05 rehabilitation works
TRANSCRIPT
-
8/13/2019 05 Rehabilitation Works
1/45
5 ROAD REHABILITATION WORKS
5.1 Introduction
5.2 Using Labour Only
5.3 Using Labour Plus Intermediate Equipment
5.4 Using Mainly Equipment
5.5 Spot Improvement
5.6 Small Structure Works
5.7 Reconstruction of Gravel Shoulders on BitumenRoads
5.8 Quality Control
5 2
5 3
5 13
5 23
5 33
5 41
5 41
5 - 44
5R
OADREHABI
LITATIONWO
RKS
-
8/13/2019 05 Rehabilitation Works
2/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 2
5 ROAD REHABILITATION WORKS
5.1 INTRODUCTION
Under Roads 2000 strategy the existing classified road network needs to be first partially
rehabilitated before maintenance can be effectively established. Spot improvement activities
are carried out after the initial rehabilitation works have been carried out. Depending on
certain circumstances, there are three rehabilitation methods that can be applied:
Using Labour Only:
This approach is appropriate for roads with a low traffic level and where sufficient local
labour is available.
The first labour gang establishes the centre line, sets out the road formation and reserve
width, and clears the road reserve area of bush and grass.
The second labour gang excavates the side drains and forms the camber. Compaction
may be achieved by traffic or pedestrian rollers.
The third labour gang opens mitre drains, cross water drains and places/replaces culvert
lines.
See details of this method in Section 5.2 (pages 5-3 to 5-12)
Using Equipment and Labour:
This approach is appropriate for roads with a higher traffic level and where sufficient local
labour is available.
The first labour gang establishes the centre line, sets out the road formation and reserve
width, and clears the road reserve area of bush and grass.
The second gang consists of motor or towed grader(s) and forms the camber. The grader
DOES NOT cut drains. Compaction is achieved using towed or self-propelled rollers.
The third labour gang opens all drains, cross water drains and places/replaces culvert
lines.
See details of this method in Section 5.3 (pages 5-13 to 5-22)
Using Mainly Equipment:
This approach is appropriate for roads where there is insufficient labour available, e.g.
semi arid and arid areas.
The first working gang establishes the centre line, sets out the road formation and reserve
width, and clears the road reserve area of bush and grass. Most of the clearing work is
done using equipment, such as dozer and grader, and supported by labour for minor
works.
The second gang consists of motor or towed grader(s) to excavate/clean the side and
mitre drains and to form the camber.
The last gang, mainly labour, deals with other drainage works. This includes scour-check
installation, cleaning of culverts and repair or installation of new culverts.
See details of this method in Section 5.4 (pages 5-23 to 5-32)
-
8/13/2019 05 Rehabilitation Works
3/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 3
5.2 USING LABOUR ONLY
In order to achieve satisfactory workmanship and simplify supervision, the road rehabilitation
process is broken down into a series of simple activities. They are carried out by separate
groups of labourers, in a sequence. In this way a train of activities moves along the roadimproving the carriageway and drainage in a controlled step-by-step manner.
The work is subdivided into three main operations, each carried out by a separate labour
gang that follow each other in sequence:
SETTING OUT + CLEARING
1st labour gang
CAMBER FORMATION
2nd Labour Gang
DRAINAGE WORK
3rd labour gang
Gang 1angGang 2ang 2Gang 3ang 3
The activities necessary for the labour only partial rehabilitation approach should be selected
from the following schedule and carried out in the sequence shown:
SEQUENCE OF PARTIAL REHABILITATION ACTIVITIES FOR EARTH AND GRAVEL ROADS
USING LABOUR ONLY
Operation Activity For Details Refer to:
Site Support Work Site Camp Installation
Site Camp Security
Water Supply
Setting Out and Measuring Aids
Tools and Tool Repair / Maintenance
Equipment
Stores Control
Equipment Control and Maintenance
Employment of Casual Labour
Sections 3, 4, 13 and
15
Setting Out Setting out Horizontal Alignment Setting out Horizontal Curves Sections 3 and 4
Clearing Bush Clearing Stripping and Grubbing
Tree and Stump Removal
Boulder Removal
Job Sheet: PR(L)03
(usually not required
for R2000 rehab.)Vertical Alignment Establishment of Levels (Slotting) Job Sheet: PR(L)04
Side Drains / Formation Ditch Excavation and sloping
Camber Formation
Job Sheet: PR(L)05
Compaction Carriageway Compaction Job Sheet: PR(L)06
Other Drainage Mitre Drains
Scour Checks
Job Sheets: PR(L)07
and PR(L)08
Culvert Rehabilitation Culvert Cleaning Culvert Replacement or New
Installation
Job Sheet: PR(L)09
-
8/13/2019 05 Rehabilitation Works
4/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 4
MINISTRY OF PUBLIC WORKS
& HOUSING
Roads 2000
JOB SHEETPARTIAL REHABILITATION
(LABOUR ONLY)
Activity: BUSH CLEARING+ STRIPPING AND GRUBBING
Code: PR(L) 03
Standard: (See Contract Specifications)
Work Method:
1. Set out pegs for bush clearing, and stripping and grubbing at 10m intervals. Use the centre pegs
as reference. Use the edge pegs as chainage pegs and mark them accordingly. Do not remove
these pegs after bush clearing has been completed.
2. Tie strings along the bush clearing reference pegs.
3. Estimate the area to be cleared.
4.
Allocate tasks to the labourers. Give individual tasks for bush clearing, and stripping andgrubbing.
!2m !2m
grass cutting and grubbing
bushclearing
bushclearing
CL
A/B/C Main + Secondary Roads = 12.4 mD/E Minor Roads = 11.8 mRAR Roads = 10.5 mReduced Section RAR/Minor Roads = 9.5m
edge pegs = chainage pegs
Manpower:
1 Headman
2 Labourers for setting out
Labour Gang for BushClearing
Labour Gang for Stripping and
Grubbing
Tools + Equipment:
Tape Measure, 30 m
1 Masons Hammer
Wooden Pegs + Strings Pangas
Grass Slashers
Axes
Rakes
Jembes
Shovels
Material:
Quality Control:
Check the cleared width and ensure that the area is free of trees, bushes, shrubs, grass and roots.Productivity: Bush Clearing = 300 - 1000 m2 / day / labourer
Stripping and Grubbing = 200 - 300 m2/ day / labourer Intech 1.94/05
-
8/13/2019 05 Rehabilitation Works
5/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 5
MINISTRY OF ROADS &
PUBLIC WORKS
Roads 2000
JOB SHEETPARTIAL REHABILITATION
(LABOUR ONLY)
Activity: VERTICAL ALIGNMENT Code: PR(L) 04Standard: (See Contract Specifications)
Work Method:A. SET-OUT SLOTS:
1. At every 10 metre station set out in plan a slot 0.5 metres wide and length from back to back of
ditch (standard lengths see figure below) using pegs and strings.
2. Set a peg immediately on either side of the centre line peg and at right angles to the centre line
(across the road). The two pegs should be fixed approx. 20 cm above the existing road level. The
tops of the pegs should be on the same level (check with a spirit level).
CL
20
back ofditch
back ofditch
spirit level
sisal twine to setout slot 50cmwide
setting out slots = from back of ditch to back of ditch
A/B/C Main + Secondary Roads = 9.6 mD/E Minor Roads = 9.0 mRAR Roads = 7.3 mReduced Section RAR/Minor Roads = 5.5 m
B. CHECK VERTICAL ALIGNMENT:
3. Set out the vertical alignment of the road adjusting the twin pegs at each slot position as
necessary using the boning rods. The difference in alignment between any 3 consecutive slots
(20 metres) should not be more than 10 cm.
10m
10m
max.10cm
Slots
CL
-
8/13/2019 05 Rehabilitation Works
6/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 6
Work Method (Cont.):C. EXCAVATE / FILL SLOTS:
4. Fix the length of the adjustable-camber-slope-ditch-template (ACSDT) according to the relevant
cross-section (use the dimension back of ditch to back of ditch and divide by 2 to get the correctmeasurement = see diagram below). Place the ACSDT on the twin pegs to get an idea of the
extent and amount of excavation required to allow the template to si t level.
5. Cut and fill within the limits of the slot area, checking with the template and spirit level from time
to time. Material may be used on either side of the centreline. If there is insufficient material to
support the template throughout in the level position then lower the twin pegs a few cm.
Conversely if there is surplus material raise the pegs a little. Include any back sloping material in
the slot. Compact the filled material using hand rammers.
CL
back ofditch
back ofditch
spirit level
CUT
FILL
adjusted length of ACSDT
D/E Minor Roads = 4.5 mRAR Roads = 3.65mReduced RAR/Minor Roads = 2.75m
A/B/C Main + Secondary Roads = 4.8 m
6. Recheck the vertical alignment and make any adjustments necessary to the pegs. Exchange
material between adjacent slots to accommodate this adjustment in template level. The slot
profile is now that of the finished compacted road camber.
