000000000001014759 assessment of impacts of retrofit nox controls on gasoil boilers

Upload: dawn-moon

Post on 06-Jul-2018

231 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    1/70

     

    Assessment of Impacts of Retrofit NOx Controlson Gas/Oil Boilers

    1014759

    Effective December 6, 2006, this report has been made publicly available in accordance

    with Section 734.3(b)(3) and published in accordance with Section 734.7 of the U.S. Export

     Administration Regulations. As a result of this publication, this report is subject to only

    copyright protection and does not require any license agreement from EPRI. This notice

    supersedes the export control restrictions and any proprietary licensed material notices

    embedded in the document prior to publication.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    2/70

     

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    3/70

    EPRI Project ManagerA. Facchiano

    ELECTRIC POWER RESEARCH INSTITUTE3420 Hillview Avenue, Palo Alto, California 94304-1338 ▪ PO Box 10412, Palo Alto, California 94303-0813 ▪ USA

    800.313.3774 ▪ 650.855.2121 ▪ [email protected] ▪ www.epri.com

    Assessment of Impacts of RetrofitNO

    x Controls on Gas/Oil Boilers

    1014759

    Technical Update, February 2007

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    4/70

     

    DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES

    THIS DOCUMENT WAS PREPARED BY THE ORGANIZATION(S) NAMED BELOW AS ANACCOUNT OF WORK SPONSORED OR COSPONSORED BY THE ELECTRIC POWER RESEARCHINSTITUTE, INC. (EPRI). NEITHER EPRI, ANY MEMBER OF EPRI, ANY COSPONSOR, THEORGANIZATION(S) BELOW, NOR ANY PERSON ACTING ON BEHALF OF ANY OF THEM:

    (A) MAKES ANY WARRANTY OR REPRESENTATION WHATSOEVER, EXPRESS OR IMPLIED, (I)WITH RESPECT TO THE USE OF ANY INFORMATION, APPARATUS, METHOD, PROCESS, ORSIMILAR ITEM DISCLOSED IN THIS DOCUMENT, INCLUDING MERCHANTABILITY AND FITNESSFOR A PARTICULAR PURPOSE, OR (II) THAT SUCH USE DOES NOT INFRINGE ON ORINTERFERE WITH PRIVATELY OWNED RIGHTS, INCLUDING ANY PARTY'S INTELLECTUALPROPERTY, OR (III) THAT THIS DOCUMENT IS SUITABLE TO ANY PARTICULAR USER'SCIRCUMSTANCE; OR

    (B) ASSUMES RESPONSIBILITY FOR ANY DAMAGES OR OTHER LIABILITY WHATSOEVER(INCLUDING ANY CONSEQUENTIAL DAMAGES, EVEN IF EPRI OR ANY EPRI REPRESENTATIVEHAS BEEN ADVISED OF THE POSSIBILITY OF SUCH DAMAGES) RESULTING FROM YOURSELECTION OR USE OF THIS DOCUMENT OR ANY INFORMATION, APPARATUS, METHOD,PROCESS, OR SIMILAR ITEM DISCLOSED IN THIS DOCUMENT.

    ORGANIZATION(S) THAT PREPARED THIS DOCUMENT

    Energy and Environmental Strategies

    Electric Power Research Institute

    This is an EPRI Technical Update report. A Technical Update report is intended as an informal report ofcontinuing research, a meeting, or a topical study. It is not a final EPRI technical report.

    NOTE

    For further information about EPRI, call the EPRI Customer Assistance Center at 800.313.3774 ore-mail [email protected].

    Electric Power Research Institute, EPRI, and TOGETHER…SHAPING THE FUTURE OF ELECTRICITYare registered service marks of the Electric Power Research Institute, Inc.

    Copyright © 2007 Electric Power Research Institute, Inc. All rights reserved.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    5/70

     

    iii

    Citations

    This report was prepared by

    Energy and Environmental Strategies50 Old Faith RoadShrewsbury, MA 01545

    Principal InvestigatorR. Afonso

    Electric Power Research Institute3420 Hillview AvenuePalo Alto, CA 94304

    Principal InvestigatorA. Facchiano

    This report describes research sponsored by the Electric Power Research Institute (EPRI).

    This publication is a corporate document that should be cited in the literature in the following

    manner:

     Assessment of Impacts of Retrofit NO x  Controls on Gas/Oil Boilers. EPRI, Palo Alto, CA: 2007.

    1014759.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    6/70

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    7/70

     

    v

    Abstract

    In 1997, when EPRI issued the version 2 of its Retrofit NO x  Control Guidelines for Gas- and Oil-

    Fired Boilers (EPRI report TR-108181), it was thought the most common NOx controls installed

    on gas and oil-fired boilers would include low NOx burners; selective catalytic reduction (SCR);

    and other vendor supplied, hardware-intensive approaches. In the years that followed, however,most of the gas and oil power generating fleet opted for less hardware intensive, more cost-effective approaches, with Induced Flue Gas Recirculation (IFGR) being the most popularapproach. In addition, a number of other promising technologies have since been proposed,including Selective Non-Catalytic Reduction (SNCR) Trim and Partial Air Heater Bypass

    (PAHB). These approaches have been successful, but they have operational impacts, the mostprominent being fan limitations at peak loads. This document, based on data and informationgathered directly from operating units including members of the EPRI Gas & Oil Boiler InterestGroup (GOBIG), revisits the guidelines to document experience from plants and units using thenewer techniques. While IFGR is the main focus, the report also summarizes information onPAHB and Forced Internal Recirculation (FIR) from earlier EPRI documents.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    8/70

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    9/70

     

    vii

    Acknowledgements

    Throughout this project, the authors sought direct communication and information from variouscompanies and individuals to augment and/or confirm the available information.

    Specifically, we would like to acknowledge the help and feedback from the followingorganizations:

    •  Consolidated Edison (Con Ed)

    o  Mr. Brian Manzino

    •  Entergy

    o  Mr. Jim Schott

    •  Dynegy

    o  Mr. Mike Ascenzi

    •  Texas Genco

    o  Mr. Ben Carmine

    •  CCA

    o  Mr. Gifford Broderick

    •  ETEC

    o  Mr. Steve Wood

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    10/70

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    11/70

     

    ix

    Acronyms

    List of Acronyms.

    o  LEA – Low Excess Air

    o  BOOS - Burners-out-of-Service

    o  LNB – Low NOx Burner

    o  OFA – OverFire Air

    o  IFGR – Induced Flue Gas Recirculation

    o  FGR – Flue Gas Recirculation

    o  FIR – Fuel Induced Recirculation

    o  PAHB – Partial Air Heater Bypass

    o  SNCR – Selective Non-Catalytic Reduction

    o  SCR - Selective Catalytic Reduction

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    12/70

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    13/70

     

    xi

    Contents

    1 Background and Objectives ................................................................................................1-1 

    Background ...........................................................................................................................1-1 

    Objectives .............................................................................................................................1-1 

    2 Technical Approach..............................................................................................................2-1 

    3 Survey Summary...................................................................................................................3-1 

    Plants/Units/Technologies in Survey.....................................................................................3-1 

    NOx Technology Performance Summaries...........................................................................3-4 

    Information Obtained through the Survey.........................................................................3-4 

    LEA BOOS...................................................................................................................3-4 

    Burner Mods/LNB ........................................................................................................3-5 

    OFA .............................................................................................................................3-5 

    IFGR ............................................................................................................................3-6 

    SCR .............................................................................................................................3-6 

    Additional Data Obtained..................................................................................................3-7 

    FIR and PAHB..................................................................................................................3-9 

    O&M Survey Responses.....................................................................................................3-10 

    IFGR...............................................................................................................................3-10 

    Boiler Upgrades .........................................................................................................3-10 

    Impacts on Boiler Operations.....................................................................................3-10 

    Capital and O&M Costs.......................................................................................................3-13 

    LEA/BOOS .....................................................................................................................3-13 LNB.................................................................................................................................3-14 

    OFA ................................................................................................................................3-14 

    Burner Mods ...................................................................................................................3-15 

    SCR................................................................................................................................3-15 

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    14/70

     

    xii

    4  References.............................................................................................................................4-1 

    A O&M Survey Responses.....................................................................................................A-1 

    IFGR..................................................................................................................................... A-1 

    LEA ...................................................................................................................................... A-8 BOOS................................................................................................................................. A-10 

    LNB .................................................................................................................................... A-13 

    OFA.................................................................................................................................... A-16 

    Burner Mods....................................................................................................................... A-21 

    SCR.................................................................................................................................... A-25 

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    15/70

     

    xiii

    List of Figures

    Figure 3-1 Burner Modifications (Source – CCA) ......................................................................3-8 

    Figure 3-2 OFA Performance (Source – CCA) ..........................................................................3-8 

