(RFO 19).Mechanical damage found at 180' guidelug determined to be preexisting.

LPCI COUPLING N/A N/A N/A

FEEDWATER RFO 6, 7, 8, VT No indications.SPARGERS 9, 10

RFO 14 VT-3/VT-I All spargers, no indications

RFO 18 VT- I Flow holes and welds in sparger arms,tees and end caps at Spargers "A", "B","C" & "4D".

VT-3 Sparger piping, end brackets & pins atSpargers "A", "B", "C" & "D"

VT-3/EVT-I Bracket integral attachment welds toRPV (8 places) at Spargers "A", "B","C" & "D"

FW Sparger End RFO 17 VT-I Examined all 8 brackets and pins (NRI)Brackets/pins

BWRVIP-75-A RF0 14 UT (Manual) JPI nozzle safe end weld RPV-N9B-IDISSIMILARMETAL WELDS RFO 15 UT (Auto) Recirculation inlet nozzle safe end weldsCategory D 2R-N2D-1, 2R-N2E-1, 2R-N2F-1, 2R-

N2G-I & 2R-N2J-1.Recirculation outlet nozzle safe end weld2R-N lB-I.Core Spray nozzle welds 14-A-I, 14-B-I,14-A-3, 14-B-3.

UT (Manual) Core Spray piping welds 14-A-0I A &14-B-10A

RFO 16 UT (Auto) Recirculation inlet nozzle safe end welds2R-N2H-1, 2R-N2K-1 & 2RN2F-1.Indication detected in N2K weld,repaired by overlay. Scope expansion

175

Page 177: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

included welds 2R-N2A-I, 2R-N2B-l &

RFO 18

UT (Manual)

UT (AutoPA)

UT (ManualPA)

included welds 2R-N2A- 1, 2R-N2B- I &2R-N2C-I.

JPI nozzle safe end weld RPV-N9B- I

Core Spray nozzle welds 14-A-I, 14-B-I,14-A-3, 14-B-3,Recirculation inlet nozzle safe end weld2R-N2G-I

Core Spray piping welds 14-A-10A &14-B-10A

BWRVIP-75-ADISSIMILARMETAL WELDSCategory E

RFO 17 UT (manual)

UT (manual)

RPV-N9A-I - Existing JPI N9A nozzlesafe end weld overlay was re-overlaid inRFO17 to make it inspectable underSupplement 11. Weld had beenpreviously overlaid in 1984 to repair twoindications in HAZ of safe end weld. Noindications reported in 2009 exam.

3-I-IR - Capped NIO CRD returnnozzle safe end weld was overlaid in2003 to repair through-wall leak. Noindications reported in 2009 exam.

176

Page 178: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Reactor Internals Inspection History

Plant: Quad Cities Unit 1

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Used Inspection Results, Repairs,

Inspection Replacements, Reinspections

Core Shroud 04/94 EVT-l and Inspections per SIL 572, indications in(BWRVIP-76) UT circumferential welds.

03/96 EVT-l and Inspections per BWRVIP Guidelines ofUT all Shroud repair design reliant hardware

prior to installation of comprehensiverepair (4 GE designed tie-rodassemblies). Inspection of shroudconsisted of EVT-I of all ring segmentwelds (accessible surfaces), EVT-1 ofvertical welds between H1I & H2 ODsurface 100% (ID not accessible), UT ofall 6 beltline vertical welds >30%length/weld, and EVT-I of vertical weldsbetween H6 & H7 OD surface >25%length/weld (ID not accessible).

11/98 VT- I No Reportable Indications.

10/00 UT Future inspections to be in accordancewith BWRVIP-76; Reinspection ofRepaired Core Shrouds.

Shroud repair hardware inspected per GErecommendations. No ReportableIndications.

Inspected shroud vertical welds V-14through V-19, inclusive, in accordancewith BWRVIP-76. One recordableindication on V-19 was acceptable toEOI under BWRVIP-76.

11/02 EVT-I 6 vertical welds from the OD perBWRVIP-76.No indications. The steam dam abovethe shroud flange had impact damageevaluated as acceptable as-is for

177

Page 179: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

indefinite continued operation.

04/05 EVT-I Examined Ring Segment Welds VI-V4(Shroud Head RSWs), V8-V13 (TopGuide RSWs), and V20-V25 (Core PlateSupport RSWs). NRI, but indicationsnotes in HAZ of shroud horizontal weldH-05-OD near core plate support RSWs.(Horizontal welds structurally replacedby shroud tie rod repair).Examined three shroud vertical weldsInaccessible for UT Inspection to gainadditional coverage (V 17, V 18, andV19). NRI

05/07 EVT-1 Examined 6 vertical welds from the OD(V-05, V-06, V-07, V-26, V-27, and V-28). NRI

05/09 UT Examined all I 1 vertical welds accessiblefor UT. One weld behind tie rod supportnot accessible. One IGSCC indication1.8" long identified in V19 HAZ.

05/11 EVT-1 Examined 16 ring segment vertical welds(VI, V2, V3, V4, V8, V9, V10, VII,V 12, V13, V20, V21, V22, V23, V24,and V25) per BWRVIP-76-Arequirements. No reportable indicationsnoted.

Shroud Repair 05/07 EVT-1, VT-3 EVT-I of all tie rod upper supportHardware vertical faces, VT-3 of high-stressed(BWRVIP Letters fasteners and other contact points, and2006-112 and 2006- overall VT-3 per BWRVIP Letters 2006-220) 112 and 2006-220. Also, VT-3 of core

plate wedges adjacent to repair hardware.No reportable indications.

Shroud Support 3/96 EVT-I EVT-I of H8 and H9 for approx 12" at 4(BWRVIP-38) locations of shroud repair hardware

attachment areas.Access hole covers; VT/UT in 1992,circumferential indications observed,permanent repair installed.

10/00 EVT-I Inspected H8 and H9 adjacent to AHC at

178

Page 180: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

JP# 10 & I I in accordance withBWRVIP-38. No reportable indications.

03/05 EVT-I Inspected H8 and H9 adjacent to JP# 7 &20 from annulus top side. Also inspectedH8 and H9 adjacent to JP# 7 & 20 frombottom side through disassembled jetpumps.

05/07 N/A No inspections performed.

05/09 N/A No inspections performed.

05/11 EVT-I Inspected H8 and H9 welds accessibleareas from the Annulus top side perBWRVIP-38 requirements. Noreportable indications noted.

VT-I Performed examination of themechanically repaired Access HoleCovers (AlIC) at 335° and 155°. Noreportable indications noted.

Core Spray Piping 1980 to 1994 VT-I (I mil) IEB 80-13/NUREG of piping and welds(BWRVIP-18) in annulus. Indication previously

observed during 1994 on T-box waspermanently repaired in 1996. Repairexamined 11/98 with no reportableindications.

04/96 EVT-I EVT- I performed to intent of BWRVIP-18 in 1996. Indications observed at twolower elbow welds, full structuralmargins on non-repaired welds.Future inspections per BWRVIP- 18.

11/98 Auto UT GE CSI-2000 with supplemental EVT-IEVT- I for unqualified welds (P8a & P4d).

Identified one new flaw at P4d 1100downcomer similar to previouslyidentified flaws at the P4d 2600 & 2900downcomers. All flaws were evaluatedfor at least 48 months of operation withfull structural margins without repairs.Previously identified flaws weredetermined to be of less extent thanoriginally sized.

179

Page 181: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

EVT-1 Inspected P8a and P4d welds @ 4downcomers in accordance withBWRVIP-18. Existing flaws at P4dwelds at 1100, 2600 and 2900downcomers showed no discernablechange from 1998 inspection.

10/00 UT BWRVIP- 18 UT examination of allaccessible Welds (32). During theprevious outage, indications wereobserved on welds 2P4D, 3P4D, and4P4D (2 separate indications) and thesewere re-inspected this outage. A newindication was also observed on 3P4Dthat was not observed in the earlieroutage. All were evaluated as acceptablefor at least one cycle.

11/02 EVT-I BWRVIP-18 EVT-I on 12 weldsinaccessible to UT. Confirmedindications on welds identified by UT.No other indications. Re-inspected T-Box repair; no indications. The corespray piping bracket clamp at 1250 wasfound loose. This condition was acceptedas-is with a recommendation forreexamination.

EVT-I Lower Elbow to Shroud Pipe WeldsIP4d, 2P4d, 3P4d, 4P4d. NRI on IP4d.No change in indications on 2P4d, 3P4d,4P4d since last exam in 2002(R17).Collar Weld to Shroud Pipe WeldsI P8a, 2P8a, 3P8a, 4P8a. NRI. Best efforton 4P8a. Separator lugs and tie rodslimited views on lower half.Supplemental visual to disposition UTindication in base metal from RI 7. NRI

03/05 VT-1, VT-3 Welds BPI, BP2, BP3, 2P2, 2P3, 3P3 atTee Box repair (clamp interferes withEVT-1). NRI

UT UT Examination of 36 welds (32 weldsin target set plus non-demonstrated

180

Page 182: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

exams on P8A welds). Sized previousindications on 2P4d, 3P4d and 4P4d withlittle or no change from previous. Newindications on 2P4a and 4P4a that couldnot be confirmed visually.