7. Mark the ditch and slope positions with pegs to the correct level using the templates, and fix
string lines, which enable the excavation quantities to be calculated and tasks to be set.
Manpower: 1 Site Supervisor (to set the
levels and check the
alignment)
1 trained Headman
3 Labourers
Tools + Equipment: Tape Measure, 30 m
1 Template (ACSDT)
1 Set Boning Rods
1 Spirit Level
1 Mason Hammer
Wooden Pegs
Strings
2 Jembes
2 Shovels
1 Pick Axe
1 Hand Rammer
Material:
Quality Control:
Check that the vertical difference from slot to slot is less than 10cm (measure over three slots)Productivity: 10 to 20 slots / day / gang
(if more slots are required then a second gang needs to be engaged)Intech 1.94/05
-
8/13/2019 05 Rehabilitation Works
7/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 7
MINISTRY OF ROADS &
PUBLIC WORKS
Roads 2000
JOB SHEETPARTIAL
REHABILITATION(LABOUR ONLY)
Activity: SIDE DRAINS AND FORMATION Code: PR(L) 05Standard: (See Contract Specifications)
Work Method:
1.Calculate earthworks between slots and allocate task rates.
2.Set out pegs and strings for slopes and ditches.
3.Excavate and fill according to the established slots. Provide enough fill to allow for compaction.
4.Check ditch and slope with a wooden template.
5.Check formation with a straight edge and the ACSDT- Template and correct where necessary.
6.After compaction fill any depressions and compact again.
CL
pegs and strings to setout ditch, slope and ifnecessary backslope
check finished formationwith the ACSD-Templateand a spirit level
check levels of ditch, slope edgeand crown with boning rods, useslots as reference points
Manpower: 1 to 2 Headpersons
Labour gangs according to
task rates
Tools + Equipment:
1 Mason Hammer
Wooden Pegs and Strings
ACSD-Template, Spirit Level
Ditch-Slope Template
Straight Edge Pick Axes or Mattocks
Rakes or Spreaders
Jembes or Forked Jembes
Shovels
Wheelbarrows
Material:
Quality Control:
Check with standard ditch/slope or ACSD template the size of the ditch and camber
Ditch to be able to drain (normally minimum 2% gradient, in flat section minimum 1%9
Ditch bottom to be of uniform gradient. Use boning rods to check.Productivity: 3 - 4 m3/ day / labourer
Intech 1.94/05
-
8/13/2019 05 Rehabilitation Works
8/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 8
MINISTRY OF ROADS &
PUBLIC WORKS
Roads 2000
JOB SHEETPARTIAL
REHABILITATION(LABOUR ONLY)
Activity: COMPACTION Code: PR(L) 06Standard: (See Contract Specifications)
Work Method:
1. Mark the exact length and width of the carriageway to be compacted after the camber has been
formed.
2. Establish the number of passes (depending on the thickness of the layer, the chosen type of
compaction device and the natural moisture content).
3. Compact if possible on the same day as the camber was formed. Arrange for the gang to work
in the afternoon if necessary.
4. Check with the straight edge where depressions on the running surface appear.
5. Fill depressions on the same day and repeat compaction on these spots (material to be
borrowed from the back slope or if necessary widen the ditch).
6. Where compaction cannot be achieved on the same day, make sure it is organised as early as
possible on the next day.
Compact layers of not more than allowed thickness Depending on the equipment 4 to 12 passes are required at each point of the carriageway Passes should overlap each other Start rolling from the edge and work towards the centre-line, then repeat on the other side
overlap ofpasses
LC
Manpower: Site Supervisor to control
passes and check quality Plant Operator
1 to 2 Labourers to assist
(cleaning roller cylinder, filling
depressions, etc.)
Tools + Equipment:
Compaction Equipment Water Bowser
Straight edge, Camber Board
Jembes, Shovels, Rakes
Material:
Water for Compaction
Quality Control:
Count passes and ensure uniform rolling as indicated above (this does not replace compaction
tests). Ensure rolling only at optimum moisture content.
Productivity:
depending on equipment used. Check Section 3.4, Equipment Intech 1.94/05
-
8/13/2019 05 Rehabilitation Works
9/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 9
MINISTRY OF ROADS &
PUBLIC WORKS
Roads 2000
JOB SHEETPARTIAL
REHABILITATION(LABOUR ONLY)
Activity: MITRE DRAINS Code: PR(L) 07Standard: (See Contract Specifications)
Work Method:
1. Set out mitre drains at minimum 20 metre intervals where possible.
2. Set out mitre drains with an angle of 30-60 to the side drain and with the same width as the
side drain, but minimum 60 cm.
3. Make sure the mitre drain is leading to an open outlet, preferably between shamba
boundaries.
4. Establish gradient of mitre drain = same gradient as ditch but not less than 3%. Use boning
rods to transfer ditch gradient and line-level to establish a new gradient.
5. Excavate the ditch and make sure the gradient is uniform. The sides should be backsloped.
Dump material on the lower side of the drain.6. Provide a block in the ditch on the downhill side of the mitre drain.
roadcentreline
sidedrain
mitredrain
side drain blockedwith material frommitre drain
angle30to60
backslope
sidedrain
1 : 1 1 : 160cm
CROSS SECTION MITRE DRAIN
Manpower: 1 Headperson to set out andcontrol mitre drains
Labour gang
Tools + Equipment: Strings and pegs
Tape measure
Set of boning rods,
3 ranging rods and line level
Jembes, mattocks, shovels
Material:
Quality Control:
- Check size cross-section of drain at regular intervals
- Check gradient of mitre drain (not less than ditch)
- Check that block at mitre-drain entrance is properly filled and compacted
Productivity:
3 to 4 m3
/ day / labourer Intech 1.94/05
-
8/13/2019 05 Rehabilitation Works
10/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 10
MINISTRY OF ROADS &
PUBLIC WORKS
Roads 2000
JOB SHEETPARTIAL
REHABILITATION(LABOUR ONLY)
Activity: SCOUR CHECKS (using wooden pegs) Code: PR(L) 08aStandard: (See Contract Specifications)
Work Method:
1. Identify road sections where ditch gradient is more than 4% using a line-level = construct scour
checks.
2. Identify exact ditch gradient and space scour checks according to gradient (see drawing).
3. Cut pegs (min 50 cm long) and prepare stones for apron
4. Construct scour check with the correct profile. Use the scour check template for control.
5. Construct stone apron below scour check of min 40cm length. Dig stones into the ground.
spirit level
1st peg
template flushwith slope edge
place 1st peg at theedge of the ditch
hammer the peginto the grounduntil the spirit levelon the templateledge is horizontal
1st peg
build scour checkflush to thetemplate
provide 1 or 2 edgepegs at the outerside of the ditch
construct an apronof stones belowthe scour check ofapprox. 40cmlength
edge pegs
flush with template
Scour CheckSpacing
not required20 m10 m5 m
Gradient of Road
4% or less5%8%10%
Manpower:
1 labour gang
Tools + Equipment: Template + Spirit level
Sledge Hammer
Mason Hammer
Panga and Shovel
Material: Pegs of min. 40cm length
for scour check
Stones for apron
Quality Control:
Check spacing of the scour checks using tape measure. Maximum tolerance of + / - 0.5m.
Confirm sizes of the stakes/pegs.
Check the shape of the scour check using the scour check template.Productivity: 3 - 4 No / day / labourer (including preparation of pegs and collection of stones)
Intech 1.94/05
-
8/13/2019 05 Rehabilitation Works
11/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 11
MINISTRY OF ROADS &
PUBLIC WORKS
Roads 2000
JOB SHEETPARTIAL
REHABILITATION(LABOUR ONLY)
Activity: SCOUR CHECKS (using stones) Code: PR(L) 08bStandard: (See Contract Specifications)
Work Method:
1. Identify road sections where ditch gradient is more than 4% using a line-level = construct
scour checks.
2. Identify exact ditch gradient and space scour checks according to gradient (see drawing).
3. Select and prepare stones (cut to shape if necessary, length minimum 35cm)
4. Construct scour check with the correct profile. Use the scour check template for control.
5. Construct stone apron below scour check of min 40cm length. Dig stones into the ground.
spirit level
1st stone
template flushwith slope edge
place 1st stone at theedge of the ditch
bury the stone intothe ground until thespirit level on thetemplate ledge ishorizontal
build scour checkflush to the template
provide 1 or 2 edgestones at the outerside of the ditch
construct an apron ofstones below the scourcheck of approx. 40cmlength
edge stone
Spacing
Gradient4% or less
5%6%7%
Spacingnot req.
