Page 1: 10 Year Capital Improvement Plan and HLS · 10 Year Capital Improvement Plan •Annually, the District has $1,400,000 to put towards capital improvement projects. The dollars come

10 Year Capital Improvement Plan and HLS

Page 2: 10 Year Capital Improvement Plan and HLS · 10 Year Capital Improvement Plan •Annually, the District has $1,400,000 to put towards capital improvement projects. The dollars come

Health Life Safety

• We are required to complete all “A” level items by the end of one year.

• We have gone through the report and determined how each item will be addressed.

• The items will be completed by one of the following means:

• District personnel (O/M Fund)

• HLS Funds (HLS Fund)

• Capital Improvement Plan will take care of it (Capital Improvement Fund)

Page 3: 10 Year Capital Improvement Plan and HLS · 10 Year Capital Improvement Plan •Annually, the District has $1,400,000 to put towards capital improvement projects. The dollars come

HLS “A” Item Costs

• “A” Item Total $419,124

• These items must be taken care of during school year 2014-15

• We will pay for these from our HLS Fund.

Page 4: 10 Year Capital Improvement Plan and HLS · 10 Year Capital Improvement Plan •Annually, the District has $1,400,000 to put towards capital improvement projects. The dollars come

HLS “B” Items : Scenario 1 • Currently we have $5,634,810 in HLS “B” Items

• Scenario 1 is based on Central and Centennial being rebuild and refurbished which would take care of $2,545,005 in “B” items

• “B” Item Total $5,634,810 • Central $1,689,205(Assumes Referendum Passes and we reuse

Central without students in attendance)

• Centennial $855,800 (Assumes Referendum Passes)

• Bottenfield $6,500 (Completed Renovation)

• Kenwood $151,000

• Robeson $12,700

• Westview $29,735

• $2,889,870 Total left for “B” Items

Page 5: 10 Year Capital Improvement Plan and HLS · 10 Year Capital Improvement Plan •Annually, the District has $1,400,000 to put towards capital improvement projects. The dollars come

HLS “B” Items : Scenario 2 • Scenario 2 is based on Central and Centennial NOT being

rebuilt and refurbished: this would add $2,545,005 to our yearly capital improvement plan.

• “B” Item Total $5,634,810

• Central $1,689,205(Referendum Does Not Pass)

• Centennial $855,800 (Referendum Does Not Pass)

• Bottenfield $6,500 (Addressed Through Renovation)

• Kenwood $151,000 (Addressed Through Renovation)

• Robeson $12,700 (Addressed Through Renovation)

• Westview $29,735 (Addressed Through Renovation)

• $5,434,875 Total left for “B” Items

Page 6: 10 Year Capital Improvement Plan and HLS · 10 Year Capital Improvement Plan •Annually, the District has $1,400,000 to put towards capital improvement projects. The dollars come

10 Year Capital Improvement Plan • Annually, the District has $1,400,000 to put towards capital

improvement projects. The dollars come from three sources:

• 61 FUND -$1,100,000

• 20 FUND- $300,000

• 90 FUND- Money can only be used for State Approved Health Life Safety needs. Current fund balance is close to $800,000

• The Operations and Maintenance Staff have identified facility needs, their projected costs, and a 10 year timeline for these improvements.

Page 7: 10 Year Capital Improvement Plan and HLS · 10 Year Capital Improvement Plan •Annually, the District has $1,400,000 to put towards capital improvement projects. The dollars come

10 Year Overview

2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24

Total Expense by Year $368,000 $709,500 $1,443,500 $1,313,500 $1,548,500 $1,585,000 $1,613,500 $1,573,500 $1,513,500 $1,413,500

61 FUND $ $350,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000

20 FUND $ $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000

Total Available $ $650,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000

Over/Under $ $282,000 $690,500 -$43,500 $86,500 -$148,500 -$185,000 -$213,500 -$173,500 -$113,500 -$13,500

Total Project Expense Over 10 Yrs $13,082,000

Total 61 Fund $ Over 10 Yrs $10,250,000

Total 20 Fund $ Over 10 Yrs $3,000,000

Total Available $ Over 10 Yrs $13,250,000

Excess $ Available Over 10 Yrs $168,000

WITHOUT HLS REQUIREMENTS

Page 8: 10 Year Capital Improvement Plan and HLS · 10 Year Capital Improvement Plan •Annually, the District has $1,400,000 to put towards capital improvement projects. The dollars come

Funding/Cost Considerations

• HLS Scenario 1 is based on $2,889,870 for “B” Items. • $419,124 first year for “A” Items paid from HLS Fund Balance.

• $722,468 each year for four years for “B” Items.

• $677,532 available for 10 Year Capital Development Plan.

• HLS Scenario 2 is based on $5,434,875 for “B” Items. • $419,124 first year for “A” Items paid from HLS Fund Balance.

• $1,358,719 each year for four years for “B” Items.

• $41,281 available for 10 Year Capital Development Plan.

• Issue HLS Bond to cover HLS costs and free up all of the $1,400,000 budgeted each year for 10 Year Capital Development Plan.