    Figure 3-3 PH Robinson Unit 2 Reheat Temperature vs. IFGR (Source: EPRI 100450)........3-11 

    Figure 3-4 PH Robinson Unit 3 Reheat Temperature vs. IFGR (Source: EPRI 1000450)......3-12 

    Figure 3-5 PH Robinson Unit 2. Heat Rate Impact vs. IFGR (Source: EPRI 1000450).........3-12 

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    16/70

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    17/70

     

    xv

    List of Tables

    Table 3-1 Overall Summary of NOx Control Technologies with the Survey Group ...................3-1 

    Table 3-2 Entergy Plant/Unit/Technologies ...............................................................................3-2 

    Table 3-3 Con Ed Plant/Unit/Technologies................................................................................3-3 

    Table 3-4 Dynegy Plant/Unit/Technologies................................................................................3-3 

    Table 3-5 NOx Control Performance for LEA/BOOS .................................................................3-4 

    Table 3-6 NOx Control Performance for Burner Mods/LNB.......................................................3-5 

    Table 3-7 NOx Control Performance for OFA............................................................................3-5 

    Table 3-8 NOx Control Performance for IFGR...........................................................................3-6 

    Table 3-9 NOx Control Performance for SCR............................................................................3-6 

    Table 3-10 NOx Performance and Capital Costs Provided by Texas Genco for IFGR andSCR....................................................................................................................................3-7 

    Table 3-11 PH Robinson Units 2 and 3. IFGR Installation Cost Comparison (Source:EPRI 1000450).................................................................................................................3-13 

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    18/70

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    19/70

     

    1-1

    1 Background and Objectives

    Background

    In 1993, EPRI issued the original version of the Retrofit NOx Control Guidelines for Gas- andOil-Fired Boilers. In 1997 , Version 2 of this document was issued. At that time, it wasanticipated that the most common NOx controls to be installed on gas and oil-fired boilers wouldinclude low NOx burners, SCR, and other vendor supplied, hardware-intensive approaches.However, subsequent to the issuance of these documents, most of the gas and oil power

    generating fleet opted for less hardware intensive, more cost-effective approaches, with InduceFlue Gas Recirculation (IFGR) becoming the most popular approach. In addition, a number ofother promising technologies have since been proposed, including SNCR Trim and Partial AirHeater Bypass (PAHB).

    Although IFGR and other more cost-effective approaches to NOx compliance have beensuccessful, they have not been without operational impacts, the most prominent being fanlimitations at peak loads. Accordingly, EPRI determined that a need existed to revisit the“guidelines” and develop a new document concentrating on the most popular controltechnologies, while emphasizing the consequences of NOx controls on boiler operability andperformance.

    Objectives

    EPRI’s vision for this Technical Update was to rely as much as possible on data and informationdirectly from operating units – primarily from within the members of the EPRI Gas & Oil BoilerInterest Group (GOBIG), – as well as other sources willing to share such experience andinformation. The emphasis of the report is on documenting actual experience from plants/unitsutilizing the various technologies, as opposed to general technology descriptions, performanceand projected costs. The previous Guidelines, as well as numerous other EPRI publications (seereferences) address these quite extensively.

    This document is, therefore, essentially a compilation of information gathered through surveys,mainly from within GOBIG, but also from other sources as applicable and possible. Given theinterest on IFGR and other lower cost techniques (i.e., PAHB), more focus is devoted there.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    20/70

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    21/70

     

    2-1

    2  Technical Approach

    Given the nature and objectives of this project, a process that aimed at gathering as much directinformation and experience from actual operating units, while minimizing the time consumptionof utility/plant personnel, was undertaken. After several initial conference calls, two surveyswere prepared for completion by the GOBIG members. The first survey was organized to gathergeneral information on plant/unit/NOx technologies; the second was designed to request as muchrelevant information as possible on the performance of the respective NOx control technologiesemployed throughout their generation fleets, with a focus on O&M impacts.

    In the next section the results of these surveys are presented. In addition, additional efforts weremade to obtain data from other gas/oil plants. In most instances these were limited to onlygeneric discussions. However, Texas Genco, provided some NOx performance data for severalof their plants (IFGR and SCR), which is included in this report.

    Finally, contacts with vendors/consultants such as ETEC (IFGR) and CCA (BurnerModifications and OFA) were fruitful to the extent that summary application lists were provided.Follow up contacts with selected sites did not yield the detailed information desired but theperformance data gathered is presented in the next section as well.

    While IFGR was the main focus of this investigation, the following control technologies were

    initially included in this effort. Not all were available at plants/units within the GOBIG group.However, EPRI has reported on some of these technologies separately and results for FIR andPAHB from previous documents are summarized.

    o  LEA

    o  BOOS

    o  Burner Modifications

    o  LNB

    o  OFA

    o  IFGR

    o  FGR

    o  FIR (e.g., COOLfuel®)

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    22/70

     

    Technical Approach

    2-2

    o  PAHB

    o  SNCR

    o  SCR

    No information was available for the application of Reburn technology, recently employed atFlorida Power & Light’s (FPL) Manatee Station. Previous EPRI reports address this technology,which has been more widely utilized in Europe.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    23/70

     

    3-1

    3  Survey Summary

    This section presents the data and information gathered through the process described inSection 2. It is organized in two major areas as follows:

    1.  NOx performance data

    o  Summary of plants/units/technologies in the survey of the major participants.

    o  NOx performance summaries for each available technology from the survey.

    o  NOx performance summaries for vendor-provided information.

    2.  Operational Impacts

    o  This is the main/original focus of the project. The information provided by theGOBIG members in response to the survey is included here.

    Plants/Units/Technologies in Survey

    Table 3-1 summarizes the distribution of plants/units and applicable NOx control technology . 

    Table 3-1Overall Summary of NOx Control Technologies with the Survey Group

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    24/70

     

    Survey Summary

    3-2

    As can be seen three of the technologies (SNCR, FIR and PAHB) are not in use at any of thefacilities, although both FIR was tested at TXU’s Collins Station and PAHB was tested at TXU’sNorth Lake 3 as discussed later in this section. Two other points seem relevant. First the growingacceptance/popularity of IFGR as a choice technology (as stated by EPRI in developing thisproject); second, the relatively wide differences in performance amongst the various technologies(exception to SCR) emphasizing the reality that site specific conditions dictate to a great extentto final performance achievable by like technologies.

    For additional ease of reference, Tables 3-2 through 3-4 present the technology distribution foreach of the three surveyed utilities.

    Table 3-2Entergy Plant/Unit/Technologies

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    25/70

     

    Survey Summary

    3-3

    Table 3-3Con Ed Plant/Unit/Technologies

    Table 3-4Dynegy Plant/Unit/Technologies

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    26/70

     

    Survey Summary

    3-4

    NOx Technology Performance Summaries

    Information Obtained through the Survey

    The NOx performance data provided by the survey respondents is summarized in this section foreach technology. An effort is made to clarify/qualify questionable or uncertain data asappropriate.

    LEA BOOS

    Table 3-5NOx Control Performance for LEA/BOOS

    BASE NOx CONTROLLED NOx %REDUCTIONUTILITYGAS OIL GAS OIL GAS OIL

    ENTERGY

    Sabine 1Sabine 2Sabine 3

    DYNEGY

    Roseton 1Roseton 2

    0.20.2

    0.26

    NANA

    NANANA

    NANA

    0.150.170.2

    0.22*0.22*

    * data

     point

    includesFGR

    NANANA

    NANA

    25%15%23%

    NANA

    NANANA

    NANA

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    27/70

     

    Survey Summary

    3-5

    Burner Mods/LNB

    Table 3-6NOx Control Performance for Burner Mods/LNB

    BASE NOx CONTROLLED NOx %REDUCTIONUTILITYGAS OIL GAS OIL GAS OIL

    ENTERGY

    Sabine 4Sabine 5

    ConEd

    E. River 60E. River 70

    ERSSS 115-119

    0.260.15

    NANANA

    NANA

    NANANA

    0.200.09

    NANA0.1*

    *w/IFGR(guarantee)

     

    NANA

    NANA

    0.35**

    **w/o IFGR(guarantee)

    30%40%

    NANANA

    NANA

    NANANA

    OFA

    Table 3-7NOx Control Performance for OFA

    BASE NOx CONTROLLED NOx %REDUCTIONUTILITYGAS OIL GAS OIL GAS OIL

    ENTERGY

    Sabine 3

    ConEd

    E. River 60E. River 70

    74th St. PB3

    0.22

    0.370.33

    NA

    NA

    0.270.31

    0.4-0.45

    0.07

    0.170.24

    (guarantee)

     NA

    NA

    0.20.24

    (guarantee)0.27

    68%

    54%21%

    NA

    NA

    NA16%

    33%-40%

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    28/70

     

    Survey Summary

    3-6

    IFGR

    Table 3-8NOx Control Performance for IFGR

    BASE NOx CONTROLLED NOx %REDUCTIONUTILITYGAS OIL GAS OIL GAS OIL

    ENTERGY

    Sabine 4Louisiana 1Louisiana 2Louisiana 3

    ConEd

    E. River 70

    ERSSS 115-119

    59th St. 118

    0.26NANANA

    0.17*

    NA

    0.26

    NA0.40.40.4

    0.2**

    NA

    0.39

    0.20NANANA

    0.11

    0.06(guarantee)

    0.15

    NA0.20.20.2

    0.19

    0.3(guarantee)0.31

    30%NANANA

    35%

    NA54%

    42%

    NA50%50%50%

    5%

    NA

    21%

    *baseline w/o OFA/IFGR=0.39**baseline w/o OFA/IFGR=0.3

    SCR

    Table 3-9NOx Control Performance for SCR

    BASE NOx CONTROLLED NOx %REDUCTIONUTILITYGAS OIL GAS OIL GAS OIL

    ENTERGY

    Lewis Creek 1Lewis Creek 2

    0.20.2

    NANA

    0.030.03

    NANA

    85%85%

    NANA

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    29/70

     

    Survey Summary

    3-7

    Additional Data Obtained

    As mentioned, additional information was provided by Texas Genco, summarizing theperformance on several of their operating units.