20m15m10m
Gradient8%9%10%
> 10%
Spacing7.5m6m5m4m
1st stoneflush withtemplate
Manpower:
1 labour gang
Tools + Equipment: Template + Spirit level
Sledge and Mason Hammer
ShovelWheelbarrow
Material: Stones of min. 35cm length
for scour check
Stones for apron
Quality Control:
Check spacing of the scour checks using tape measure. Maximum tolerance of + / - 0.5m.
Confirm sizes of the stones. Check the shape of the scour check using the scour check template.Productivity: 3- 4 No / day / labourer (including collection of stones)
Intech 1.94/05
-
8/13/2019 05 Rehabilitation Works
12/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 12
MINISTRY OF ROADS &
PUBLIC WORKS
Roads 2000
JOB SHEETPARTIAL
REHABILITATION(LABOUR ONLY)
Activity: CULVERT CLEANING Code: PR(L) 09Standard:
Clean culverts of specified size including pipe barrels, the outlet/inlet structures, and the outlet
drains, keeping them free of all debris, weed, silt and any obstruction to ensure free passage of
water at all times.
Deposit debris in approved spoil dumps directed by the Engineer.
Maintain correct widths and slopes of the outlet drains. The gradient of the outlet to be checked to
ensure it is greater than 2 % using boning rods and line and level.
All broken culvert barrels to be reported to the Engineer.Work Method:
1. Check culvert inlets, barrel and outlets for silt, sand and debris (use torch to check barrel).
2. Remove material from the inlet, barrel and outlet, and dispose of material well clear of thedrainage system preferably on the lower side of the road or as instructed by the Engineer.
3. Check outlet gradient and ensure a minimum gradient of 2% using line-level and boning rod set.
Ensure that the drain bottom has a uniform gradient. Set out outlet width and length using pegs
and strings.
4. When the culvert is cleaned out check for cracks in the barrels (use torch if necessary). In case ofdamages report to the Engineer.
CL
culvert blocked withsilt and debris
repair inlet and outlet aprons includinghead and wingwalls if necessary
clean silt and debris fromoutlet, culvert and inlet
maintain same gradient asthe culvert
excavate outlet with aminimum width of 60cm
gradient2to5%
use long handled shovelor trowel for cleaning
Special Considerations:
If the culvert is severely blocked use long handled tools, like shovel and rode (iron bar 10 to
12mm, 12m long) or scoop with a bucket tied to a rope.
Tools and Equipment: Tape Measure, 30 m
Set of boning rods
Shovel, Jembe, Pick Axe, Panga
Long handled shovel + trowel
Material:
Pegs
Strings
Safety Signs and Devices
Safety Vest
Quality Control:
Visual inspection to check that the culvert, inlet and outlet are cleaned out and maintained to the
correct standard dimensions.
Check longitudinal profile of outlet using boning rods and string and line-level.
Suggested Productivity Range: Cleaning = 1/4 to 4 culvert lines / day / labourer(depending on
blockage level and length of culvert) Intech 05
-
8/13/2019 05 Rehabilitation Works
13/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 13
5.3 USING LABOUR AND INTERMEDIATE EQUIPMENT
The activities for this method are carried out by separate groups of labourers and/or
equipment, in a sequence. In this way a train of activities moves along the road improving
the carriageway and drainage in a controlled step-by-step manner.
The work is subdivided into three main operations, each carried out by a separate work gang
that follow each other in sequence:
SETTING OUT + CLEARING
1st labour gang
SHOULDER & CARRIAGEWAY
GRADING
equipment grading gang
DRAINAGE WORK
2nd labour gang
Gang 1angGang 2ang 2Gang 3ang 3
For grading either tractor towed heavy graders or motor graders can be used. The 5-tonne
towed grader has to be pulled by a 100HP tractor to be able to manage rehabilitation
grading. Compaction is achieved with either a towed dead weight or a self propelled roller.
The activities necessary for the labour and equipment partial rehabilitation approach should
be selected from the following schedule and carried out in the sequence shown:
SEQUENCE OF PARTIAL REHABILITATION ACTIVITIES FOR EARTH AND GRAVEL ROADS
USING LABOUR AND EQUIPMENT
Operation Activity For Details Refer to:
Site Support Work Site Camp Installation
Site Camp Security
Water Supply
Setting Out and Measuring Aids
Tools and Tool Repair / Maintenance
Equipment selection, control and maint.
Stores Control
Employment of Casual Labour
Sections 3, 4, 13 and
15
Setting Out Setting out Horizontal Alignment Setting out Horizontal Curves
Sections 3 and 4
Clearing Bush Clearing Stripping and Grubbing
Tree and Stump Removal
Boulder Removal
Job Sheet: PR(E+L)03
(usually not required
for R2000 rehab.)
Shoulder Grading Ditch and Slope Grading Job Sheet: PR(E+L)04
Camber Formation Camber Grading Job Sheet: PR(E+L)05
Compaction Carriageway Compaction Job Sheet: PR(E+L)06
Side Drains Ditch Excavation Job Sheet: PR(E+L)07Other Drainage Mitre Drains
Scour Checks
Job Sheets:
PR(E+L)08 and 09
Culvert Rehabilitation Culvert Cleaning Culvert Replacement or New Installation
Job Sheet: PR(E+L)10
-
8/13/2019 05 Rehabilitation Works
14/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 14
MINISTRY OF PUBLIC WORKS
& HOUSING
Roads 2000
JOB SHEETPART. REHAB.
(EQUIPMENT ANDLABOUR)
Activity: BUSH CLEARING+ STRIPPING AND GRUBBING
Code: PR(E+L) 03
Standard: (See Contract Specifications)
Work Method:
1. Set out pegs for bush clearing, and stripping and grubbing at 10m intervals. Use the centre
pegs as reference. Use the edge pegs as chainage pegs and mark them accordingly. Do not
remove these pegs after bush clearing has been completed.
2. Tie strings along the bush clearing reference pegs.
3. Estimate the area to be cleared.
4. Allocate tasks to the labourers. Give individual tasks for bush clearing, and stripping and
grubbing.
!2m !2m
grass cutting and grubbing
bushclearing
bushclearing
CL
A/B/C Main + Secondary Roads = 12.4 mD/E Minor Roads = 11.8 mRAR Roads = 10.5 mReduced Section RAR/Minor Roads = 9.5m
edge pegs = chainage pegs
Manpower:
1 Headman
2 Labourers for setting out
Labour Gang for Bush
Clearing Labour Gang for Stripping and
Grubbing
Tools + Equipment:
Tape Measure, 30 m
1 Masons Hammer
Wooden Pegs + Strings
Pangas Grass Slashers
Axes
Rakes
Jembes
Shovels
Material:
Quality Control:
Check the cleared width and ensure that the area is free of trees, bushes, shrubs, grass and roots.Productivity: Bush Clearing = 300 - 1000 m2 / day / labourer
Stripping and Grubbing = 200 - 300 m2/ day / labourerIntech 1.94/05
-
8/13/2019 05 Rehabilitation Works
15/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 15
MINISTRY OF ROADS &
PUBLIC WORKS
Roads 2000
JOB SHEETPART. REHAB.
(EQUIPMENT ANDLABOUR)
Activity: SHOULDER GRADINGCode: PR(E+L) 04
Standard: (See Contract Specifications)
Work Method:1. Set out the guide pegs for the towed grader to follow in 20 metre intervals along straight
sections and 10 metre intervals in curves. Measure the relevant width from the centre line as
shown in the table below.
CL
outer side ditch peg
centre peg
A/B/C Main + Secondary Roads = 5.40 mD/E Minor Roads = 5.10 mRAR Roads = 4.05mReduced RAR/Minor Roads = 3.55m
centre line to back of ditch
chainage peg chainage peg
centre line to back of ditch
2. Cut a V ditch with the grader in 1 or 4 passes and grade the shoulder. The edge of the grader
blade follows the established line of outer ditch pegs. Check the crossfall from time to time withthe AC or ACSDT -Template so that the amount of material required to form the camber can be
estimated.
3. 2 to 3 labourers accompany the grader to remove large stones, roots and to support manually
wherever necessary.
CL
V-ditch along line of pegs
grader blade
Manpower:
1 Site Supervisor
1 to 2 Grader Operators
1 Headperson + 1 labourer for
setting out
2 to 3 labourers per grader to
support
Tools + Equipment:
2 heavy towed graders + 100
HP tractors or motor grader
Tape Measure, 30 m
1 Mason Hammer
Wooden Pegs
AC- or ACSDT -Template with
Spirit Level
Material:
Quality Control: Check camber at regular intervals using AC or ACSDT templateProductivity: Together with activity Camber Formation approximately 1km / day / towed graderor 1.5 to 2km per motor grader, depending on the existing condition.
Intech 8.94/05
-
8/13/2019 05 Rehabilitation Works
16/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 16
MINISTRY OF ROADS AND
PUBLIC WORKS
Roads 2000
JOB SHEETPART. REHAB.(EQUIPMENT AND
LABOUR)
Activity: CAMBER FORMATION Code:PR(E+L) 05Standard: (See Contract Specifications)
Work Method:1. Grade carriageway from edge towards centre, then from centre towards edge, with 4 to 6
passes to obtain the correct crossfall.
