1 cs 501 spring 2005 cs 501: software engineering lecture 4 project management
Post on 21-Dec-2015
218 views
TRANSCRIPT
1 CS 501 Spring 2005
CS 501: Software Engineering
Lecture 4
Project Management
2 CS 501 Spring 2005
Administration
Projects
• Announcements by project teams
Quiz 1
• Quiz 1 is next Thursday. Information is posted on the web site.
3 CS 501 Spring 2005
OS 360
The operating system for the IBM 360 was two years late.
Question: How does a project get two years behind schedule?
Answer: One day at a time!
Fred Brooks Jr., The Mythical Man Month
4 CS 501 Spring 2005
The Aim of Project Management
To complete a project:
• On time
• On budget
• With required functionality
• To the satisfaction of the client
• Without exhausting the team
To provide visibility about the progress of a project
5 CS 501 Spring 2005
Aspects of Project Management
Planning
• Outline schedule during feasibility study
• Detailed schedule at the beginning of a project or phase of a project
Progress tracking
• REGULAR COMPARISON OF PROGRESS AGAINST PLAN
Final analysis
• Analysis of project for improvements during next project
6 CS 501 Spring 2005
Terminology
Deliverable
Work product that is provided to the customer (report, presentation, documentation, code, etc.)
Milestone
Completion of a specified set of activities (e.g., delivery of a deliverable)
7 CS 501 Spring 2005
Terminology
Activity
Part of a project that takes place over time (also known as a task).
Event
The end of a group of activities.
Dependency
An activity that cannot begin until some event is reached
Resource
Staff time, equipment, or other limited resources required by an activity.
8 CS 501 Spring 2005
General Approach to Project Planning
Identify deliverables and milestones
Divide project into activities (tasks)
For each task estimate:
• time to complete from when activity begins
• dependencies on events before beginning
• resource requirements
Build a model that uses this data to create a work-plan, including schedule, resource allocation, and flexibility
9 CS 501 Spring 2005
Project Planning Methods
Critical Path Method, Gantt charts, Activity bar charts, etc.
• Build a work-plan from activity data.
• Display work-plan in graphical form.
Project planning software (e.g., Microsoft Project)
• Maintain a database of activity data with input tools
• Calculate and display schedules
• Provide progress reports
10 CS 501 Spring 2005
Project Planning Methods
All project planning methods are best when:
1. Plan is updated regularly (e.g., weekly or monthly)
2. The structure of the project is well understood
3. The time estimates are reliable
4. Activities do not share resources
Unfortunately, #2, #3, #4 rarely apply to software development
11 CS 501 Spring 2005
A Simple Gantt Chart
Source: Microsoft using Excel
12 CS 501 Spring 2005
A More Complex Gantt Chart
Source: SmartDraw
13 CS 501 Spring 2005
Gantt Charts
• Dates run along the top (days, weeks or months).
• Each row represents an activity. Activities may be scheduled sequentially, in parallel or overlapping.
• The scheduled for an activity is a horizontal bar. The left end marks the planned beginning of the task. The right end marks the expected end date.
• The chart may be updated by filling in each activity to a length proportional to the work accomplished.
• Progress to date can be compared with the plan by drawing a vertical line through the chart at the current date.
14 CS 501 Spring 2005
Activity Graph
An activity
A dummy activity
An event
A milestone
A scheduling technique that emphasizes dependencies
15 CS 501 Spring 2005
Example: Activity GraphAn Open University Course
Deliverables:
16 Written texts (bound in pairs)
8 Television programs
8 Radio programs
4 Computer programs
1 Home experimental kit
4 Assignments and sample solutions
16 CS 501 Spring 2005
Activity Graph (part)
Edit Unit 3
PrintUnit 3
Revise Unit 3
MailUnit 3
otheractivities
START END
17 CS 501 Spring 2005
Activity Graph (continued)
Edit Unit 3
TypesetUnit 3
Revise Unit 3
MailUnits 3/4
otheractivities
Edit Unit 4
PrintUnits 3/4
Revise Unit 4
otheractivities
TypesetUnit 4
START
18 CS 501 Spring 2005
Activity Graph (continued)
START
Edit Unit 3
ScriptTV 2
MakeTV 2
Edit Unit 4
Prototype Computer 1
ProgramComputer 1
DocumentComputer 1
19 CS 501 Spring 2005
Scheduling: Background
PERT
Program Evaluation and Review Technique introduced by the U.S. Navy in 1957 to support the development of its Polaris submarine missile program.
PERT/Time
Activity graph with three time estimates (shortest, most probable, longest) on each activity to compute schedules.
PERT/Cost
Added scheduling of resources (e.g., facilities, skilled people, etc.)
20 CS 501 Spring 2005
Critical Path Method
Uses Activity Graph with single time estimate for each activity to estimate:
earliest start date -- every activity begins at first possible time
latest start date -- every activity begins at the last possible time
slack -- difference between the latest and earliest start dates
A standard method for managing large construction projects.
On big projects, activity graphs with more than 10,000 activities are common.
