-------------------------- ENGR 300 Dept. of Computer Science and Engineering University of Bridgeport, CT 06601. NET PRESENT VALUE - NPV. Measures inflows vs. outflows Today’s dollars Cradle to Grave. NET PRESENT VALUE - NPV. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/1.jpg)
-------------------------- ENGR 300
Dept. of Computer Science and EngineeringUniversity of Bridgeport, CT 06601
![Page 2: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/2.jpg)
NET PRESENT VALUE - NPV
Measures inflows vs. outflowsToday’s dollarsCradle to Grave
![Page 3: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/3.jpg)
NET PRESENT VALUE - NPV
Not only accounts for the Costs of Inflows and Outflows, but for their timing
Sales Revenues Loan Payments Development Costs Ramp Up and Production Costs Marketing and Support Costs Disposal Costs
![Page 4: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/4.jpg)
SENSITIVITY ANALYSIS
Answers “What If?” Questions
Helps in Making Project Tradeoffs
Cost is a Critical FactorCritical Factor in Design
??? ?
![Page 5: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/5.jpg)
SENSITIVITY ANALYSIS
Project Parameters can be Varied Development Time Project Loading Interest Rates Sales Price Product Quality
![Page 6: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/6.jpg)
QUALITATIVE ANALYSIS
Complex Factors
Risks
External Factors
![Page 7: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/7.jpg)
DEPRECIATION
Only a portion of the cost of an asset can be deducted for tax purposes in one year
Tangible Assets decrease in value over time Cars Equipment Buildings
![Page 8: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/8.jpg)
DEPRECIATION METHODS
An Asset has an Initial and a Salvage Value at the start and end of
its service life
The Book Value is the remaining undepreciated value of the asset
Straight Line Method (equal amounts) Accelerated Cost Recovery System Modified Accelerated Cost Recovery System
![Page 9: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/9.jpg)
DECISIONS CAN BE INFLUENCED BY THE TIME VALUE OF MONEY
One dollar today
Will be worth more in the future
$ + time = $$$
Present
Future
![Page 10: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/10.jpg)
TIMING OF INFLOWS AND OUTFLOWS
Present Future cash outflows
Future cash inflows
time
Cash Flow Diagram graphically shows relationships
![Page 11: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/11.jpg)
BASIC TERMINOLOGY
P= Present value (NPV in Today's Dollars) F= Future value (Tomorrow’s Dollars) n = Number of compounding periods between
“present” and “future” A = uniform Amount received or paid out each
compounding period
![Page 12: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/12.jpg)
INTEREST RATE
The reward that investors demand for accepting delayed payment
Sometimes referred to as the Discount Rate n is the number of periods per year Must convert the yearly percentage rate to its decimal
equivalent rate
iinPeriodYearly
PerYear
% .01
![Page 13: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/13.jpg)
COMPOUNDING OF INTEREST
ANNUAL PERCENTAGE RATE (APR) INCREASES WITH SHORTER PERIODS OF COMPOUNDING
12% Yearly = 12% APR 3% Quarterly = 12.55% APR 1% Monthly = 12.68% APR Continuous = 12.75% APR
![Page 14: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/14.jpg)
COMPOUNDING FORMULAS
APR i
APR ePeriod
n
i
per year
Yearly
( ) _
% .
1 1
101CONTINUOUS
FIXED PERIODS
![Page 15: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/15.jpg)
PRESENT vs. FUTURE VALUE
Dollars today are worth more than the same amount of dollars in the future
$1000 today will grow to $3300.39 in 10 years at 12% compounded monthly
PF
iPeriodnTotal
( )1
![Page 16: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/16.jpg)
PRESENT vs. FUTURE VALUE Find Present given the Future Value
$120 one year from now is worth $113.03 today n=12 periods or monthly Yearly interest rate is 6%, per month is .005
P
$120
( . )$113.
1 0050312
![Page 17: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/17.jpg)
PRESENT vs. FUTURE VALUE How Many Periods?
How many years does it take to double your money if the APR=9%
PP
n years
n
21 09
2109
8 043
( . )ln
ln( . ).
SOLVING
LOG FUNCTION WORKS TOO
![Page 18: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/18.jpg)
PRESENT vs. FUTURE VALUEWhat interest rate is needed?