    Table 3-10NOx Performance and Capital Costs Provided by Texas Genco for IFGR and SCR

    Separately, vendor/consultant CCA provide generic information on the performance of several of

    their technology applications (Burner Mods/OFA). As a result and due to the large number ofdata provided, the information is presented in graph format, subdivided into boiler type and fuelgroupings.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    30/70

     

    Survey Summary

    3-8

    CCA - Burner Modifications

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    0 100 200 300 400 500 600 700 800 900 1000

    MW

       %    N

       O  x   R  e   d  u  c   t   i  o  n

    gas - wall-fired

    gas - T-fired

    oil - wall-fired

    oil - T-fired

    OFA only

     

    Figure 3-1Burner Modifications (Source – CCA)

    CCA - OFA

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    0 100 200 300 400 500 600 700 800 900 1000

    MW

       %    N

       O  x   R  e   d  u  c   t   i  o  n

    oil - T-fired

    oil wall-fired

    gas - wall-fired

     

    Figure 3-2OFA Performance (Source – CCA)

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    31/70

     

    Survey Summary

    3-9

    FIR and PAHB

    Lastly, it is important to reference technologies not directly addressed in the survey, butnevertheless previously reported by EPRI. Specifically, FIR (COOLfuel®) and PAHB have beentested and documented in EPRI publications.

    COOLfuel® is a fuel dilution technology, essentially inducing flue gas into the burner nozzle,thereby creating the equivalent of a lower heating value (BTU) fuel. This is accomplished byusing the inherent kinetic energy of the natural gas supply to “induce” the flue gas into theburner nozzle. The result is a “new” fuel that exhibits lower peak flame temperature andassociated lower NOx emissions. The technology has been used in utility as well as largeindustrial applications with results. At TXU’s Collins Station, the technology indicated NOxreductions of up to about 65% (~0.05 lb/MBtu).

    For applications where further NOx reductions may be required, the technology can be utilizedwith high-pressure steam to increase the quantity of induced flue gas. This has two benefits asthe steam not only increases the amount of FGR, but also further dilutes the fuel gas. Of course,

    this needs to be considered in light of the added steam related cost. At Collins, this furtherdecreased NOx levels to about 0.03 lb/MBu. However, the plant does not operate in this modedue to stack appearance (haze). Finally, care is needed to address lower furnace CO levels, andthe case of Collins Station, the lowest level of burners do not use COOLfuel®. Reported costsfor the technology by J. Zink Co. range from about $10 - $20/KW for smaller units (less than300 MW) and about $7 - $13/KW for larger units. Reference: “ Assessment of Advanced Low- NOx Burners for Gas-Fired Applications”, EPRI, Palo Alto, CA: 2002. 1004126. 

    PAHB is an EPRI-developed technique used in conjunction with IFGR, to help mitigate apotential limitation associated with IFGR – load reduction due to FD fan capacity. The concept issimple and is predicated on the fact that the APH is one of the largest pressure loss components

    for the air/gas flows. Therefore, by alleviating this pressure loss, it may be possible to get higherlevels of IFGR at a given load, and possibly more importantly, the ability to utilize IFGR athigher loads than without the PAHB.

    As with all technologies, trade-offs are part of the decision-making process. The very nature ofbypassing the APH yields lower air temperatures, which help minimized NOx formation (inaddition to the reductions due to the IFGR). At the same time, an efficiency penalty is associatedwith the reduced combustion air temperature. Site-specific conditions and objectives will dictatethe appropriateness of the application.

    The technology was tested at TXU Electric’s North Lake 3 Station. In summary, these tests

    successfully allowed the unit to operate at the NOx limit of 0.2 lb/MBtu at close to 350 MW, anincrease of about 20 MW over the previous highest load (without PAHB). The full results aredocumented in “Partial Air Heater Bypass – Field Demonstration Results”, EPRI, Palo Alto,CA: 2001. 1004052. 

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    32/70

     

    Survey Summary

    3-10

    O&M Survey Responses

    This section presents a summary and brief discussion of the major responses obtained from theO&M impacts survey. This was the original main focus of this technical update. As expected, thelevel of detail obtained varied from unit to unit. The survey was organized to be consistent with

    the main areas of interest presented in EPRI report TR-108181 (Boiler upgrades, Impact onOperations, Capital and O&M Cost). The complete set of information is grouped by NOx controltechnology for all of the plants/units applicable to each technology and presented in Appendix A.

    IFGR

    Boiler Upgrades

    The reported information indicates that several levels of upgrades associated with IFGR retrofitshave been implemented.

    In all cases, ductwork and dampers/controls were installed typically between the ID fansdischarge and the FD fan inlets. In at least one system dual (East and West) IFGR ducts wereinstalled. Conversely, there were no reports of heat transfer surface modifications with any ofthese installations. With respect to measurement and controls, the range of applications includeflow meters and dedicated O

    2 analyzers to using windbox O

    2 for safety only (e.g., shut off at

    some setpoint), as well as potential damper control. No special mixing devices were reported asthe IFGR is introduced upstream of the FD fans and as accordingly the FD fans themselves serveas the mixing chamber.

    Also reported in two cases were upgrades to the combustion control systems, including BMSupgrades and reprogramming as well as the additional of a dedicated controller for the IFGR

    loop.

    Impacts on Boiler Operations

    No instances of flame stability and/or vibration were reported. Load restrictions due to systemlimitations were noted with both gas and oil firing, ranging from approximately 80% to 90% offull load (although one unit reported no load restriction with the IFGR in operation). Reasonsgiven for load restrictions included FD/ID fan limitations, RH temperatures, as well as opacityconcerns when firing oil.

    Steam temperatures impacts were reported for two units while firing gas. In one case the impacton steam temperature was reported as “higher than in the past”, and was being managed at highload (95%) with the RH bypass open 100% and the IFGR damper backed off from about 70% toabout 45%. On oil firing one unit experienced no impact on steam temperatures, while a secondunit was unable to reach full load due to a steam atomization issue and was therefore, not fullytested.

    Previous experience has shown the potential impact of IFGR on steam temperatures and FDfan/load limitations. Management of these parameters is crucial in optimizing the IFGR system

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    33/70

     

    Survey Summary

    3-11

    throughout the load range. Examples of this reported in EPRI 1000450 for AEP’s BarneyDavis 1, Nueces Bay 6 and Lon Hill 3, showed that these units required more SH attemperationto maintain steam temperature with increasing IFGR flow. FD fan capacity was a limiting factoron the amount of IFGR at Barney Davis and Nueces Bay.

    Data from PH Robinson units 2 (490 MW) and 3 (575 MW) provides another example ofvarying impacts due to unit specific conditions. Figures 3-3 and 3-4 show the impact of IFGR onRH temperature. On Unit 2 the excessive temperatures presented some limitations to theutilization of IFGR, while in Unit 3 no adverse steam temperature impacts were noted and theIFGR was only limited by FD fan capacity at high load (above 450 MW).

    RH TEMPERATURE - 350 MW

    998

    1000

    1002

    1004

    1006

    1008

    1010

    1012

    1014

    0 20 40 60 80 100

    IFGR DAMPER POSITION (%0)

       R   H    T

       E   M

       P   E   R   A   T   U   R

       E

       [   d  e  g   F   ]

     

    Figure 3-3PH Robinson Unit 2 Reheat Temperature vs. IFGR (Source: EPRI 100450)

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    34/70

     

    Survey Summary

    3-12

    RH TEMPERATURE

    996

    998

    1000

    1002

    1004

    1006

    1008

    1010

    1012

    1014

    0 20 40 60 80 100

    IFGR DAMPER POSITION %

       R   H

       T   E   M   P   E   R   A   T   U   R   E   (   d  e  g

       F   )

     

    Figure 3-4

    PH Robinson Unit 3 Reheat Temperature vs. IFGR (Source: EPRI 1000450)

    Heat rate impacts on PH Robinson Unit 2 are shown in Figure 3-5. Clearly in this case the largerimpact occurred at the lower load points.

