zero onsite fossil-fuels: the davis student village › media › default › ... · • auger,...
TRANSCRIPT
Efficiency Vermont- 10 Feb 2011
Zero Onsite Fossil-Fuels: The Davis Student Village
Efficiency Vermont- 10 Feb 2011
Efficiency Vermont is a Registered Provider with The AmericanInstitute of Architects Continuing Education Systems (AIA/CES).Credit(s) earned on completion of this program will be reported toAIA/CES for AIA members. Certificates of Completion for both AIAmembers and non-AIA members are available upon request.
This program is registered with AIA/CES for continuing professionaleducation. As such, it does not include content that may be deemedor construed to be an approval or endorsement by the AIA of anymaterial of construction or any method or manner of handling, using,distributing, or dealing in any material or product.
Questions related to specific materials, methods, and services will beaddressed at the conclusion of this presentation.
Efficiency Vermont- 10 Feb 2011
Learning Objectives
At the end of this program, participants will be able to:
• Know the solution concepts employed for a fossil fuel free program
•Understand how the thermal envelope contributed to an innovative mechanicalsystem
•Understand the procurement method used to deliver the project on time andbelow budget
•Know the resulting temp and RH data, energy use and patterns of occupancy
Efficiency Vermont- 10 Feb 2011
Course EvaluationsIn order to maintain high-quality learning experiences, please access
the evaluation for this course by logging into CES Discovery andclicking on the Course Evaluation link on the left side of the page.
Efficiency Vermont- 10 Feb 2011
Our Team
Millard Dority Director of Campus Planning
Marc Rosenbaum, PE Energy & Systems Consultant
Sam Coplon, ASLA Landscape Architect
Thomas RC Hartman, AIA Project Architect
Rob Shea, PE CM Project Manager
Phil LaClaire Owner’s Representative
Consultants Major Subcontractor’s
Acentech Acoustical Consultants Atlantic Landscape Construction
Ryan Hellwig, PE Structural Engineering Harold MacQuinn, Inc.
Hedefine Engineering Civil Engineering Evergreen Home Performance
Petersen Engineering Mechanical Engineering Northeast Plumbing & Heating
Bartlett Design Electrical Engineering King Electric, Inc.
Efficiency Vermont- 10 Feb 2011
The client- initial goal - ZERO FOSSIL FUELS
Efficiency Vermont- 10 Feb 2011
Selection Process- a very long interview- 4 hour workshop
Efficiency Vermont- 10 Feb 2011
Context Plan
Efficiency Vermont- 10 Feb 2011
SC-Site context-existing
Efficiency Vermont- 10 Feb 2011
Timeline
Began Schematic Design at the end of 2003 through 2004
Hold through 2005
Started up on Design Development 2006
Construction Drawings completed for bidding in Jan 2007
Construction Completed for Fall 2008
Ongoing monitoring- 2009 to present
Efficiency Vermont- 10 Feb 2011
SC-Site existing site plan
Efficiency Vermont- 10 Feb 2011
Design Process
Efficiency Vermont- 10 Feb 2011
Design Program
NSF/Space Number Total Area
Bedrooms ( double) 200 2 400Bedrooms (single) 130 4 520Group Study 120 1 120Bathrooms 50 2 100Kitchen 120 1 120Dining 150 1 150Living 150 1 150
Laundry
Storage
Sub-TOTAL 1,560
Circulation and structural multiplier 1.7
TOTAL
Houses 2652 6 15,912
SPACE NEED PER RESIDENCE "HOUSE"
2,652
One space for six
houses — see below
One exterior (unheated)
space per house — see
below
Seminar/social space 650 1 650
Social space 550 1 550
Laundry/Games space 650 1 650
Accessible bathroom 100 1 100
Accessible bedroom 200 2 400
Janitor and storage 50 1 50
Mechanical room 500 1 500
Sub-TOTAL 2,900
1.6
TOTAL 4640
GRAND TOTAL
500
Exterior storage space for bicycles and
outdoor equipment — 10 s.f per
student
20,552
Circulation and structural multiplier
SUPPLEMENTARY SOCIAL SPACE NEED
Efficiency Vermont- 10 Feb 2011
Solution Concepts
Efficiency Vermont- 10 Feb 2011