05/07 EVT-1 Inspected 16 P4 welds; four P8a welds;3P6, 2p3 and 3P3, BP1 and BP2 at TeeBox repair; Tee Box repair clamp.Measured indications on 2P4d, 3P4d and4P4d with no change from previous.

05/09 EVT-1 Inspected 20 welds: 5 P4 welds withprevious indications, II for which two-sided UT is not demonstrated (8 P8 and3P4), and 4 that can only be inspectedfrom one side due to repair clampinterferences (BPI, BP2, 2P3, 3P3). Nonew RI. No change in previousindications.

05/1I EVT-I Inspected 22 welds per BWRVIP-1 8 Rev1: 1 P1, 1 P2, 4 P3, 4 P4a, 4 P4d, 4 P8a,4 P8b. No coverage on 2P2 due toclamp. An INR documents no change inprevious indications on 2P4d, 3P3, 3P4d,4P4d; accept as-is.

Examined all 8 Core Spray pipingbracket vessel ID Attachment welds perBWRVIP-48-A and BWRVIP-18 Rev 1.NRI.

VT-I/VT-3 Examined repair Clamp at 1850. Noreportable indications.

UT UT Examination of 34 welds: API, AP2,IP3, 2P3, 4P3 and all four of P5, P6, P7,P8a and P8b. 15 for which two-sided UTis not demonstrated (8 P8, 3 P4, and 4P3) and 2 that can only be inspected fromone side due to repair clamp interferences(BPI, BP2). All 4 P4b for required 25%sample of P4 welds. Limited (one-sided)exams on all 4 P4d, and 2P4a and 4P4a.

181

Page 183: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

ICNFs document no change in previous______________ I I_______ _______ indications; accept as-is.

Core Spray Sparger(BWRVIP-18)

1980 to 1994

04/96

11/98

11/02

03/05

05/07

05/09

05/11

VT-I (I mil)

EVT-1 orVT-3

EVT-1MVT-1

EVT-1 ofSI,S2, &S4;VT-1 ofS3:VT-1 ofbrackets

N/A

EVT- I

N/A

EVT- I/VT- I

IEB 80-13 of welds on sparger. Noindications found.

EVT-l performed to intent of BWRVIP-18, on T-box cover plate welds, T-box tosparger welds, end cap welds and bracketwelds. VT-3 of spargers and nozzles.

Future inspections per BWRVIP-18.

End caps, cover plates and tee branchwelds were EVT-I examined. Allsparger connections and bracket weldswere MVT- I examined. No reportableindications.

Examined all 20 S1, S2, and S4 spargerwelds, 50% of the S3a, b & c nozzlewelds, and all 12 sparger brackets.Examined for IEB 80-13 and BWRVIP-18. No indications.

No examinations performed.

Examined all 20 S1, S2, and S4 spargerwelds. No indications.

No examinations performed.

Examined 32 Sparger pipe and bracketwelds and all Nozzles on all 4 lowerspargers per BWRVIP-18, Rev 1. AnINR documents no change in minormovement on the 1900 Bracket; acceptas-is.

CNFs

document no change in previous

indications;

accept as-is.

Top Guide (Rim, etc.) 03/94 VT-I VT-I of 4 cells. No indications.(BWRVIP-26,BWRVIP-183) 04/96 VT- I VT- I of alignment assemblies. No

indications.

11/98 VT-I VT-l of alignment assemblies andadjacent rim welds. No reportableindications.

182

Page 184: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

10/00

11/02

03/05

05/07

05/09

EVT- I

VT-3

EVT- 1, VT- I

N/A

VT-I

EVT-I

Inspected accessible areas of location I Iin accordance with BWRVIP-26. Noreportable indications.

Examined 9 pin welds (FS/GT-ARPIN-1)per BWRVIP-47. No Indications.

Alignment pin assemblies at 00 and 2700.NRI. EVT-I of rim weld. Numerousmachined holes identified in thehorizontal plate adjacent to the rim weldsimilar to those found on Unit 2.

No examinations performed.

Alignment pin assemblies at 90' and1800. NRI.

EVT- I of accessible portions of rimweld. NRI.EVT-I of 9 top guide grid cells (5%).NRI.

± 4

Core Plate (Rim, etc.)(BWRVIP-25)

N/A

11/98

05/07

N/A

VT-I

VT-3

Installed core plate wedges inconjunction with comprehensive shroudrepair 1996.

Wedges inspected in conjunction withshroud repair hardware. No reportableindications.

Wedges inspected in conjunction withshroud repair hardware. No reportableindications.

.4- 4

Jet Pump Assembly(BWRVIP-41)

03/94 VT- I Hold down beams, beam bolt keepers,lock-plates and retainers; restrainerwedges, stops, and adjusting screws,clamp bolts and keepers; riser braceassemblies, adapter and baffle platewelds, sensing lines and sensing linebrackets per various SILS. Latestinspections were in 1994. No reportableindications.Diffuser to baffle plate welds examined.No reportable indications.

183

Page 185: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

04/96 VT- I Jet pump riser brace to riser weld at JP5/6 repaired 1994, repair examined 1996and 1998, no changes noted. Diffuser tobaffle plate welds examined. Noreportable indications.

04/96 UT One jet pump beam replaced 1986 due toindication. Jet pump beams are UTexamined each outage using techniquecapable of detecting cracking at throatand ears. No subsequent indications.

11/98 VT-I Inspected all 20 jet pump assemblies.Identified indication at JP7/8 riser braceto riser weld. Repair installed 4/99.

11/98 EVT- I Inspected jet pump riser welds RS- I,-2&-3. Visually identified 3 indications atJP 19/20 RS-1 weld. Subsequently sizedindications with UT. The RS- I weld wasevaluated for at least 24 months ofoperation with full structural marginwithout repair.

10/00 EVT- I Inspected >50% of high priority welds(DF-2, AD-3a,b, AD-I &AD-2) inaccordance with BWRVIP-41. Onerecordable indication at JP-16 backingring adjacent to AD-3a,b oriented axiallyacross backing ring. Expanded sample toinclude 100% of AD-3a',b welds.Inspected BWR-3 beams at 16 jet pumpswith UT (ends and center) in accordancewith BWRVIP-41. No reportableindications. The RS-I weld at JP 19/20was permanently repaired.

11/02 EVT-I EVT-I of DF-2, AD3-a&b, AD-1, AD-2for all 20 jet pumps (except DF-2 on JP11; EVT-I of RB-I and RB-2 of pumps3, 4, 9, 10, 11, and 15-20; EVT-I ofrisers on jet pumps 3/4, 9/10, 11/12,15/16, 17/18, and 19/20; EVT-I of MX-2, MX-3a&b, and MX-4 on pumps 4, 5,9, 10, 11, 14/18 and 20; EVT-I of MX-1

184

Page 186: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

and DF-1 for pumps 6-11, 14-18 and 20;EVT-1 on the risers of pumps 3/4, 9/10,11/12, 15/16, 17/18, and 19/20; VT-I ofAS-I and AS-2 on pumps 5, 7, 8, and 20,VT-of wedges on jet pumps 16 and 20,VT-I of clamp at RS-1 on jet pumps19/10, and VT-3 of existing repairhardware at IN-5 on pumps 6-11, 14-17and 20.

One indication was found on JP 2 at AD-3b and two indications were found on JP7 at AD-3b.Jet pump sensing line clamps wereinstalled on 8jet pumps (1, 2, 3, 10, 11,12, 13, and 20).

03/05 EVT-I Risers: Six RS-1 welds, five RS-2 welds,and all ten RS-3 welds due to limitedexams previously. Examined RS-4 andRS-5 on riser 11/12. Re-examined RB-lb on JP3, RB-2b on JPI I and RB-2a onJP 20. All NRI.Mixers: Examined MX-2 in JP 11 and14. Examined MX-3a&b on 17 & 18.NRI.Diffuser/Adapter: Examined high prioritywelds, including 11 AD-1, 12 AD-2, 12AD-3a,b, and II DF-2 (reinspection ofJP2, JP7, JP16 known flaws). Oneadditional branch noted on JP16indication compared to previous exam in2000. No discernable change in previousindications on JP2 and JP7. No other RI.

VT- 1, VT-3 Reinspected repair on Jet Pump 19/20RS-l. NRI

05/07 EVT-1 Re-measured previous indications at AD-3a,b on JP2, JP7 and JP 16. No changes.

VT- 1, VT-3 Inspected all main wedges with nounusual wear noted.Inspected one aux wedge and set screw.NRI.

185

Page 187: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

05/09 EVT-1 71 medium priority componentsinspected to complete baseline exams.NRI.

VT-I Inspected all main wedges with nounusual wear noted. Inspected one auxwedge and set screw. NRI. Replaced onehold down beam on JP05. Installed oneaux wedge on JP05 due to gapdiscovered during post-installationinspection.

VT-3 Inspected IN-5 bolting. Inspected oneJPSL clamp installed in 2007. NRI.