2. Check the achieved crossfall with the AC or ACSDT-Template and correct where necessary.
Additional material can be added if necessary by labour during the follow up drainage works.
Also check the uniformity of the fill with a straight edge.
3. Assign 2 to 3 labourers to accompany the grader to remove large stones, roots and to support
manually wherever necessary.
CL
CL
7-10%
AC or ACSDT-Template Straight Edge
Manpower: 1 Site Supervisor
1 to 2 Grader Operator
2 to 3 labourers per grader to
support
Tools + Equipment:
2 heavy towed graders + 100
HP tractors
AC or ACSDT-Template with
Spirit Level
Straight Edge
Material:
Quality Control: Check camber at regular intervals using AC or ACSDT templateProductivity: Together with activity Shoulder Grading approximately 1km / day / towed grader
Intech 8.94/05
-
8/13/2019 05 Rehabilitation Works
17/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 17
MINISTRY OF ROADS &
PUBLIC WORKS
Roads 2000
JOB SHEETPART. REHAB.
(EQUIPMENT ANDLABOUR)
Activity: COMPACTION Code: PR(E+L) 06Standard: (See Contract Specifications)
Work Method:
1. Mark the exact length and width of the carriageway to be compacted after the camber has been
formed.
2. Establish the number of passes (depending on the thickness of the layer, the chosen type of
compaction device and the natural moisture content).
3. Compact if possible on the same day as the camber was formed. Arrange for the gang to work
in the afternoon if necessary.
4. Check with the straight edge where depressions on the running surface appear.
5. Fill depressions on the same day and repeat compaction on these spots (material to be
borrowed from the back slope or if necessary widen the ditch).
6. Where compaction cannot be achieved on the same day, make sure it is organised as early as
possible on the next day.
Compact layers of not more than allowed thickness Depending on the equipment 4 to 12 passes are required at each point of the carriageway Passes should overlap each other Start rolling from the edge and work towards the centre-line, then repeat on the other side
overlap ofpasses
LC
Manpower: Site Supervisor to controlpasses and check quality Plant Operator
1 to 2 Labourers to assist
(cleaning roller cylinder, filling
depressions, etc.)
Tools + Equipment:
Compaction Equipment Water Bowser
Straight edge, Camber Board
Jembes, Shovels, Rakes
Material:
Water for Compaction
Quality Control:
Count passes and ensure uniform rolling as indicated above (this does not replace compaction
tests).
Ensure rolling only at optimum moisture content.
Productivity: depending on equipment used. Check Section 3.4, EquipmentIntech 1.94/05
-
8/13/2019 05 Rehabilitation Works
18/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 18
MINISTRY OF ROADS &
PUBLIC WORKS
Roads 2000
JOB SHEETPART. REHAB.
(EQUIPMENT ANDLABOUR)
Activity: SIDE DRAINSCode:PR(E+L) 07
Standard: (See Contract Specifications)
Work Method:1. Establish inner and outer ditch lines using pegs and strings. Set pegs at 10m intervals. Use
centre pegs or chainage pegs as reference points.
2. Excavate ditch slots every 5 to 10m. Use template to check size and shape. Slots can be used
to calculate the volume of excavation and to issue task rates.
3. Excavate/ widen the ditch according to the slots (the ditch becomes rectangular). Use material
to raise camber or to fill depressions on the carriageway if required. Otherwise cast material
well clear of the ditch, so that it will not wash back.
4. Check finished ditch using the ditch template and if necessary correct.
CLditch template
pegs in 10m intervalsalong inner ditch line
slots every 5 to10 metres
A/B/C Main + Secondary Roads = 4.2 mD/E Minor Roads = 3.9 mRAR Roads = 3.25mReduced RAR/Minor Roads = 2.75m
centre line to front of ditch
Manpower:
1 Site Supervisor and one
trained Headman
Labour Gang
Tools + Equipment:
3 Ranging Rods
Tape Measure, 30 m
1 Mason Hammer
Wooden Pegs and Strings Ditch or ACSDT-Template +
Spirit Level
Straight Edge
Jembes and Shovels
Mattocks
Rakes or Spreaders
Material:
Quality Control:
Check every slot using template and spirit level. Check drain after reconstruction again.
Productivity: 20 to 50 metres / day / labourer (or equivalent to 3 to 4 m3)Intech 8.94705
-
8/13/2019 05 Rehabilitation Works
19/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 19
MINISTRY OF ROADS &
PUBLIC WORKS
Roads 2000
JOB SHEETPARTIAL
REHABILITATION(LABOUR ONLY)
Activity: MITRE DRAINS Code: PR(E+L) 08Standard: (See Contract Specifications)
Work Method:
1. Set out mitre drains at minimum 20 metre intervals where possible.
2. Set out mitre drains with an angle of 30-60 to the side drain and with the same width as the side
drain, but minimum 60 cm.
3. Make sure the mitre drain is leading to an open outlet, preferably between shamba boundaries.
4. Establish gradient of mitre drain = same gradient as ditch but not less than 3%. Use boning rods
to transfer ditch gradient and line-level to establish a new gradient.
5. Excavate the ditch and make sure the gradient is uniform. The sides should be backsloped.
Dump material on the lower side of the drain.
6. Provide a block in the ditch on the downhill side of the mitre drain.
roadcentreline
sidedrain
mitredrain
side drain blockedwith material frommitre drain
angle30to60
backslope
sidedrain
1 : 1 1 : 160cm
CROSS SECTION MITRE DRAIN Manpower: 1 Headperson to set out andcontrol mitre drains
Labour gang
Tools + Equipment:
Strings and pegs Tape measure
Set of boning rods,
3 ranging rods and line level
Jembes, mattocks, shovels
Material:
Quality Control:
- Check size cross-section of drain at regular intervals
- Check gradient of mitre drain (not less than ditch)
- Check that block at mitre-drain entrance is properly filled and compacted
Productivity: 3 to 4 m3/ day / labourerIntech 1.94/05
-
8/13/2019 05 Rehabilitation Works
20/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 20
MINISTRY OF ROADS &
PUBLIC WORKS
Roads 2000
JOB SHEETPART. REHAB.
(EQUIPMENT ANDLABOUR)
Activity: SCOUR CHECKS (using wooden pegs) Code: PR(E+L) 09aStandard: (See Contract Specifications)
Work Method:
1. Identify road sections where ditch gradient is more than 4% using a line-level = construct scour
checks.
2. Identify exact ditch gradient and space scour checks according to gradient (see drawing).
3. Cut pegs (min 50 cm long) and prepare stones for apron
4. Construct scour check with the correct profile. Use the scour check template for control.
5. Construct stone apron below scour check of min 40cm length. Dig stones into the ground.
spirit level
1st peg
template flushwith slope edge
place 1st peg at theedge of the ditch
hammer the peginto the grounduntil the spirit levelon the templateledge is horizontal
1st peg
build scour checkflush to thetemplate
provide 1 or 2 edgepegs at the outerside of the ditch
construct an apronof stones belowthe scour check ofapprox. 40cmlength
edge pegs
flush with template
Scour CheckSpacing
not required20 m10 m5 m
Gradient of Road
4% or less5%8%10%
Manpower:
1 labour gang
Tools + Equipment: Template + Spirit level
Sledge Hammer
Mason Hammer
Panga and Shovel
Material: Pegs of min. 40cm length
for scour check
Stones for apron
Quality Control:
Check spacing of the scour checks using tape measure. Maximum tolerance of + / - 0.5m.
Confirm sizes of the stakes/pegs.
Check the shape of the scour check using the scour check template.Productivity: 3 - 4 No / day / labourer (including preparation of pegs and collection of stones)
Intech 1.94/05
-
8/13/2019 05 Rehabilitation Works
21/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 21
MINISTRY OF ROADS &
PUBLIC WORKS
Roads 2000
JOB SHEETPART. REHAB.
(EQUIPMENT AND LABOUR)
Activity: SCOUR CHECKS (using stones) Code: PR(E+L) 09bStandard: (See Contract Specifications)
Work Method:
1. Identify road sections where ditch gradient is more than 4% using a line-level = construct scour
checks.
2. Identify exact ditch gradient and space scour checks according to gradient (see drawing).
3. Select and prepare stones (cut to shape if necessary, length minimum 35cm)
4. Construct scour check with the correct profile. Use the scour check template for control.
5. Construct stone apron below scour check of min 40cm length. Dig stones into the ground.
spirit level
1st stone
template flushwith slope edge
place 1st stone at theedge of the ditch
bury the stone intothe ground until thespirit level on thetemplate ledge ishorizontal
build scour checkflush to the template
provide 1 or 2 edgestones at the outerside of the ditch
construct an apron ofstones below the scourcheck of approx. 40cmlength
edge stone
Spacing
Gradient4% or less
5%6%
7%
Spacingnot req.
