02930 lawns & grasses rev 1 - biznet.ct.gov€¦ · locations " will be received by the...

160
SPECIFICATIONS & BID FORM FOR “SIDEWALK AND RAMP RECONSTRUCTION, VARIOUS LOCATIONS ” GROTON, CONNECTICUT Contract # 20-08 BID OPENING DATE: AUGUST 20, 2020 TIME: 2:00 P.M. PREVAILING TIME PLACE: TOWN HALL ANNEX 134 GROTON LONG POINT ROAD (OPPOSITE FITCH HIGH SCHOOL) GROTON, CONNECTICUT 06340 TOWN COUNCIL PATRICE GRANATOSKY, MAYOR PORTIA BORDELON JUAN MELENDEZ AUNDRÉ BUMGARDNER LIAN OBREY RACHEL FRANCO JULIETTE PARKER CONRAD F. HEEDE JOE ZEPPIERI TOWN MANAGER DIRECTOR OF PUBLIC WORKS JOHN BURT GREG A. HANOVER, P.E. PREPARED BY: Engineering Division Public Works Department Town of Groton, CT BID DOCUMENT

Upload: others

Post on 15-Aug-2020

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

SPECIFICATIONS & BID FORM FOR

“SIDEWALK AND RAMP RECONSTRUCTION, VARIOUS LOCATIONS ”

GROTON, CONNECTICUT

Contract # 20-08

BID OPENING DATE: AUGUST 20, 2020 TIME: 2:00 P.M. PREVAILING TIME PLACE: TOWN HALL ANNEX 134 GROTON LONG POINT ROAD

(OPPOSITE FITCH HIGH SCHOOL) GROTON, CONNECTICUT 06340

TOWN COUNCIL

PATRICE GRANATOSKY, MAYOR

PORTIA BORDELON JUAN MELENDEZ AUNDRÉ BUMGARDNER LIAN OBREY RACHEL FRANCO JULIETTE PARKER

CONRAD F. HEEDE JOE ZEPPIERI

TOWN MANAGER DIRECTOR OF PUBLIC WORKS JOHN BURT GREG A. HANOVER, P.E. PREPARED BY: Engineering Division Public Works Department Town of Groton, CT

BID DOCUMENT

Page 2: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

2

INDEX

Advertisement for Bids............................................................................... 3

Information for Bidders.............................................................................. 4

Bid Proposal..........................................................................................….17

Form of Contract........................................................................................29

Payment Bond............................................................................................30

Performance Bond......................................................................................32

General Conditions.....................................................................................34

Supplementary Conditions..........................................................................50

State of CT Application for Review of Encroachment Permit .................. 55

Technical Specifications.............................................................................57

BID DOCUMENT

Page 3: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

3

ADVERTISEMENT FOR BIDS “SIDEAWALK AND RAMP RECONSTRUCTION

VARIOUS LOCATIONS”

TOWN OF GROTON, CONNECTICUT (Owner)

Sealed bids for "SIDEWALK AND RAMP RECONSTRUCTION, VARIOUS LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road (across from R. E. Fitch High School) Groton, CT until 2:00 p.m., prevailing time, on August 20, 2020, and then at said office publicly opened and read aloud. Bids must be enclosed in a sealed envelope and designated as bid for “SIDEWALK AND RAMP RECONSTRUCTION, VARIOUS LOCATIONS ".

Any bid may be withdrawn prior to the above scheduled time for opening of bids. Any bid received after the time and date specified will be returned unopened.

All Contract Documents may be examined at the following:

TOWN HALL ANNEX – 134 GROTON LONG POINT ROAD, GROTON, CT PUBLIC WORKS DEPARTMENT

PROJECT DESCRIPTION This project includes the removal and reconstruction of concrete and asphalt sidewalks and ramps in the following locations in the Town of Groton, CT; Poquonnock Plains Park entrance, High Street at Academy Lane and Gravel Street at Clift Street.

Contract documents, including Plans and Specifications, are available on the Town of Groton Website: www.groton-ct.gov.

The Town of Groton reserves the right to waive any formalities or to reject any or all bids.

Each bidder must deposit, with his bid, security in the form of bid bond or certified check subject to the conditions provided in the Information for Bidders.

No bidder may withdraw his bid within 60 days after the actual date of the opening thereof.

Greg A. Hanover, P.E. Director of Public Works Town of Groton, Connecticut

The Town of Groton is An Equal Opportunity/Affirmative Action Employer.

Page 4: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

4

INFORMATION FOR BIDDERS

1. Sealed Bids 2. Method of Award 3. Bid Schedule 4. Arithmetic Discrepancies 5. Bid Security 6. Qualifications of BIDDER 7. Identity of SUB-CONTRACTORS 8. Bonds 9. Non-Resident Contractor Guarantee Bonds 10. Insurance 11. Receipt of Bonds & Insurance Certificates Prior to Signing

Contract 12. Obligation of Bidder 13. Damages for Failure to Enter into Contract 14. Execution of Contract and Notice to Proceed 15. Time of Completion and Liquidated Damages 16. Addenda and Interpretations 17. Substitution Clause 18. Retainage 19. Laws and Regulations 20. List of Utilities in the Area 21. Sales Tax 22. Site Investigation and Conditions Affecting the Work 23. Permits 24. Work Area 25. Change Orders 26. Wages 27. Unbalanced Bids 28. OSHA Violations 29. Local Vendor Preference

Page 5: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

5

INFORMATION FOR BIDDERS

1. Sealed Bids

Sealed bids for "SIDEWALK AND RAMP RECONSTRUCTION, VARIOUS LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m. prevailing time on August 20, 2020, and then at said office publicly opened and read aloud. Bids must be enclosed in a sealed envelope and designated as bid for “SIDEWALK AND RAMP RECONSTRUCTION, VARIOUS LOCATIONS ".

Any bid may be withdrawn prior to the above scheduled time for the opening of bids. Any bid received after the time and date specified will be returned unopened.

2. Method of Award

The Town of Groton intends to award the contract to the lowest responsible bidder. The Town reserves the right to reject any and all bids and to award each contract to the bidder who is most responsive to the interests of the Town. If the lowest base bid submitted by a responsible bidder does not exceed the amount of funds then estimated by the Owner as available to finance the contract, the contract will be awarded on the base bid only. If such bid exceeds such amount, the Owner will reject all bids.

3. Bid Schedule

Bids must be made on these forms and returned intact. Bidders will state both in writing and in figures, in ink or typewritten, the proposed price for each separate item of the work called for in the bid schedule, by which prices will be compared. If any price is omitted, the blank shall be filled with the highest price named by any bidder for that item or the bid may be rejected. Alterations and erasures must be initialed by the signer.

4. Arithmetic Discrepancies

A. For the purpose of initial evaluation of bids, the following will be utilized in resolving arithmetic discrepancies found on the face of the bidding schedule as submitted by bidders:

1. Obviously misplaced decimal points will be corrected. 2. In case of discrepancy between unit price and extended price, the

unit price will govern. 3. Apparent errors in extension of unit prices will be corrected.

Page 6: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

6

4. Apparent errors in addition of lump sum and extended prices will

be corrected.

B. For the purpose of bid evaluation, the Town will proceed on the assumption that the bidder intends his bid to be evaluated on the basis of the unit prices, extensions, and totals arrived at by resolution of arithmetic discrepancies as provided above and the bid will be so reflected on the abstract of bids.

5. Bid Security

If the total amount of the bid submitted exceeds $50,000, or if the bid contains any add alternates and the combination of the base bid plus all add alternates exceeds $50,000, then the bid must be accompanied by a CERTIFIED CHECK or a BID BOND, signed by a responsible Surety, in the amount of 10% of the total amount of the tendered bid and made payable to the order of the Town of Groton. All bid checks or bonds, except those of the lower three (3) bidders will be returned within ten (10) days of the opening of bids. Those of the lower three (3) bidders will be retained by the Town of Groton until one of the lower three (3) bidders signs the contract or until all bids are rejected; however, in no case will the bid check or bond be retained for more than 60 days unless forfeited as hereinafter stipulated. No bidder may withdraw his bid within 60 days after the actual date of the opening thereof.

Should there be reasons why the CONTRACT cannot be awarded within the specified period, the time may be extended by mutual agreement between the OWNER and the BIDDER.

If the total amount of the bid (or base bid plus alternates) submitted is $50,000 or less, then no bid security is required.

The Bid Bond and Surety’s Letter of Intent must be provided by a Surety Company that meets all of the following qualifications as of the date of bid.

A. Licensed to do business in the State of Connecticut B. Listed on the current U. S. Treasury “T” List C. Rate A- or better by A. M. Best

6. Qualifications of BIDDER

The OWNER may make such investigations as he deems necessary to determine the ability of the BIDDER to perform the work, and the BIDDER shall furnish to the OWNER all such information and data for this purpose as the OWNER may request. The OWNER reserves the right to reject any bid if the evidence submitted by, or investigation of, such BIDDER fails to satisfy the OWNER that such BIDDER is properly qualified to carry out the obligations of the

Page 7: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

7

CONTRACT and to complete the work contemplated therein. Conditional bids shall not be accepted. Any CONTRACTOR, who is in litigation or arbitration with the Town at the time of the bid opening, or prior to the execution of the CONTRACT, may be considered an unacceptable BIDDER and may be disqualified.

7. Identity of SUB-CONTRACTORS

If any portion of the work is to be performed by persons or entities not considered to be part of the bidder's own forces, the successful bidder shall, upon notification of the award of a contract, furnish a written list of such other persons or entities and a description of the work to be performed by them. If requested by the Owner, the successful bidder shall be required to establish, to the satisfaction of the Owner, the reliability and responsibility of such Sub-Contractors.

8. Bonds A. Performance Bond If the total bid price for the project exceeds $50,000, or if the bid contains any alternates and the combination of the base bid plus all Town accepted alternates exceeds $50,000, then either of the following is required:

1. The Contractor shall furnish a bond covering faithful performance of the Contract. Surety shall be qualified to do business in the State of Connecticut, listed on the current U. S. Treasury “T” list, and rated "A-" or better by A. M. Best. The cost of the bond premium shall be included in the Contract Sum. The amount of the bond shall be equal to 100 percent of the Contract Sum.

OR

2. In lieu of a Performance Bond, a security in a form acceptable to the Town (for example, letter of credit or an assigned passbook) in the amount of 100% of the Contract may be substituted.

The Contractor shall deliver the required security to the Owner on the date the agreement is entered into.

The Contractor shall require the attorney-in-fact, who executes the required bond on behalf of the surety, to affix thereto a certified and current copy of the power-of-attorney.

Page 8: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

8

In the case where add alternates are part of the bid, and where acceptance of any alternates would cause the Contract Sum to exceed the $50,000 threshold, then the price of the alternate shall include the cost of the required bond or security. B. Payment Bond

If the total bid price for the project exceeds $100,000, or if the bid contains any alternates and the combination of the base bid plus all Town accepted alternates exceeds $100,000, then either of the following is required: 1. The Contractor shall furnish a bond covering payment of obligations arising under the terms of the Contract. Surety shall be qualified to do business in the State of Connecticut, listed on the current U.S. Treasury “T” list, and rated “A-“or better by A.M. Best. The cost of the bond premium shall be included in the Contract Sum. The amount of the bond shall be equal to 100 percent of the Contract Sum.

OR 2. In lieu of a Payment Bond, a security in a form acceptable to the Town (for example, a letter of credit or an assigned passbook) in the amount of 100% of the Contract may be substituted. The Contractor shall deliver the required security to the Owner on the date the Agreement is entered into. The Contractor shall require the attorney-in-fact, who executes the required bond on behalf of the surety, to affix thereto a certified copy of the power-of-attorney. In the case where add alternates are part of the bid, and where acceptance of any alternates would cause the Contract Sum to exceed the $100,000 threshold, then the price of the alternate shall include the cost of the required bond or security. If the total bid (or base bid plus alternates) for the project is $100,000 or less, then in lieu of providing any security listed in Section 8.B, the Contractor can elect to substitute the following: 1. Provide certified lien waivers from each supplier and sub- contractor affirming that they have been paid for work and materials for which previous payment applications were issued by the Owner and payments received by the Contractor.

9. Non-Resident Contractor Guarantee Bonds

Page 9: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

9

A Non-Resident Contractor is required to post a Guarantee Bond (form AU-766) or Cash Bond (form AU-72) with the State of Connecticut Department of Revenue Services (DRS) in the amount of 5% of the total contract price. This Bond will secure payment for applicable taxes payable to the State related to this Project. The State will issue a Certificate of Compliance once an acceptable bond has been submitted by the Non-Resident Contractor. This Certificate of Compliance must be provided by the Contractor to the Town prior to the release of the first progress payment under the Contract, or the Town must remit 5% of the total contract value directly to the State. This 5% is in addition to the Project retainage. Special Notice SN2012(2), published by the State of Connecticut Department of Revenue Services, details the procedures and requirements regarding the Guarantee Bond or Cash Bond. The Special Notice and bond forms can be obtained at the State of Connecticut Department of Revenue Services webpage, www.ct.gov/DRS. 10. Insurance

The Contractor must provide a CERTIFICATE OF INSURANCE as specified in the General and Supplementary Conditions.

11. Receipt of Bonds & Insurance Certificates Prior to Signing Contract

The Contractor to whom the contract shall be awarded must file the requisite BONDS and CERTIFICATE OF INSURANCE as specified and any other forms and documents required by the specifications prior to signing of the contract, and within 21 days from the date of receipt of notification of said award.

12. Obligation of Bidder

Bidders, if requested, must be able to present evidence satisfactory to the Director of Public Works that they have been regularly engaged in the business of constructing such work as they propose to execute, and that they are fully prepared with the necessary capital, materials, and equipment to conduct the work to be contracted for, and to begin it promptly when ordered.

Prior to submitting his bid, the bidder must inspect the site and thoroughly read all plans, specifications and bid and contract documents. The failure or omission of any bidder to examine any form, instrument or document and to thoroughly examine the site shall in no way relieve any bidder from any obligations in respect to his bid.

13. Damages for Failure to Enter into Contract

The party to whom the CONTRACT is awarded will be required to execute the CONTRACT within thirty (30) calendar days from the date when Notice of Award is

Page 10: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

10

delivered to the BIDDER. In case of failure of the BIDDER to execute the CONTRACT, the OWNER may at his option, consider the BIDDER in default, in which case the bid security accompanying the proposal shall become the property of the OWNER as liquidated damages and not as a penalty.

14. Execution of Contract and Notice to Proceed

The OWNER within twenty (20) days of receipt of acceptable PERFORMANCE BOND, PAYMENT BOND and CONTRACT signed by the party to whom the CONTRACT was awarded shall sign the CONTRACT and return to such party an executed duplicate of the CONTRACT. Should the OWNER not execute the CONTRACT within such period, the BIDDER may by written notice withdraw his signed CONTRACT. Such notice of withdrawal shall be effective upon receipt of the notice by the OWNER.

The Notice to Proceed shall be issued within ten (10) days of the execution of the CONTRACT by the OWNER. Should there be reasons why the Notice to Proceed cannot be issued within such period, the time may be extended by mutual agreement between the OWNER and the CONTRACTOR. If the Notice to Proceed has not been issued within the ten (10) day period or within the period mutually agreed upon, the CONTRACTOR may terminate the CONTRACT, whereupon it shall become null and void and all rights and obligations created thereunder shall be extinguished.

15. Time of Completion and Liquidated Damages

BIDDER must agree to commence work on or before a date to be specified in a written Notice to Proceed from the OWNER and to fully complete the project within 30 consecutive calendar days thereafter. Bidder must agree also to pay as liquidated damages, the sum of $200.00 for each consecutive calendar day thereafter as hereinafter provided in the GENERAL CONDITIONS.

It is hereby understood and mutually agreed, by and between the CONTRACTOR and the OWNER, that the date of beginning and the time for completion during the normal working hours as specified in the General Conditions of the work to be done hereunder are essential conditions of this CONTRACT; and it is further mutually understood and agreed that the work embraced in this CONTRACT shall be commenced on a date to be specified in the "Notice to Proceed".

The CONTRACTOR agrees that said work shall be prosecuted regularly, diligently, and uninterruptedly at such rate of progress as will insure full completion thereof within the time specified. It is expressly understood and agreed, by and between the CONTRACTOR and the OWNER, that the time for the completion of the work described herein is a reasonable time for the completion of same, taking into consideration the average climatic range and usual industrial conditions prevailing in this locality.

If the said CONTRACTOR shall neglect, fail or refuse to complete the work within the time herein specified, or any proper extensions thereof granted by the OWNER, then the CONTRACTOR does hereby agree, as a part consideration for the awarding of this

Page 11: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

11

CONTRACT, to pay to the OWNER the amount specified in the Information for Bidders, not as a penalty but as liquidated damages for such breach of CONTRACT as hereinafter set forth, for each and every calendar day that the CONTRACTOR shall be in default after the time stipulated in the CONTRACT for completion of the work.

The said amount is fixed and agreed upon by and between the CONTRACTOR and the OWNER because of the impracticability and extreme difficulty of fixing and ascertaining the actual damages the OWNER would in such event sustain, and said amount is agreed to be the amount of damages which the OWNER would sustain and said amount shall be retained from time to time by the OWNER from current periodic estimates.

It is further agreed that time is of the essence of each and every portion of this CONTRACT and of the specifications wherein a definite and certain length of time is fixed for the performance of any act whatsoever; and where under the CONTRACT an additional time is allowed for the completion of any work, the new time limit fixed by such extension shall be of the essence of this CONTRACT. The CONTRACTOR shall not be in default when the delay in completion of the work is due:

A. To any preference, priority or allocation order duly issued by the State or Federal

Government B. To unforeseeable cause beyond the control and without the fault or negligence of

the CONTRACTOR, including, but not limited to, acts of God, or of the public enemy, acts of the OWNER, acts of another contractor in the performance of a contract with the OWNER, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes and severe weather. The CONTRACTOR shall, within ten (10) days from the beginning of any such delay, unless the OWNER shall grant a further period of time prior to the date of final settlement of the CONTRACT, notify the OWNER, in writing, of the causes of the delay. The Owner shall ascertain the facts and extent of the delay and notify the CONTRACTOR within a reasonable time of its decision in the matter.

16. Addenda and Interpretations All questions about the meaning or intent of the Contract Documents are to be directed to the Owner. Interpretations or clarifications considered necessary by the Owner in response to such questions will be issued by Addenda mailed or delivered to all parties recorded by the Owner as having received the Bidding Documents. Questions received less than seven days prior to the date for opening of Bids may not be answered. Only questions answered by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.

Addenda will be issued to modify the Bidding Documents as deemed advisable by the Owner.

Page 12: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

12

17. Substitution Clause

Wherever in the Plans and Specifications any item of equipment or material is designed by reference to a particular brand, manufacturer, or trade name, it is understood that an approved equal product, acceptable to the OWNER, may be substituted by the BIDDER or the CONTRACTOR.

18. Retainage

The Town of Groton reserves the right to retain 5% of the final contract price for a period not to exceed six (6) months from the date of final acceptance of the project.

19. Laws and Regulations

The bidder's attention is directed to the fact that all applicable Federal and State law, municipal ordinances, and the rules and regulations of all authorities having jurisdiction over construction of the project shall apply to the contract throughout, and they will be deemed to be included in the contract the same as though herein written out in full.

20. List of Utilities in the Area

Attention is called to the fact that the following Utility Companies have facilities in the area:

Groton Utilities – Water Frontier – Telephone Comcast Cablevision Co. – CATV Thames Valley Communications, Inc. – CATV Eversource – Electric Groton Utilities - Electric Town of Groton – Sewer Eversource - Gas

Information and data reflected in the Contract Documents with respect to Underground Facilities at or contiguous to the site is based upon information and data furnished to Owner by owners of such Underground Facilities or others, and Owner does not assume responsibility for the accuracy or completeness thereof unless it is expressly provided otherwise in the Supplementary Conditions. The Contractor should acquaint himself with and adhere to the regulations of those utilities which are in the area of this Contract.

When requested by the Contractor, all underground utilities will be located and marked on the surface by the controlling utility company at no cost to him. Contractor will be responsible for notifying the Utility clearinghouse, "Call-Before-You-Dig" 48 hours prior to any excavation, to allow for the location of the existing utilities by controlling Utility Company.

Page 13: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

13

21. Sales Tax

Under the terms of the regulations referring to CONTRACTORS and SUBCONTRACTORS, issued by the STATE TAX COMMISSION in administration of the STATE Sales and Use Tax, to which the BIDDER is referred, the CONTRACTOR may purchase materials or supplies to be consumed in the performance of this contract without payment of tax and shall not include in his bid nor charge any use or sales tax thereon.

22. Site Investigation and Conditions Affecting the Work

Arrangements to visit the site may be made by calling the Public Works Department Engineering Division, (860) 448-4083, Monday through Friday, 8:30 a.m. to 3:30 p.m.

A. The Contractor acknowledges that it has taken steps reasonably necessary to

ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to:

1. Conditions bearing upon transportation, disposal, handling, and storage of

materials; 2. The availability of labor, water, electric power, and roads; 3. Uncertainties of weather, river stages, tides, or similar physical conditions

at the site; 4. The conformation and conditions of the ground; and 5. The character of equipment and facilities needed preliminary to and during

work performance.

B. The Contractor also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by the Town, as well from the drawings and specifications made a part of this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Town.

C. The Town assumes no responsibility for any conclusions or interpretations made by the Contractor based on the information made available by the Town. Nor does the Town assume responsibility for any understanding reached or representation made concerning conditions, which can affect the work by any of

Page 14: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

14

its officers or agents before the execution of this contract, unless that understanding or representation is expressly stated in this Contract.

D. The Contract Documents contain the provisions required for the construction of the project. Information obtained from an officer, agent or employee of the OWNER or any other person shall not affect the risks or obligations assumed by the CONTRACTOR or relieve him from fulfilling any of the conditions of the CONTRACT.

23. Permits

The Contractor must obtain all necessary construction and building permits; however, the fee for any permits issued by the Town of Groton shall be waived.

24. Work Area

Construction will be confined to the immediate work area only. Trespass on property other than Town property or easements acquired by the Town for the project will be by written permission of the property owner only.

25. Change Orders

Any deviations from, additions to, or deductions from either scope of work or contract price shall be submitted by the Contractor to the Town in the form of a contract change order. The Director of Public Works must approve this contract change order before said deviations, additions, or deductions shall be enacted.

Further, all changes in scope of work involving unit price items shall be governed by the unit price indicated by the Contractor on the Base Bid Form.

26. Wages

Bidder is directed to Paragraph 45 of the General Conditions for wage rate scales and legislation applicable to this contract.

27. Unbalanced Bids An unbalanced bid is one in which the contractor’s unit prices are:

a. Significantly higher or lower than the Engineer’s estimate.

b. “Front loaded” so contractor receives a disproportionate payment for work done during the early stages of a project.

c. Token bid prices (i.e. penny unit bids).

While it is often impossible to designate precisely the dividing line between a balanced bid and an unbalanced bid, contractors should be aware that the Department may regard the

Page 15: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

15

unbalancing of a bid as so extreme, undeniable, or detrimental to the interests of the Town that it may question the contractor about the apparent unbalancing of the bid proposal, and, if the contractor cannot provide a satisfactory explanation of the apparent unbalancing, and if the Department’s assessment of the risk to the Town is unacceptable, reject the bid as nonresponsive. 28. OSHA Violations In accordance with Connecticut General Statute Section 31-57b, no contract shall be

awarded to a bidder if it is determined that the bidder (person or firm) has been cited for three (3) or more willful or serious violations of any occupational safety and health act or of any standard, order or regulation promulgated pursuant to such act during the three (3) year period preceding the date of bid opening.

29. Local Vendor Preference The Town of Groton has adopted a policy of providing preference to selecting Local

Vendors as outlined in this section. The term “Local Vendor” as used in this section shall mean, and be used interchangeably with, “Bidder” and “Contractor”.

A. Definition: The term “Local Vendor” shall mean a company, firm, LLC, partnership,

sole proprietorship or similar business with its principal place of business located within the Town of Groton. A business shall not be considered a local vendor unless satisfactory evidence has been submitted with the bid that clearly establishes that it has a bona fide principal place of business, including branches or satellite offices, in the Town of Groton. Such documentation shall include evidence of ownership such as real estate and personal property bills, a lease agreement for the real estate from which the principal place of business operates, copies of deeds, or copies of paid real estate and personal property bills.

B. Application: To be considered, and be given preference as a local vendor, the bidder

must complete and submit with their bid, a local vendor registration affidavit of eligibility (included hereinafter) together with copies of any of the documents listed above in paragraph A. A local vendor registration affidavit of eligibility submitted after bids are opened will not be considered.

C. Implementation: If the total bid amount, together with any add or deduct alternates the

Town wishes to accept, submitted by a qualified responsive Local Vendor is not more than five percent (5%) higher than the lowest bid, then the Town has the right to award the contract to the local vendor provided he agrees to match the lowest bid.

In the instance of two or more Local Vendors being within the 5% threshold, then the qualified responsive local vendor with the lowest actual bid will be given the first opportunity to match the low bid. For bids involving unit prices, and when the qualified responsive local vendor agrees to match the low total bid amount, he must also submit updated individual unit prices

Page 16: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

16

showing the total amount to meet the low bid. The Town of Groton reserves the right to approve or disapprove which unit prices are used to net the total bid amount.

D. Notification: When a local vendor meets the criteria for submitting a successful bid

and has provided all of the required documentation, a letter signed by the Public Works Director will be sent to the local vendor. The letter will notify the local vendor that they have met all of the criteria of this provision and will formally request that they respond in writing to the Town within five (5) business days that they are willing to match the lowest price bid. In the case of bids with unit prices, the local vendor must also include a revised list of unit prices. Once the local vendor has agreed to match the low bid and all other conditions of a successful bid have been met, the contract will be awarded to the local vendor.

E. Exemptions: Any bid made under the following are exempt from this section:

a. Projects utilizing any Federal or State of Connecticut funds or grants b. Projects utilizing any special grant that stipulates the award must be made

to the lowest qualified bidder

END OF SECTION

Page 17: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

17

PROPOSAL “SIDEWALK AND RAMP RECONSTRUCTION, VARIOUS LOCATIONS ”

Proposal of hereinafter called "BIDDER" *a corporation of the State of *a partnership, or *an individual doing business as To the Town of Groton, Connecticut Gentlemen: The undersigned hereby declares that no person or persons other than those named herein are interested in this proposal or in the Contract proposed to be taken; that it is made without any connection with any other person making any proposal for the same work, and is in all respects fair and without collusion or fraud; that no person acting for or employed by the Town of Groton is directly interested therein, or in the supplies or works to which it relates, or in any portion of the profits thereof; that it is understood that the Town, its agents and employees are not to be in any manner held responsible for the accuracy of, or bound by, the estimates or borings or plan of borings relative to the work and appearing on plans or in the foregoing notice; and that all such estimates, etc., are to be considered solely for the purpose of filling out and comparing the several proposals. The undersigned further declares that he has carefully examined the Information For Bidders, Contract documents, including the Plans and Specifications, and has inspected the site and will contract to provide all necessary tools, apparatus and implements, freight, cartage, and expense, and to do all the work and furnish all the materials necessary in the manner and upon the conditions specified and upon the following terms at the prices specified on the following pages. The undersigned agrees to furnish satisfactory bonds and insurance as required by Paragraph 1 of the General Conditions, Section 8, 9, 10 and 11 of the Information for Bidders and by the Supplementary Conditions Section 1, and to execute within 30 days after notice of the award, a formal contract with the Town of Groton for the fulfillment of this proposal, and it is agreed that in case of failure on the part of the undersigned to do so, the certified check or bid bond deposited herewith shall be forfeited to the Town of Groton as liquidated damages for such failure.