• HLS Bonds would increase our Bond and Interest Levy, but would allow for us to fully implement our 10 Year Capital Improvement Plan.

Page 9: 10 Year Capital Improvement Plan and HLS · 10 Year Capital Improvement Plan •Annually, the District has $1,400,000 to put towards capital improvement projects. The dollars come

140722 CapImpPlan2014

Location Capital Improvements Projects Project Costs 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24

HLS Yr 1 HLS Yr 2 HLS Yr 3 HLS Yr 4 HLS Yr 5

Scenario 1 HLS "A" Items Paid from HLS Fund Balance $419,124 $419,124

HLS "B" Items Paid from HLS Fund; 20 Fund; 61

Fund $2,889,870 $722,468 $722,468 $722,468 $722,466

Location Capital Improvements Projects Project Costs 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24

IPA Interior Remodeling (casework, paint, furniture, flooring, etc.) $666,500 $137,000 $68,500 $68,500 $68,500 $50,000 $68,500 $68,500 $68,500 $68,500

IPA Additional Keyless Door Access $35,000 $35,000

Mellon Additional Keyless Door Access $35,000 $35,000

Edison Additional Keyless Door Access $35,000 $35,000

Jefferson Additional Keyless Door Access $35,000 $35,000

Southside Additional Keyless Door Access $15,000 $15,000

Centennial Replace interior doors and hardware $510,000 $150,000 $60,000 $60,000 $60,000 $60,000 $60,000 $60,000

Centennial Replace A/C plant $570,000 $570,000

Centennial Replace all HVAC supply fans - 10 Year Lease Purchase $2,100,000 $350,000 $350,000 $350,000 $350,000 $350,000 $350,000

Central Replace hot water heater $26,000 $26,000

Central Replace fire alarm system $380,000 $380,000

Central Replace Boilers $250,000 $250,000

Central Window Replacement $1,750,000 $250,000 $250,000 $250,000 $250,000 $250,000 $250,000 $250,000

Central Exterior Concrete Replacement $50,000 $50,000

Columbia Interior Door and Hardware Replacement $0

District Other Capital Projects $311,500 $180,000 $131,500

Bottenfield Roof Restoration $350,000 $350,000

IPA Roof Restoration $350,000 $350,000

Garden Hills Roof Restoration $350,000 $350,000

Dr. Howard Roof Restoration $350,000 $350,000

Westview Roof Restoration $350,000 $350,000

Edison Roof Restoration $350,000 $350,000

Franklin Roof Restoration $350,000 $350,000

Jefferson Roof Restoration $350,000 $350,000

Centennial Roof Restoration $0

Central Roof Restoration $0

District Asphalt Replacement $600,000 $100,000 $100,000 $100,000 $100,000 $100,000 $100,000

IPA Fire Alarm Replacement $100,000 $100,000

Dr Howard Fire Alarm Replacement $100,000 $100,000

Southside Fire Alarm Replacement $100,000 $100,000

Edison Fire Alarm Replacement $200,000 $200,000

Franklin Fire Alarm Replacement $100,000 $100,000

Jefferson Fire Alarm Replacement $100,000 $100,000

Columbia Fire Alarm Replacement $100,000 $100,000

IPA Phones/Intercom Replacement $175,000 $175,000

Dr Howard Phones/Intercom Replacement $175,000 $175,000

Southside Phones/Intercom Replacement $175,000 $175,000

Stratton Phones/Intercom Replacement $175,000 $175,000

Edison Phones/Intercom Replacement $250,000 $250,000

Franklin Phones/Intercom Replacement $175,000 $175,000

Central Phones/Intercom Replacement $250,000 $250,000

CECC Update BAS System $60,000 $60,000

Stratton Update BAS System $60,000 $60,000

Barkstall Update BAS System $60,000 $60,000

IPA Update BAS System $60,000 $60,000

Dr Howard Update BAS System $60,000 $60,000

Southside Update BAS System $60,000 $60,000

Edison Update BAS System $60,000 $60,000

Central Update BAS System $60,000 $60,000

Columbia Update BAS System $0

Dr Howard Hot water heater replacement $3,000 $3,000

Dr Howard Return pump replacement $7,000 $7,000

Dr Howard Repair interior stairs $18,000 $18,000

Jefferson Phone Replacement $170,000 $170,000

South Side Replace package boiler $60,000 $60,000

Total Project Expense Over 10 Years 13,082,000.00$ 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24

Total Expense by Year $368,000 $709,500 $1,443,500 $1,313,500 $1,548,500 $1,585,000 $1,613,500 $1,573,500 $1,513,500 $1,413,500

61 FUND $ $350,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000

20 FUND $ $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000

Total Available $ $650,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000

Over/Under $ $282,000 $690,500 -$43,500 $86,500 -$148,500 -$185,000 -$213,500 -$173,500 -$113,500 -$13,500

Total Project

Expense Over 10 Yrs $13,082,000Total 61 Fund $

Over 10 Yrs $10,250,000Total 20 Fund $

Over 10 Yrs $3,000,000Total Available $

Over 10 Yrs $13,250,000

Page 10: 10 Year Capital Improvement Plan and HLS · 10 Year Capital Improvement Plan •Annually, the District has $1,400,000 to put towards capital improvement projects. The dollars come