Loads - Resources - Conversion Technology - Recovery Technology
Efficiency Vermont- 10 Feb 2011
• Superinsulated envelope
• Heat recovery ventilation
• Central wood pellet-fired mini-district system for heat and DHW
• Drainwater heat recovery
• Minimum of 3 uninterrupted south facing roofs for solar electricity forlighting and plug loads
Energy Solution Concepts
Efficiency Vermont- 10 Feb 2011
Ground Floor Plan
Efficiency Vermont- 10 Feb 2011
Second Floor Plan
Efficiency Vermont- 10 Feb 2011
Third Floor Plan
Efficiency Vermont- 10 Feb 2011
Section
Efficiency Vermont- 10 Feb 2011
Schematic Model
Efficiency Vermont- 10 Feb 2011
SC-Proposed site in context of Campus Landscape Master Plan
Efficiency Vermont- 10 Feb 2011
SC-Davis Village site plan
Efficiency Vermont- 10 Feb 2011
SC-Davis Village view east- BEFORE
Efficiency Vermont- 10 Feb 2011
SC-Davis Village view east- AFTER
Efficiency Vermont- 10 Feb 2011
SC-Davis Village view Northeast- BEFORE
Efficiency Vermont- 10 Feb 2011
SC-Davis Village view Northeast- AFTER
Efficiency Vermont- 10 Feb 2011
SC-Davis Village view south design sketch
Efficiency Vermont- 10 Feb 2011
Photo by Sam Coplon
SC-Davis Village- view south
Efficiency Vermont- 10 Feb 2011
Photo by John Rivers
SC-Man itʼs cold
Efficiency Vermont- 10 Feb 2011
Photo by John Rivers
Summer
Efficiency Vermont- 10 Feb 2011
Photo by John Rivers
Summer
Efficiency Vermont- 10 Feb 2011
Photo by Sam Coplon
Winter- Whereʼs Millard?
Efficiency Vermont- 10 Feb 2011
Photo by B rain Vanden B rink
Winter
Efficiency Vermont- 10 Feb 2011
WinterPhoto by B rain Vanden B rink
Efficiency Vermont- 10 Feb 2011
Homey Interiors with acoustic separationPhotos by John Rivers
Efficiency Vermont- 10 Feb 2011
SC- LEP and Infrastructure
Efficiency Vermont- 10 Feb 2011
•Underslab- 3” eps type IX rigid
•Walls- R 40, 12”double wall w/ densepack cellulose
•Windows- triple glazed fiberglasscasements or awnings
•Doors- Thermatru- nothing special
•Roof- 14” I-joist with cellulose, hot roof
•Airtightness goal- 1 ACH 50
Summary of Thermal Envelope components
Efficiency Vermont- 10 Feb 2011
Air Sealing drawings Air sealing drawing by Jesse Selman of C&H
Efficiency Vermont- 10 Feb 2011
Taped Exterior Sheathing
Efficiency Vermont- 10 Feb 2011
• Viessmann 150 kW (512 kBTU/hr) pellet boiler
•Brock silo for pellet storage (15 tons)
• Auger, de-ashing and cleaning system
• 425 gallon storage tank as thermal capacitance
• Two Viessmann condensing gas boilers 192 kBTU/hr each - providedheating prior to pellet boiler coming on line, provides redundancy,provides higher peak capacity for other buildings
Central Heating Plant
Efficiency Vermont- 10 Feb 2011
Boiler Building
Efficiency Vermont- 10 Feb 2011
Boiler Building
Efficiency Vermont- 10 Feb 2011
District Heating System Diagram
Efficiency Vermont- 10 Feb 2011
Central Heating Plant- System Diagram & tank Drawing by Petersen Engineering
Efficiency Vermont- 10 Feb 2011
• Housing design load is 180 kBTU/hour
• Deering Commons, an adjacent DER, is 120 kBTU/hr
• Sea Fox, an adjacent un-renovated building, is 240 kBTU/hr presentlyyet could be DER’d to 120 kBTU/hr or less
• Pre-insulated and jacketed polyethylene piping was buried and carriesthe hot water to the buildings
• Pumps are variable speed
• In each of the six houses, there is a heat exchanger and storage tankfor DHW
• Hot water delivered to the housing is used directly for heating
Mini-district system
Efficiency Vermont- 10 Feb 2011
Pellet Boiler
Efficiency Vermont- 10 Feb 2011
• Heating load is about 8 BTU/sf-hr
• First floor is slab on grade so hydronic radiant floor was selected
• Two upper floors - ventilation CFM is roughly half of the CFM requiredfor heating, so heating is delivered via forced air
• Composter exhaust is about 40 CFM and is unbalanced
• Venmar 1.8HE HRV supplies about 150 CFM