Page 18: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

18

BIDDER hereby agrees to commence work under this contract on or before a date to be specified in written NOTICE TO PROCEED of the OWNER and to fully complete the project in strict compliance with the Contract Documents within 30 days of the start date in the notice to proceed. BIDDER further agrees to pay as liquidated damages, the sum of $200.00 for each consecutive calendar day thereafter as hereinbefore provided in Paragraph 15 of the Information for Bidders. BIDDER acknowledges receipt of the following addendum: ______________________________________________________________________________ ______________________________________________________________________________ The undersigned further agrees, in case of a corporation or fictitious trade name, that an acceptable certificate will be filed showing the proper officer or person authorized to sign said contract. Amounts are to be shown in both words and figures. In case of discrepancy, the amount shown in words will govern. Any unit prices shall include all labor, materials, bailing, shoring, removal, overhead, profit, insurance, etc., to cover the finished work of the several kinds called for. Bidder understands that the Owner reserves the right to reject any or all bids and to waive any formalities in the bidding. The bidder agrees that this bid shall be good and may not be withdrawn for a period of 60 calendar days after the scheduled closing time for receiving bids. The bid Security attached in the sum of: _______________________________________________________dollars ($____________) is to become the property of the Owner in the event the Contract and Contract Bonds are not executed within the time above set forth, as liquidated damages for the delay and additional expense to the Owner caused thereby.

Page 19: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

19

SCHEDULE OF PRICES “SIDEWALK AND RAMP RECONSTRUCTION, VARIOUS LOCATIONS ”

GROTON, CONNECTICUT NOTE: All prices must be written in ink or typewritten, in words and in figures for the entire

proposal. In case of discrepancy, words will take precedence over numbers and unit prices will take precedence over extended prices.

ESTIMATED BRIEF DESCRIPTION AND UNIT PRICE TOTAL PRICE ITEM SECTION QUANTITY UNIT PRICE IN WORDS__ IN FIGURES IN FIGURES 1. 01505 LS Mobilization, per Lump Sum ________________dollars ________________cents $__________ $__________ ______________________________________________________________________________ 2. 01570 LS Maintenance and Protection of Traffic, Per Lump Sum ________________dollars ________________cents $__________ $__________ ______________________________________________________________________________ 3. 01571 144 MH Traffic Directors, Per Man Hours ________________dollars ________________cents $__________ $__________ ______________________________________________________________________________ 4. 02275 100 LF Erosion Control Per Linear Foot ________________dollars ________________cents $__________ $__________ ______________________________________________________________________________

Page 20: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

20

ESTIMATED BRIEF DESCRIPTION AND UNIT PRICE TOTAL PRICE ITEM SECTION QUANTITY UNIT PRICE IN WORDS__ IN FIGURES IN FIGURES 5. 02511 4 Tons HMA, S0.375 Per Ton ________________dollars ________________cents $__________ $__________ ______________________________________________________________________________ 6. 02511 6 Tons HMA, S0.50 Per Ton ________________dollars ________________cents $__________ $__________ ______________________________________________________________________________ 7. 02514 10 LF Bituminous Concrete Curbing Per Linear Foot ________________dollars ________________cents $__________ $__________ ______________________________________________________________________________ 8. 02515 85 SF Bituminous Concrete Sidewalk Per Square Foot ________________dollars ________________cents $__________ $__________ ______________________________________________________________________________ 9. 02520 85 SF Concrete Sidewalk Per Square Foot ________________dollars ________________cents $__________ $__________ ______________________________________________________________________________

Page 21: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

21

ESTIMATED BRIEF DESCRIPTION AND UNIT PRICE TOTAL PRICE ITEM SECTION QUANTITY UNIT PRICE IN WORDS__ IN FIGURES IN FIGURES 10. 02521 20 LF Concrete Curbing Per Linear Foot ________________dollars ________________cents $__________ $__________ ______________________________________________________________________________ 11. 02522 800 SF Integral Concrete Sidewalks and Curbs Per Square Foot ________________dollars ________________cents $__________ $__________ ______________________________________________________________________________ 12. 02920 20 SY Topsoil Per Square Yard ________________dollars ________________cents $__________ $__________ ______________________________________________________________________________ 13. 02930 20 SY Lawn Seeding Per Square Yard ________________dollars ________________cents $__________ $__________ ______________________________________________________________________________

Page 22: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

22

THE TOTAL BID OF ITEMS 1 THROUGH 13, AS COMPUTED BY THE BIDDER, USING THE ESTIMATED QUANTITIES SHOWN: IN FIGURES: IN WORDS:

Page 23: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

23

The undersigned offers the following information as evidence of his qualifications to perform the work as bid upon according to all requirements of the Plans and Specifications. 1. Have been in business under present business name: years. 2. Ever failed to complete any work? 3. List the more important contracts recently completed by you, stating approximate cost for

each, and the month and year completed.

a. Location__________________________________________________________

Project/Phone#_____________________________________________________

Engineer/Phone#____________________________________________________

Completion Date____________________________________________________

Amount of Contract_________________________________________________

b. Location__________________________________________________________

Project/Phone#_____________________________________________________ Engineer/Phone#____________________________________________________

Completion Date____________________________________________________

Amount of Contract_________________________________________________

c. Location__________________________________________________________

Project/Phone#_____________________________________________________

Engineer/Phone#____________________________________________________

Completion Date____________________________________________________

Amount of Contract____________________________________ _____________

4. Bank Reference/Phone#

Page 24: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

24

This firm consists of the following members: Full Name Residence ______________________________________________________________________________ ______________________________________________________________________________ ______________________________________________________________________________ ______________________________________________________________________________ The officers are: Full Name Residence President:______________________________________________________________________ Treasurer:_____________________________________________________________________ Directors:______________________________________________________________________

______________________________________________________________________

______________________________________________________________________

Respectfully Submitted:

__________________________________________ (Firm Name)

SEAL: (If bid is by a Corporation) By: ______________________________________

(Signature) __________________________________________

(Typed Name and Title) __________________________________________

__________________________________________

(Business Address) __________________________________________

(Telephone) _________________________________________

(Fax) __________________________________________

(Email)

Page 25: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

25

(ACKNOWLEDGMENT OF PRINCIPAL, IF A CORPORATION) STATE OF ___________ ss: COUNTY OF _________

ON THIS DAY OF , 20__, BEFORE ME PERSONALLY CAME AND APPEARED , TO ME KNOWN, WHO, BEING BY ME DULY SWORN, DID DEPOSE AND SAY THAT HE RESIDES AT , THAT HE IS THE OF , THE CORPORATION DESCRIBED IN AND WHICH EXECUTED THE FOREGOING INSTRUMENT THAT HE KNOWS THE SEAL OF SAID CORPORATION - THAT ONE OF THE IMPRESSIONS AFFIXED TO SAID INSTRUMENT IS AN IMPRESSION OF SUCH SEAL - THAT IT WAS SO AFFIXED BY ORDER OF THE DIRECTORS OF SAID CORPORATION, AND THAT HE SIGNED HIS NAME THERETO BY LIKE ORDER. (SEAL) ______________________________

(NOTARY PUBLIC) ******************************************************************************

(ACKNOWLEDGMENT OF PRINCIPAL, IF A PARTNERSHIP) STATE OF____________

ss: COUNTY OF _________ ON THIS DAY OF , 20__, BEFORE ME PERSONALLY CAME AND APPEARED , TO ME KNOWN AND KNOWN TO ME TO BE ONE OF THE MEMBERS OF THE FIRM OF DESCRIBED IN AND WHO EXECUTED THE SAME AS AND FOR THE ACT AND DEED OF SAID FIRM. (SEAL) ______________________________

(NOTARY PUBLIC) ******************************************************************************

(ACKNOWLEDGMENT OF PRINCIPAL, IF AN INDIVIDUAL) STATE OF____________

ss: COUNTY OF__________ ON THIS DAY OF , 20__, BEFORE ME PERSONALLY CAME AND APPEARED TO ME KNOWN AND KNOWN TO ME TO BE THE PERSON DESCRIBED IN AND WHO EXECUTED THE SAME. (SEAL) ______________________________

(NOTARY PUBLIC)

Page 26: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

26

TOWN OF GROTON

LOCAL VENDOR REGISTRATION

AFFIDAVIT OF ELIGIBILITY

Legal Name of Business:_________________________________________________________ Business Type: �Corporation �LLC �Partnership �Sole Proprietorship �Other Physical Groton Address:________________________________________________________ Mailing Address (if different):____________________________________________________ City:_______________________________________ State:________ Zip Code:____________ Owner/Principal Name:__________________________________________________________ Phone:___________________________ E-Mail:______________________________________ Supporting Documentation Attached (check one):

� Copy of cancelled check for payment of real estate or personal property taxes

� Copy of long term lease of the real estate from which the business is operated

� Copy of deed

� Other:________________________________________________________

Under penalty of perjury, the undersigned states that the foregoing statements are true and correct.

Authorized Signature:___________________________________ Date:____________________

Printed Name:________________________________ Title:_____________________________

Personally appeared,______________________________________________ owner/principal of

________________________________________________________, signer and sealer of the foregoing instrument and acknowledged the truth of the foregoing before me on the _____day of____________in the year__________

_________________________________ Notary Public

My Commission expires:_____________

Page 27: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

27

BID BOND

KNOW ALL MEN BY THESE PRESENTS, that we, the undersigned, _____________ ______________________ as Principal, and _________________________________________ as Surety, are hereby held and firmly bound unto The Town of Groton as owner in the penal sum of for the payment of which, well and truly to be made, we hereby jointly and severally bind ourselves, our heirs, executors, administrators, successors and assigns.

Signed this day of , 20__

The condition of the above obligation is such that whereas the Principal has submitted to The Town of Groton a certain bid, attached hereto and hereby made a part hereof to enter into a contract in writing for the NOW, THEREFORE,

A. If said Bid shall be rejected, or in the alternate, B. If said Bid shall be accepted and the Principal shall execute and deliver a

contract in the Form of Contract attached hereto, properly completed in accordance with said Bid, and shall furnish a bond for his faithful performance of said contract, and for the payment of all persons performing labor or furnishing materials in connection therewith, and shall provide the required evidence of insurance,

THEN, this obligation shall be void, otherwise the same shall remain in force and

effect; it being expressly understood and agreed that the liability of the Surety for any and all claims hereunder shall, in no event, exceed the penal amount of this obligation as herein stated.

The Surety, for value received, hereby stipulates and agrees that the obligations of said Surety and its bond shall be in no way impaired or affected by any extension of the time within which the Owner may accept such Bid; and said Surety does hereby waive notice of any such extension.

Page 28: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

28

IN WITNESS WHEREOF, the Principal and the Surety have hereunto set their hands and seals, and such of them as are corporations have caused their corporate seals to be hereto affixed and these presents to be signed by their proper officers, the day and year first set forth above. ATTEST: ________________________________ _________________________(S) (Principal) Secretary Principal (SEAL) _________________________________ By ________________________ (S) Witness as to Principal Attorney-in-Fact _________________________________ ___________________________ (Address - Zip Code) (Address - Zip Code) ATTEST: _________________________________ ___________________________ (Surety) Secretary Surety (SEAL) _________________________________ By ________________________(S) Witness as to Surety Attorney-in-Fact _________________________________ ___________________________ (Address - Zip Code) (Address - Zip Code)

Page 29: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

29

TOWN OF GROTON CONTRACT # 20-08

This Contract is entered into this ____ day of _________, 20__, between the TOWN OF GROTON, hereinafter called the TOWN and _______________________________________ hereinafter called the CONTRACTOR, whereby the CONTRACTOR agrees to complete the work on the project entitled SIDEWALK AND RAMP RECONSTRUCTION, VARIOUS LOCATIONS in accordance with the contract documents which consist of the Instructions to Bidders, the Proposal, General and Supplementary Conditions, plans and specifications and which are hereby made part of this Contract. The CONTRACTOR agrees to carry on the work with diligence and dispatch, and to furnish such equipment and labor as is consistent with good construction practice and furnish the completed project to the TOWN in a good and usable condition. The TOWN agrees that it will pay the CONTRACTOR as specified in the Specifications and the Proposal, and upon satisfactory completion of the work, it will accept the project. After completion of the project, and acceptance by the TOWN the CONTRACTOR shall submit an itemized final estimate. No later than 31 days after acceptance of the final estimate by the TOWN, the TOWN shall pay 95% of the Contract price. No later than six (6) months after acceptance of the final estimate, the TOWN will pay the 5% retained, unless in that time the materials or workmanship in the project shall have been found to be defective. The total payment will be ______________________________________________________________________________($__________________). Signed at Groton, Connecticut this _____ day of _______________, 20__ For the CONTRACTOR FOR TOWN OF GROTON _____________________________ _____________________________

John Burt Town Manager

_____________________________ _____________________________

Cindy R. Landry Director of Finance

_____________________________ Greg A. Hanover, P.E. Director of Public Works

Page 30: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

30

PAYMENT BOND

Bond #____________

KNOW ALL MEN BY THESE PRESENTS: That we _______________________________________________________________________

(Name of Contractor) a _________________________________________________hereinafter called “Principal” and

(corporation, partnership or individual) _____________________________, of ______________________, State of _______________,

(Surety) (City/Town) hereinafter called “Surety” are held and firmly bound unto ______________________________,

(Owner) of ____________________________________, hereinafter called “Owner”, in the penal sum of (City/Town, State) _______________________________________________________________________ Dollars ($_________________________) in lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators and successors, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION is such that Whereas, the Principal entered into a certain contract with the Owner, dated the ______ day of ___________________, 20__, a copy of which is hereto attached and made a part hereof for the construction of: Sidewalk and ramp reconstruction in three (3) locations in the Town of Groton, CT as shown on the contract drawings.

NOW, THEREFORE, if the Principal shall make payment to all persons, firms, subcontractors, and corporations furnishing materials for or performing labor in the prosecution of the work provided for in such contract, and any authorized extension or modification thereof, including all amounts due for materials, lubricants, oil, gasoline, coal and coke consumed, repairs on machinery, equipment and tools, or insurance premiums on said work, and for all labor, performed in such work whether by subcontractor or otherwise, then this obligation shall be void; otherwise to remain in full force and effect.

PROVIDED, FURTHER, that the said surety, for value received hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the contract or to the work to be performed thereunder or the specifications accompanying the same shall in any way affect its obligation on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the contract or to the work or to the specifications.

Page 31: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

31

PROVIDED, FURTHER, that no final settlement between the Owner and the Contractor shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied.

PROVIDED, FURTHER, that the provisions of Sec. 49-41a of the Connecticut General Statutes are incorporated herein and made a part hereof. Any provision of this bond contrary to such statutory provisions shall not be enforceable.

IN WITNESS, WHEREOF, this instrument is executed in three (3) counterparts, each

one of which shall be deemed an original, this the _____ day of _________________, 20__. ATTEST: ________________________________ _________________________(S) (Principal) Secretary Principal (SEAL) _________________________________ By ________________________ (S) Witness as to Principal Attorney-in-Fact _________________________________ ___________________________ (Address - Zip Code) (Address - Zip Code) ATTEST: _________________________________ ___________________________ (Surety) Secretary Surety (SEAL) _________________________________ By ________________________(S) Witness as to Surety Attorney-in-Fact _________________________________ ___________________________ (Address - Zip Code) (Address - Zip Code) NOTE: Date of Bond must not be prior to date of Contract. If Contractor is Partnership, all partners should execute bond.

Page 32: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

32

PERFORMANCE BOND

Bond #____________

KNOW ALL MEN BY THESE PRESENTS:

That we _______________________________________________________________________ (Name of Contractor) a _________________________________________________ hereinafter called “Principal” and (corporation, partnership or individual) _____________________________ of ______________________, State of _______________, (Surety) (City/Town) hereinafter called the “Surety”, are held and firmly bound unto ___________________________ (Owner) of ______________________________________________, hereinafter called “Owner”, in the (City/Town, State) penal sum of ____________________________________________________________Dollars ($__________________________) in lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators and successors, jointly and severally, firmly by these presents. THE CONDITION OF THIS OBLIGATION is such that Whereas, the Principal entered in a certain contract with the Owner, dated the ______ day of ____________________, 20__, a copy of which is hereto attached and made a part hereof for the construction of: Sidewalk and ramp reconstruction in three (3) locations in the Town of Groton, CT as shown on the contract drawings.

NOW, THEREFORE, if the Principal shall well, truly and faithfully perform its duties, all the undertakings, covenants, terms, conditions, and agreements of said contract during the original term thereof, and any extensions thereof which may be granted by the Owner, with or without notice to the Surety, and if he shall satisfy all claims and demands incurred under such contract, and shall fully indemnify and save harmless the Owner from all costs and damages which it may suffer by reason of failure to do so, and shall reimburse and repay the Owner all outlay and expense which the Owner may incur in making good any default, then this obligation shall be void; otherwise to remain in full force and effect.

PROVIDED, FURTHER, that the said Surety, for such value received hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the contract or to the work shall in any way affect its obligation on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the contract or to the work or to the specifications.

Page 33: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

33

PROVIDED, FURTHER, that no final settlement between the Owner and the Contractor shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied. IN WITNESS WHEREOF, this instrument is executed in three (3) counterparts, each of which shall be deemed an original, this the _______ day of ____________________, 20__. ATTEST: ________________________________ _________________________(S) (Principal) Secretary Principal

___________________________ (SEAL) _________________________________ By ________________________ (S) Witness as to Principal Attorney-in-Fact _________________________________ ___________________________ (Address - Zip Code) (Address - Zip Code) ATTEST: _________________________________ ___________________________ (Surety) Secretary Surety (SEAL) _________________________________ By ________________________(S) Witness as to Surety Attorney-in-Fact _________________________________ ___________________________ (Address - Zip Code) (Address - Zip Code) NOTE: Date of Bond must not be prior to date of Contract. If Contractor is Partnership, all

partners should execute Bond.

Page 34: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

34

GENERAL CONDITIONS

1. Insurance Requirements 2. Town Representation 3. Contractor Field Supervision 4. Engineering 5. Contract Drawings, Maps and Specifications 6. Utility Relocation 7. Test Pits 8. Explosives 9. Dust Control 10. Sanitary Facilities 11. Pre-Construction Meeting 12. Construction Meetings 13. Quantities 14. Differing Site Conditions 15. Reports 16. Eliminated Items 17. Work Stoppages 18. Traffic Control 19. Protection of Existing Vegetation, Structures, Equipment, Utilities &

Improvements 20. Engineer 21. Progress Payments 22. General Guaranty 23. Daily Clean Up 24. Nondiscrimination 25. Roadway Closings 26. Extra Work 27. Samples 28. Quality of Equipment and Materials 29. Shop or Setting Drawings 30. Plans & Specifications at the Site 31. Materials, Services and Facilities 32. Contractor's Title to Materials 33. Inspection of Construction 34. Inspection and Testing of Materials 35. Contractor's Obligation 36. Weather Conditions 37. Provisions Required by Law Deemed Inserted 38. Right of the Owner to Terminate Contract 39. Acceptance of Final Payment Constitutes Release

Page 35: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

35

40. Assignments 41. Codes, Regulations and Issue Date of Standard Specifications 42. Emergency Telephone Number 43. Other Contracts 44. The Owner's Duties and Rights 45. Wage Rates 46. Contract Bid Breakdown (Lump Sum) 47. Hours of Work 48. Waste Disposal

Page 36: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

36

1. Insurance Requirements

The Contractor must carry insurance under which the Town is an ADDITIONAL INSURED. Such insurance must be by insurance companies licensed to write such insurance in Connecticut against the risks and for no less than the minimum amounts and duration’s as set forth in the SUPPLEMENTARY CONDITIONS, Section 1.

2. Town Representation The Town will be represented at all times by the Director of Public Works or an

authorized representative of the Public Works Department. They shall have the responsibility and authority for the interpretation of the Contract, its specifications and drawings.

3. Contractor Field Supervision The Contractor must have a competent Field Supervisor on the job during all working

hours. His name, address and phone number shall be available to the Town for after-hour emergencies.

4. Engineering All field engineering and inspection shall be provided by the Engineering Division of the

Public Works Department. No field changes shall be allowed without specific notification of and approval by the Owner. Any changes will be recorded on prints and initialed by the Construction Observer.

5. Contract Drawings, Maps and Specifications A. Omissions from the drawings or specifications or the mis-description of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or mis-described details of the work but they shall be performed as if fully and correctly set forth and described in the drawings and specifications. B. The Contractor shall check all drawings furnished to him immediately upon their receipt and shall promptly notify the Owner of any discrepancies. Figures marked on drawings shall in general be followed in preference to scale measurements. The Contractor shall compare all drawings and verify the figures before laying out the work and will be responsible for any errors which might have been avoided thereby. C. Any discrepancies found between the Drawings and Specifications and site conditions or any errors or omissions in the Drawings or Specifications shall be immediately reported to the DIRECTOR OF PUBLIC WORKS in writing, who shall promptly correct such error or omission in writing. Any work done by the

Page 37: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

37

CONTRACTOR after his discovery of such discrepancies, errors or omissions without notifying the DIRECTOR OF PUBLIC WORKS shall be done at the CONTRACTOR'S risk. D. Further instructions may be issued by the DIRECTOR OF PUBLIC WORKS during the progress of the work by means of Drawings or oral or written instruction to make more clear or specific the Drawings and Specifications or as may be necessary to explain or illustrate changes in the work to be done. The CONTRACTOR shall carry out the work in accordance with the additional Drawings and instructions. 6. Utility Relocation

All temporary utility relocations encountered shall be the responsibility of the Contractor and all labor and materials shall be included in his general expense. All permanent utility relocations listed on the drawings or as directed by the Town shall be paid for by the Town.

7. Test Pits

At locations shown on the plans or designated by the Owner, the Contractor shall excavate and expose existing utilities and other structures prior to start of construction. Elevations and locations and other pertinent data of the exposed utilities and other structures are to be recorded and forwarded to the Owner.

8. Explosives

Explosives shall not be used for rock excavation. 9. Dust Control

Calcium Chloride shall be used as directed. Maximum application shall be at a rate one pound per square yard. Water vehicles may also be used as deemed necessary. The Contractor shall erect temporary dust curtains/walls so that no dust or debris shall enter the adjoining areas.

10. Sanitary Facilities

The Contractor shall provide temporary sanitary facilities for his employees. These facilities shall be cleaned regularly and in all ways comply with the State and Town Health Regulations.

11. Pre-Construction Meeting

The Owner will conduct a pre-construction meeting with the selected Contractor. The purpose of the meeting will be to answer any questions the Contractor may have about

Page 38: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

38

scheduling, the scope of work, the methods of work to be applied, and/or other technical or contractual issues.

12. Construction Meetings

To enable orderly review during progress of the Work and to provide for systematic discussion of problems, the Owner will conduct project meetings throughout the construction period. Persons designated by the Contractor to attend and participate in the project meetings shall have all required authority to commit the Contractor to solutions agreed upon in the project meetings.

13. Quantities

The estimated quantities of work to be done and materials to be furnished under this Contract, are provided only for use in comparing bids and to indicate the approximate total amount of the Contract.

14. Differing Site Conditions A. The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Owner of: 1. Subsurface or latent physical conditions at the site which differ materially from those indicated in this contract, or 2. Unknown physical conditions at the site, of an unusual nature, which

differ materially from those ordinarily encountered and provided for in the Contract.

B. The Owner shall investigate the site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease

in the Contractor's cost of, or the time required for, performing any part of the work under this Contract, whether or not changes as a result of the conditions, an equitable adjustment shall be made under this clause and the contract modified in writing accordingly.

C. No request by the Contractor for an equitable adjustment to the contract under this clause shall be allowed, unless the Contractor has given the written notice required.

D. No request by the Contractor for an equitable adjustment to the Contract for differing site conditions shall be allowed if made after final payment under this contract.

Page 39: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

39

15. Reports The Contractor and each of his subcontractors shall submit to the Town, such schedules of quantities and costs, progress reports, payrolls, estimates, delivery tickets and other data as the Town may request.

16. Eliminated Items

Should any items contained in the proposal be found unnecessary for the proper completion of the contracted work, or if due to over expenditure on other contract items; the Owner may eliminate certain items from the Contract. Such action shall in no way invalidate the Contract and no allowance will be made for such items in making final payment except for such work already completed or materials previously purchased for those items.

17. Work Stoppages

Should the Town be prevented or enjoined from proceeding with work either before or after the start of construction by reason of any litigation or other reason beyond the control of the Town, the Contractor shall not be entitled to or assert claim for damage by reason of said delay. However, time for completion of the work will be extended to such reasonable time as the Town may determine. Such time extension will be set forth in writing.

18. Traffic Control

The Contractor will furnish and pay for traffic control men to direct and control traffic in the immediate construction area. The Contractor will be responsible for maintenance of adequate barricades, signs, and warning systems to protect the job and the traveling public.

Use of uniformed police or traffic control personnel will in no way relieve the Contractor of his responsibility for traffic accidents caused by his failure to provide adequate barricades, signs and warning devices.

19. Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to

be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut.

Page 40: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

40

B. The Contractor shall protect from damage all existing improvements and utilities (1) at or near the work site and (2) on adjacent property of a third party, the

locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the

property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the

Contractor fails or refuses to repair the damage promptly, the Owner may have the necessary work performed and charge the cost to the Contractor.

20. Engineer

The term "Engineer" shall mean the duly authorized representative of the Public Works Department.

21. Progress Payments

On the first of each month but not more than once each month, the Contractor may submit a Request for Payment for work done. The CONTRACTOR shall furnish the OWNER all reasonable facilities required for obtaining the necessary information relative to the progress and execution of the work. He must, if requested by the Owner, submit satisfactory evidence that he has paid in full for all labor, materials, and equipment included in the monthly estimate. The estimates shall be made on forms furnished by the Town and the Contractor shall certify that the estimate is correct and the work performed is in conformity with the plans and specifications.

Within fifteen (15) days from the date of approval of a Request for Payment by the OWNER, the TOWN shall:

A. Pay the Request for Payment as approved less a five percent (5%) retainage.

B. Approve such other amount as he shall decide is due the CONTRACTOR, informing the CONTRACTOR in writing of his reasons for approving the amended amount, or

C. Withhold payment in whole or in part on a approved Request for Payment to the extent necessary to protect itself from loss on account of any of the following causes discovered subsequent to approval of Request for Payment by the OWNER provided he informs the CONTRACTOR in writing of his reasons for withholding payment in whole or in part:

1. Defective work.

2. Evidence indicating the probable filing of claims by other parties against the CONTRACTOR.

Page 41: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

41

3. Failure of the CONTRACTOR to make payments to SUBCONTRACTORS, material suppliers or labor.

4. Damage to another CONTRACTOR.

After completion of the project and acceptance by the Town, the Contractor shall submit an itemized final estimate. No later than six (6) months after acceptance of the final estimate, the Town shall pay the 5% retained, unless, within that time, the materials or workmanship in the project have been found defective. The Contractor agrees that the OWNER may expend the same in making such repairs or replacements of said work as the OWNER may deem expedient upon proper notification in writing to the Contractor.

22. General Guaranty

Neither the final certificate of payment nor any provision in the contract documents, nor partial or entire occupancy of the premises by the Owner, shall constitute an acceptance of work not done in accordance with the contract documents or relieve the Contractor of liability in respect to any express warranties or responsibility for faulty materials or workmanship. The Contractor shall remedy any defects in the work and pay for any damage to other work resulting therefrom. The Owner will give notice of observed defects with reasonable promptness.

