1
Xcel Energy PMO: Success from the Start
Eric Weimert, IT Portfolio ManagerJill Rodning, Senior Portfolio LiaisonAnne Olson, Program Manager for Utility Innovations
2
Agenda
Xcel Overview
Why Projects Fail
PMO Overview
PMO Tools for Success
Support Structure
Organization Engagement
PMO Results
3
Xcel Energy Overview3.3 million electricity customers and 1.8 million natural gas customers in 8 Western and Midwestern states
9,000+ employees; I/T staff of 640+ professionals
Total Annual Revenue revenues of $10B
$142M Operating I/T budget for 2007$75M Capital I/T budget for 2007
90% of I/T functions and services delivered to Xcel Energy through 3rd
generation outsourcing partnership with IBM Global Services
2
4
Why Projects FailPoorly Developed Business CaseLack of User involvementLack of qualified resourcesUnrealistic ExpectationsLack of Executive Support (I/T and Business)Changing RequirementsProject Team StructureNot aligned with Business PrioritiesNo Project Oversight & VisibilityPoor Risk Management
5
End-to-end PMO1.0 Idea
2.0 Planning
3.0 Business Case Analysis
4.0 Project Execution
5.0 Project Close
Business unit prioritizes ideas, plans, budgets and develops business casePMO provides portfolio management, planning support and seeks consolidation opportunities
Business unit approves projects, Project Change Requests (PCRs) and Finance Leader agrees to benefits/budget impact Project Manager manages project and tracks issues, risks, dependencies and PCRsPMO manages cross-unit dependencies and risks
PMO compares benefits realized to original projections
Closed Loop
PMO Overview
6
Idea/PlanningIdea• Idea involves identifying and prioritizing business unit
needs and objectivesPlanning1. PMO Kickoff Meeting
• The Liaison will work with the project team to discuss how the project will be managed, as a:
• Single Project• Single Work Effort• Larger Program made up of possibly multiple Projects and/or Work Efforts
2. Project Charter• The Project Charter describes the:
• Outlines the need for the project. • Necessary resources• Timeframes & cost estimates to complete the Business Case Suite (BCS)
2.0 Planning
3.0 Business Case Analysis
4.0 Project Execution
5.0 Project Close
Closed Loop
PMO Overview
1.0 Idea
3
7
Business Case AnalysisBCS Deliverables
ScopeBusiness DesignTechnical DesignRiskScheduleCost Benefit Analysis (CBA)
Milestone Approvals
2.0 Planning
3.0 Business Case Analysis
4.0 Project Execution
5.0 Project Close
1.0 Idea
Closed Loop
PMO Overview
8
Funding GovernanceGovernance Layers
3.0 Business Case Analysis
4.0 Project Execution
5.0 Project Close
1.0 Idea
Closed Loop
Idea Charter BCSExecute& Imp PCR’s
Approvals: Cumulative Of total
Dir Fin. and PMO NA NA <$250K <$1M <20%
SLT* NA NA <$5M <$5M >20%
IRC NA NA <$10M <$10M >20%
Board NA NA >$10M >$10M >20% Funded by: Business Unit Business Unit Business Systems Business Systems Business Systems
*SLT = Senior Leadership Team in Business Systems (Ray Gogel and his direct reports)
Notes:• The cost to develop an idea and preparation of a charter is authorized by management within the
Business Unit.• Business Systems Finance Director, PMO Director, or Asset Director approve material requests up
to $500K• CIO signs all contracts and approves material requests above $500K• If the project is canceled because the business case does not support it, the business unit absorbs
the cost of the BCS effort
2.0 Planning
PMO Overview
9
Project Execution & Tracking• After a project has been approved by the business
unit, the Project Manager can begin project execution
• Project execution is comprised of five key elements:– Status reporting– Issue management– Risk management– Dependency management– Project Change Request (PCR) management
1.0 Idea
2.0 Planning
3.0 Business Case Analysis
4.0 Project Execution
5.0 Project Close
Closed Loop
PMO Overview
4
10
Status Reporting - Project Health It is the responsibility of the Project Manager to accurately track (metric driven) and anticipate (issue driven) project health changes.The project “health” calculation is based on the following:
Spend to Date (LTD)Estimated spend at completion (EAC)Labor (Hours)Number of tasks completedMilestones past dueIssues
Project Execution & Tracking
1.0 Idea
2.0 Planning
3.0 Business Case Analysis
4.0 Project Execution
5.0 Project Close
Closed Loop
PMO Overview
11
Project Execution & Tracking
1.0 Idea
2.0 Planning
3.0 Business Case Analysis
4.0 Project Execution
5.0 Project Close
Closed Loop
Project Change Requests (PCRs)Project Managers update project baseline information for all approved PCR'sThree types of PCRs
Type A – New functionalityApprovals Required – Sponsor, Business Manager, Business Technology Executive (BTE), Governance
Type B – Missed requirementsApprovals Required – Sponsor, Business Manager, BTE, Governance
Type C – No Scope, end date or $ changeApproval Required - Liaison
PMO Overview
12
Project Close/Closed Loop
Project Close• Project Managers should continue to focus on project
close-out activities including:• Submit Final Status Report• Project Completion Report• Lessons Learned• Work Order close out
Closed Loop• BTEs, PMO and Business Unit will set a future date to
validate the benefits have been realized (Closed Loop)
1.0 Idea
2.0 Planning
3.0 Business Case Analysis
4.0 Project Execution
5.0 Project Close
PMO Overview
Closed Loop
5
13
Support Structure: PMO Infrastructure
PMO Tools for Success
14
Support Structure: PMO Library
PMO Tools for Success
15
Support Structure: Process Automation
PMO Tools for Success
1. Submit Idea
2. Route Idea
4. PMO Kickoff Meeting
3. Annual Budget
4. Route Budgeted Idea
6
16
Support Structure: MS Project Sourced Metrics
PMO Tools for Success
17
Support Structure: Forums/TrainingQuarterly Refresher Training
Modularized training½ day sessions
Onboarding TrainingJust-in-time trainingModularized training
Monthly PM ForumIntroductionsPM Community
Staffing ChangesRecognition Key Highlights
Special TopicsResourcesPM Forum Roadmap
PMO Tools for Success
18
Organizational Engagement: IT & the BusinessMilestone Approvals
CharterBusiness Case MilestonesUpon Deployment
Scope, design validation, transition to operations3.0 Business Case
Analysis
5.0 Project Close
1.0 Idea
Closed Loop
4.0 Project Execution
2.0 Planning
PMO Tools for Success
7
19
Organizational Engagement: GovernancePurpose: Provide Business and Business Systems Senior Management Oversight in the areas of
prioritization, funding, exception management and progress tracking.