20m15m
10m
Gradient8%9%10%
> 10%
Spacing7.5m6m5m
4m
1st stoneflush withtemplate
Manpower:
1 labour gang
Tools + Equipment: Template + Spirit level
Sledge and Mason Hammer
Shovel
Wheelbarrow
Material: Stones of min. 35cm length
for scour check
Stones for apron
Quality Control:
Check spacing of the scour checks using tape measure. Maximum tolerance of + / - 0.5m.
Confirm sizes of the stones. Check the shape of the scour check using the scour check template.Productivity:
3- 4 No / day / labourer (including collection of stones) Intech 1.94/05
-
8/13/2019 05 Rehabilitation Works
22/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 22
MINISTRY OF ROADS &
PUBLIC WORKS
Roads 2000
JOB SHEETPART. REHAB.
(EQUIPMENT ANDLABOUR)
Activity: CULVERT CLEANING Code: PR(E+L) 10Standard:
Clean culverts of specified size including pipe barrels, the outlet/inlet structures, and the outlet
drains, keeping them free of all debris, weed, silt and any obstruction to ensure free passage of
water at all times.
Deposit debris in approved spoil dumps directed by the Engineer.
Maintain correct widths and slopes of the outlet drains. The gradient of the outlet to be checked to
ensure it is greater than 2 % using boning rods and line and level.
All broken culvert barrels to be reported to the Engineer.Work Method:
1. Check culvert inlets, barrel and outlets for silt, sand and debris (use torch to check barrel).
2. Remove material from the inlet, barrel and outlet, and dispose of material well clear of thedrainage system preferably on the lower side of the road or as instructed by the Engineer.
3. Check outlet gradient and ensure a minimum gradient of 20% using line-level and boning rod set.
Ensure that the drain bottom has a uniform gradient. Set out outlet width and length using pegs
and strings.
4. When the culvert is cleaned out check for cracks in the barrels (use torch if necessary). In case ofdamages report to the Engineer.
CL
culvert blocked withsilt and debris
repair inlet and outlet aprons includinghead and wingwalls if necessary
clean silt and debris fromoutlet, culvert and inlet
maintain same gradient asthe culvert
excavate outlet with aminimum width of 60cm
gradient2to5%
use long handled shovelor trowel for cleaning
Special Considerations:
If the culvert is severely blocked use long handled tools, like shovel and rode (iron bar 10 to
12mm, 12m long) or scoop with a bucket tied to a rope.
Tools and Equipment: Tape Measure, 30 m
Set of boning rods
Shovel, Jembe, Pick Axe, Panga
Long handled shovel + trowel
Material:
Pegs
Strings
Safety Signs and Devices
Safety Vest
Quality Control:
Visual inspection to check that the culvert, inlet and outlet are cleaned out and maintained to the
correct standard dimensions.
Check longitudinal profile of outlet using boning rods and string and line-level.
Suggested Productivity Range: Cleaning = 1/4 to 4 culvert lines / day / labourer(depending on
blockage level and length of culvert) Intech 05
-
8/13/2019 05 Rehabilitation Works
23/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 23
5.4 USING MAINLY EQUIPMENT
The activities for this method are carried out mainly using equipment. Some labour input is
required for those activities that cannot be carried out by equipment, such as scour check
construction, culvert repair or installation, support work, etc. The work process is broken
down into a series of simple activities. The work is subdivided into three main operations,each carried out by a separate work gang that follow each other in sequence:
SETTING OUT + CLEARING equipment with labour
support
DITCH AND CAMBER GRADING grader and compactor with
labour support
OTHER DRAINAGE WORKS labour
Gang 1angGang 2ang 2Gang 3ang 3
For grading either tractor towed heavy graders or self-propelled motor graders can be used.
The 5 tonne towed grader will have to be pulled by a 100 HP tractor to be able to manage
rehabilitation grading. Compaction is achieved with either a towed dead weight roller or a self
propelled roller.
The activities necessary for the equipment partial rehabilitation approach should be selectedfrom the following schedule and carried out in the sequence shown:
SEQUENCE OF PARTIAL REHABILITATION ACTIVITIES FOR EARTH AND GRAVEL ROADS
USING LABOUR AND EQUIPMENT
Operation Activity For Details Refer to:
Site Support Work Site Camp Installation
Site Camp Security
Water Supply
Setting Out and Measuring Aids
Tools and Tool Repair / Maintenance
Equipment selection, control and maint.
Stores Control
Employment of Casual Labour
Sections 3, 4, 13 and
15
Setting Out Setting out Horizontal Alignment
Setting out Horizontal Curves
Sections 3 and 4
Clearing Bush Clearing Stripping and Grubbing
Tree and Stump Removal
Boulder Removal
Job Sheet: PR(E)03
(usually not required
for R2000 rehab.)
Rehabilitation Grading
(heavy grading)
Cleaning / Excavating Side Drains
Cleaning / Excavating Mitre Drains
Reforming The Camber
Job Sheets: PR(E)04
and PR(E)05
Compaction Carriageway Compaction Job Sheet: PR(E)06
Other Drainage Works Scour Checks
Relief Drainage Structures Culvert Cleaning
Culvert Replacement or New Installation
Job Sheets: PR(E)09
and PR(E)10
-
8/13/2019 05 Rehabilitation Works
24/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 24
MINISTRY OF ROADS &
PUBLIC WORKS
Roads 2000
JOB SHEETPARTIAL
REHABILITATION
(EQUIPMENT)
Activity: BUSH CLEARING+ STRIPPING AND GRUBBING Code: PR(E+L) 03
Standard: (See Contract Specifications)
Work Method:
1. Set out pegs for bush clearing, and stripping and grubbing at 10m intervals. Use the centre pegs
as reference. Use the edge pegs as chainage pegs and mark them accordingly. Do not remove
these pegs after bush clearing has been completed.
2. Tie strings along the bush clearing reference pegs.
3. Estimate the area to be cleared.
4. Allocate tasks to the labourers. Give individual tasks for bush clearing, and stripping and
grubbing.
!2m !2m
grass cutting and grubbing
bushclearing
bushclearing
CL
A/B/C Main + Secondary Roads = 12.4 mD/E Minor Roads = 11.8 mRAR Roads = 10.5 mReduced Section RAR/Minor Roads = 9.5m
edge pegs = chainage pegs
Manpower:
1 Headman
2 Labourers for setting out
Labour Gang for BushClearing
Labour Gang for Stripping and
Grubbing
Tools + Equipment:
Tape Measure, 30 m
1 Masons Hammer
Wooden Pegs + Strings Pangas
Grass Slashers
Axes
Rakes
Jembes
Shovels
Material:
Quality Control:
Check the cleared width and ensure that the area is free of trees, bushes, shrubs, grass and roots.Productivity: Bush Clearing = 300 - 1000 m2 / day / labourer
Stripping and Grubbing = 200 - 300 m2/ day / labourer Intech 1.94/05
-
8/13/2019 05 Rehabilitation Works
25/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 25
MINISTRY OF ROADS &
PUBLIC WORKS
Roads 2000
JOB SHEETPARTIAL
REHABILITATION(EQUIPMENT)
Activity: CLEANING/EXCAVATING SIDE AND
MITRE DRAINS
Code: PR(E) 04
Standard: (See Contract Specifications)
Work Method:1. Set out the guide pegs for the towed or motor grader to follow in 20 metre intervals along straight
sections and 10 metre intervals in curves. Measure the relevant width from the centre line as
shown in the table below.
2. Define where mitre drains have to be excavated, mark with pegs and discuss/agree with
landowners.
CL
outer side ditch peg
centre peg
A/B/C Main + Secondary Roads = 5.40 mD/E Minor Roads = 5.10 mRAR Roads = 4.05mReduced RAR/Minor Roads = 3.55m
centre line to back of ditch
chainage peg chainage peg
centre line to back of ditch
3. Drain away any standing water from carriageway and drains.
4. Cut a V ditch with the grader in 1 or 4 passes and grade the drain and shoulder.
(See detailed operation on back of Job Sheet).
5. Cut V-shape mitre drains at the pre-defined locations.
6. 2 to 3 labourers accompany the grader to remove large stones, roots and to support manually
wherever necessary.
Manpower:
1 Site Supervisor 1 to 2 Grader Operators
1 Headperson + 1 labourer for
setting out
2 to 3 labourers per grader to
support
Tools + Equipment:
2 heavy towed graders + 100HP tractors or self-propelled
grader
Tape Measure, 30 m
1 Mason Hammer
Wooden Pegs
AC- or ACSDT -Template with
Spirit Level
Material:
Quality Control: Check drain gradient using boning rods. Ensure uniform profile of V ditch.Productivity: Together with activity Camber Formation approximately 1km / day / towed graderor 1.5 to 2km per self-propelled grader, depending on the existing condition.