23. Daily Clean-Up

Before the completion of each days work, the Contractor shall be responsible for cleaning up and removing or relocating all excavated material, debris, equipment and like and for temporary backfilling or filling excavations as necessary to insure the continuous flow of traffic in roadways where work is progressing including access to private property during non-working hours.

24. Nondiscrimination

Discrimination is prohibited under this contract.

No person in the United States shall, on the ground of race, color, national origin, or sex, be excluded from participation under any program or activity of a recipient government which government receives funds made available under Subtitle A of the State and Local Fiscal Assistance Act of 1972. Any prohibition against discrimination on the basis of age under the Age Discrimination Act of 1975 (hereinafter referred to as discrimination on the basis of age) or with respect to an otherwise qualified handicapped individual as provided in section 504 of the Rehabilitation Act of 1973, (hereinafter referred to as discrimination on the basis of handicapped status) or any prohibition against discrimination on the basis of religion, as well as any exemption from such prohibition as provided in the Civil Rights Act of 1964 or the Civil Rights Act of 1968 (hereinafter referred to as discrimination on the basis of religion) shall also apply to any such program or activity.

Page 42: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

42

All of subpart E of “Regulations governing the Payment of Entitlements under Title I of the State and Local Fiscal Assistance Act of 1972” as Amended by the State and Local Fiscal Assistance Amendments of 1976 applies.

The Town of Groton does not discriminate against individuals with disabilities as provided in the Americans With Disabilities Act (ADA). The Town expects that the vendors and/or contractors with whom it does business will comply with the American With Disabilities Act to the extent required by law. If awarded a contract with the Town, the successful vendor/contractor will be required to sign a statement agreeing to comply with the provisions of ADA.

25. Roadway Closings

In certain cases where deemed necessary for protection of the public, the Groton Director of Public Works MAY officially close a road to vehicular traffic for a specified period of time. Prior to closing any roads in accordance with this paragraph, detours shall be established by the CONTRACTOR, approved by the OWNER, and suitable signs erected. Access to all homes and business shall be maintained at all times for area residents and emergency vehicles.

26. Extra Work

The Contractor shall be responsible for performing any extra work, as requested by the Owner, made necessary by changes in plan or required to fulfill the scope of the project. Such work shall be performed by the Contractor at the unit or lump sum price provided in the Contract.

27. Samples

All samples called for in the Specifications or required by the OWNER shall be furnished by the CONTRACTOR at his expense and shall be submitted to the OWNER for his approval. Samples shall be furnished so as not to delay fabrication, allowing the OWNER reasonable time for the consideration of the samples submitted. CONTRACTOR shall furnish such samples of materials, and workmanship shall be in accordance with approved samples.

28. Quality of Equipment and Materials

A. Everything furnished and provided shall be new, and all materials and equipment shall be of the quality specified. All unspecified materials and equipment shall be equal in grade and quality to specified materials. The CONTRACTOR shall furnish satisfactory evidence as to the kind and quality of all materials. B. In order to establish standards of quality, the OWNER may have, in the detailed Specifications, referred to certain products by name and catalog number. This procedure is not to be construed as eliminating from competition other products of equal or better quality by other manufacturers where fully suitable in design.

Page 43: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

43

C. The CONTRACTOR shall abide by the OWNER'S judgment when proposed substitute materials or items of equipment are judged to be unacceptable and shall furnish the specified materials or items of equipment in such cases. All proposals for substitutions shall be submitted in writing by the General CONTRACTOR and not by individual trades or material suppliers. The OWNER will approve or disapprove proposed substitutions in writing within a reasonable time. No substitute materials shall be used unless approved in writing.

29. Shop or Setting Drawings

The Contractor shall submit promptly to the Owner two copies of each shop or setting drawing prepared in accordance with the schedule predetermined as aforesaid. After examination of such drawings by the Owner and the return thereof, the Contractor shall make such corrections to the drawings as have been indicated and shall furnish the Owner with two corrected copies. If requested by the Owner, the Contractor must furnish additional copies. Regardless of corrections made in, or approval given to, such drawings by the Owner, the Contractor will nevertheless be responsible for the accuracy of such drawings and for their conformity to the Plans and Specifications, unless he notifies the Owner in writing of any deviations at the time he furnishes such drawings.

30. Plans and Specifications at the Site

The Contractor shall maintain at the Work Site, one copy of all Drawings, Specifications, Addenda, approved Shop Drawings, Change Orders and other modifications, Schedules, Instructions, etc. in good order and marked to record all changes made during construction. These shall be available at all times to the Owner or his authorized representatives.

31. Materials, Services, and Facilities

It is understood that except as otherwise specifically stated in the contract documents, the Contractor shall provide and pay for all materials, labor, tools, equipment, water, light, power, transportation, superintendence, temporary construction of every nature, and all other services and facilities of every nature whatsoever necessary to execute, complete, and deliver the work within the specified time.

32. Contractor's Title to Materials

No materials or supplies for the work shall be purchased by the Contractor or by any Subcontractor subject to any chattel mortgage or under a conditional sale contract or other agreement by which an interest is retained by the seller. The Contractor warrants that he has good title to all materials and supplies used by him in the work, free from all liens, claims or encumbrances.

Page 44: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

44

33. Inspection of Construction

A. Definition. "Work" includes, but is not limited to materials, workmanship, and manufacture and fabrication of components.

B. The Contractor shall maintain an adequate inspection system and perform such

inspections as will ensure that the work called for by this contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Town. All work is subject to inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

C. Town inspections and tests are for the sole benefit of the Town and do not:

1. Relieve the Contractor of responsibility for providing adequate quality control measures;

2. Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

3. Constitute or imply acceptance;

D. The presence or absence of a Town inspector does not relieve the Contractor from

any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Owner's written authorization.

34. Inspection and Testing of Materials

A. All materials and equipment used in the construction of the project shall be subject to adequate inspection and testing in accordance with accepted standards. The laboratory or inspection agency shall be selected by the Owner. The Owner will pay for all laboratory inspection service direct, and not as a part of the Contract.

B. Materials of construction, particularly those upon which the strength and

durability of the structure may depend, shall be subject to inspection and testing to establish conformance with specifications and suitability for uses intended.

35. Contractor's Obligations

The Contractor shall and will, in good workmanlike manner, do and perform all work and furnish all supplies and materials, machinery, equipment, facilities and means, except as herein otherwise specified, necessary or proper.

Page 45: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

45

36. Weather Conditions

In the event of temporary suspension of work, or during the inclement weather, or whenever the Owner shall direct, the Contractor will, and will cause his Subcontractors to protect carefully his and their work and materials against damage or injury from the weather. If, in the opinion of the Owner, any work or materials shall have been damaged or injured by reason of failure on the part of the Contractor or any of his Subcontractors so to protect his work, such materials shall be removed and replaced at the expense of the Contractor.

37. Provisions Required By Law Deemed Inserted

Each and every provision of law and clause required by law to be inserted in this Contract shall be deemed to be inserted herein and the Contract shall be read and enforced as though it were included herein, and if, through mistake or otherwise, any such provision is not inserted, or is not correctly inserted, then upon the application of either party the contract shall forthwith be physically amended to make such insertion or correction.

38. Right of the Owner to Terminate Contract

In the event that any of the provisions of this contract are violated by the Contractor, or by any of his subcontractors, the Owner may serve written notice upon the Contractor and the Surety of its intention to terminate the Contract, such notices to contain the reasons for such intention to terminate the contract, and unless within (10) days after the serving of such notice upon the Contractor, such violation or delay shall cease and satisfactory arrangement of correction to be made, the contract shall, upon the expiration of said ten (10) days, cease and terminate. In the event of any such termination, the Owner shall immediately serve notice thereof upon the Surety and the Contractor and the Surety shall have the right to take over and perform the contract; provided, however, that if the Surety does not commence performance thereof within ten (10) days from the date of the mailing to such Surety of notice of termination, the Owner may take over the work and prosecute the same to completion by contract or by force account for the account and at the expense of the Contractor and the Contractor and his Surety shall be liable to the Owner for any excess cost occasioned the Owner thereby; and in such event the Owner may take possession of and utilize in completing the work, such materials, appliances, and plant as may be on the site of the work and necessary therefore.

In the event of such termination, the OWNER may take possession of the work and of all materials, tools and equipment thereon and may finish the work by whatever method and means he may select. The CONTRACTOR shall consider it default whenever he shall:

A. Declare bankruptcy, become insolvent, or assign his assets for the benefit of his

creditors.

B. Disregard or violate important provisions of the Contract Documents or OWNER'S instructions, or fail to prosecute the work according to the agreed Schedule of Completion including extensions thereof.

Page 46: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

46

C. Fail to provide a qualified superintendent, competent workmen or SUBCONTRACTORS, or proper materials, or fail to make prompt payment thereof.

If the right of the CONTRACTOR to proceed is so terminated, the OWNER may take possession of and utilize in completing the work such materials, appliances, supplies, plant and equipment as may be on the site of the work, and necessary therefor. Upon termination of the CONTRACT by the OWNER, no further payments shall be due the CONTRACTOR until the work is completed. If the unpaid balance of the Contract Amount shall exceed the cost of completing the work including all overhead costs and damages resulting from delay, the excess shall be paid to the CONTRACTOR.

If the cost of completing the work shall exceed the unpaid balance, the CONTRACTOR and his sureties shall pay the difference to the OWNER.

39. Acceptance of Final Payment Constitutes Release

The acceptance by the Contractor of final payment shall be and shall operate as a release to the Owner of all claims and all liability to the Contractor for all things done or furnished in connection with his work and for every act and neglect of the Owner and others relating to or arising out of this work. No payment, however, final or otherwise, shall operate to release the Contractor or his sureties from any obligations under this contract or the Performance and Payment Bond.

40. Assignments

The Contractor shall not assign the whole or any part of this contract or any moneys due or to become due hereunder without written consent of the Owner. In case the Contractor, with the consent of the Owner, assigns all or any part of any moneys due or to become due under this contract, the instrument of assignment shall contain a clause substantial to the effect that it is agreed that the right of the assignee in and to any moneys due or to become due to the Contractor shall be subject to prior claims of all persons, firms and corporations of services rendered or materials supplied for the performance of the work called for in this contract.

41. Codes, Regulations and Issue Date of Standard Specifications

Where standard specifications, codes, regulations and similar publications of governmental agencies, technical societies, manufacturer's associations and regulatory groups or bureaus are referred to in these Specifications, the applicable portion thereof shall be of the same effect as if fully printed herein, and the work done in full accordance therewith. The edition current as of the date of issue of this Specification shall be used except where publication date is specifically stated.

Page 47: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

47

42. Emergency Telephone Number

The CONTRACTOR is required to provide the OWNER with a telephone number, which can be used during emergencies, 24 hours per day, seven days per week, to reach the CONTRACTOR.

43. Other Contracts The Town may undertake or award other contracts for additional work at or near the site of the work under this contract. The Contractor shall fully cooperate with the other contractors and with Town employees and shall carefully adapt scheduling and performing the work under this contract to accommodate the additional work, heeding any direction that may be provided by the Owner. The Contractor shall not commit or permit any action that will interfere with the performance of work by any other contractor or by Town employees.

44. The Owner's Duties and Rights

A. The OWNER will provide the lands shown on the Drawings upon which the work under the CONTRACT is to be performed and to be used for rights-of-way for access. Any delay in furnishing these lands by the OWNER shall be deemed proper cause for adjustment in the Contract Amount and in time of completion.

B. The OWNER shall have the right to suspend the work or any portion thereof at

any time provided that he gives the CONTRACTOR five (5) days written notice of suspension which shall set forth the date on which work is to be resumed. The CONTRACTOR shall resume the work upon written notice from the OWNER and within ten (10) days after the date set forth in the notice of suspension. If the OWNER does not give written notice to resume work within ten (10) days of the date fixed in the notice of suspension, the CONTRACTOR may abandon that portion of the work so suspended and shall be entitled to payment for all work done on the portions so abandoned, plus 15 percent of the value of the abandoned work to compensate for overhead, plant expense, and anticipated profit.

C. The OWNER shall have the authority to suspend the work, wholly or in part, for

such period or periods, as may be deemed necessary, due to unsuitable weather, or such other conditions as are considered unfavorable for prosecution of the work, or failure on the part of the CONTRACTOR to carry out the provisions of the CONTRACT or to supply materials meeting the requirements of the Specifications. The CONTRACTOR shall not suspend operations due to unsuitable weather without the OWNER'S permission.

D. The OWNER shall have the right to correct any deficiencies, without prejudice to

any other remedy he may have, upon failure of the CONTRACTOR to perform the work in accordance with the Contract Documents, including any requirements with respect to the Schedule of Completion, after five (5) days written notice to

Page 48: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

48

the CONTRACTOR. The cost of the work so performed by the OWNER shall be paid for by the CONTRACTOR.

E. The OWNER shall have the authority to direct the CONTRACTOR not to correct

work that has been damaged, or that was not performed in accordance with the Contract Documents. An equitable deduction from the Contract Amount shall be made to compensate the OWNER for the uncorrected work.

F. The OWNER shall have the right to order changes in the work through additions,

deletions or modifications without invalidating the CONTRACT.

G. The OWNER shall have the right to take possession of and use any completed or partially completed portions of the work, not withstanding that the time for completing the entire work or such portions may not have expired; but such taking possession and use shall not be deemed an acceptance of any work not completed in accordance with the Contract Documents. If such prior use increases the cost of or delays the completion of uncompleted work or causes refinishing of completed work, the CONTRACTOR shall be entitled to such extra compensation, or extension of time or both, as the OWNER may determine.

45. Wage Rates

It has been estimated that the cost of this project is less than $100,000.00, and under Section 31-53 of the State Statutes, as amended, State Prevailing Wage Rates do not apply. For this reason, State Wage Rates are not included.

However, should a Contractor's bid exceed the $100,000.00 threshold, it shall be incumbent upon the Contractor to include the applicable prevailing wage rates in the submittal of the bid. In the case where add alternates are part of the bid, and where acceptance of any alternates would cause the contract sum to exceed the $100,000 threshold, then the price of the alternate shall include the applicable prevailing wage rate for the entire project.

46. Contract Bid Breakdown (Lump Sum)

The Contractor shall furnish a breakdown of each lump sum bid within 10 days after date of award of contract. Partial payments will be based on this breakdown. The Contractor's breakdown will be reviewed by the OWNER to insure that costs are proportioned properly between early and late pay items. Any unbalanced items or other discrepancies will be revised by the OWNER and the approved breakdown will be utilized as a basis for progress payment to the Contractor.

47. Hours of Work

Any work necessary to be performed after regular working hours, on Sundays or Legal Holidays, shall be performed without additional expense to the Owner.

Page 49: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

49

48. Waste Disposal

The Contractor shall be responsible for the cost and legal disposal of all construction debris, municipal solid waste, stumps, and excess materials.

The Contractor shall legally dispose of any hazardous materials at approved sites at his own expense.

END OF SECTION

Page 50: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

50

SUPPLEMENTARY CONDITIONS

1. Insurance Requirements

2. Worker's Compensation Provision

3. Indemnification

4. Enumeration of Contract Drawings, Specifications, Appendices and Addenda

5. Lock-Out Tag-Out Standard

6. Hazard Communication 7. Permits

Page 51: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

51

1. Insurance Requirements

Insurance shall be written with carriers approved in the State of Connecticut and with a minimum AM Best’s Rating of “A-“VIII. In addition, all carriers are subject to approval by the Town of Groton and no coverage shall contain special limitations on the scope of protection afforded to the Town, its officers, officials, employees or volunteers. The Town of Groton shall be named as an Additional Insured on a primary and non-contributory basis to all policies except Workers Compensation. All policies should also include a waiver of subrogation. General Liability (Minimum Limits) Each Occurrence $1,000,000 General Aggregate $3,000,000 Products/Completed operations Aggregate $3,000,000 -Policy must contain no exclusion for Explosion. Collapse and underground Hazard (XC & U) -Contractor must notify the Town whenever claims Reduce the General Aggregate below $1,000,000 -The Town should be notified if the Aggregate limits Include defense costs Auto Liability Combined Single Limit Each Accident $1,000,000 Umbrella (Excess Each Occurrence $1,000,000 Liability) Aggregate $1,000,000 Workers Compensation WC Statutory Limits Employers Liability EL Each Accident $1,000,000 EL Disease Each Employee $1,000,000 EL Disease Policy Limit $1,000,000 For Contractors: (Should a Contractor be involved in operations requiring coverage under special State or Federal Acts Such as Maritime or Railroad, the Contractor must provide evidence of this coverage. Should a Contractor be exempt from the Workers Compensation Laws of the State of Connecticut, or any other State or Federal requirements, evidence of such exemption must be provided and a “Hold-Harmless” agreement provided in language satisfactory to the Town, holding it harmless in the event of any claim for injury or damages. Contractors based out-of-state must provide evidence that their Workers Compensation policy will cover injuries/illness sustained while working in the State of Connecticut. The Contractor is responsible for ensuring that all of its subcontractors carry Workers Compensation Insurance, as described above.

Page 52: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

52

If any policy is written on a “Claims Made” basis, the policy must be continually renewed for a minimum of three (3) years from the completion date of this contract. If the policy is replaced and/or the retroactive date is changed, then the expiring policy must be endorsed to extend the reporting period for claims for the policy in effect during the contract for three (3) years from completion date. Original, completed Certificates of Insurance must be presented to the Town of Groton Public Works prior to purchase order/contract issuance. Contractor agrees to provide replacements/renewal certificates at least 60 days prior to the expiration of any policy. Should any of the above described policies be cancelled before the expiration date, written notice must be made to the Town thirty (30) days prior to cancellation).

2. Worker's Compensation Provision

Before entering into the contract for the project, the successful bidder must comply with all aspects of State Statute 31-286a, including providing the Town with a current statement from the State Treasurer that, to the best of his knowledge and belief as of the date of the statement, the Contractor or any of his Subcontractors was not liable to the State for any Worker's Compensation payments made pursuant to Section 31-355 of the General Statutes.

Contract documents will not be signed until the statement has been received by the Town from the State Treasurer.

3. Indemnification

The Contractor will indemnify and hold harmless the Owner (Town of Groton) and the Engineer and their agents and employees from and against all claims, damages, losses and expenses including attorney's fees arising out of or resulting from the performance of the work, provided that any such claims, damage, loss or expense is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property including the loss of use resulting therefrom. The Contractor, subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable will be held responsible for any type of pollution and/or environmental impairment into or upon land, the atmosphere or any course or body of water that is above or below ground; and is caused in whole or in part by any negligent or willful or wanton act or omission of any of the above stated individuals or group of individuals. The Contractor, Subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable will be held responsible for acts that are outside of the contract specifications and without the supervision or direction of the Town, its architects, and engineers. These same individuals or group of individuals will also be held responsible for the misuse or malfunction of any equipment rented, owned or leased by any of these individuals or groups of individuals that would create any type of pollution or environmental damage.

The owner assumes no responsibility or liability arising from loss or damage to Contractor's equipment, materials or supplies.

Page 53: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

53

4. Enumeration of Contract Drawing, Specifications, Appendices and Addenda

The following are the contract drawings, specifications, appendices and addenda which form a part of this contract as set forth in paragraph 5 of the General Conditions. Specifications

Specifications and Bid Form for “SIDEWALK AND RAMP RECONSTRUCTION, VARIOUS LOCATIONS ”

Information for Bidders Bid Proposal General Conditions Supplementary Conditions Technical Specifications

Addenda

None

Plans

“SIDEWALK AND RAMP RECONSTRUCTION, VARIOUS LOCATIONS ” prepared by “Town of Groton Public Works Department, Engineering Division”, sheets: 1. Cover Sheet 2. Poquonnock Park Entrance Site Plan 3. Gravel Street at Clift Street Site Plan 4. High Street at Academy Lane Site Plan 5. Details and Notes 6. Details

5. Lock-Out Tag-Out Standard

The Town of Groton requires that any Contractor that maintains or is hired to work on any Town equipment, abide by the OSHA "Lock-Out Tag-Out" standard. The Contractor must provide his workers with locks, hasps and keys approved by OSHA for the proper locking and tagging out of equipment from its power source according to the OSHA standard. The Town of Groton is not responsible for providing the Contractor with the locks and hasps. The Contractor is responsible for complying with this standard and assuring that all of his employees comply with it while working on Town of Groton equipment. The Town requires that any Contractor's equipment brought on to Town property by the Contractor be properly locked or tagged out from its power source in accordance with the OSHA standard.

Page 54: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

54

6. Hazard Communication

The Town of Groton requires that any vendor or Contractor using hazardous materials, or any material that would fall under the OSHA "Right to Know" standard, provide a list to the Town of Groton of those materials that will be used while on Town property, as well as the material safety data sheets for those products. Conversely, the Town of Groton shall inform the Contractor of where the "Employee Right to Know" station is in the area where they are working so that the Contractor's employees can be aware of any substances that they may encounter while working within the Town of Groton workplace.

7. Permits

The contractor is required to obtain all necessary permits from the Connecticut Department of Transportation (CT DOT) for work within the State’s right of way. The Contractor is required to schedule and coordinate all required inspections and pay all applicable fees. The Contractor shall fill out the CT DOT’s “Application for Review of Encroachment Permit” form and submit to the Engineer for review prior to submitting to the CT DOT. CT DOT’s “Application for Review of Encroachment Permit” is included with this bid specification.

END OF SECTION

Page 55: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

55

TOWN OF GROTON

SIDEWALK AND RAMP RECONSTRUCTION, VARIOUS LOCATIONS

TECHNICAL SPECIFICATIONS

TABLE OF CONTENTS

SECTION DESCRIPTION…………………………………………..NUMBER OF PAGES

01010 Summary of Work……………………………………….…………………….. 2

01025 Measurement & Payment …………...…………………….………………….. 1

01040 Coordination and Meetings ……………...……………………………….…... 2

01070 Definitions and Standards ……………………………………………………. 4

01300 Submittals …………………………………………………………………...... 6

01400 Quality Control …………………………………………………………...…… 2

01410 Testing Laboratory Services ……………………………………………...…… 3

01500 Construction Facilities and Temporary Controls …………………………….. 5

01505 Mobilization…………………………………………………………………… 2

01570 Maintenance and Protection of Traffic ……………………………..…………. 4

01571 Traffic Directors …………………………………………………………...…... 5

02230 Excavating, Backfilling and Compacting for Sidewalks, Curbing, Driveway

Aprons and Roadway Repair …………………………………………………... 8

02240 Subgrade ……………………………………………………………………….. 5

02241 Bank Run Gravel Subbase …………………………………………………….. 4

02242 Processed Gravel …………………………………………………………...….. 4

02275 Erosion Control …………………..…………………………………………… 4

02511 Bituminous Concrete Paving ………………………………………………….. 7

02514 Bituminous Concrete Curbing ………………………………………………… 4

02515 Bituminous Concrete Sidewalks ………………………………………………. 5

02518 Sawcut and Seal Bituminous Concrete ……………………………..…………. 2

02520 Concrete Sidewalks …………………………………………………………..... 4

02521 Concrete Curbing …………………………………………………………...….. 5

02522 Integral Concrete Sidewalks, Curbs and Driveway Aprons ............................... 5

02920 Topsoil ……………………………………………...…………………………. 4

02930 Lawns and Grasses ………………………………...………………………….. 6

Page 56: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

Fee: (for DOT use) # $ Rec'd:

DISTRICT 1 (1107 Cromwell Avenue, Rocky Hill, CT 06067) DISTRICT 3 (140 Pond Lily Avenue, New Haven, CT 06515) (860) 258-4544 (203) 389-3000

DISTRICT 2 (171 Salem Turnpike, Norwich, CT 06360) DISTRICT 4 (359 South Main Street, Thomaston, CT 06787) (860) 823-3230 (203) 591-3627

Date: APPLICATION FOR REVIEW OF ENCROACHMENT PERMIT The attached check list is to be included with and considered part of the application.

(PLEASE FILL OUT COMPLETELY. NOTE: ORIGINAL SIGNATURE OF OWNER REQUIRED - BLUE INK)

Description of Project:

Location: (complete street address, if none, provide map/block/lot information and provide plan(s) as needed)

Town and Zip Code:

Planning and Zoning Approval:

Date Received: Date Expected: Not Required:

Property Owner’s Name as noted in the Municipal Land Records: (If there is more than one land owner, a separate application page shall be shown for each)

Street Address:

Town, State, & Zip Code:

Telephone: Mobile Number:

Email:

Developer/Applicant/Representative’s Name (if different from Owner):

Street Address:

Town, State, & Zip Code:

Telephone: Mobile Number:

Email:

By signing this form, the owner indicates that the authorized representative designated below is conferred general authority to act on behalf of the owner/developer with respect to all matters arising from the review of this application.

Property Owner’s Signature (Original/Blue Ink) Developer/Applicant/Representative’s Signature (Original)

Property Owner’s Name Developer/Applicant/Representative’s Name (Typed)

S T A T E O F C O N N E C T I C U T DEPARTMENT OF TRANSPORTATION BUREAU OF HIGHWAY OPERATIONS AND

MAINTENANCE

FOR COMMERCIAL PROPOSALS ONLY

Proposed Gross Floor Area (GSF) and Land Use: Total Parking Spaces:

Developer/Applicant/Representative’s Title

□□□□

*A

decastrojs
Text Box
PMT-1 Rev.10/18
Page 57: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

Name of Surety Company:

Bond Amount: Required Amount for Job: Bond #:

Name of Party to whom Bond is Issued:

Phone Number:

Insurance Policy Number: Expiration:

Name of Party to whom Insurance is Issued:

Phone Number:

In evaluating this application, the Office of Maintenance will rely on the information provided by the applicant. If such

information subsequently proves to be false, deceptive, incomplete, and/or inaccurate, the Department reserves the right to

deny the reviewed application and require a resubmission.

OSTA TRAFFIC DRAINAGE PDU DISTRICT PUBLIC TRANS. OTHER □ □□ □ □ □□

Page 58: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

01010/1-2

SECTION 01010

SUMMARY OF WORK

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Project/Work Identification

B. Work Covered by Contract Documents

C. Work by Owner

D. Contractor Use of Premises, Work Sequence, and Owner Occupancy

1.02 PROJECT/WORK IDENTIFICATION

A. The name of the Project is "SIDEWALK AND RAMP RECONSTRUCTION,

VARIOUS LOCATIONS", and is located in Groton, Connecticut. The work of this

Contract has been identified in the Contract Documents by the Town of Groton Public

Works Engineering Division by the Contract number 20-08.

1.03 WORK COVERED BY CONTRACT DOCUMENTS

A. Briefly and without force and effect upon Contract Documents, the work of the

Contract can be summarized as follows:

1. Site Work: Sidewalk and ramp reconstruction in various locations in the

Town of Groton, CT as shown on the contract drawings.

1.04 WORK BY OWNER

A. Work of the Project which will be executed during Work of this Contract, and

which is specifically excluded from this Contract are as follows:

1. None.

Page 59: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

01010/2-2

1.05 CONTRACTOR USE OF PREMISES, WORK SEQUENCE, AND OWNER

OCCUPANCY

A. Contractor shall have use of the site for Work, storage, and access. Under no

conditions, shall roads be blocked.

B. Assume full responsibility for protection and safekeeping of products under this

Contract.

C. Obtain and pay for use of additional storage or work areas needed for operations

under this Contract.