    Heat Rate vs. IFGR

    0

    50

    100

    150

    200

    250

    300

    0 20 40 60 80 100

    IFGR Damper, %

       D  e   l   t  a   H   R  -   (   B   T   U   /   K   W  -

       H   R   )

    350 MW

    250 MW

    150 MW

    80 MW

     

    Figure 3-5PH Robinson Unit 2. Heat Rate Impact vs. IFGR (Source: EPRI 1000450)

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    35/70

     

    Survey Summary

    3-13

    Capital and O&M Costs

    Capital costs are always difficult to estimate or provide general guidance, due to applicationspecific items that may distort generalizations. It should be noted that cost information providedis also complicated by the simultaneous inclusion, for certain plants, of system up-grades such as

    combustion control (Con Ed plants) or modulating dampers (Entergy Sabine #4). This is truethroughout the industry and applies to most power plant equipment. Competitive concerns or thefact that equipment is often purchased as part of larger turnkey projects are a few of the morecommon reasons why cost comparisons often prove difficult. The responses received from onecompany during this survey included some indication of costs and while here too some combinedcosts were provided, the capital costs were in range of $1.5/KW – 3/KW for the technologyequipment and no additional hardware was typically involved in the refurbishments reported, andtesting and tuning service costs associated with these modifications were, in general, seen to berelatively minor (under $100,000). Although not to be ignored, these costs did not appear toimpact the final investment in any significant manner $5/KW for installation costs. Thesenumbers are higher than those reported previously in EPRI 1000450, which indicated totalinstalled costs in the range of $1.5/KW.

    O&M costs proved more difficult to quantify. In one case, it was indicated that increased costswere not anticipated, although no formal assessment had been completed. Other respondentsanticipated some costs associated with the need to inspect and test IFGR equipment on a periodicbasis. As shown previously, (reference Figure 3-5) heat rate impacts, although applicationspecific, would need to be considered as well, along with incremental maintenance/laborimpacts.

    Information documented in “Guidelines for Induced Flue Gas Recirculation – Volume 2: Roadmap for Application of IFGR”, EPRI, Palo Alto, CA: 2002. 1004050, provides costs for twounits at PH Robinson Station (Unit 2, gas-fired, supercritical 490 MW and Unit 3, gas-fired,

    supercritical 575 MW). Table 3-11 compares these units side-by-side and indicates the variationexpected in these types of projects, where site specific considerations have a significant impacton final costs ($1.30/kW for Unit 2 vs. $0.78/kW for Unit 3):

    Table 3-11PH Robinson Units 2 and 3. IFGR Installation Cost Comparison (Source: EPRI 1000450)

    UNIT #2 UNIT #3

    COST COMPONENT COST COST

    MATERIALS $201,659 $122,908LABOR $302,014 $205,773DESIGN $112,810 $122,430

    TOTAL $616,483 $451,111

    LEA/BOOS

    In the case of Low Excess Air (LEA) and Burners Out-of-Service (BOOS), the respondentsindicated that essentially these applications were absent additional new hardware (e.g., O

    monitors). In most cases no outside dedicated test program/tuning was performed, and no

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    36/70

     

    Survey Summary

    3-14

    operational impacts were observed. In one instance, in-house “minor” tuning was conducted, butno associated costs were reported. Also, two units reported that minor modifications to theirBMS were implemented. Finally, one unit required some modifications to the fuel piping toisolate individual burner cells.

    Impacts on boiler operations such as flame impingement, load restrictions, steam temperatures,CO/opacity was not observed.

    Capital costs provided indicated installed costs of about $0.6/KW for the implementation ofBOOS and an associated $0.95/KW for the BMS modification.

    LNB

    Todd Dynaswirl oil/gas burners were installed in five units previously capable of oil firing only.The retrofits included new windbox internal baffles, front wall and burner throats. Additionally,atomizing steam and gas balancing valves were also installed.

    The major comment received emphasized the fact that the oil-to-gas change required operators toincorporate new procedures, which presented a significant learning curve. Gas firing emissionsseemed to be consistent with expected performance.

    Capital costs were estimated at $25/KW for equipment and $75/KW for installation. These costsincluded BMS and combustion controls upgrades, as well as the installation costs associated withthe concurrent installation of the IFGR system. It should be noted that these are smaller boilers(5 x 150Klb/hr), which may explain the initial appearance of higher than expected costs. Fullcharacterization of the O&M impacts was not completed and therefore not quantified. Anyimpacts however, were expected to be minor.

    OFA

    Four units reported OFA installations. All included multi stage (two and three) ports designswith individual control dampers/actuators. Designs included direct air supply from the winbox aswell as from the APH outlet. In all cases new tube wall panels were installed. In one application,the front wall is the super heater, and accordingly, tube panels were fabricated of stainless steel.In three units the OFA ports included a dedicated flow measurement probe.

    Most comments indicated that the OFA installations have not yielded major concerns. Minorinitial CO increases have been solved. No concerns were noted regarding opacity, flame stability,

    vibration, system temperatures or load restrictions. One report of the fire ball being higher in thefurnace and closer to the sidewalls seems consistent with general experience with OFAexperience.

    Capital costs were reported in the $5/KW – $8/KW range for equipment and about $10/KW forinstallation. These costs include combustion control system upgrades in some cases.Engineering, field testing/tuning costs were reported between $250K and $270K. No informationregarding potential maintenance/O&M labor impacts was reported and expectations were that no

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    37/70

     

    Survey Summary

    3-15

    significant O&M impacts would be found. One comment made on the unit where the higher fireball was observed was that this higher flame location exacerbated a previous overheatingproblem with the flue gas bypass at the junction of the furnace rear and side walls.

    Burner Mods

    “Burner Modifications”, often an alternative to full LNB retrofit, were installed in four units.These included oil and steam upgrades (balancing valves), and airflow management (swirlers). Inthese cases no ignitors/scanners were retrofit. Modifications to the fuel supply were limited togas pressure balancing (orifices being considered if necessary), as well as minor changes to thefuel tips.

    As these modifications were often installed concurrent with other technologies (OFA, IFGR),performance testing specific to the burner modification technology was not possible. In oneinstallation with the Burner Modifications only, no changes in operating conditions were noted(O

    2, PM, opacity). However, CO was observed to increase to about 100 ppm from a baseline of

    0 – 10 ppm.

    Costs for the burner modifications were reported from one source at $1.10/KW (equipment) and$0.40/KW (installation). In the other installations they were part of the larger project andaccordingly could not be identified.

    SCR

    Two SCR installations were included in the survey. These were typical installations on gas unitswith sufficient space between the economizer and the APH to accommodate the catalyst. As aresult, added pressure loss imposed a 30 MW load restriction due to FD fan limitation. This was

    anticipated and deemed economically viable prior to the installation. No additionalmaintenance/O&M labor impacts noted. Catalyst disposal had not yet been experienced. Reagent(ammonia) costs were $0.56/KW-yr.

    Capital costs reflected a smaller, gas unit retrofit at $13/KW for the SCR equipment, and$12/KW installation.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    38/70

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    39/70

     

    4-1

    4  References

    “Retrofit NOx Control Guidelines for Gas- and Oil-Fired Boilers – Version 2.0”, EPRI PaloAlto, CA: 1997. TR-108181.

    “Assessment of Advanced Low-NOx Burners for Gas-Fired Applications”, EPRI, Palo Alto, CA:2002. 1004126.

    “Partial Air Heater Bypass – Field Demonstration Results”, EPRI, Palo Alto, CA: 2001.1004052.

    “Induced Flue Gas Recirculation Performance Tests”, EPRI, Palo Alto, CA, and AmericanElectric Power, Columbus, OH: 2000. 1000208.

    “Guidelines for Induced Flue Gas Recirculation – Volume 2: Roadmap for Application ofIFGR”, EPRI, Palo Alto, CA: 2002. 1004050.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    40/70

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    41/70

     

    A-1

    A O&M Survey Responses

    The survey was organized to be consistent with the main areas of interest presented in EPRIreport TR-108181. The complete set of information is grouped by NOx technology, for all of theplants/units applicable to each technology.

    IFGR

    IFGR 

    BOILER UP-GRADES

    ENTERGYSABINE #4 

    LOUISIANAUNIT 1A 

    LOUISIANAUNIT 2A

    LOUISIANAUNIT 3A

    FGR FANS, DUCTWORK,DAMPERS, CONTROLS

    New ductwork, dampers& damper controls.

