13-1567

Upload: anonymous-lmtmffmpl

Post on 07-Aug-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/20/2019 13-1567

    1/16

     Farnsworth, C.B., Bartlett, S.F., and Lawton, E.C. 1 

    ESTIMATION OF THE TIME-RATE OF SETTLEMENT FOR MULTI-LAYERED

    CLAYS UNDERGOING RADIAL DRAINAGE

    Authors:

    Clifton B. Farnsworth, Ph.D., P.E. (Corresponding Author)Assistant Professor

    Construction Management

    Brigham Young University230 SNLB

    Provo, Utah 84602

    Ph: (801) 422-6494

    F: (801) 422-0653email: [email protected]

    Steven F. Bartlett, Ph.D., P.E.

    Associate ProfessorCivil & Environmental Engineering

    University of Utah

    110 Central Campus Drive, Suite 2000Salt Lake City, Utah 84112

    Ph: (801) 587-7726

    F: (801) 585-5477email: [email protected]

    Evert C. Lawton, Ph.D., P.E.

    Professor

    Civil & Environmental EngineeringUniversity of Utah

    110 Central Campus Drive, Suite 2000Salt Lake City, Utah 84112

    Ph: (801) 585-3947

    F: (801) 585-5477

    email: [email protected]

    Paper Length:

    6,197 Words

    5 Figures0 Tables 

    TRB 2013 Annual Meeting Paper revised from original submittal

  • 8/20/2019 13-1567

    2/16

     Farnsworth, C.B., Bartlett, S.F., and Lawton, E.C. 2 

    ABSTRACTThis paper demonstrates how the finite difference technique can be used to estimate the

    time-rate of settlement for soft, compressible clayey soils treated with prefabricated verticaldrains, at sites where primary consolidation settlement is occurring in a multilayered system at

    varying rates. Semi-empirical methods based on surface settlement monitoring have typically

     been used to estimate the progression of primary consolidation settlement. However,interpretation of such methods can be problematic for multilayered soil profiles. For such sites,it is crucial to obtain a reasonable characterization of the foundation soils’ horizontal drainage

     properties and include these estimates in the time rate of settlement projections. Field

    monitoring of subsurface instrumentation is extremely valuable in providing additionalinformation regarding the consolidation behavior of different layers. When subsurface field

    measurements are coupled with the proposed numerical method, far more reliable projections are

    obtained. This paper focuses on how to integrate field and laboratory data with time-rate of

    settlement projections obtained from semi-empirical and finite difference methods to moreaccurately predict the time-rate of consolidation behavior of multilayered foundation soils.

    TRB 2013 Annual Meeting Paper revised from original submittal

  • 8/20/2019 13-1567

    3/16

     Farnsworth, C.B., Bartlett, S.F., and Lawton, E.C. 3 

    INTRODUCTIONConstruction of large embankments, or other heavy structures, atop soft, thick

    compressible foundation soils requires considerable time to complete end of primary (EOP)consolidation settlement. In urban environments rapid construction techniques are often utilized

    to lessen construction time, thus minimizing disruption to the public and generally decreasing the

    cost of the project. In soft, low permeability soils, prefabricated vertical (PV) drains aretypically used to decrease settlement duration. These drains allow dissipation of excess pore pressures to occur primarily in the horizontal direction by shortening the drainage path and

    therefore markedly decreasing the time to reach EOP consolidation.

    Even if vertical drains are used, the time required to complete EOP consolidationsettlement can still be considerable, making this a critical path activity of many soft ground

    construction projects. Thus, having an accurate projection of the settlement duration is vital for

     project planning and construction. For example, during the reconstruction of I-15 through Salt

    Lake City, Utah (1998-2002),without ground treatment the low permeability thick clayey soilsfound in the underlying Lake Bonneville sediments were expected to produce lengthy primary

    settlement durations greater than two years (1). These lengthy EOP settlement durations could

    not be accommodated in the planned construction schedule without the use of ground treatment.The installation of PV drains and extensive field monitoring of settlement progression

    allowed for the successful completion of the project within the allotted time (2). The use of PV

    drains decreased the time associated with primary settlement to about three to six months,

    depending on the spacing. The Asaoka method for predicting settlement (3) was used as the primary tool for forecasting the EOP consolidation date and correspondingly allowing surcharge

    fill to be removed and paving operations to commence (4). Settlement projections were made

    solely from the surface using settlement plates extending through the fill; thus, the projectionswere based on the composite settlement of the foundation soils.

    As monitoring progressed, the design-build team noted problems with their Asaoka

     projections. Typically as the original EOP projection date neared, an updated projection showed

    that additional settlement time was required. Geotechnical designers suspected that this phenomenon resulted from multiple layers consolidating at different rates, with some of the

    deeper, thicker layers consolidating more slowly. This “delayed” consolidation and its

    associated increase in construction time seriously impacted the project schedule. It wasconcluded that the Asaoka method was not valid for the subsurface conditions found along parts

    of the I-15 alignment due to the heterogeneity in drainage properties of the multilayered profile.

    This paper summarizes subsequent research efforts to analyze the effects of differingconsolidation rates within a subsurface profile on the projection of EOP primary consolidation

    settlement and to develop a more reliable projection method for such conditions (5).