D. Coordinate the Progress Schedule and operations with the Town and the Engineer.

E. Cooperate with the Town and the Engineer in scheduling operations to minimize

conflict and to facilitate Owner usage. Provide any and all temporary measures to

ensure the safety of the Town and the Town's representatives.

F. In particular, the Contractor is not to disrupt existing utility service, interfere with

normal school bus, auto, and pedestrian traffic, or obstruct existing exits and life

safety systems, including access to private driveways.

END OF SECTION

Page 60: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

01025/1-1

SECTION 01025

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Measurement

B. Payment

1.02 UNIT PRICE CONTRACT

A. Measurement

1. Prior to submitting payment requisition, Contractor shall measure all

applicable items.

2. Quantity measurement and limits shall be as specified in each appropriate

section.

3. Town construction inspector shall witness and verify all unit

measurements.

4. Town survey crews may be utilized when necessary to measure or verify

quantities.

5. Measure only completed work, or materials stored on site, for the period

payment is requested for.

6. Lump sum bid items shall be measured based on a percentage of the work

completed.

B. Payment

1. Submit payment requisitions in accordance with the General Conditions of

the specifications.

2. Payment shall only be made for the actual measured quantity of each item

completed, or materials stored on site, for the payment period.

END OF SECTION

Page 61: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

01040/1-2

SECTION 01040

COORDINATION AND MEETINGS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Coordination

B. Preconstruction Meeting

C. Progress Meetings

1.02 COORDINATION

A. Coordinate scheduling, submittals, and Work of the various Sections of

specifications to assure efficient and orderly sequence of installation of

interdependent construction elements.

B. Coordinate work of various Sections having interdependent responsibilities for

installing, connecting to, and placing in service, such equipment.

C. Coordinate completion and clean up of Work of separate Sections in preparation

for Substantial Completion and for portions of Work designated for Towns partial

occupancy.

D. During Town use of premises, coordinate access to site for correction of defective

Work and work not in accordance with Contract Documents, to minimize

disruption of Town's use of premises.

1.03 PRECONSTRUCTION MEETING

A. The Engineer will administer preconstruction conference for execution of Town-

Contractor Agreement and exchange of preliminary submittals.

B. Attendance: Town, Engineer, and his Consultants, and General Contractor.

C. Suggested Agenda:

1. Submission of executed bonds and insurance certificates

2. Signing of Contract Documents

Page 62: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

01040/2-2

3. Submission of list of proposed subcontractors, list of proposed products,

Schedule of Values, and progress schedule.

4. Procedures and processing of field decisions, submittals, substitutions,

applications for payments, proposal requests, Change Orders, and

Contract Close-out procedures.

5. Critical work sequencing.

6. Major equipment deliveries and priorities.

1.04 PROGRESS MEETINGS

A. General Contractor shall schedule and administer Project meetings throughout

progress of the Work at intervals as required by the Town.

B. Make physical arrangements for meetings, prepare agenda with copies for

participants, preside at meetings, record minutes, and distribute copies within two

days to Engineer, participants, and those affected by decisions made at meetings.

C. Attendance: Job superintendent, contractors, major subcontractors, suppliers,

Town and Engineer as appropriate to agenda topics for each meeting.

D. Minimum Agenda

1. Approval of minutes of previous meetings

2. Review of Work progress

3. Field observations, problems, and decisions

4. Identification of problems which impede planned progress

5. Review of submittals schedule and status of submittals

6. Review of off-site fabrication and delivery schedules

7. Maintenance of progress schedule

8. Corrective measures to regain projected schedules

9. Planned progress during succeeding work period

10. Coordination of projected progress

11. Maintenance of quality and work standards

12. Effect of proposed changes on progress schedule and coordination

13. Other business relating to Work

END OF SECTION

Page 63: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

SECTION 01070

DEFINITIONS AND STANDARDS

PART I GENERAL

1.01 SECTION INCLUDES

A. Definitions

B. Specification Format and Explanations

C. Industry Standards

1.02 DEFINITIONS

Definitions and explanations of this section are not necessarily either complete or

exclusive, but are general for the work to the extent not stated more

explicitly in another provision of the contract documents.

A. General Requirements: Apply to entire work of Contract and, where so

indicated, to other elements of work which are included in the project.

B. Indicated: The term "indicated" refers to graphic representations, notes or

schedules on the drawings, to other paragraphs or schedules in the

specifications, and to similar requirements in the contract documents.

Where terms such as "shown", "noted", "scheduled", and "specified" are

used, it is to help reference, and no limitation of location is intended

except as specifically noted.

C. Directed, Requested, etc.: Where not otherwise explained, terms such as

"directed", "requested", "authorized", "selected", "approved", "required",

"accepted", and "permitted" mean "directed by Engineer", "requested by

Engineer", etc. However, no implied meaning will be interpreted to

extend Engineer's responsibility into Contractor's area of construction

supervision.

D. Approve: Where used in conjunction with Engineer's response to the

Contractor's submittals, requests, applications, inquiries, reports and

claims, the meaning of the term "approved" is limited to the Engineer's

responsibilities and duties as specified in General and supplementary

Conditions. In no case will "approval" by Engineer be interpreted as a

release of Contractor from responsibilities to fulfill requirements of the

Contract Documents.

E. Project Site: The space available to Contractor for performance of the

work, either exclusively or in conjunction with others performing other

work as part of the Project. The extent of Project Site is shown on the

drawings, and may or may not be identical with description of the land

upon which project is to be built.

01070/1-4

Page 64: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

F. Furnish: Except as otherwise defined in greater detail, the term "furnish"

is used to mean "supply and deliver to project site, ready for unloading,

unpacking, assembly, installation, etc.", as applicable in each instance.

G. Install: Except as otherwise defined in greater detail, the term "install" is

used to describe operations at project site including "unloading",

unpacking, assembly, erection, placing, anchoring, applying, working to

dimension, finishing, curing, protecting, cleaning and similar operations",

as applicable in each instance.

H. Provide: Except as otherwise defined in greater detail, the term "provide"

means "furnish and install at said party's expense, complete and ready for

intended use", as applicable in each instance. All items specified shall be

"provided" unless specifically noted otherwise.

I. Installer: An "Installer" is an entity engaged by the Contractor, either as an

employee, subcontractor or sub-contractor for performance of a particular

construction activity, including installation, erection, application and

similar operations. Installers are required to be experienced in the

operations they are engaged to perform.

J. Regulation: The term "Regulations" includes laws, statutes, ordinances

and lawful orders used by authorities having jurisdiction, as well as rules,

conventions and agreements within the construction industry that control

performance of the Work, whether they are lawfully imposed by

authorities having jurisdiction or not.

K. Testing Laboratories: A "testing laboratory" is an independent entity

engaged to perform specific inspections or tests, either at the Project Site

or elsewhere, and to report on, and, if required, to interpret, results of

those inspections or tests.

1.03 FORMAT AND SPECIFICATION EXPLANATIONS

This Article is provided to help the user of these Specifications understand the format,

language, implied requirements, and similar conventions. None of the explanations shall

be interpreted to modify the substance of Contract requirements.

A. Specifications Format: These Specifications are organized into Divisions,

Sections or Trade Headings based on the Construction Specifications Institute's

16-Division format and the SPECTEXT numbering system. This organization

conforms generally to recognized construction industry practice. The section

titles are not intended to limit meaning or content of the section, or to be fully

descriptive of requirements specified therein, nor to be an integral part of text

which specifies requirements.

01070/2-4

Page 65: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

B. Specification Content: This Specification has been produced employing

conventions in the use of language and the intended meaning of certain terms,

words, and phrases when used in particular situations or circumstances. These

conventions are explained as follows:

1. Language used in the Specifications and other Contract Documents is the

abbreviated type. Implied words and meanings will be appropriately

interpreted. Singular words will be interpreted as plural and plural words

interpreted as singular where applicable and where the full context of the

Contract Documents so indicates.

2. Imperative Language is used generally in the Specifications.

Requirements expressed imperatively are to be performed by the

Contractor. At certain locations in the text, for clarity, subjective language

is used to describe responsibilities, which must be fulfilled indirectly by

the Contractor, or by others when so noted. The words "shall be" shall be

included by inference where a colon (:) is used within sentences or

phrases.

C. Assignment of Specialists: The Specification requires that certain specific

construction activities shall be performed by specialists who are recognized

experts in the operations to be performed. The specialists must be engaged for

those activities, and the assignments are requirements over which the Contractor

has no choice or option. Nevertheless, the ultimate responsibility remains with

the Contractor.

1. This requirement shall not be interpreted to conflict with enforcement of

building codes and similar regulations governing the Work. It is

also not intended to interfere with local trade union jurisdictional

settlements and similar conventions.

2. Trades: Use of titles such as "carpentry" is not intended to imply that

certain construction activities must be performed by accredited or

unionized individuals of a corresponding generic name, such as

"carpenter".

It also does not imply that requirements specified apply exclusively to

tradepersons of the corresponding generic name.

D. Graphic Legends, Graphic Symbols and Abbreviations: As used on the Drawings,

are generally those recognized in the construction industry for the purposes

indicated.

01070/3-4

Page 66: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

E. Mechanical/Electrical Drawings: Graphic symbols used on mechanical and

electrical Drawings are generally aligned with symbols recommended by

ASHRAE. Where appropriate, they are supplemented by more specific

symbols recommended by technical associations including ASME, ASPE, IEEE

and similar organizations. Refer instances of uncertainty to the Engineer for

clarification before proceeding.

1.04 INDUSTRY STANDARDS

A. Applicable standards of construction industry have same force and effect and are

made a part of contract documents by reference as if copied directly into

contract documents, or as if published copies were bound herewith.

B. Reference standards (referenced directly in contract documents or by governing

regulations) take precedence over unreferenced standards, which are recognized in

industry as applicable to the work.

C. Unreferenced standards recognized in the construction industry are hereby

defined, except as otherwise limited in contract documents, to have direct

applicability to the work, and will be so enforced for performance of the work.

D. Publication Dates: Except as otherwise indicated, where compliance with an

industry standard is required, comply with the latest edition and revisions thereof,

if any, in effect as of date of execution of the contract.

E. Copies of Standards: Provide where needed for proper performance of the work;

obtain directly from publication sources.

F. Abbreviations and Names: Where acronyms or abbreviations are used in

specifications or other contract documents, they are defined to mean the industry-

recognized name of trade associations, standards generating organization,

governing authority or other entity applicable to context of text provision. Refer

to "Encyclopedia of Associations", published by Gale Research Company,

available in large libraries.

END OF SECTION

01070/4-4

Page 67: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

01300/1-6

SECTION 01300

SUBMITTALS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Submittal Procedures

B. Construction Progress Schedules

C. Proposed Products List

D. Shop Drawings

E. Product Data

F. Samples

G. Manufacturer's Instructions

H. Manufacturer's Certificates

1.02 SUBMITTAL PROCEDURES

A. Review submittals prior to submission. Verify field measurements, catalog

numbers and other information critical to construction or installation. Coordinate

each submittal with requirements of Work and of Contract Documents.

B. Notify Engineer in writing at time of submission of deviations in submittals from

requirements of Contract Documents. Responsibility for deviations from

requirements of Contract Documents is not relieved by Engineer's review of

submittals, except when given written acceptance of specific deviation.

C. Transmit each submittal with Engineer accepted form.

D. Identify Project, Contractor, Sub-contractor or supplier; pertinent Drawing sheet

and detail number(s), and specification Section number, as appropriate.

E. Apply Contractor's stamp, signed or initialed, certifying that review, verification

of Products required, field dimensions, adjacent construction Work, and

coordination of information, is in accordance with the requirements of the Work

and Contract Documents.

Page 68: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

01300/2-6

F. Schedule submittals in accordance with approved project schedule so as to cause

no delay to the Work. Deliver to Engineer at his business address or email.

Coordinate submission of related items.

G. Identify variations from Contract Documents and Product or system limitations

which may be detrimental to successful performance of the completed Work.

H. Provide space for Contractor review stamp and a 3"x5" Engineer review stamp.

I. Obtain new samples, revise drawings and/or data as required by Engineer review

and resubmit, identify changes made since previous submittal.

J. Engineer will review shop drawings, product data, and samples and return

submittals. The Engineer's stamp will read as follows:

1. Approved: Means that fabrication, manufacture or construction may

proceed, providing submittal complies with Contract Documents.

Contractor assumes sole responsibility for the required compliance. No

response is required of the Contractor.

2. Approved as Noted - Resubmission Not Required: Means that fabrication,

manufacture or construction may proceed, provided the submittal is

amended to comply with the Engineer's notations and the Contract

Documents.

3. Approved as Noted - Resubmission Required: The Contractor will

"resubmit" Shop Drawings or "Confirm" in writing that he will amend the

Shop Drawings.

4. Comments Attached or See Accompanying Letter: Means that fabrication,

manufacture or construction may proceed provided the Contractor

complies with the comments attached. Engineer's comments may help to

further clarify contract documents or make required selections such as

color or finish desired. The Contractor shall "resubmit" Shop Drawings or

"Confirm" in writing that he will comply with Engineer's comments if so

marked on the Shop Drawing Review Stamp. If for any reason the

Contractor cannot comply with comments attached, the Contractor shall

notify Engineer before fabrication, manufacture, or construction.

5. Disapproval or Rejected: Means that submittal does not comply with

Contract Documents, and that fabrication, manufacture, or construction as

submitted must not proceed under any circumstances. Submittals stamped

"Rejected" are not permitted on job site.

Page 69: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

01300/3-6

K. Distribute copies of reviewed submittals to concerned persons including Test Lab,

Special Inspector, Building Official, and Clerk of the Works (Construction

Inspector). Instruct recipients to promptly report any inability to comply with

provisions.

L. Begin no work which requires submittals until return of submittals with

Engineer's review stamp and initials or signature indicating review and

distribution to concerned persons.

1.03 CONSTRUCTION PROGRESS SCHEDULES

A. Submit initial progress schedule and schedule of values (if lump sum project) in

duplicate within 15 days after date established for commencement of work. After

review by Engineer, revise and resubmit as required. Submit revised schedules

with every Application for Payment, reflecting changes since previous submittal.

B. Comply with progress schedule for submittals related to Work progress.

Coordinate submittal of related items.

C. Show complete sequence of construction by activity, identifying Work of separate

stages and other logically-grouped activities. Show projected percentage of

completion for each item of Work as of time of each Application for Progress

Payment.

D. Show submittal dates required for Shop Drawings, product data, and samples, and

product delivery dates, including those furnished by Owner and those under

Allowances.

1.04 PROPOSED PRODUCT LIST

A. Within 15 days after date of Notice to Proceed, submit complete list of major

products proposed for use, with name of manufacturer, trade name, and model

number of each product.

B. For products specified only by reference standards, give manufacturer, trade

name, model or catalog designation, and reference standards.

1.05 SHOP DRAWINGS

A. Shop Drawings include specially-prepared technical data for this project,

including Drawings, diagrams, performance curves, data sheets, schedules,

templates, patterns, reports, calculations, instructions, measurements and similar

information not in standard printed form for general application to several

projects.

Page 70: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

01300/4-6

B. Provide newly-prepared information, on reproducible sheets, with graphic

information at accurate scale (except as otherwise indicated), with name of

preparer indicated (firm name). Maximum sheet size shall be 24 in. x 36 in.

Show dimensions and note which are based on field measurement. Identify

materials and products in the work shown. Indicate compliance with standards

and special coordination requirements.

Identify details by reference to sheet numbers shown on Contract Drawings and

Specification Sections, page numbers and paragraph line numbers. Contract

Design Drawings shall not be traced or otherwise reproduced for use as Shop

Drawings.

C. Submit 1 reproducible mylar and 3 opaque reproductions of newly prepared Shop

Drawings to Engineer. Where design calculations are required, submit 3 copies.

D. Do not allow Shop Drawing copies without appropriate approval markings by

Engineer to be used in connection with the Work.

E. Indicate on shop drawing whether it is a full or partial submittal.

F. Fabrication and installation of components requiring Shop Drawings shall not

begin until Shop Drawings have approval of Engineer unless directed otherwise in

writing by same.

1.06 PRODUCT DATA

A. Product data includes standard printed information on materials, products and

systems; not specially prepared for this project, other than the designation of

selections from among available choices printed therein.

B. Collect required data into one submittal for each unit of Work or system; and

clearly mark each copy to show which choices and options are applicable to the

project. Include manufacturer's standard printed recommendations for application

and use, compliance with standards, application of labels and seals, notation of

field measurements which have been checked, special coordination requirements,

instructions for delivery, storage, assembly, installation, adjusting and finishing.

C. Submit 4 copies of product data of which one will be retained by the Engineer.

1.07 SAMPLES

A. Samples include both fabricated and unfabricated physical examples of materials,

products and units of Work; both as complete units and as smaller portions of

units of Work; either for limited visual inspection or (where indicated) for more

detailed testing and analysis.

Page 71: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

01300/5-6

B. Provide units identical with final condition of proposed materials or products for

the Work. Include "range" samples (not less than 3 units) where unavoidable

variations must be expected, and describe or identify variations between units of

each set. Provide full set of optional samples where Engineer’s selection is

required. Prepare samples to match Engineer's sample where so indicated.

Include information with each sample to show generic description, source or

product name and manufacturers, limitations, and compliance with standards.

Samples are submitted for review and confirmation of color, pattern, texture and

"kind" by Engineer. Engineer will not "test" samples (except as otherwise

indicated) for compliance with other requirements, which are therefore the

exclusive responsibility of the Contractor.

C. Submit the number of samples stated in each Specification Section.

D. Mock-ups are a special form of samples, which are too large or otherwise

inconvenient for handling in specified manner for transmittal of sample

submittals.

E. Where mock-ups and similar samples are indicated in individual work sections

recognized as a special type of sample, comply with requirements for "samples" to

greatest extent possible, and process transmittal forms to provide a record of

activity.

1.08 MANUFACTURER'S INSTRUCTIONS

A. When specified in individual specification Sections, submit manufacturer's printed

instructions for delivery, storage, assembly, installation, start-up, adjusting, and

finishing, in quantities specified for Product Data.

B. Identify conflicts between manufacturer's instructions and Contract Documents.

1.09 MANUFACTURER'S CERTIFICATES

A. When specified in individual specification Sections, submit manufacturer's

certificate to Engineer for review, in quantities specified for Product Data.

B. Indicate whether material or product conforms to or exceeds specified

requirements. Submit supporting reference date, affidavits, and certifications as

appropriate.

C. Certificates may be recent or previous test results on material or Product, but must

be acceptable to Engineer.

Page 72: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

01300/6-6

1.10 ENGINEER REVIEW

A. Engineer will endeavor to review shop drawings, product data, and samples, and

to return submittals within 10 working days.

END OF SECTION

Page 73: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

01400/1-2

SECTION 01400

QUALITY CONTROL

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Quality assurance and control of installation.

B. Field samples.

C. Manufacturers' field services and reports.

1.02 RELATED SECTIONS

A. Section 01300 - Submittals

1.03 QUALITY ASSURANCE/CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, products, services, site

conditions, and workmanship, to produce Work of specified quality.

B. Comply fully with manufacturer's instructions, including each step in sequence.

C. Should manufacturer's instructions conflict with Contract Documents, request

clarification from Engineer before proceeding.

D. Comply with specified standards as a minimum quality for the Work except when

more stringent tolerances, codes, or specified requirements indicate higher

standards or more precise workmanship.

E. Perform work by persons qualified to produce workmanship of specified quality.

F. Secure Products in place with positive anchorage devices designed and sized to

withstand stresses, vibration, physical distortion or disfigurement.

1.04 FIELD SAMPLES

A. Install field samples at the site as required by individual specifications Sections

for review.

B. Acceptable samples represent a quality level for the work.

Page 74: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

01400/2-2

C. Where field sample is specified in individual Sections to be removed, clear area

after field sample has been accepted by Engineer.

1.05 MANUFACTURERS' FIELD SERVICES AND REPORTS

A. When specified in individual specification Sections, require material or Product

suppliers or manufacturers to provide qualified staff personnel to observe site

conditions, conditions of surfaces and installation, quality of workmanship, start-

up of equipment, test, adjust, and balance of equipment as applicable, and to

initiate instructions when necessary.

B. Individuals to report observations and site decisions or instructions given to

applicators or installers that are supplemental or contrary to manufacturer's written

instructions.

C. Submit report in duplicate within 30 days of observation to Engineer for review.

END OF SECTION

Page 75: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

SECTION 01410

TESTING LABORATORY SERVICES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Selection and Payment

B. Laboratory Reports

C. Limits on Testing Laboratory Authority

D. Contractor Responsibilities

1.02 RELATED SECTIONS

A. Section 01300 - Submittals

1.03 REFERENCES

A. ANSI/ASTM D3740 - Practice for Evaluation of Agencies Engaged in Testing

and/or Inspection of Soil and Rock as Used in Engineering Design and

Construction.

B. ANSI/ASTM E329 - Recommended Practice for Inspection and Testing Agencies

for Concrete, Steel, and Bituminous Materials as Used in Construction.

C. See appropriate sections for additional references.

1.04 SELECTION AND PAYMENT

A. Owner may employ and pay for services of an independent testing laboratory to

perform specified inspection and testing. If employed, Contractor shall prepare

and submit materials for testing to the testing laboratory.

B. Employment of a testing laboratory shall in no way relieve Contractor of

obligation to perform Work in accordance with requirements of Contract

Documents.

C. The testing laboratory is to supply a signed statement, which indicates that the

testing and inspection procedures required have been performed along with a

description of any discrepancies which have not been resolved at the completion

of the project.

01410/1-3

Page 76: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

1.05 LABORATORY REPORTS

A. After each inspection and test, the testing laboratory will submit two copies of the

laboratory report to Engineer, and two copies to the Contractor.

B. Report will include:

1. Date issued

2. Project title and number

3. Name and signature of inspector

4. Date and time of sampling or inspection

5. Temperature and weather conditions

6. Identification of product and Specifications section

7. Location in the Project

8. Type of inspection or test

9. Date of test

10. Results of tests

11. Conformance with Contract Documents

C. When requested by Engineer, the laboratory will also provide interpretation of test

results.

1.06 LIMITS ON TESTING LABORATORY AUTHORITY

A. Laboratory may not release, revoke, alter, or enlarge on requirements of Contract

Documents.

B. Laboratory may not approve or accept any portion of the work.

C. Laboratory may not assume any duties of Contractor.

D. Laboratory has no authority to stop work.

1.07 CONTRACTOR RESPONSIBILITIES

A. Deliver to laboratory at designated location adequate samples of materials

proposed to be used which require testing, together with proposed mix designs.

B. Cooperate with laboratory personnel, and provide access to work and to

manufacturer's facilities.

C. Provide copies of reviewed and stamped shop drawings and product data as

required by laboratory.

01410/2-3

Page 77: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

D. Provide incidental labor and facilities to provide access to work to be tested, to

obtain and handle samples at the site or at source of products to be tested, to

facilitate tests and inspections, and for storage and curing of test samples.

E. Provide to the laboratory and the Engineer the preliminary design mix proposed to

be used for concrete, and other material mixes which require control by the testing

laboratory.

F. Notify the Engineer and the laboratory 24 hours prior to expected time for

operations requiring inspection and testing services.

G. Furnish copies of product test reports as required.

H. Employ and pay for the services of the testing laboratory to perform additional

inspections, sampling and testing required when initial tests indicate work

does not comply with Contract Documents.

I. Make arrangements with laboratory and pay for additional samples and tests

required for Contractor's convenience.

J. Change concrete proportions and consistency to correct any deficiencies indicated

by tests and laboratory or field specimens.

K. Facilitate work and cooperate with Laboratory Inspectors at all times. Contractor

shall furnish ample notification of construction schedules and shall be responsible

to insure that Inspectors are present as required. No concrete shall be placed until

Inspector is present.

L. Provide concrete curing box with associated utilities for concrete cylinders per

requirements of the testing laboratory and the Engineer.

M. Contractor shall bear any cost associated with a visit by the Owner's Testing Lab

Representative and/or Special Inspector when the activity or item scheduled for

review is not prepared or unavailable for inspection. This would include, but is

not limited to, failure of concrete loads or equipment deliveries to arrive as

scheduled, for any reason.

END OF SECTION

01410/3-3

Page 78: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

SECTION 01500

CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

PART 1 GENERAL

1.01 SECTION INCLUDES

Unless noted otherwise, the General Contractor shall provide the following:

A. Temporary Utilities

1. Electricity, Lighting

2. Heat, Ventilation

3. Telephone Service

4. Temporary Water

5. Sanitary Facilities

B. Temporary Controls

1. Barriers

2. Enclosures

3. Protection of Installed Work

4. Hoists

5. Construction Aids

6. Water Control

C. Construction Facilities

1. Cleaning During Construction

2. Field Offices and Sheds

3. Access on Roads

4. Parking

D. Removal of Utilities, Facilities and Controls

01500/1-5

Page 79: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

1.02 TEMPORARY ELECTRICITY, LIGHTING

A. Arrange with utility company and pay all costs to provide service required for

construction operations, with branch wiring and distribution boxes located to

allow service and lighting by means of construction-type power cords.

B. Provide artificial lighting, at a rate of 1 watt per square foot minimum, for

construction operations when natural light is not adequate for work.

C. Existing and permanent lighting may be used during construction. Maintain

lighting and make routine repairs.

D. When working on Town sites or buildings and electricity is readily available, the

Contractor may use the Town's electric service at no expense. (This does not

include any field offices.)

1.03 TEMPORARY HEAT, VENTILATION

A. Provide temporary heat and ventilation as required to maintain adequate

environmental conditions to facilitate progress of the work, to meet specified

minimum conditions for the installation of materials, and to protect materials and

finishes from damage due to temperature or humidity.

B. Provide and pay for heat devices and heat as required to maintain specified

condition for construction operations.

C. Maintain minimum temperatures as listed in the appropriate Sections.

D. Provide ventilation of enclosed areas to cure materials, to disperse humidity, and

to prevent accumulations of dust, fumes, vapors, or gases.

1.04 TELEPHONE SERVICE

A. If field offices are used, arrange with local telephone company to provide direct

line telephone service to field office and Engineers field office and pay all costs

for installation, maintenance, removal and service charges for calls (except toll

calls made by Town Inspectors).

1.05 TEMPORARY WATER

A. Arrange with utility company and pay all costs to provide service required for

construction operations.

B. Water may be trucked in at the Contractor's option.

C. When working on Town sites or buildings and water is readily available, the

Contractor may use the Town's water service at no expense.

01500/2-5

Page 80: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

1.06 TEMPORARY SANITARY FACILITIES

A. Provide and maintain required sanitary facilities and enclosures in compliance

with laws and regulations.

1.07 BARRIERS

A. Provide as required to prevent unauthorized entry to construction areas, to allow

for Owner's and Town's use of site, and to protect existing facilities and adjacent

properties from damage from construction operations and demolition.

B. Provide barricades and covered walkways as required by governing authorities for

public rights-of-way and for public access to existing buildings.

C. Provide barriers around trees and plants designated to remain. Protect against

vehicular traffic, stored materials, dumping, chemically injurious materials, and

puddling or continuous running water.

1.08 ENCLOSURES

A. Provide temporary insulated weather-tight closures where indicated and where

reasonably required to ensure adequate workmanship and protection from weather

and unsatisfactory ambient conditions for work to allow for temporary heating.

1.09 PROTECTION OF INSTALLED WORK

A. Protect installed Work and provide special protection where specified in

individual Specification Sections.

B. Provide temporary protection for installed products. Control activity in immediate

area to minimize damage.