    GAS MIXING DEVICES  No

    GAS MEASUREMENT AND CONTROL DEVICES

    Modulating damper

    HEAT TRANSFERSURFACE

    MODIFICATIONS?

    No

     ADDITIONAL REMARKS

    Recirculate gas comesoff APH gas outlet atbottom of stack andenters into FD Fan inletplentums.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    42/70

     

    O&M Survey Responses

    A-2

    IFGR 

    BOILER UP-

    GRADES

    CONEDEAST RIVER 70 

    CONEDERSSS 115-119

    CONED59TH STREET - 118

    FGR FANS, DUCTWORK,DAMPERS, CONTROLS

    Two IFGR ducts runs installed;East and West. Ductwork fromID fan discharge (after IDcontrol damper) to FD fanintake. Control damper withBeck actuator, manual shutoffdamper and x-joints installed.

    Duct work front the ID fandischarge (between the fan andthe control damper) to the FDfan inlet. Expansion jointinstalled just off each fanhousing. Control damper withactuator and manual shut offdamper are installed in eachIFGR system.

    Duct work from the ID fandischarge (between the fanand the control damper) tothe FD fan inlet. Expansion joint installed just off each fanhousing. Control damper withactuator was installed.

    GAS MIXING DEVICES FD fan acts as themixing device.

    FD fan acts as the mixingdevice.

    FD fan acts as the mixingdevice.

    GAS MEASUREMENT ANDCONTROL DEVICES

    O2 analyzer for E & W windbox

    air inlet ducts for safetypurposes. IFGR flow meter ineach run for indication only.

    Windbox O2, for safety not

    control (closes IFGR damperbelow set point).

    IFGR flow meter for use in

    control system. Windbox O2,for safety and potentialcontrol use.

    HEAT TRANSFERSURFACE

    MODIFICATIONS?

    n/a n/a

     ADDITIONAL REMARKS

    Combustion Control systemwas upgraded; new I/O andprogramming.Platforms were installed toreach the control dampers.

    Minor modifications andre-programming to existingboiler airflow meters.BMS upgrade required. Addition of a single loopcontroller for IFGR control.Programming for both.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    43/70

     

    O&M Survey Responses

    A-3

    IFGR 

    IMPACT ONBOILEROPERATIONS

    ENTERGYSABINE #4 

    LOUISIANAUNIT 1A 

    LOUISIANAUNIT 2A

    LOUISIANAUNIT 3A

    POTENTIAL FLAMEINSTABILITY AND

    BOILER VIBRATION

    No

    LOAD RESTRICTIONSDUE TO FURNACE,

    FD FAN, ORWINDBOX PRESSURE

    LIMITATIONS

    No

    EFFECT ON STEAMTEMPERATURE

    CONTROLNo

    FGR FAN POWERNo FGR Fansrequired.

     ADDITIONALREMARKS

     At approximately 80%load, recirculationdamper is closed dueto FD Fan capacityand Reheattemperatures.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    44/70

     

    O&M Survey Responses

    A-4

    IFGR 

    IMPACT ONBOILEROPERATIONS

    CONEDEAST RIVER 70 

    CONEDERSSS 115-119

    CONED59TH STREET -

    118

    POTENTIAL FLAMEINSTABILITY AND

    BOILER VIBRATION

    None noted None noted None noted

    LOAD RESTRICTIONSDUE TO FURNACE,

    FD FAN, ORWINDBOX PRESSURE

    LIMITATIONS

    Boiler air in leakage is limitingthe ID fan, particularly on oilfiring. On oil firing the boiler iscurrently not doing more than~87% to 90% load. Theshutting down of the IFGRdampers happens at about83% load. Gas firing is not asmuch of an issue and the unitis doing about 95% load withthe IFGR dampers still partiallyopen.

    Currently can't usewith oil at high loadsdue to the runningout of fans andopacity issues.

    Can't use with oilat high loads dueto the running outof fans andopacity issues.

    EFFECT ON STEAMTEMPERATURE

    CONTROL

    When on gas firing the RHtemperatures are runninghigher than in past. At 95%load the RH bypass dampersare open 100% and the IFGRdampers have to be partiallyclosed (down to 45% from ahigh of 70% open at lowerloads).

    FGR FAN POWERn/a Having scanner

    trouble when firingoil and IFGR systemin service.

    n/a

     ADDITIONALREMARKS

    RH temperatures are not anissue during oil firing. SHtemperatures have also notbeen a problem, reason isprobably two fold. 1. Theattemperation system canhandle the increase intemperature (haven't checkedfor increased usage). 2. Thefirst stage of the superheater isthe furnace front wall (radiantSH). Thus since IFGR usuallyincrease back endtemperatures we believe thatless absorption in the furnacecombined with more

    absorption in the back passare essentially balancing eachother out.

    Couldn’t make full loadon oil due to an atmstm issue, so not fullytested.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    45/70

     

    O&M Survey Responses

    A-5

    IFGR 

    CAPITAL COST[$/Kw]

    CONEDEAST RIVER 70 

    CONEDERSSS 115-119

    CONED59TH STREET - 118

    TECHNOLOGYEQUIPMENT

    $500K loaded capital cost.Engineering and equipment byB&W.

    ~$150K loaded capital cost butwas included in burner materialpurchase. This is for all fiveboilers. IFGR system wasdesigned and supplied by Todd.

    $140K loaded capital cost. Theengineering and equipment ofthe IFGR system was by Coen.

    INSTALLATION

    $900K loaded capital cost. ~$500K loaded capital cost butwas included in burner installationcost. This is for all five boilers.

    $360K loaded capital cost.

    SYSTEM UP-GRADES

    Combustion Control systemupgrades were included with these

    costs.

    BMS and combustion controlprogramming of the IFGR system

    was included with burner projectcosts.

    BMS and CC upgradesincluded with these costs.

     ADDITIONAL HARDWAREPlatforms were included with thesecosts.

    TEST/TUNING SERVICES$35K additional loaded capital cost. $60K loaded capital cost.

     ADDITIONAL REMARKS

    This was a DEC consent ordermandated project.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    46/70

     

    O&M Survey Responses

    A-6

    IFGR 

    CAPITAL

    COST [$/Kw]

    ENTERGY

    SABINE #4 

    LOUISIANA

    UNIT 1A 

    LOUISIANA

    UNIT 2A

    LOUISIANA

    UNIT 3A

    TECHNOLOGYEQUIPMENT

    New ductwork, dampers &damper controls.

    INSTALLATION No

    SYSTEM UP-GRADES

    Modulating damper

     ADDITIONALHARDWARE

    No

    TEST/TUNINGSERVICES

    Recirculate gas comes off APHgas outlet at bottom of stack andenters into FD Fan inletplentums.

     ADDITIONALREMARKS

    IFGR O&M COSTADJUSTMENT[$/YR]

    ENTERGY

    SABINE #4 

    LOUISIANA

    UNIT 1A 

    LOUISIANA

    UNIT 2A

    LOUISIANA

    UNIT 3A

    O&M LABOR IMPACT?No

    TECHNOLOGYMAINTENANCE

    COMPONENTNo 

    B.O.P. ADDITIONALMAINTENANCE No

    BOILER EFFICIENCYIMPACT

    No FGR Fansrequired.

     ADDITIONAL REMARKS At approximately

    80% load,recirculation damperis closed due to FDFan capacity andReheattemperatures. 

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    47/70

     

    O&M Survey Responses

    A-7

    IFGR O&M COSTADJUSTMENT[$/YR]

    CONED

    EAST RIVER70 

    CONED

    ERSSS 115-119

    CONED

    59TH STREET -118

    O&M LABOR IMPACT? Installed in fall 2002so we haven't hadto deal with it yet.In general it isadditionalequipment that willneed to beinspected andtested on a periodicbasis.

    Installed in fall 2004 sowe haven't had to dealwith it yet. In general it isadditional equipmentthat will need to beinspected and tested ona periodic basis.

    Installed in fall 2004so we haven't had todeal with it yet. Ingeneral it is additionalequipment that willneed to be inspectedand tested on aperiodic basis.

    TECHNOLOGYMAINTENANCE

    COMPONENT

    Not expect muchmaintenance as only

    ductwork and dampers.

    Not expect muchmaintenance as only

    ductwork anddampers.

    B.O.P. ADDITIONALMAINTENANCE

    Not expect muchmaintenance asonly ductwork anddampers.

    BOILER EFFICIENCYIMPACT

    not quantified, ifany.

    not quantified, if any. not quantified, if any.

     ADDITIONAL REMARKS System has yet tobe fully automated.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    48/70

     

    O&M Survey Responses

    A-8

    LEA

    LEA  

    BOILER UP-GRADES SABINE UNIT #1  SABINE UNIT #2  SABINE UNIT #4

    WERE NEW MONITORS (I.E., O2,CO) REQUIRED AND/ORINSTALLED?