    A critical step in the estimation of settlement behavior is a complete geotechnical

    characterization of the subsurface soils, including identifying the subsurface stratification, thethickness of critical layers, and compressibility and drainage properties of these layers. The

    quality and quantity of the subsurface investigation greatly impacts the settlement projections,

    and for time-critical projects it is imperative that sufficient subsurface evaluations be performed

    to reduce uncertainties. For foundation soils to be treated with PV drains this also includeshaving an adequate knowledge of the horizontal drainage properties of the various soil layers.

    Current methods for obtaining this information include back calculation from field performance

    data, CPTU pore pressure dissipation or other in situ permeability tests, and laboratory Rowe

    TRB 2013 Annual Meeting Paper revised from original submittal

  • 8/20/2019 13-1567

    4/16

     Farnsworth, C.B., Bartlett, S.F., and Lawton, E.C. 4 

    Cell testing (5). Of these methods, the CPTU pore pressure dissipation test appears to be the

    most widely used technique for measuring the horizontal coefficient of consolidation.

    The accuracy of any EOP settlement projection is a function of the predictive methodsemployed and their simplifying assumptions. For some geologic environs with multilayer

    deposits, the evaluation method(s) should consider the potential for various layers consolidating

    at different rates, primarily due to differences in horizontal permeability. This paper contains anevaluation of several potential EOP projection methods, their associated assumptions, andimplementation issues, progressing from simplified to more elaborate techniques.

    ASAOKA PROJECTION METHODThe progression of consolidation settlement is often monitored to verify initial settlement

     projections and design parameters and to release areas for subsequent construction. In essence,

    this is an application of the Observational Method (6 ), where decisions or revision of fast-paced

    construction schedules are made according to the most recent field observations. Semi-empiricalmethods, such as the Asaoka method, are attractive because they rely on observed settlement

    data to make EOP projections that can be updated as more data become available.

    The Asaoka method can be used to forecast the amount of EOP settlement and to backcalculate the coefficient of consolidation. It is applicable to a homogeneous clay layer

    undergoing primary consolidation settlement owing to the application of a constant load. This

    method follows the theory of consolidation introduced by Mikasa (7 ) that the 1-D consolidation

    of clay is a function of the compressive strain, as opposed to the excess pore water pressuredissipation used in Terzaghi theory (8). Asaoka used Mikasa theory because by being developed

    from compressive strain, it was directly linked to the settlement. However, Asaoka considered

    that a uniform strain develops throughout the clay profile, which is an incorrect assumption formany situations. Duncan clearly demonstrated that this common assumption significantly

    reduces the accuracy of the estimated time rate of settlement (9). When the strains decrease with

    depth, which they typically do, the consolidation occurs more rapidly than when the strains are

    uniform, when drainage occurs only at the top of the layer. Therefore, the relationship betweenthe degree of consolidation and the actual strain profile must be accounted for to accurately

    estimate the time rate of settlement.

    In implementing the Asaoka method, settlement monitoring is generally performed at thesurface using settlement plates that measure the composite vertical compression of the

    foundation soils. The data analysis for this method involves selecting settlement data at

    successive equal time steps. The settlement for the current time step (N) is then plotted againstthe settlement for the previous time step (N – 1). As settlement progresses the difference between

    successive readings decreases and upon completion of settlement the values are equal.

    Therefore, the best-fit line through these points intercepts a 1:1 sloped line, thus, providing the

    ability to estimate both the projected magnitude of settlement and the time remaining to the endof primary settlement. The basic form of the resulting first order difference equation is:

    S i = β 0 + β 1 S i-1 (1)

    where S  is the measured settlement at time i, and β 0 and β 1 are the intercept and slope,

    respectively, of the plotted line (3).When successive data points are plotted they often do not follow the linear relationship

    suggested by Asaoka, especially in the early part of the settlement history. Figure 1 shows an

    example of this, using settlement data generated for a single layer with a numerical model. Thetheoretical settlement data are plotted at equal time intervals starting from the initial settlement

    TRB 2013 Annual Meeting Paper revised from original submittal

  • 8/20/2019 13-1567

    5/16

     Farnsworth, C.B., Bartlett, S.F., and Lawton, E.C. 5 

    reading. Even though the projection becomes more linear as the EOP consolidation settlement

    nears, the nonlinearity in the early part of the projection unfortunately causes an increase in the projected settlement data as more data are obtained and plotted.

    Asaoka also suggested that a higher order autoregressive equation can be used for multi-

    layered systems. This general settlement prediction model is expressed as:

    S i = β 0 + ∑  β  L S i- L  (2)

    where the subscript, L, represents the number of different layers. However, there is not any

    guidance for determining the partial slopes, β  L, for Equation (2). Instead the focus is on the single

    layer application to interpreting and forecasting field data (3). The higher order autoregressive

    equation was not used by the I-15 designers for their predictions. Rather, the first order equationwas applied for forecasting, thus essentially treating the foundation system as a single

    homogeneous clay layer. Unfortunately, for the multilayered system with differing consolidation

    rates, the use of Equation (1) provided somewhat inaccurate results.