05/11 EVT-1 I medium priority Riser Brace (RB-la onJP 4. NRI.15 high priority riser welds (RS-1, RS-2and RS-3 on risers 1/2, 5/6, 7/8, 13/14,19/20, except RS-I on JP 19/20 which iscovered by a clamp). One RI for JP13/14 which had two indications reportedin the HAZ of the RS-2 weld on theelbow side of the weld on the extrados ofthe elbow. An INR documents thiscondition; technical evaluationperformed to accept as-is for one cycle ofoperation. Examined the remaining 5RS-2 welds for extent of condition withno additional reportable indicationsidentified.10 medium priority riser welds (RS-8 andRS-9 welds on risers 3/4, 9/10, 15/16,17/18). NRI.12 medium priority DF-1 and DF-2welds (JP 2, 3, 4, 5, 8, 9, 12, 13, 14, 17,18, and 19). NRI.14 high priority AD-3a,b welds (JP 2, 3,4, 5, 7, 8, 9, 12, 13, 14, 16, 17, 18, 19)(reinspection ofJP2, JP7, JP16 knownflaws). An INR documents no change inknown flaws on JP2 and JP7. Previouslyreported JPI 6 flaw was found to be anon-relevant scratch.18 medium priority AD-I and AD-2welds (both welds on JPs 1,2, 6, 7, 10,

186

Page 188: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

13, 14, 19, and 20). NRI.

UT

VT-I

Performed UT on 8 Modified Group-2Jet Pump Beams. The remaining 12beams are Group-3 style beams and werenot inspected. The UT identified noreportable indications.

20 Jet Pump wedges WD-1. An INRdocuments existing wear on JPI18 with nodiscernable changes; accept as-is. TwoINRs also document no change in slightwear on JPI0 and JP19 wedge rodsleeves; accept as-is.

Examined Aux wedges and set screws onJP5 and JP20.

Examined the JP sensing line clamp onJP 2.

Examined the retainer cup tack welds on6 swing gates on JP 6, 12, 14, 16, 19, 20.An INR documents no change in a JP 19tack weld area where fusion to thebracket brace metal is not evident. Norotation evident. Accept as-is.

CRD Guide Tube(BWRVIP-47)

11/02

03/05

05/07

05/09

VT- I, VT-3on CRGT- l;EVT- 1 onCRGT-2 & 3

N/A

N/A

VT-3, EVT- I

Examined 9 sets of guide tube welds(CRGT-1, CRGT-2, and CRGT-3) andone additional weld (CRGT-2) perBWRVIP-47. No Indications.

No inspections performed.

No inspections performed.

Examined 9 sets of CRGT-1 and FS/GT-ARPIN (NRI) and 9 CRGT-2/CRGT-3.Metal slivers attached to one CRGT-2from initial manufacture.

CRD Stub Tube N/A N/A N/A(BWRVIP-47)

In-Core Housing N/A N/A N/A(BWRVIP-47)

187

Page 189: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

IRM/SRM Dry Tubes(SIL 409)

03/94

03/96

10/00

11/02

VT

VT

Replaced 2 dry tubes 1994.

Replaced 5 dry tubes in 1996.

MVT-I

VT-I

Inspected original dry tubes at 7locations. No recordable indications.

Examined 5 dry tubes. Verified plungersengaged at Top Guide. No ReportableIndications.

All remaining original dry tubes (5)replaced.

04/05 N/A

Standby Liquid 04/05 PT Nozzle To Safe End, N 10-F l. NRIControl(BWRVIP 27) 05/09 PT Nozzle To Safe End, N 10-F1. NRI

Instrument N/A N/A N/APenetrations(BWRVIP-49)

Vessel ID Brackets 03/94 VT-I and Section XI inspections ofjet pump riser(BWRVIP-48) VT-3 brace, dryer, feedwater sparger, core

spray, and surveillance capsule holder

brackets, performed once per interval.VT-3 or VT-I if in beltline region. Noindications noted.

04/05 VT-1, VT-3 Examined two Moisture Separator shroudguide rod support brackets. Minorgouges and bent top pins. No changessince previous inspection in 11/03 (F51).

VT-3 Examined two steam dryer guide rodsupport brackets upper and lower (fourinspections). NRI

EVT-I, VT-3 Examined four steam dryer wall supportlugs. NRI

VT- 1, VT-3 Examined six upper and six lowersurveillance sample bracket attachments

to RPV and sample holders. NRI exceptfor one sample holder that was notengaged in the lower bracket. Bracketwas re-engaged during the outage.

188

Page 190: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

05/07

05/09

05/I I

EVT-1, VT-3

VT-3

EVT- 1, VT-3

EVT-I, VT-3

EVT- 1, VT-3

Examined eight feedwater sparger end-bracket assemblies. Five of eight hadless than three protruding threads.Tightened and applied additional tackwelds.

Examined eight feedwater sparger lug tovessel attachment welds. NRI.

Examined four steam dryer wall supportlugs (WSL). Rub marks/gouges fromdryer lifting noted on cladding at three ofthe four WSLs.Re-examined one bent MoistureSeparator guide rod support bracket. Nochange since 2003.

Examined four steam dryer wall supportlugs (WSL). Rub marks/gouges fromdryer lifting noted on cladding at three ofthe four WSLs.Re-examined one bent MoistureSeparator guide rod support bracket. Nochange since 2003.

Examined all four steam dryer wallsupport lugs (WSL) per BWRVIP-48-A.An INR documents rub marks/gougesfrom dryer lifting on all four WSLs; therewas one new indication noted due torubbing on the 2200 lug and no change tothe other three lugs; accept as-is.Re-examined one bent MoistureSeparator guide rod at 2000. An INRdocuments no change; accept as-is.

RPV Internal 03/96 VT-3 Examined one patch. NRI.Surfaces (Cladding)(ASME B.N. 1) 11/98 VT-3 Examined four patches. NRI.

11/02 VT-3 Examined all accessible surfaces. NRI

03/05 VT-3 Examined all accessible surfaces. Minoracceptable indentations.

05/07 VT-3 Examined all accessible surfaces. Two

189

Page 191: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

new acceptable indentations identified.

05/09 VT-3 Per approved Relief Request, Section XIB-N-I exam credited to sum of BWRVIPexams

LPCI Coupling N/A N/A Not applicable to this plant.

Steam Dryer(SIL 644, BWRVIP-139)

03/05

05/06

Best effortVT- 1, VT-3

Best EffortVT- I, VT-3

The steam dryer was originally scheduledto be replaced during QIR18, but was notready in time (the dryer was laterreplaced in May 2005). The followinginspections were then performed duringQIRI8:Examined exterior surfaces includingouter hoods, historical repair areas, tiebars and attachment welds, four liftingassemblies, four hold down assemblies,two man way covers, cover plates,gussets, upper ring welds, vertical guidewelds, outlet plenum lower horizontalwelds, outlet plenum vertical welds, andperforated plates. Previous indicationswere identified that had been repaired,stop drilled or dispositioned to use as isin 2003. Additional indications werenoted in the perforated plates. Examinedinterior surfaces including: drain channelwelds, supports, vertical and horizontalplates, support ring, horizontal crossbeams, and horizontal cross beamgussets. Previous indications wereidentified that had been repaired, stopdrilled or dispositioned to use as is in2003. New indications were observed indryer bank vertical welds and verticalstruts in the ID.Examined interior and exterior skirt.Indications noted.Dryer was repaired and returned toservice prior to replacement in May2005.

Performed baseline inspection of newsteam dryer installed in June 2005 perBWRVIP-139 and GE recommendations.

190

Page 192: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

NRI

05/07

05/09

05/11

Best EffortVT- 1, VT-3

Best EffortVT-I, VT-3

GeneralVisual/EVT-1

Performed inspection steam dryer perBWRVIP-139 and GE recommendations.NRI

Repeated inspections on steam dryer perBWRVIP-139 and GE recommendations(same scope as 2006 and 2007). NRI

Performed general visual inspections ofthe replacement steam dryer OD per GErecommendations, No reportableindications.

+ -4-

Feedwater Spargers(NUREG 0619)

1982

1986

1989

1992

1996

1998

2002

04/05

Manual UT

Manual UT

Manual UT

Manual UT

Manual UT

UT (GERIS)

UT (GERIS)

EVT- I /VT-3

VT-1, VT-3

UT of all four N4 nozzles and inner radii.NRI

UT of all four N4 nozzles and inner radii.NRI

UT of all four N4 nozzles and inner radii.NRI

UT of all four N4 nozzles and inner radii.NRI

UT of all four N4 nozzles and inner radii.NRI

UT of all four N4 nozzles and inner radii.Acceptable.

UT of all four N4 nozzles and inner radii.Acceptable.

Examined all 8 Sparger end brackets perNUREG-0619 program and BWRVIP-48. No indications.

Visual inspection of sparger flow holesand welds. Slight distortion noted in oneflow hole. A small piece of wire foundin one flow hole. All FW sparger endbracket stop nuts were run up and tackedwelded into place.