(1)
Idea
(2)
Charter Governance
(3) Business
Case Analysis Governance
Project
Initiation
(4) Project
Execution
(5) Project
Close
Not drawn to scale to reflect relative effort or duration
IdeaPrioritization
Future – BU Work Authorization Process
(e.g. WRAP & demand Capture))
Annual Budgeting
Program & Project CharterPresentation Funding for
Business Case Development
Business Case PresentationFunding for
Project Execution
Tuesday Project Review Meetings(upon request)
Issue, Risk, DependencyEscalation (as needed)
Future – Post ImplementationMeasurement
Status Reporting(every other week)
Scope, Business Design, and
Technical Design Acceptance
Project Health = Red or YellowCorrective Action Implementation
PCR - Funding orSchedule Change
Project Steering Committee(high profile projects)
Go No-goDecision
Transition to OperationsTransition to Support
Financial Governance
Oversight Governance
PMO Tools for Success
20
2005 General Computer Controls
99.3%
92.0%
96.5%
88%
90%
92%
94%
96%
98%
100%
Jan Feb March
% o
f GCC
s P
asse
d
0
2
4
6
8
10
12
14
16
18
20
# of
Rev
iew
s
PassedReviews
For 1Q05, 494 GCCs have been tested in 45 QA Review s. Overall 1Q05 compliance is 96.4%
BCS ReviewsRated Satisfactory
10.0%30.0%50.0%70.0%90.0%
Jan-0
4Fe
bMar Apr
May
June
/July
Augus
tSep
tOct Nov
Dec
% o
r Rev
iew
s
Improved checklists revealed previously
undetected problems
Project Development End to End Process Framework
Idea PlanningPlanning BusinessCase
AnalysisBusiness
CaseAnalysis
ProjectExecutionProject
ExecutionProjectCloseProjectClose
GovernanceGovernance
Control 7Control 6
ScopeDesignRisk Assess. Sched. CBA
Control 2Control 1
Control 5Control 4Control 3
Control 8
Project Development End to End Process Framework
Idea Planning CaseBusiness
CaseAnalysis
ProjectProjectExecution Project
CloseProjectClose
Finance and Accounting ProceduresFinance and Accounting Procedures
GovernanceGovernance
Control 7Control 6
ScopeScopeDesignDesignRisk Assess.Risk Sched.Sched.
Control 9
Organizational Engagement: Integration
PMO Tools for Success
21
Project Health
2003 2004 2005 2006 2007Green Target 75% 82.50% 85.0% 90.0% 90.0%Green 82.5% 86.0% 90.5% 94.9% 89.3%Yellow 5.2% 6.8% 4.0% 6.0%Red 8.8% 2.6% 1.1% 4.7%
Days Healthy
Mercury ITG Project and Work Effort Health - YTD Trend by %Projects in "Healthy" Green
0%10%20%30%40%50%60%70%80%90%
100%
Week Ending 06/29/07
% o
f Pro
ject
s
Green
Red
Yellow
Target - Green - 90%
Target - Yellow - 6.7%
Target - Red - 3.3%
2004
=85
.9%
94%
2%
4%
Year to date average:Green: 89.38% (target GE 90%) Yellow : 5.91% (target LE 6.7%)Red: 4.71% (target LE 3.3%)
2005
= 9
0.53
PMO Results
8
22
PCRs – 2003 through 2007
PMO Results
LTD PCR Summary - $s
$-
$20,000,000
$40,000,000
$60,000,000
$80,000,000
$100,000,000
$120,000,000
$140,000,000
Actuals To Date PCR Actuals Remaining Budget Budget
Remaining Budget $30,174,092
PCR Actuals $62,459,061 $62,306,686 $11,880,684 $5,664,286 $2,245,649
Actuals To Date $26,740,939 $69,793,314 $57,690,774 $66,143,714 $42,780,259
Budget $89,200,000 $132,100,000 $69,571,458 $71,808,000 $75,200,000
2003 70.0%
200447.2%
200517.1%
20067.9%
2007 4.3% of Actuals2.7% of Budget