    ASAOKA PROJECTIONS WITH DATA INTERPOLATION Field settlement data are often not gathered in equal time intervals, even though this is

    necessary for utilizing the Asaoka method. For these cases, data interpolation is a useful tool for

    0

    0.2

    0.4

    0.6

    0.8

    1

    1.2

    1.4

    0 0.2 0.4 0.6 0.8 1 1.2 1.4

    Settlement at time N-1 (m)

       S  e   t   t   l  e  m  e  n   t  a   t   t   i  m  e   N   (  m

    FIGURE 1 Numerically modeled settlement data plotted with the

    Asaoka Method demonstrating nonlinearity, especially in the early

    portion of the dataset.

    TRB 2013 Annual Meeting Paper revised from original submittal

  • 8/20/2019 13-1567

    6/16

     Farnsworth, C.B., Bartlett, S.F., and Lawton, E.C. 6 

    creating continuous curves and generating equal time intervals. The I-15 design team used this

    approach, fitting the field data with a theoretical 1-D consolidation curve based on Terzaghi’s

    theory (8), and then interpolating the data to equal time increments prior to performing theirAsaoka projections.

    The 1-D primary consolidation settlement at any time (t ) after a load has been applied is

    estimated by the following equation: S c(t ) = U v S c(t =∞)  (3)where S c is the settlement at time t , and U v is the degree of consolidation with vertical drainage.

    It should be noted that this equation is fundamentally incorrect. Values of U v actually represent

    the average degree of dissipation of excess pore water pressure within the compressible layer andnot the average degree of primary consolidation settlement. Duncan demonstrated how the use

    of the assumption shown in Equation (3) can provide unrealistic results, because conventional

    theory assumes that the stress-strain behavior of the soil skeleton is linear and elastic (9). For

    one-dimensional consolidation this is essentially the equivalent of assuming that the strains areconstant throughout the compressible layer (10). However, strains are more closely related to the

    log of effective stress. This means that the strains are greatest in the upper portions of the soil

    layer and decrease with depth within the layer. Duncan further showed that the dissipation ofexcess pore water pressure needs to correspond to the actual strain profile to provide accurate

    results (9).

    Equation (4) from Sivaram and Swamee (11) is a best-fit approximation of Terzaghi’s 1-

    D equation and can be used to calculate the average degree of consolidation for two-way verticaldrainage (e.g., where PV drains have not been used):

    U v = 100 * [(4T v / π)0.5

    ] / [1 + (4T v / π)2.8

    ]0.179

      (4)

    where T v is the dimensionless time factor for two-way vertical drainage and is a function of thecoefficient of vertical consolidation, cv, the drainage path length, H , and the time of

    consolidation, t . To match field settlement data with Equation (4), both the estimated EOP

    settlement and T v must be adjusted until a best fit of the field data is obtained.

    To calculate the average degree of consolidation for radial drainage (e.g., where PVdrains have been used), the equation given by Barron (12) may be used:

    U r  = 1 –  e-8T r  / F (n)  (5)

    where U r  is the degree of consolidation with radial drainage, T r  is the radial drainage time factor,and F (n) is equal to:

     F (n) = ln(n) * [n2 / (n

    2 - 1)] –  [(3n

    2 - 1) / (4n

    2)] (6)

    and n is the drain spacing ratio defined by:n = d e / d w  (7)

    and d e is the equivalent diameter of influence and d w is the diameter of the drain. T r  is similar to

    the dimensionless vertical drainage time factor, T v, but T r  is a function of the coefficient of

    horizontal consolidation, ch, the length of the horizontal drainage path, d e, (which is equal to twotimes the radius of an equivalent soil cylinder from which radial drainage occurs), and the time

    of consolidation, t . Values of T r  are related to these parameters by ch/d e2. As before, to match

    the field settlement data with the analytical curve(s), trial values of EOP settlement and T r  must

     be made until a best fit is obtained.Because Equations (4) and (5) are based on Terzaghi’s 1-D consolidation theory, the

    accuracy of the results are therefore limited by the simplifying assumptions for which

    conventional theory is based, as mentioned. However, this research has demonstrated thatAsaoka projections relying solely on surface settlement data can provide reasonable results for

    TRB 2013 Annual Meeting Paper revised from original submittal

  • 8/20/2019 13-1567

    7/16

     Farnsworth, C.B., Bartlett, S.F., and Lawton, E.C. 7 

    sites with multiple layers consolidating at or near the same rate, but this is not true for sites

    where multiple layers are consolidating at very different rates. For such cases, additional

    monitoring data and analytical approach are required, as discussed subsequently.

    ASAOKA PROJECTIONS WITH SUBSURFACE MEASUREMENTS 

    During the I-15 Reconstruction Project, magnet extensometers were placed at keylocations to measure the compression of individual clay layers within the soil profile. Thismonitoring strategy is preferable where clay layers are consolidating at markedly different rates

     because this technique can provide more reliable estimates of the time rate of consolidation than

    surface monitoring. Project data from magnet extensometer MR s29-6-1 will be used as anexample to show how to calculate the rate of consolidation for individual layers.