191

Page 193: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

05/07

05/09

05/11

VT- i, VT-3

VT-I

UT

VT-I, VT-3

VT- 1, VT-3

Examined all 8 Sparger end brackets.Top of pins are wearing into top side ofbracket on 3 end brackets.

Performed VT-I of flow holes. NRI.

UT of all four N4 nozzles and inner radii.NRI.

Examined all 8 Sparger end brackets.Top of pins are wearing into top side ofbracket on 3 end brackets. New (slight)wear identified on two brackets. Nochange in previous wear on 3 otherbrackets.

Examined all 8 Sparger end brackets perGE SIL 658. Top of pins show minorwear into top side of bracket on 5 endbrackets. An INR documents no change;accept as-is. One new indication on abottom tack weld of the pin to nut wasidentified at the 2060 position; An INRdocuments this condition; accept as-is.

Dissimilar Metal 05/09 N/A Four Category A DM welds examinedWelds per ASME Section XI, Appendix VIII,(BWRVIP-75-A Cat. Supplement 10. All of the exams wereA) automated. No flaws were identified and

no weld overlays were performed.

05/11 N/A No Category A DM welds examined

Dissimilar Metal 05/09 N/A No Category B DM welds examinedWelds(BWRVIP-75-A Cat. 05/11 N/A No Category B DM welds examinedB)

Dissimilar Metal 05/09 UT Examined 5 Category C DM welds perWelds BWRVIP-75 and ASME Section X1,(BWRVIP-75-A Cat. Appendix VIII, Supplement 10 (out of aC) total of 15 Category C welds that were

examined). No flaws were identified andno weld overlays were performed. All ofthe exams were automated. None of thewelds contained Alloy 82/182 butter.

05/11 UT Examined one (1) Category C DM weld

192

Page 194: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

per BWRVIP-75 and ASME Section XI,Appendix VIII, Supplement 10 (out of atotal of 13 Category C welds that wereexamined). No flaws were identified andno weld overlays were performed. Theexam was manual. None of the weldscontained Alloy 82/182 butter.

193

Page 195: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Reactor Internals Inspection History

Plant: River Bend

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Inspection Results, Repairs,

Inspection Used Replacements, Reinspections

Core Shroud 94 VT-I/VT-3 Partial inspection during forced outage.Welds H-3 thru H-7, Limited verticalweld inspection. No indication detected.

96 VT-3 ASME XI inspection of accessible areasincluding the grid. No indicationsdetected.

RF-7 97 UT UT from OD, Welds H3, H4, H6A, H7(No indications)

RF-12 Oct 2004 UT UT From OD: Welds H6A and H7 ( noindications)

RF-14 Jan. 2008 UT H3 no indications 76.6% inspectedH4 indications 92.7% inspected 9% weldflawed

RF-16 Jan 2011 UT UT- H6A and H7 Welds- No indications

Shroud Support 94 VT-1/VT-3 Inspection of accessible areas duringforced outage. Access hole cover; VT.No indications.

96 VT-3 Access hole cover. No indications.RF-8 1999 VT-I Access hole cover. No indicationsRF-9 2000 EVT-1 Shroud Support to Shroud (No

Indications)RF-9 2000 EVT-I Support Plate to Shroud (No Indications)RF-10 Oct. 2001 VT-I Access Hole Cover- No indicationsRF-12 Oct 2004 VT-I Access Hole Cover (No indications)RF-12 Oct. 2004 UT UT From Bio-shield wall H8 & H9 (no

indications)RF-14 Jan 2008 EVT-I Access hole cover NRIRF-16 Jan 2011 EVT-I Access hole cover NRI

Core Spray Piping 1987 to VT-I/VT-3 Piping and welds in annulus, every otherpresent cycle, starting 1994 every cycle. No

indications.

RF-7 1997 EVT- BWRVIP-018 (Baseline Inspection)1/MVT-I No indications

194

Page 196: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

RF-8

RF-9

RF-10

RF-I l

RF-12

RF-13

RF- 14

RF-15

RF-16

Apr 1999

March 2000

Oct. 2001

March 2003

Oct 2004

April 2006

Jan. 2008

Oct 2009

Jan 2011

EVT-1/MVT-I

EVT-1/MVT-i

UT

EVT-I

UT

EVT-I

EVT- I

EVT-1

EVT-I

BWR VIP-01 8 No Indications

BWR VIP-018 No Indications

12 welds examined No Indications

17 welds examined No Indications

8 welds examined No indications

8 welds examined No indications

8 welds examined No indications

20 welds examined No indications

8 welds examined no indications

Core Spray Sparger

RF-7

RF-8

RF-9

RF-10

RF-I I

RF-12

RF-13

RF-14

1987 topresent

1997

Apr 1999

March 2000

Oct.200 I

March 2003

Oct 2004

April 2006

Jan 2008

VT-I /VT-3

EVT-I/MVT-1

EVT-l/MVT-1

EVT-l/MVT-l

EVT-1,VT-I

EVT- 1/VT-1

EVT- 1/VT-I

EVT- I1/VT-I

EVT- I1/VT-

Nozzles, end caps, support (guides),every other outage. Selected Tee (welds)every other outage. All tee (welds), endcaps and nozzles each outage starting1996.BWRVIP-018 (Baseline Inspection)No indications

BWRVIP-018 No Indications

BWRVIP-018 No Indications

BWRVIP-0I 8-No indications

36 welds examined No indications

32 items examined no indications

15 items examined no indications

42 items examined no indications

195

Page 197: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

I Includes spare brackets pin and pad, pad

RF-I 5 Oct 2009 EVT-I/VT- 28 items examined one of two tacksI welds cracked on alignment pin at the @

the276 degree azimuth annulus side

RF-16 Jan 2011 EVT-I/VT- 34 items examined-No indicationsI

Top Guide (Rim, etc.) 1987 to VT-3 100% per Interval (Hold down studs,present nuts and keeper). No indications.

RF-14 Jan. 2008 VT-3 No indications

Core Plate (Rim, etc.) N/Access N/A N/ARF-14 Jan 2008 VT-3 8 exams (Jet Pump disassembled)

SLCRF-12 Oct 2004 Enhanced VT-2 inspection of NIl nozzle at vessel

VT-2 hydroNo leakage observed

RF- 13 SLC April 2006 Enhanced VT-2 inspection of N 11 nozzle at vesselVT-2 hydro

No leakage observed

RF- 14 Jan 2008 Enhanced VT-2 inspection of N I1 nozzle at vesselVT-2 hydro

No leakage observed

RF-15 Oct 2009 Enhanced VT-2 inspection of N I nozzle at vesselVT-2 hydro No leakage observed

RF-16 Jan 2011 Enhanced VT-2 inspection of N 1 nozzle at vesselVT-2 hydro No leakage observed

Jet Pump Assembly 1987 to VT-I/VT-3 Twenty pumps. 1/3 inspected eachpresent period first Interval(Diffuser Assembly,

Riser Assembly, Riser Braces, inletsuction area, riser brace, wedgeassembly, Hold down beam (bolt keeperand tack welds). Wedges, adjustingscrews (tack welds), sensing lines receiveVT per various SILs. Jet Pump Beamsreplaced 1994. VT of completeassemblies in 1994 forced outage.

RF-7 1997 EVT-1 Jet Pump Riser Elbow Welds

196

Page 198: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

MVT-1MVT-1MVT-I

EVT-I

EVT-1

RF-8

RF-10

RF-1 I

RF-12

RF- 13

RF-14

1999

Oct. 2001

Ma~rch 90I 03 1 EVT-1Mac 20•JVI V

No indicationsJet Pump Riser Brace Welds (6 of 10)No indications

Restrainer Assembly (6 of 10)No movement

Riser Pipe to Transition Piece (LimitedAccess) No Indications (5 ea)Inlet elbow to sleeve weld, inlet sleeve

to nozzle weld, restrainer bracket wedge,riser pipe of the upper brace and lowerbrace attachment yoke welds (6 weldsinspected

RB welds 14 welds examined JP-I I thru20, No IndicationsRS-3 weld 5 welds examined JP-I 1 thru20 No IndicationsRS-6 weld 10 welds examined JP-1 I thrU20 No IndicationsRS-7 weld 10 welds examined JP-1 I thru20 No inactionsRS-8 weld 5 welds examined JP-I I thru20 No IndicationsRS-9 weld 10 welds examined JP-1 thru20 One indication found JP-19/20 riserbraceIN-I/IN-2 weld 10 welds each examinedJP- I I thru 20 No indications foundDF-1, DF-2, DF-3A, DF-3B weld 10welds each examined JP-I I thru JP-20.No indications found.AD-2 weld 10 welds examined JP-I Ithru JP-20 No indications foundWD-1 weld 6 welds examined JP-11,12,13,14,19 and 20 No indicationsfound

RS-9 previous crack found in RF- I l (Qty1) & RS-8 (Qty 1) & WD-I (Qty I)

RS-9 reinspection previous crack & RS-8

JP-19/20 -RS-8 & 9 AD-1, AD-2, DF-3a, b, IN-I & 2, WD-l, DF-l, 2 (Jet

Oct. 2004

April 2006

Jan. 2008

EVT- 1/VT-I

EVT-1

EVT-1/VT-I

197

Page 199: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

RF-15 Oct 2009

Jan 2011

EVT- 1/VT-I

VT-3/UT

EVT- I/VT-I

Pump disassembly )JP-1 thru 20 RB-Ia,b,c,d, No indicationsexcept for previously reported RS-9indication

VT-3 -JP-I thru 20 sensing lines atwelded attachment & penetration. JP Ithru 10- 140 welds and 10 expandedscope of the AD-2 welds. AD-2indication at JP 4, UT was performed atthe AD-2 from inside and indication wasfound non-relevant VT- I of WD- Iwedges at JP 19/20

Examined RS-8 and RS-9 welds asrequired by OE from Laguna Verde Qty-30 welds no indications, also examinedWD-1 (wedges) on all 20 Jet Pumps Nowedge wear reported.

