    FACTORIES AND MACHINERY

    ACT 1967 (FMA 1967)

    Chapter 3

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    2/48

    FKM, UTM 2

    Objective:

    Control of factories operationswithrespect to safety, health and welfare ofpersons

    Registration and inspectionof machinery

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    3/48

    FKM, UTM 3

    Application

    OSHA 1994 supersedes the FMA 1967 in theevent of any conflict

    FMA 1967 applies to mainly factories and

    construction sites FMA and OSHA enabling act (give power to

    minister to gazette detail regulations)

    Contains some general provision on safety,health and welfare

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    4/48

    FKM, UTM 4

    Application

    1. FMA - limited to manufacturing industry,mining and quarrying and construction

    2. do not contain detail provisions on specificmatters

    Detail provisions are stipulated under theregulations

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    5/48

    FKM, UTM 5

    Arrangement

    FMA 1967 divided into 6 parts:

    Part 1 Preliminary

    Part 2 Safety, health and welfare

    Part 3 Persons-in-charge and certificates ofcompetency

    Part 4 Notification of accidents, dangerous occurrence

    and dangerous diseases Part 5 Notice of occupation of factory and registration

    and use of machinery

    Part 6 General

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    6/48

    FKM, UTM 6

    Part 1: Preliminary

    Definition of a factory:

    a) There must be premises and its boundaries can bedefined;

    b) Within the premises there is manual labor doingprocess

    c) The process must involve the making, altering,repairing, ornamenting, finishing, cleaning, washing,breaking up demolition or adapting for sale any article;

    andPart I building operations, hoisting machine,machinery, steam

    d) The processes must be for trading.

    (Other definitions in boiler)

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    7/48

    FKM, UTM 7

    Part 2: Safety, Health andWelfare

    Key points:

    1. Premises must be structurally sound with safe accessto work areas, materials and goods must be safelystacked (Section 10)

    2. Machinery must be of sound construction anddangerous parts must be fenced (Section 14, 15, 16)

    3. Employees must not misuse safety and healthequipment (Section 20)

    4. Employees not to endanger himself or other person

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    8/48

    FKM, UTM 8

    Part 2: Safety, Health andWelfare

    Key points:

    5. Premises must be kept in clean state, withadequate work space, ventilation, lighting and

    toilets (Section 22)6. Persons must be supplied with adequate

    facilities for clothing, storage, drinking, water,first aid and washing facilities (Section 25)

    7. Employees must be trained on the safety ofmachinery (Section 26)

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    9/48

    FKM, UTM 9

    Part 3: Persons-in-charge andCertificates of Competency

    Key points:

    Machinery operators must be adequately

    trained or under the supervision of atrained person (Section 26);

    Young persons(< 16 years) must not

    operate machinery (Section 28)

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    10/48

    FKM, UTM 10

    Part 4: Notification of Accidents, DangerousOccurrence and Dangerous Diseases

    1. The occupier must notify the nearest inspectorof accidents and diseases. Accidents include:

    Loss of life;

    Injury to a person who loses more than 4 days work(loss time injury LTI);

    Serious damage to machinery or other property(Section 31).

    2. Inspectors may investigate accidents anddangerous occurrence and hold enquiries intomore serious cases (Section 33)

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    11/48

    FKM, UTM 11

    Part 5: Notice of Occupation of Factory

    and Registration and Use of Machinery

    1. Notify Department of Occupational Safety ad Health(DOSH) within 3 months of the intended start date(Section 34)

    2. Building operations must be notified if last more than 6weeks (Section 35)

    3. Changes to the use of factory or machinery must benotified to DOSH

    4. Fills a standard form together with (a) layout plan of thefactory; (b) list of products to be manufactured; (c) list ofmachines to be used; (d) list of chemicals, toxic orflammable substances to be used, and (e) detail flowchart of the processes.

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    12/48

    FKM, UTM 12

    Part 6: General

    1. General penalty RM2,000.00

    2. Certain sections is RM5,000.00 (Section

    51)