    Prior to fill placement, a magnet extensometer was installed in the foundation soils. Nine

    spider magnets were strategically placed within the subsurface, one at the base of the drill-hole

    and another just beneath the ground surface, and seven others in between targeting major soil boundaries (see Figure 2). Spider magnets are designed to remain at the relative soil location at

    which they are installed. An extensometer probe subsequently measures the decreasing relative

    distance between adjacent magnets, thus revealing the compression of the individual soil layers(13). Magnet elevations for this extensometer were predetermined using a CPT profile. Figure 2

    shows the CPT profile for this site and the corresponding magnet elevations in relation to the soil

     boundaries. The four major layers contributing to the foundation settlement at this site include

    the upper Lake Bonneville clay (ULBC), interbedded silts and sands (IB), lower Lake Bonnevilleclay (LLBC), and deeper Pleistocene alluvium and clay (PA) (see Figure 2).

    The settlement at this location was caused by the placement of a 12-m high embankment

    (including surcharge) that was constructed over PV drain treated foundation soil. The settlementcurves in Figure 3(a) are calculated from the change in elevation with respect to time for each

    magnet. Because the settlement measured at each magnet is cumulative, these plots show the

    total amount of compression that occurred in all layers below each magnet position. Therefore,

    magnets with the largest settlement are those positioned closest to the surface. The embankment that caused this settlement was placed in two major stages, with the

    second stage of construction beginning in September 1998. The bottom two magnets (base

    magnet and magnet 1) did not show any measurable settlement; thus, the elevation of thesemagnets did not change due to the placement of the embankment, as shown in Figure 3(a). In

    contrast, the top two magnets (magnet 7 and surface magnet) represent the total settlement of the

    soil profile because all of the measured foundation settlement occurred beneath the elevations ofthese two magnets. These data indicate that there was about 0.8 m of foundation settlement that

    occurred over a 9-month period.

    As indicated earlier, the Asaoka method is based on the assumption that the loading

    remains continuous throughout the settlement record. In this case, the Asaoka method can beapplied to the data starting from the beginning of embankment placement through September, or

    it can be applied to the data starting in September through the end of the record. However, the

    data for the second stage is generally more important because it represents the full loading

    condition, and its settlement behavior controls the start date for subsequent pavementconstruction. Because the settlement history is known in each major layer, the Asaoka method

    can be used to estimate the total settlement, consolidation rates, and drainage properties for each

    layer. The settlement plots in Figure 3(b) were obtained by differencing the total settlementmeasurements for each of the four major layers contributing to the foundation settlement.

    TRB 2013 Annual Meeting Paper revised from original submittal

  • 8/20/2019 13-1567

    8/16

     Farnsworth, C.B., Bartlett, S.F., and Lawton, E.C. 8 

    Subsequently, the data in Figure 3(b) was used to make Asaoka projections for the

    individual layers shown in Figure 3(a). Equation (5) was used to interpolate the data to equal

    time increments prior to completing the projections. The percentage of EOP settlement at day279 (the final day within the record) was 99.6, 98.2, 84.2, and 93.7%, for the ULBC layer, IB

    layer, LLBC layer, and PA layer, respectively. An Asaoka projection was also performed for the

    entire soil profile using only surface settlement data and resulted in the foundation soilsachieving 95.4% consolidation at day 279. However, this percentage is misleading because itfails to account for the varying consolidation rates actually occurring within each layer. The

    individual layer results clearly identify that the different intervals are consolidating at different

    rates. Surface settlement projections cannot account for these differences and therefore over project the actual level of consolidation. In this case, the result would be additional settlement

    within the LLBC layer.

    PA

    LLBC

    IB

    ULBC

    Base

    1

    2

    3

    4

    5

    67Surface

    FIGURE 2 Predominant subsurface layers shown with corresponding magnets

    (horizontal lines labeled base through surface) for magnet extensometer MR s29-6-1.

    TRB 2013 Annual Meeting Paper revised from original submittal

  • 8/20/2019 13-1567

    9/16

     Farnsworth, C.B., Bartlett, S.F., and Lawton, E.C. 9 

    -0.30

    -0.25

    -0.20

    -0.15

    -0.10

    -0.05

    0.00

    10 100 1000

    Days

       S  e   t   t   l  e  m  e  n   t   (  m   )

    PA (1 to 3)

    LLBC (3 to 4)

    IB (4 to 5)

    ULBC (5 to 6)

    FIGURE 3 (a) Settlement versus time data for magnet extensometer MR s29-6-

    1, (b) Total settlement record for each of the subsurface target intervals,

    plotted against the logarithm of time.

    PA

    LLBC

    IB

    ULBC

    TRB 2013 Annual Meeting Paper revised from original submittal

  • 8/20/2019 13-1567

    10/16

     Farnsworth, C.B., Bartlett, S.F., and Lawton, E.C. 10 

    To maximize the effectiveness of the surcharge, the I-15 design team selected 98% EOP

    consolidation as the target value for starting surcharge removal and subsequent pavement

    construction (2). This value was calculated based on Asaoka projections that used surfacemonitoring from a single settlement plate placed at the base of the fill, since the use of magnet

    extensometers was relatively limited for this project. However, the results clearly indicate that

     better EOP estimates could have been made if layer-by-layer projections and more appropriatemethods with consistent assumptions had been used. This research indicates that magnetextensometers should be deployed for heterogeneous, multilayered systems, especially for cases

    where high quality geotechnical data are not available to adequately quantify the coefficient of

    consolidation for the various layers. This is especially true for time critical embankments wherethe subsurface soils are not fully characterized and estimates of drainage properties have not

     been obtained or are poorly supported by the data at hand.