Intech 8.94/05
-
8/13/2019 05 Rehabilitation Works
26/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 26
Narrow flat-bottomed ditches are not well suited tomaintenance by grader. These should be cleaned outby hand.
Graders should be used to maintain V-shaped ditchesand wide flat-bottomed ditches.
If unsuitable, material from the ditch should not normallybe graded onto the running surface. In certaincircumstances the engineer may instruct the recovery
and mixing of ditch material, where the running surfacelacks suitable fines present in the ditch
The first grading passcleans the side slope near theroad and windrows the material to the bottom of theditch.
The second grading passcleans the ditch back slopeand removes the material to the top of the ditch.
If possible, a third grading passis used to push thematerial away from the edge of the ditch, to prevent itwashing back.
Mitre Drainscan also be constructed with a grader.They lead the water away from the edge of the road andfollow closely the natural contours of the ground.
Mitre Drains should be spaced more closely as gradients
become steeper. The discharge of water should be littleand often to minimise erosion in the drains andadjoining land.
-
8/13/2019 05 Rehabilitation Works
27/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 27
MINISTRY OF ROADS AND
PUBLIC WORKS
Roads 2000
JOB SHEETPARTIAL
REHABILITATION
(EQUIPMENT)
Activity: CAMBER FORMATIONCode:
PR(E) 05
Standard: (See Contract Specifications)
Work Method:1. Grade carriageway from edge towards centre, then from centre towards edge, with 4 to 6
passes to obtain the correct crossfall.
2. Check the achieved crossfall with the AC or ACSDT-Template and correct where necessary.
Additional material can be added if necessary by labour during the follow up drainage works.
Also check the uniformity of the fill with a straight edge.
3. Assign 2 to 3 labourers to accompany the grader to remove large stones, roots and to support
manually wherever necessary.
CL
CL
7-10%
AC or ACSDT-Template Straight Edge
Manpower: 1 Site Supervisor
1 to 2 Grader Operator
2 to 3 labourers per grader to
support
Tools + Equipment:
2 heavy towed graders + 100
HP tractors
AC or ACSDT-Template with
Spirit Level
Straight Edge
Material:
Quality Control:
Check camber at regular intervals using AC or ACSDT templateProductivity: Together with activity Shoulder Grading approximately 1km / day / towed grader
Intech 8.94/05
-
8/13/2019 05 Rehabilitation Works
28/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 28
Heavy Grading to Restore the Camber:
CL
CL
C
C
Heavy grading requires additional passes to achieve the required camber. Workshould be completed on one side of the road at a time. Start grading from roadshoulder and work your way towards the centre line.
An even number of passes should be used to avoid a flat finished crown (centre ofroad).
Normally initial cutting passes are required to bring the material in from the edgesof the road towards the centre.
Spreading passes are required to redistribute the material away from the crowntowards the shoulder.
Source: PIARC, International Road Maintenance Handbook
-
8/13/2019 05 Rehabilitation Works
29/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 29
MINISTRY OF PUBLIC
WORKS & HOUSING
Roads 2000
JOB SHEETPARTIAL REHABILITATION
(EQUIPMENT)
Activity: COMPACTION Code:PR(E) 06Standard: (See Contract Specifications)
Work Method:
1. Mark the exact length and width of the carriageway to be compacted after the camber has been
formed.
2. Establish the number of passes (depending on the thickness of the layer, the chosen type of
compaction device and the natural moisture content).
3. Compact if possible on the same day as the camber was formed. Arrange for the gang to work
in the afternoon if necessary.
4. Check with the straight edge where depressions on the running surface appear.
5. Fill depressions on the same day and repeat compaction on these spots (material to be
borrowed from the back slope or if necessary widen the ditch).
6. Where compaction cannot be achieved on the same day, make sure it is organised as early aspossible on the next day.
Compact layers of not more than allowed thickness Depending on the equipment 4 to 12 passes are required at each point of the carriageway Passes should overlap each other Start rolling from the edge and work towards the centre-line, then repeat on the other side
overlap ofpasses
LC
Manpower: Site Supervisor to control
passes and check quality Plant Operator
1 to 2 Labourers to assist
(cleaning roller cylinder, filling
depressions, etc.)
Tools + Equipment:
Compaction Equipment
Water Bowser Straight edge, Camber Board
Jembes, Shovels, Rakes
Material: Water for Compaction
Quality Control: Count passes and ensure uniform rolling as indicated above (this does not replace compaction
tests).
Ensure rolling only at optimum moisture content.
Productivity: depending on equipment used. Check Section 3.4, Equipment Intech 1.94/05
-
8/13/2019 05 Rehabilitation Works
30/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 30
MINISTRY OF ROADS &
PUBLIC WORKS
Roads 2000
JOB SHEETPARTIAL REHABILITATION
(EQUIPMENT)
Activity: SCOUR CHECKS (using wooden pegs) Code: PR(E) 09aStandard: (See Contract Specifications)
Work Method:
1. Identify road sections where ditch gradient is more than 4% using a line-level = construct scour
checks.
2. Identify exact ditch gradient and space scour checks according to gradient (see drawing).
3. Cut pegs (min 50 cm long) and prepare stones for apron
4. Construct scour check with the correct profile. Use the scour check template for control.
5. Construct stone apron below scour check of min 40cm length. Dig stones into the ground.
spirit level
1st peg
template flushwith slope edge
place 1st peg at theedge of the ditch
hammer the peginto the grounduntil the spirit levelon the templateledge is horizontal
1st peg
build scour checkflush to thetemplate
provide 1 or 2 edgepegs at the outerside of the ditch
construct an apronof stones belowthe scour check ofapprox. 40cmlength
edge pegs
flush with template
Scour CheckSpacing
not required20 m10 m5 m
Gradient of Road
4% or less5%8%10%
Manpower:
1 labour gang
Tools + Equipment: Template + Spirit level
Sledge Hammer
Mason Hammer
Panga and Shovel
Material: Pegs of min. 40cm length for scour
check
Stones for apron
Quality Control:
Check spacing of the scour checks using tape measure. Maximum tolerance of + / - 0.5m.
Confirm sizes of the stakes/pegs.
Check the shape of the scour check using the scour check template.Productivity: 3 - 4 No / day / labourer (including preparation of pegs and collection of stones)
Intech 1.94/05
-
8/13/2019 05 Rehabilitation Works
31/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 31
MINISTRY OF ROADS &
PUBLIC WORKS
Roads 2000
JOB SHEETPARTIAL REHABILITATION
(EQUIPMENT)
Activity: SCOUR CHECKS (using stones) Code: PR(E) 09bStandard: (See Contract Specifications)
Work Method:
1. Identify road sections where ditch gradient is more than 4% using a line-level = construct scour
checks.
2. Identify exact ditch gradient and space scour checks according to gradient (see drawing).
3. Select and prepare stones (cut to shape if necessary, length minimum 35cm)
4. Construct scour check with the correct profile. Use the scour check template for control.
5. Construct stone apron below scour check of min 40cm length. Dig stones into the ground.
spirit level
1st stone
template flush
with slope edge place 1st stone at theedge of the ditch
bury the stone intothe ground until thespirit level on thetemplate ledge ishorizontal
build scour checkflush to the template
provide 1 or 2 edgestones at the outerside of the ditch
construct an apron ofstones below the scourcheck of approx. 40cmlength
edge stone
Spacing
Gradient4% or less
5%
6%7%
Spacingnot req.
20m
15m10m
Gradient8%9%
10%> 10%
Spacing7.5m6m
5m4m
1st stoneflush withtemplate
Manpower:
1 labour gang
Tools + Equipment: Template + Spirit level
Sledge and Mason Hammer
Shovel
Wheelbarrow
Material: Stones of min. 35cm length
for scour check
Stones for apron
Quality Control:
Check spacing of the scour checks using tape measure. Maximum tolerance of + / - 0.5m.
Confirm sizes of the stones.
Check the shape of the scour check using the scour check template.Productivity: 3- 4 No / day / labourer (including collection of stones)
Intech 1.94/05
-
8/13/2019 05 Rehabilitation Works
32/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 32
MINISTRY OF ROADS &
PUBLIC WORKS
Roads 2000
JOB SHEETPARTIAL
REHABILITATION(EQUIPMENT)
Activity: CULVERT CLEANING Code: PR(E) 10Standard:
Clean culverts of specified size including pipe barrels, the outlet/inlet structures, and the outlet
drains, keeping them free of all debris, weed, silt and any obstruction to ensure free passage of
water at all times.
Deposit debris in approved spoil dumps directed by the Engineer.
Maintain correct widths and slopes of the outlet drains. The gradient of the outlet to be checked to
ensure it is greater than 2 % using boning rods and line and level.
