1570w d li j t1570w dragline project goedgevonden …docs\major dragline repair - d...
TRANSCRIPT
INDEX
• Introduction
• Planning• Planning
• Safety
Sit ti• Site preparation
• Boom down
• Planned repairs
• Challenges
2
Introduction
• History of machine – Rietspruit Mine- 5 Seam Mine- GGV Mine
• Dragline walk – 16km walk 5Seam to GGVg- 11 x power lines- 1 x public roadp- 1 x river - 1 x gas pipeline
3
g p p
Planning of repairs
• Assessment of required repairs ssess e t o equ ed epa s
• Manufactured spares – Tub Manufactured spares Tub - Back legs & lugs- Electrical equipment Electrical equipment
• Tracking of progress
• unplanned
4
Safety
• JHA, risk assessment & controls
• Permit system & Pto's
• Safety drive – scratch cards
• Achievements & rewards – 93 241 man hrs
• One incident – fall from stairs 1.5m- low blood pressure
5
low blood pressure
Project structure
Xstrata
OPS Manager
Xstrata
Engineer
ImpactBucyrus
BucyrusImpact
MechanicalMechanical
Tub
Bucyrus
Electrical
6
Tub Manufacturing
• Manufactured by a u actu ed byBucyrus
• 4 Months
• Coded welders
• Part AA5 & AA10 in 3rd
ring
12
Tub assembly on site
• Parts AA1- AA4a ts
• 12 Coded welders12 Coded welders
• 3 Months3 Months
• Procedure• Procedure
13
Segment welding
ID % Complete Task Name Duration Start Finish
19 19% EF Segment 17 days Sat 09/04/18 Tue 09/05/0520 50% Pre heat 1 day Sat 09/04/18 Sun 09/04/1921 100% Block weld 5 days Sun 09/04/19 Fri 09/04/2422 25% Filler welding 9 days Fri 09/04/24 Sun 09/05/03
M E B M E B M E B M E B M E B M E B M Ed Quarter 3rd Quarter 4th Quart
22 25% Filler welding 9 days Fri 09/04/24 Sun 09/05/0323 0% Back gouge 1 day Sun 09/04/19 Mon 09/04/2024 0% Grind 1 day Mon 09/04/20 Tue 09/04/225 0% UT 1 day Tue 09/04/2 Wed 09/04/2226 0% Filler weld 8 days Wed 09/04/22 Thu 09/04/3027 0% Capping 2 days Thu 09/04/30 Sat 09/05/0228 0% Grinding 10 days Wed 09/04/22 Sat 09/05/0229 0% Painting 3 days Sat 09/05/02 Tue 09/05/0530 19% DE Segment 17 days Fri 09/04/24 Mon 09/05/1131 50% Pre heat 1 day Fri 09/04/24 Sat 09/04/2532 100% Block weld 5 days Sat 09/04/25 Thu 09/04/3033 25% Filler welding 9 days Thu 09/04/30 Sat 09/05/09g y34 0% Back gouge 1 day Sat 09/04/25 Sun 09/04/2635 0% Grind 1 day Sun 09/04/26 Mon 09/04/2736 0% UT 1 day Mon 09/04/27 Tue 09/04/2837 0% Filler weld 8 days Tue 09/04/28 Wed 09/05/0638 0% Capping 2 days Wed 09/05/06 Fri 09/05/0839 0% G i di 10 d T 09/04/28 F i 09/05/08
14
39 0% Grinding 10 days Tue 09/04/28 Fri 09/05/0840 0% Painting 3 days Fri 09/05/08 Mon 09/05/1
Upper rail installation
• GPS alignment on G S a g e t oupper and lower rail
• Special equipment for safe installation
• Hooks for extra support
20
Line boring
• All bearing landings bea g a d gswas line bored
• Bearing landing welded
• Landing machined
• Equipment used
24
Electrical upgrade
• Removing of all cabling and e o g o a cab g a dpanels
• New PLC replacing old technology
• New DC drives replacing exciter set
32
MV upgrade
• New MV switchgear –e s tc geaAlstom
• 2 New 10MVA skids
• Interlock protection between links & Transformer
34
Advantage of electrical upgrade
• Easier fault finding – PLC
• Improved response on controls
• Safety – MCC panels
• 100% Improved protection on circuits
• Permanent condition monitoring
35
Challenges
• Weathereat e
• TimeTime
• Overhead linesOverhead lines
• Centre pintle crack• Centre pintle crack
36
Conclusion
• Planning27 December 2009
• Safety
• Site preparation
• Boom down
• Planned repairs
39
• Challenges & Success