    The magnet extensometer data can also be used to back-calculate the effective horizontal

    coefficient of consolidation, ch(e), for each consolidating layer. The term “effective” is used because the back calculated values represent the average horizontal coefficient of consolidation

    for the selected interval between two respective magnets, influenced by the disturbed zone that

    typically develops around the PV drains. The back calculation is performed from magnetextensometer data for each individual soil layer using the technique described by Bergado (14).

    This technique utilizes results from the Asaoka projection method, and therefore maintains the

    same limitations as the Asaoka method, as previously identified. The simplified equation for this

     back calculation is:ch(e) = ( F n + F  s) / [C 1 + (C 2 / qw)] (8)

    where F n is a drain spacing correction, F  s accounts for the installation smear effects, C 2 accounts

    for drain well resistance, and qw is the discharge capacity of the drain. The C 1 term requires theslope of the projection line (i.e., β 1) and the incremental time step (i.e., Δt) from the Asaoka

     projection, along with the equivalent PV drain zone of influence (5).

    Back calculated values of ch(e) using the settlement record from magnet extensometer MR

    s29-6-1 are 38, 25, 10, and 16 mm2/min for the UBLC, IB, LLBC, and PA layers, respectively.

    The average value of ch(e) for the entire subsurface is 18 mm2/min. The above ch(e) values are

    useful because they represent estimates of the actual drainage properties for the PV drain treated

    soils, including installation disturbance effects. For this particular example, the horizontalcoefficient of consolidation for the LLBC layer is only one-fourth that of the ULBC layer.

    PROJECTIONS USING THE FINITE DIFFERENCE METHODTerzaghi’s 1-D consolidation equation is a 2

    nd order partial differential equation that can

     be solved in a variety of ways. Perrone developed a general finite-element 1-D consolidation

    computer program for vertical drainage of multilayered systems (15). However, this program

    does not address radial drainage in soils with PV drains. We believe that the finite differencemethod (FDM) offers the simplest and most direct way of numerically modeling the

    consolidation process for PV drain treated soil (16 , 17 ). In addition, the properties required for

    the FDM can be obtained from high-quality laboratory testing, or from in situ measurements that

    are further verified and calibrated with magnet extensometer data for multilayered systems.Regardless of the numerical approach, conventional theory (8, 18) has three important

    assumptions that must be addressed to provide reliable estimates of the consolidation process (9).

    These assumptions are that the coefficient of consolidation is constant, the stress-strain behavior

    TRB 2013 Annual Meeting Paper revised from original submittal

  • 8/20/2019 13-1567

    11/16

     Farnsworth, C.B., Bartlett, S.F., and Lawton, E.C. 11 

    of the soil skeleton is linear and elastic, and how the vertical strain distribution in the soil profile

    relates to the average degree of consolidation and the dimensionless time factor (T).

    Regarding the first assumption, the coefficient of consolidation greatly decreases as thevertical effective stress reaches the preconsolidation pressure and also varies as a function of

    depth and with time in a given layer (9). These considerations are accommodated by the FDM

     because its fundamental algorithm allows for material properties to change with respect tooverconsolidation ratio and effective vertical stress at each time step, for each sublayer or node.Regarding the second assumption, soil behavior is actually nonlinear; thus, 1-D Terzaghi

    consolidation theory (8) is not applicable for large-strain consolidation problems like those found

    in highly compressible clays (9). Standard consolidation tests show that the change in void ratio(or vertical strain) is proportional to the change in the logarithm of effective stress for

    recompression and virgin compression. Thus, results from representative laboratory

    consolidation tests can be used describe the nonlinear relationship between void ratio and

    effective vertical stress for recompression and virgin compression. However, in doing so, therecompression and virgin compression indices (i.e, cr  and cc) should be corrected using a method

    such as that developed by Schmertmann (19) to obtain the slopes for “field corrected” cr  and cc 

    values for each sublayer. Also, a good definition of the overconsolidation ratio is needed so thatthe appropriate compression index can be used to calculate the incremental settlement within

    each sublayer.

    Finally, the third assumption is not necessary in the implementation of the FDM because

    the strain is calculated between nodal points within the mesh. Therefore, no a priori assumptionis needed regarding the strain distribution that develops within the mesh.