All broken culvert barrels to be reported to the Engineer.Work Method:
1. Check culvert inlets, barrel and outlets for silt, sand and debris (use torch to check barrel).
2. Remove material from the inlet, barrel and outlet, and dispose of material well clear of thedrainage system preferably on the lower side of the road or as instructed by the Engineer.
3. Check outlet gradient and ensure a minimum gradient of 20% using line-level and boning rod set.
Ensure that the drain bottom has a uniform gradient. Set out outlet width and length using pegs
and strings.
4. When the culvert is cleaned out check for cracks in the barrels (use torch if necessary). In case ofdamages report to the Engineer.
CL
culvert blocked withsilt and debris
repair inlet and outlet aprons includinghead and wingwalls if necessary
clean silt and debris fromoutlet, culvert and inlet
maintain same gradient asthe culvert
excavate outlet with aminimum width of 60cm
gradient2to5%
use long handled shovelor trowel for cleaning
Special Considerations:
If the culvert is severely blocked use long handled tools, like shovel and rode (iron bar 10 to12mm, 12m long) or scoop with a bucket tied to a rope.
Tools and Equipment: Tape Measure, 30 m
Set of boning rods
Shovel, Jembe, Pick Axe, Panga
Long handled shovel + trowel
Material:
Pegs
Strings
Safety Signs and Devices
Safety Vest
Quality Control:
Visual inspection to check that the culvert, inlet and outlet are cleaned out and maintained to the
correct standard dimensions.
Check longitudinal profile of outlet using boning rods and string and line-level.
Suggested Productivity Range: Cleaning = 1/4 to 4 culvert lines / day / labourer(depending onblockage level and length of culvert)
Intech 05
-
8/13/2019 05 Rehabilitation Works
33/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 33
5.5 SPOT IMPROVEMENT
Spot improvement operations can be very varied as the defect situations also vary greatly.
However, very common defects are short sections of roads that have been flooded or
structures that are damaged and impassable.
In terms of work implementation, spot improvement operations are technically andmanagerially challenging.
Wherever possible spot improvement work is carried out using principally labour-based
methods. Equipment will be mainly required for the haulage of material, such as gravel,
stones, chipping, etc., and for compaction.
The nature of spot improvement work changes from case to case and requires careful
planning and monitoring by the District Engineer or hired Consultant. The Contractor may be
confronted with a number of different possible operations as described in the following list:
5.5.1 Reconstruction of a Road Section
Roads are occasionally impassable due to short sections, which have completely failed. Inmost cases such sections have been swept away by floods or the effect of heavy rains and
the road section requires full reconstruction.
!The construction methods for Rural Access and Minor Roads are
described in detail in the Technical Manual, Volume I, Minor
Roads Programme.
A contractor carrying out full labour-based reconstruction of short road sections requires the
following main resources on site:
One or two fully trained and qualified Site Supervisors Number of competent (on-the-job trained) Headmen/women
Handtool set for approximately 50 to 80 labourers
Two to three tractors with trailers or two tipper trucks (exact number depends on hauling
distance)
One 3 to 5 tonne dead weight roller or two pedestrian vibrating rollers
One towed water bowser
One pick-up for supervision and transport of smaller items
Site camp facilities (stores, office, accommodation for staff)
5.5.2 Regravelling of a Road Section:
The main defect on the classified unpaved road network is the missing or insufficient gravel
layer. This are usually steep sections or sections with weak sub-grades, like black cotton soil.
The contract document specifies the detailed standards to be achieved for gravelling works
of a particular contract and road. If labour-based methods are used, the work execution is the
same as for the Rural Access and Minor Roads Programme.
!The labour-based gravelling methods for Rural Access and
Minor Roads are described in detail in the Technical Manual,
Volume I, Minor Roads Programme.
A contractor carrying out regravelling of short road sections using labour-based methods
requires the following main resources on site:
-
8/13/2019 05 Rehabilitation Works
34/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 34
One or two fully trained and qualified Site Supervisors
Number of competent (on-the-job trained) Headmen/women
Handtool set for approximately 50 labourers
Two to three tractors with trailers or two tipper trucks (exact number depends on hauling
distance) One 3 to 5 tonne dead weight roller or two pedestrian vibrating rollers
One towed water bowser
One pick-up for supervision and transport of smaller items
Site camp facilities (stores, office, accommodation for staff)
!If the road section is longer than 2km, additional hauling equipment is required.
In cases where the gravelling work is carried out using mainly equipment the following
resources are required:
One fully trained and qualified Site Supervisors
One or two competent (on-the-job trained) Headmen/women
Handtool set for approximately 10 labourers
One dozer and one front end loader for gravel excavation and loading
Three to four tractors with trailers or three to four tipper trucks (exact number depends on
hauling distance)
One 3 to 5 tonne dead weight roller or one self-propelled vibrating roller
One water bowser with spraying bar
One pick-up for supervision and transport of smaller items
Site camp facilities (stores, office, accommodation for staff)
!If the road section is longer than 2km, additional hauling equipment is required.
! Note: using equipment for short sections of regravelling mayonly be economical if local labour is not available.
5.5.3 Rehabilitation of a Single Barrel Culvert:
Non-functional culverts are a very common problem on existing roads and often need to
repaired or replaces
There are three basic culvert installation situations and they each require separate
arrangements depending on the outfall gradient:
A- Flat Outfall (10% approx.)
-
8/13/2019 05 Rehabilitation Works
35/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 35
Culvert Type A; Flat Outfall
This should be used in flat areas and watercourses with shallow gradients. In these
circumstances a culvert set tool low would simply silt up. A culvert set too high would
cause silting upstream and possibly erosion problems in the outfall.
The road has to be built up over the culvert using a ramp/embankment. The verticalalignment must be adjusted.
-
8/13/2019 05 Rehabilitation Works
36/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 36
Culvert Type B; Intermediate Outfall
This arrangement should be used when the outfall gradients are between 5% and 10%
approximately. The culvert may be excavated slightly into the existing ground and the
outfall ditch will be of reasonable length. However, the road will still require to be built upover the culvert barrel with gentle ramps of less than 5% extending at least 20 metres
either side of the culvert.
-
8/13/2019 05 Rehabilitation Works
37/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 37
Culvert Type C; Steep Outfall
On steep sidelong ground (above 10%) the culvert can be installed without adjusting the
vertical alignment of the road. The culvert barrel may be buried and adequate cover
achieved with an outfall ditch or reasonable length. A suitable drop pit will need to be
constructed at the culvert inlet. It should be large enough to allow later access formaintenance of the culvert barrel. At the outlet, particular attention should be given to
preventing erosion, particularly on steep slopes and easily erodible soils.
-
8/13/2019 05 Rehabilitation Works
38/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 38
Culvert Installation:
The exact site of the culvert should be determined at each low point in the vertical alignment
and at each location where a relief or crossover culvert is required. These locations have to
be determined by the Engineer and the Contractor to be instructed accordingly.
The next step is to determine the type of installation arrangement required: A, B or C, so thatthe culvert may be correctly set out. The following provides guidance on this procedure
taking a 5.40m wide road (carriageway width) as an example:
PROCEDURE FOR SETTING OUT 60 CM CULVERT
If the culvert site is flat check the watercourse gradient for 20 metres downstream form the
location of the culvert outlet. Use boning rods and Abney Level, or line level, for this
purpose. If the gradient is less than 5% (1m fall in 20m), then construct the culvert in
arrangement Type A with the culvert inverts as close to the existing ground/water course
level as possible, use guidelines of Figure G.1. Also construct arrangement Type A, if the
height of the embankment fill (measured to edge of running surface) at the culvert is atleast 1.1m. Otherwise proceed with the following steps to install arrangements Type B or
C.
-
8/13/2019 05 Rehabilitation Works
39/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 39
Culvert Bedding:
The culvert must be bedded on stable material. Firm clay or sandy material is suitable. We,
soft or organic material should be excavated and replaced with fine murram (gravel). Large
stones could damage the culvert rings under loading and must not be allowed in contact with
the rings. They should be removed, or covered with suitable material. If necessary murram
(gravel) containing stones up to 20mm, or concrete, may be used to bed the culvert rings.
The culvert bed should be excavated to give continuous support over the lower third of the
barrel. The shape of the bed should be controlled with a culvert template (see following
Figure). The gradient should be controlled using boning rods and the established excavation
pegs.
-
8/13/2019 05 Rehabilitation Works
40/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 40
PROCEDURE FOR CONSTRUCTION AND CONTROLLING CULVERT BED
Backfilling should be carried out in layers of about 15cm compacted with hand rammers.
Material must be particularly compacted against the culvert rings to avoid later settlement.
Care must be taken that stones larger than 20mm are not placed in contact with the rings.
The backfill cover requirements as detailed in the contract specifications (3/4 of barrel
diameter minimum) must be ensured.