C. Prohibit traffic from lawns and landscaped areas.

1.10 HOISTS

A. Provide adequate hoist facilities for loading and unloading materials.

1.11 CONSTRUCTION AIDS

A. Provide construction aids and equipment required by personnel and to facilitate

execution of the Work; scaffolds, staging, ladders, ramps, runways, platforms,

railings, cranes, chutes and other such facilities and equipment. Refer to

respective sections for particular requirements for each trade.

B. Maintain facilities and equipment in first-class condition.

01500/3-5

Page 81: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

1.12 WATER CONTROL

A. Grade site to drain.

B. Maintain excavations free of water. Provide, operate and maintain pumping

equipment.

C. Protect site from puddling or running water. Provide water barriers as required to

protect site from soil erosion.

1.13 CLEANING DURING CONSTRUCTION

A. Control accumulation of waste materials and rubbish; periodically dispose of off-

site.

B. Streets and drives in the area of construction shall be kept free of accumulation of

mud, clay, gravel, and any other materials which vehicles or equipment may track

or scatter onto these surfaces.

C. No burning or disposal of rubbish at the job site will be permitted.

1.14 FIELD OFFICES AND SHEDS

A. Contractor may erect and maintain a temporary field office on the project site.

Place field office in coordination with Town's direction.

B. Field Office:

1. Weather-tight, with lighting, electrical outlets, heating, ventilating and air

conditioning equipment, and equipped with furniture.

2. Provide space for project meetings, with table and chairs to accommodate

6 persons.

3. Provide separate private office, similarly equipped and furnished, for use

of Town Inspector and Engineer. Include a 36" x 48" drafting table,

standard office desk and chair, three two-drawer file cabinets, drafting

lamp and stool, and separate phone service. Pay for all costs associated

with phone except toll calls. Town will reimburse Contractor as part of

the Application for Payment process.

C. Storage Sheds for Tools, Materials, and Equipment: Weathertight, with heat and

ventilation for Products requiring controlled conditions, with adequate space for

organized storage and access, and lighting for inspection of stored materials.

01500/4-5

Page 82: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

1.15 ACCESS ON ROADS

A. Maintain passage of roads and driveways during construction unless otherwise

authorized. Spray roads periodically with calcium chloride to keep dust to a

minimum.

B. Provide means of removing mud from vehicle wheels before entering public

streets.

1.16 REMOVAL OF UTILITIES, FACILITIES AND CONTROLS

A. Remove temporary above grade or buried materials, equipment, utilities, and

construction prior to Substantial Completion inspection. Remove underground

installations to a depth of 2 feet; grade site as indicated.

B. Clean and repair damage caused by installation or use of temporary work or

facilities. Restore existing facilities used during construction to original

condition. Restore permanent facilities used during construction to specified

condition.

END OF SECTION

01500/5-5

Page 83: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

SECTION 01505

MOBILIZATION

PART 1 GENERAL

1.01 WORK INCLUDED

A. The work under this section includes all labor, materials, tools, and equipment

necessary for the movement of personnel and equipment to the project site, and

for the establishment of all field offices and other facilities necessary for the

performance of the work.

1.02 MEASUREMENT AND PAYMENT

A. Measurement - This work shall be measured for payment in the manner described

below.

1. When the first payment requisition is paid, fifty percent (50%) of the lump

sum bid for this item or five percent (5%) of the total original contract

price, whichever is less, will be certified for payment.

2. When ten percent (10%) of the original contract price is earned, seventy-

five percent (75%) of the lump sum bid for this item or seven and one-half

percent (7.5%) of the total original contract price, whichever is less, minus

any previous payment, will be certified for payment.

3. When thirty percent (30%) of the original contract price is earned, one-

hundred percent (100%) of the lump sum bid for this item or ten percent

(10%) of the total original contract price, whichever is less, minus any

previous payment, will be certified for payment.

4. Upon completion of all work for the project, payment of any amount bid

for mobilization in excess of ten percent (10%) of the original contract

amount will be paid.

NOTE: The determination of the total contract price earned shall not include the

amount of mobilization earned during the period covered by the current monthly

estimate. However, it shall include amounts previously earned and certified for

payment.

01505/1-2

Page 84: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

B. Payment

1. Mobilization shall be paid for at the contract price per lump sum,

measured as described above, for "Mobilization", which price shall include

all materials, equipment, tools, labor, transportation, operations and all

work incidental thereto.

END OF SECTION

01505/2-2

Page 85: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

SECTION 01570

MAINTENANCE AND PROTECTION OF TRAFFIC

PART 1 GENERAL

1.01 WORK INCLUDED

A. The work under this section includes all the labor, materials, tools, and equipment

necessary for maintaining and protecting traffic in the project area to the satisfaction

of the applicable local regulatory agencies and the Engineer. Unless otherwise

specified within the Contract Documents, the Contractor must maintain pedestrian

and vehicular traffic and permit access to businesses, residences, and intersecting

streets at all times.

1.02 RELATED WORK

A. Section 01571 - Traffic Directors

1.03 REFERENCE STANDARDS

A. Federal Highway Administration Manual on Uniform Traffic Control Devices

(MUTCD), Part VI.

1.04 MEASUREMENT AND PAYMENT

A. Measurement

1. Maintenance and Protection of Traffic shall be measured by the percent

complete of the total lump sum bid for this item.

B. Payment

1. Maintenance and Protection of Traffic shall be paid for at the contract unit

price per lump sum for "Maintenance and Protection of Traffic", which price

shall include all materials, tools, equipment, and labor required to complete

this item throughout the duration of the project.

PART 2 PRODUCTS

2.01 SIGNAGE

A. All sign panels shall be the product of a professional sign painter or fabricator

experienced in the production of signage meeting the requirements of the Manual of

Uniform Traffic Control Devices. Panel size, colors, legend and letter type shall

01570/1-4

Page 86: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

be strictly observed. Panel material shall be exterior plywood, aluminum sheet or

extruded shapes, or other material acceptable to the Engineer. All items shall be

completely weatherproof for the required length of the display.

B. Panel supports shall be wood or metal of substantial proportions and sufficiently

braced to provide a reliable installation for the duration of the work. Supports shall

be designed for 60 mph wind loads. Portable installations shall be ballasted to meet

this requirement.

2.02 CHANNELING DEVICES

A. Traffic cones, pylons, vertical panels, barricades and other warning devices shall

provide high visibility and be constructed of material which will impart minimum

damage to errant vehicles or passengers. 55 gallon steel drums will not be allowed.

2.03 WARNING LIGHTS

A. Warning lights shall be self-contained, weatherproof units and maintained to

produce a sharp strobe beam, amber in color. Flash frequency shall be at least 20

per minute.

PART 3 EXECUTION

3.01 INSTALLATION

A. The type, number, deployment pattern, sequence of installation and dismantling,

covering of permanent signs and all other details pertaining to various conditions

evolving from construction operations as outlined in the Manual of Uniform Traffic

Control Devices shall be strictly observed. Conditions not covered shall be resolved

to the mutual satisfaction of the Engineer and the regulatory agency having

jurisdiction over the right of way.

B. Temporary pedestrian routes shall comply with applicable ADA standards for

accessibility.

3.02 MAINTENANCE

A. The Contractor shall maintain all installed devices to the satisfaction of the

Engineer. Losses incurred as the result of accident, errant vehicles or pilferage shall

be replaced in kind at the earliest date possible.

01570/2-4

Page 87: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

3.03 DISMANTLING

A. As soon as the work is complete and the site capable of receiving normal traffic

operations, all temporary signs and control devices shall be removed and the

original patterns restored. Modifications to permanent signage shall be removed.

3.04 TEMPORARY ACCESS

A. Contractor shall arrange his operations to provide access to properties along the

street including temporary bridges to driveways, and provide access to fire hydrants,

manholes, gate boxes, or other utilities.

B. Whenever any trench will obstruct traffic in or to any public street, private driveway,

or property entrance, the Contractor shall take such steps as required to maintain

necessary traffic and access including temporary bridging if required.

C. The Contractor shall confine his occupancy of public or traveled ways to the

smallest space compatible with the efficient and safe performance of the work

contemplated by the Contract.

3.05 CONTRACTOR RESPONSIBILITIES

A. The Contractor will be held responsible for any damages that the Engineer,

Governmental units, or their heirs or assigns may have to pay as a consequence of

the Contractor's failure to protect the public from injury, and the same may be

deducted from any payments that are due or may become due to the Contractor

under this Contract.

B. The Contractor will be required, under the contract Lump Sum Price for

"Maintenance and Protection of Traffic", to maintain and protect the traffic

throughout the duration of the Contract. No claim for additional payment due to

unusual project area conditions encountered or delay caused by the Contractor or

other outside agencies shall be considered.

3.06 SNOW REMOVAL

A. If the Contractor's operations or conditions created by his operations on any public

street or highway, interfere with the removal or sanding of snow or ice by the public

authorities or adjoining land owners, in their customary manner, the

01570/3-4

Page 88: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

Contractor shall be required to perform such services for the public authorities or

adjoining owners without charge.

B. If the Contractor fails to do so, he shall reimburse the said authorities or adjoining

owners or the Owner for any additional cost to them for doing such work together

with any damage to the equipment of said parties, or claims of any parties for

damage or injury or loss by reason of failure to remove snow or ice or to sand icy

spots under these conditions.

END OF SECTION

01570/4-4

Page 89: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

SECTION 01571

TRAFFIC DIRECTORS

PART 1 GENERAL

1.01 WORK INCLUDED

A. The work under this section includes all of the labor, materials, tools, and

equipment necessary for directing traffic safely and expeditiously through or

around work areas within the right-of-way.

1.02 RELATED WORK

A. Section 01570 - Maintenance and Protection of Traffic

1.03 REFERENCE STANDARDS

A. Federal Highway Administration, Manual on Uniform Traffic Control Devices

(MUTCD), Part VI.

1.04 TRAFFIC DIRECTORS

A. Traffic Directors are responsible for human safety and make the greatest number

of public contacts of all construction personnel. It is important that qualified

personnel be selected. A Traffic Director shall possess the following minimum

qualifications:

1. Average Intelligence.

2. Good physical condition, including sight and hearing.

3. Mental alertness.

4. Courteous but firm manner.

5. Neat appearance.

6. Sense of responsibility for safety of public and crew.

B. The use of orange clothing such as a vest, shirt, or jacket shall be required for

Traffic Directors. For nighttime conditions, similar outside garments shall be

reflectorized.

C. Traffic Directors are provided at work sites to stop traffic intermittently as

necessitated by work progress or to maintain continuous traffic past a work site at

reduced speeds to help protect the work crew. For both of these functions, the

Traffic Director must, at all times, be clearly visible to approaching traffic for a

distance sufficient to permit proper response by the motorist to the flagging

instructions, and to permit traffic to reduce speed before entering the work site.

01571/1-5

Page 90: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

In positioning Traffic Directors, consideration must be given to maintaining color

contrast between the Traffic Director's protective garments and his background.

1.05 MEASUREMENT AND PAYMENT

A. Measurement

1. Traffic Directors shall be measured by the number of man hours worked at

the work site for each Traffic Director.

2. To be considered for payment under this section, the designated Traffic

Director shall have no other duties except those described by this section.

B. Payment

1. Traffic Directors shall be paid for at the stipulated contract unit price for

"Traffic Directors", which price shall include all materials, tools,

equipment and labor required to perform the safe direction of traffic

throughout the site.

2. The stipulated unit price shall include full compensation and any other

cost or liability incidental thereto for furnishing the Traffic Directors.

3. Uniformed Police Officers, when required, shall be paid directly by the

Town.

PART 2 PRODUCTS

2.01 FLAGS

A. Flags used for signaling purposes shall be a minimum of 24 by 24 inches in size,

made of a good grade of red material securely fastened to a staff approximately 3

feet in length. The free edge should be weighted to insure that the flag will hang

vertically, even in heavy winds.

2.02 PADDLES

A. Sign paddles should be at least 18 inches wide with letters at least 6 inches high.

A rigid handle shall be provided. (A 6' handle (staff) is recommended). This

combination sign may be fabricated from sheet metal or other light semi-rigid

material. The background of the "STOP" face shall be red with white letters and

border. The background of the "SLOW" shall be orange with black letters and

border. When used at night the "STOP" face shall be reflectorized red with white

reflectorized letters and border, and the "SLOW" face shall be reflectorized

orange with black letters and border.

01571/2-5

Page 91: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

PART 3 EXECUTION

3.01 FLAGGING

A. The following methods of signaling with a flag shall be used:

1. To Stop Traffic: The Traffic Director shall face traffic and extend the

flag horizontally across the traffic lane in a stationary position so that the

full area of the flag is visible hanging below the staff. For greater

emphasis, the free arm may be raised with the palm toward approaching

traffic.

2. When it is Safe for Traffic to Proceed: The Traffic Director shall stand

parallel to the traffic movement, and with flag and arm lowered from view

of the driver, motion traffic ahead with his free arm. Flags shall not be

used to signal traffic to proceed.

3. Where it is Desired to Alert or Slow Traffic: Where it is desired to alert

or slow traffic by means of flagging, the Traffic Director shall face traffic

and slowly wave the flag in a sweeping motion of the extended arm from

the shoulder level to straight down without raising the arm above a

horizontal position.

B. If a sign paddle is used, it shall be held in a stationary position with the arm

extended horizontally away from the body. For added emphasis, the Traffic

Director may slowly raise and lower his free hand with the palm down.

C. Lights approved by the Director of Public Works, or reflectorized sign paddles or

reflectorized flags, shall be used to flag traffic at night. Daytime flagging

procedures shall be followed whenever such lights, paddles or flags are used at

night.

3.02 TRAFFIC DIRECTORS STATIONS

A. Traffic Directors stations shall be located far enough in advance of the work site

so that approaching traffic will have sufficient distance to reduce speed before

entering the project. This distance is related to approach speed and physical

conditions at the site, however, in no case will the distance be greater than 200 to

300 feet between stations.

01571/3-5

Page 92: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

B. The Traffic Directors shall stand either on the shoulder adjacent to the traffic he is

controlling or in the barricaded lane. At a "spot" obstruction he may have to stand

on the shoulder opposite the barricaded section to operate effectively. Under no

circumstances should he stand in the lane being used by moving traffic. He should

be clearly visible to approaching traffic at all times. For this reason, he should

stand alone, never permitting a group of workmen to congregate around him. He

should be stationed sufficiently in advance of the work force to warn them of

approaching danger, such as out-of-control vehicles.

C. Traffic Directors stations shall be adequately protected and preceded by proper

advance warning signs. At night, flagmen stations shall be adequately

illuminated.

D. At short construction and maintenance lane closures where adequate sight

distance is available for the safe handling of traffic, the use of one Traffic Director

may be sufficient.

3.03 ONE-WAY TRAFFIC CONTROL

A. Where a one-way lane section is of any length, there shall be some means of

coordinating movements at each end so that vehicles are not simultaneously

moving in opposite directions in the section and so that delays are not excessive at

either end.

B. Control points at each end of the route should be chosen so as to permit easy

passing of opposing lines of vehicles.

C. Alternate one-way traffic control shall be accomplished by one of the following

means:

1. Traffic Director control, one at each end, using hand signals.

2. Traffic Director control, using hand-held radios.

D. Where the one-lane section is short enough so that each end is visible from the

other end, traffic may be controlled by means of a Traffic Director at each end of

the section. One of the two should be designated as the Chief Traffic Director for

purposes of coordinating movement. They should be able to communicate with

each other verbally or by means of signals. These signals should not be such as to

be mistaken for flagging signals.

01571/4-5

Page 93: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

E. Where the end of a one-lane section is not visible from the other end, the Traffic

Director shall maintain contact by means of hand-held radios. So that a Traffic

Director may know when to allow traffic to proceed into the section, the last

vehicle from the opposite direction can be identified by description or license.

3.04 COORDINATION

A. If a Traffic Direction Service is used, the Contractor shall make all necessary

arrangements and coordinate the need for traffic control before the service is

required. The Contractor shall identify the number of personnel required and the

time to report.

3.05 USE OF POLICE

A. During certain times throughout the construction, and as determined by the Chief

of Police or the Director of Public Works, Police Officers may be assigned to the

construction site. These Officers will be assigned during period of heavy traffic or

at intersection of major roads. The Police Officer will be in charge of traffic

control at these sites. The Traffic Directors will augment the Police Officers.

Coordination of the assignment of the Officers will occur between the Engineer

and the Contractor.

END OF SECTION

01571/5-5

Page 94: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02230/1-8

SECTION 02230

EXCAVATING, BACKFILLING, AND COMPACTING FOR

SIDEWALKS, CURBING, DRIVEWAY APRONS, AND ROADWAY REPAIR

PART 1 GENERAL

1.01 WORK INCLUDED

A. The work under this section includes all the labor, materials, tools, and equipment

necessary to perform, to the lines and grades shown on the plans, all earthwork

required to install asphalt and concrete driveway aprons, sidewalks, asphalt and

concrete curbs, handicap ramps, and roadway repair as shown on the plans or

referenced in the specifications. Earthwork shall include excavation, grading,

removal of topsoil and subsoil as well as the disposal of excess or unsuitable

material.

1.02 RELATED WORK

A. Section 01300 - Submittals

B. Section 01400 - Quality Control

C. Section 01410 - Testing Laboratory Services

D. Section 02275 - Erosion Control

E. Section 02242 - Processed Gravel Base

F. Section 02520 - Concrete Sidewalks

G. Section 02521 - Concrete Curbing

H. Section 02511 – Bituminous Concrete Paving

1.03 REFERENCE STANDARDS

A. Form 818, State of Connecticut Department Transportation, Standard

Specifications for Roads, Bridges and Incidental Construction, 2020.

B. ASTM American Society for Testing and Materials

1. D422, Particle-size Analysis of Soils

2. D2922, Density of Soil and Soil Aggregate in Place by Nuclear Methods

3. D1557, Moisture Density Relations of Soils and Soil Aggregate Mixtures

using 10 lb. Rammer and 18-inch drop.

1.04 QUALITY ASSURANCE

A. Testing of compacted fill materials may be performed by an independent soils

laboratory employed by the Town in accordance with Section 01410. Testing will

be performed so as to minimize interference with the work.

Page 95: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02230/2-8

B. When work of this section or portions of work are completed, notify the testing

laboratory to perform density tests. Do not proceed with additional portions of

work until results have been verified.

C. If, during progress of work, tests indicate that compacted materials do not meet

specified requirements, notify Engineer and request direction to proceed. If

required by Engineer, Contractor will remove defective work, replace and retest at

no cost to Town.

D. Ensure compacted fills are tested before proceeding with placement of surface

materials.

E. Examine existing and finish grades as shown on grading plan and excavation and

fill as indicated on plans and elevations. Protect and maintain site boundaries and

project limits during construction. If disturbed, destroyed or exceeded, repair as

directed by Engineer.

1.05 SUBMITTALS

A. Submit under provisions of Section 01300 for all materials to be used in this

section.

B. Fill Materials: Submit minimum of three samples of each type of fill material to

be used. Forward samples to appointed testing laboratory, packed tightly in

containers to prevent contamination. Retain one sample for on-site comparison.

1.06 SITE CONDITIONS

A. Verify and confirm all existing conditions in the field.

B. Restore any and all areas outside the contract limit lines that are disturbed during

the progress of work as directed by the Engineer at the Contractor's expense.

C. If subsurface investigations have been made, the results are included elsewhere.

The data shown, if any, is for general information only. Bidders are expected to

examine the site and the compiled record of investigations, and then decide for

themselves the character of materials to be encountered. No warranty, either

expressed or implied, is made as to the accuracy of the subsurface information

presented.

D. The Bidders will be allowed, with concurrence of the Town, the right to make any

subsurface explorations they deem necessary to satisfy themselves of the existing

ground conditions.

Page 96: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02230/3-8

1.07 COORDINATION

A. Coordinate work with Town surveyors for layout and grading.

B. Coordinate with affected utility companies.

1.08 PROTECTION

A. Protect bench marks, monuments, other reference points, existing structures,

roads, sidewalks, paving, curbs, overhead and underground utilities against

damage from equipment and vehicular or foot traffic.

B. Grade around excavation to prevent surface water runoff into excavated areas.

1.09 MEASUREMENT AND PAYMENT

A. Measurement and Payment

1. There shall be no separate measurement or payment for the work under

this section as it shall be included in the appropriate bid item (i.e. concrete

sidewalk, concrete curb, etc...)

PART 2 PRODUCTS

2.01 MATERIALS

A. Fill: Usable material excavated within the limits of work conforming to Article

M.02.06 Grading “A” of Form 818.

B. Bank Run Gravel: Conform to Article M.02.06 Grading "A" of Form 818.

C. Processed Gravel: Conform to Article M.02.06 Grading "C" of Form 818.

D. Topsoil: Conform to Article M.13.01-1 of Form 818.

PART 3 EXECUTION

3.01 STRIPPING AND STOCKPILING TOPSOIL

A. Reusable topsoil shall be stripped and stockpiled for use in finish grading.

Stockpile only soil which conforms to Item M.13.01-1 of Form 818. Topsoil shall

be fertile, friable agricultural soil with a loam texture class capable of sustaining

vigorous plant growth and suitable for growth of grass, neither excessively

alkaline, nor acidic, and free from clay lumps, gravel, brush, weeds, and

objectionable material.

Page 97: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02230/4-8

B. Install all perimeter silt fence, sedimentation basins and other required erosion

controls prior to stripping topsoil.

C. Stockpile topsoil so that natural drainage is not obstructed and no off-site

sediment damage shall result.

D. Side slopes of the stockpile shall not exceed a 2 to 1 slope.

E. Test stockpiled topsoil immediately following stockpiling operations and provide

test results prior to spreading topsoil.

F. Seed stockpiled topsoil with temporary grass seed of the type and at the rate

indicated in Section 02930 within 10 days of the formation of the stockpile.

G. Install silt fence around perimeter of stockpiled topsoil.

H. No topsoil shall be excavated, graded or worked in saturated or frozen condition.

I. Dispose of unsuitable material off site in a legal manner.

3.02 REMOVING EXISTING PAVEMENT SURFACES

A. No excavation shall be made until existing paved surfaces have been neatly saw-

cut. Pavement which is weakened or destroyed beyond the limits indicated shall

be re-cut and trimmed as directed by the Engineer. The additional pavement shall

be removed and replaced by the Contractor at no additional expense to the Town.

B. All pavement removal within state controlled highway lines shall be in strict

accordance with all requirements of the State Highway Department. Conditions

of permits for excavation within established rights-of-way shall be strictly

observed and the Contractor shall assume full responsibility for violations thereof.

3.03 EARTH EXCAVATION

A. Excavation shall be in open cut in such manner and to such widths as will allow

for the placing of the gravel sub-base.

B. All excavations carried outside of the lines and grades given or specified, together

with the disposal of such material, and all excavations and other work resulting

from slides, cave-ins, swellings or upheavals, will be at the Contractor's own cost

and expense. All spaces resulting from unauthorized excavations or from slides

or cave-ins shall be refilled at the Contractor's expense with suitable material, as

directed and approved by the Engineer.

C. When materials encountered are not suitable for the subgrade or when it is found

desirable or necessary to go to additional depth, the excavation shall be carried to

an additional depth as ordered and refilled and compacted with suitable fill as

directed by the Engineer.

Page 98: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02230/5-8

3.04 SITE CONTAMINATION

A. The suspicion of, or unanticipated discovery of, contaminated ground during the

excavation, or other work task under this contract, shall be reported immediately

to the Engineer and/or Town. The Contractor, at all times, shall exercise caution

to protect workmen, observers, and residents from harm. The Contractor shall

provide all reasonable and necessary assistance to the Town and/or Engineer to

ascertain the nature and source of ground contamination.

B. Any unreasonable delays to an established work schedule or any significant

changes to the Contractor's normal operation resulting from the Town's directed

corrective action for the ground contamination will be considered during review

of time extension and extra work order requests by Contractor.

3.05 PROTECTION OF WORK

A. Provide safe working conditions for the protection of men, materials and

equipment involved in the work, and to protect the public, adjacent structures,

utilities, poles, pipe lines, duct, conduit, streets and other public or private

property from cave-ins, slides, settlement or other damage.

B. Contractor shall assume full responsibility for compliance with all local codes or

State and Federal laws which pertain to safe working conditions for the protection

of men, materials and equipment during excavation.

C. Existing pipes, poles, wires, fences, curbing, property-line markers, and other

structures, which must be preserved in place without being temporarily or

permanently relocated, shall be carefully supported and protected from injury.

Should such items be damaged, they shall be restored by the Contractor, without

compensation, to at least as good a condition as that in which they were found

immediately before the work was begun.

D. Cooperate closely with all agencies involved to ascertain the exact locations of all

utilities prior to excavation. Existing utilities will be protected from damage

during construction, and if damaged, will be repaired by the Contractor at his own

expense. Note that it is the policy of the local utilities not to mark locations of

services on private property. Therefore, it is the responsibility of the Contractor to

locate utilities on private property.

E. Power-driven excavating machinery shall be handled with care to prevent damage

to shade trees, particularly to overhanging branches. Branches shall not be cut off

except by special permission from the Engineer.

F. Dig up, handle, protect and properly reset signs, posts, guard rails and the like

along the line of or adjacent to the work.

Page 99: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02230/6-8

G. Utility poles or other structures in close proximity to excavations must be tied

back, braced or otherwise temporarily supported to the satisfaction of the utility

company. Costs for providing such support, or damages resulting from

inadequate or insufficient support, shall be the Contractor's sole responsibility and

no separate compensation will be made.

H. Damage to electric poles, or their attachments, underground duct lines, utility

manholes, conduits or their components caused by the Contractor shall be repaired

by the controlling power and communications agency, but the financial

responsibility shall rest with the Contractor.

3.06 CARE AND RESTORATION OF PROPERTY

A. Do not use or operate tractors, bulldozers, or other power-operated crawler

equipment on paved surfaces; the treads or wheels of which are so shaped as to

cut or otherwise injure such surfaces without providing proper protection for the

pavement.

B. Replace in kind, all granite, concrete or bituminous curbing removed. Granite or

pre-cast concrete curbing shall be set plumb and true to the lines and grades

established and shall be backed up with materials equal to those removed.

Existing cast-in-place or bituminous curbing which is damaged or destroyed by

the Contractor, or pre-cast concrete or granite curbing which is damaged, and is

not scheduled for removal, shall be replaced with new curbing equal to that

removed at the Contractor's sole expense.

C. All surfaces which have been injured by the Contractor's operations shall be

restored to a condition at least equal to that in which they were found immediately

before work was begun. Suitable materials and methods shall be used for such

restoration.

D. The restoration of existing property or structures shall be done as promptly as

practicable and shall not be left until the end of the construction period.

E. In case of failure on the part of the Contractor to restore damaged property, the

Engineer may, upon forty-eight (48) hours written notice to the Contractor,

proceed to have the necessary repairs, rebuilding, or restoration work performed

and the cost thereof may be deducted from any monies due, or to become due, to

the Contractor under this Contract, or the Town may deduct from any monies due,

or to become due, a sum sufficient in the judgement of the Engineer to reimburse

the Town of the property so damaged or injured.

3.07 DISPOSAL OF SURPLUS AND UNSUITABLE EXCAVATED MATERIALS

A. Dispose of material off-site in a legal manner.

Page 100: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02230/7-8

3.08 DUST CONTROL

A. Conduct operations and maintain the area of activities, including sweeping and

sprinkling of area as necessary, so as to minimize the creation and dispersion of

dust. If it is necessary to use calcium chloride for more effective dust control, the

Contractor shall furnish and spread the material as directed.