RF-16

Jet Pump Diffuser see Jet Pump N/A N/AAssembly

CRD Guide TubeRF-4 1992 VT-3 Inspected accessible tubes during bottom

head drain line replacement. Noindications observed.

CRD Stub Tube N/A N/A N/A

In-Core Housing 92, 96 VT-3 Upper portion only per Silrecommendation. No indications.

RF-8 1999 VT-I Upper portion per GE recommendations(7 ea.)

RF-Il March 2003 VT-3/VT-1 Examined 15 CRDM Total of 60 weldsEVT-I No indications found CRGT-I,2,3

FS/GTARPIN-I

RF-14 Jan 2008 VT-3 QTY-2 CRDH assembly NRI (BelowCore Plate)

Dry TubeRF-I 1 March 2003 VT-I IRM/SRM dry tubes QTY 10 inspected

No indications

RF-14 Jan 2008 VT-I Inspected II of 12 5 dry tubes hadI indications one dry tube deferred until

198

Page 200: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

RF-I 5

RF-15 Oct 2009 VT-I Examined QTY-I IRM and QTY-9LPRM's no indications. Replaced 5 drytubes with indications found in RF-14

RF-16 Jan 2011 VT-I Examined QTY-10 LPRM's noindications

Instrument 1994 VT-3 Inspected penetration at vessel duringPenetrations forced outage. No indications noted.

Vessel ID Brackets 1987 to VT-I/VT-3 Section XI inspections once per interval.present VT-3, or VT-I if in beltline region. No

indications noted.

Vessel Interior Oct 2004 VT-3 Vessel cladding area as required bysection XI No indications

Vessel Brackets Jan 2008 VT-3, Feedwater brackets, Core Spray brackets,EVT-1 Steam Dryer brackets NRI

RF-14 Vessel Interior Jan 2008 VT-3 Vessel Cladding

RF-16 Jan 2011 VT-3 Vessel Cladding

LPCI Coupling 1989, 92 VT-3 Two of three lines in 1989 and two ofthree lines in 1992. No indications.

RF-8 1999 MVT-I No Indications (I ea.)

RF-9 2000 EVT-I No Indications (2 ea.)

RF-12 2004 EVT-1 9 welds inspected No indications

RF-15 Oct 2009 EVT-I 7 welds examined no indications

Steam DryerRF-9 2000 EVT-I Indications identified CR-RBS-0686

RF-10 2001 EVT-I Indications less than 4.5 inches

RF-l I 2003 EVT-I Indications less than 4.5 inches

RF-12 2004 VT-3 Indications less than 4.5 inches

RF-13 2006 EVT- I New Indication identified dryer skirt3/4"long Ref. CR-RBS-2006-01770,

199

Page 201: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

RF-14

RF-15

RF-16

Jan 2008

Oct. 2009

Jan 2011

VT-I

VT-I

VT-I

indications identified in RF-9 less than4.5"

BWRVIP-139 exam 2 cracks found andrepaired welds V 14 and V27Upper support ring indications greaterthan 4.5JCO re-inspect next outage

Re-examined indications and repairedwelds on upper support ring, V-14 andV27 from RF-14 no changes noted

Support Ring indications- No change4 * -.

Feedwater SpargerRepair areas at AZ 45& 135 degreesRF-7

RF-8

RF-9

RF-10

RF-I I

RF-12

RF-13

RF-14

RF-15

RF-16

1997

1999

2000

2001

2003

2004

2006

Jan. 2008

Oct 2009

Jan 2011

VT-I

VT-I

VT-I

VT-I

VT-I

EVT- I

EVT-1

EVT- 1/VT-3

VT-I

VT-1

No Indications

No Indications

No Indications

No Indications

No Indications

No indications

No indications

Qty-8 Brackets to vessel and endbrackets -NRIEnd brackets had ware on pins re-inspectnext outage

Re-inspected feedwater end brackets andthe repair areas no changes noted

Re-inspected feedwater end brackets andthe repair areas no changes noted alsoexamined Flow holes no indications

SHASM RetainingPinRF-I 1 2003 VT-3 No Wear Noted

200

Page 202: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

RF- 12 2004 VT-3 No wear noted Qty 12 inspected

RF- 13 2006 VT-3 No wear noted Qty 12 inspected

RF-14 Jan 2008 VT-3 No Wear noted Qty 12 examined

RF-15 Oct 2009 VT-3 No Wear noted Qty 12 examined

RF-16 Jan 2011 VT-3 No Wear noted Qty 12 examined

Below Core Plate

RF-14 Jan. 2008 VT-3 QTY 16 items examined NRI

DM Welds BWRVIP-75-A

RF-12 Feb. 2004 UT (PDI) Qty-10 (N2)

RF-14 Feb 2008 UT (PDI) Qty-17 (NI Qty-2, N4 Qty-3, N5 Qty-4,N6- Qty-6, N9- Qty-2

RF-16 Feb 2011 UT (PDI) Qty-2 (N4-Qty-2)

201

Page 203: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Reactor Internals Inspection History

Plant: Susquehanna Unit #2

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Inspection Results, Repairs,

Inspection Used Replacements, Reinspections

Core Shroud 1993, 1995,1996, 1997,and 2001results.

Unit #2 7RIO, circumferential welds HIthrough H7 inspected ultrasonically usingthe GE OD Tracker system. Crackingfound in HI (210), H2 (940), H4 (680),H5 (50), and H6B (121°). Structuralmargins were maintained based onBWRVIP documents GENE-523-113-0894, Rev. 1, and Supplement 1, Rev. 1,and independent calculations.

Unit #2 8RIO (Spring 97), no shroudinspections scheduled based oninspection results of Unit # 1 Shroud infall of 1996.

Unit 2 9RIO (Spring 1999), Welds H1,H2, H4 and H6B were examined thisoutage. Each of these welds exhibitedcracking in the past. H4 was the worstweld showing 47.6% flawed in thecircumferential direction. Analysisshowed that 10 years of operation beforereinspection was possible whilemaintaining adequate safety factors. NoRecordable Indications for the 5 verticalwelds inspected.

Vertical Welds H6B/H7 at 90°and 270'to determine possible sources ofinterference to develop tooling necessaryfor fuiture EVT- I

Three Vertical Shroud Welds, NoRecordable Indications

GE OD Tracker for H3, H5, H6A, andH7. H3 No Recordable Indications, H5,H6A, H7 increase in % flawed from 1995

2003

2005

VT-3

EVT-1

UT

202

Page 204: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

baseline exams. All welds acceptable perBWRVIP-76 flaw analysis.

2007 EVT-1 Two Vertical Shroud Welds, NoRecordable Indications

2009 EVT-1 Eight vertical shroud welds. NoRecordable Indications.

UT GE OD Tracker for HI, H2, H3, H4,H6A, H613. Increase in percent flawedfrom previous exams for all welds expectH6A. All welds acceptable perBWRVIP-76 flaw analysis.

Shroud Support Prior to 1995 VT-I, VT- VT-I of 00 to 3600 of H8 and H9 duringI the first interval with no recordableenhanced, indications.and UT

Inspect (VT-1) every outage. NoRecordable Indications to date.

VT-3 of all 14 shroud support legs andsupport leg stub pad to RPV attachmentwelds per BWRVIP-38. No RecordableIndications.

VT-I examinations were performed onshroud weld H8 at 180 deg. to verify apreviously noted crack adjacent to theaccess hole cover. The indication wasdetermined to be non-relevant due todark grit built up at the weld toe.

Baffle Plate 2011 VT-3 As found VT-3 examination of undersidearea surface of baffle plate (215-225).No Recordable Indications.

H8/H9 1995 EVT-1 Unit #2 7RIO (Fall 95) examined H8 andH9 (enhanced VT-I) for 3600. NoRecordable Indications.

1997 UT Unit #2 8RIO (Spring 97) UT of H9 fromvessel OD and VT-l enhanced of H8.No Recordable Indications.

2001 UT UT of H9 from vessel OD - 100%. No

203

Page 205: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Recordable Indications

2003

2009

2011

2003

2011

2003/2007

2009

Shroud Support Legs

Access Hole Covers

EVT-l /VT-3

EVT-l/VT-3

EVT- 1/VT-3

VT-3

VT-3

VT-I

EVT-I/VT-3

EVT-I of H8 to satisfy BWRVIP-38 andVT-3 of H8 and H9 underside VT-3inspections performed with GE remotefirefly inspection vehicle down diffuserinlet mixers removed for modification.No Recordable Indications.