    For this research, the FDM was developed in spreadsheet format using the equations for

    1-D consolidation summarized by Das (17 ) for both the vertical and radial drainage cases (5).The basic finite difference equation to express the dissipation of excess pore water pressure for

    1-D vertical consolidation of a soil layer using two-way vertical drainage is:

    u0,t +Δt  = (Δt  / (Δ z )2) * (u1,t  + u2,t  - 2u0,t ) + u0,t   (9)

    where u is the excess pore water pressure, Δt  is a factor equal to the coefficient of verticalconsolidation, cv, multiplied by the change in time, Δt , and Δ z  is the change in depth. In this

    equation, node 0 represents the selected node, node 1 represents the adjacent node directly

    above, and node 2 represents the adjacent node directly below. With this equation, a linear set ofvertical nodes can be used to calculate the 1-D dissipation of excess pore pressures within the

    subsurface profile considering only vertical drainage.

    The FDM can also be used to estimate the dissipation of excess pore pressures for theradial drainage case. The basic finite difference solution for one-dimensional consolidation

    considering only radial drainage is:

    u0,t +Δt  = (Δt /(Δr )2)*{u3,t +u4,t +[(u4,t  – u3,t )/2(r /Δr )]-2u0,t } + u0,t   (10)

    where u is the excess pore water pressure, Δt  is a factor equal to the coefficient of horizontalconsolidation, ch, multiplied by the change in time, Δt , r  is the radius of drainage influence for

    the PV drain, and Δr  is the change in radius. In this equation, node 0 represents the selected

    node, node 3 represents the adjacent node directly to the left, and node 4 represents the adjacent

    node directly to the right. From this equation, a linear set of horizontal nodes can be used tocalculate the 1-D radial dissipation of excess pore pressures within the subsurface profile.

    For PV drain treated soil, both horizontal and vertical drainage occur. However, for

    relatively thick clay layers (3 to 5 m, or greater) and with typical PV drain spacing (1.5 m

    TRB 2013 Annual Meeting Paper revised from original submittal

  • 8/20/2019 13-1567

    12/16

     Farnsworth, C.B., Bartlett, S.F., and Lawton, E.C. 12 

    triangular spacing), drainage will occur predominately in the radial direction; thus, vertical

    drainage was neglected for the analyses and results shown later.

    The value of Δt  / (Δr )2 in Equations (9) and (10) must remain less than 0.5 for

    convergence of the solution. The best approximation of the solution occurs for Δt  / (Δr )2 equal

    to the ratio of 1/6 (20). Additionally, because consolidation is a highly nonlinear process, it is

    important to subdivide relatively thick layers into sublayers approximately 0.3-m thick. Theincrease in effective vertical stress for each sublayer can be calculated using methods thataccount for the geometry of the embankment or applied loading and layering of the foundation

    soils. For this research, a 2-D vertical stress distribution was developed using the Boussinesq

    solution for the calculation of vertical stress beneath the center of an embankment (21). It wasfurther assumed that the initial excess pore water pressure was equal to the change in vertical

    stress, based on the vertical stress distribution.

    The use of the FDM to calculate the time-rate of settlement of foundation soils provides

    the ability to replicate the actual fill placement process, which may take several weeks and iscommonly referred to as a ramp loading. The actual load can be adjusted at the appropriate time

    steps within the finite difference model to represent the loading sequence or to use an average

    loading condition for the duration of the ramp loading and then adjust the model to the final loadcondition at the completion of the ramp loading sequence. Additionally, if staged embankment

    construction is used, the staged loading can be modeled as a series of instantaneous loads that are

     placed at certain intervals of time. Thus, the FDM has the inherent ability (because it is a time

    stepping technique) to provide estimates of pore pressure dissipation for the anticipated or actualloading scenario.

    To implement the FDM for a PV drain treated soil, a horizontal 1-D finite mesh is created

    for each sublayer and representative values of the horizontal coefficient of consolidation must beselected for each sublayer. Back calculated values of ch(e) from magnet extensometer data are

    especially useful, because they provide an average horizontal coefficient of consolidation for

    specific layers, including any disturbance effects resulting from PV drain installation. If back

    calculated ch(e)

     values are not available, then an assumption must be made regarding the degreeof disturbance and its effect upon the horizontal coefficient of consolidation. In most instances,

    field performance data will not be available and the horizontal drainage properties of the soil

    layers must be obtained in some other manner. The most common technique is with the CPTU pore pressure dissipation test. However, other in situ permeability tests could also be performed.

    An underutilized technique is utilization of the Rowe Cell, which can be used to perform a 1-D

    laboratory consolidation test with radial drainage. Each of these techniques provides a measureof the horizontal coefficient of consolidation.

    Once all compressibility and drainage properties were defined for this research, the FDM

    spreadsheet was used to calculate the dissipation of the excess pore water pressure, the change in

    vertical effective stress, and the subsequent vertical strain and settlement as a function of timedue to the placement of the embankment. The effective vertical stress at each time step was

    calculated as the average dissipated excess pore water pressure in the sublayer added to the

    original in situ effective stress for hydrostatic conditions. The change in void ratio for virgin

    compression during each time increment is calculated as:

    e = cc log (vt +t   / v(t )) (11)For recompression, the same equation can be used, except that cr  is substituted for  cc. The

    vertical strain for each sublayer is calculated from:

    vi = e / (1 + eo) (12)

    TRB 2013 Annual Meeting Paper revised from original submittal

  • 8/20/2019 13-1567

    13/16

     Farnsworth, C.B., Bartlett, S.F., and Lawton, E.C. 13 

    where eo is the initial void ratio for recompression or the void ratio at the preconsolidation stress

    for virgin compression. The settlement for each sublayer is:

    S vi = vi * i  (13)The summation of settlement for all individual sublayers produces the total settlement at eachtime increment.