3.09 DEWATERING

A. Contractor shall at all times keep the excavation free from water. The water shall

be disposed of by the Contractor to the satisfaction of the Engineer and in

accordance with the General Conditions and applicable laws and regulations.

B. Contractor shall provide all necessary pumps, dams, drains, ditches, flumes, well

points, and other means for excluding and removing water from excavations, and

for preventing the slopes from sliding or caving. Contractor shall satisfactorily

remove all water which interferes with the work. The Contractor shall sufficiently

de-water all excavations to completely dry out and solidify the sub-grade below

the processed gravel base to whatever depth is necessary to provide a firm, solid,

completely dry sub-grade on which to lay the processed gravel base.

C. No additional payment will be made for de-watering, temporary stream or

underground diversion, pumping, bailing or for equipment necessary for the

satisfactory de-watering of the excavation but the cost thereof is considered to be

included in the unit price for sidewalk and driveway apron excavation.

3.10 SUBGRADE

A. Definition: The surface on which the processed gravel base is to be placed.

B. All soft and yielding material and other portions of the sub-grade which will not

compact readily shall be removed and replaced with suitable material.

C. The sub-grade shall be compacted to achieve the density listed in paragraph

3.11.D.

D. After compacting, the sub-grade shall be true to the required line and grade.

E. Contractor shall protect the completed sub-grade.

3.11 BACKFILLING

A. Back-filling in this section shall mean the placing, grading, and compacting of the

processed gravel sub-base for all driveway aprons and sidewalks shown on the

plan to be installed.

B. Grading shall be done by hand for each lift, to produce a smooth surface that after

compaction shall be true to the required line and grade.

Page 101: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02230/8-8

C. Frozen material shall not be placed in the backfill nor shall backfill be placed

upon frozen material. Previously frozen material shall be removed or shall be

otherwise treated as required before new backfill is placed.

D. Backfill shall be placed in lifts no greater than four (4) inches and shall be

thoroughly compacted to ninety-five (95) percent of maximum dry density as

determined by ASTM test D1157, Method D, by mechanical compactors

vibrators, and/or vibratory or 2 Ton steel-wheeled static rollers before additional

lifts are placed.

E. If necessary to ensure proper compaction by rolling, the material shall first be wet

by sprinkling. However, no compaction by tamping or rolling shall be done when

the material is too wet either from rain or too great an application of water to be

compacted properly. At such times, the work will be suspended until the

previously placed and new materials have dried out sufficiently to permit proper

compacting, or such other precautions shall be taken as may be necessary to

obtain proper compaction.

F. Care shall be taken that stones and lumps do not become nested and that all voids

between stones shall be completely filled with fine material.

END OF SECTION

Page 102: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

SECTION 02240

SUBGRADE

PART 1 GENERAL

1.01 WORK INCLUDED

A. The work under this section includes all labor, materials, tools and equipment

necessary for the grading and compaction of the subgrade for the sidewalks,

ramps, and roadway repair. Also, included is the removal and disposal of

unsuitable or excess material. The resetting and adjusting of existing utilities, as

required to match finish pavement grades, is included within this section of work.

1.02 RELATED WORK

A. Section 01410 - Testing Laboratory Services

B. Section 02275 - Erosion Control

C. Section 02511 - Bituminous Concrete Paving

1.03 REFERENCE STANDARDS

A. Form 818, State of Connecticut Department of Transportation, Standard

Specification for Roads, Bridges and Incidental Construction, 2020.

B. ASTM American Society for Testing and Materials

1. D422, Particle-size Analysis of Soils

2. D2922, Density of Soil and Soil Aggregate in Place by Nuclear Methods

3. D1557, Moisture Density Relations of Soils and Soil Aggregate Mixtures

using 10 lb. Rammer and 18-inch drop.

1.04 QUALITY ASSURANCE

A. Testing of compacted fill materials may be performed by an independent soils

laboratory employed by the Town in accordance with Section 01410. Testing will

be performed so as to minimize interference with the work.

B. When work of this section, or portions of work are completed, notify the testing

laboratory to perform density tests. Do not proceed with additional portions of

work until results have been verified.

02240/1-5

Page 103: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

C. If, during progress of work, tests indicate that compacted materials do not meet

specified requirements, notify Engineer as to direction to proceed. If required by

Engineer, Contractor will remove defective work, replace and retest at no cost to

Town.

D. Ensure compacted fills are tested before proceeding with placement of surface

materials.

E. Examine existing and finish grades as shown on grading plan and excavation and

fill as indicated on plans and elevations. Protect and maintain site boundaries and

project limits during construction. If disturbed, destroyed or exceeded, repair as

directed by Engineer.

1.05 SUBMITTALS

A. Submit under provisions of Section 01300 for all materials to be used in this

section.

B. Fill Materials: Submit minimum of three samples of each type of fill material to

be used. Forward samples to appointed testing laboratory, packed tightly in

containers to prevent contamination. Retain one sample for on-site comparison.

1.06 DEFINITIONS

A. Subgrade: The area upon which the pavement structure and gravel base is placed

shall be known as the subgrade. This is the plane coincident with the bottom of

the gravel subbase, as shown on the plans and cross-sections. The work of

formation of subgrade shall be performed at this plane.

1.07 COORDINATION

A. Coordinate with affected utility companies.

1.08 PROTECTION

A. Protect bench marks, monuments, other reference points, existing structures,

roads, sidewalks, paving, curbs, overhead and underground utilities against

damage from equipment and vehicular or foot traffic.

1.09 MEASUREMENT AND PAYMENT

A. Measurement and payment

1. There shall be no separate measurement or payment for the work under

this section as it shall be included in the appropriate bid item (i.e. concrete

sidewalk, concrete curb, etc...).

02240/2-5

Page 104: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

PART 2 PRODUCTS

2.01 MATERIALS

A. Processed Gravel: Conform to Article M.02.06 Grading "C" of Form 818.

PART 3 EXECUTION

3.01 SUBGRADE PREPARATION

A. All soft and yielding materials and other portions of the subgrade which will not

compact readily when rolled or tamped, shall be removed as directed, and all

loose rock or boulders over 5 inches in size, found in the earth, shall be removed

or broken off to a depth of not less than one foot below the subgrade.

B. All holes or depressions made by the removal of material, as described, shall be

filled with approved fill material as described above and compacted uniformly.

Excess recycled material shall be used. If additional material is required,

processed gravel shall be used, with written approval from the Town of Groton.

C. Excess recycled material shall be removed such that after compaction, the

subgrade elevation will allow for a six (6) inch curb reveal after sidewalk and

ramp installation and pavement repair.

3.02 GRADING

A. The subgrade shall be graded to produce a smooth surface that when compacted

meets the lines and grades shown on the plan.

B. Grading shall be done after all underground utilities have been installed and their

trenches backfilled and compacted.

3.03 COMPACTING

A. Roll the entire subgrade with an approved power roller having a minimum

compression of 300 pounds per inch of width of tread on the rear wheels and

weighing not less than 10 tons. Vibrating units shall have a static weight of not

less than 4 tons.

02240/3-5

Page 105: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

B. Any portion of the subgrade which is not accessible to a roller shall be compacted

thoroughly with approved mechanical tampers.

C. The rolling and tamping shall be continued until the entire subgrade is uniformly

and thoroughly compacted to the true lines and grades given.

D. The dry density after compaction shall not be less than 95 percent of the dry

density for that soil when tested in accordance with AASHTO T 180, Method D.

Correction for particles retained in the 3/4 inch sieve shall be as specified in

AASHTO Method T-224.

E. Water may be used during the compaction and binding operation. Water shall be

applied from an approved watering device and the direction and intensity of the

stream shall be as directed by the Engineer.

F. The compacting and binding operation shall cover the entire surface of the course

with uniform overlapping of each preceding track or pass. Areas of super-

elevation and special cross slope shall be compacted by beginning at the lowest

edge and proceeding towards the higher edge unless otherwise directed by the

Engineer.

G. The compacting and binding operation shall be continued until the voids in the

aggregates have been reduced to provide a firm and uniform surface satisfactory

to the Engineer. The amount of compactive effort shall be as directed by the

Engineer, but in no case shall be less than four (4) complete passes of the

compacting and binding operations.

H. All aggregate shall be completely compacted and bound at the end of each day's

work or when traffic is to be permitted to operate on the road.

I. Should the subbase material become churned up or mixed with the bottom course

material at any time, the Contractor shall, without additional compensation,

remove the mixture. The Contractor shall add new subbase material, if required,

and reshape and recompact the subbase.

J. Any surface irregularities which develop during or after work, shall be corrected

by loosening material already in place and removing or adding aggregate as

required, after which the entire area, including the surrounding surface, shall be

recompacted and rebound until it is brought to a firm and uniform surface

satisfactory to the Engineer.

02240/4-5

Page 106: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

3.04 IMPERVIOUS MATERIAL

A. When, in the opinion of the Engineer, areas of the subgrade have become

impervious due to a concentration of fine materials and present a hard, smooth

and dense surface, such areas shall be lightly scarified, to correct the impervious

condition and then recompacted. In particularly severe cases, it may become

necessary to remove such fine materials and to replace them with suitable

materials prior to recompaction.

3.05 PROTECTION

A. All ditches and drains shall be completed sufficiently to drain effectively before

the placing of any construction material shall be permitted. In handling materials,

tools, equipment, etc., the Contractor shall protect the subgrade from damage by

exercising such precautions as the Engineer may deem necessary.

B. At all times the subgrade surface shall be kept in such condition that it will drain

readily and correctly.

C. The subgrade shall be checked and approved before any pavement material is

placed.

3.06 EXISTING UTILITIES ADJUSTMENT

A. The Contractor shall reset and adjust existing utilities (ie. manhole frame and

covers, water supply valve boxes, etc.) as necessary to match finish pavement

grades.

3.07 DUST CONTROL

A. The Contractor shall conduct operations and maintain the area of activities,

including sweeping and sprinkling of area as necessary, so as to minimize the

creation and dispersion of dust. The Contractor shall furnish and spread liquid-

applied calcium chloride on all disturbed areas on a daily basis and as directed by

the Engineer. More specifically, the Contractor is required to apply calcium

chloride before the end of each day to areas which were disturbed during the

course of that day.

3.08 DISPOSAL OF UNSUITABLE/EXCESS MATERIAL

A. The Contractor shall be responsible and bear all costs for hauling all unsuitable

and/or excess material off site and disposing of in a proper and legal manner.

END OF SECTION

02240/5-5

Page 107: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

SECTION 02241

BANK RUN GRAVEL SUBBASE

PART 1 - GENERAL

1.01 WORK INCLUDED

A. The work under this section includes all the labor, materials, tools, and equipment

necessary for the placing, grading and compaction of a bank run gravel subbase

for construction or reconstruction of the roadway to the lines, grades and depth

shown on the plans.

1.02 RELATED WORK

A. Section 01300 - Submittals

B. Section 01400 - Quality Control

C. Section 01410 - Testing Laboratory Services

D. Section 02230 – Excavating, Backfilling and Compacting for Sidewalks, Curbing,

Driveway Aprons and Roadway Repair.

E. Section 02240 - Subgrade

F. Section 02511 - Bituminous Concrete Paving

1.03 REFERENCE STANDARDS

A. Form 818, State of Connecticut Department Transportation. Standard

Specifications for Roads, Bridges and Incidental Construction, 2020.

B. ASTM American Society for Testing and Materials

1. D422, Particle-size Analysis of Soils

2. D2922, Density of Soil and Soil Aggregate in Place by Nuclear Methods

3. D1557, Moisture Density Relations of Soils and Soil Aggregate Mixtures

using 10 lb. Rammer and 18-inch drop.

1.04 QUALITY ASSURANCE

A. Testing of compacted fill materials may be performed by an independent soils

laboratory employed by the Town in accordance with Section 01410. Testing will

be performed so as to minimize interference with the work.

02241/1-4

Page 108: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

B. When work of this section or portions of work are completed, notify the testing

laboratory to perform density tests. Do not proceed with additional portions of

work until results have been verified.

C. If, during progress of work, tests indicate that compacted materials do not meet

specified requirements, notify Engineer as to direction to proceed. If required by

Engineer, Contractor will remove defective work, replace and retest at no cost to

Town.

D. Ensure compacted fills are tested before proceeding with placement of surface

materials.

E. Examine existing and finish grades as shown on grading plan and excavation and

fill as indicated on plans and elevations. Protect and maintain site boundaries and

project limits during construction. If disturbed, destroyed or exceeded, repair as

directed by Engineer.

1.05 SUBMITTALS

A. Submit under provisions of Section 01300 for all materials to be used in this

section.

1.06 COORDINATION

A. Coordinate work with Town surveyors for layout and grading.

B. Coordinate with affected utility companies.

1.07 PROTECTION

A. Protect bench marks, monuments, other reference points, existing structures,

roads, sidewalks, paving, curbs, overhead and underground utilities against

damage from equipment and vehicular or foot traffic.

1.08 MEASUREMENT AND PAYMENT

A. Measurement and payment

1. There shall be no separate measurement or payment for the work under

this section as it shall be included in the appropriate bid item (i.e. concrete

sidewalk, concrete curb, etc...).

02241/2-4

Page 109: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

PART 2 - PRODUCTS

2.01 MATERIALS

A. Bank Run Gravel: Conform to Article M.02.06 Grading "A" of Form 818.

PART 3 - EXECUTION

3.01 PLACING

A. The bank run gravel subbase shall be spread upon the prepared subgrade in layers

of not over 6 inches in depth after final compaction.

B. Frozen material shall not be placed on the subgrade nor shall the gravel subbase

be placed upon a frozen subgrade. Previously frozen material shall be removed or

shall be otherwise treated as required before new material is placed.

3.02 GRADING

A. Each lift of bank run gravel shall be uniformly graded to produce a smooth surface

and that the desired lines and grades are met after compaction.

B. The top lift of bank run gravel must be graded to the proposed subgrade.

3.03 COMPACTING

A. After the gravel subbase is spread and graded, it shall be thoroughly compacted

and bound by use of equipment specifically manufactured for that purpose.

Rollers shall deliver a ground pressure of not less than 300 pounds per lineal inch

of contact width and shall weigh not less than 10 tons. Vibratory rollers shall

have a static weight of not less than 4 tons.

B. Where it is impractical to use large rollers, mechanical tampers or small rollers

can be used.

C. The dry density after compaction shall not be less than 95 percent of the dry

density for that subbase material when tested in accordance with AASHTO T-180,

Method D. Correction for particles retained on the 3/4 inch sieve shall be as

specified in AASHTO T-224.

D. Water may be used during the compaction and binding operation. Water shall be

applied from an approved watering device and the direction and intensity of the

stream shall be as directed by the Engineer.

02241/3-4

Page 110: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

E. The compacting and binding operation shall begin at the outside edges,

overlapping the shoulders for a distance of not less than 6 inches and progress

towards the middle, parallel with the centerline of the pavement. The work shall

cover the entire surface of the course with uniform overlapping of each preceding

track or pass. Areas of super-elevation and special cross slope shall be compacted

by beginning at the lowest edge and proceeding towards the higher edge, unless

otherwise directed by the Engineer.

F. The compacting and binding operation shall be continued until the voids in the

aggregates have been reduced to provide a firm and uniform surface satisfactory

to the Engineer. The amount of compactive effort shall be as directed by the

Engineer, but in no case shall be less than four (4) complete passes of the

compacting and binding operations.

G. All aggregate shall be completely compacted and bound at the end of each day's

work or when traffic is to be permitted to operate on the road.

H. Should the subbase material become churned up or mixed with the bottom course

material at any time, the Contractor shall, without additional compensation,

remove the mixture. The Contractor shall add new subbase material, if required,

and reshape and recompact the subbase.

I. Any surface irregularities which develop during, or after work, shall be corrected

by loosening material already in place and removing or adding aggregate as

required, after which the entire area, including the surrounding surface, shall be

recompacted and rebound until it is brought to a firm and uniform surface

satisfactory to the Engineer.

END OF SECTION

02241/4-4

Page 111: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02242/1-4

SECTION 02242

PROCESSED GRAVEL

PART 1 - GENERAL

1.01 WORK INCLUDED

A. The work under this section includes all the labor, materials, tools, and equipment

necessary for placing, grading and compacting the processed gravel to the lines,

grades and depth shown on the plans.

1.02 RELATED WORK

A. Section 01300 - Submittals

B. Section 01400 - Quality Control

C. Section 01410 - Testing Laboratory Services

1.03 REFERENCE STANDARDS

A. Form 818, State of Connecticut Department Transportation. Standard

Specifications for Roads, Bridges and Incidental Construction, 2020.

B. ASTM American Society for Testing and Materials

1. D422, Particle-size Analysis of Soils

2. D2922, Density of Soil and Soil Aggregate in Place by Nuclear Methods

3. D1557, Moisture Density Relations of Soils and Soil Aggregate Mixtures

using 10 lb. Rammer and 18-inch drop.

1.04 QUALITY ASSURANCE

A. Testing of compacted fill materials may be performed by an independent soils

laboratory employed by the Town in accordance with Section 01410. Testing will

be performed so as to minimize interference with the work.

B. When work of this section or portions of work are completed, notify the testing

laboratory to perform density tests. Do not proceed with additional portions of

work until results have been verified.

C. If, during progress of work, tests indicate that compacted materials do not meet

specified requirements, notify Engineer as to direction to proceed. If required by

Engineer, Contractor will remove defective work, replace and retest at no cost to

Town.

Page 112: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02242/2-4

D. Ensure compacted fills are tested before proceeding with placement of surface

materials.

E. Examine existing and finish grades as shown on grading plan and excavation and

fill as indicated on plans and elevations. Protect and maintain site boundaries and

project limits during construction. If disturbed, destroyed or exceeded, repair as

directed by Engineer.

1.05 SUBMITTALS

A. Submit under provisions of Section 01300 for all materials to be used in this

section.

1.06 COORDINATION

A. Coordinate work with Town surveyors for layout and grading.

B. Coordinate with affected utility companies.

1.07 PROTECTION

A. Protect bench marks, monuments, other reference points, existing structures,

roads, sidewalks, paving, curbs, overhead and underground utilities against

damage from equipment and vehicular or foot traffic.

1.08 MEASUREMENT AND PAYMENT

A. Measurement and payment

1. There shall be no separate measurement or payment for the work under

this section as it shall be included in the appropriate bid item (i.e. concrete

sidewalk, concrete curb, etc...).

PART 2 - PRODUCTS

2.01 MATERIALS

A. Processed Gravel: Conform to Article M.02.06 Grading "C" of Form 818.

PART 3 - EXECUTION

3.01 PLACING

A. The processed gravel shall be spread upon the prepared subgrade in layers of not

over 6 inches in depth after final compaction.

Page 113: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02242/3-4

B. Frozen material shall not be placed on the subbase nor shall the gravel subbase be

placed upon a frozen subgrade. Previously frozen material shall be removed or

shall be otherwise treated as required before new material is placed.

3.02 GRADING

A. Each lift of processed gravel shall be uniformly graded and compacted to produce

a smooth surface and the desired lines and grades are met after compaction.

B. Processed Gravel must be finish graded using a motorized road grader specifically

manufactured for that purpose.

C. Hand grading may be permitted where it is impractical for grading by machinery.

3.03 COMPACTING

A. After the gravel is spread and graded, it shall be thoroughly compacted and bound

by use of equipment specifically manufactured for that purpose. Rollers shall

deliver a ground pressure of not less than 300 pounds per lineal inch of contact

width and shall weigh not less than 10 tons. Vibratory rollers shall have a static

weight of not less than 4 tons.

B. Where it is impractical to use large rollers, mechanical tampers or small rollers

can be used.

C. The dry density after compaction shall not be less than 95 percent of the dry

density for that subbase material when tested in accordance with AASHTO T-180,

Method D. Correction for particles retained on the 3/4 inch sieve shall be as

specified in AASHTO T-224.

D. Water may be used during the compaction and binding operation. Water shall be

applied from an approved watering device and the direction and intensity of the

stream shall be as directed by the Engineer.

E. The compacting and binding operation shall begin at the outside edges,

overlapping the shoulders for a distance of not less than 6 inches and progress

towards the middle, parallel with the centerline of the pavement. The work shall

cover the entire surface of the course with uniform overlapping of each preceeding

track or pass. Areas of super-elevation and special cross slope shall be compacted

by beginning at the lowest edge and proceeding towards the higher edge, unless

otherwise directed by the Engineer.

F. The compacting and binding operation shall be continued until the voids in the

aggregates have been reduced to provide a firm and uniform surface satisfactory

to the Engineer. The amount of compactive effort shall be as directed by the

Engineer, but in no case shall be less than four (4) complete passes of the

compacting and binding operations.

Page 114: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02242/4-4

G. All aggregate shall be completely compacted and bound at the end of each day's

work or when traffic is to be permitted to operate on the road.

H. Should the subbase material become churned up or mixed with the bottom course

material at any time, the Contractor shall, without additional compensation,

remove the mixture. The Contractor shall add new subbase material, if required,

and reshape and recompact the subbase.

I. Any surface irregularities which develop during, or after work, shall be corrected

by loosening material already in place and removing or adding aggregate as

required, after which the entire area, including the surrounding surface, shall be

recompacted and rebound until it is brought to a firm and uniform surface

satisfactory to the Engineer.

END OF SECTION

Page 115: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02275/1-4

SECTION 02275

EROSION CONTROL

PART 1 GENERAL

1.01 WORK INCLUDED

A. The work under this section includes all labor, materials, tools, and equipment

required to provide catch basin protection and any other measures as required or

as directed by the Engineer as necessary to prevent erosion and resulting

sedimentation in areas adjacent to the site.

1.02 RELATED WORK

A. Section 01010 – Summary of Work

B. Section 02230 – Excavating, Backfilling and Compacting for Sidewalks, Curbing,

Driveway Aprons and Roadway Repair.

1.03 REFERENCE STANDARDS

A. Reference Standards:

1. Form 818, State of Connecticut Department of Transportation, Standard

Specifications for Roads, Bridges and Incidental Construction, 2020.

2. The Erosion and Sediment Control Handbook for Connecticut published

by the U. S. Department of Agriculture, Soil Conservation Service.

3. Guidelines for Soil Erosion and Sediment Control - Connecticut,

published by The Connecticut Council on Soil and Water Conservation -

Latest Edition.

1.04 SUBMITTALS

A. Submit under provisions of Section 01300

1.05 MEASUREMENT AND PAYMENT

A. Measurement

1. Shall be by the actual number of linear feet of “Sedimentation Control

System” installed and accepted.

Page 116: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02275/2-4

B. Payment

1. Sedimentation Control System shall be paid for at the contract unit price

per linear foot for “Sedimentation Control System” which price shall

include all materials, tools, equipment, and labor required to complete

installation.

1.04 SITE CONDITIONS

A. Existing Conditions: The Contractor shall examine all work that the work of this

Section is contingent upon, and report any deficiencies to the Engineer.

Commencement of the work will be construed to mean complete acceptance by

the Contractor of the preparatory work of others. No adjustment will be made for

discrepancies brought to the Engineer's attention after work has begun.

B. Protection of Adjacent Lands:

1. The Contractor shall be totally responsible for protection of any lands or

properties as may be subject to any effect or by-product of his

demolition/construction effort. Special care shall be taken to avoid

erosion of fill or cut slopes onto adjacent property or downstream siltation

or diversion of existing surface drainage. Any damage is to be corrected

immediately.

2. Erosion control measures in the locations shown and as detailed and

described in the Contract Documents, shall be considered minimum

requirements and the Contractor shall take whatever other erosion and

sedimentation control steps that are necessary to accommodate his

particular construction procedures.

C. Schedule Procedure:

1. Erosion control construction shall be done prior to the commencement of

demolition, site preparation or earthwork operations. The initial

construction outlined herein is intended to route all practicable surface

water from the excavation area into erosion control facilities. The

Contractor shall install any additional protective measures as may be

required to control siltation from the site.

2. The following sequence of construction shall be followed: Revisions shall

be only with the approval of the Engineer and the responsible municipal

governing agency.

Page 117: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02275/3-4

a. Place sedimentation control measures along slopes, at catch basins

and across swales and outfalls and as shown on the drawings, and

where directed by the Engineer.

b. Proceed with construction of the remaining items of work in

accordance with the approved project sequence and schedule. The

Contractor shall be responsible for maintaining the integrity of all

sediment and erosion control measures for the duration of the

Contract.

c. Clean and maintain all sedimentation control components to

achieve the intended purpose of both temporary and permanent

erosion and sediment control facilities.

PART 2 PRODUCTS

2.01 MATERIALS

A. Silt Fence:

1. Silt Fence Fabric: Conform to the requirements of Article M.08.01-19 of

Form 818. The fabric used must be recommended by its manufacturer for

use as silt fencing, minimum 30 inches high, fastened to posts.

PART 3 EXECUTION

3.01 INSTALLATION

A. Catch Basins:

1. Existing catch basins shall be wrapped with filter fabric and ringed with

hay bales.

3.02 MAINTENANCE AND CLEANING

A. General: All temporary erosion and sedimentation control devices shall be

maintained and cleaned as required from the time of their installation until their

final removal. Permanent erosion control devices shall be maintained and cleaned

as required until their final acceptance.

Page 118: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02275/4-4

B. Erosion Control Supervisor:

1. The Contractor shall name one (1) individual as his sediment and erosion

control supervisor whose responsibility will be maintenance and repair of

all on-site erosion and control measures. He will keep a daily log of his

activities and an updated schedule of proposed construction activities. The

log shall be made available to the local authority as well as any

State/Federal Inspectors.

3.03 REMOVAL AND CLEAN UP

A. At the end of construction, when turf is established, remove and legally dispose

of, off site, all non-permanent erosion control devices and restore the damaged

areas. Leave the site neat and clean.

END OF SECTION

Page 119: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

SECTION 02511

BITUMINOUS CONCRETE PAVING

PART 1 GENERAL

1.01 WORK INCLUDED

A. The work under this section includes all labor, materials, tools, and equipment

necessary for the installation of bituminous concrete pavement in the roadway to the

grades and compacted thicknesses as shown on the plans.

1.02 RELATED WORK

A. Section 01300 - Submittals

B. Section 01410 - Testing Laboratory Services

C. Section 02240 - Subgrade

1.03 REFERENCE STANDARDS

A. Form 818 - State of Connecticut Department of Transportation Standards

Specifications for Roads, Bridges, and Incidental Construction, 2020.

B. AASHTO - American Association of State Highway and Transportation Officials

Standards and Supplements.

C. ASTM - American Society for Testing and Materials.

1.04 SUBMITTALS

A. Submit under provisions of Section 01300.

B. Bituminous Concrete Paving: Material certificates signed by material producer and

Contractor, certifying compliance with specifications for bituminous concrete.

1.05 MEASUREMENT AND PAYMENT

A. Measurement

1. Shall be by the actual tons of bituminous concrete (HMA S0.375 and HMA

S0.5) laid to the compacted thickness, lines, and grades as shown on the

plans.

2. Bituminous concrete weight slips from an approved scale, shall be used as

measurement of the weight.

02511/1-7

Page 120: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

B. Payment

1. Bituminous concrete shall be paid for at the Contract unit price per ton for

"HMA S*" for each class listed in the bid form which price shall include all

materials, tools, equipment and labor required to complete the paving.

PART 2 PRODUCTS

2.01 MATERIALS

A. Bituminous Concrete:

1. Mixtures, sources of supply, formula for mix, mix tolerances, approval of

mix formula and control of mixture for bituminous pavements shall conform

to the requirements of Section M.04 of Form 818.

2. Classification of bituminous concrete shall conform to the superpave master

ranges for bituminous concrete mixture design criteria as required in Section

M.04of Form 818 as shown on the Drawing.