    NO NO NO

    WERE COMBUSTION TESTSPERFORMED?

    NO NO NO

    WAS BOILER TUNINGINCLUDED IN THE SCOPE?

    NO NO NO

    WAS BMS MODIFIED TO ALLOWLEA OPERATION? NO NO YES

     ADDITIONAL REMARKS

    LEA  

    IMPACT ON BOILEROPERATIONS

    SABINE UNIT #1  SABINE UNIT #2  SABINE UNIT #4

    WERE NEW MONITORS (I.E., O2,CO) REQUIRED AND/ORINSTALLED?

    NO NO NO

    WERE COMBUSTION TESTSPERFORMED?

    NO NO NO

    WAS BOILER TUNINGINCLUDED IN THE SCOPE?

    NO NO NO

    WAS BMS MODIFIED TO ALLOWLEA OPERATION? NO NO NO

     ADDITIONAL REMARKS

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    49/70

     

    O&M Survey Responses

    A-9

    LEA  

    CAPITAL COST

    [$/Kw]

    SABINE UNIT #1  SABINE UNIT #2  SABINE UNIT #4

    TECHNOLOGY EQUIPMENTNO NO NO

    INSTALLATION NO NO NO

    SYSTEM UP-GRADES NO NO NO

     ADDITIONAL HARDWARENO NO NO

    TEST/TUNING SERVICES

     ADDITIONAL REMARKS

    Minor tuning wasrequired which did nothave any costsassociated with it.

    Minor tuning wasrequired which did nothave any costsassociated with it.

    Only minor tuning wasrequired, therefore nocosts were associated withthis.

    LEA  O&M COST ADJUSTMENT

    [$/YR]SABINE UNIT #1  SABINE UNIT #2  SABINE UNIT #4

    O&M LABOR IMPACT?

    TECHNOLOGY MAINTENANCECOMPONENT

    B.O.P. ADDITIONALMAINTENANCE

    BOILER EFFICIENCY IMPACT

     ADDITIONAL REMARKS

    O&M LABOR IMPACT?

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    50/70

     

    O&M Survey Responses

    A-10

    BOOS

    BOOS 

    BOILER UP-GRADES ROSETON#1  ROSETON #2  SABINE #1 SABINE #2 SABINE #4

    WERE NEW MONITORS (I.E.,O2, CO) REQUIRED AND/ORINSTALLED?

    NO NO

    WERE COMBUSTION TESTSPERFORMED?

    NO  YES 

    WAS BOILER TUNINGINCLUDED IN THE SCOPE?

    NO  YES 

    WAS BMS MODIFIED TO ALLOW LEA OPERATION?

    YES  YES 

    WAS FUEL SUPPLY SYSTEMMODIFIED?

    NO  YES

     ADDITIONAL REMARKS

    NO  Fuel piping had tobe modified sothat each cell ineach pair could

    be isolated.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    51/70

     

    O&M Survey Responses

    A-11

    BOOS 

    IMPACT ON BOILEROPERATIONS

    ROSETON#1 

    ROSETON #2  SABINE #1 SABINE #2 SABINE #4

    DID 02 LEVEL CHANGE?YES

    CHANGE IN OPACITY, CO AND PARTICULATES?

    NO

    FLAME IMPINGEMENTNOTED?

    NO

    FLAME

    INSTABILITY/VIBRATION?

    NO

    STEAM TEMPERATURE? NO

    LOAD RESTRICTIONS? NO

    O&M FLEXIBILITY DUE TOLESS BURNERS IN-

    SERVICE?

    NO

     ADDITIONAL REMARKS

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    52/70

     

    O&M Survey Responses

    A-12

    BOOS CAPITAL COST[$/Kw]  ROSETON

    #1 ROSETON #2  SABINE #1 SABINE #2 SABINE #4

    TECHNOLOGY EQUIPMENT

    $0.47/Kw

    INSTALLATION$0.10/Kw

    SYSTEM UP-GRADES$0.95/Kw forBMS

     ADDITIONAL HARDWARE

    TEST/TUNING SERVICES

     ADDITIONAL REMARKS

    Only minormodifications to

    the BMS wasrequired,therefore therewere no costsassociated

    Only minormodifications to

    the BMS wasrequired,therefore therewere no costsassociated

    BOOS O&M COST

     ADJUSTMENT [$/YR]  ROSETON#1  ROSETON #2  SABINE #1 SABINE #2 SABINE #4O&M LABOR IMPACT?

    TECHNOLOGYMAINTENANCE

    COMPONENT

    B.O.P. ADDITIONALMAINTENANCE

    BOILER EFFICIENCY IMPACT

     ADDITIONAL REMARKS

    O&M LABOR IMPACT?

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    53/70

     

    O&M Survey Responses

    A-13

    LNB

    LNB 

    BOILER UP-GRADES ERSSS UNIT 115 - 119 

    BURNER ASSEMBLIES & RELATED EQUIPMENT

    Original oil only Peabody burners were previously modified(by EPT) for low NOx operation. New Todd low NOxDynaswirl burners added gas firing capability while stillmaintaining the oil firing capability of the boilers.

     AIR REGISTERSSecondary slide damper and a tertiary air zone. Windboxinternals and proportioning dampers were gutted. Newwindbox internal baffles were installed.

    FUEL ELEMENTS Steam atomized oil gun. Gas fuel carriage is a 3-poker(trident) design around a center gas (oil gun passes throughthe center gas gun).

    IGNITORS class 1 gas

    SCANNERS 2 UV scanners per burner (existing)

    FUEL & AIR SUPPLY SYSTEM MODIFICATIONS Oil, atm stm and gas balancing valves were installed as partof the project.

    UPGRADE FD FANS n/a

    POTENTIAL WATERWALL MODIFICATIONS The refractory front wall and burner throats were completelyrebuilt.

     ADDITIONAL REMARKSIFGR system was designed and installed with the burners.BMS upgrade for the gas firing; minor changes for oil firing.Combustions Controls conversion from WDPF to Ovation andexpansion upgrade for gas firing.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    54/70

     

    O&M Survey Responses

    A-14

    LNB 

    IMPACT ON BOILER OPERATIONS ERSSS UNIT 115 - 119 

    CHANGE IN EXCESS O2? The change from oil firing to gas firing is a large change forthe station operations personnel. The oil procedures changedslightly for the new burners. Operations had to learn gas firingprocedures and controls and the new combustion controlsystem in general. We do not expect the oil firing emissions tochange much from the old burners. The change from oil to gashas a significant change in the emissions for the station butthey are what you would expect for this type of change.Having some trouble reaching full load while firing oil. Not fullytested due to other issues.Having some trouble reaching full load while firing oil. Not fullytested due to other issues

    CHANGE IN OPACITY

    CHANGE IN CO

    CHANGE IN PM EMISSIONS

    FAN POWER REQUIREMENT

     ADDITIONAL REMARKSWe have several issues which are still being worked out. Dueto the issues there has been very little oil firing and testing.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    55/70

     

    O&M Survey Responses

    A-15

    LNB 

    CAPITAL COST [$/Kw]ERSSS UNIT 115 - 119 

    TECHNOLOGY EQUIPMENT

    $2.5 mil loaded capital cost. This is for all five boilers. Theburners are by Todd, as well as the windbox dampers andboiler gas train valves.

    INSTALLATION$7.5 mil loaded capital cost. This is for all five boilers.

    SYSTEM UP-GRADESThe BMS and CC upgrades are included with these costs(material was $1 mil capital cost).

     ADDITIONAL HARDWARE The material and installation of the IFGR system was includedwith these costs (material was about $100K capital cost).

    TEST/TUNING SERVICES Was an additional cost to the capital costs listed.

     ADDITIONAL REMARKS The front wall rebuilds were an additional $400K in loadedcapital cost.

    LNB 

    O&M COST ADJUSTMENT [$/YR] ERSSS UNIT 115 - 119 

    O&M LABOR IMPACT? Installed in fall 2004 so we haven't had to deal with it yet. Ingeneral it is additional equipment that will need to beinspected and tested on a periodic basis.

    TECHNOLOGY MAINTENANCE COMPONENT Routine maintenance, inspections, calibration, etc areexpected.

    B.O.P. ADDITIONAL MAINTENANCE

    BOILER EFFICIENCY IMPACT Not quantified, if any. Expected to be a wash with the oldburners.

     ADDITIONAL REMARKS Systems have yet to be fully tuned and placed in automatic,especially for oil.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    56/70

     

    O&M Survey Responses

    A-16

    OFA

    OFA  

    BOILER UP-GRADES

    EAST RIVER UNIT 70  EAST RIVER UNIT

    60 74TH STREET

    UNIT PB3SABINE #3

    TUBE WALL PANELSFOR OFA PORTS

    Six new tube panels were installedon the front wall. Since the frontwall is a superheater the panels arestainless steel tubing. Each panelwas essentially in line with acolumn of burners.