What interest rate is needed to make $200 grow to $1000 in ten years, if interest is paid yearly?
$200$1000( )
. .ln( )
1
1 1746 17 46%
10
1000200
10
i
i e
SOLVING
![Page 19: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/19.jpg)
![Page 20: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/20.jpg)
PRESENT VALUE(P) OF A SERIES OF AMOUNTS
n = number of payments of amount A i=interest rate per period (decimal) A= amount of each payment
PA i
i
n
( ( ) )1 1
![Page 21: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/21.jpg)
PRESENT VALUE OF EQUAL PAYMENTS
$10 monthly payments for one year interest rate is 6% per year = .005 per month
P
$10 ( ( . ) )
.$116.
1 1 005005
0912
Present Value is greater than one single paymentof $120 after a year (in that case, P was $113.03)
![Page 22: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/22.jpg)
AMOUNT OF A LOAN PAYMENT
P=$100,000 i=9% per year = .0075 per month n=360 monthly payments
A
$100000 .( ( . ) )
$804.0075
1 1007562360
Note in 30 years, $289,663 will be paid in payments
![Page 23: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/23.jpg)
MATHEMATICAL BASIS
A SERIES OF PAYMENTS IS BROKEN DOWN INTO SUMS OF INFINITE STRINGS OF PAYMENTS
etc.P1=A/iA
etc.A
A
P=P1-P2
Subtract
P2=A/(i(1+i) n)
![Page 24: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/24.jpg)
PRESENT VALUEOF INCREASING AMOUNTS
PA i
i
B i n i
i
P
nk
nk n
k
k
( ( ) ) ( ( ) ( ) ( ) )
$15 ( ( . ) ).
$10 ( ( . ) ( . ) )
.$114.
1 1 1 1 1
1 1015015
1015 3 1015
01591
1
1
41
34
A A+BA+2B A+3B
Present
A=$15 & B=$104A+6B=$120i=.06/4=.015n=4 (quarterly) Future
![Page 25: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/25.jpg)
ECONOMIC COMPARISON
Decisions often include comparisons of economic costs/benefits of alternative actions
Inflows/Outflows may occur at several different times
Time-value of money must be considered
![Page 26: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/26.jpg)
ALTERNATIVES WITH EQUAL LIVES
For each alternative, compute the Net Present Value (NPV)
Compute P for all inflows Compute P for all outflows NPV = P(inflows) - P(outflows) Alternative with highest NPV is the best
choice from an economic viewpoint
![Page 27: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/27.jpg)
ALTERNATIVES WITH UNEQUAL LIVES
For each alternative, compute the equivalent uniform cost per period (EUC/P)Assume identical replacement at end of lifeCompute A for all inflowsCompute A for all outflowsEUC/P = A(outflows) - A(inflows)
Alternative with lowest EUC/P is the best choice from an economic viewpoint
![Page 28: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/28.jpg)
DEALING WITH RISK AND UNCERTAINTY
Use Expected Value (EV) for inflows and outflows with estimated uncertaintiesEV = (p1)(V1) + (p2 )(V2) + .......+ (pn)(Vn)
pn is the probability that a value will be Vn
where p1 + p2 +.......+ pn = 1 Calculate NPV or EUC/P based on expected
values
![Page 29: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/29.jpg)
EXPECTED VALUE
Saturdays, the following probabilities exist .35 won’t study at all .15 will study for 4 hours .20 will study for 2 hours .30 will study for 1 hour
EV . . . . .35 0 15 4 20 2 30 1 131.3 IS THE EXPECTED NUMBER OF HOURS OF STUDY ON A TYPICAL SATURDAY
![Page 30: -------------------------- ENGR 300 Dept. of Computer Science and Engineering](https://reader036.vdocuments.mx/reader036/viewer/2022062411/56814b05550346895db81bef/html5/thumbnails/30.jpg)
WHAT IF?
What If questions can be supported by doing a sensitivity analysis.– Take one variable at a time, holding others fixed,
make small changes in that variable observe effect on NPV or on EUC/P
– Spreadsheet program is useful for this purpose and doing time value of money calculations