• Each of the two upper floors has a separate heating coil in the ductwork, and the Fantech FG6 fan serves both
• Low air flows mean critical duct sealing and attention to balancing
Distribution inside each house
Efficiency Vermont- 10 Feb 2011
Hot water coils in ERVDrawing by Petersen Engineering
Efficiency Vermont- 10 Feb 2011
HRV
Filter and fan
Hydronic coils
Fresh air supply
Field layout
Efficiency Vermont- 10 Feb 2011
BIM for coordination of mechanical in tight spaces
Efficiency Vermont- 10 Feb 2011
It Fits…6 times!ProcessMel-Truth Serum
Efficiency Vermont- 10 Feb 2011
Air Tightness meeting- getting everyone on board
Efficiency Vermont- 10 Feb 2011
Air tightness standards & testing
Efficiency Vermont- 10 Feb 2011
Blower Door Results from Final Testing
College of Atlantic, Davis Student Housing
15-Dec-08
Conducted by Evergreen Home Performance: Richard Riegel Burbank, Test Manager
Building East Wing Middle West Wing Total
Averages for
Testing
Round
Deduct Correction Factor
of 82.5 Pa with Closed
Mechanical Vents
Inner North : First Round of Testing (Ventilation intake and exhaust open, composting toilet vent open, A few windows were not fully closed)
423 218 435.5 1076.5
408 250.5 440 1098.5
395.5 272.5 436 1104
392.5 275 444 1111.5
396.5 278 442.5 1117
392.5 278 436 1106.5
390.5 277.5 435.5 1103.5
400 241.5 554 1195.5
0 1114.125 1031.625
Inner North: Second Round of Testing (Vent intakes/exhaust/composting toilet sealed, a few windows were closed better)
378.5 160 300 838.5
369.5 156 296 821.5
368.5 155 293 816.5
370.5 167 306.5 844
370 166.5 302 838.5
372 163.5 302 837.5
832.8 832.8
Inner North: Third Round of Testing (Building in same condition as second round except intakes and exhausts are opened and compost vents reconnected)
420 151.5 346 917.5
419.5 149.5 358 927
422 145 351 918
415 142 350 907
419.5 144.5 347 911
419 145.5 348 912.5
915.5 833
Final Test Results
Initial Test at taped plywood- 593 cfm50, then up.. Then down…1 Air Change per Hour at 50 pascals in a 65,000 cubic feet volume is calculated:1 ACH 50 = 65,000 cf / 60 minutes = 1,083 cfmFinal test was 833 cfm50 or 0.77 ACH 50 (Energy Star is 5.0 ACH 50)
Efficiency Vermont- 10 Feb 2011
Metering-simplicity with humans in each house
Btu meter
Ventilation Control Electric Meter Total Water Meter
Hot Water Meter Thermostat
Efficiency Vermont- 10 Feb 2011
Meter collections per building
Efficiency Vermont- 10 Feb 2011
Some data from master SS
-Water
- DHW
- Electricity
Can you have someone in your office extract this from the SS forone year? Good to have water and DHW in gallons/person/day.Good to have electricity in kWh/person/day and kWh/sf/yr
Data variations by house
Efficiency Vermont- 10 Feb 2011
• HDD65s in Bar Harbor 2009 plus Jan/Feb 2010 = 10,299
• Pellets used = 50 tons = 820 MMBTU
• Energy delivered to the system 75% efficiency = 615 MMBTU
• Propane used = none (or a wee bit)
• DHW estimate = 63 MMBTU, 84 MMBTU at the boiler
• Energy for heating and to the ground = 552 MMBTU
• Ft2 heated = 7,500 + 19,500 = 27,000 ft2
• BTU/ft2/HDD = 2.0 at the building; 2.65 at the boiler
Heating energy usage ESTIMATE!
Efficiency Vermont- 10 Feb 2011
Total energy usage ESTIMATE!
Total electricity usemeasured at eachbuilding meter
52, 919 kwh/ year9.2 kbtu/sf/year
Heating energy- 50tons per year is 820 MMBtuAssuming equal use between Housing and DeeringHousing is 72% of the total area of 27,000 sf
Pellet use is 590 MMbtu at 19,500 sf is 30.2 kbtu/sf/year
Total site energy is 39.4 kbtu/sf/year
Good, but not great. Goal is 25.
Efficiency Vermont- 10 Feb 2011
Hobos-outside temp
Some data from hoboes
-Temps seem high- RHs are high - need to look carefully at what’s going on - is fresh air getting to BRs and stale air being exhausted?
Efficiency Vermont- 10 Feb 2011
Hobos-one bedroom- GIVEN CONTROL
Efficiency Vermont- 10 Feb 2011
Updated information for Winter 2011