B. Tack Coat:

1. Tack coat shall conform to the requirements of Section M.04 of Form 818.

PART 3 EXECUTION

3.01 EXAMINATION

A. The Contractor and the Engineer shall jointly inspect the site prior to beginning the

paving operations. Any deficiencies found shall be corrected prior to the start of the

paving work. The beginning of paving operations shall indicate acceptance of the

site conditions as suitable for the paving work.

3.02 TRANSPORTATION OF MIXTURE

A. Mixture shall be transported from the mixing plant in trucks having tight bodies

which have previously been cleaned of all foreign material.

B. Use of kerosene, gasoline, fuel oil or similar products for the coating of the inside of

truck bodies is strictly prohibited. Truck body coatings may consist of soapy water

or commercial oil emulsions (also known as soluble oils) in the proportions

recommended by the manufacturer. If such coatings are applied, truck bodies shall

be raised immediately prior to loading to remove any excess coating material.

C. Loaded trucks shall be tightly covered with waterproof canvas or other suitable

covers. Mesh-type covers are prohibited. Both front and rear of the cover must be

fastened to minimize air infiltration.

02511/2-7

Page 121: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

D. Hot mixed bituminous concrete shall be delivered at a temperature that is within 25°

F of the approved job mix formula.

3.03 PAVING EQUIPMENT

A. Paving equipment shall be of the self-powered type with an adapter to provide

guidance of the screeding action. Screed or strike-off member shall be adjustable to

the shape of the cross section of the finished pavement. Some method shall be

provided for the tilting of the screed while in operation to secure the proper "drag"

and to provide the compressive screeded surface required.

B. The machine shall have a sufficient number of driving wheels so there will be no

undue amount of slippage. Whenever the design of the equipment and plan of

operation are such that the driving wheels travel on the finished surface of a

completed pavement, said wheels shall be equipped with rubber tires or other means

to protect the finished surface.

C. Screeding members shall be preheated, and means shall be provided for heating the

screeding members by some method that will prevent accumulation of bituminous

material.

3.04 PLACING OF MIXTURE

A. Mixture shall not be placed when weather conditions of fog or rain prevail nor when

the pavement surface shows signs of any moisture.

B. Mixture shall be placed only when the base temperature is above 40° F and the

depth of pavement to be placed is a minimum of 1-1/2 inches. For a 1 inch depth of

pavement to be placed, the base temperature shall be above 50° F.

C. When overtaken by sudden storms, the Engineer may permit work to continue up to

the amount which may be in transit from the plant at the time, provided the mixture

is within temperature limits specified.

D. At time of placement, the mixture shall be within 25° F+ of the temperature

specified in the approved mix formula.

E. Upon arrival, mixture shall be dumped into the approved mechanical spreader and

immediately spread and struck off to the full width required and to such appropriate

loose depth for each successive course that when the work is completed, the

designed depth will be obtained.

F. Hopper and tunnel shall be properly loaded at all times during the paving operations.

02511/3-7

Page 122: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

G. Before any rolling is started, the finished surface struck by the machine shall be

checked. Any imperfections shall be repaired and all "dripping", i.e., fat, sandy

accumulations from the screed, and all fat spots from any source, shall be removed

and replaced with satisfactory material.

H. In areas where, because of physical limitations, it is impractical to operate paving

equipment, the Engineer may permit use of other type spreaders or the mixture may

be spread and screeded by hand.

1. When hand-spreading is permitted, upon arrival, the mixture shall be

dumped on approved steel dump sheets outside of the area on which it is to

be spread, and shall then be immediately distributed into place by means of

suitable shovels and other tools, and spread with metal lutes in a uniformly

loose layer of such depth as will result in a completed pavement having the

designed depth. Any deviation from standard crown or section shall be

immediately remedied by placing the additional material or removing

surplus as directed.

I. Contact surfaces of curbing, gutters, manholes, etc., shall be painted with a thin

uniform tack coat just before the mixture is placed against them. Such a tack coat

shall not be paid for.

J. A very light, web-like tack coat shall be applied to the entire pavement base before

paving the surface course if the base has been in place longer than five calendar

days. Emulsions for tack coat shall be diluted 50/50 with water and shall not be

heated in excess of 160° F. Care must be taken not to apply too heavy a coating:

application rate of the diluted emulsion shall be 0.03 to 0.10 gallons per square yard.

The emulsion shall be applied by a pressurized spray method. The equipment used

and method of placing an overall tack coat must be approved by the Engineer.

K. Refueling of equipment is prohibited in any location on the paving project where

fuel might come in contact with bituminous concrete mixtures already placed or to

be placed.

L. Solvents and cleaners for use in cleaning mechanical equipment or hand tools shall

be stored well clear of areas paved or to be paved. Before any such equipment and

tools are cleaned, they shall be moved off the paved or to-be-paved area, and they

shall not be returned for use until after they have been allowed to dry.

3.05 COMPACTION

A. After placing, each course shall be compacted to meet the following density

requirements:

02511/4-7

Page 123: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

1. The in-place density of each layer or course of mixture of bituminous

concrete placed shall be compacted to a density of at least 92 percent and no

more than 97 percent of the theoretical void-free density as determined by

AASHTO T209.

2. Theoretical densities shall be determined by AASHTO T209.

B. Cessation temperature for continued compaction of the mat shall be 175° F.

C. Compaction equipment, whether vibratory or non-vibratory, must be of a type and

size approved by the Engineer. Such equipment must be maintained in proper

operating condition and must be ready, at the job site, prior to delivery of

bituminous concrete.

D. On certain bridge deck overlays and paving jobs where, due to physical limitations,

a full roller contingent is not practical, utilize a lesser number of rollers, provided all

compaction requirements are met.

E. Non-vibratory Rollers:

1. In general, rolling shall consist of initial or breakdown rolling, intermediate

rolling and final or finish rolling. Rolling shall be performed with at least

two power-driven steel-wheel tandem or 3-wheel roller weighing not less

than 10 tons.

2. Intermediate rolling may be done with a self-propelled pneumatic tire roller.

If a pneumatic tire roller is used, it shall be equipped with wide-tread

compaction tires capable of exerting an average contact pressure from 60 to

90 pounds per square inch uniformly over the surface, adjusting ballast and

tire inflation pressure as required. Furnish evidence regarding tire size,

pressure and loading to confirm that the proper contact pressure is being

developed and that the loading and contact pressure are uniform for all

wheels.

3. All non-vibratory rollers shall travel at a speed no greater than 5 mph (440

fpm).

F. Vibratory Rollers:

1. A vibratory roller may be included in the compaction train providing the

vibratory roller is operated in accordance with the manufacturer's

recommendations. The vibratory roller shall be of a self-propelled type

specifically designed for the compaction of bituminous concrete.

02511/5-7

Page 124: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

2. Vibratory rollers shall be equipped with a speed control device which shall

be set to prevent the roller from traveling in excess of 2-1/2 mph or 220 fpm

when the roller is operating in a vibratory mode, and 5 mph or 440 fpm

when the roller is operating in a static mode.

3. Vibratory rollers shall be shut off from the vibrating mode when reversing

directions. Vibratory rollers shall be equipped with automatic reversing

eccentrics (weights).

4. One vibratory roller may be substituted for both a breakdown roller and

pneumatic roller for the compacting train. The course shall be finish-rolled

with a steel-wheel tandem roller having a minimum weight of 10 tons.

5. Dual vibrating drum roller meeting the requirements of a steel-wheel tandem

roller and operating in the static mode may be used as the finish roller,

however, this single vibratory shall not be used as both the breakdown roller

and the finish roller.

6. One vibratory roller and one steel-wheel tandem roller shall be provided for

each single-lane paver. The type(s) of rollers and number must be approved

by the Engineer.

7. THE USE OF A VIBRATORY ROLLER IN THE DYNAMIC OR

VIBRATORY MODE IS STRICTLY PROHIBITED ON BRIDGE

DECKS OR CONCRETE STRUCTURES.

8. The Contractor assumes full responsibility for the cost of repairing all

damages which may occur to highway components and adjacent property. If

the Engineer determines that the compaction obtained is less than that

specified, or damage to highway components and/or adjacent property

occurs with the use of the vibratory compaction equipment, the Contractor at

no additional expense, shall immediately cease using the equipment and

shall proceed with the work in accordance with the conventional compaction

procedure outlined in the specifications.

3.06 SURFACE TEST OF THE PAVEMENT

A. Random spot-checks shall be performed with a contractor supplied, standard ten

foot straightedge. Provide or designate some employee whose duty it is to use the

straightedge under the observation of the Engineer.

02511/6-7

Page 125: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

B. Finished pavement shall not vary more than 1/4 inch from a 10 foot straightedge

applied parallel to the centerline of the pavement. Any irregularity of the surface

exceeding the above limits shall be corrected. Depressions which may develop after

the initial rolling shall be remedied. Such compression or compositions, or that do

not comply with the requirements of the specifications shall be taken up, removed

and replaced with suitable mixture, properly laid in accordance with these

specifications at the expense of the Contractor.

C. The surface of the finished base course shall not vary by more than 3/8 inch from a

10 foot straightedge applied perpendicular to the centerline of the pavement.

3.07 JOINTS

A. Placement of the bituminous material shall be as continuous as possible. Rollers

shall not pass over the unprotected end of a freshly-placed mixture.

B. Transverse joints shall be formed by cutting back on the previous run, existing

bituminous concrete pavement, or bituminous concrete driveways to expose the full

depth of the course. Waste materials shall be disposed of in an acceptable manner.

C. On cold joints, a brush coat of asphaltic material or approved equal shall be used on

contact surfaces of transverse and longitudinal joints just before additional mixture

is placed against the previously rolled material.

D. The longitudinal joint in one layer shall offset the previous joint in the layer

immediately below by approximately six inches. However, the joint in the top

layer shall be at the centerline of the roadway.

E. In compacting the joint, the steel-wheel roller shall be shifted onto the previously

placed lane so that only 1 or 2 inches of the drive wheel extends over the

uncompacted material. The steel wheel roller shall continue to roll along this line

and its position shifted gradually across the joint until the joint has been rolled with

the entire width of the drive wheel. Rolling with steel wheel and pneumatic-tired

rollers shall be continued until a thoroughly compacted, neat joint is obtained.

F. When the vibratory roller is used for breakdown rolling, compacting the joint shall

be accomplished with the roller on the uncompacted material shifted 1 to 2 inches

across the joint onto the previously placed lane.

END OF SECTION

02511/7-7

Page 126: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

SECTION 02514

BITUMINOUS CONCRETE CURBING

PART 1 GENERAL

1.01 WORK INCLUDED

A. The work under this section includes all labor, materials, tools, and equipment

necessary for the installation of a machine-laid bituminous concrete curbing on

the pavement in the locations and to the dimensions shown on the plans.

1.02 RELATED WORK

A. Section 01300 - Submittals

B. Section 01400 - Quality Control

C. Section 01410 - Testing Laboratory Services

D. Section 02511 - Bituminous Concrete Paving

1.03 REFERENCE STANDARDS

A. Form 818 - State of Connecticut Department of Transportation, Standard

Specification for Roads, Bridges, and Incidental Construction, 2020.

B. AASHTO - American Association of State Highway and Transportation Officials

Standards and Supplements.

C. ASTM - American Society for Testing and Materials.

1.04 SUBMITTALS

A. Submit under provisions of Section 01300.

B. Bituminous Concrete Curbing: Material certificates signed by material producer

and Contractor, certifying compliance with specifications for bituminous concrete.

02514/1-4

Page 127: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

1.05 MEASUREMENT AND PAYMENT

A. Measurement

1. Shall be by the linear feet of bituminous concrete curbing laid to the lines

as shown on the plans.

B. Payment

1. Bituminous Concrete Curbing shall be paid for at the Contract unit price

per linear foot for "Bituminous Concrete Curbing" listed in the bid form

which price shall include all materials, tools, equipment and labor required

to complete the installation.

PART 2 PRODUCTS

2.01 MATERIALS

A. Bituminous concrete:

1. Mixtures, sources of supply, formula for mix, mix tolerances, approval of

mix formula and control of mixture for bituminous pavements shall

conform to the requirements of Section M.04 of Form 818.

2. Bituminous concrete shall conform to control points for curb mix mixtures

as shown in Table M.04.02-1 of Form 818.

B. Tack Coat:

1. Tack coat shall be RS-1 conforming to Section M.04 of form 818.

PART 3 EXECUTION

3.01 TRANSPORTATION OF MIXTURE

A. Mixture shall be transported from the mixing plant in trucks having tight bodies

which have previously been cleaned of all foreign material.

B. Use of kerosene, gasoline, fuel oil or similar products for the coating of the inside

of truck bodies is strictly prohibited. Truck body coatings may consist of soapy

water or commercial oil emulsions (also known as soluble oils) in the proportions

recommended by the manufacturer. If such coatings are applied, truck bodies

shall be raised immediately prior to loading to remove any excess coating

material.

02514/2-4

Page 128: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

C. Loaded trucks shall be tightly covered with waterproof canvas or other suitable

covers. Mesh-type covers are prohibited. Both front and rear of the cover must

be fastened to minimize air infiltration.

D. Hot mixed bituminous concrete shall be delivered at a temperature that is within

25° F of the approved job mix formula.

3.02 SURFACE PREPARATION

A. Prior to the arrival of the mixture on the site, the surface of the pavement where

the curbing is to be constructed shall be cleaned of all loose and foreign

material. The surface, which shall be perfectly dry and clean at the time the mix is

placed and shall be coated with the tack coat just prior to placing the mixture.

3.03 TEMPERATURE REQUIREMENTS

A. Mixture shall be placed only when the air temperature is above 40° F.

B. When overtaken by sudden storms, the Engineer may permit work to continue up

to the amount which may be in transit from the plant at the time, provided the

mixture is within temperature limits specified.

C. At time of placement, the mixture shall be within 25° F+ of the temperature

specified in the approved mix formula.

3.04 INSTALLATION

A. On arrival at the site, the mixture shall be transferred from the truck to the hopper

of the curbing machine; and the mixture shall be kept clean and free from dirt and

foreign materials at all times.

B. The surface of the curbing shall be tested with a 10-foot straightedge, and any

variation from a true line exceeding 1/4 inch shall be satisfactorily corrected. The

only compaction required shall be that obtained by the approved mechanical

curbing machine.

C. Where machine work is impractical, the Engineer may permit hand-laid curbing to

be constructed.

D. If the design of the curbing machine is such that the outside wheels operate

outside of the curb, the Contractor will be required to obtain a smooth surface by

grading and consolidating the area on which the outside wheel of the machine

rides, and this work shall be done at his expense.

02514/3-4

Page 129: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

3.05 PROTECTION

A. After the completion of curbing, traffic shall be kept at a safe distance for a period

of not less than 24 hours and until the curbing has set sufficiently to prevent injury

to the work.

B. The Contractor shall replace any broken or damaged curbing that occurs, until

completion of the project, at no additional expense to the Town.

END OF SECTION

02514/4-4

Page 130: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

SECTION 02515

BITUMINOUS CONCRETE SIDEWALKS

PART 1 - GENERAL

1.01 WORK INCLUDED

A. The work under this section includes the furnishing of all Labor, Materials, Tools,

and equipment necessary for the construction of Bituminous Concrete (Asphalt)

sidewalks to the lines, grades, and details shown on the plans.

1.02 RELATED WORK

A. Section 01300 - Submittals

B. Section 01400 - Quality Control

C. Section 01410 - Testing Laboratory Services

D. Section 02230 – Excavating, Backfilling and Compacting for Sidewalks, Curbing,

Driveway Aprons and Roadway Repair.

1.03 REFERENCE STANDARDS

A. Form 818 - State of Connecticut Department of Transportation Standard

Specifications for Roads, Bridges and Incidental Construction, 2020.

B. AASHTO - American Association of State Highway and Transportation Officials

Standards and Supplements

C. ASTM - American Society for Testing and Materials

1.04 SUBMITTALS

A. Submit under provisions of Section 01300.

B. Bituminous Concrete: Material Certificates signed by material producer and

Contractor, certifying compliance with specifications for Bituminous Concrete.

1.05 MEASUREMENT AND PAYMENT

A. Measurement

1. Bituminous Concrete sidewalks shall be measured by the square footage

02515/1-5

Page 131: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

of sidewalk installed to the lines and grades as shown on the plans.

2. Excavation, preparation of subgrade and installation of gravel base shall

be included for payment under this section.

B. Payment

1. Bituminous concrete sidewalk shall be paid for at the contract unit price

per square foot for "Bituminous Concrete Sidewalk", which price shall

include all materials, tools, equipment and labor (including excavation,

preparation of subgrade, and gravel base) required to complete the

sidewalks.

PART 2 - PRODUCTS

2.01 MATERIALS

A. Bituminous concrete:

1. Mixtures, sources of supply, formula for mix, mix tolerances, approval of

mix formula and control of mixture for bituminous pavements shall

conform to the requirements of Section M.04. of Form 818.

2. Classification of bituminous concrete shall conform to S0.375 as required

in Section M.04.02 of Form 818.

PART 3 - EXECUTION

3.01 EXCAVATION AND BASE PREPARATION

A. Excavate, prepare subgrade, and install gravel base in accordance with Section

02230.

3.02 FORMING

A. Set clean timber or metal forms true to line. Firmly stake forms in place, strong

enough to resist the pressure of paving without springing.

3.03 TRANSPORTATION OF MIXTURE

A. Mixture shall be transported from the mixing plant in trucks having tight bodies

which have previously been cleaned of all foreign material.

02515/2-5

Page 132: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

B. Use of kerosene, gasoline, fuel oil or similar products for the coating of the inside

of truck bodies is strictly prohibited. Truck body coatings may consist of soapy

water or commercial oil emulsions (also known as soluble oils) in the proportions

recommended by the manufacturer. If such coatings are applied, truck bodies

shall be raised immediately prior to loading to remove any excess coating

material.

C. Loaded trucks shall be tightly covered with waterproof canvas or other suitable

covers. Mesh-type covers are prohibited. Both front and rear of the cover must

be fastened to minimize air infiltration.

D. Hot mixed bituminous concrete shall be delivered at a temperature that is within

25° F of the approved job mix formula.

3.04 PLACING OF MIXTURE

A. Mixture shall not be placed when weather conditions of fog or rain prevail nor

when the pavement surface shows signs of any moisture.

B. Mixture shall be placed only when the base temperature is above 40° F and the

depth of pavement to be placed is a minimum of 1-1/2 inches. For a 1 inch depth

of pavement to be placed, the base temperature shall be above 50° F.

C. When overtaken by sudden storms, the Engineer may permit work to continue up

to the amount which may be in transit from the plant at the time, provided the

mixture is within temperature limits specified.

D. At time of placement, the mixture shall be within 25° F+ of the temperature

specified in the approved mix formula.

E. Upon arrival, mixture shall be dumped into the formed sidewalk and immediately

spread with metal lutes and struck off to the full width required and to such

appropriate loose depth that when the work is completed, the designed depth will

be obtained.

F. Contact surfaces of curbing, gutters, manholes, etc., shall be painted with a thin

uniform tack coat just before the mixture is placed against them. Such a tack coat

shall not be paid for.

G. Refueling of equipment is prohibited in any location on the paving project where

fuel might come in contact with bituminous concrete mixtures already placed or to

be placed.

H. Solvents and cleaners for use in cleaning mechanical equipment or hand tools

shall be stored well clear of areas paved or to be paved. Before any such

equipment and tools are cleaned, they shall be moved off the paved or to-be-paved

area, and they shall not be returned for use until after they have been allowed to

dry.

02515/3-5

Page 133: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

3.05 COMPACTION

A. After placing, the bituminous concrete shall be compacted by multiple passes of a

roller weighing not less than 500 pounds to meet the following density

requirements:

1. The in-place density of each layer or course of mixture of Class 2 placed

shall be compacted to a density of at least 92 percent and no more than 97

percent of the theoretical void-free density as determined by AASHTO

T209.

2. Theoretical densities shall be determined by AASHTO T209.

B. Cessation temperature for continued compaction of the mat shall be 175° F.

C. Compaction equipment must be maintained in proper operating condition and

must be ready, at the job site, prior to delivery of bituminous concrete.

3.06 SURFACE TEST OF THE PAVEMENT

A. Random spot-checks shall be performed with a Contractor supplied, standard ten-

foot straight-edge. Provide or designate some employee whose duty it is to use

the straight-edge under the observation of the Engineer.

B. Finished bituminous concrete sidewalks shall not vary more than 1/4 inch from a

10 foot straight-edge applied parallel to the centerline of the sidewalk. Any

irregularity of the surface exceeding the above limits shall be corrected.

Depressions which may develop after the initial rolling shall be remedied. Such

compression or compositions, or other irregularities that do not comply with the

requirements of the specifications shall be taken up, removed and replaced with

suitable mixture, properly laid in accordance with these specifications at the

expense of the Contractor.

C. The surface of the finished bituminous concrete sidewalk shall not vary by more

than 3/8 inch from a 10 foot straight-edge applied perpendicular to the centerline

of the sidewalk.

3.07 JOINTS

A. Placement of the bituminous material shall be as continuous as possible. Rollers

shall not pass over the unprotected end of a freshly-placed mixture.

B. Transverse joints shall be formed by cutting back on the previous run, or existing

bituminous concrete sidewalk to expose the full depth of the course. Waste

materials shall be disposed of in an acceptable manner.

02515/4-5

Page 134: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

C. On cold joints, a brush coat of asphaltic material or approved equal shall be used

on contact surfaces of transverse joints just before additional mixture is placed

against the previously rolled material.

END OF SECTION

02515/5-5

Page 135: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

SECTION 02518

SAWCUT AND SEAL BITUMINOUS CONCRETE

PART 1 GENERAL

1.01 WORK INCLUDED

A. The work under this section includes all labor, tools, materials, and equipment

necessary for saw-cutting and sealing bituminous concrete pavement at the

locations shown on the plans, or as directed by the Engineer.

1.02 RELATED WORK

A. Section 01300 - Submittals

B. Section 01400 – Quality Control

C. Section 02511 - Bituminous Concrete Paving

1.03 REFERENCE STANDARDS

A. Form 818 - State of Connecticut Department of Transportation Standard

Specifications for Roads, Bridges, and Incidental Construction, 2020.

1.04 SUBMITTALS

A. Submit under provisions of Section 01300.

1.05 MEASUREMENT AND PAYMENT

A. Measurement

1. There shall be no separate measurement or payment for the work under

this section as it shall be included in the appropriate bid item (i.e. concrete

sidewalk, concrete curb, etc...).

PART 2 PRODUCTS

2.01 MATERIALS

A. Joint Seal Material shall conform to the requirements of Article M.04, Form

818.

02518/1-2

Page 136: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

PART 3 EXECUTION

3.01 CONSTRUCTION METHODS

A. Sawing, cleaning, and sealing of joints shall conform to the requirements of

Section 4.06.03, Form 818 and in accordance with the joint seal material

manufacturer.

END OF SECTION

02518/2-2

Page 137: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

SECTION 02520

CONCRETE SIDEWALKS

PART 1 GENERAL

1.01 WORK INCLUDED

A. The work under this section includes the furnishing of all labor, materials, tools,

and equipment necessary for the construction of concrete sidewalks to the lines,

grades and details as shown on the plans.

B. Handicap ramps shall be considered part of the concrete sidewalk and shall be

built to the dimensions as shown on the plans.

1.02 RELATED WORK

A. Section 01300 - Submittals

B. Section 01400 - Quality Control

C. Section 01410 - Testing Laboratory Services

D. Section 02230 - Excavating, Backfilling, and Compacting for Sidewalks, Curbing,

Driveway Aprons, and Roadway Repair

1.03 REFERENCE STANDARDS

A. Form 818 - State of Connecticut Department of Transportation, Standard

Specifications for Roads, Bridges and Incidental Construction, 2020.

B. ACI - American Concrete Institute

C. ASTM - American Society for Testing and Materials

1.04 SUBMITTALS

A. Submit under provisions of Section 01300.

B. Concrete: Manufacturer's product data, test reports, mix design and materials

certifications.

02520/1-4

Page 138: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

1.05 MEASUREMENT AND PAYMENT

A. Measurement

1. Concrete sidewalks shall be measured by the square footage of sidewalk

installed to the lines and grades as shown on the plans.

2. Excavation, preparation of subgrade and installation of gravel base shall

be included for payment under this section.

B. Payment

1. Concrete sidewalk shall be paid for at the contract unit price per square

foot for "Concrete Sidewalk", which price shall include all materials,

tools, equipment and labor (including excavation, preparation of subgrade,

and gravel base) required to complete the sidewalks.

PART 2 PRODUCTS

2.01 MATERIALS

A. Concrete:

1. Cement shall meet ASTM C150 or C595 Type II.

2. Mixing water shall be clean and free from injurious amounts of oils, acids,

alkalis, organic materials or other deleterious substances in accordance

with ACI 318.

3. Air-entraining admixture shall conform to ASTM C260.

4. Any other admixtures shall only be used if approved by the Engineer.

5. Concrete shall have the following properties:

a. Materials shall be proportioned to produce concrete with a

minimum compressive strength of 3,500 psi at 28 days.

b. The air content shall be 5 percent by volume with a tolerance of +

2 percent.

c. Maximum size of aggregate shall be 3/4".

d. Minimum cement content shall be 520 pounds per cubic yard.

02520/2-4

Page 139: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

e. Concrete shall be delivered at the minimum slump necessary for

efficient mixing, placing and finishing. The maximum slump shall

be 4 in. with a tolerance of + 1 in.

f. The concrete shall be batched and mixed in accordance with

ASTM C94.

B. Premolded Joint Filler: Preformed strips, non-extruding and resilient bituminous

type, of thickness indicated, complying with ASTM D994.

C. Welded Wire Fabric: Cold-drawn steel wire conforming to ASTM A185 or A497

and the sizes indicated on the plans.

PART 3 EXECUTION

3.01 EXCAVATION AND BASE PREPARATION

A. Excavate, prepare subgrade, and install gravel base in accordance with Section

02230.

3.02 FORMING

A. Set clean timber or metal forms true to line. Firmly stake forms in place, strong

enough to resist the pressure of concrete without springing, and tight enough to

prevent mortar leakage. Tops of forms shall be at exact finished grade.

3.03 CONCRETING

A. Spade concrete thoroughly along forms and expansion joints. Vibrate, tamp and

screed to a dense mass.

B. Provide 1/2 inch wide premolded expansion joints. Cut back joints 1/4 inch

below finish of pavement. Provide additional expansion joints around utility

structures and where concrete abuts other structures.

C. After concrete is placed, screeded, bullfloat and steel trowel to a smooth even

surface. Bring sufficient mortar to the surface for the finish.

D. Score contraction joints using scoring tool while concrete is workable.

E. Broom finish using new street broom. Bristle marks shall be perpendicular to the

length of the sidewalk.

F. Finish the outside edge of the slab and all joints with a 1/4" radius edging tool.

Dummy joints must be straight and perpendicular to the sides of the

sidewalk. The greatest allowable ridge formed by the back of the edging or

jointing tool is 1/8".

02520/3-4

Page 140: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

G. The finished surface will be checked with a 5' straight-edge. No dips or rises over

1/8" in the surface of the sidewalk will be permitted.

H. Forms shall not be removed from freshly placed concrete until it has set for at

least 24 hours. After the forms have been removed, the ends of all joints shall be

cleaned and any "honeycombed" areas shall be patched with cement.

3.04 CURING

A. Moist Curing

1. After the surface of the concrete has been given its final finish and has

adequately set, it shall be protected by covering it with either impervious

sheets of plastic or paper.