    The FDM is particularly useful as an observational technique during construction tointerpret field performance data by adjusting or calibrating the model to match the subsurfacesettlement measurements. Because magnet extensometer measurements were available for this

    research, values of ch(e) for each layer were back calculated using the settlement data shown in

    Figure 3(b). A trial and error method was used by varying ch(e) values for each layer until the

    FDM model matched the observed settlement record, as shown in Figure 4. Other FDM model parameters, including estimates of the initial effective vertical stress, OCR, and the field

    corrected cr  and cc for each layer, were obtained from laboratory Rowe Cell testing utilizing

    horizontal drainage (5).

    The back calculated ch(e) values were 26, 13, 5, and 9 mm2/min for the ULBC, IB, LLBC,

    and PA layers, respectively. These values are lower than those obtained using the Asaoka backcalculation method, varying between approximately 30% - 50% smaller. Comparably, values of

    ch(e) for typical Lake Bonneville clay deposits, obtained in the laboratory using a Rowe Cell with

    horizontal drainage capabilities, vary between about 4 and 90 mm2/min (5). The laboratory

    -0.80

    -0.70

    -0.60

    -0.50

    -0.40

    -0.30

    -0.20

    -0.10

    0.00

    0 50 100 150 200 250 300

    Time (days)

       S  e   t   t   l  e  m  e  n   t   (  m   )

    layer 5-6

    layer 4-5

    layer 3-4

    layer 1-3

    Total Settlement

    FIGURE 4 Finite difference generated settlement profiles (solid lines) with actual

    individual layer results from magnet extensometer MR s29-6-1, as well as the

    total settlement curve and numerically modeled results for the entire profile.

    TRB 2013 Annual Meeting Paper revised from original submittal

  • 8/20/2019 13-1567

    14/16

     Farnsworth, C.B., Bartlett, S.F., and Lawton, E.C. 14 

    values provided a much wider range, because samples from many different depths were tested,

    while the back calculated effective values represent an average across each layer. Furthermore,

    the FDM results show the dissipation of excess pore pressure at day 279 as 99.3, 91.7, 63.4, and82.6% for the ULBC, IB, LLBC, and PA layers, respectively. These results show that the bottom

    three layers do not have nearly the dissipation of excess pore pressure as originally obtained

    using the Asaoka back projection method, especially the LLBC layer. The FDM results areapproximately 7% - 25% smaller. This further demonstrates the importance of correctlymodeling pore pressure dissipation for time-rate of settlement calculations.

    Figure 4 also shows the calculated composite settlement curve from the FDM calibrated

    to the magnet extensometer data, demonstrating a good fit to the observed data. Thus, weconclude that the FDM can be used to reasonably estimate the total settlement curve for a

    multilayered system consolidating at different rates, when properly calibrated. However, the use

    of magnet extensometer data provides a better understanding of the individual layers contributing

    to the composite settlement profile and demonstrates the value of such data.

    CONCLUSIONS

    In many instances of highway embankment construction over soft soil sites within anurban environment, the time required for primary consolidation settlement to occur governs the

    critical path of the embankment construction. Having an accurate projection of the end of

     primary settlement is often much more critical than having an accurate estimate of the magnitude

    of the total settlement. To provide accurate time-rate of settlement estimates, it is of foremostimportance that an appropriate geotechnical investigation and subsurface characterization be

     performed and that subsequent design and construction techniques are appropriately utilized.

    The Asaoka projection method can be a valuable tool for estimating EOP consolidationsettlement, but its accuracy is limited by its simplifying assumptions. For foundations with fairly

    uniform consolidation properties, the Asaoka method with curve-fitting techniques can be

    effectively used for both vertical and radial drainage. However, this method loses accuracy for

    cases when the foundation soils include multiple layers consolidating at substantially differentrates. For such cases, more rigorous methods, such as the FDM, are recommended.

    The data obtained from magnet extensometers can greatly improve the accuracy of EOP

     projections. The use of magnet extensometer data, in conjunction with the Asaoka method,makes it possible to estimate the level of consolidation for each subsurface layer. Such data can

     be utilized with back calculation methods to provide the effective coefficient of consolidation for

    each subsurface layer, which considers disturbance effects resulting from PV drain installation.The FDM is an underutilized numerical tool with the ability to provide accurate estimates

    of the time-rate of settlement of foundation soils with radial drainage. This accuracy occurs

     because the dissipation of excess pore pressures and its relation to vertical strain is more

    correctly accounted for in the calculations. However, to implement the FDM a comprehensivecharacterization of the foundation soils is required to provide reliable projections. This research

    demonstrated that the FDM coupled with magnet extensometer measurements provides an

    accurate fit of the observed settlement behavior. This research suggests that the FDM be more

    universally applied.The methods described within this paper should be utilized to provide more accurate

    time-rate of settlement estimates for layered clay systems with radial drainage, with the best

    method being the FDM coupled with magnet extensometer data. Maintaining a harmonious balance between the geotechnical evaluations and the use of observational data is an important

    TRB 2013 Annual Meeting Paper revised from original submittal

  • 8/20/2019 13-1567

    15/16

     Farnsworth, C.B., Bartlett, S.F., and Lawton, E.C. 15 

     part of geotechnical engineering. When used together appropriately, they provide the ability to

    achieve accurate and reliable estimates of the time-rate of settlement behavior for soft

    multilayered foundation soils.