EVT-1 of H8 to satisfy BWRVIP-38 andVT-3 per ASME XI. No RecordableIndications.

H9 inspected 25% per VIP-38 andASME Section XI. No RecordableIndications. VT-3 examination of H8and H9 welds-215-225 underside duringjet pump 12 disassembly. No RecordableIndications.

Shroud Support legs inspected during JetPump Beam modifications. NoRecordable Indications.

Shroud support legs J-K examined duringJet Pump 12 disassembly. No RecordableIndications.

VT-I of AHC welds at 0 and 180degrees. No Recordable Indications.

EVT-1 of 0 and 180 degree AHC tosatisfy BWRVIP-180 and VT-3 perASME XI. No Recordable Indications.

Shroud Head Bolts 2005

2007

2009

UT

VT-3

UT

UT exam of 43 "Old Style" Shroud HeadBolts per SIL 433. No RecordableIndications.

VT-3 of Shroud Head bolts windows andpins for wear. Window / Pin weardiscovered in 30 of 48 bolts. Allacceptable one cycle. Two to be replacednext outage.

UT exam of 41 "Old Style" Creviced"Shroud Head Bolts per SIL 433. No

204

Page 206: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Recordable Indications.

VT-3 VT-3 of two bolts that exhibited abovenormal wear in 2007. No change incondition noted. Bolts acceptable.

2011 VT-3 VT-3 of Shroud Head Bolt 14, 16.Recordable Indications. No visualchange from previously recordedindications. VT-3 of Bolt 48 with NoRecordable Indications.

Core Spray Piping 1980's to VT-1, VT- Piping and welds in annulus. No1995 3 Recordable Indications.

1997 VT-I Unit #2 8RIO (Spring 97) Inspect perenhanced B WRVI P- 18, no recordable

indications.

1999 EVT-I Inspect per VIP-18, no recordableindications.

2001 EVT-1 & Unit #2 10 RIO Inspect per VIP-] 8 TwoUT indications were recorded, one on the P5

weld and one on the P8b weld. Bothindications were evaluated to haveexpected lifetimes of 7.9 and 18.4 yearsrespectively.

2003 EVT-I Examined core spray piping welds perBWRVIP-I18 that were not inspectedprevious outage by UT, P4D, 7deg, P8Aboth loops 7, 170, 187, and 352 degrees.No Recordable Indications. Also EVT-Iof welds with indicated defects byprevious UT, welds P5 352 degrees andP8B 187 degrees. No visible defectsdetected. Since defects are not visiblethrough visual exam they are confirmedas subsurface.

2005 EVT-I BWRVIP-18A - EVT- I of welds that donot have approved UT procedure andcontaining flaws. Scope similar to 2003exams. No Recordable Indications.Note: It was determined that the P8Bwelds contain a site-specific double weld

205

Page 207: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

configuration; UT exam is not acceptablefor collar to shroud weld. EVT-1performed for BWRVIP-18Acompliance.

UT UT exam by CSI 2000 of Core Spraypiping welds per BWRVIP-18A. Weldsexamined both loops, P2, P3, P3, P6, andP7. Rotating sample of one each P4A,P4B, P4C, P4D welds. No RecordableIndications. P5 352 degrees P8B 187degrees no growth in previouslyidentified flaws.

2007 EVT-1 BWRVIP-I 8A of welds that does nothave an approved UT technique, P8A,P8B welds and 1 P4C weld and one P5weld with UT discovered flaw. NoRecordable Indications.

VT-I All 8 piping brackets and welds, PB.

2009 EVT-I Core Spray piping per BWRVIP-18A.All P2, P3, P5, P6, P7, P8A, and P8Bwelds. Two each P4A-D. One 2.5"crack in Cover Plate base metal adjacentto base metal gouge, Use As Is.No Recordable Indications in welds.

2011 EVT-1 Examined N5A PI, P2, P3, P5, P6, P7,P8A, P8B and N5B, PI, P2, P3, P4, P5,P6, P7, P8A, P8B. No RecordableIndications.

VT-1 N5B bracket weld A has a RecordableIndication, gouge, identified in aprevious outage, no growth noted. N5BBracket weld B has a new RecordableIndication for bracket and pipe wear.

Core Spray Sparger 1997 VT-I,VT-3 Unit #2 8RIO (Spring 97) Inspect perBWRVIP-1 8. Several Shroud CoreSpray Support Bracket welds found withcracking on shroud ID. Determinedacceptable to Use-as-is.

2001 EVT-I Inspect per VIP-18, No Recordable

206

Page 208: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Indications.

2003 EVT-l Examined all four upper and lowerVT-I spargers, EVT-I SI S2 S4 VT-I S3a,

S3b, S3c(lower), and sparger bracketswelds (VT-3), per BWRVIP-1 8. NoRecordable Indications. SB-03reinspection of previous indication.Approximately 3" crack visible next toSB03 in shroud. Crack in shroudadjacent to SB03 evaluated as crack invertical shroud weld per BWRVIP-76.Structural margins maintained.

2005 EVT-1 EVT-I exams of all 12 Core SprayUT Spargers Brackets (SBs). SB03 previous

indication in shroud side. Newindications found in shroud outside ofHAZ during inspection of SB-02, SB-04,SB-I 1. UT performed utilizing GETracker tool for sizing of defects inshroud. BWRVIP-76 vertical welddefect acceptance criteria employed. Allindications acceptable for multiplecycles.

2007 EVT-I Examined all four upper and lowerVT-I spargers, EVT-I SI S2 S4 VT-I S3a,

S3b, $3c (lower), and sparger bracketswelds (VT-3), per BWRVIP-18A. NoRecordable Indications.

2009 EVT- / EVT- I of four brackets with perviousVT-I indications on shroud side bracket welds

HAZ. Additional cracking discovered intwo brackets. VT-I of eight bracketswith no pervious indications. Shroudside HAZ cracking observed in threebrackets.

2011 EVT-1 Examined a total of 61 core spray spargerVT- I components including the following:

N5A-B (S1, S2 S3A, S3B, $3C, S4),N5A-D (S1, S2 S3A, S3B, S4), N5B-A(S1, S2, S4), N5B-C (S1, S2, S4, S5).No Recordable Indications. N5A-B S3B

207

Page 209: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

NOZZ - 080 - 090 exam shows newRecordable Indication, a cracked lowerelbow-to-nozzle tack weld.

I 4 4

Top Guide (Rim, etc.) To 1995

1997

2003

2007

2009

2011

VT-3

VT-3

VT-3

VT-I

VT-3

EVT-1

EVT-I/VT-3

(VT-3) of accessible cells up topercentage of total over the interval(lower surfaces only). Also, inspectionof hold-down bolts. Minor misalignment(bowing) of several cross-members oftop guide.

Unit #2 7RIO (Fall 95). Eight cells lowersurfaces and inspected wedges. NoRecordable Indications.

Unit #2 8RIO (Spring 97). Ten cellslower surfaces, no recordable indications.

VT-I of 22 Top Guide locations perBWRVIP-26. No RecordableIndications.

Four VT-3 Code ASME XI exams madeaccessible during BWRVIP-47 GuideTube exams. No Recordable Indications.

Three EVT-1 exams to satisfy BWRVIP-183. Two small, one-quarter inch each,cracks in one beam of one cell.Evaluated as acceptable.

Six EVT-1 exams completed to satisfyBWRVIP-183. No RecordableIndications. Six VT-3 Code ASMESection XI exams through BWRVIP-47GUIDE TUBE EXAMS. No RecordableIndications.

Core Plate (Rim, etc.) Prior to 2003 VT-I of Unit #2 6RIO (Spring 94) Inspected oncesurface 900 of plate and bolting accessible. Nowelds and Recordable Indications. Following thisbolt tack inspection and the questionable valuewelds on added, no further exams performedupper pending VIP recommendations.surfaces

VT-3 of

208

Page 210: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

bolt anduppersurface andcross-members

2003 VT-3 VT-3 of core support plate welds andcore support plate, VT-3 18 of 34 CoreSupports bolts from below core platemade accessible through removal ofjetpumps for modification. No RecordableIndications.

2007 VT-3 Four VT-3 Code ASME XI exams madeaccessible during BWRVIP-47 GuideTube exams. No Recordable Indications.

2009 VT-3 Three VT-3 Code ASME XI exams madeaccessible during BWRVIP-47 GuideTube exams. No Recordable Indications.

2011 VT-3 Examined Core Plate area 06-27, 38-39,54-35 per Code ASME Section XI. NoRecordable Indications

SLC 1992 VT-3 Unit #2 5RIO (Fall 92) One side of theStandby Liquid Control Standpipe wasinspected. Disassembly of the jet pumpsfor a Power Uprate modification madeinspection possible. No RecordableIndications were found.

2003 VT-3 VT-3 of SBLC piping per BWRVIP-027.No Recordable Indications.

2005 to Enhanced Enhanced VT-2 Per BWRVIP-27A ofpresent VT-2 SLC Nozzle and Safe-End. No

Recordable Indications.