    Six sidewall tube panels(three per side). The unitwas originally a downfired boiler to the OFAports are actually in thesidewall arches andpoint on a downwardangle. The burners hadbeen relocated to thevertical section of thesidewalls (below thearches) many years ago. A front wall tube panelwas also installed at thecenter of the wall.

    One 6-tube panel in righthand sidewall of thepackage boiler.System was intended tobe a test system so nocontrols or damperactuators were addedand the system is notautomated from thecontrol room. Dampershave hand wheels.

    Yes

    OFA PORTSSix 2-stage OFA ports installed.The boiler is a cold cased unit sothere was some difficulty withdesigning a seal that would allowfor proper movement of the tubewall vs the casing/ofa port. Eachport has a 1/3 and a 2/3 openingthat is controlled by a separatedamper and actuator. The controllogic for the dampers is that eachdamper is either open or closed,they do not modulate in-betweenopen and closed positions.

    Seven 2-stage portstotal. Three in eachsidewall arch and one inthe front wall. Each porthas a 1/3 and a 2/3opening that iscontrolled by a separatedamper and actuator.The control logic for thedampers is that eachdamper is either open orclosed, they do notmodulate in-betweenopen and closed.

    positions.

    Three ports in a verticalcolumn. The controldamper (manual handwheel) is installed in thecommon OFA ducttakeoff. Biasing dampersare installed in the threeduct split offs.Directional vanes areinstalled in each of theOFA ports.

    Yes

     AIR SUPPLY DUCTS OFA duct are from the air inletducts to the front wall, above thewindboxes

    OFA duct are from theair inlet ducts to thesidewalls, above eachwindbox. A duct wasalso taken run from eachair inlet duct to feed theone front wall port.

    Single duct takeoff thatspits to go to the threeports.

    Yes

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    57/70

     

    O&M Survey Responses

    A-17

    OFA  

    BOILER UP-

    GRADES(CONT’D)

    EAST RIVER UNIT 70  EAST RIVER UNIT60 

    74TH STREET

    UNIT PB3

    SABINE #3

    OFA MEASUREMENT &CONTROL OF EACHPORT

    Each OFA duct has a flow probefor indication only.

    Each OFA duct has aflow probe for indicationonly.

    OFA flowmeasurement installed.

    No measurementbut controlled ateach port withdampers.

     AIR SUPPLY (WINDBOXVS. NEW FAN)

    From the east and west air inletducts.

    From the air inlet ducts. Duct take off is fromthe AH air outlet duct(windbox inlet)

    Windbox

     ADDITIONAL REMARKS Needed to add I/O and terminationcabinets for the WDPF CombustionControl System. Programming forthe OFA system was also

    performed.

    Platforms and buildingsteel had to be installedto access all seven ofthe new OFA ports.

    4 expansion jointsinstalled; one at takeoffand one with each port.

    New OFA ductscame off existingwindboxes.Existing

    windboxes had tobe replaced withsmaller ones toallow sameamount ofsecondary air tobe distributed tonew OFA ports.

    MODIFIED FUELSUPPLYSYSTEM/ATOMIZERS AND GAS?????INCREASED BURNERFUEL ????

    Air and fuel balancing was alsodone as part of this project.

     Air and fuel balancingwas also done as part ofthis project. A swirlerwas added to each ofthe burners.Combustion Control(WDPF) programmingfor the OFA system was

    performed.

    Burner barrel wassleeved to neck downthe area. Windboxproportional damperswere replaced (manualhand wheels).Existing boiler airflowmeasurement to the

    boiler were replacedwith a new systemcompatible with theOFA flowmeasurementinstrument.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    58/70

     

    O&M Survey Responses

    A-18

    OFA  

    IMPACT ON BOILEROPERATIONS

    EAST RIVERUNIT 70 

    EAST RIVERUNIT 60 

    74THSTREET

    UNIT PB3

    SABINE #3

    CHANGE IN EXCESS O2 No significantchange noted.

    Not tested as ofyet but no majorproblems areexpected.Superheatertemperaturecontrol and boilerexterior BRILCissues (similar toER70) arepotential itemsthat could have to

    be dealt with.

    Not significant Yes

    CHANGES IN OPACITY, CO,PARTICULATE

    No significantchange noted.Levels are withinguaranteed limitsfrom vendor.

    Some CO issuesarose during thetesting stage. Alot of this wasattributed to fluegas bypass.Once holes werepatched the COemissions camedown.

    NO

    FLAME IMPINGEMENT Fire ball is higherand closer to thesidewalls.

    None noted NO

    FLAME INSTABILITY none noted None noted NO

    BOILER VIBRATION none noted None noted NO

    STEAM TEMPERATURECONTROL

    The IFGRsystem seems tobe having abigger effect. Orat least theproblem is beingmitigated byclosing down onthe IFGR asopposed to theOFA dampers.

    No issue noted. NO

    LOAD RESTRICTIONS Unit loadrestrictions wouldseem to be dueto other issueand not the OFAsystem.

    Not related toOFA system

    Yes

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    59/70

     

    O&M Survey Responses

    A-19

    OFA CAPITAL COST[$/Kw]  EAST RIVER

    UNIT 70 EAST RIVER

    UNIT 60 74TH

    STREETUNIT PB3

    SABINE #3

    TECHNOLOGY EQUIPMENT

    $900K loadedcapital cost forthe equipment. Additional $250Kin capital cost forengineering ofthe system, fieldsupport, andtesting/tuning.Engineering,equipment, andtesting of OFA

    system by CCA.

    $1 mil loadedcapital cost for theequipment. Additional $270Kin loaded capitalcost forengineering of thesystem, fieldsupport, andtesting/tuning.Engineering,equipment, and

    testing of OFAsystem by CCA.

    $240K loadedcapital cost. Theengineering andequipment wasby B&W.

    $7.15/Kw

    INSTALLATION$2.1 mil loadedcapital cost.

    $2.25 mil loadedcapital cost.

    $450K loadedcapital cost.

    $9.50/Kw

    SYSTEM UP-GRADESWDPFCombustionControl Systemupgrade wasincluded withthese costs.

    CombustionControl (WDPF)upgrades includedin these costs.

    none

     ADDITIONAL HARDWARE Burner balancingvalves wereincluded with

    these costs.

    Burner balancingvalves wereincluded with

    these costs.Swirlers wereincluded withthese costs.

     All additionalhardware wasincluded in these

    costs.

    none

    TEST/TUNING SERVICES Included withengineeringservices cost.

    Included withengineeringservices.

    $40K loadedcapital cost.

    Included intechnologyEquipment

     ADDITIONAL REMARKSPlatforms andbuilding steelwere included withthese costs.

    System setup iscurrently only formanual operation(due to this beinga test project).Remote orautomatic controlwould require

    additionalengineering,equipment,materials andcost

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    60/70

     

    O&M Survey Responses

    A-20

    OFA  O&M COST

     ADJUSTMENT [$/YR]  EAST RIVER UNIT 70  EAST RIVERUNIT 60 

    74TH STREETUNIT PB3

    SABINE #3

    O&M LABOR IMPACT? Installed in fall 2003 so wehaven't had to deal with it yet.In general it is additionalequipment that will need tobe inspected and tested on aperiodic basis.

    Installed in fall2004 so wehaven't had todeal with it yet.In general it isadditionalequipment thatwill need to beinspected andtested on aperiodic basis.

    Installed in Winter2004 so we haven'thad to deal with ityet. In general it isadditionalequipment that willneed to beinspected andtested on a periodicbasis.

    TECHNOLOGYMAINTENANCE

    COMPONENT

    The higher flames areexacerbating two locations ofoverheating of the exteriorBRILC that exists on eachsidewall. Problem with flue

    gas by-pass at the junction ofthe furnace rear wall tosidewall existed previously.But the OFA would seem tobe exacerbated the problemas the casing is now activelyburning through. A repaireffort of these areas will haveto be planned andundertaken at an unknowncost impact.

    Not expect muchmaintenance asonly ductwork anddampers.

    B.O.P. ADDITIONALMAINTENANCE

    BOILER EFFICIENCY IMPACT not quantified, if any. not quantified, ifany.

    not quantified, ifany.

     ADDITIONAL REMARKS

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    61/70

     

    O&M Survey Responses

    A-21

    Burner Mods

    BURNERMODS 

    BOILER UP-GRADES

    EAST RIVER UNIT70 

    EAST RIVERUNIT 60 

    59TH STREETUNIT 118

    SABINE #5

    BURNER ASSEMBLIES& RELATEDEQUIPMENT

    Oil and atomizing steambalancing valves wereinstalled.

    Oil and atomizingsteam balancingvalves were installed.Swirlers wereinstalled on eachburner. The swirlerswere installed aroundthe barrel thatseparates the primaryfrom the secondaryair zones as opposedto it being located onthe end of the oil gunguide pipe.