Location Capital Improvements Projects Project Costs 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24

HLS Yr 1 HLS Yr 2 HLS Yr 3 HLS Yr 4 HLS Yr 5

Scenario 2 HLS "A" Items Paid from HLS Fund Balance $419,124 $419,124

HLS "B" Items Paid from HLS Fund; 20 Fund; 61 Fund $5,320,575 $1,358,719 $1,358,719 $1,358,719 $1,358,719

Location Capital Improvements Projects Project Costs 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24IPA Interior Remodeling (casework, paint, furniture, flooring, etc.) $666,500 $137,000 $68,500 $68,500 $68,500 $50,000 $68,500 $68,500 $68,500 $68,500

IPA Additional Keyless Door Access $35,000 $35,000

Mellon Additional Keyless Door Access $35,000 $35,000

Edison Additional Keyless Door Access $35,000 $35,000

Jefferson Additional Keyless Door Access $35,000 $35,000

Southside Additional Keyless Door Access $15,000 $15,000

Centennial Replace interior doors and hardware $510,000 $150,000 $60,000 $60,000 $60,000 $60,000 $60,000 $60,000

Centennial Replace A/C plant $570,000 $570,000

Centennial Replace all HVAC supply fans - 10 Year Lease Purchase $2,100,000 $350,000 $350,000 $350,000 $350,000 $350,000 $350,000

Central Replace hot water heater $26,000 $26,000

Central Replace fire alarm system $380,000 $380,000

Central Replace Boilers $250,000 $250,000

Central Window Replacement $1,750,000 $250,000 $250,000 $250,000 $250,000 $250,000 $250,000 $250,000

Central Exterior Concrete Replacement $50,000 $50,000

Columbia Interior Door and Hardware Replacement $0

District Other Capital Projects $311,500 $180,000 $131,500

Bottenfield Roof Restoration $350,000 $350,000

IPA Roof Restoration $350,000 $350,000

Garden Hills Roof Restoration $350,000 $350,000

Dr. Howard Roof Restoration $350,000 $350,000

Westview Roof Restoration $350,000 $350,000

Edison Roof Restoration $350,000 $350,000

Franklin Roof Restoration $350,000 $350,000

Jefferson Roof Restoration $350,000 $350,000

Centennial Roof Restoration $0

Central Roof Restoration $0

District Asphalt Replacement $600,000 $100,000 $100,000 $100,000 $100,000 $100,000 $100,000

IPA Fire Alarm Replacement $100,000 $100,000

Dr Howard Fire Alarm Replacement $100,000 $100,000

Southside Fire Alarm Replacement $100,000 $100,000

Edison Fire Alarm Replacement $200,000 $200,000

Franklin Fire Alarm Replacement $100,000 $100,000

Jefferson Fire Alarm Replacement $100,000 $100,000

Columbia Fire Alarm Replacement $100,000 $100,000

IPA Phones/Intercom Replacement $175,000 $175,000

Dr Howard Phones/Intercom Replacement $175,000 $175,000

Southside Phones/Intercom Replacement $175,000 $175,000

Stratton Phones/Intercom Replacement $175,000 $175,000

Edison Phones/Intercom Replacement $250,000 $250,000

Franklin Phones/Intercom Replacement $175,000 $175,000

Central Phones/Intercom Replacement $250,000 $250,000

CECC Update BAS System $60,000 $60,000

Stratton Update BAS System $60,000 $60,000

Barkstall Update BAS System $60,000 $60,000

IPA Update BAS System $60,000 $60,000

Dr Howard Update BAS System $60,000 $60,000

Southside Update BAS System $60,000 $60,000

Edison Update BAS System $60,000 $60,000

Central Update BAS System $60,000 $60,000

Columbia Update BAS System $0

Dr Howard Hot water heater replacement $3,000 $3,000

Dr Howard Return pump replacement $7,000 $7,000

Dr Howard Repair interior stairs $18,000 $18,000

Jefferson Phone Replacement $170,000 $170,000

South Side Replace package boiler $60,000 $60,000

Total Project Expense Over 10 Years 13,082,000.00$

2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24

Total Expense by Year$368,000 $709,500 $1,443,500 $1,313,500 $1,548,500 $1,585,000 $1,613,500 $1,573,500 $1,513,500 $1,413,500

61 FUND $ $350,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000

20 FUND $ $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000

Total Available $ $650,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000

Over/Under $ $282,000 $690,500 -$43,500 $86,500 -$148,500 -$185,000 -$213,500 -$173,500 -$113,500 -$13,500

Total Project

Expense Over

10 Yrs $13,082,000 NOTE: Remaining Excess amounts are carried over to the next year.

Total 61 Fund $

Over 10 Yrs $10,250,000Total 20 Fund $

Over 10 Yrs $3,000,000

Total Available

$ Over 10 Yrs $13,250,000

Excess $

Available Over

10 Yrs $168,000 WITHOUT HLS REQUIREMENTS