2. Sheets shall be laid longitudinally over the surface of the finished walk by

unrolling from a supported roll so as not to bring excessive weight upon,

nor mar the new surface. Cover material shall be securely weighted down.

3. Sheets shall be kept on the sidewalk for five days. During this period,

concrete shall be kept thoroughly wet at all times.

4. In the event that hair checking develops before the cover can be placed,

moist curing mats shall be used for the initial 24 hour period.

B. Membrane Curing

1. Apply suitable curing agent in accordance with the manufacturer's

specifications. Membrane curing shall be applied in the presence of the

Engineer and contain a fugitive dye to insure thorough application.

3.05 Protection

A. After the completion of the walks and driveway aprons, traffic shall be kept at a

safe distance for a period of not less than 24 hours or until the concrete has set

sufficiently to prevent injury to the work.

B. Replace any broken or damaged walks and driveway aprons, until completion of

the project, or acceptance of the road.

END OF SECTION

02520/4-4

Page 141: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

SECTION 02521

CONCRETE CURBING

PART 1 GENERAL

1.01 WORK INCLUDED

A. This section covers the furnishing of all labor, materials, tools and equipment

necessary for the construction of concrete curbing to the lines, grades and details

as shown on the plans.

B. Excavation, subgrade preparation, gravel base, and backfill shall be included in

this section.

1.02 RELATED WORK

A. Section 01300 - Submittals

B. Section 01400 - Quality Control

C. Section 01410 - Testing Laboratory Services

D. Section 02230 - Excavating, Backfilling, and Compacting for Sidewalks, Curbing,

Driveway Aprons, and Roadway Repair.

1.03 REFERENCE STANDARDS

A. Form 818 - State of Connecticut Department of Transportation Standards

Specifications for Roads, Bridges and Incidental Construction, 2020.

B. ACI - American Concrete Institute

C. ASTM - American Society for Testing and Materials

1.04 SUBMITTALS

A. Submit under provisions of Section 01300.

B. Concrete: Manufacturer's product data, test reports, mix design and materials

certifications.

C. Pre-cast curbing: Manufacturer's product data, test reports, mix design and

materials certifications.

02521/1-5

Page 142: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

1.05 MEASUREMENT AND PAYMENT

A. Measurement

1. Concrete curbs shall be measured by the linear foot of concrete curbing

installed to the lines and grades as shown on the plans.

2. Excavation, preparation of subgrade and installation of gravel base shall

be included for payment under this section.

B. Payment

1. Concrete curbing shall be paid for at the contract unit price per linear foot

for "Concrete Curbing", which price shall include all materials, tools,

equipment and labor required to complete the concrete curbing.

PART 2 PRODUCTS

2.01 MATERIALS

A. Concrete:

1. Cement shall meet ASTM C150 or C595 Type II.

2. Mixing water shall be clean and free from injurious amounts of oils, acids,

alkalies, organic materials or other deleterious substances in accordance

with ACI 318.

3. Air-entraining admixture shall conform to ASTM C260.

4. Any other admixtures shall only be used if approved by the Engineer.

5. Concrete shall have the following properties:

a. Materials shall be proportioned to produce concrete with a

minimum compressive strength of 3,500 psi at 28 days.

b. The air content shall be 5 percent by volume with a tolerance of +

2 percent.

c. Maximum size of aggregate shall be 3/4".

d. Minimum cement content shall be 520 pounds per cubic yard.

02521/2-5

Page 143: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

e. Concrete shall be delivered at the minimum slump necessary for

efficient mixing, placing and finishing. The maximum slump shall

be 4 in. with a tolerance of + 1 in.

f. The concrete shall be batched and mixed in accordance with

ASTM C94.

B. Premolded Joint Filler: Preformed strips, non-extruding and resilient bituminous

type, of thickness indicated, complying with ASTM D994.

C. Welded Wire Fabric: Cold-drawn steel wire conforming to ASTM A185 or A497

and the sizes indicated on the plans.

PART 3 EXECUTION

3.01 EXCAVATION AND BASE PREPARATION

A. Excavate, prepare subgrade, and install gravel base in accordance with Section

02230.

3.02 FORMING

A. Set clean timber or metal forms true to line. Firmly stake forms in place, strong

enough to resist the pressure of concrete without springing, and tight enough to

prevent mortar leakage. Tops of forms shall be at exact finished grade.

3.03 CONCRETING

A. Spade concrete thoroughly along forms and expansion joints. Vibrate, tamp and

screed to a dense mass.

B. Provide 1/2 inch wide premolded expansion joints. Cut back joints 1/4 inch

below finish of pavement. Provide additional expansion joints around utility

structures and where concrete abuts other structures.

C. After concrete is placed, screeded, bullfloat and steel trowel to a smooth even

surface. Bring sufficient mortar to the surface for the finish.

D. Score contraction joints using scoring tool while concrete is workable.

E. Broom finish using new street broom. Bristle marks shall be perpendicular to the

length of the sidewalk.

02521/3-5

Page 144: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

F. Finish the outside edge of the slab and all joints with a 1/4" radius edging tool.

Dummy joints must be straight and perpendicular to the sides of the sidewalk.

The greatest allowable ridge formed by the back of the edging or jointing tool is

1/8".

G. The finished surface will be checked with a 5' straight-edge. No dips or rises over

1/8" in the surface of the sidewalk will be permitted.

H. Forms shall not be removed from freshly placed concrete until it has set for at

least 24 hours. After the forms have been removed, the ends of all joints shall be

cleaned and any "honeycombed" areas shall be patched with cement.

3.04 CURING

A. Moist Curing

1. After the surface of the concrete has been given its final finish and has

adequately set, it shall be protected by covering it with either impervious

sheets of plastic or paper.

2. Sheets shall be laid longitudinally over the surface of the finished walk by

unrolling from a supported roll so as not to bring excessive weight upon,

nor mar the new surface. Cover material shall be securely weighted down.

3. Sheets shall be kept on the sidewalk for five days. During this period,

concrete shall be kept thoroughly wet at all times.

4. In the event that hair checking develops before the cover can be placed,

moist curing mats shall be used for the initial 24 hour period.

B. Membrane Curing

1. Apply suitable curing agent in accordance with the manufacturer's

specifications. Membrane curing shall be applied in the presence of the

Engineer and contain a fugitive dye to insure thorough application.

3.05 Protection

A. After the completion of curbing, traffic shall be kept at a safe distance for a period

of not less than 24 hours or until the curbing has set sufficiently to prevent injury

to the work.

B. Replace any broken or damaged curbing, until completion of the project, or

acceptance of the road.

02521/4-5

Page 145: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

3.06 Pre-Cast Curbing

A. Concrete used for pre-cast curbing shall meet the requirements of section 2.01 of

this specification for concrete curbing.

B. The profile for pre-cast curbing shall match that of cast-in-place curbing.

C. On curve with a radius of 100’ or less, pre-cast curbs shall be curved to conform

to the required radius (straight sections will not be allowed).

D. Excavate, prepare subgrade and install processed gravel in accordance with

Section 02230.

E. Set the top of the curb to finished grade. Dowel pre-cast curbing sections together.

Backfill around the pre-cast curbing with processed gravel to ensure it remains in

position during and after construction.

END OF SECTION

02521/5-5

Page 146: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

SECTION 02522

INTEGRAL CONCRETE SIDEWALKS, CURBS AND DRIVEWAY APRONS

PART 1 GENERAL

1.01 WORK INCLUDED

A. The work under this section includes all labor, materials, tools, and equipment

necessary for the construction of integral concrete sidewalks, curbs and driveway

aprons to the lines, grades, and details as shown on the plans.

B. Handicap ramps shall be considered part of the integral concrete sidewalk and

curb and shall be built to the dimensions as shown on the plans.

1.02 RELATED WORK

A. Section 01300 - Submittals

B. Section 01400 - Quality Control

C. Section 01410 - Testing Laboratory Services

D. Section 02230 - Excavating, Backfilling, and Compacting for Sidewalks, Curbing,

Driveway Aprons and Roadway Repair

1.03 REFERENCE STANDARDS

A. Form 818 - State of Connecticut Department of Transportation Standards

Specifications for Roads, Bridges and Incidental Construction, 2020.

B. ACI - American Concrete Institute

C. ASTM - American Society for Testing and Materials

1.04 SUBMITTALS

A. Submit under provisions of Section 01300.

B. Concrete: Manufacturer's product data, test reports, mix design and materials

certifications.

02522/1-5

Page 147: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

1.05 MEASUREMENT AND PAYMENT

A. Measurement

1. Integral concrete sidewalks, curbs and driveway aprons shall be measured

by the square footage of integral sidewalk, curb and driveway aprons

installed to the lines and grades as shown on the plans. The width shall be

measured from back of walk to face of curb.

2. Excavation, preparation of subgrade and installation of gravel base shall

be included for payment under this section.

B. Payment

1. Integral concrete sidewalks and curbs shall be paid for at the contract unit

price per square foot for "Integral Concrete Sidewalks and Curbs".

Integral concrete driveway apron and curbs shall be paid for at the contract

unit price, per square foot for "Integral Concrete Driveway Apron and

Curb". Price shall include all materials, tools, equipment and labor

(including excavation, preparation of subgrade and gravel base) required

to complete the integral concrete sidewalks, curbs and driveway aprons.

PART 2 PRODUCTS

2.01 MATERIALS

A. Concrete:

1. Cement shall meet ASTM C150 or C595 Type II.

2. Mixing water shall be clean and free from injurious amounts of oils, acids,

alkalies, organic materials or other deleterious substances in accordance

with ACI 318.

3. Air-entraining admixture shall conform to ASTM C260.

4. Any other admixtures shall only be used if approved by the Engineer.

5. Concrete shall have the following properties:

a. Materials shall be proportioned to produce concrete with a

minimum compressive strength of 3,500 psi at 28 days.

b. The air content shall be 5 percent by volume with a tolerance of +

2 percent.

02522/2-5

Page 148: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

c. Maximum size of aggregate shall be 3/4".

d. Minimum cement content shall be 520 pounds per cubic yard.

e. Concrete shall be delivered at the minimum slump necessary for

efficient mixing, placing and finishing. The maximum slump shall

be 4 in. with a tolerance of + 1 in.

f. The concrete shall be batched and mixed in accordance with

ASTM C94.

B. Premolded Joint Filler: Preformed strips, non-extruding and resilient bituminous

type, of thickness indicated, complying with ASTM D994.

C. Welded Wire Fabric: Cold-drawn steel wire conforming to ASTM A185 or A497

and the sizes indicated on the plans.

PART 3 EXECUTION

3.01 EXCAVATION AND BASE PREPARATION

A. Excavate, prepare subgrade, and install gravel base in accordance with Section

02230.

3.02 FORMING

A. Set clean timber or metal forms true to line. Firmly stake forms in place, strong

enough to resist the pressure of concrete without springing, and tight enough to

prevent mortar leakage. Tops of forms shall be at exact finished grade.

3.03 CONCRETING

A. Spade concrete thoroughly along forms and expansion joints. Vibrate, tamp and

screed to a dense mass.

B. Provide 1/2 inch wide premolded expansion joints. Cut back joints 1/4 inch

below finish of pavement. Provide additional expansion joints around utility

structures and where concrete abuts other structures.

C. After concrete is placed, screeded, bullfloat and steel trowel to a smooth even

surface. Bring sufficient mortar to the surface for the finish.

D. Score contraction joints using scoring tool while concrete is workable.

E. Broom finish using new street broom. Bristle marks shall be perpendicular to the

length of the sidewalk.

02522/3-5

Page 149: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

F. Finish the back edge of the slab and all joints with a 1/4" radius edging tool. Use

a 1" radius edging tool for the outside edge of curbing. Dummy joints must be

straight and perpendicular to the sides of the sidewalk. The greatest allowable

ridge formed by the back of the edging or jointing tool is 1/8".

G. The finished surface will be checked with a 5' straight-edge. No dips or rises over

1/8" in the surface of the sidewalk will be permitted.

H. Forms shall not be removed from freshly placed concrete until it has set for at

least 24 hours. After the forms have been removed, the ends of all joints shall be

cleaned and any "honeycombed" areas shall be patched with cement.

3.04 CURING

A. Moist Curing

1. After the surface of the concrete has been given its final finish and has

adequately set, it shall be protected by covering it with either impervious

sheets of plastic or paper.

2. Sheets shall be laid longitudinally over the surface of the finished sidewalk

and curb by unrolling from a supported roll so as not to bring excessive

weight upon, nor mar the new surface. Cover material shall be securely

weighted down.

3. Sheets shall be kept on the sidewalk for five days. During this period,

concrete shall be kept thoroughly wet at all times.

4. In the event that hair checking develops before the cover can be placed,

moist curing mats shall be used for the initial 24 hour period.

B. Membrane Curing

1. Apply suitable curing agent in accordance with the manufacturer's

specifications. Membrane curing shall be applied in the presence of the

Engineer and contain a fugitive dye to insure thorough application.

3.05 BACKFILLING

A. After the concrete has set sufficiently, the grading shall be completed to the lines

shown on the plans, by filling to the required elevation with approved material which

shall be placed in layers of not over 4 inches in depth and compacted until firm and

solid

02522/4-5

Page 150: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

3.06 Protection

A. After the completion of the walks and driveway aprons, traffic shall be kept at a

safe distance for a period of not less than 24 hours or until the concrete has set

sufficiently to prevent injury to the work.

B. Replace any broken or damaged walks and driveway aprons, until completion of

the project, or acceptance of the road.

END OF SECTION

02522/5-5

Page 151: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02920/1-4

SECTION 02920

TOPSOIL

PART 1 GENERAL

1.01 WORK INCLUDED

A. The work under this section includes all labor, materials, tools, and equipment

necessary for the installation of topsoil in preparation for seeding in the areas shown

on the plans, and areas disturbed by the Contractor's operations.

1.02 RELATED WORK

A. Section 01300 - Submittals

B. Section 01400 - Quality Control

C. Section 01410 - Testing Laboratory Services

D. Section 02930 - Lawns and Grasses

1.03 REFERENCE STANDARDS

A. Form 818, State of Connecticut Department of Transportation. Standard

Specifications for Roads, Bridges and Incidental Construction, 2020.

B. AASHTO American Association of State Highway and Transportation Officials

Standards and Supplements.

C. ASTM American Society for Testing Materials

1. D422, Particle-size Analysis of Soils

2. D2922, Density of Soil and Soil Aggregate in Place by Nuclear Methods

3. D1557, Moisture Density Relations of Soils and Soil Aggregate Mixtures

Using 10 lb. Rammer and 18 inch Drop

1.04 QUALITY ASSURANCE

A. Testing of topsoil materials will be performed by an independent soils laboratory

employed by the Town in accordance with Section 01410. Testing will be

performed so as to minimize interference with the Work.

B. When Work of this Section or portions of Work are completed, notify the testing

laboratory to perform tests. Do not proceed with additional portions of Work until

results have been verified.

Page 152: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02920/2-4

C. If, during progress of Work, tests indicate that Topsoil materials do not meet

specified requirements, notify Engineer as to direction to proceed. If required by

Engineer, Contractor will remove defective Work, replace and retest at no cost to

Town.

D. Ensure compacted fills are tested before proceeding with placement of surface

materials.

E. Examine existing and finish grades as shown on grading plan and excavation and

fill as indicated on plans and elevations. Protect and maintain site boundaries and

project limits during construction. If disturbed, destroyed or exceeded, repair as

directed by Engineer.

1.05 TESTING

A. All loam testing shall be done by the local office of the United States Department of

Agriculture, Cooperation Extension Service, or an independent test laboratory

approved by the Engineer. The Contractor shall provide the laboratory with

representative soil samples for testing and send test reports directly to the Engineer.

All costs for testing shall be at the expense of the Contractor.

B. Loam shall be tested for the following: pH, Nitrogen, Phosphorus, Potash, Calcium,

Aluminum, Magnesium, Soluble Salts and any other mechanical or chemical tests

considered necessary by either the testing agency or the Engineer. All tests shall be

conducted in accordance with the current standards of the Association of Official

Agricultural Chemists.

C. Loam test reports will also contain specific recommendations as the exact types and

times and rates of application of soil adhesives and fertilizers. These

recommendations shall be followed during lawn construction and all Contractors

shall note that any and all materials and procedures, with respect to soil additives

and fertilizers, contained herein are approximate and are given to assist bidding and

that they may be adjusted to comply with test reports.

1.06 SUBMITTALS

A. Submit under provisions of Section 01300.

B. Topsoil: Test results of stockpiled topsoil and each source of off-site topsoil.

1.07 MEASUREMENT AND PAYMENT

A. Measurement shall be by the square yard of in-place topsoil furnished and placed,

and graded completely to the lines and grades as specified and as shown on the

plans.

Page 153: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02920/3-4

B. Topsoil shall be paid for at the contract unit price per square yard for "Topsoil",

which price shall include all materials, tools, equipment and labor required to

complete.

PART 2 PRODUCTS

2.01 TOPSOIL

A. Topsoil: Conform to M.13.01-1 of Form 818. Texture Class: Loam.

PART 3 EXECUTION

3.01 SPREADING, GRADING AND COMPACTING

A. After acceptance of subgrade, the Contractor shall do whatever additional grading is

necessary to bring the subgrade to a true smooth slope, parallel to and 4" below

finished grade, for all areas to be seeded.

B. The top 3" of the subgrade immediately prior to being covered with loam shall be

raked, rototilled, or otherwise loosened and shall be free from stones, rock and other

foreign material 3" or greater in dimensions.

C. Sufficient grade stakes, as determined by the Engineer, shall be used to insure

correct line and grade of subgrade and of finished grade.

D. Subgrade will be inspected and approved by Engineer before placing of loam.

E. Loam shall be as specified above, and shall be placed and spread over approved

areas to a 4 inch thickness in such a manner that after natural settlement and light

rolling, the completed work will conform to the lines, grades and elevations

indicated. Additional loam, after testing and approval, shall be supplied as may be

needed to provide the specified thickness and finished grades.

F. After loam has been spread, it shall be carefully prepared by scarifying or harrowing

and hand raking. All large stiff clods, lumps, brush, roots, stumps, litter and other

foreign matter, and stones over 1" in diameter shall be removed from the loam

which shall also be free of smaller stones in excessive quantities as determined by

the Engineer.

G. The surface shall then be rolled with a hand roller weighing not more than 100 lbs.

per ft. of width.

H. During the rolling, all depressions caused by settlement of rolling shall be filled with

additional loam and the surface shall be regraded and rolled until presenting a

smooth and even finish to the required grade.

I. No topsoil shall be excavated, graded or worked in frozen or muddy conditions.

Page 154: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

02920/4-4

3.02 STOCKPILE

A. Stockpile topsoil so that natural drainage is not obstructed and no off-site sediment

damage shall result.

B. Side slopes or stockpiles shall not exceed 2 to 1 slope.

C. Install silt fence around perimeter of stockpiled topsoil.

END OF SECTION

Page 155: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

SECTION 02930

LAWNS AND GRASSES

PART 1 GENERAL

1.01 WORK INCLUDED

A. The work under this section includes all labor, materials, tools, and equipment

required to provide and establish lawns where shown on the plans.

1.02 RELATED WORK

A. Section 01300 - Submittals

B. Section 01400 - Quality Control

C. Section 01410 - Testing Laboratory Services

D. Section 02275 - Erosion Control

E. Section 02920 - Topsoil

1.03 QUALITY ASSURANCE

A. Include the following test requirements:

1. Supply written analysis, and chemical requirements for lawns, based on

the mechanical analysis and pH value of the tested topsoil.

B. Provide letters from supplier(s) of grass seed and sod indicating mix analysis.

1.04 SUBMITTALS

A. Submit under provisions of Section 01300.

B. Samples: Provide the following:

1. One typical seed bag tag.

2. One typical fertilizer and lime bag tags.

1.05 DELIVERY, STORAGE AND HANDLING

A. Deliver grass seed in original containers showing guaranteed analysis of seed

mixture, percentage of pure seed, year of production, net weight, date of

packaging and location of packaging. Damaged packages are not acceptable.

02930/1-6

Page 156: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

B. Deliver fertilizer and lime in waterproof bags showing weight, chemical analysis,

and name of manufacturer or supplier.

1.06 MEASUREMENT AND PAYMENT

A. Measurement

1. Lawn areas shall be measured for payment by the number of square yards

of surface area of accepted established grass as specified.

B. Payment

1. Lawn areas shall be paid for at the Contract price per square yard for

"Lawn Seeding", which price shall include all materials, mowing,

maintenance, equipment, tools, labor, and work incidental thereto.

PART 2 PRODUCTS

2.01 MATERIALS

A. Lime: Ground limestone, 95 percent passing through a 100-mesh screen.

B. Fertilizer: Complete fertilizer as determined by topsoil analysis derived from

natural organic sources. Store so as to be kept dry.

C. Seed:

1. Of the previous year's crop, weed seed content not to exceed one-quarter

percent by weight, conforming to all State and Federal regulations.

No noxious weeds will be allowed. The total percentage by weight of crop

seed and weed seed shall be less than one-half percent. Inert matter shall

be less than 3%.

2. Mixtures shall be as follows (or approved equal):

Permanent Seed % by Weight

Perennial Ryegrass 30

Kentucky Bluegrass (approved combination

of three of the new improved varieties)

20

Creeping Red Fescue 20

Shadow Chewings Fescue 30

02930/2-6

Page 157: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

3. Germination and purity minimum shall meet current standards of the

Association of Official Seed Analysts.

4. Seed varieties, mixtures, and percentages may be modified by Engineer

due to topsoil analysis or time of seeding operation.

D. Water: Potable

E. Chemical Preventative and Controls: Commercial materials for agricultural use,

manufactured by Scotts, duPont, or equal approved by the Engineer. NOTE:

Immediately prior to the application of any chemical preventatives and controls,

Contractor shall determine whether each of the items is permitted in the State of

Connecticut and Town of Groton.

1. For Crab Grass: Siduron product

2. For Broad Leaf Weeds: 2-4-D material

3. For Lawn Pests or Disease: Material recommended by the Extension

Service's Entomologist or State Experiment Station.

4. For Soil Insects: Material recommended by the Extension Service's State

Entomologist.

F. Hay Mulch:

1. Obtained from acceptable grass or legume mowing, free from weeds,

coarse matter or other objectionable material.

2. Free from rot or mold with moisture content of not more than 15 percent

when delivered to project.

3. Mulch Adhesive: Emulsified asphalt conforming to ASTM D977, Grade

SS-1H.

G. Jute Mesh: Heavy duty, uniform, plain weave with 11 gauge (or heavier) staples.

PART 3 EXECUTION

3.01 TIME OF WORK

A. Normal time for lawn installation is between April 15 and June 1, or August 15

and October 15. Work to be performed at other times must be approved by the

Engineer.

02930/3-6

Page 158: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

3.02 RATES OF PRODUCT APPLICATION

A. Quantities of lime, fertilizer and other amendments shall be as recommended from

the results of the topsoil test.

Material Per 1,000 Square Feet

Grass Seed 8 lbs. in Fall/4 lbs. in Spring

Cellulose Pulp Fiber 32 lbs.

Hay Mulch 80 lbs. providing 75-90% coverage

Crabgrass Preventative Manufacturer's Recommendations

Lawn Pests/Disease Control Extension Service - State Entomologist's

Recommendations or State Experiment Stations

Recommendations

Soil Insect Control Extension Service - State Entomologist's

Recommendations

Broad Leaf Weed Control Manufacturer's Recommendations

Grass Refertilizing 20 lbs.

3.03 GRASS CONSTRUCTION

A. Preparation:

1. Loosen topsoil to a depth of 4 inches by scarifying or other disking

methods. Obtain a loose friable soil.

2. Remove any weeds, and debris and stones having any dimension greater

than 1 inch.

3. Fine grade to a smooth even surface.

4. Surface shall be approved by Engineer before seeding.

B. Hydraulic Seeding:

1. Mix materials with water. Keep in an agitated state so that the materials

are uniformly suspended in the water.

2. Spraying equipment shall be so designed that when the solutions are

sprayed over an area, the resulting deposits of lime, fertilizer, grass seed

and mulch shall be equal in quantity to those specified.

02930/4-6

Page 159: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

3. Before commencing work, submit to the Engineer a certified statement of

the quantities of materials per 100 gallons of water, and the area that this

quantity can cover.

C. Mechanical Seeding:

1. Apply lime and fertilizer evenly at rates determined by topsoil test results

and thoroughly incorporate into the upper 4 inches of topsoil.

2. Rake finish surface smooth.

3. Sow seed applying half the quantity in one direction and the remaining

quantity at right angles to it. Do not sow seed on a windy day, or when the

ground is frozen, wet or otherwise non-tillable. See Paragraph 3.02 for

rates of application.

4. Cover seed with a thin layer of topsoil by raking or dragging.

5. Roll with a hand roller not heavier than 300 lbs.

6. Maintain a moist seed bed at all times. Water seed bed so that the topsoil

is wet to a depth of 2 inches. Apply one complete coverage to the seeded

area in an 8 hour period.

D. Protect the seed bed with barricades, where necessary, to keep all traffic off the

area.

E. Apply approved mulch on all seeded areas which are less than a 3:1 slope. Install

jute mesh on seeded slopes which are 3:1 or steeper. Follow procedures in

Section 02270, Soil Erosion and Sediment Control.

F. Reseeding shall consist of the following:

1. If areas are low, utilize topsoil to bring to grade.

2. Scratch soil surface to about 1/2 inch in depth. Apply seed using a drop-

type spreader at application rate as specified and incorporate seed into top

1/4 inch of soil.

3. Use light roller to go over the area to ensure good seed-soil contact or use

a commercial type slice seeding process to incorporate the seed into

existing topsoil to ensure proper seed to soil contact and to minimize soil

erosion.

4. Water seed bed so that the topsoil is wet to a depth of 2 inches.

02930/5-6

Page 160: 02930 Lawns & Grasses Rev 1 - biznet.ct.gov€¦ · LOCATIONS " will be received by the Town of Groton at the Town Hall Annex, 134 Groton Long Point Road, Groton, CT until 2:00 p.m

5. Spring-seeded areas shall be reseeded in the Fall and Fall-seeded areas

reseeded in the Spring.

3.04 CLEAN UP

A. Dispose off-site, excess materials and debris resulting from sodding and seeding

work.

B. Leave work area clean and neat upon completion of the work.

3.05 MAINTENANCE

A. Period Required: Immediately after installation and continue until acceptance as

defined in Paragraph 3.06.

B. Perform all NECESSARY reseeding and watering, mowing, weeding and rolling,

insect or disease control, refertilizing and repair of wash-outs.

C. Water minimum 3 times per week so that the depth of moisture is minimum 4

inches.

D. When average height of grass becomes 3-1/2 inches, mow to the height of 2-1/2

inches. Remove heavy clippings. Minimum 2 mowings.

E. Second Fertilization: In the Fall after Spring installation and in the Spring after

Fall installation. Notify Engineer in writing 10 days prior to when this

fertilization is to be done. See Paragraph 3.02 for rate of application.

3.06 INSPECTION AND ACCEPTANCE

A. Submit written notice requesting inspection by the Engineer at least 10 days prior

to the anticipated date.

B. No lawn areas will be inspected for acceptance:

1. Prior to the completion of this Contract.

2. Minimum 60 days from date of installation.

3. Prior to the completion of 2 mowings.

C. Engineer will be the sole judge of acceptance.

D. Unacceptable lawn areas shall be reconstructed under the direction of the

Engineer.

END OF SECTION

02930/6-6