Where the road has to be kept open to traffic, the culvert may be constructed in two halves.
Care must be taken to protect the culvert works, and the traffic both during and after working
hours. Suitable warning signs and barricades should be placed.
Required Resources:
A contractor carrying out culvert rehabilitation works requires the following main resources on
site:
One fully trained and qualified Site Supervisors
Handtool set for approximately 5 to 8 labourers
One tractor with trailer or one flat-bed/tipper truck (depends on hauling distance) for
transporting culvert rings or material to cast culverts on site.
One small concrete mixer for cases where culverts have to be haunched.
One pick-up for supervision and transport of smaller items
-
8/13/2019 05 Rehabilitation Works
41/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 41
5.6 SMALL STRUCTURE WORKS
Missing or defective structures are often the cause for impassable roads and are therefore
the critical spots in the road network. It is advisable to construct wherever possible multiple
culvert lines, drifts or simple structures instead of bridges. These have three main
advantages:- they are cheaper,
- they can be built using locally available resources, and
- they can be easier maintained.
A contractor carrying out structure works requires the following main resources on site:
One fully trained and qualified Site Supervisors
Handtool set for up to 20 labourers
Form work material for concrete structure elements
One tractor with trailer or one flat-bed/tipper truck (depends on hauling distance) for
transporting culvert rings or material to cast culverts on site.
One concrete mixer (size depending on the amount of concrete to be mixed) One concrete vibrator with one 40mm and one 60mm needle.
One pick-up for supervision and transport of smaller items
Site camp facilities (stores, office, accommodation for staff)
! For technical and operational information on concrete andmasonry works refer to Sections 7 and 8 of this Handbook.
5.7 RECONSTRUCTION OF GRAVEL SHOULDERS ON BITUMEN ROADS
Most shoulders along the bitumen roads of Kenya are unpaved. Gravel shoulders are subject
to constant wear and tear by vehicle and animal traffic and to softening and erosion by
surface water. Edge repair and shoulder regravelling are usually dealt with in one operation.
Where edge repair is not necessary and only shoulder regravelling needs to be carried out,
the work procedure is the same as detailed in method 1 of the work description presented
below:
Work Description (Method 1)
Define the depth of the shoulder erosion
and check whether the base or even the
sub-base is affected.ShoulderBase
Sub-base
Surfacing
SHOULDER TO STANDARD
If base and sub-base are not affected,
regravel the shoulder and then repair the
edge (see method 1).
SURFACE EDGE BROKEN ANDSHOULDER ERODED
-
8/13/2019 05 Rehabilitation Works
42/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 42
If the base and sub-base are affected, first
repair the entire shoulder including the base
and sub-base and then the road edge (see
method 2).SURFACE EDGE BROKEN, SHOULDERERODED, BASE AND SUB-BASEDEFECTIVE
Dig and remove all unstable material
(surface and shoulder) to the depth of the
base.
Brush out and clean the area.
Loosen the existing shoulder gravel to allow
a key for the added material.
Add new gravel in layers of not more than
10 cm to shoulder, add water if necessaryand compact with hand rammer or hand
roller.
Allow for some surplus material (level of
shoulder to be slightly higher than surface)
for later settlement.
Make sure the crossfall of the shoulder is
the same as for the carriageway.
Remove excess material for further use and
clear the section of debris.
Mark out the line along the road edge to be
cut. Cut a trench of about 8 cm width and 8
cm depth into the base. Make sure the sides
are vertical.
Brush out and clean the excavation area.
Apply a prime coat to the surface of the
excavated area. Make sure edges of patch
are well coated.
Place premix carefully in the edge trenchand rake the material to the correct level.
Compact the premix thoroughly. The
surface of the new edge should stand
approximately 5 mm above the existing road
surface after compaction.
The surface of the patch must be dusted or
sanded just before the final compaction
pass to prevent pick-up by vehicles.
After 3 days or more the patch must be
sealed by applying bitumen emulsion and a
single layer of 6 mm chippings. The
chippings must be well rolled.
-
8/13/2019 05 Rehabilitation Works
43/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 43
Work Description (Method 2)
Dig and remove all unstable material until
you find firm material. Level the area.
Brush out and clean the area.
Rebuilt the base and sub-base using the
same material. Compact thoroughly.
Rebuilt the shoulder as described in
method 1.
Repair the surface edge as described in
method 1.
Required Resources:
A contractor carrying out shoulder and bitumen edge rehabilitation works requires the
following main resources on site:
One fully trained and qualified Site Supervisors
Handtool set for 10 to 10 labourers. If labour is used for excavation, loading and spreading
of gravel up to 50 labourers require tools.
Two to three tractors with trailer or two to three tipper trucks (depending on hauling
distance) for transporting gravel for shoulder repair.
Dozer and Loader for gravel excavation and loading if equipment is used.
One grader for spreading shoulder gravel, if equipment is used. One bitumen emulsion hand sprayer
One pedestrian vibrating roller
One pick-up for supervision and transport of smaller items
For larger sites camp facilities (stores, office, accommodation for staff)
Depending on the existing surface and base composition, additional material will be required
to carry out the repair work. In most places the following material will be used:
lime (for stabilisation of base)
tack coat (for spaying the prime coat)
bituminous premix (for the edge repair)
bitumen emulsion (for patch seal) chippings, 6 mm (for patch seal)
-
8/13/2019 05 Rehabilitation Works
44/45
Improvement Works 5 ROAD REHABILITATION WORKS
5 - 44
5.8 QUALITY CONTROL
For Contractors it is advisable to maintain an own quality control system that ensures
constant checking through all working steps. It is in the interest of the Contractor to detect
any shortcomings as early as possible so that rectifications can be carried out at low cost.
The following tables provide practical quality control measures for the most important workitems for labour-based road works.
ROAD DIMENSION TESTS
(i) Type of tests:Simple checks on the dimensional accuracy of the construction works.
(ii) Methods used:Tapes and/or templates are used to measure the completed works.
Test Method Location Test Interval(every ..)
Tolerance
Width of carriage way sub-base terrace(excavation to level) tape field 100m +/- 50mm
Width and depth of side drains template field 10m +/- 20mm
ROAD PROFILE TESTS
(i) Type of tests:Checks on the camber and longitudinal profile of the carriageway.
(ii) Methods used:Camber boards, boning rods and/or levelling instrument are used to measure the completedbase and surface layer.
Test Method Location Test Interval(every ..)
Tolerance
Camber template field 20m +/- 10mm
Longitudinal profile boningrods
field 20m +/- 50mm
GRAVEL SOURCE TESTS (FOR BASE LAYER)
(i) Type of tests:Check on the suitability of a gravel source for surface layer. Unlike most other tests, the clientcan only carry out these tests in the laboratory before construction commences. However, ifyou are doubtful about the quality of the material you may use a simple field test to identify the
suitability of the chosen gravel. If the test described below shows doubtful results, then theclient should be consulted for further instructions.
(ii) Methods used:
- Bottle test to identify the grading.- Moulding and drying test to identify plasticity and strength
Test Method Location When? Tolerance
Grading bottle field when in doubtof quality
NA
Plasticity moulding field when in doubtof quality
NA
Strength drying field when in doubtof quality
NA
-
8/13/2019 05 Rehabilitation Works
45/45
Improvement Works 5 ROAD REHABILITATION WORKS
GRAVEL LAYER TESTS (FOR BASE OR SURFACE LAYER)
(i) Type of tests:Tests on the thickness and degree of compaction of the finished base layer.
(ii) Methods used:- Tapes are used to measure the gravel thickness.
- Special laboratory tests are used by the client to measure the degree of compaction. A simpleway of ensuring the compaction is achieved is by ensuring that the required minimum number ofcompaction passes, at optimum moisture content, are actually made. This method does not
provide the contractor with the actual result but ensures that the desired compaction is achievedin most cases.
Test Method Location Test Interval(every ..)
Tolerance
Thickness of gravel layer tape field 50 m (in centreand towards
edge)
+/- 10 mm
Degree of compaction countingcompaction
passes
field always 0
Field Density Test For Gravel Layers
To control whether the required compaction has been achieved density tests have to be
regularly taken during the construction period. This is part of the measurement procedure of
the client or his representative.
However, as a contractor you are also interested to find out yourself:
whether the density specified in the contract has been achieved before the clientmeasures, and
what the minimum compaction operation is to achieve this required density so that you do
not carry out more work and spend more money then what is actually required.
For large-scale contracts the contractors are required to establish a site laboratory whereboth the client and the contractor can carry out the tests. For small-scale contracts,
where mainly labour is used, such laboratories are usually not set up. However, tests canstill be carried out, for example by using the laboratory facilities of Road Departments or
Material Departments.
!Several methods are used for determining the achieved field
density. These are explained in Section 6 of this Hand Book.
Quality control checks for concrete works and mortar are
provided in Sections 7 and 8 respectively.