2008 facility plan update may 2008. purpose comprehensive plan through 2033 –builds on past work...
TRANSCRIPT
2008 Facility Plan Update
May 2008
Purpose
Comprehensive Plan through 2033– Builds on Past Work– Adjust for Changing Conditions
Identify Capacity, Compliance, and Rehabilitation needs– Robert W. Hite Treatment Facility– Biosolids Management Program– Transmission System
Develop Cost-Effective Capital Improvement Program– To meet Future (more stringent) Effluent Quality Requirements – Accommodate Growth
Renewal 2003 Wastewater Utility Plan– Denver Regional Council of Governments (DRCOG)
Updates 2003 Wastewater Utility Plan
Defines South Secondary Improvements (PAR 1085)
Updates Transmission System InfoWorks Model
Updates 2007 Land Use Model
Updates Plant GPS-X and Hydraulic Models
Includes PELs from Future Effluent Limits Study
Updates 2003 Facility Plan & 2002 Service Area Utility Plan, and 2007 Biosolids Study
Incorporates North Secondary Improvements (PAR 942)
What’s Included in 2008 Update
Does not include IS/Support facilities
South Secondary Improvements
Parallel Track– Ammonia Compliance Deadline December 31, 2014
Jan 08
South Secondary Predesign
Define South Secondary Needs
Jun 07 Jul 07
Technical Team Review
Develop Alternative Layouts and Costs
Aug 07
Begin Facility Plan
Feb 07
Complete Facility Plan
Mar 08
Complete Predesign Mar 09
Metro District Service Area
615 square miles and includesCity and County of Denver and parts ofAdams, Arapahoe, and Jefferson counties
Six Drainage Basins
Member Municipalities and Special Connectors
20 Member Municipalities and 25 Special Connectors
Metro District Service Area Including Brighton and South Adams
Population and Employment Projections
Projections based on:– Updated Member Municipality & Special Connector information– Current population, employment & boundary information from DRCOG
TAZ Data (Transportation Analysis Zones)– Buildout projections from the Land Use Model
Population – Increase 39% or 1.5% per year thru 2033 Employment – Increase 52% or 2.0% per year thru 2033
Parameter 2007 2015 2033 Buildout
Population 1,588,000 1,745,000 2,213,000 2,833,000
Employment 985,000 1,190,000 1,492,000 2,371,000
Population Equivalent
1,785,000 1,983,000 2,511,000 3,307,000
Flow and Load Projections
Parameter 2007 2015 2033 Buildout
Flow, million gallons per day (mgd)
147 164 208 227
BOD load, tons per day (tpd)
167 187 237 262
TSS load, tpd 180 199 252 276
TKN load, tpd 23.4 26.1 33.2 36.7
Unit Flow Factors– 85 gallons per capita per day– 17 gallons per day per employee
Developed Service Area Projections Adjusted to Determine Primary Influent Flows and Loads
– Exclusion of area tributary to a future Box Elder WWTP– Reduction in flow of 5 mgd for the Sand Creek Water Reclamation Facility– Additional loads, such as in-plant and hauled wastes– Increase in BOD loads from DIA
Historic and Projected Primary Influent Flow and Loads
Existing Robert W. Hite Treatment Facility Liquid Stream Capacity
Current max month rated capacity 220 mgd with EPC (~185 mgd Annual Average) Capacity without EPC 161 mgd Annual Average (Secondary Treatment) North and South Secondary Expansions required to meet capacity and regulatory requirements RWHTF AAF capacity needs to be 210 mgd in 2033
Existing Robert W. Hite Treatment Facility Solids Stream Capacity
Improvements to the digesters and high-solids centrifuges are planned during 2008-2013.
Existing Transmission System Summary
219 miles of interceptors, 12 miles of force mains and 4 lift stations
Capacity evaluation based on:– Previous modeling from 2002 SAUP– Updated Land Use Model– Updates to existing InfoWorks Model
0.040.04-0.10
33-8
Phase 5 Beyond 2023
Discharge Permit Requirements Anticipated to Remain Unchanged Through Planning Period
3Minimum dissolved oxygen, mg/L
6.0-9.0pH range, standard units
0.011Maximum chlorine residual, mg/L
30TSS, mg/L
17CBOD, mg/L
–8.68
–
–8.68
–
Nitrates (plus nitrites), mg-N/L Daily maximum 7-day average 30-day average
6.2-12.71.7-2.22.0-4.6
21.5-30.0 –
9.7-15.0
Total ammonia, mg-N/L Daily maximum 7-day average 30-day average
Discharge Permit Requirements Anticipated to Change in Phase 2
Phase 32013-2018
Phase 22008-2013Parameter
0.50.04-1.0
Total phosphorus, mg-P/L Phasing Assumption Assumed Range
83-8
Total nitrogen, mg-N/L Phasing Assumption Assumed Range
Phase 4 2018-2023Parameter
Discharge Permit Requirements Anticipated to Change in Phases 4 and 5
Regulatory Assumptions
Improvements and Project Implementation
Transmission System improvements driven by rehabilitation needs and capacity constraints due to growth
RWHTF improvements phased over planning period to meet capacity, regulatory, and rehabilitation needs
Used recently developed Metro District Cost Estimating Guide for consistent and better cost estimates
Recommended improvements “packaged,” according to type, location, and timing
– Construction Efficiencies– Save Capital Costs
Goal of the phased program is to continuously meet customer service and regulatory requirements through the end of the planning period
Transmission System Rehabilitation
Inspection Program– Closed-circuit television and surface inspections– CCTV inspection annually on portion of system– CCTV taping of each interceptor every 10 years– Three categories based on degree of degradation
Transmission Division reviews to assess condition Engineering Department performs second review,
further refines the condition, develops a cost estimate and schedule
Transmission System Rehabilitation
CIPP Slip Lining Manhole Rehab
Transmission System Capacity Improvements
Transmission System hydraulic modeling– 2002 model updated with Sand Creek Basin
Wastewater Master Plan– Model updated with revised population,
employment, and unit flows– Model runs performed for 2007, 2015, and 2030– Assumed northeast Service Area flows will
continue to RWHTF – Flow data being collected to further refine model
calibration in 2008
Metro District Transmission System Capacity Concerns in 2015
Metro District Transmission System Capacity Concerns in 2030
Transmission System Project Implementation Schedule
Basis for RWHTF Recommended Improvements
2003 Facility Plan established basic direction– Five-stage air-activated sludge with BNR– Phasing out the high-purity oxygen system
North Secondary Improvements Project (PAR 942)– CaRRB process to address centrate treatment
Objective is to have similar processes in the North and South Complexes that operate and perform in a comparable fashion
RWHTF Recommended Improvements
RWHTF Project Implementation Schedule
Projected Capital Expenditures
$1.86 billion projected 2008-2033 $1,528,000,000 – RWHTF $332,000,000 – Transmission System
Questions
RWHTF Buildout Site Plan (230 mgd)