    ACKNOWLEDGEMENT

    The authors wish to acknowledge and thank the Research Division of the UtahDepartment of Transportation for their financial contributions and technical support to thisresearch project. 

    REFERENCES(1) Farnsworth, C.B., S.F. Bartlett, D. Negussey, and A.W. Stuedlein. Rapid Construction and

    Settlement Behavior of Embankment Systems on Soft Foundation Soils. Journal of Geotechnical

    and Geoenvironmental Engineering, Volume 134, No. 3, 2008, pp. 289-301.

    (2) Saye, S.R., C.C. Ladd, P.C. Gerhart, J. Pilz, and J.C. Volk. Embankment Construction in anUrban Environment: The Interstate 15 Experience. Foundations and Ground Improvement,

     Proceedings, ASCE Specialty Conference, Blacksburg, Virginia, June, 2001, pp. 842-857. 

    (3) Asaoka, A.“Observational Procedure of Settlement Prediction. Soils and Foundations Journal, Vol. 18, No. 4, 2008, pp. 87-101.

    (4) Bartlett, S.F., G. Monley, A. Soderborg, and A. Palmer. Instrumentation and Construction

    Performance Monitoring for the I-15 Reconstruction Project, Salt Lake City, Utah.

    Transportation Research Record: Journal of the Transportation Research Board ,  No. 1772,2001, pp. 40-47.

    (5) Farnsworth, C.B., and S.F. Bartlett. Evaluation of Methods for Determining Horizontal

     Drainage Properties of Soft Clayey Soils. Research Report No. UT-08.11, Utah Department ofTransportation, 2008.

    (6 ) Peck, R.B. Advantages and Limitations of the Observational Method in Applied Soil

    Mechanics. Geotechnique, Vol. 19, No. 2, 1969, pp. 169-187.

    (7 ) Mikasa, M. The Consolidation of Soft Clay –  A New Consolidation Theory and itsApplication. Civil Engineering in Japan, 1965, pp. 21-26.

    (8) Terzaghi, K. Erdbaumechanik auf Bodenphysikalischer Grundlage. Franz Deuticke, Leipzig

    and Wein, 1925.(9) Duncan, J.M. Limitations of Conventional Analysis of Consolidation Settlement,” Journal of

    Geotechnical Engineering , Vol. 119, No. 9, 1993, pp. 1333-1359.

    (10) Lawton, E.C. Practical Foundation Engineering Handbook . McGraw-Hill, New York,2000.

    (11) Siviram, B., and P. Swamee. A Computational Method for Consolidation Coefficient. Soils

    and Foundations Journal , Vol. 17, No. 2, 1977, pp. 48-52.

    (12) Barron, R.A. Consolidation of Fine-Grained Soils by Drain Wells. ASCE Transactions, Vol.113, 1948, pp. 718-742.

    (13) Bartlett, S.F., and C.B. Farnsworth. Monitoring and Modeling of Innovative Foundation

    Treatment and Embankment Construction used on the I-15 Reconstruction Project, Project

     Management Plan and Instrument Installation Report . Research Report No. UT-04.19, UtahDepartment of Transportation, 2004.

    (14) Bergado, D.T. Asian Experiences on the Use of Prefabricated Vertical Drains in Soft

    Bangkok Clay. Proceedings of the 1st International Symposium on Lowland Technology, Saga,Japan, November, 1998, pp. 49-60.

    TRB 2013 Annual Meeting Paper revised from original submittal

  • 8/20/2019 13-1567

    16/16

     Farnsworth, C.B., Bartlett, S.F., and Lawton, E.C. 16 

    (15) Perrone, V.J. One Dimensional Computer Analysis of Simultaneous Consolidation and

    Creep of Clay. Dissertation, Virginia Polytechnic Institute and State University, Blacksburg,

    Virginia, 1998.(16 ) Harr, M.E. Foundations of Theoretical Soil Mechanics. McGraw-Hill, New York, 1966.

    (17 ) Das, B.M. Advanced Soil Mechanics. Hemisphere Publishing, New York, 1983.

    (18) Terzaghi, K., and O.K. Frolich. Theory of Settlement of Clay Layers. Leipzig, 1936.(19) Schmertmann, J.H. The Undisturbed Consolidation Behavior of Clay. ASCE Transactions,Vol. 120, 1955, pp. 1201-1233.

    (20) Scott, R.F. Principles of Soil Mechanics. Addison-Wesley, Reading, 1963.

    (21) Boussinesq, J. Application des Potentials a L’etude de L’equilibre et du Mouvement desSolides Elastiques. Gauthier-Villars, Paris, 1863.