21 CS 501 Spring 2005
Time Estimates for Activities (Weeks)
6
4
2
2
3
3
3
3
82
1 1
4
12
12
1
4
22 CS 501 Spring 2005
Earliest Start Dates
6
4
2
2
3
3
3
3
82
11
4
12
12
1
4
0
1
12
12
4
17
19
23
5
2522
17
17
15
15
8
2023 24
All activities beginning at a given event have the same earliest start date.
23 CS 501 Spring 2005
Latest Start Dates
6
4
2
2
3
3
3
3
82
11
4
12
12
1
11
12
14
13
15
20
23 24 25
4 22
0
17
17
10
1817
2019
Each event must be achieved by the date shown or the final date will not be met.
24 CS 501 Spring 2005
Critical Path
0/0
1/11
12/12
12/14
4/13
15/15 17/17
17/17
17/17
19/20
22/23 23/24 25/25
Every activity on the critical path must begin on the earliest start date.
25 CS 501 Spring 2005
Slack
0/0
1/11
17/17
23/24
1
22
12/12
12/14
4/13
15/15 17/17
17/17 19/20
22/23 25/25
4
8
123 2
312
4
4
3
3
6
1 1
Slack of activity = (latest start)end - (earliest start)begin - (time estimate)
10 10
00 0
0
00
9
9
2
2
23
11
11
5
26 CS 501 Spring 2005
Estimating the Time for an Activity
With experienced staff, estimating the actual time to carry out a single task is usually fairly accurate, but ...
The little bits and pieces are underestimated
• The time from almost "done" to completely "done" is much longer than anticipated. (There's just one thing to tidy up. I need to put the comments into better shape. I really should get rid of that patch.)
• The distractions are not planned for. (My system crashed and I decided to upgrade the software. My child's school was closed because of snow. I spent the day showing visitors around.)
Some things have to be done twice.
27 CS 501 Spring 2005
Start-up Time
On a big project, the start-up time is typically three to six months:
• Personnel have to complete previous projects (fatigue) or be recruited.
• Hardware and software has to be acquired and installed.
• Staff have to learn new domain areas and software (slow while learning).
• Clients may not be ready.
28 CS 501 Spring 2005
Final Analysis with Critical Path Method
Administrative computing department at Dartmouth used the Critical Path Method for implementation phase of major projects (plan developed after project was well-understood).
Experience: Elapsed time to complete projects was consistently 30% to 40% longer than predicted by model.
Analysis:
• Some tasks not anticipated (incomplete understanding)• Some tasks had to be redone (change of requirements, technical changes)• Key personnel on many activities (schedule conflicts)• System ZZZ (non-billable hours)
29 CS 501 Spring 2005
Adding Resources to Activity Graph or Gantt Chart
Each activity is labeled with resources, e.g.,
Number of people (e.g., 2 Java programmers)
Key personnel (e.g., chief system architect)
Equipment (e.g., 3 servers with specified software)
Facilities (e.g., video conference center)
Each resource is labeled with availability, e.g.,
Hiring and training
Vacations
Equipment availability
30 CS 501 Spring 2005
Using Critical Path Method for Resources
Assume every activity begins at earliest start date:
In each time period, calculate:
resources required
resources available
Identify shortage / surplus resources
Adjust schedule
acquire extra staff (e.g., consultants)
rearrange schedule (e.g., change vacations)
change order of carrying out activities
The earlier that a problem is known, the easier it is to fix.
31 CS 501 Spring 2005
Key Personnel: The Mythical Man Month
In computing, not all people are equal
• The best are at least 5 times more productive.• Some tasks are too difficult for everybody.
Adding more people adds communications complexity
• Some activities need a single mind.• Sometimes, the elapsed time for an activity can not be
shortened.
What happens to the project if a key person is sick or quits?
32 CS 501 Spring 2005
Open University Example:Flexibility
Schedule: Dates for broadcasting TV and radio programs are fixed. Printing and mailings can be accelerated if overtime is used.
Functionality: The course team can decide what goes into the components of the course.
Resources: The size of the course team can be increased slightly.
33 CS 501 Spring 2005
Value of Scheduling Tools
Planning discipline
• Identify all activities and inter-relationship
• Provide schedule for each resource (identify clashes)
• Early warning of difficulties (e.g., timing of equipment purchase)
Routine updating of schedule
• Focus on key milestones
• Visibility for management
Weekly staff meeting -- What did we expect to accomplish? What did we accomplish? What is expected for next week?
34 CS 501 Spring 2005
The Project Manager
• Create and maintain the schedule.• Track progress against schedule.• Keep some slack in the schedule (minimize risk).• Continually make adjustments:
Start activities before previous activity completeSub-contract activitiesRenegotiate deliverables
• Keep senior management informed (visibility).
35 CS 501 Spring 2005
Updating the Plan
A PROJECT PLAN IS USELESS IS IT IS NOT UPDATED:
• Whenever changes occur
• On a regular schedule (weekly or monthly)
The project manager needs the support of the head of the development team and the confidence of the team members.
A realistic, current project plan is an essential part of visibility.
*