Jet Pumps 1993 VT-I, Riser brace welds inspected every otherVOL, VT-3 outage. Jet pump beam volumetrics once

in ten years. Remaining components(welds (VT-1), set screws (VT-3),wedges (VT-3), sensing line clamps (VT-I & VT-3), tack welds (VT-i), etc areonce per period. Jet pump beamsreplaced

209

Page 211: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

1994 Unit #2 6RIO (Spring 94) Beamsreplaced. One old beam found cracked inleg area. Non-rejectable gaps insetscrews reported over several outages.

Unit #2 6RIO (Spring 94) cracked weldson #13 and #14 instrument lines.Repaired with clamps.

1997 Unit #2 (Spring 97) Weld #3 baselined.No Recordable Indications.

1999 Inspected per VIP-41, no recordableindications

2001 VT- I Inspected per VI P-41, excessive gaps,wedge wear and slider rod damage onvarious jet pumps. Auxiliary temporaryspring wedges installed on Jet Pumps 03and 17.

Riser Brace 2003 EVT-I RB l a, b, c and RB 2 a, b, c, d for RiserD No Recordable Indications.

2005 VT- I VT- I Expanded Inspection Scope ofRiser Brace welds RB-IA, B, C, D andRB-2 A, B. C, D for Jet Pump Riser Kdue to jet pump wedge wear. BWRVIP-41 expanded scope exam. NoRecordable Indication

2007 EVT-I RBla, b, c, d, and RB 2 a, b, c, d forRiser Brace F and H. Expanded scopeinspections for Riser brace G due to jetpump set screw gaps. No RecordableIndications.

2009 EVT-1 RBIa, b, c, d, and RB 2 a, b, c, d forRiser Brace C and E. No RecordableIndications.

2011 EVT-I RBI A, B,C,D exams for Riser Brace F& J. RB2 A,B,C,D exams for Riser BraceF & J. Riser brace J exams are fromscope expansion due to JPI 7 set screw

210

Page 212: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

gap. No Recordable Indications.

Riser Pipe 2003 EVT-1 RS1 RS2 RS3 for risers C,D,E RS6 RS7RS8 and RS9 for Riser C No RecordableIndications.

2005 EVT-1 / EVT-I RS-6and RS-7 for Jet Pumps 05VT-I and 06 for BWRVIP-41 baseline credit.

BWRVIP-41 expanded scope exam VT-Iof RS-6 and RS-7 for JP08, JP12, JPI9,and JP20 due to wedge wear. NoRecordable Indications.

2007 EVT-I EVT-1 RS-6 and RS-7 JP20Risers F and H RS-8 and RS-9 welds.RSI, RS2, RS3 for risers F, H NoRecordable Indications.

2009 EVT-1 RSI, RS2, RS3 for jet pump risers B, D,E, G, H. No Recordable Indications24 Medium Priority RS6, RS7, RS8, RS9original scope. Expanded scope RS6,RS7, RS8, RS9 for 18 additional examsdue to wedge wear scope expansion. NoRecordable Indications

Diffuser 2003 EVT-I IN-4 and MX2 for jet pumps 07,09, 10DF-I for jet pumps 07, 09, 10, 13,14, 17,18 DF2 inspected for jet pump 05, 06,07, 08, 09, 10 AD-I and AD-2 welds forall 20jet pumps, Eight AD-2 welds fromID when inlet mixers removed. NoRecordable Indications.

2007 EVT-I EVT-I IN-4JPI I and JPI2 NoRecordable Indications.

2009 EVT-1 46 Medium and High Priority welds,ADI, AD2, DFI, DF2, MX2, IN4. NoRecordable Indications.

Adjusting Screws 2003 VT-I Set screw gap inspection for all 20 jetpumps for pre and post modificationinspection. One gap exceeded 10 milsduring final inspection, spring wedgeinstalled. Also several cracked set screw

211

Page 213: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

tack welds observed, Use-As-Is.

2005 VT-I VT-I of set screws for those jet pumpsexhibiting wedge wear or movement,JP08, JPI2 (Movement only), JP19,JP20. JPI 9 excessive gap, auxiliarywedge installed. Two cracked tack weldsobserved Use-As-Is.

2007 VT-I VT-I of set screws for those pumps withprevious wedge wear observed in 2005,JP08, JP12, JPI9. Cracked tack weldsobserved, Use-As-Is.

2009 VT-I ASI set screw gap inspection for three jetpumps with set screws "digging into"belly band. Four AS2 exams for jetpump with existing cracked tack welds.Six exams for previously installedauxiliary spring wedges. Fourteenadditional AS I and AS2 exams based onjet pump wedge wear scope expansion.Results:

" Set screw digging into belly band- JPO1, JP04 (SS and VS), andJPl2.

* Additional cracked tack weld:JPI3

* Auxiliary Spring Wedge digginginto belly band-JP03 SS, JPI9SS, JP20 SS

* Excessive set screw gap: JPOI* Auxiliary Spring Wedge past

maxi mum allow travel distanceJP03SS

" Excessive downward verticalwedge movement: JP12

" New auxiliary spring wedgesinstalled

o JPOI SS and VS GAPSo JP12 SS and VS

Excessive vertical wedgemovement

o JP03SS End of travel

212

Page 214: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

1VT-I AS-] exam all aux wedges and all AS-2locations. Jet Pump indications include

the following:" Restrainer Bracket & AS-I wear:

JP12 VS &SS" AS-1 wear into Belly Band (New and

Additional)-JPI I SS &VS, JP16 SS,JP19 VS, JPl7 VS, JP18 VS, JPIOSS &VS, JP09 VS, JP02 VS & SS,JP04 SS & VS, JP07 VS, JP08 SS,JP12 SS &VS, JPOI SS & VS, JP14SS, JP03 SS, JP07 SS

" Cracked AS-2's- JP16 SS (ID &OD), JPl3 SS (ID & OD), JPI7 VS& SS (ID), JP15 SS (ID)

" AS-I Gaps (New & Additional)-JP17 SS, JP17 VS, JP08 VS

Aux Wedge Movement and Wear(New & Additional)- JP12 SS, JP14 SS,JP20 VS, JPI9 SS, JPOI SS, JP03 SS

Assembly 2003 EVT-I Labyrinth Seal EDM cuttingmodification performed on all 20 jetpump inlet mixers. Damaged wedgeassemblies replaced. Damaged rodsreplaced. Restrainer brackets resurfaced.Post modification inspection on inletmixer, set screw gaps and wedge heights.

Post modification inspection revealed 3inlet mixers with uneven EDM burn dueto non-conductive material in mixer.Use-As-Is.

2005 VT- I VT-I of all 20 Jet Pump wedges, WD-Iexam and replacement hardware installedin 2003, (wedge rods and auxiliaryclamp) for I cycle inspection for damagefrom labyrinth seal modification in 2003.Moderate wedge wear in JPI9. Slip Jointclamp installed to reduce vibration.Minor wedge damage in JP08, JPI9, andmovement noted for JP12 wedge. AllUse-As-Is. Expanded inspection scopefor damage to riser brace and piping forthose Jet Pumps with wedge damage or

213

Page 215: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

movement. No Recordable Indications..

2007 VT-I VT-I of all 20 Jet Pump wedges androds, WD-1 exam and replacementhardware, one auxiliary spring wedge,installed in 2005.Minor wedge wear on 6jet pumps.Expanded visual exams revealed largegap at one set screw for two jet pumps.Auxiliary spring wedges for both vesselside and shroud side installed.Minor rod wear observed on 14 rods.Major wear on 2 rods, for one cycle to bereplaced next outage.Cracked tack welds and indentations intobelly band Use-As-IsAuxiliary spring wedge installed in 2005at end of travel. New spring wedgeinstalled in place.

2009 VT-I VT-I of all 20 wedges to support EPUand determine if additional wedge wearhas occurred. Scope expansion requiredfor two jet pumps due to wear or wedgemovement.

Additional minor wedge and/orrod wear for 13 jet pumps - JPO1,JP02, JP03, JP04, JP07, JP09,JPI I, JPI2, JP]3, JPI5, JPI8, andJP20.

2011 VT-I VT-I of all 20 wedges due to wedgewear observed in 2009 and EPU.Movement and Wear- JPI 8, JPI 7, JP02,JPO3, JP07, JP08, JP09, JPIO, JP04, JP06

2011 VT-I VT-I of Jet PuMp 12 Lab Seal duringmain wedge replacement. Slip Joint IDwear pattern: area between SS AS-I &VS AS- INoticeable Wear on the outside of riserpipe location. Wear on Lab Seal foundwear in the restrainer bracket observedwhile wedge was removed. Significantwear & damage on set screws (SS &

214

Page 216: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

VS). Inspected while aux. wedges wereremoved.No wear pattern at main wedge location.Scope expansion to remove aux. wedgesat two additional jet pumps to inspect setscrews for wear. Additional wear foundat both jet pumps.

Sensing Line 2003 VT-3 Inspection of two Jet Pump sensing lineswelds and supports per BWRVIP-041and Power Uprate. No RecordableIndications.