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    13/48

    FKM, UTM 13

    Schedules

    Schedule 1Defines dangerous occurrences to machinery

    that need to be notified

    Schedule 2Describes the types of injury that may be

    classified as serious bodily injury

    Schedule 3

    Lists notifiable industrial diseases

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    14/48

    FKM, UTM 14

    Regulations under the Act

    1. Factories and Machinery (Certificates ofCompetency Examinations) Regulations,1970

    2. Factories and Machinery (Electric Passengerand Goods Lift) Regulations, 1970

    3. Factories and Machinery (Fencing ofMachinery and Safety) Regulations, 1970

    4. Factories and Machinery (Notification ofFitness and Inspections) Regulations, 1970

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    15/48

    FKM, UTM 15

    Regulations under the Act

    5. Factories and Machinery (Person-In-Charge)Regulations, 1970

    6. Factories and Machinery (Safety, Health and

    Welfare) Regulations, 19707. Factories and Machinery (Steam Boiler and

    Unfired Pressure Vessel) Regulations, 1970

    8. Factories and Machinery (Administration)

    Regulations, 1970

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    16/48

    FKM, UTM 16

    Regulations under the Act

    9. Factories and Machinery (Compounding ofOffences) Rules, 1978

    10. Factories and Machinery (Compounding ofOffences) Regulations, 1978

    11. Factories and Machineries (Lead) Regulations,1984

    12. Factories and Machineries (Asbestos Process)

    Regulations, 1986

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    17/48

    FKM, UTM 17

    Regulations under the Act

    13. Factories and Machinery (Building Operationsand Works of Engineering Construction)(Safety) Regulations, 1986

    14. Factories and Machinery (Noise Exposure)Regulations,1989

    15. Factories and Machinery (Mineral Dust)Regulations, 1989

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    18/48

    Factories and Machinery(Certificates of Competency

    Examinations) Regulations, 1970

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    19/48

    FKM, UTM 19

    Factories and Machinery (Certificates ofCompetency Examinations) Regulations, 1970

    1. Set up the framework for the certificates of competencyrequired under Factories and Machinery (Persons-In-Charge) Regulations

    2. Laid down pre-requisite for the application for acertificate of competency and the examinationprocedure

    3. All certificates of competency have requirements forexperience and an examination pass before they can be

    granted

    4. Certificates of competency can be suspended orcancelled if the holder is medically unfit or in case ofserious misconduct or if judged unfit after an enquiry or

    a court case

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    20/48

    Factories and Machinery(Electric Passenger and Goods

    Lift) Regulations, 1970

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    21/48

    FKM, UTM 21

    Factories and Machinery (Electric Passengerand Goods Lift) Regulations, 1970

    1. All new lifting machines (cranes, crab, winch) andlifting appliances (pulley and chain blocks) have amanufacturers certificate specifying safe working loadwith design drawing and load calculations

    2. Apply to lifts used to carry persons and goods

    3. Owner to provide detail design to obtain approval fromDOSH (Regulation 6)

    4. Capacity of a lift is based on lift car floor area anddisplayed clearly on each lift car (Regulation 7)

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    22/48

    FKM, UTM 22

    Factories and Machinery (Electric Passengerand Goods Lift) Regulations, 1970

    5. Specifications for the following components ofa lift system:

    Machine room (Regulation 9)

    Lift well (Regulation 10)

    Landing doors (Regulation 12 and 13)

    Lift car (Regulation 14 to 19)

    Suspension system (Regulation 20 to 29)

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    23/48

    FKM, UTM 23

    Factories and Machinery (Electric Passengerand Goods Lift) Regulations, 1970

    6. Duties of lift owner to maintain the lift (3monthly inspections and monthly service bycompetent person)

    7. Enter details of all inspections andmaintenance activities in lift register(Regulation 31)

    8. Owner must display certificate of registrationin the lift car or at the bottom of the landing(Regulation 32)

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    24/48

    Factories and Machinery(Notification of Fitness and

    Inspections) Regulations, 1970

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    25/48

    FKM, UTM 25

    Factories and Machinery (Notification ofFitness and Inspections) Regulations, 1970

    Details of notification, certificate of fitnessand inspections carried out by DOSH

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    26/48

    FKM, UTM 26

    Part 1

    Specify the forms that must be used tonotify the DOSH officer of a newoccupancy of a factory, the start of

    building work, the installation of certainmachinery and the notification of accidentsand diseases

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    27/48

    FKM, UTM 27

    Part 2

    Describes the certificateof fitness thatmust be held for steam boilers, UPV andhoisting machines

    Certificateof fitness is valid for 15 monthsfrom the date of inspection (Regulation 10)

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    28/48

    FKM, UTM 28

    Part 3

    1. Governs the inspection of factory ormachinery by DOSH

    Factory and machinery inspected at regular

    intervals (15 months but up to 36 months atthe discretion of DOSH Regulation 14)

    DOSH give advance notice of the inspection

    to the occupier Occupier prepare machinery for inspection

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    29/48

    FKM, UTM 29

    Part 3

    2. DOSH may direct not complying factoryto improve the situation (Regulation 27)

    3. Stop work notice may be issued formachinery without a current certificate offitness (Regulation 28)

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    30/48

    FKM, UTM 30

    Part 4

    Inspection fees charged by DOSH

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    31/48

    Factories and Machinery(Fencing of Machinery andSafety) Regulations, 1970

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    32/48

    FKM, UTM 32

    Factories and Machinery (Fencing ofMachinery and Safety) Regulations, 1970

    1. Safeguarding of machinery

    2. All dangerous parts of machine includingthe power source and transmission mustbe guarded

    3. methods of guarding described forvarious parts of machine:

    Part 2: Prime mover (power source)

    Part 3: Transmission machinery

    Part 4: Driven machinery

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    33/48

    FKM, UTM 33

    Part 4 specifies the methods for

    guarding different types of machinery:

    1. Abrasive and grinding machinery

    2. Machinery using rolls

    3. Saws4. Planers

    5. Spindle moulders

    6. Grooving and tenoning machine

    7. Chain-mortice machine

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    34/48

    FKM, UTM 34

    Part 4 specifies the methods for

    guarding different types of machinery:

    8. Mixers

    9. Grinding mills

    10.Centrifuges

    11.Presses

    12.Guillotines13.Conveyors

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    35/48

    FKM, UTM 35

    Other machinesmust also be securely fenced

    Other form of guardings switches andinterlocks

    Workers trainedin the operation of certaindangerous machines and aware of the dangersof such machines

    Six schedules gives further specificationfor thematerials and dimensions of machine guards

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    36/48

    Factories and Machinery(Person-In-Charge)Regulations, 1970

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    37/48

    FKM, UTM 37

    Factories and Machinery (Person-In-Charge) Regulations, 1970

    1. Specify persons-in-charge of certainmachinery require certificate of competencyincluding:

    Steam boiler

    Steam engine

    Internal combustion engine

    Dredge

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    38/48

    FKM, UTM 38

    Factories and Machinery (Person-In-Charge) Regulations, 1970

    2. Steam boiler include UPV (pressure v/l) withsteam connected to it

    3. Steam boiler and steam engine require steam

    boiler drivers certificate of competency or asteam engine drivers certificate of competencyfor smaller boilers (

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    39/48

    FKM, UTM 39

    Factories and Machinery (Person-In-Charge)Regulations, 1970

    5. IC engines < 100 hp need a holder of IC engine driverscertificate

    6. Larger IC engine need a holder of an IC engineengineers certificate in charge

    7. Dredge operated by steam or IC engine must have aperson who holds an engineers (steam) certificate ofcompetency or an engineers (IC engine) certificate ofcompetency or dredgemasters certificate ofcompetency (Regulation 7)

    8. Requirement to provide instruction and training tooperators of certain machinery

    Each operator must have a course of instruction and 10 days ofsupervision by an experienced operator (Regulation 20)

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    40/48

    FKM, UTM 40

    Factories and Machinery (Person-In-Charge)Regulations, 1970

    9. Schedule 1 lists machineries that requirea trained operator:

    Presses

    Saws

    Metal working machines

    Hoisting machines

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    41/48

    Factories and Machinery(Safety, Health and Welfare)

    Regulations, 1970

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    42/48

    FKM, UTM 42

    Factories and Machinery (Safety, Healthand Welfare) Regulations, 1970

    Deal with factory premises and various safety,health and welfare requirements

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    43/48

    FKM, UTM 43

    Factories and Machinery (Safety, Healthand Welfare) Regulations, 1970

    Key points:

    1. Safe means of access and safe place ofemployment, provision of edge protection on flooropenings and stairs (Regulation 7, 8)

    2. All stairways and floors must be of good constructionand properly maintained; ladders must be ofadequate construction and maintained in a soundcondition (Regulations 9 to 11)

    3. Persons must be protected from falls of more than10 feet by the use of safety belts or ropes(Regulation 12)

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    44/48

    FKM, UTM 44

    Factories and Machinery (Safety, Healthand Welfare) Regulations, 1970

    Key points:

    4. Adequate protection are necessary beforeworking inside a confined space (Regulation13)

    5. Flammable and dangerous liquids must besecurely stored and precautions taken

    against fire and explosion (Regulations 14 to17, 21, 22)

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    45/48

    FKM, UTM 45

    Factories and Machinery (Safety, Healthand Welfare) Regulations, 1970

    6. Materials and finished goods must besecurely stacked and stored (Regulations19, 20)

    7. Specifications are laid down for cleaning ofsurfaces inside factory (Regulation 23)

    8. Lighting, ventilation and climate

    requirements are all detailed (Regulations24-29)

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    46/48

    FKM, UTM 46

    Factories and Machinery (Safety, Healthand Welfare) Regulations, 1970

    Key points:

    9. Working clothes and protective

    equipment (Regulation 32)10.Welfare facilities such as toilets, drinking

    water, washing facilities and first aid

    (Regulation 33 to 38)

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    47/48

    FKM, UTM 47

    Four Schedules of the regulations:

    First Schedule specify classes of factoriesthat do not need internal surfaces whitewashed every 12 months;

    Second Schedule describes the level oflighting required in different parts of the factory

    Third Schedule lists work activities that needeye protection or protective screens

    Fourth Schedule contents of first aid box

  • 8/10/2019 03 FMA 1967 Part I Modified by Zamani-libre

    48/48