    Yes

     AIR REGISTERS Airflow was balanced byadjusting / closing in on theair damper to each burnercompartment for whatwould be considered OFAfiring positions. Windbox iscompartmentalized foreach burner.

     Airflow was balancedby adjusting / closingin on the air registersto each burner forwhat would beconsidered OFA firingpositions.

    NO

    FUEL ELEMENTS Oil and atm stm valveswere throttled to balanceand bias the flows fromburner to burner and levelto level (3 levels of 6burners).

    Oil and atm stmvalves will be throttledto balance and biasthe flows from burnerto burner and level tolevel (2 levels of 3burners on eachside).

    NO

    IGNITORS n/a n/a NO

    SCANNERS n/a n/a NO

    FUEL & AIR SUPPLYSYSTEMMODIFICATIONS

    Yes

    CONTROL OFFUEL&AIRDISTRIBUTION TOBURNERS ?

    Yes

     ADDITIONAL REMARKS Gas pressures werebalanced (burner toburner) enough thatbalancing valves or orificeplates were not installed.

    Gas pressures will bechecked (burner toburner). If neededorifice plates may beinstalled to balancethe fuel.

    Modifications weremade to the fuel tips andfuel distribution piping.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    62/70

     

    O&M Survey Responses

    A-22

    BURNERMODS 

    IMPACT ON BOILEROPERATIONS

    EAST RIVERUNIT 70 

    EAST RIVER

    UNIT 60 59TH STREET

    UNIT 118SABINE #5

    CHANGE IN EXCESS O2Effect of the air andfuel balancing wasnot investigatedseparate from theOFA projectinstallation andtesting/tuning.

    Effect of the air andfuel balancing andthe swirlers will notbe investigatedseparate from theOFA projectinstallation andtesting/tuning.

    NO

    CHANGES IN OPACITY, CO,PARTICULATE

    NO

    CHANGE IN CO Yes

    CHANGE IN PM EMISSIONS NO

    FAN POWER REQUIREMENT NO

     ADDITIONAL REMARKS Station needs toremove the valvehandles so theOperationspersonnel do not usethe balancing valvesas shutoff valves.

    Station will need toremove the valvehandles so theOperationspersonnel do notuse the balancingvalves as shutoff

    valves.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    63/70

     

    O&M Survey Responses

    A-23

    BURNERMODS 

    O&M COST

     ADJUSTMENT [$/YR]  EAST RIVER UNIT70  EAST RIVER UNIT60  59TH STREETUNIT 118 SABINE #5

    O&M LABOR IMPACT? No impact expected. Downthe road the valves mayhave to be repacked orchanged.

    No impact expected.Down the road thevalves may have to berepacked or changed.Inspect swirlers fordamage but none isexpected due to theirlocation.

    TECHNOLOGYMAINTENANCE

    COMPONENT

    Freeing up the old windboxcompartment dampers hasbeen difficult.

    B.O.P. ADDITIONAL

    MAINTENANCE

    BOILER EFFICIENCY IMPACT not quantified, if any. not quantified, if any.

     ADDITIONAL REMARKS

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    64/70

     

    O&M Survey Responses

    A-24

    BURNERMODS 

    CAPITAL COST[$/Kw]  EAST RIVERUNIT 70 

    EAST RIVERUNIT 60 

    59THSTREETUNIT 118

    SABINE #5

    TECHNOLOGY EQUIPMENT

    The air and fuelbalancing workwas purchases,installed, tested,and tuned aspart of the OFAproject. Thevalve supply andbalancing wasprovided byCCA.

    The swirlers and airand fuel balancingwork was purchases,installed, tested, andtuned as part of theOFA project. Theswirler, valve supplyand balancing wasprovided by CCA

    $1.10/KW

    INSTALLATION$0.40/Kw

    SYSTEM UP-GRADES

     ADDITIONAL HARDWARE

    TEST/TUNING SERVICES Included in TechnologyEquipment cost.

     ADDITIONAL REMARKS

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    65/70

     

    O&M Survey Responses

    A-25

    SCR

    SCR 

    BOILER UP-GRADES LEWIS CREEK UNIT #1  LEWIS CREEK UNIT #2 

    SCR REACTOR,DUCTWORK & SUPPORTSTRUCTURE

    YES YES

    REAGENT UNLOADING &STORAGE EQUIPMENT

    YES YES

    REAGENT CONVEYING &INJECTION EQUIPMENT

    YES YES

    PROCESS CONTROLSYSTEM

    YES YES

     AIR HEATER SOOTBLOWER UP-GRADE

    NO NO

    UP-GRADE OOR NEWFD/ID FANS

    NO NO

     ADDITIONAL REMARKS Catalyst was able to be installedin area between economizerand APH.

    Catalyst was able to beinstalled in area betweeneconomizer and APH.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    66/70

     

    O&M Survey Responses

    A-26

    SCR IMPACT ON BOILEROPERATIONS LEWIS CREEK UNIT #1  LEWIS CREEK UNIT #2 

    INCREASED PRESSUREDROP & FAN POWERREQUIREMENTS

    YES YES

    POTENTIAL LOADRESTRICTION DUE FD FANDOR WINDBOX LIMITATIONS

    YES YES

    NH3 SLIP/AIR HEATERPLUGGING

    NO NO

    EFFICIENCY LOSS? NO NO

    CATALYST DISPOSAL None yet None yet

    REAGENT COST $145,000/yr (Anhydrous Ammonia)

    $145,000/yr (Anhydrous Ammonia)

     ADDITIONAL REMARKS A 30 MW restriction was takendue to FD Fan capacity. This wasevaluated prior to installation anddecision was made to takerestriction.

     A 30 MW restriction was taken due toFD Fan capacity. This was evaluatedprior to installation and decision wasmade to take restriction.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    67/70

     

    O&M Survey Responses

    A-27

    SCR O&M COST

     ADJUSTMENT [$/YR] LEWIS CREEK UNIT #1  LEWIS CREEK UNIT #2 

    O&M LABOR IMPACT?

    TECHNOLOGYMAINTENANCE

    COMPONENT

    B.O.P. ADDITIONALMAINTENANCE

    BOILER EFFICIENCY IMPACT

     ADDITIONAL REMARKS

    SCR CAPITAL COST[$/Kw] 

    LEWIS CREEK UNIT #1  LEWIS CREEK UNIT #2 

    TECHNOLOGY EQUIPMENT

    $13/Kw $13/Kw

    INSTALLATION$12/Kw $12/Kw

    SYSTEM UP-GRADES

     ADDITIONAL HARDWARE

    TEST/TUNING SERVICES Included in Technology Equipmentcost.

    Included in Technology Equipment cost.

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    68/70

     

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    69/70

     

  • 8/17/2019 000000000001014759 Assessment of Impacts of Retrofit NOx Controls on GasOil Boilers

    70/70

     

    Export Control Restrictions

    Access to and use of EPRI Intellectual Property is

    granted with the specific understanding and

    requirement that responsibility for ensuring full

    compliance with all applicable U.S. and foreign export

    laws and regulations is being undertaken by you and

    your company. This includes an obligation to ensurethat any individual receiving access hereunder who is

    not a U.S. citizen or permanent U.S. resident is

    permitted access under applicable U.S. and foreign

    export laws and regulations. In the event you are

    uncertain whether you or your company may lawfully

    obtain access to this EPRI Intellectual Property, you

    acknowledge that it is your obligation to consult with

    your company’s legal counsel to determine whether

    this access is lawful. Although EPRI may make

    available on a case-by-case basis an informal

    assessment of the applicable U.S. export classification

    for specific EPRI Intellectual Property, you and your

    company acknowledge that this assessment is solely

    for informational purposes and not for reliance

    purposes. You and your company acknowledge that it

    is still the obligation of you and your company to make

    your own assessment of the applicable U.S. export

    classification and ensure compliance accordingly. You

    and your company understand and acknowledge your

    obligations to make a prompt report to EPRI and the

    appropriate authorities regarding any access to or use

    of EPRI Intellectual Property hereunder that may be in

    violation of applicable U.S. or foreign export laws or

    regulations.

    The Electric Power Research Institute (EPRI)

    The Electric Power Research Institute (EPRI), with

    major locations in Palo Alto, California, and Charlotte,

    North Carolina, was established in 1973 as an

    independent, nonprofit center for public interest energy

    and environmental research. EPRI brings together

    members, participants, the Institute’s scientists andengineers, and other leading experts to work

    collaboratively on solutions to the challenges of electric

    power. These solutions span nearly every area of

    electricity generation, delivery, and use, including

    health, safety, and environment. EPRI’s members

    represent over 90% of the electricity generated in the

    United States. International participation represents

    nearly 15% of EPRI’s total research, development, and

    demonstration program.

    Together…Shaping the Future of Electricity

    © ( )