2005 VT-3 VT-3 for sensing lines with clampsinstalled for power up-rate vibrationconsiderations or defect mitigation. NoRecordable Indications.

2007 VT-3 Inspection of two Jet Pump sensing lineswelds and supports per BWRVIP-041and Power Uprate. No RecordableIndications

2009 VT-3 VT-3 for sensing line clamps due toPower Uprate vibration consideration ordefect mitigation. Crack detected insupport to line weld, Lack of Contactbetween clamp and pipe and evidence ofmovement.

2011 VT-3 VT-3 of sensing lines for EPU vibrationconsiderations. No RecordableIndications.VT-3 of sensing line clamps inspected in2009 to determine if any change incondition. One clamp showed additionallack of contact, two clamps showedadditional movement.

JP Beams 2005 UT UT exam for all 20 Jet Pump beams, BB-1, BB-2, BB-3 regions per BWRVIP-41.No Recordable Indications.

2011 UT UT exam for all 20 Jet Pump beams, BB-1, BB-2, B13-3 regions per BWRVIP-41.No Recordable Indications.

215

Page 217: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

CRD Guide Tubes

CRD Guide TubesOD

2003

2007

2009

2011

2003

2011

2011

EVT-t andVT-3

EVT-I andVT-3

EVT-I andVT-3

EVT-1 andVT-3

VT-3

VT-3

VT-3

EVT-I and VT-3 of CRGT-1, -2, -3 andFS/GT-ARPIN on 9 guide tubes. NoRecordable Indications.

EVT-I and VT-3 of CRGT-1, -2, -3 andFS/GT-ARPIN on 4 guide tubes. NoRecordable Indications

EVT-I and VT-3 of CRGT-1, -2, -3 andFS/GT-ARPIN on 4 guide tubes. NoRecordable Indications

EVT-I and VT-3 of CRGT-1, -2, -3 andFS/GT-ARPIN on 3 guide tubes. NoRecordable Indications

Inspected 52 CRD Guide Tubes OD inlower plenum periphery made accessiblethrough removal ofjet Pumps formodification per BWRVIP-47 guidelines.No Recordable Indications.

Inspected 3 CRD Guide Tubes OD inlower plenum made accessible during jetpump modifications. No RecordableIndications.

Inspected 3 stub tubes and attachmentweld to RPV. No RecordableIndications.

VT-3 of 40 stub tubes and attachmentwelds to RPV per BWRVIP-47guidelines.No Recordable Indications.

Dry Tubes Prior to 2003 VT-I VT-I inspections of 3 dry tubes per SIL-409. One tube plunger separated andmissing from tube. One tube linearindication in creviced area. Bothdamaged tubes replaced.

2003 VT-3 VT-3 examination of remaining 9 drytubes to determine if plungers stillpresent. No Recordable Indications.

216

Page 218: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2005 VT-3 VT-3 examination of remaining 6 drytubes to determine if plungers stillpresent. No Recordable Indications.

Instrument 1986 to VT-2 VT-2 Exams during RPV pressure testPenetrations present each outage.

Vessel ID Brackets Prior to 2005 VT-I and 1989 Section Xl inspections of jet pumpVT-3 riser brace, dryer, feedwater brackets,

core spray header brackets, andsurveillance capsule holder brackets,performed once per interval.

"Measurable but acceptable wear"

VT-3 Examinations were performed onthe dryer support brackets andattachment welds located at 4, 94, 184and 274 degrees. No new indicationswere observed. Previously recorded wearon support lug "D" at 274 deg. wasverified and no additional wear noted.

VT-3 (VT-I beltline) exam of Guide rodBracket, Steam Dryer Hold downbrackets, Surveillance Brackets. EVT-Iof seven sets of Jet Pump Riser Brace toPad Welds and EVT-I of all eight CoreSpray Brackets to RPV attachmentwelds. All inspections per BWRVIP-048

2005 VT-3 VT-3 of one Steam Dryer Hold DownBracket per ASME XI / BWRVIP-48.No Recordable Indications.

2007 VT-3 VT-3 of 274 degree dryer supportbracket. Bracket wear was neverquantified during prior exams. Expandedscope to other dryer support brackets.No Recordable Indications.

EVT-l / Two Jet pump riser support brackets toVT-3 vessel. Eight feedwater bracket to vessel

welds. No Recordable Indications.

VT-I / VT- Guide Rod brackets No Recordable

217

Page 219: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

3 Indications.

2009

2011

EVT-I

VT- 1/VT-3

VT-3

EVT- 1/VT-3

VT-3

VT-3

VT-3

VT-I

EVT-1 of six jet Pump riser supportbracket to vessel welds (three pair)

Three surveillance specimen brackets.No Recordable Indications.

One each Dryer Hold down bracket andGuide Rod Bracket. Minor rubbing/wearmarks on guide rod. All attachmentwelds, No Recordable Indications.

Dryer Support Brackets (four) Pre andpost EDM to support EPU new dryerVT-3 to establish new baseline. EVT-Ipost EDM of bracket surface and EVT-Iof bracket to vessel welds. NoRecordable Indications.

VT-3 of Guide Rod Bracket with minorrubbing identified in 2009. No changefrom condition reported in 2009.

VT-3 of four Dryer Hold down brackets.No Recordable Indications

VT-3 of four Dryer Support Brackets toidentify wear patterns

VT-1 of four Dryer Support Bracketsweld to RPV. Required by new dryermanufacturer for new steam dryer.

LPCI Coupling N/A N/A Not applicable to this plant

Steam Dryer 2005 VT-I VT-1 exam of all steam dryercomponents per GE SIL 644 Rev. I andBWRVIP-139 in anticipation of EPU.Inspections included Hood Panel Welds,Lifting Lugs, Drain Channel Welds,Hood/End Panel Welds, Steam Dam toHood Joint Welds, Tie Bar Welds, VaneBundle to Vane Assembly, and allpreviously identified indications. Minorgrowth in existing minor IGSCC crackssome new IGSCC minor cracks in Drain

218

Page 220: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

2007

2009

2011

VT-I

VT-i

VT- I/VT-3

Channel and Hood/End Panel Welds.Existing Vane Bundle Assembly to SeamDam weld grew in length from 10" in2003 to 14" in 2005. Entire flaw lengthrepaired through underwater welding.

VT-I of welds with previous indicationsand those weld types with defects thatrequired weld repair last two outages.Minor growth in lifting lug tack weld.Acceptable. No other growth or defectsnoted.

VT-I Baseline post-construction of newsteam dryer. No Recordable Indications.

Baseline exams of new steam dryer afterone cycle. Exams include all BWRVIP-139 components and additional locationsrequired by the manufacture, includingunderside exams. Major Indications:Dryer Seismic Ring Lug A- Through-Wall indication in Skirt Panel-Approx4.5" Repaired though stop drill repair.Dryer Lug LL-B 140 Deg- Crack-likeIndication on Dryer lower Bracket toLifting Lug Weld- Approx. 0.5".Multiple IGSCC indications (4 areas)found during VT-I of Dryer Skirt Weld135 Deg- most prominent cracks are0.5"- shallow depth. Use-as-is.

Steam Separator 2007

2007

2009

2011

VT-I

VT-3

VT- I

VT- I

VT-I of 25% of support ring to gussetwelds. Minor IGSCC cracks found in 9welds. Use-As-Is.

VT-3 of all tie bars. Two severed tie barsfound, loose ends cut back to attachmentwelds.

VT-I of additional 25% of support ringto gusset welds. Minor IGSCC cracksfound in 19 welds. Use-As-Is. Nine re-looks at welds with previous indications,no growth detected.

VT-I of previous IGSCC indications.

219

Page 221: 2012-091 BWR Vessel & Internals Project (BWRVIP) · 2012-091 BWR Vessel & Internals Project (BWRVIP) May 2, 2012 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville

Additional minor IGSCC discovered attwo gusset welds. Use-as-is.

Feedwater Spargers 2007 VT-I / VT- VT-I of feedwater sparger welds andand Brackets 3 nozzles. VT-3 of brackets for OE for pin

wear into bracket top. No RecordableIndications.

2011 VT-3 VT-3 of all twelve brackets for pin wear.Minor pin wear found on four brackets.Use-as-is.

Miscellaneous 2009 UT During the U2-14RIO, fifteen (15)dissimilar metal (DM) IGSCC Category

DM Welds C welds containing Alloy 82/182 weldmaterial and two (2) IGSCC Category Cwelds containing stainless steel weldmaterial were examined to therequirements of ASME Section XI,Appendix VIII, Supplement 10, usingautomated ultrasonic equipment ormanual ultrasonic examination. Nofailures were identified. Additionally,one IGSCC Category C weld wasmodified to an IGSCC Category A weldduring the outage, decreasing the totalSusquehanna Unit 2 IGSCC Category Cpopulation from 22 to 21.

2011 UT U2-15RIO six (6) dissimilar metal (DM)IGSCC Category C welds containingAlloy 82/182 were examined to therequirements of ASME Section X1Appendix VIII, Supplement 10.

220